CountryYear
178 ERC Refinery project E&I Package for the tie-in works HCC EGYPT 2017
177Al Burullus Power Plant
4800 M.W
Electro-Mechanical Construction
for Balance of Plant (BOP)HCC EGYPT 2016
176Al Burullus Power Plant
4800 M.W
Electro-Mechanical Construction
for 1 Steam Turbine (STG)HCC EGYPT 2016
175Al Burullus Power Plant
4800 M.W
Electro-Mechanical Construction
for 2 HRSGHCC EGYPT 2016
174Al Burullus Power Plant
4800 M.W
Electro-Mechanical Construction
for 2 Gas Turbines (CTG)HCC EGYPT 2016
173El Nasr Company for
Fertilizers and Chemical.Mechanical & Installation works HCC EGYPT 2016
172Al-Shabab & West
Damietta Power Project IBDT Al-Shabab & West Damietta HCC EGYPT 2016
171 ERC Refinery project SMP Package for Tie-in Work HCC EGYPT 2016
170El Nasr Company for
Fertilizers and Chemical.
Mechanical Rehabilitation
ActivitiesHCC EGYPT 2016
169Al-Shabab & West
Damietta Power Project
Piping Fabrication Al-Shabab &
West damiettaHCC EGYPT 2016
168
Al-Shabab Power Project
Converting Existing Simple
Cycle to Combined Cycle
Supply,Fabrication and Erection
of Fire Water TankHCC EGYPT 2016
167 ERC Refinery project Civil Package of Tie - in Works. HCC Egypt 2016
166SIDPEC Petrochemicals
Plant
Supply & Fabrication of heat
exchanger.HCC Egypt 2016
Al Hashemiah International Contracting Company
Reference list
Sr. EPC Contractor/Clients. Project Name Project Scope
Contract
or/
Fabricat
or
Project
CountryYear
Al Hashemiah International Contracting Company
Reference list
165West Damietta Combined
Cycle Power Plant
6 Deaerator supply,Fabrication
and exporting.HCC Egypt 2015
164The Egyptian Methanex
Methanol Company S.A.E.
Heat Exchangers Maintenance &
RepairHCC Egypt 2015
163 Mirfa Power Plant3 Blowdown Tank
supply,Fabrication and exporting.HCC U.A.E 2015
162
Assil & Karam
Development Project -
BAPETCO
Pressure Vessel fabrication HCC Egypt 2015
161 Assuit Oil Refinery Plant. Boiler Economizer fabrication HCC Egypt 2015
160 ERC Refinery project Piping Fabrication HCC Egypt 2015
159
Midele Delta Electricity
Production Company
(Nubaria Power Plant )
Maintenance & Repair for 2 Boiler HCC Egypt 2015
158SIDPEC Petrochemicals
Plant
6 Heat Exchanger Supply and
FabricationHCC Egypt. 2015
157 Mirfa Power Plant3 Deaerator supply,Fabrication
and exporting.HCC U.A.E 2015
156 Mirfa Power Plant3 HRSGs Piping Fabrication and
exporting.HCC U.A.E 2015
155
Bort Said Power Plant
Menia Power Plant
Assuit Power Plant
Beni Swef Power Plant
( fast track project)
24 Tank Supply & fabricationHCC Egypt. 2015
154Ataqa Power Plant
(fast track project)
4 Gas Turbine Electro-Mechanical
Installation 170 M.WHCC Egypt. 2015
153Ataqa Power Plant
(fast track project)BOP Mechanical Installation HCC Egypt. 2015
Sr. EPC Contractor/Clients. Project Name Project Scope
Contract
or/
Fabricat
or
Project
CountryYear
Al Hashemiah International Contracting Company
Reference list
152 Midelec Power PlantMechanical Works for Gas
Turbine 1,2 Outage HCC Egypt. 2015
151SIDPEC Petrochemicals
Plant
3 Heat Exchanger Supply and
FabricationHCC Egypt. 2015
150 Damitta Power Plant Chemical Cleaning for Boiler 1 & 2 HCC Egypt 2015
149Sidi Krir Power Plant 750
MW
Mainteance & Repair for Boiler
No.1,2HCC Egypt 2014
148
Middle Delta Electricity
Production Company
(Talkha Power Plant)
Mainteance & Repair for Boiler
No.1HCC Egypt 2014
147
Industrial & Mining Projects
Authority ( Safaga mining
port )
supply and erection the
Telescopic with dust control
system
HCC Egypt 2014
146 Damitta Power Plant Rehabilitation for Boiler 1 & 2 HCC Egypt 2014
145
Midele Delta Electricity
Production Company
(Nubaria Power Plant )
Rehabilitation for gas turbine HCC Egypt 2014
144
Cairo Electricity Production
Company
(Shobra Power Plant )
Rehabilitation for Boiler No.03 HCC Egypt 2014
143Brothers Group beverage
plant
Supply , fabrication and erection
for 7 Tanks.HCC Egypt 2014
142Delta Co. For Fertilizers &
Chemical Industries
Rehabilitation for Primary
Reformer include furnace, Burner
and reaction tube x-36.
HCC Egypt 2014
141Delta Co. For Fertilizers &
Chemical IndustriesRehabilitation for Boilers HCC Egypt 2014
140Delta Co. For Fertilizers &
Chemical Industries
Catalyst loading (nickel Oxide
Methantor , Cooper Oxide low
temp shiest reactor , Iron Oxide
High temp shiest reactor and
nickel Oxide secondary reformer )
HCC Egypt. 2014
Sr. EPC Contractor/Clients. Project Name Project Scope
Contract
or/
Fabricat
or
Project
CountryYear
Al Hashemiah International Contracting Company
Reference list
139Suez Thermal Power Plant
650 M.WBoiler External piping fabrication. HCC Egypt 2014
138
Suiz Steel Company
Direct Reduction
Plant(DRP)
Supply and fabrication for belt
convoyers , PGH Steam Super
heater bundle and Venturi body
for dusting.
HCC Egypt 2014
137
Suiz Steel Company
Direct Reduction
Plant(DRP)
erection , commissioning and
start-up activities for Direct
Reduction Plant DRP(Reactor ,
PG Heater ,Co2 plant , water
treatment plant ,…etc.)
HCC Egypt 2013
136
Banha Power Plant 750
M.W (CP106) Steam
Turbine
Installation for Steam turbine ,
Generators,Condensers include
all auxiliary components ,piping
,steel,..etc.
HCC Egypt 2013
135Suez Thermal Power Plant
650 M.WSupply & fabrication of tanks HCC Egypt 2013
134Suez Thermal Power Plant
650 M.WPressure parts fabrication
DSD/
HCCEgypt 2013
133SIDPEC Petrochemicals
Plant
Heat Exchanger Supply and
FabricationHCC Egypt. 2013
132 Midelec Power Plant2 GAS TURBINES Mechanical &
Installation Work.HCC Egypt. 2013
131Talkha Power Plant 750
MWRehabilitation for Boiler 1 & 2 HCC Egypt 2013
130
Banha Power Plant 750
M.W (CP118) BOP
Package
BOP package installation HCC Egypt 2013
129
Banha Power Plant 750
M.W (CP118) BOP
Package
BOP Steel Structure fabrication HCC Egypt 2013
128
Banha Power Plant 750
M.W (CP118) BOP
Package
BOP Piping fabrication HCC Egypt 2013
127Banha Power Plant 750
M.W (CP105) HRSG
2 HRSG Chemical Cleaning,
Steam Blowing and pre-
commisioning.
HCC Egypt 2013
Sr. EPC Contractor/Clients. Project Name Project Scope
Contract
or/
Fabricat
or
Project
CountryYear
Al Hashemiah International Contracting Company
Reference list
126Banha Power Plant 750
M.W (CP105) HRSG 2 HRSG Installation HCC Egypt 2013
125Banha Power Plant 750
M.W (CP105) HRSG
Pressure parts supply and
fabricationHCC Egypt 2013
124Egyption & Indian
petrochemical plant
Piping fabrication and Installation
for the plant HCC Egypt 2013
123The Nile Ritz-Carlton,
Cairo
3 Sand fillter supply and
fabricationHCC Egypt 2013
122
Banha Power Plant 750
M.W (CP111) Water
Treatment plant
23 Pressure Vessel Supply ,
fabrication and erectionHCC Egypt 2013
121
Giza North Power Plant
2250 M.W (CP111) Water
Treatment plant
23 Pressure Vessel Supply ,
fabrication and erectionHCC Egypt 2013
120
(ANRPC)
Alexandria National
Refining & Petrochemicals
Co.
Suppy , Fabrication and erection
of Boiler EconomizerHCC Egypt 2012
119
El Nasr company for
intermediate chemicals for
Al fayoum fertilizers plant
Hopper and 2 Tanks supply and
fabrication and erectionHCC Egypt 2012
118Touggourt Desalination
Plant
5 Pressure Vessels Suppy ,
Fabrication and exportingHCC Algeria 2012
117Denszli 750MW Combied
cycle Power Plant.
Service on site for the pressure
parts installaionHCC TURKEY 2012
116 Suez Steel Company
Rehabilitation for 2 boilers and 2
pressure vessels (Stripper &
Absorber)
HCC Egypt 2012
115Delta Co. For Fertilizers &
Chemical IndustriesRehabilitation for E127 Unit HCC Egypt. 2012
114 Borg Al Arab AirportSupply , Fabriation and Insallation
for the Airport new extensionHCC Egypt. 2012
Sr. EPC Contractor/Clients. Project Name Project Scope
Contract
or/
Fabricat
or
Project
CountryYear
Al Hashemiah International Contracting Company
Reference list
113Talkha Power Plant 750
MWPressure Parts Modifications. HCC Egypt. 2012
112 Abo Qir Oil Rigs
Tanks, Pressure Vessel , Piping
& Steel Structure Fabrication and
Erection
HCC Egypt. 2012
111West Damietta Simple
Cycle Power Plant
Fabrication and Installation of the
treatment plantHCC Egypt. 2012
110 Mostroud plantFabrication and Installation of the
mechanical equipmentHCC Egypt. 2012
109SIDPEC Petrochemicals
Plant
Heat Exchanger Supply and
FabricationHCC Egypt. 2012
108 Midelec Power Plant2 GAS TURBINES Mechanical &
Installation Work.HCC Egypt. 2012
107 Attamya Plant tank and Piping fabrication HCC Egypt. 2012
106Gemsa Petroleum Co.
(TOM)Marine Plant Condenser Retubing HCC Egypt. 2012
105 Damanhour Power Plant Retubing pipes for 2 cooler HCC Egypt 2012
104Cairo Electricity Production
CompanyHaprs Rehabilitation for Unit 4 HCC Egypt 2012
103
Suiz Steel Company
Direct Reduction
Plant(DRP)
Material Handling Modification HCC Egypt 2012
102El Nasr Company for
Fertilizers and Chemical.Super Heater Fabrication HCC Egypt 2012
101El Nasr Company for
Fertilizers and Chemical.
Change under ground 24" pipe
for 15 kmHCC Egypt 2012
Sr. EPC Contractor/Clients. Project Name Project Scope
Contract
or/
Fabricat
or
Project
CountryYear
Al Hashemiah International Contracting Company
Reference list
100
Suiz Steel Company
Direct Reduction
Plant(DRP)
General service and repair
activites for spiral welded pipes in
DRP Area
HCC Egypt 2012
99El Nasr Company for
Fertilizers and Chemical.
Rehabilitation of Ammonia Plant
(Startup heater,Primery reformer,
Secondery reformer,Convention
system)
HCC Egypt 2012
98
Suiz Steel Company
Direct Reduction
Plant(DRP)
WEAR RESISTANT LINING FOR
EXHAUSTED PROCESS GAS HCC Egypt 2012
97El Nasr Company for
Fertilizers and Chemical.
Rehabilitation of the Ammonia
ConverterHCC Egypt 2012
96El Segundo 750 MW
Combied cycle Power Plant.
2 HRSGs Fabrication and
ExportingHCC U.S.A 2012
95Egyption Iron and steel
Company
Heat Exchangers for lubricating
cellers Supply & FabricationHCC Egypt 2012
94Egyption Liquefied Natural
Gas Co.Mechanical Maintenance HCC Egypt 2011
93 Boilers Factory Phase II .Steel Structure Engineering,
Supply, Fabrication & Installation.HCC Egypt 2011
92Cairo Electricity Production
CompanyRetubing for Unit A Condenser HCC Egypt 2011
91El Nasr Company for
Fertilizers and Chemical.
Boiler installation and piping
installationHCC Egypt 2011
90 Daber Ltd Co.
Steel structure installation in New
GF Manufacturing Plant of Dabur
Egypt LTD Supply , Fabrication
and Installation
HCC Egypt 2011
89Abu Qir Power Plant Super
Heater
Supply and fabrication of
superheat low temperature
elements and new hanging
system design
HCC Egypt 2011
88 IETOS Co.4 pressure vessel fabrication and
InstallationHCC Egypt 2011
Sr. EPC Contractor/Clients. Project Name Project Scope
Contract
or/
Fabricat
or
Project
CountryYear
Al Hashemiah International Contracting Company
Reference list
87ALNASR Co. for
Intermediate Chemicals.
S.S Piping Fabrication Services
and transportation to site .HCC Egypt. 2011
86 Abu Zaabal Fertilzers Plant
Tanks, Gas ducts, Fired Boilers,
Piping Systems
Removing, Suppling, Fabrication,
Installation, Precommisioinig.
HCC Egypt. 2011
85International Company
Chemical Plant in Gamasa.
"Methanol & Chemicals" Tanks,
Fire Firghting System, Cooling
System
Engineering, Fabrication and
Installation.
HCC Egypt. 2011
84 ALNASR COKE Co.Boiler Economizer Supply,
Fabrication and Installation.HCC Egypt. 2010
83Kuraimat 1500 MW
Combined Cycle.
Cooler Repair and all tubes
changing.HCC Egypt. 2010
82Hemewg 750 MW Combied
cycle Power Plant.
2 HRSGs Fabrication and
ExportingHCC HOLLAND 2010
81Sidi Krir Power Plant 750
MWAlloy Piping System Installation. HCC Egypt. 2010
80 Aswan Fertilzers Plant
Belt conveyors
Supply, Fabrication, INstallation
and Pre-commisioning.
HCC Egypt. 2010
79 Etaka Power Plant 900 MW.Etaka Fired Boiler Coils
Installation.HCC Egypt. 2010
78Denszli 750MW Combied
cycle Power Plant.
2 HRSGs Fabrication and
ExportingHCC TURKEY. 2010
77 MAKRO CASH & CARRYFire fighting system fabrication
and installation.HCC Egypt. 2010
76Bachaquero 750 MW
Combied cycle Power Plant.
2 HRSGs Fabrication and
Exporting HCC Venezuela 2010
75
Mansoura for Resins &
Chemical Industries
Co. SAE
New Cemical Plant fabrication
and Installation.HCC Egypt. 2010
Sr. EPC Contractor/Clients. Project Name Project Scope
Contract
or/
Fabricat
or
Project
CountryYear
Al Hashemiah International Contracting Company
Reference list
74TAMARA 750 MW
Combied cycle Power Plant.
2 HRSGs Fabrication and
Exporting HCC Venezuela 2010
73Kuraimat Solar Power Plant
140 MWAlloy Tubes Fabication HCC Egypt. 2010
72Sidi Krir Power station 750
MW Combied cycle project
Piping Installation adding to Start
up and operation and reliabilty
test in progress and health safety
enviromental in work site test
HCC Egypt. 2010
71Eencogen Power Plant 750
MW.
2 HRSGs Fabrication and
Exporting HCC HOLLAND 2010
70 Ezz Flat Steel Factory Steel Structure Fabrication.NSF/HC
CEgypt. 2010
69 El-Atf Power Plant 750 MW2 HRSGs Chemical Cleaning
Systems.HCC Egypt. 2010
68 SIDI KRIR Power Plant
750 MW
2 HRSGs Chemical Cleaning
Systems.HCC Egypt. 2010
67 Sinoma Cement Factory Steel Structure Fabrication.NSF/HC
CEgypt. 2010
66 Midelec Power Plant2 GAS TURBINES Mechanical &
Installation Work.HCC Egypt. 2010
65 Saint-Gobain Glass Factory. Steel Structure Fabrication and
Installation
NSF/HC
CEgypt. 2010
64 Boilers Factory .Electrical System Engineering
and installation.HCC Egypt. 2010
63 Boilers Factory .Steel Structure Engineering,
Supply, Fabrication & Installation.HCC Egypt. 2010
62
Magnum 750 MW
Combined Cycle Power
Plant.
2 HRSGs Fabrication and
ExportingHCC HOLLAND 2009
Sr. EPC Contractor/Clients. Project Name Project Scope
Contract
or/
Fabricat
or
Project
CountryYear
Al Hashemiah International Contracting Company
Reference list
61Kuraimat Solar Power Plant
140 MWSteel Fabrication.
NSF/HC
CEgypt. 2009
60 Saint-Gobain Glass Factory.
Piping System, Furnace, Fire
Fighting, Equipments, Steel
Structure Fabrication and
Installation
HCC Egypt. 2009
59Kurimat 1500 MW Power
Plant III Site services for BOP. HCC Egypt. 2009
58Kurimat 1500 MW Power
Plant III
2 HRSGs Fabrication and
Installation, Chemical cleaning,
Blowing, Pre-Commissioning
Support.
HCC Egypt. 2009
57Kurimat 1500 MW Power
Plant III
Electrical & Instrumentation Site
Work.HCC Egypt. 2009
56Cairo West Power Station
1300 MW.
Piping, Vessels and Tanks
Installation.HCC Egypt. 2009
55Kurimat 1500 MW Power
Plant II Pressure Parts Modifications. HCC Egypt. 2009
54 EL-Hesn Co. Boiler Maintainance. HCC Egypt. 2009
53Eltebien Power Station 700
MW.
Piping, Vessels and Tanks
Installation.HCC Egypt. 2009
52 Alameria Petroluem Co. Boilers, Heat exchangers Repairs. HCC Egypt. 2009
51 Gemsa Petroleum Co.Marine Plant Condenser
Replacment.HCC Egypt. 2009
50Kuraimat Solar Power Plant
140 MWInstallation Activities HCC Egypt. 2009
49 Abu Qir Power Plant
Boiler Coils Fabrication
(Superheat Low tempreture
elements)
HCC Egypt. 2009
Sr. EPC Contractor/Clients. Project Name Project Scope
Contract
or/
Fabricat
or
Project
CountryYear
Al Hashemiah International Contracting Company
Reference list
48Cairo West 660 MW Power
Plant
Fired Boiler Coils and Water wall
Fabrication.
NSF/HC
CEgypt. 2009
47Nubaria 1500 MW Power
Plant 2 HRSGs Harps Fabrication
NSF/HC
CEgypt. 2009
46 Gemsa Petroleum Co. Heat Exchangers MaintenanceNSF/HC
CEgypt. 2009
45 Midelec Power Plant2 GAS TURBINES Mechanical &
Installation Work.HCC Egypt. 2009
44 Alatf Power Plant 750 MW 2 HRSGs Fabrication. HCC Egypt. 2009
43Talkha Power Plant 750
MWPressure Parts Modifications. HCC Egypt. 2009
42 Midelec Power Plant2 GAS TURBINES Mechanical &
Installation Work.HCC Egypt. 2008
41Sidi Krir Power Plant 750
MWPiping Fabrication for 2 HRSGs HCC Egypt. 2008
40SIDPEC Petrochemicals
PlantSuper Ceritical Piping Installation. HCC Egypt. 2008
39 Besos 750 MW Power Plant2 HRSGs Fabrication and
exporting.HCC Spain 2008
38 Khalda Oil Co. PlantS.S Piping System Fabrication
and Installation.HCC Egypt. 2008
37
Kerewalapitya 300 MW
Combined Cycle Power
Plant
2 HRSGs & BOP Fabrication and
exporting.HCC Sirilanka 2008
36Darling Downs 1500 MW
Power Plant
3 HRSGs Fabrication and
exporting.HCC Austeralia 2008
Sr. EPC Contractor/Clients. Project Name Project Scope
Contract
or/
Fabricat
or
Project
CountryYear
Al Hashemiah International Contracting Company
Reference list
35Massaied Power Plant -
2250 MW
6 HRSGs Fabrication and
exporting.HCC Qatar 2008
34
Egyptian Linear Alkyl
Benzene Project 100000
MT/year.
Piping Systems Supplying,
Fabrication and Installation.HCC Egypt. 2008
33 Midelec Power Plant2 GAS TURBINES Mechanical &
Insulation Work.HCC Egypt. 2007
32Luxor Water Treatment
Plant. Piping , Equipments Installation HCC Egypt. 2007
31 Assuit Oil Refinery Plant.Boiler Fabrication,Super
Heater,Reheater.HCC Egypt. 2007
30Kuraimat Power 1500 MW
Combined Cycle II & III.
Water Treatment Plant
Fabrication & Installation.HCC Egypt. 2007
29Kuraimat Power 1500 MW
Combined Cycle II Condenser Fabrication
IBSF/
HCCEgypt. 2006
28CAIRO North Power 1500
MW Combined Cycle II
2 HRSGs & BOP Piping
Installation Hydrotest, Chemical
Cleaning, Steam Blowing and
pre-commisioning.
IBSF/
HCCEgypt. 2006
27 Beni Swief Cement Project.SteelStructure and Handrails
Fabrication.
IBSF/H
CCEgypt. 2006
26Water Treatment Project in
MatrohPiping System Installation. HCC Egypt. 2006
25CAIRO North Power 1500
MW Combined Cycle II
2 HRSGs & BOP Piping
Fabrication .
IBSF/
HCCEgypt. 2006
24CAIRO North Power 1500
MW Combined Cycle II
Electrical & Instrumentation Site
Work.HCC Egypt. 2006
23 General Motors Factory.Piping system Fabrication &
InstallationHCC Egypt. 2006
Sr. EPC Contractor/Clients. Project Name Project Scope
Contract
or/
Fabricat
or
Project
CountryYear
Al Hashemiah International Contracting Company
Reference list
22CAIRO North Power 1500
MW Combined Cycle II
2 HRSGs Harps and Drums
Fabrication.
IBSF/
HCCEgypt. 2006
21CAIRO North Power 1500
MW Combined Cycle II
2 HRSGs Steel Structure, Stack
Fabrication.
IBSF/
HCCEgypt. 2006
20CAIRO North Power 1500
MW Combined Cycle II Condenser Fabrication.
IBSF/
HCCEgypt. 2006
19 Oil Fired Power Plant.Boiler Casing, Steel Structure,
Coils and water wall Fabrication
IBSF/
HCC LYBIA 2006
18 Combined Cycle 750 MW
Powr Plant.Stack Fabrication and Exporting.
IBSF/
HCCGreece 2006
17 Asuit Petrolum Co. Boilers Ducts Fabrication.IBSF/
HCCEgypt. 2006
16 Oil Plant Project.Oil Plant Piping System
Fabrication and Installation.HCC Egypt. 2005
15Nubaria Power Plant 1500
MW Combined Cycle.
Water Treatment Plant
Installation.HCC Egypt. 2005
14 Asuit Petrolum Co. Boiler 2 Long type Economizer
Fabrication.
IBSF/
HCCEgypt. 2005
13Amonia/ Urea Fertilizers
Project Suez II .Ceritical Piping PWHT.
OCI/HC
CEgypt. 2005
12 SYRIA ( MAGHASEL ). Boiler Economizer Fabriation. HCC Egypt. 2005
11 EASTERN CO. BOILERS Maintenance. HCC Egypt. 2005
10 Agiba Petroleum project Duplex & S.S Piping Fabrication. HCC Egypt. 2005
Sr. EPC Contractor/Clients. Project Name Project Scope
Contract
or/
Fabricat
or
Project
CountryYear
Al Hashemiah International Contracting Company
Reference list
9 Midelec Power Plant2 GAS TURBINES Mechanical &
Insulation Work.HCC Egypt. 2006
8 Alamyria Petroleum project
PIPING SYSTEMS
FABRICATION , Boiler Super
Heater.
IBSF/
HCCEgypt. 2005
7 Midelec Power Plant2 GAS TURBINES Mechanical &
Insulation Work.HCC Egypt. 2005
6Nubaria Combined Cycle
Power Plant 1500 MW
Water Treatment Plant
Fabrication.HCC Egypt. 2004
5 Abou Zaabal Fertilizers Tanks Fabrication & Installation. HCC Egypt. 2004
4 Mahmodia Power Plant Inspecting & Supplying C.S piping
System & Steel Structure.HCC Egypt. 2004
3 Alamyria Petroleum project. Boiler Economizer Fabrication. IBSF/
HCCEgypt. 2004
2Spanish Egyption Gas
LNG Plant. Piping Site Installation Activities. HCC Egypt. 2003
1Spanish Egyption Gas LNG
Plant.
Inspecting & supplying piping
system high pressure valves.HCC Egypt. 2003