Page 1: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the

AL JAZEERAH DRILLING L.L.C

P.O. Box 2845 Sharjah

United Arab Emirates

Tel: +971 6 7490559

Fax: +971 6 7490523

Email: [email protected]

Page 2: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the

Contents

1 TECHNICAL DETAILS 2 PREVIOUS PROJECTS

3 BIO DATA OF STAFF

4 PROGRESS PHOTOGRAPHS

5 REGISTRATION AND LICENSES

6 APPROVALS AND CERTIFICATES

7 PLANT AND MACHINERIES

Page 3: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the

Al Jazeerah Drilling was formed in 2005, and offer rapid city and the surrounding

communities many services such as water and sewer installation, horizontal auger

boring, pipe ramming, concrete pipe jacking, demolition of services and lagoon and

water way reconstruction.

JD is locally owned and operated assuring that the owners possess a personal and

financial stake in the company’s future. The management at JD strives to provide real

value to the business and to its business associates.

The organization is constantly growing and developing in search of innovative

technology. Progressive management and devoted employees create an empowering

environment that is entrepreneurial in nature and is directed towards proving our clients

with employees on our staff. Our reputation attracts quality personnel hard working

people who are committed to producing projects that set a standard for excellence.

This integrity, innovation and sophistication have earned the company great respect

throughout the industry. JD operates under a defined set of values that foster a true sense

of commitment to only the finest craftsmanship and desire to build relationship that are

based on old fashioned principles like trust and integrity a true respect for the individuals

and a heart felt obligation to give back to the community.

Page 4: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the

1. TECHNICAL DETAILS

Page 5: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the

PIPE JACKING AND DIRECTIONAL DRILLING METHOD STATEMENT

AL JAZEERAH DRILLING L.L.C

Page 6: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the

PIPE –JACKING METHOD STATEMENT

1. CROSSING DETAIL:

1.1 Length & Diameter : Different steel sleeve diameter will depend on the diameter

of the carrier pipe ( 800mm to 2800mm steel sleeve can be used). The steel

sleeve pipe will be jacked to the full required length and the carrier pipe will then

be installed. The joint of the steel pipe will be fully welded.

1.2 Ground conditions: Ground conditions at the location of the drives to be checked & classified from medium to very dense sand or very hard rock.

2. THRUST PIT: The size of the thrust pit will depend on the local site condition &service

crossings at the location. In general the drive shaft will be a minimum of 6x4m,and

receiving pit 400mm below the pipe invert level or depends upon the site condition.

3. RECEPTION PIT: the receiving pit minimum requirement for manhole construction or carrier pipe construction and depth of the pipe invert level.

4. PIPE JACKING EQUIPMENT SET UP:

a. Main jacks: 2 No. hydraulically operated. Capacity 350 tones each. Stroke 1200mm. b. 10,000 psi Hydraulic power pack, with high pressure hoses.

SET UP: Two steel guide rails are set up on timbers in the thrust pit to the correct line

and gradient and then concrete base of 200mm thick is formed to keep them in

position. The thrust ring is set up ensuring that the jacks are accurately positioned at

the axis level of the sleeve pipe. A steel thrust plate 35mm thick is placed to transfers

the jacking forces to the concrete thrust wall.

THRUST WALL: the thrust wall is cast directly against the vertical face of the

excavation in the jacking pit. A steel thrust plate 35mm thick is placed to transfer the

jacking force to the concrete thrust wall.

5. INSTALLATION OF PIPE: The sleeve steel pipe are jacked into position using

an open steel pushing ring to distribute the pressure around the pipe starting

with the steel lead pipe. The steel sleeve is pushed into the face of the soil to

secure it, plug could be upto 0.3m depending on the site condition then the face

is excavated manually. The soil will be loaded into a wheel skip and winched to

the thrust pit, where it would be lifted to ground level by excavator/crane.

2

Page 7: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the

6. LIGHTING & VENTILATION: Lighting to the face will be provided using a mobile 2 KVA

generator fitted with a 220 volt transformer. Forced air ventilation will also be provided.

7. SHIFT REPORT: A daily report is produced each morning for the previous day work recording the following:

a. Labour & Plant resources. b. Progress of work.

c. Line & level. d.

Face condition.

e. jacking pressure. 8. INSTALATION OF CARRIER PIPE IN STEEL SLEEVE: Pipes will be supported in

special designed clamps. The clamp is fixed to the invert level of the sleeve via a flat steel

bar to secure the pipe and the coupler in position and also to prevent any movement.

9. GROUTING:

9.1 Steel sleeve annulus: On completion of the installation of the steel sleeve, injection

nozzle will be fixed at 4.0m intervals at the soffit of the steel pipe. Water/Cement grout

is then injected through these points until annulus are completely filled. 9.2 Grouting around carrier pipes:

a. Stop Ends: On completion of the carrier pipe laying and its supports concrete blocks

walls would be constructed on both ends. At low end of crossing injection inlet pipe will be

provided for grout at crown level. The other end will be incorporate one breather pipes.

b. Grouting: Grouting will proceed using sand/cement mix by means of a pump at the

rate of approximately 12cum./hr. the grouting operation will continues until the sleeve is

3

Page 8: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the

completely filled. For short up to 30m length drives grouting may be carried out by

means of pouring the grout through a cone fixed with a pipe connected to the injection

grout point at the sleeve. 10. ACCURACY: Steel Sleeve: Where there are no obstruction we would bore the steel sleeve to an accuracy of +/-75mm on line and level at any point.

11. EQUIPMENTS:

a. Set of hydraulic jacks. b. Power pack. c. Electric air winch. d. Welding machine. e. Air compressor. f. Grout pump/diaphragm pump. g. Skip. h. Pushing ring. i. Bogey. j. Pushing ring. k. Steel plate. l. Theodolite & level instrument.

4

Page 9: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the

Glossary of terms in general use

1. Thrust pit: A working shaft at the beginning of the jacked section of pipeline,

in which the specialized equipment is installed and from which the jacking

operations are carried out.

2. Thrust wall: A wall at the rear of the thrust pit, generally in reinforced concrete

designed to spread the reaction loads to the ground behind the thrust pit.

3. Pressure plates: A steel pressure plate or plates located between the rear end of the

jacks and the concrete wall to back spread intensive loading when necessary.

4. Hydraulic jacks: High pressure, hydraulically operated jacks providing the

power to move the pipeline.

5. Power pack: A motorized hydraulic pump unit feeding the fluids to

activate the hydraulic jacks.

6. Spacer blocks: Fabricated blocks in matched sets which are used to augment

the jack stroke when necessary.

7. Guide rails: steel or timber rails set firmly in the thrust pit to give directional control

of the concrete pipes for the drive and for accurate location of the pipe joints.

8. Jacking shield: A fabricated steel cylinder from within which the excavation is

carried out either by hand or machine. Incorporated within the shield are

facilities to allow the shield to be adjusted to control line and level.

9. Jacking pipe: A steel sleeve pipe designed specifically for jacking. Reception pit: A shaft at the end of the jacked section of the pipeline from which the jacking shield is recovered.

5

Page 10: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the

AL JAZEERAH DRILLING LLC METHODS

DIRECTIONAL DRILLING METHOD STATEMENT

With directional drilling, the equipment consists of three main parts:

1. The Hydraulic power pack. 2. The rig 3. The mixer.

The rig is a hydraulic device that either pushes the drill-rods into or draws them out of the soil.

During this process, rotating movements can be made at the same time. With the mixer, a

construction of devices, drilling mud is made and this can be pressurized as required. The

drilling mud consists of fine clay with polymer and water, in the required proportion. Both the rig

and the mixer are powered by the power pack.

Once the project is established and the entering and exit points are known, the process can

begin. The drilling is set up and drill rack is set to a determined angle. This is usually between 5

to 20 degrees, depending on the characteristic of the crossing. The initial drill rod and cutter

head are set into the drilling chuck. The first piece of drill pipe is made out of an antimagnetic

material to eliminate any interference to the survey probe.

The drill-head is situated at the front of the first drill-rod and is equipped with an electronic sonde

(survey probe), in order to localize the drill-head. Also, “nozzles” have been installed, that enable the

drill mud to flow and thus loosen and transport the soil, and to form a drill tunnel. The drill-head is

shaped in such a way that steering corrections can be carried out. Depending on its position, the

drill-head will take certain direction when the drill-rods are pushed in. During this process, the drill

rods are not rotating. By means of rotating and pushing in the drill rods at the same time, a straight

line is drilled. Directional drilling enables you to steer in all required directions.

When the drilling begins, the drilling solution pump is turned on and the cutter head is rotated

into the ground. As the first section is being buried the operator monitors the head location and

compares the information to a plotted chart. If there is any deviation from the intended line, the

operator makes the steering corrections. Once the first section is buried, the drill section id

uncoupled from the drill chuck and another section of drill stem (pipe) is added. The sequence

continues until the pilot hole is completed.

1

Page 11: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the

AL JAZEERAH DRILLING LLC METHODS

Once the pilot hole is completed, the product line (duct pipe) should be ready to be pulled back.

For pulling back a products line or lines, first the cutter head is removed and a back reamer is

installed in its place. A back-reamer is cutting head with its cutters facing the drill pipes string.

Its purpose is to clear a path for the products line being installed. Directly, behind the back

reamer (away from the drill stem) a bearing swivel is installed. The bearing swivel is attached to

a cap that has been installed on the products line. As the products line is pulled into the hole,

the drill string is rotated and the drilling solution is pumped in to maintain the integrity of the

hole. The product line is pulled all the way back to the initial entry in the ground.

Depending on the diameter of the required tunnel, reaming can be done several times. In this

case, every time a larger reamer will be used. When reaming for the last time, the pipes is

mounted directly behind the reamer and swivel. The coupling between the swivel and the pipe

prevents the pipe from rotating while being pulled in.

In the case of 800mm (OD) HDPE pipe, the reamer size required will be 900mm diameter to pull the pipe under the asphalt road.

Once the pilot 3” (76mm) dia. Is drilled to the correct profile a 300mm reamer is connected to the

string line and reamed through and second reaming operation will be a 550mm reamer, the third

reaming operation will be a 800mm reamer and finally on the last reaming operation the 710mm

(OD) HDPE pipe is mounted directly behind the 800mm reamer and swivel and pulled through under

the asphalt road. The same principle will apply for other HDPE Pipes with different reamer sizes.

2

Page 12: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the

METHOD

S

AL JAZEERAH DRILLING LLC

Method Statement for Pipeline

(a) Method Statement for Survey work

1. Confirm the Bench mark elevation and coordinates from the approved construction drawing

received from the Consultant Engineer.

2. Locate the Bench mark on the site jointly with Consultant staff and confirm the location.

3. Shift the Benchmark to near by locations of the required sites and recheck the elevation value

and coordinates with Consultant surveyor. 4. Protect the Bench mark (Steel Pin) by concrete protection and surrounding by warning tape.

5. Incase of any difference between the value of bench marks inform the Engineer accordingly with

the difference and new value of the same.

6. Pre-survey of the all OGL’s Levels and alignments of the pipelines route and the status of the

existing asphalt and tiles finishing surface and take photo for the records and compare all information’s with the construction Drawings .

(b) Method Statement for Trial holes & Locating existing services

1. Check all NOC Drawings and mark the lines conflicting, crossing or adjacent to the proposed

pipe lines, Valve chambers and the thrust blocks on the site.

2. Remove the existing Asphalt or Interlocking tiles for the Trial holes locations.

3. Carefully excavate by hand and mark the locations of each chamber and make the location of

trial holes along the route of the pipeline . 4. Surround the excavated trial pits by warning tape and PVC nets as the safety precautions.

5. Support the services during the excavation by some beams or timbers as required by the service

departments. Incases of services not found as shown on the drawing check the same with the concerned department.

6. Incase of services damaged accidentally for not shown on the drawings or unknown reasons

inform the emergency telephone numbers immediately.

7. Upon completion of excavation of the pipe line and Valve chambers backfill the trial holes in

layers with dune sand and make it as before. 1

Page 13: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the

METHOD

S

AL JAZEERAH DRILLING LLC

(c) Method Statement for Excavation & Dewatering

1. Circulate Notices to all residence, shops and others two weeks in advance to the starting date to

the effected entries of the works.

2. For Asphalt roads or foot path arrange Traffic diversion from authorities and Isolate the working

area by warning tape and barriers and fix the traffic cones and signs as required.

3. Arrange the dewatering as it is required by fixing the well point pipes every one meter on one or

two sides as per the required depths. 4. Excavate carefully and keep the helper away from the machine swinging area.

5. Arrange the stepping method for excavation for not exceeding more than 3.0 meter and provide

more steps for the depths more than 3.0 meter and up to 5.0 meter.

6. Provide steel trench box support for the depths more than 5.0 meter and not exceeding 7.0 meter

while excavation. 7. For any sand stone or hard material found it should be informed to the concerned Engineer.

8. For depth of excavation exceeding more than 7.0 meter we should make the excavation on two

stages. Stage 1: Reduce the ground level from 2.0 – 3.0 meter till reaching the water level. Stage 2: Fix the well point system on low level and fix the trench box while excavation

9. Upon completion of excavation with shoring and pipe laying, remove the trench box and refix it

on the reduced level and continue the same activities on the next frame.

(d) Method Statement for Backfilling

1. Before starting the backfilling take the sample of the excavated material and arrange the required test like Soil Compaction test and Sieve Analysis to evaluate the excavated material whether it is suitable for backfilling or not. If it is found suitable within the reasonable maximum dry density which could be used for backfilling.

2. Upon the completion of the work like pipeline, Chambers construction and any other concrete

structure work back fill in layers of 300mm with hand compaction till one meter on the top of the pipe line and using mechanical compactor after that.

2

Page 14: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the

METHOD

S

AL JAZEERAH DRILLING LLC

3. Make the Field Density Test on each layer along the pipeline and continue backfilling the other

layers till to top level by repeating the compaction test.

(e) Method Statement for Pipe laying of Rising main

1. Upon completion of excavation for the required levels and bedding aggregate is in place.

2. Clean the socket of pipes and rubber gasket for each pipe before fix it in place. 3. Fix the required aggregate bed as per the specification .

4. Fix the pipe from down stream towards upstream as per the approved design drawings.

5. Connect the spigot ended pipelines to the Double bell coupling or to the Socket using the chain block pipe

puller and check the level and alignment of the fixed pipe and repeat the same activities for the other pipes till the next chamber and fix the aggregate surround with hand compaction .

6. Arrange the water pressure test to the rising main pipe line to the specified pressure (pressure test should

be done upon completion the backfilling .

7. Arrange the backfilling as per the method of backfilling.

8. Lay the warning tape on the top of the pipeline at level as per the drawings .

(f) Method Statement for Concreting of Valve Chambers, Air Valve and Washout

1. Arrange the formation levels of the structures and make it the same level as per the drawings.

2. Fix the concrete blinding of the same thickness as per the drawings.

3. Fix the water proofing and protection board as per the method of water proofing.

4. Fix the form work for base slab and the water stop to the wall kicker.

5. Fix the steel reinforcement for the base slab and the first stage of the walls as per drawings and fix the

starter steel for the walls. 6. Concreting of the base slab using the required vibrator with adequate numbers.

7. Arrange the curing of the same and clean the joint by making it solid using steel brush and shipping

hummer to make it rough surface. 8. Fix the internal form works for the walls.

3

Page 15: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the

METHOD

S

AL JAZEERAH DRILLING LLC

9. Fix the steel reinforcement for wall as per the drawings with the required spacers.

10. Fix the external form works of the walls to the required levels .

11. Cast the concrete for walls.

12. Remove the form works and arrange the required curing.

13. Precast the Roof slab with the cover opening as per the drawings and fix it to the place and fix the cover

with frame

14. Prepare the internal surface for the applying of the approved internal coating . 15. Apply the external water proofing and protection.

4

Page 16: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the

METHOD

S

AL JAZEERAH DRILLING LLC

Method Statement for Construction of Pumping Stations , Screen Chamber Electrical Substation and Surge Vessel

(a) Substructure works for Pumping Stations & Screen Chamber :

1. Setting out the central lines of the Pumping Station as per the approved site location, checking the ground levels & locate the services which conflicting with or close to the structure and expose it by trial holes.

2. Lower the original Ground level to 3.5 m below the existing level by making steps near the

edge and arrange even levels of the plat form for the Auger to work the shoring system .

3. Installation of initial dewatering system well point with the required number of pumps we Planning to use 10 Nos. sump pumps as per the site conditions.

4. Fixing the Steel H-Beams 300 x 300 mm by auger excavation every 1.08 m spacing centre to centre ( according to the shoring design ) and fix the H-Beam and to the total depth as per the required design and as per the sketch layout all in straight line and one meter clearance away from the foundation edge .

5. Excavate for the structure and fix the R.C. Slabs between the H-Beams as per the excavation

going down and provide the R.C. Slabs with the support frame system as per the design and sketch .

6. Check the formation level as per the drawings and Specifications and arrange the compaction

in case of lose soil with compaction test then Fix the side formworks with the demarcation and the levels.

7. Fix the concrete blinding as per the drawing & design level.

8. Apply the water proofing with the protection board or screed.

9. Fix the External water stop as per the proposed shop drawings and fix the water stop fittings

By welding in the intermediate of the construction joints for all the proposed stages of concrete as per the drawings.

10. Fix the form work for the 1st

stage of base slab and fix steel reinforcement according to the drawing and specifications and extend the water stop from the blinding to the base slab and kicker as per the approved method

11. Cast the concrete base slab with wall kicker and allow for the curing.

1

Page 17: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the

METHOD

S

AL JAZEERAH DRILLING LLC

12. Repeat item no. 10 & 11 for the other two stages of the base slabs as per the drawing.

13. Cleaning and brushing the first stage of concrete to allow good joint between the new and old

concrete and allow for box out for he inlet and outlet pipes and provide intermediate water sop for all box outs.

14. Extend the form work to the first stage of walls and fix the steel reinforcement including

the water stop and cast the concrete.

15. Extend the form work to the second stage of walls and fix the steel reinforcement including

the water stop and cast the concrete.

Method Statement for Construction of Pumping Stations

1. Extend the form work to the walls and roof slab and fix the steel reinforcement including the water stop of the final stage and cast the concrete.

2. Fix the external water proofing membrane after applying the primer.

3. Fix the internal pipes & fittings and fix all Electro-mechanical items including the

Pumps as per the approved shop drawings.

4. Prepare the concrete internal surface and apply the approved Coating.

5. Backfilling around the chamber in stages till the final level.

(b) Superstructure works for Pumping Stations , Screen Chamber & Substation

1. Setting out and preparation the excavation for the foundation level and arrange for the concrete blinding with the water proofing .

2. Foundation preparation for all superstructure of P.S3A , Screen Chamber

and Substation including the water proofing and protection .

3. Continue the activities for the above substructure from items 6 to 15 .

4. Fixing the Block works for the walls and between the columns with the

required anchors .

2

Page 18: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the

METHOD

S

AL JAZEERAH DRILLING LLC

5. Arrange the plaster works for the block works and other external concrete and arrange for the opening for the doors and windows with the required lintels.

6. Arrange the conducts for the Electrical works , Plumping and other services as per

the drawings .

7. Fix the Floor tiles with the approved tile glue and grout.

8. Fix the Aluminum windows , doors and stairs as per the drawings .

9. Arrange for the internal and external painting as per the approved colors .

10. Fix all Electro-mechanical works including all items as per the approved shop drawings .

11. Arrange the power connection by SEWA for the location giving all details of the

load and the capacity required to the Pumping Station.

12. Allow for testing, commissioning and handing over the Pumping Station.

13. Fix all the Mechanical pipes, fittings, valve etc. and the Electrical works in the over to pumping station till the completion, testing and commissioning of the same and handing Engineer and Client.

(c) Substructure works for Surge Vessel :

1. Setting out and preparation the excavation for the foundation level and arrange for the concrete blinding with the water proofing .

2. Foundation preparation for all superstructure of surge Vessel with the required Anchor

bolts as per the E& M approved shop drawings including the water proofing and protection.

3. Fix the surge Vessel in place as per the approved location .

4. Arrange the outlet connection from the surge vessel with alignment and level with the

inlet of the valve chamber.

5. Connection the outlet of surge vessel to the Valve chamber .

6. Arrange the E& M works for the same .

3

Page 19: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the

2. PREVIOUS PROJECTS

Page 20: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the

List of Projects Completed

S.NO Client Consultant Name of Project Contract

Value Dhs

Completion

Date

1 M/s SEWA M/s SEWA Tech

sec

DJ-395 Laying of 800mm dia water main from

layyah to mamzar –Sub-contractor

24,911,050.00 2010

2 M/s SMDD M/s Halcrow DJ-406 Pumping station 3A & Rising Main–Sub-

contractor

58,471,248.00 2011

3 M/s SMDD M/s SMDD Development of Al Khan Cornich Foul Sewer DJ-

409–Sub-contractor

15,965,040.00 2011

4 M/s SEWA & M/s

Ministry of Public

Works

M/s SEWA Tech

Sec

Microtunneling works SEWA crossing dhaid

madam road

39,000.00 2012

5 M/s Sharjah Transport M/s Al Turath &

Rostamani LLC

Pipes Jacking of Sharjah Transport DJ-407A 327,000.00 2012

6 M/s Transco Abu

Dhabi

M/s Idroesse Road Crossing GRP 1200mm dia duct for water

transmission system to umm al quwain emirates

339,463.00 2012

7 M/s DPW M/s Halcrow

International

Contract R692 external work for the executive

office of H.H sheikh Jawaheer in Al Gulayaa DJ-

429 –Sub-contractor

2,241,723.00 2012

8 M/s Transco M/s SEWA Tech

Sec

Water main at Fili and Foah area laying of HDPE

225mm dia and 110mm dia with pipe jacking

1,097,660.00 2012

Page 21: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the

List of Projects Completed

S.NO Client Consultant Name of Project Contract

Value Dhs

Completion

Date

9 Shaikh Khaled Bin

Naser Al Thani

- Extension of Mr Shaikh Khaled Bin naser Al Thani

villa

800,000.00 2013

10 M/s DPW M/s WSP Improvement of Corniche road DJ-432 –Sub-

contractor

2,545,321.51 2012

11 M/s SEWA and M/s

Ministry of Public

works

M/s SEWA Directional drilling under the asphalt across

emirates road and by pass road

448,300.00 2012

12 M/s SEWA M/s SEWA Directional Drilling at Mileiha 39,000.00 2012

13 M/s EXPO & M/s

AMBB

M/s WSP Expo centre Sharjah Expansion DJ-438 –Sub-

contractor

3,922,792.25 2013

14 M/s Saif Zone M/s Saif Zone Extension of MCQ1 Road sewer and irrigation

main line saif zone DMJ 307 –Sub-contractor

2,130,660.00 2013

15 M/s SEWA M/s SEWA phase 2 & 3 desal & steam turbines outfall

concrete channel repair

165,400.00 2013

Page 22: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the

List of Projects Completed

S.NO Client Consultant Name of Project Contract Value

Dhs

Completion

Date

16 M/s SEWA M/s SEWA phase 1 outfall culvert repair in layyah power

station

2,059,687.50 2013

17 M/s FEWA M/s Green Osais NDRC Works At 17w2012 Rehabilitation Of

Distribution Network And Transmission

System In Fujairah

50,000.00 2013

18 M/s SEWA M/s SEWA Phase 1 outfall culvert repair in layyah power

station

500,000.00 2014

19 M/s Laing O

Rourke

M/s Laing O

Rourke

Al Nasseriya Community Mall Project

(Drainage Connection Work)

200,000.00 2014

20 M/s HFZ SEWA Phase 2 Water Network (ZONE 1&2) 12,069,635.00 2014

21 M/s FEWA M/s FEWA 24W/2012 Construction of transmission

pipeline within city and insutrial area Ajman

DJ-439- Sub-contractor

34,400,700.00 2015

22 Ajman

Municipality

and Planning

Dept

Ajman Municipality

and Agriculture

Dept

Contract No 16/2013 Construction Of Irrigation

Line Phase 2 At Itihad Road Ajman (DJ-453) –

Sub-contractor

4,500,000.00 2015

23 M/s SEWA M/s SEWA Construction Of Rcc Concrete Tank (Clear

Well Tank) Khorfakkan Power Station

2,968,745.00 2015

Page 23: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the

List of Projects Completed

S.NO Client Consultant Name of Project Contract Value Dhs Completion

Date

24 Engg Essam

AL Mulla

M/s Oasis Construction of Eng Essam Al Mulla villa 1,750,000.00 2014

25 Mr Waseem M/s International Extension of private villa (Mr. Waseem

sawan) g+1 at al barashi area sharjah

700,000.00 2015

26 M/s DPW M/s SMDD Foul Drainage Network for four Hotels in Al

Rifa Sharjah (DJ479)

9,268,952.00 2015

27 M/s SMDD M/s HALCROW Al Jubail Market Sewafe Lifting Station

Sharjah (DJ486)

Complete 2015

Page 24: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the

List of Running Project

S.NO Client Consultant Name of Project Contract Value Dhs Completion

Date

1 M/s DPW M/s SMDD Construction of Foul Drainage Network in Al

Nahda Area- Sharjah(DJ499)

5,900,000.00 In Progress

2 M/s SEWA M/s SMART

VISION

Proposed Warehouse, Office Building,

Labour Accommodation, Compound Wall (

In Sajja Industrial Area (JP30)

300,000.00 In Progress

3 M/s SMDD M/s SMDD Construction Of Irrigation Line For Al

Nukhailat Par At Al Nukhailat Area- Sharjah

(DMJ330)

- In Progress

4 M/s SAIF

ZONE

M/s HALCROW Construction of Road Work at New

Extionsion Area T5- Saif Zone(DJ501)

- In Progress

5 M/s SEWA M/s SEWA Nouf Development ( Laying Of GRE Pipeline

On Sharjah- Kalba Road (JP34)

- In Progress

Page 25: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the

3. BIO DATE OF STAFF

Page 26: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the

CURRICULUM VITAE

PERSONAL DETAILS :

Name : Awni Moh’d. Ali Sawan

Date of Birth : 13th January, 1957

Place of Birth : Gaza – Palestine

Gender : Male

Nationality : Palestinian

Address : P.O.Box 2845

Sharjah – UAE

Contact Phones : Office : 06-7490559

Mobile : 050-6411285

Email : [email protected]

Marital Status : Married & having 6 Children

Driving License : Having valid UAE Driving License

Passport No. : P00016697

Language : Arabic – Mother Tongue

English – Very Good

Page 27: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the

ACADEMIC QUALIFICATION :

* B.Sc. in Civil Engineering in June 1980, From University of Alexandria – Egypt

* Associated Membership of American Society of Civil Engineering ASCE,

Associated

Member since April 2000.

COMPUTER KNOWLEDGE :

Good knowledge of Auto Cad, MS Excel, MS Word, Winproject etc.

PROFESSIONAL EXPERIENCE :

1980-1981

Project : General Building & Constructions Contracts in

Different

Locations in Gaza

Employer : AL KHATIB ENGG. CO. , GAZA-PALESTINE

Consultant : Gaza Municipality

Client : Gaza Municipality

Position : Site Engineer

Page 28: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the

1981-1983

Project : WED-W23/78 Abu Dhabi – Al Ain Main Pipe line

Employer : AL SALMEEN BOVIS J. V CONT. CO.

Consultant : Bineese & Partners

Client : Water & Electricity Department – Abu Dhabi

Position : Section Engineer

Project Description : Laying of 123 km of 1000 mm dia. D.I. Pipes including

all

associated works of concrete structure such as Valve

Chamber, Washout, Isolating Valve, Thrust Blocks

Etc..Testing, Commissioning till the completion of the

project.

1983-1984

Project : ADSS 121/3 – Abu Dhabi H.

Employer : AL SALMEEN BOVIS J. V CONT. CO.

Consultant : John Taylor & Sons

Client : Sewerage Project Committee (SPC) Abu Dhabi

Position : Site Engineer

Project Description : Main Sewerage lines, Subsidiaries & Connections & all

associated works of concrete structure such as

Manholes,

Chamber & NDRC works under Hamdan St. &

Khalifah St.

including the connections to the existing sewage

Page 29: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the

1984-1985

Project : ADSS 161/1-Abu Dhabi-Mafraq-Construction of

Pumping

Employer : AL SALMEEN BOVIS J. V CONT. CO.

Consultant : John Taylor & Sons

Client : Sewerage Project Committee(SPC)-Abu Dhabi

Position : Site Engineer

Project Description : Construction of Pumping Station including Laying

12km

600mm dia. GRP pipe Pumping Main from the pumping

station to the plant treatment at Mafraq with all

associated

works of Thrust Block & other structure

1985-1986

Project : DS-9 & DS-9 Vol.1 – Dubai - Jumairah

Employer : AL SALMEEN BOVIS J. V CONT. CO.

Consultant : Watson & Hawaksly Int.

Client : Dubai Municipality (Drainage Section)

Position : Site Engineer

Project Description : Main Sewage lines, Subsidiaries & H. Connections &

all

associated works of concrete structure such as

Manholes,

Page 30: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the

chamber & NDRC & pumping stations & lifting

manholes

including the connections to the existing sewage.

1986-1987

Project : ADSS 126/2 & 126/3 – Abu Dhabi

Employer : AL SALMEEN BOVIS J. V CONT. CO.

Consultant : John Taylor & Sons

Client : Sewerage Project Committee(SPC)-Abu Dhabi

Position : Site Engineer

Project Description : Main Sewage lines, Subsidiaries & H. Connections &

all

associated works of concrete structure such as

Manholes,

chamber including all the connections to the existing

sector

1987-1988

Project : ADSS 152/3 – Abu Dhabi – 7 Nos. Irrigation Reservoirs

Employer : AL SALMEEN BOVIS J. V CONT. CO.

Consultant : John Taylor & Sons

Client : Sewerage Project Committee(SPC) -Abu Dhabi

Position : Site Engineer

Project Description : Construction of 7 Nos. R.C. Under Ground Irrigation

Page 31: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the

reservoirs including associated Pipe lines & Manholes

in

Abu Dhabi

1988-1989

Project : Mafraq Sewerage Treatment Plant Extension.

Employer : AL SALMEEN BOVIS J. V CONT. CO.

Consultant : John Taylor & Sons

Client : Sewerage Project Committee(SPC) -Abu Dhabi

Position : Project Engineer

Project Description : Mafraq Sewerage treatment plant extension with 2x2

M.G.

Irrigation tank and pipe lines up to 1300mm dia.

1989-1990

Project : ADSS 122/2 & 131/1 – Abu Dhabi

Employer : AL SALMEEN BOVIS J. V CONT. CO.

Consultant : John Taylor & Sons

Client : Sewerage Project Committee (SPC) -Abu Dhabi

Position : Project Engineer

Project Description : Construction of Pumping Station including Laying 3km

500mm dia. GRP pipe Pumping Main from the pumping

Station to Discharge Chamber & Construction of Main

Sewage lines, Subsidiaries & H.Connections & all

Page 32: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the

Associated works of concrete structure such as

Manholes,

Chamber including all the connections to existing sector

Including NDRC works.

1990-1991

Project : Mafraq Sewerage Treatment works Immediate

Remedial

Measures

Employer : AL SALMEEN BOVIS J. V CONT. CO.

Consultant : Engineering science

Client : Sewerage Project Committee (SPC) -Abu Dhabi

Position : Project Engineer

Project Description : Mafraq Sewerage treatment works with construction of

R.C tanks with all the related pipe works including

Electro-

Mechanical works.

1991-1993

Project : Street Naming & Building Numbering System in Abu

Dhabi

Employer : AL SALMEEN BOVIS J. V CONT. CO.

Consultant : Pan Emirate Pol Services

Page 33: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the

Client : Abu Dhabi Municipality Department (Engg. Section)

Position : Project Engineer

Project Description : Fixing for all street & Building complete system after

the

Completion of survey of all new & under Construction

Street

& building corroborated on updated Drawings for the

Complete system.

1993-1995

Project : Access Road to Abu Dhabi Int. Airport Surface water

collector main and pump stations 105/2A

Employer : AL SALMEEN BOVIS J. V CONT. CO.

Consultant : Diwi Consult ( Emirates)

Client : Department of Public Works – Abu Dhabi

Position : Project Manager

Project Description : Construction of 10,800 m of 600mm dia. R.C Pipes

Including 50Nos. Manholes depth from 2-8m.

Tunneling of

130 m of GRP Pipes under Airport Bridge, Construction

of

3 Nos. Pumping Stations & Connections to the existing

formation drain system.

1995-1996

Project : Building Construction of 20 typical Floor + Roof in

Abu

Page 34: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the

Dhabi

Project Value : 3,400,000 Dhs.

Employer : AL SALMEEN BOVIS J. V CONT. CO.

Consultant : Al Meedan Engineers

Client : Abu Dhabi Comm. Building – Government of Abu

Dhabi

Position : Project Manager

Project Description : Workman ship for Shuttering & steel reinforcement for

High rise Building starting from the Basement of level 6m

under ground mezzanine floor, 20 typical floor and

the roof till the completion of the structure.

1997-1998

Project : Layyah to Halwan Trunk water main at Sharjah

Project Value : 7,900,000 Dhs.

Employer : Darwish Engineering Emirates

Consultant : Halcrow International Partnership

Client : Sharjah Electricity & Water Authority (SEWA)

Position : Project Manager

Project Description : Laying of 7.5km 800mm dia. A/C pressure pipes

including

Testing, Sterilization, Commissioning till the handing

over

to the Client and Construction of all Valve Chambers,

Washout , Air Valves and other thrust on the line

including

8 Nos. of Non disruptive road Crossings (NDRC).

Page 35: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the

1998-1999

Project : Sharjah Bidaya Road – University of External Roads-

Effluent pipeline

Project Value : 2,300,000 Dhs.

Employer : Darwish Engineering Emirates

Consultant : Halcrow International Partnership

Client : Sharjah Municipality

Position : Project Manager

Project Description : Laying of 5.5km 600mm dia. A/C pressure pipes

including

Testing, Commissioning till the handing over

to the Client and Construction of all Valve Chambers,

Washout, Air Valves and other Concrete thrust Block.

2000-2002

Project & Descriptions : Al Nahda Foul and Surface Water Drainage - Sharjah

Project Value : 24,600,000 Dhs.

Employer : Darwish Engineering Emirates

Consultant : Halcrow International Partnership

Client : Sharjah Municipality-Drainage Section (SMDS)

Position : Project Manager

Project Description : Excavation, Dewatering, Laying, Testing and

Backfilling of

Page 36: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the

miscellaneous A/C pipes, UPVC pipes and GRP pipes

for

drainage system and surface water including two

pumping

stations for Al Nahda Area at Sharjah. Thrust boring of

Sharjah – Dubai Main road works and Directional

drilling

of other asphalt roads. Three variation to the above

project

as follows :

1. Al Nukhailat UPVC 500mm Pumping main from Pumping Station No. 4 to

Sea.

2. Pumping Main & Road Crossing by Directional Drilling at Industrial Areas 1,

2, 3, 7, 8 & 9 to connect the existing A/C 600mm Pumping Main

3. UPVC 400mm Pumping Main from Treatment Plant at Al Nahda to Industrial

Area No.1

2002-2003

Project : Mamzar (Al Taawon ) Proposed Foul Sewer, Pumping

Station , Pumping Main to P.S.3 in Ind. area 1 at Shj

Project Value : 6,900,000 Dhs.

Employer : Darwish Engineering Emirates

Consultant : Halcrow International Partnership

Client : Sharjah Municipality-Drainage Section (SMDS)

Position : Project Manager

Project Description : Excavation, Dewatering, Laying, Testing & Backfilling

of

miscellaneous uPVC pipes and GRP Pipes for drainage

system including Pumping Station, Pumping Main and

Page 37: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the

Tunneling works for Al Taawon area at Sharjah

2003 -2004

Project : Al Khalidia Area Foul System

Project Value : 14,178,000 Dhs.

Employer : Darwish Engineering Emirates

Consultant : Halcrow International Partnership

Client : Sharjah Municipality-Drainage Section (SMDS)

Position : Project Manager

Project Description : Excavation, Dewatering, Laying, Testing & Backfilling

of

Miscellaneous uPVC pipes and GRP Pipes for drainage

System including Pumping Station and Pumping Main

for

Al Khalidia area at Sharjah

2003 - 2004

Project : Ajman Sewage System – Emergency Disposal

of Pumping Main

Project Value : 10,900,000 Dhs.

Employer : Darwish Engineering Emirates

Consultant : Black & Veatch Ltd.

Client : Ajman Municipality Drainage Section

Position : Projects Manager

Project Description : Excavation, Dewatering, Laying, Testing & Backfilling

of

Page 38: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the

750mm dia. Pumping Main of GRP Pipes for drainage

system including at Ajman

2004 – 2006

Project : Al Azra Area Foul Drainage

Project Value : 21,600,000 Dhs.

Employer : Darwish Engineering Emirates

Consultant : Halcrow International Partnership

Client : Sharjah Municipality-Drainage Section (SMDS)

Position : Projects Manager

Project Description : Excavation, Dewatering, Laying, Testing & Backfilling

of

Miscellaneous uPVC pipes and GRP Pipes for drainage

System including Pumping Station and Pumping Main

for

Al Azra area at Sharjah

2004 – 2006

Project : Pumping Station No.4 – Rising Main

Project Value : 11,400,000 Dhs.

Employer : Darwish Engineering Emirates

Consultant : Halcrow International Partnership

Client : Sharjah Municipality-Drainage Section (SMDS)

Position : Projects Manager

Project Description : Excavation, Dewatering, Laying, Testing & Backfilling

of

600mm dia. Rising Main GRP Pipes for drainage

Page 39: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the

System including connection Existing Pumping

Station No.4

2006 – 2007

Project : Construction of R.C. Concrete Reservoir No.1 at

Halwan

Project Value : 28,700,000 Dhs.

Main Contractor : Darwish Engineering Emirates

Consultant : Halcrow International Partnership

Client : Sharjah Electricity & Water Authority- Water (SEWA)

Position : Projects Manager

Project Description : Construction of R.C.Concrete Reservoir of 15 Million

GLS. Capacity with all associated pipeline

inlets and outlets , Overflow , Balancing pipes ,with all

associated chambers such as Isolating valves chambers,

Air Valves and washout and all Electro-Mechanical

works including the connection to the Existing water

Reservoirs & Pumping Station

2007 – 2008

Project : Laying of 800mm dia. Water Main (AC Pipes) -

from Saja'a to Bedia.(9.9km Approx)

Project Value : Dhs.6,800,000.00

Main Contractor : Darwish Engineering Emirates

Consultant : SEWA – Technical Section

Client : Sharjah Electricity & Water Authority- Water (SEWA)

Position : Projects Manager

Project Description : Excavation ,Dewatering, protection of excavation,

Laying of AC Pipes, Initially backfilling, pressure

Page 40: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the

Testing and backfilling including reinstatement of

Surface, Asphalt interlock, footpath etc…..

- Microtunelling work Or Pipe jacking including all

connection to existing main line.

- Constructing of all valve chambers, Air Valves,

Washout

and Fire hydrant as per the drawing including Fixing of

built in pipe valves, adaptors and coupling as per the

specification & drawings .

- Sterilization and colourization of pipeline before

commissioning and handover to the Client.

2007 – 2008

Project : 800mm Dia Rising Main Laying From Fisht to

Halwan

Project Value : Dhs.8,700,000.00

Main Contractor : Darwish Engineering Emirates

Consultant : SEWA – Technical Section

Client : Sharjah Electricity & Water Authority- Water (SEWA)

Position : Projects Manager

Project Description : Excavation ,Dewatering, protection of excavation,

Laying of AC Pipes, Initially backfilling, pressure

Testing and backfilling including reinstatement of

Surface, Asphalt interlock, footpath etc…..

Page 41: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the

- Microtunelling work Or Pipe jacking including all

connection to existing main line.

- Constructing of all valve chambers, Air Valves,

Washout

and Fire hydrant as per the drawing including Fixing of

built in pipe valves, adaptors and coupling as per the

specification & drawings .

- Sterilization and colourization of pipeline before

commissioning and handover to the Client.

2008 – 2009

Project : Laying of 800 mm Water Main from Layyah to

Mamzar

Project Value : Dhs.24,911,050.00

Main Contractor : Darwish Engineering Emirates

Consultant : SEWA – Technical Section

Client : Sharjah Electricity & Water Authority- Water (SEWA)

Position : Projects Manager

Project Description : Excavation, Dewatering, protection of excavation,

Laying of AC Pipes, Initially backfilling, pressure

Testing and backfilling including reinstatement of

Surface, Asphalt interlock, footpath etc…..

- Microtunelling work Or Pipe jacking including all

Connection to existing main line.

- Constructing of all valve chambers, Air Valves,

Washout

and Fire hydrant as per the drawing including Fixing of

builtin

Page 42: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the

pipe valves, adaptors and coupling as per the

specification &

drawings .

- Sterilization and colourization of pipeline before

Commissioning and handover to the Client.

2010 – 2012

Project : Pumping Station 3A Rising Mains

Project Value : Dhs.58, 471,248.00

Main Contractor : Darwish Engineering Emirates

Consultant : M/s.Halcrow International Ptn

Client : Sharjah City Municipality

Project Description : - Excavation, Dewatering, Laying, Testing &

Backfilling

800mm dia. Rising Main GRP Pipes 800mm Twin lines

of from PS3A to Sewage Treatment work plant with all

associated structures such as Isolating valves chambers,

Air Valves and washout and all Electro-Mechanical

works including connection to Existing Pumping Station

No.3.

- Construction of RC Concrete Pumping Station and

Screen Chamber at excavation in level of -11.70m

including of all E&M works and electrical substation,

boundary wall with gate and all other site general works

of such storm water, foul drainage and asphalt road and

footpath works till the completion of the project.

Commissioning, Testing and Handing Over of the

project to the Consultant and the Client.

Page 43: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the

- Supply and Install 45m rising main GRP Pipes 800mm

dia and steel sleeves 1200mm NDRC using pipe jacking

method under the asphalt road.

2010 – 2011

Project : Development of Al Khan Corniche Foul Sewer

Network

Project Value : Dhs.15,965,040.00

Main Contractor : Darwish Engineering Emirates

Client : Sharjah City Municipality

Project Description : Construction of Foul Sewer

Pumping Station complete with all Electromechanical

Works, Wall Chamber Flow meter, Control Room, Screen

Chamber/Odour Control in building, Gate Valve, Non-

Return Valve, Testing and Commissioning etc and

Construction of surface water pumping station complete

with all Electromechanical Works including Non-Return

valve, Gate valve, Valve Chamber, Testing and

Commissioning etc…Laying of gravity PVC pipe line of

dia 200mm, 250mm, 350mm, 400mm, 500mm & 600mm

including construction of manholes of 1200mm, 1500mm

dia depths from 1.50m to 9.0mtr including Breaking up

and reinstatement of existing asphalt, kerb footpath tiles

as per original condition. Laying of pressure line UPVC

pipe 225mm, 400mm including all fittings with concrete

thrust block and construction of Air valve, Washout

Chamber, Pressure reducer chamber, Testing and

Commissioning etc…., including Breaking up and

reinstatement of existing asphalt, kerb footpath tiles as per

original condition. Supply and install 8 nos NDRC total

301.50LM UPVC pipes 500mm dia, 400mm dia and

225mm dia steel sleeves 1200mm dia & 800mm dia

NDRC using pipe jacking method under the asphalt road.

2011 - 2012

Page 44: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the

Project : Contract R692 External Work for the Executive

Office of HH Sheikh Jawaher in Al Gulayaa

Project Value : Dhs. 4,000,000.00 (approx)

Main Contractor : Darwish Engineering Emirates

Client : Directorate of Public Works

Consultant : M/s.Halcrow Int Ptn

Description : Parking for Sheikh Office including Road works

footpath street lighting and foul drainage network, surface water network,

surface

water pumping station and rising main (300mm dia) app.300mtr discharge to sea

including all and landscaping and gate control.

2011 – 2012

Project : Contract no. R532 - Improvement of Corniche Road

Main Contractor : Darwish Engineering Emirates

Client : Directorate of Public Works

Consultant : M/s.WSP Middle East

Description : Improvement of Ajman corniche two direction carrage

way with side parking, diagonal parking, footpath, designed alumina fence lagoon,

fence for median, street light, storm water network, drainage network, etisalat

network, water network with two surface water lifting station. Include all traffic sign

board signals and road marking.

Project Duration: 2013 - 2014

Project : Phase 2 Water Network – Hamriyah Free Zone.

Project Value : Dhs.12,069,634.35

Page 45: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the

Main Contractor : Al Jazeerah Drilling LLC

Client : Hamriyah Free Zone Authority

Consultant : Sharjah Electricity and Water Authority

Duration : 12 Months

Project Description : Excavate, Supply, Lay & Backfilling of Water Line

GRE Pipe of Dia 100,150,200,300 & 500mm dia pipe including necessary fittings.

Construction of Chambers, Sluice Valve, Washout and Air Valve Chambers & Fire

Hydrants. Connection of 100,150,200,300 & 500mm dia pipeline (inter connecting the

new pipelines along the boundary limits between sectors, comprising to exposing,

protection, necessary drilling, making good, backfilling and reinstatement). Complete

Line Pressure Test & Line Flushing, Chlorination and Disinfection of Line. Supply

and install NDRC by Directional Drilling Method wherever required in the project

with the under the asphalt road.

2014-2015

Project : FOUL SEWER NETWORK FOR FOUR HOTEL

IN AL RIFA'A SHARJAH

Project Value : Dhs.11, 303,600.00

Main Contractor : Darwish Engineering Emirates

Client : M/s.Directorate of Public Works

Duration : 12 Months

Consultant : M/s.Sharjah Municipality Drainage Dept - SMDD

Project Description : Construction of Foul Sewer Pumping Station complete with

all Electromechanical Works, Valve Chamber Flow meter, Control Room, Screen

Chamber/Odour Control in building, , Testing and Commissioning etc and …Laying

Page 46: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the

of gravity PVC pipe line of dia 200mm, 315mm, 400mm, 500mm & 600mm

including construction of manholes of 1200mm, 1500mm dia depths from 1.50m to

7.0 including Breaking up and reinstatement of existing asphalt, kerb footpath tiles as

per original condition. Testing and Commissioning of complete line (Gravity line)

etc….,. Supply and install NDRC Works total 100mtr UPVC pipes 500mm dia,

400mm dia using steel sleeves by Directional Drilling Method under asphalt road.

01/12/2014 – 30/04/2015

Project : CONTRACT NO. 19/2014 - CONSTRUCTION OF

IRRIGATION LINE PHASE - 2 AT SHEIKH

MOHAMMED BIN ZAYED ROAD

Project Value : Dhs.3, 862,690.40

Main Contractor : Darwish Engineering Emirates

Client : M/s.Directorate of Public Works

Consultant : M/s.Sharjah Municipality Drainage Dept

Duration : 05 Months

Project Description : Excavate, Supply, Lay & Backfilling of Irrigation Line of

450mm GRP line of Approximately 4Km including necessary Fittings. Construction

of Flow meter, Butterfly, Washout, Air Valve Chambers along with the respective

fittings on the proposed line. Connect new 450 mm dia GRP pipe line to existing

225mm dia & 600mm dia GRP pipe line. NDRC Works for 450mm dia GRP Line of

about 30mtr by Microtunelling Method. Testing & commissioning of the Irrigation

line in complete respect.

Project Duration: 2014-2015

Project : Roads and Drainage Works of Noamiyah Street,

College

Street and Sheikh Jaber Al Sabah Street - Ajman

Page 47: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the

Project Value : 18,000,000.00 Dhs.

Employer : Darwish Engineering Emirates

Consultant : CDM Smith

Client : Ajman Municipality

Duration : 12 Months

Project Description : Excavation, Dewatering, Laying, Testing & Backfilling

of

UPVC Pipes and Fittings (approximately 4km) along with the respective fittings and

GRP Force main. Construction of 1200, 1500 & 1800mm dia Manholes and Gullies

along with the respective fittings. Construction of Pumping Station A Naimiyah Area

10mtr depth with the pumps including valve chamber. Breaking of existing pavement

of roads and reinstate. Connection of proposed line to existing manholes as described.

Pressure Testing complete line and Commissioning of Pumping Station.

Project Duration: 2015 - 2016

Project : Foul Drainage System to Four Hotels area at Al Rifa’a

Area - Foul Drainage System

Project Value : 11,303,148 Dhs.

Employer : Darwish Engineering Emirates

Consultant : Sharjah Municipality-Drainage Section (SMDS)

Client : M/s. Directorate of Public Works Sharjah (DPW)

Position : Project Manager

Project Description : Excavation, Dewatering, Laying, Testing & Backfilling

of

Page 48: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the

Miscellaneous uPVC pipes and GRP Pipes for Foul Drainage

System from Rafa’a area to Mirqab area including Pumping

Station , Screen Chamber and Odor Control unit with all

associated E & M Works . Also laying of Pumping Main

from the P. Station at Al Mirqab area to Nukhailat area at

Sharjah .

Project Duration: 2015 - 2016

Project : Foul Drainage Pumping Station for Al Jubail Market at

Sharjah

Project Value : 5,450,430.00 Dhs.

Employer : Darwish Engineering Emirates

Consultant : M/s. CH2M Halcrow

Client : M/s. Directorate of Public Works Sharjah (DPW)

Position : Project Manager

Project Description : Excavation, Dewatering, Laying, Testing & Backfilling

of twin with the twin 225 HDPE ,SDR 11, PN16 rising

main

to existing PS2 at Al Soor area at Sharjah .

Construction of Pumping Station and Odor Control unit

with all associated E & M Works .

Project Duration: 2016 -To date

Page 49: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the

Project : Construction of Road Work at New Extension Area

T5 –

at SAIF Zone at Sharjah

Project Value : Dhs.15,751,350.87

Main Contractor : Darwish Engineering Emirates

Client : SAIF Zone Authority

Duration : 12 Months

Consultant : M/s. CH2M Halcrow

Description : Road works including landscaping with footpath and all

the

Infrastructure works of water net works , Irrigation

works and

Foul Drainage network, Surface water Drainage

network,

Foul drainage gravity main to existing STP including all

the

associated works of Manholes ,Chambers , Gully traps,

Soak

away tanks Etc,

Project Duration: 2016 -To date

Project : Al Qasimia University pumping Foul Drainage Station ,

Rising main and Temporary Sewage Treatment Plant

Page 50: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the

Project Value : 7,270,000 Dhs.

Contractor : Darwish Engineering Emirates

Duration : 6 Months

Consultant : M/s. CH2M Halcrow

Client : Directorate of Public Works Sharjah (DPW)

Position : Project Manager

Project Description : Excavation, Dewatering, Laying, Testing & Backfilling

of

twin rising main of HDPE 280 mm Foul Drainage lines

including Pumping Station with all associated E&M

Works

with Odor Control unit and Temporary Sewage

Treatment

Plant with the outlet pipeline to existing storage tank at

Al

Qasimia University area Authority

Page 51: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the

5. REGISTRATION AND LICENSES

Page 52: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the
Page 53: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the
Page 54: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the
Page 55: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the
Page 56: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the
Page 57: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the
Page 58: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the

6. APPROVALS AND CERTIFICATES

Page 59: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the
Page 60: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the
Page 61: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the
Page 62: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the
Page 63: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the
Page 64: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the
Page 65: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the
Page 66: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the
Page 67: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the
Page 68: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the
Page 69: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the
Page 70: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the
Page 71: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the
Page 72: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the
Page 73: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the

7. PLANT AND MACHINERIES

Page 74: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the

AL JAZEERAH DRILLING L.L.C

PLANT SCHEDULE

S.no DESCRIPTION ENGINE NO. CHASIS NO MODEL PLATE PLATE

PLACE

COLOUR

1 LOADER 950F CATER PILLER 3116 4DJ03688 1997 15876 WHITE AJMAN

YELLOW

2 CHAIN EXCAVATOR 320B CAT 3066 3MR04564 1999 - - -

YELLOW

3 CHAIN EXCAVATOR 325 CAT 3116 8JG00267 1995 - - -

YELLOW

4 CHAIN EXCAVATOR 325L CAT 3116 7CJ00518 1994 - - -

YELLOW

5 JCB 3CX YELLOW 595751 405426 1992 44195 ORANGE SHJ

6 PICKUP 3 TON MITSUBISHI 4D32G69695 JMYFE635E0KA17526 1999 67122 ORANGE SHJ

CANTER GREEN

7 TRUCK HEAVY DUTY - NONE WDB6524681K115854 1995 25627 WHITE SHJ

MERCIDEZ - RED/YELLOW

8 DOUBLE CABIN TOYOTA 2RZ2722268 JTFDM626520021642 2002 9804 WHITE AJMAN

A

9 CAR TOYOTA COROLLA 1ZZ2772433 JTDBR22E873199004 2007 38472 ORANGE SHJ

10 PICKUP 3 TON MITSUBISHI 4D34L52624 JL7BCE1J18K003917 2008 17673 ORANGE SHJ

CANTER WHITE

11 MINI BUS WHITE XG491QME942328 LSHDAA98K065532 2008 96740 ORANGE SHJ

12 PICKUP MITSUBISHI - 200L 4G64AB7857 MMBJNKA508D016451 2008 17656 ORANGE SHJ

13 PICK UP TOYOTA 2723924 JTFDM626920021840 2002 9803 WHITE AJMAN

A

14 SUZUKI SWIFT M15A1178004 JS2ZC21SX75152168 2007 23208 WHITE SHJ

15 CHAIN EXCAVATOR 325L - NONE 7LM00708 1999 - - -

CATERPILLAR

16 CHAIN EXCAVATOR 320L - NONE 9KK04434 1999 - - -

CATERPILLAR

17 SHOVEL 950F CATERPILLAR NIL 5SK02051 1998 70137 ORANGE SHJ

YELLOW

Page 75: AL JAZEERAH DRILLING L.L · PDF file · 2017-01-19receiving pit 400mm below the pipe invert level or depends upon the ... A steel thrust plate 35mm thick is placed to transfer the

AL JAZEERAH DRILLING L.L.C

PLANT SCHEDULE

S.no Machinaries Total No. Remarks

19 Plate Compactor 10 06 Small & 4 Big Bomac Air Compressor Inma Atlas

20 Coopco 4

21 Air Compressor Blue 270L 4

22 Dewatering Pump Oisas Pump 25

23 Dewatering Pump Sykes 10

24 Jetting Pump 3

25 Concrete Vibrator 10

26 Welding Machine 4 Miller Brand

27 Asphalt Cutter Machine 2

28 Pressure Pump 2 Honda

29 Generator 2 Robine Patrol 2500/3000w

30 Radio Detection CAT 2

31 Jack Hammer 23kg 4

32 Hydraulic Jack 1

33 Power Pack 1

34 Electric Air winch 1

35 Theodolite & Level instrument 3

36 Butt Fusion Machine 1

Vermeer Horizontal Directional

37 Drilling Machine D36x50 1