airport master plan for montgomery-gibbs executive airport · 1/16/2018 · final public meeting....
TRANSCRIPT
Airport Master Plan forMontgomery-Gibbs Executive Airport PAC Meeting #4
Agenda
> Introductions> Public Meetings Overview> Introduction to Alternatives
> Airside> Landside
> World Café Instructions> Public Comment> Next Steps
Project Team Update
Public Meeting Overview
> Project website post> Email to contact database> Email to elected officials (Peters,
Sherman, Cate, Zapf, Bry)
> Nov 15, 2017 > Public Utilities Dept. Auditorium
> Notices included:
Public Meeting Overview
Public Meeting Overview
> Print ads, web ads, and/or online community calendar posts to:> Beach and Bay Press> Clairemont Community News> Clairemont Town Council Newsletters> La Jolla Village News> Mission Times Courier> Clairemont Times> Tierrasanta Community Council
Public Meeting Overview> Nextdoor posts to:
> Serra Mesa Northwest> Serra Mesa Central> Serra Mesa Northeast> Serra Mesa West Central> East Clairemont Mesa College> East Clairemont Lindbergh> Clairemont Olive Grove> Clairemont Madison> North Clairemont Innovation> Kearny Mesa> Spectrum> Murphy Canyon> La Jolla> Pacific Beach> Allied Gardens> Del Cerro
Public Meeting Overview
> Meeting format: Presentation and Information Stations
> Information presented:> Project process> Existing conditions of the airport> Environmental considerations> Forecasts of aviation demand> Facility requirements: Airside and landside
> Attendance: 29 (signed-in)> Meeting materials and public comments
available for review on the project website
Master Plan Process
Existing Conditions
Analysis
Forecasting & Facility
Requirements
Alternatives Evaluation &
FFA
Preferred Alternative &
CEQA Analysis
Master Plan Adoption &
ALP Approval
Ongoing Public Outreach
ALP – Airport Layout PlanCEQA – California Environmental Quality Act FFA – Financial Feasibility Analysis
Spring 2017 Summer 2018
We Are
Here
Introduction to Alternatives
Alternatives Analysis
Evaluation
• Identifies best options to meet existing and forecast aviation activity
Sources
• Working Papers 2 and 3 – Forecast of Aviation Demand and Facility Requirements
Elements• Airside and Landside Considerations
Application• Preferred Alternative Selection
Airside Alternatives
Alternative #1 No Action
DRAFTAlternative #2
DRAFTAlternative #3
DRAFTAlternative #4
Landside Alternatives
Alternative #1 No Action
DRAFTAlternative #2
DRAFTAlternative #3
DRAFTAlternative #4
World Café Instructions
World Café
PAC Comment
Public Comment
Next Steps
Alternatives Evaluation
Preferred Alternative
Working Paper 5 –Alternatives Analysis
Final Public Meeting
ALP Development
CEQA
ALP – Airport Layout PlanCEQA – California Environmental Quality Act