air_india_project rr

Upload: vishaljadhav1

Post on 09-Apr-2018

214 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/7/2019 AIR_INDIA_PROJECT rr

    1/50

    CAPITAL BUDGETING INAIR-INDIA

    PROJECT REPORT SUBMITTED IN PARTIAL FULFILLMENT OFTHE REQUIREMENTS FOR THE AWARD OF THE DEGREE OF

    MASTER OF MANAGEMENT STUDIES.

    MUMBAI UNIVERSITY

    SUBMITTED BY: -

    Mr. VISHAL D. JADHAV

    M.M.S 09-11 (Finance)

    SUBMITTED TO: -

    AIR- INDIA LTD.

    UNDER THE GUIDANCE: -

    Mr. SHOBHAN A. TALAVDEKAR

  • 8/7/2019 AIR_INDIA_PROJECT rr

    2/50

    DECLARATION

    I HEREBY DECLARE THAT I HAVE COMPLETED THIS PROJECT ON CAPITAL

    BUDGETING IN THE ACADEMIC YEAR 2010-2011. THIS INFORMATION IS TRUE AND

    ORIGINAL TO THE BEST OF MY KNOWELEDGE.

    ACKNOWLEDGMENT

    2

  • 8/7/2019 AIR_INDIA_PROJECT rr

    3/50

    It is indeed a great pleasure to express my thanks & gratitude to all those people who helped me

    during this summer training period. This project would not have been materialized without the

    help from many quarters.

    I express a deep sense of gratitude to Miss Pervin Choksey, Asst. General Manger-Finance and

    all the members of Capital Budget & Property Control Section, Finance Department. Their

    guidance suggestion & expertise have been a source of inspiration & were very helpful to me

    during our project work.

    I am deeply thankful to Mr. Shobhan Talavdekar, Dy. Manger-Finance and Mr. Bindoo M.

    Katti Asst. Manager Finance for guiding me through general training and providing valuable

    advice through out the project work.

    INDEX

    3

  • 8/7/2019 AIR_INDIA_PROJECT rr

    4/50

    Sr.

    No

    Topic Page no.

    1 INTRODUCTION TO AIR INDIA 4

    2 FINANCE DEPARTMENT IN AIR INDIA 14

    3 CAPITAL BUDGETING SECTION 16

    4 CAPITAL BUDGET PROCESS 20

    5 PREPARATION OF CAPITAL BUDGET 23

    6 PROJECT CLASSIFICATION 28

    7 CAPITAL EXPENDITURE/INVESTMENT DECISIONS 29

    8 ACCOUNTING OF CAPITAL EXPENDITURE 40

    9 NACIL CAPITAL BUDGET 2010-11 44

    10 CONCLUSION 48

    11 RECOMMEDATION 49

    12 BIBLIOGRAPHY 50

    BRIEF HISTORY OF AIR INDIA

    Air India is Indias national Airline. Air Indias history can be

    traced to October 15, 1932. On this day J.R.D. Tata, the father ofCivil Aviation in India and founder of Air India, took off from

    Drigh Road Airport, Karachi, in a tiny, light single-engine de

    Havilland Puss Moth on his flight to Mumbai via Ahmadabad.

    Air India was earlier known as Tata Airlines. At the time of its

    4

  • 8/7/2019 AIR_INDIA_PROJECT rr

    5/50

    Commencement, Tata Airlines consisted of one Puss Moth, one Leopard Moth, one palm-

    thatched shed, one whole time pilot, one part-time engineer, and two apprentice-mechanics. Tata

    Airlines was converted into a Public Company under the name of Air India in August 1946. On

    March 8, 1948, Air India International Limited was formed to start Air Indias international

    operations. On June 8, 1948, Air India started its international services with a weekly flight from

    Mumbai to London via Cairo and Geneva with a Lockheed Constellation aircraft.

    In early 1950s due to deteriorating financial condition of various airlines, the Government

    decided to nationalize air transport. On August 1, 1953 two autonomous corporations were

    created. Indian Airlines was formed with merger of eight domestic airlines to operate domestic

    services, while Air India International was established to operate the overseas services. The word

    'International' was dropped in 1962. With effect from March 1, 1994 the airline has been

    functioning as Air India Limited. Air India's worldwide network today covers 44 destinations by

    operating services with its own aircraft and through code-shared flights. Important destinations

    covered by Air India are Bangkok, Hong Kong, Jakarta, Kuala Lumpur, Osaka, Singapore,

    Tokyo, Seoul, Dar-es-Salam, Nairobi, Frankfurt, London, Paris, Birmingham, Abu Dhabi, Al

    Ain, Bahrain, Dammam, Doha, Dubai, Jeddah, Muscat, Riyadh, Kuwait, Los Angeles, Chicago,Newark, New York, and Toronto.

    INCORPORATION

    Established in 1953 under Air Corporations Act

    Became Public Limited Company in 1994

    Registered Office : New Delhi

    Head Office : Mumbai

    Authorized Capital : Rs 500.00 Crores

    Paid-up Capital : Rs 153.84 Crores

    SUBSIDIARY COMPANIES

    5

  • 8/7/2019 AIR_INDIA_PROJECT rr

    6/50

    Air India has the following Subsidiary Companies with an Authorized / Paid-up Capital

    (in Rs. Crores) as under:

    Authorised Paid-up

    (a) Hotel Corporation of India 41.00 40.00

    (b) Air India Charters Ltd. 30.00 30.00

    (c) Air India Air Transport Services Ltd. 100.00 0.05

    (d) Air India Engineering Services Ltd. 10.00 0.05

    Hotel Corporation of India Ltd (HCI)

    Centaur Hotels at Juhu, Mumbai Airport and Rajgir Sold

    Centaur Hotel at Delhi, Chefair-New Delhi and Chefair-Mumbai Under Disinvestment

    Air India Charters Ltd (AICL)

    New Airline Air India Express set-up under AICL in 2005. It is Air-Indias low-cost

    subsidiary which was established during the aviation boom in India

    All AI Express operations carried out on B-737-800 with a current

    Fleet strength of 12.

    Air India Air Transport Services Ltd (AIATSL )

    Incorporated in June 2003

    set up to undertake ground handling & other allied activities

    being operational zed at all domestic airports

    Air India Engineering Services Ltd (AIESL)

    Incorporated to undertake engineering and other allied activities

    To be operational zed

    Cabinet approval required

    INDIAN AIRLINES

    6

    http://en.wikipedia.org/wiki/Air-India_Expresshttp://en.wikipedia.org/wiki/Low-cost_airlinehttp://en.wikipedia.org/wiki/Air-India_Expresshttp://en.wikipedia.org/wiki/Low-cost_airline
  • 8/7/2019 AIR_INDIA_PROJECT rr

    7/50

    Indian Airlines was Indias first state owned domestic airline. Indian Airlines was set up under

    the aegis of federal Union Ministry of Civil Aviation and based in New Delhi. Its main bases

    were the international airports in Chennai, Mumbai, Kolkata and New Delhi.

    Indian Airlines came into being with the enactment of the Air Corporations Act, 1953. Indian

    Airlines started its operations from 1st August, 1953, with a fleet of 99 aircraft and was the

    outcome of the merger of seven former independent airlines, namely Deccan Airways, Airways-

    India, Bharat Airways, Himalayan Aviation, Kalinga Air Lines, Indian National Airways and Air

    Services of India. The year 1964 saw the Indian Airlines moving into the jet era with the

    introduction of Caravelle aircraft into its fleet followed by Boeing 737-200 in the early 1970.

    Along with its wholly owned subsidiary Alliance Air, it flies a fleet of 70 aircraft including

    Airbus A300, Airbus A320, Airbus A319, Boeing 737, Dornier Do-228, ATR-4, Airbus A319,

    A320 & A321. Along with Indian cities, it flies to many foreign destinations which include

    Kuwait, Singapore, Oman, UAE, Qatar, Bahrain, Thailand, Singapore, Malaysia, and Myanmar

    besides Pakistan, Afghanistan, Nepal, Bangladesh, Sri Lanka and Maldives.

    The main base of the Indian airlines are Chatrapati Shivaji International Airport, Mumbai; Indira

    Gandhi International Airport, Delhi; Netaji Subhash Chandra Bose International Airport,

    Kolkata; Chennai International Airport, Chennai.

    NATIONAL AVIATION COMPANY OF INDIA LIMITED (NACIL)

    (Amalgamation of Air India Limited and Indian Airlines Limited)

    The Government of India, on 1 March 2007, approved the merger of Air India and Indian

    Airlines. Consequent to the above, a new Company viz National Aviation Company of

    India Limited (NACIL) was incorporated under the Companies Act, 1956 on 30 March 2007

    with its Registered Office at Airlines House, 113 Gurudwara Rakabganj Road, New Delhi.

    The Certificate to Commence Business was obtained on 14 May 2007.

    7

  • 8/7/2019 AIR_INDIA_PROJECT rr

    8/50

    The Scheme of Amalgamation of Air India Limited and Indian Airlines Limited with

    National Aviation Company of India Limited was approved by the Board of Directors of all

    the three Companies.

    Thereafter, the Meetings of Secured and Unsecured Creditors of Air India and Indian Airlines

    were held in New Delhi on 28 June 2007, in which the Scheme of Amalgamation was approved

    by the Creditors. The final hearing of the merger petition was held on 31 July 2007 wherein

    the last date of submissions of objections was fixed on 8 August 2007 and the Order Ministry

    of Corporate Affairs is awaited.

    The Authorized and Paid-Up Share Capital of the merged entity is Rs.1500,05,00,000/-

    and Rs.145,00,00,000/-, respectively.

    COMPANY PROFILE:

    It has been decided that post merger, the new entity will be known as Air India while

    Maharaja will be retained as its mascot. The logo of the new airline will be a red colored

    flying swan with the Konark Chakra in orange placed inside it. The flying swan has been

    morphed from Air Indias characteristic logo The Centaur whereas the Konark Chakra

    was reminiscent of Indians logo. The Corporate Office of NACIL will be at Mumbai.

    This new airline is also a member of the Star Alliance, the largest airline alliance.

    8

  • 8/7/2019 AIR_INDIA_PROJECT rr

    9/50

    The Government has approved the appointment of Shri V Thulasidas and Dr V Trivedi as

    Chairman & Managing Director and Joint Managing Director, respectively, of the merged entity,

    with effect from the date of merger.

    Presently, the Board of NACIL consists of:

    Shri Raghu Menon, Addl Secretary & Financial Advisor, Ministry of Civil Aviation

    Shri R K Singh, Jt Secretary, Ministry of Civil Aviation

    Shri Rajiv Bansal, Director, Ministry of Civil Aviation

    AIR INDIA (NACIL) CURRENT FLEET:

    9

  • 8/7/2019 AIR_INDIA_PROJECT rr

    10/50

    Note:

    * Includes 3 under Sale & Lease Back.

    ** All under Sale & Lease Back.

    *** Includes 8 under Sale & Lease Back. and 11 more are under proposal for sale.**** Includes 2 under Sale & Lease Back.

    % 2 A310 Freighters are under process of Lease Out.

    10

    NACIL Fleet (As on 1st February 2010)

    -

    -

    - *

    -

    -

    - **

    -

    ***

    -

    - ****

    -

  • 8/7/2019 AIR_INDIA_PROJECT rr

    11/50

    OBJECTIVES

    1. To provide safe, efficient, adequate, economical and properly co-ordinate international airservices, and develop such services to the best advantage.

    2. To provide high standard of services to passengers and customers on ground and in the air.

    11

  • 8/7/2019 AIR_INDIA_PROJECT rr

    12/50

    3. To achieve, maintain and improve its rightful place in the international air transport

    industry.

    4. To make an increasing contribution to the national economy and maximize revenues withefficient fleet utilization and route network.

    5. To promote international tourism to India and improve the nations foreign exchangeresources.

    6. To assist in the promotion of nations export trade.

    7. To improve the national economy by encouraging local skills and technology to getequipment and materials other than air crafts, indigenously manufacture with the intention

    to curtain imports steadily.

    8. To promote healthy relations with the various employees unions for ensuring employees cooperation in the performance of companies activities.

    9. To provide wider participation amongst its employees in management functions.

    12

  • 8/7/2019 AIR_INDIA_PROJECT rr

    13/50

    SWOT ANALYSIS:

    13

    STRENGTHS WEAKNESSES

    Professionally qualified team contributingvital inputs on corporate decisions

    Expertise in Treasure & currencyManagement in a multi currency Global

    environment.

    Effective compliance of Govt. auditobservation / suggestions resulted in NILaudit reports from comptroller and Auditor

    General (CAG) during the last 4

    consecutive years.

    Active participation in international forumViz. IATA, ICAO etc relating to

    Global Aviation financing issues.

    Negotiating Skills-on financing relatedissues with International Banks, financial

    institutions, Insurers, underwriters, Fuel

    contractors, Export credit Agencies etc.

    Effective monitoring on Repayment ofAircraft /Non Aircraft loans-resulting in

    NO DEFAULT ever in Debt servicing.

    Ban on recruitmenta) Time-bound promotion policy-inability to

    reward talents

    b) Ageing, non-qualified/professional staff

    Lack of adequate IT systems and procedure toadapt to the enhanced level of corporate

    surveillance being introduced by the Govt. atvarious levels in order to prevent corporate

    delinquencies/ bankruptcies.

  • 8/7/2019 AIR_INDIA_PROJECT rr

    14/50

    FINANCE DEPARTMENT (AIR INDIA)

    14

    OPPORTUNITIES THREATS

    International Banks - Ready to offerglobal cash Management

    System.

    Swap Interest/currency- Reduce InterestBurden & cap the burden Due to

    fluctuation in interest rate.

    Fuel Hedging- RBI approval received andcounter party selection in process for

    hedging in fuel prices for international

    uplifts.

    Arranging new Aircraft loans to financenetwork & introduction of real time /

    online computerized based systems.

    Introduction of the system of corporateGovernance & Accounting at various levels

    including the establishment of Audit

    committees following the implementation of

    Naresh Chandra committee recommendation

    by the Government, resulting in the

    maintenance & administration of more string

    stringent standards at various levels in theorganizational hierarchy.

    Threats of Mergers, Amalgamation,Consolidation by Mega carriers and

    Marginalization of small carriers, line with

    practices followed by mega carriers for inter &

    intra firm comparison.

    Introduction of US GAAP by many companiesin India in order to provide greater transparency

    to International Financial Institution and enable

    funding by Export credit Agencies.

    NACIL being an International company andbeing a Global player has to train a number of

    staffs in the field of provide the cutting edge

    financial technology.

  • 8/7/2019 AIR_INDIA_PROJECT rr

    15/50

  • 8/7/2019 AIR_INDIA_PROJECT rr

    16/50

    Manages interlinked settlement with different airlines.

    Cargo and Mail Section

    Manages revenues collected by the cargo.

    Taxation

    Calculates taxes like VAT, Income Tax, Sales Tax, Service Tax, Octri, Revenue Tax, etc.

    Pay Accounts

    Concerned with the salary calculation of the employees taking into consideration the

    allowances granted to the staff, paid leave, leave without pay, increments, etc.

    Internal Audit Section

    This section deals with the internal audit of accounts prepared by the Financial

    Accounting section.

    3. Stores Accounts Section:

    Stores are those products which are purchased by Air India to be provided on board to the

    travelers or for sale. Purchasing of such products is dealt by this section.

    4. Insurance Section:

    Deals with aircraft insurance and also non-aircraft insurance like vehicles, machinery and

    furniture.

    ORGANISATIONAL STRUCTURE OF CAPITAL BUDGETING

    SECTION:

    16

  • 8/7/2019 AIR_INDIA_PROJECT rr

    17/50

  • 8/7/2019 AIR_INDIA_PROJECT rr

    18/50

    Capital budget is prepared on yearly basis for new & continuing projects. It is allocation of funds

    category wise & department wise for the particular year. Subsequent years capital budget is

    prepared by considering last year project cost addition & deletions/utilization during the year.

    CONTINUING PROJECT

    Each department may have some previous years project to be continues this year also.

    NEW PROJECT

    Each department may have some new project to be started this year.

    SANCTION REQUEST FORM (SRF)

    Approved SRf are sent by the Department for each project, partly or fully to property control

    section. Same is sent to purchase Department for procurement action. Along with purchase

    requisition form (PR). It is checked that SRFs risen by departments should not cross the

    financial limits of the particular project.

    PURCHASE ORDER (PO)These are prepared sent by stores & purchase department to property control section.

    WORK ORDER (WO)

    Work order are prepared & properties department & engineering department

    VENDORS INVOICE:

    Invoices are sent by purchase department for advance payments or full & final settlement.

    As case may be along with authorization for making par et to property control section with GRN

    or installation report.

    BILL INTERIM PAYMENTS CERTIFICATE/FINAL FOR PAYMENT

    18

  • 8/7/2019 AIR_INDIA_PROJECT rr

    19/50

    These are sent by civil work & engineering Department to property control section along with

    authorization for making payment advance or full & final as case may be.

    CASH VOUCHER (CV)

    Cash voucher is prepared for all the invoices received & the amount is debited to respective

    capital asset account (nearly 100) or advance account as the case may be. Payment register is

    maintained for all cash/cheque payments for partys invoices received forms s & p as well as

    civil work.

    JOURNAL VOUCHER (JV)

    In case GRN or installation report is received after some period, JV is passed for debiting

    appropriate Capital Asset Account adjusting the Advance Account debited earlier. On half yearly

    basis, C.W. & P. Engineering Department sends an ABC statement giving status of the various

    projects. Referring to that statement for completed project a JV is passed for debiting appropriate

    asset account/ work-in-progress account.

    DETAIL COLLECTION FOLDER:These folders are written on the basis of cvs, jvs passed at property control section. These

    folders are written monthly Account wise. Station wise property purchase Advices & property

    receipt advances received from stations quarterly.

    FIXED ASSETS REGISTER (NON AIRCRAFT)

    Fixed asset register is written annually using the detail collection folder & maintained account

    code wise, station wise, department wise.

    FIXED ASSET REGISTER (AIR CRAFT)

    This is written on the basis of Jv, prepared & sent by project control section.

    19

  • 8/7/2019 AIR_INDIA_PROJECT rr

    20/50

    SCRAPPAGE ENTRY

    Scrap page advices duly approved & received from various department & control section & JV is

    passed for asset value, cumulative depreciation, written down value, sales proceeds, profit & loss

    etc. scrapped is maintained account code wise.

    CAPITAL BUDGET PROCESS

    Capital Budgeting is a complex process which may be divided into the following phases:

    Identification of potential investment opportunities.

    Organizing proposed investment.

    20

  • 8/7/2019 AIR_INDIA_PROJECT rr

    21/50

  • 8/7/2019 AIR_INDIA_PROJECT rr

    22/50

    Proposals are usually classified into various categories for facilitating decision making

    budgeting, and control. An illustration classified is given below:

    Replacement investment

    Expansion investment

    New product/service investment

    Obligatory and welfare investment

    (C) Decision making

    A problem of rupee gateways usually characterizes capital investment decision making. Under

    this system, executives are vested with the power to approve investment proposals up to certain

    levels. For example, in one company the plant superintendent can approve investment outlays, up

    to Rs. 2.00 crores, the works manager up to Rs. 1.00 crores. Investments requiring higher outlays

    need the approval of the board of directors.

    (D) Preparation of capital budgeting appropriations

    Process involving smaller outlays and which can be decided by executives at lower levels are

    covered by blanket appropriation for expeditious action. Projects involving larger capital are

    included in the capital budget after necessary approvals. Before undertaking such project an

    appropriation order is usually required. The purpose of this check is mainly to ensure that the

    funds position of the firm is satisfactory at the time of implementation.

    (E) Implementation

    Implementing an investment proposal into a concrete project is a complex, time consuming, risk

    fraught task. Delays in Implementation, can lead to substantial reduction in rate of return.For expeditious Implementation at a reasonable cost, the following are helpful.

    i. Adequate formulation of project

    22

  • 8/7/2019 AIR_INDIA_PROJECT rr

    23/50

  • 8/7/2019 AIR_INDIA_PROJECT rr

    24/50

  • 8/7/2019 AIR_INDIA_PROJECT rr

    25/50

    2. The capital budget is prepared and submitted to the board according to departments,

    regions and SBUs (Strategic Business Unit). It is requested to all concerned directors,

    executive directors and SBU heads to submit their proposals under New and Continuing

    Schemes.

    3. The capital budget requirment is to be submitted by the respective director, executive

    directors and SBU heads relating to their departments/ unit under the different categories

    for the both New and Continuing Schemes uneder the enclosed format specified for each

    category.

    There are certain guidelines given in the circular which are to be followed for preparing

    and compiling the Capital Budget requirement of the department, unit and region.

    1. The schemes which are not required to be implemented further are to be deleted.

    Wherever additional provisions are required for continuing schemes, same is to be shown

    separately with justification along with estimated amount of expenditure.

    2. The departmental proposals regarding building/ workshops under new and continuing

    schemes are to be routed through Properties and Facilities Department to weigh the

    project by them and for obtaining project cost and estimated expenditure for the budgetedyear.

    3. The requirement for replacement of vehicles for operational areas pertaining to the

    department should be routed through Ground Service Department (GSD) with full details

    of stations where GSD representatives are present. Similarly, the requirement for new

    vehicle should be approved by head quarters. Without the HQs approval the requirement

    will not be considered in the budget formation.

    4. The Office Equipment, vehicles and miscellaneous items costing less than Rs. 10 lacks

    will be budgeted under new schemes only. The balance from last years budget under

    above categories will not be carried forward and will be lapsed.

    5. The project report is to be submitted by departments for project/ schemes costing more

    than Rs. 1 crore each giving cost benefit analysis as required by the Board.

    25

  • 8/7/2019 AIR_INDIA_PROJECT rr

    26/50

    6. As per the Institute Of Chartered Accountant manual, Capital expenditure costing less

    than rupees 5000 each, is not treated as Capital expenditure and not provided in the

    capital budget. The details of such expenditure be included in the Departments Revenue

    Expenditure Budget.

    7. It is requested to exercise utmost economy in expenditure and submit the requirements

    with full details in the prescribed format for continuing and new schemes under each

    category latest by mid of December.

    8. On compilation of the information by Capital Budget and Property Control Section, the

    proposals will be discussed with the respective Departments/Units/Regions before

    finalization and submission to the Board for approval.

    9. Capital budget booklet is prepared by Property Control Section for Boards approval. The

    proposal approved by the Board are entered in the system category wise and department

    wise under new and continuing schemes, including block funds for unforeseen

    circumstances.

    STAGE-I: The proposals when received from various departments are categorized under one

    of the following:a. Building and workshops -Budget category F

    b. Ground Handling and Ramp Equipment - Budget category C

    c. Workshop Equipment and Plant and Machinery -Budget category D

    d. Computer facilities and Equipment - Budget category H

    e. Office Equipment and Furniture including PCs - Budget category A

    f. Vehicles - Budget category B

    They are checked with reference to need/justification, details cost breakup etc and query list is

    prepared (Time 15 days).

    STAGE II: After scrutiny of proposals the query list is sent to respective departments for

    further details-clarifications. On receipt of reply a summer for each department category wise is

    prepared showing estimated payments of all proposals (time 10 days).

    26

  • 8/7/2019 AIR_INDIA_PROJECT rr

    27/50

    STAGE-III: The section further scrutinizes the proposal in the light of justification, resources

    position of the company (time 10 days).

    STAGE-IV: They call departments representatives for discussions, for further information/

    clarification in respect of major projects. Based on this an inclusion/deletion of proposals are

    finalized and the budget is sized up. Operational requirement are to be considered first while

    sizing up (time 7 days).

    STAGE -V: The sized up budget is thereafter forwarded by finance department to Headquarters

    for approval of MD/Chairman before it is finalized. For project costing above Rs. 1.00 crore

    included in the budget are to be presented by respective department before MD/CMD or Board.

    STAGE-VI: The budget proposals so cleared by MD/Chairman, is sent by section to printing

    press for preparation of the capital budget booklets. These booklets are then forwarded to HQ

    well in time for submitting to the Board members (time 15 days).

    PROJECT CLASSIFICATION

    27

  • 8/7/2019 AIR_INDIA_PROJECT rr

    28/50

    Project analysis entails time and effort. The cost incurred in this exercise must be justified by the

    benefits from it, certain projects, given their complexity and magnitude, may warrant detailed

    analysis. Hence firms normally classify projects into different categories. Each category is then

    analyzed somewhat differently.

    While the system of classification may vary from one firm to another, the following categories

    are found in most classifications.

    (A)Mandatory investments

    These are expenditures required to comply with statutory requirements. Examples of such

    investments are pollution control equipments, medical dispensary, fire fighting equipments,

    crche in factory premises, and so on. These are often non revenue producing investments. In

    analyzing such investments the focus is mainly on finding the most cost-effective way of

    fulfilling a given statutory need.

    (B) Replacement projects.

    Firms routinely invest in equipments meant to replace obsolete inefficient equipments, eventhough they may be in serviceable condition. The objective of such investment is to reduce costs

    (of labour, raw material and power), increased yield, and improve quality. Replacement projects

    can be evaluated in a fairly straightforward manner, though at times the analysis may be quite

    detailed.

    (C) Expansion projects

    These projects are meant to increase capacity and/or widen the distribution network. Such

    investments call for explicit forecast of growth. Since this can be risky and complex, expansion

    projects normally warrant more careful analysis than replacement projects. Decisions relating to

    such projects are taken by the top management.

    (D)Diversification projects

    28

  • 8/7/2019 AIR_INDIA_PROJECT rr

    29/50

    These investments are aimed at producing new products and services or entering into nearly new

    geographical areas. Often diversification projects entail substantial risks, involve large outlay,

    and require considerable managerial effort and attention. Given their strategic importance, such

    projects call for a very thorough evaluation, both quantitative and qualitative. Further, they

    require a significant involvement of the board of directors.

    (E) Research and development projects

    Traditionally, R&D projects absorbed a very small proportion of capital budget in most Indian

    Companies. Things, however, are changing. Companies are now allocating more funds to R&D

    projects, more so in knowledge intensive industries. R&D projects are characterized by

    numerous uncertainties and typically involve sequential decision making. Such projects are

    decided on the basis of managerial judgment. Firms which rely more on quantitative methods use

    decision tree analysis and option analysis to evaluate R&D projects

    (F) Miscellaneous projects

    This is a catch-all category that includes items like interior decoration, recreational facilities,

    executive aircrafts, land spaced gardens, and so on. There is no standard approach for evaluatingthese projects and decisions regarding them are based on personal preferences of top

    management.

    ECONOMIC EVALUATION OF INVESTMENT PROPOSALS

    The analysis stipulates a decision rule for:

    I) accepting or II) rejecting investment projects

    (A) Net present value (NPV)

    29

  • 8/7/2019 AIR_INDIA_PROJECT rr

    30/50

    The NPV method is used for evaluating the desirability of investments or projects.

    where:

    Ct = the net cash receipt at the end of year t

    Io = the initial investment outlay

    r = the discount rate/the required minimum rate of return on investment

    n = the project/investment's duration in years.

    The discount factor r can be calculated using:

    Examples:

    Decision rule:

    If NPV is positive (+): accept the projectIf NPV is negative(-): reject the project

    (B) The internal rate of return (IRR)

    The IRR is the discount rate at which the NPV for a project equals zero. This rate means

    that the present value of the cash inflows for the project would equal the present value of its

    outflows.

    The IRR is the break-even discount rate.

    30

  • 8/7/2019 AIR_INDIA_PROJECT rr

    31/50

    The IRR is found by trial and error.

    wherer = IRR

    IRR of an annuity:

    where:

    Q (n,r) is the discount factor

    Io is the initial outlay

    C is the uniform annual receipt (C1 = C2 =....= Cn).

    Economic rationale for IRR:

    If IRR exceeds cost of capital, project is worthwhile, i.e. it is profitable to undertake.

    (C) The profitability index - PI

    This is a variant of the NPV method.

    Decision rule:

    PI > 1; accept the project

    PI < 1; reject the project

    If NPV = 0, we have:

    NPV = PV - Io = 0

    PV = Io

    Dividing both sides by Io we get:

    PI of 1.2 means that the project's profitability is 20%. Example:

    31

  • 8/7/2019 AIR_INDIA_PROJECT rr

    32/50

    PV of CF Io PIProject A 100 50 2.0

    Project B 1,500 1,000 1.5

    Decision:

    Choose option B because it maximizes the firm's profitability by $1,500.

    Disadvantage of PI:

    Like IRR it is a percentage and therefore ignores the scale of investment.

    (D)The payback period (PP)

    The CIMA defines payback as 'the time it takes the cash inflows from a capital investment

    project to equal the cash outflows, usually expressed in years'. When deciding between two or

    more competing projects, the usual decision is to accept the one with the shortest payback.

    Payback is often used as a "first screening method". By this, we mean that when a capital

    investment project is being considered, the first question to ask is: 'How long will it take to pay

    back its cost?' The company might have a target payback, and so it would reject a capital project

    unless its payback period was less than a certain number of years.

    Example 1:

    Years 0 1 2 3 4

    Project B - 10,000 5,000 2,500 4,000 1,000

    Payback period lies between year 2 and year 3. Sum of money recovered by the end of the

    second year

    = $7,500, i.e. ($5,000 + $2,500)

    Sum of money to be recovered by end of 3rd year

    = $10,000 - $7,500

    = $2,500

    = 2.625 years

    32

  • 8/7/2019 AIR_INDIA_PROJECT rr

    33/50

    Disadvantages of the payback method:

    It ignores the timing of cash flows within the payback period, the cash flows after the end of

    payback period and therefore the total project return.

    It ignores the time value of money. This means that it does not take into account the fact that

    $1 today is worth more than $1 in one year's time. An investor who has $1 today can

    consume it immediately or alternatively can invest it at the prevailing interest rate, say 30%,

    to get a return of $1.30 in a year's time.

    It is unable to distinguish between projects with the same payback period.

    It may lead to excessive investment in short-term projects.

    Advantages of the payback method:

    Payback can be important: long payback means capital tied up and high investment risk.

    The method also has the advantage that it involves a quick, simple calculation and an easily

    understood concept.

    Allowing for inflation

    So far, the effect of inflation has not been considered on the appraisal of capital investment

    proposals. Inflation is particularly important in developing countries as the rate of inflation tends

    to be rather high. As inflation rate increases, so will the minimum return required by an investor.

    For example, one might be happy with a return of 10% with zero inflation, but if inflation was

    20%, one would expect a much greater return.

    Example:

    Keymer Farm is considering investing in a project with the following cash flows:

    TIME

    ACTUAL CASH FLOWS

    Z$

    0 (100,000)

    1 90,000

    2 80,000

    3 70,000

    33

  • 8/7/2019 AIR_INDIA_PROJECT rr

    34/50

    Keymer Farm requires a minimum return of 40% under the present conditions. Inflation is

    currently running at 30% a year, and this is expected to continue indefinitely. Should Keymer

    Farm go ahead with the project?

    Let us take a look at Keymer Farm's required rate of return. If it invested $10,000 for one year on

    1 January, then on 31 December it would require a minimum return of $4,000. With the initial

    investment of $10,000, the total value of the investment by 31 December must increase to

    $14,000. During the year, the purchasing value of the dollar would fall due to inflation. We can

    restate the amount received on 31 December in terms of the purchasing power of the dollar at 1

    January as follows:

    Amount received on 31 December in terms of the value of the dollar at 1 January:

    = $10,769

    In terms of the value of the dollar at 1 January, Keymer Farm would make a profit of $769 which

    represents a rate of return of 7.69% in "today's money" terms. This is known as the real rate of

    return. The required rate of 40% is a money rate of return (sometimes known as a nominal rate of

    return). The money rate measures the return in terms of the dollar, which is falling in value. Thereal rate measures the return in constant price level terms.

    The two rates of return and the inflation rate are linked by the equation:

    (1 + money rate) = (1 + real rate) x (1 + inflation rate)

    where all the rates are expressed as proportions.

    In the example,

    (1 + 0.40) = (1 + 0.0769) x (1 + 0.3)

    = 1.40

    So, which rate is used in discounting? As a rule of thumb:

    a) If the cash flows are expressed in terms of actual dollars that will be received or paid in the

    future, the money rate for discounting should be used.

    b) If the cash flows are expressed in terms of the value of the dollar at time 0 (i.e. in constant

    price level terms), the real rate of discounting should be used.

    34

  • 8/7/2019 AIR_INDIA_PROJECT rr

    35/50

    In Keymer Farm's case, the cash flows are expressed in terms of the actual dollars that will be

    received or paid at the relevant dates. Therefore, we should discount them using the money rate

    of return.

    TIME CASH FLOW DISCOUNT FACTOR PV

    $ 40% $

    0 (150,000) 1.000 (100,000)

    1 90,000 0.714 64,260

    2 80,000 0.510 40,800

    3 70,000 0.364 25,480

    30,540

    The project has a positive net present value of $30,540, so Keymer Farm should go ahead with

    the project.

    The future cash flows can be re-expressed in terms of the value of the dollar at time 0 as follows,

    given inflation at 30% a year:

    TIME ACTUAL CASH FLOW CASH FLOW AT TIME 0 PRICE LEVEL

    $ $

    0 (100,000) (100,000)

    1 90,000 69,231

    2 80,000 47,337

    3 70,000 31,862

    The cash flows expressed in terms of the value of the dollar at time 0 can now be discounted

    using the real value of 7.69%.

    TIME CASH FLOW DISCOUNT FACTOR PV$ 7.69% $

    0 (100,000) 1.000 (100,000)

    1 69,231 64,246

    35

  • 8/7/2019 AIR_INDIA_PROJECT rr

    36/50

    2 47,337 40,804

    3 31,862 25,490

    30,540

    The NPV is the same as before.

    Expectations of inflation and the effects of inflation

    When a manager evaluates a project, or when a shareholder evaluates his/her investments, he/she

    can only guess what the rate of inflation will be. These guesses will probably be wrong, at leastto some extent, as it is extremely difficult to forecast the rate of inflation accurately. The only

    way in which uncertainty about inflation can be allowed for in project evaluation is by risk and

    uncertainty analysis.

    Inflation may begeneral, that is, affecting prices of all kinds, orspecific to particular prices.

    Generalized inflation has the following effects:

    a) Inflation will mean higher costs and higher selling prices. It is difficult to predict the effect of

    higher selling prices on demand. A company that raises its prices by 30%, because the general

    rate of inflation is 30%, might suffer a serious fall in demand.

    b) Inflation, as it affects financing needs, is also going to affect gearing, and so the cost of

    capital.

    c) Since fixed assets and stocks will increase in money value, the same quantities of assets must

    be financed by increasing amounts of capital. If the future rate of inflation can be predicted with

    some degree of accuracy, management can work out how much extra finance the company will

    need and take steps to obtain it, e.g. by increasing retention of earnings, or borrowing.

    However, if the future rate of inflation cannot be predicted with a certain amount of accuracy,

    then management should estimate what it will be and make plans to obtain the extra finance

    accordingly. Provisions should also be made to have access to 'contingency funds' should the rate

    of inflation exceed expectations, e.g. a higher bank overdraft facility might be arranged should

    the need arise.

    36

  • 8/7/2019 AIR_INDIA_PROJECT rr

    37/50

    (I) PURCHASE V/S LEASING

    In many cases it may be found that leasing is economical and advantageous to the company as in

    quite a number of countries tax benefits accruing to the lesser are passed on to the lessees.

    Besides, leasing terms may provide full or partial maintenance which will save considerable

    recurring expenditure incidental to outright purchase.

    Further, in either leasing or outright purchase consideration could be given for TSC arrangement

    whereby cash outgo can be avoided. The TSC arrangement is moreover advantageous to the

    company as the carriage provided on the companys services is against normal applicable

    fares/freight rates whereas in some parts of the world actual sale cost of such transportation may

    be less.

    Care should be taken that the expenditure proposal related to item of durable nature which can be

    easily maintained/ service and also there is a commonality in usage so as to avoid maintenance

    problem as well as stocking of excessive inventories of spares, etc, if different items/model are to

    be procured.

    In terms of delegation of financial power as explained above, financial concurrence is a must. In

    case of abstention this requirement would have to be met not only at the station level but also at

    the regional level whereby a proposal pertaining to a station requires to be vetted not only by the

    Accounts Manager of the station but also by the Regional Director concerned in consultation

    with the Regional Finance and Accounts Manager.

    Why Should They Lease Equipment Instead of Buy?

    Leasing is flexible

    37

  • 8/7/2019 AIR_INDIA_PROJECT rr

    38/50

    Companies have different needs, different cash flow patterns and sometimes irregular-

    streams of income. For example, start-up companies typically are characterized by little cash

    and limited debt lines. Mature companies might have other needs: to keep debt lines free, to

    comply with debt covenants, and avoid committing to equipment that may quickly become

    obsolete. Therefore, your business conditions-cash flow, specific equipment needs, and tax

    situation- may help define the terms of your lease.

    Moreover, a lease provides the use of equipment for specific periods of time at fixed rental

    payments. Therefore, leasing allows you to be more flexible in the management of your

    equipment.

    Leasing is practicalBy leasing, you transfer the uncertainties and risk of equipment ownership to the lesser,

    which allows you to concentrate on using that equipment as a productive part of your

    business.

    Leasing is cost effectiveEquipment is costly and some of the costs are unexpected. When you lease, your risk of

    getting caught with obsolete equipment is lower because you can upgrade or add equipment

    to best meet your needs.

    Further, your equipment needs can change over time due to change in your company, such as

    diversification. Leasing allows you to stay on the cutting edge of technology. Sophisticated

    business managers have learned that the primary benefits of higher productivity and profit

    come from the use of equipment, not owing it.

    Leasing has tax advantages

    38

  • 8/7/2019 AIR_INDIA_PROJECT rr

    39/50

    Rather than deal with depreciation schedules and Alternative Minimum Tax (AMT)

    problems, you, the lessee, simply make the lease payment and deduct it as a business

    expense.

    Leasing helps conserve your operating capitalLeasing keeps your lines of credit open. You dont tie up your cash in equity. Also, you

    avoid costly down payments. With other advantages such as off balance sheet financing,

    leasing helps you better manage your balance sheet.

    CONTROLS

    Capital expenditure budget itself is a system of controlling in advance, after assessing the

    requirements of various operating units and which are duly vetted by the Finance Department.Boards approval is merely an administrative sanction as mentioned before, but before the

    expenditure is actually committed and incurred, a process known as Executive Sanction or

    Sanction Request Form has to be progressed. Delegation of powers to departmental/station heads

    specify the powers of financial limits up to which the departmental/station heads can operate the

    budget and accord Executive Sanction which thus provide an opportunity to have a second look

    before committing funds on capital expenditure. Major items of expenditure, by this process

    have always to be cleared by the Chief Executive, which means that expenditure on such items

    cannot be simply committed merely for the reason that there is an administrative approval in

    existence. This is a very useful and effective system of controlling capital expenditure and in fact

    provides the organization with every opportunity of reviewing the expenditure on capital items

    even right up to the time of actual procurement action .

    39

  • 8/7/2019 AIR_INDIA_PROJECT rr

    40/50

    ACCOUNTING OF CAPITAL EXPENDITURE

    40

  • 8/7/2019 AIR_INDIA_PROJECT rr

    41/50

    With executive sanction for incurring the capital expenditure having been obtained as stated

    above, actual procurement action may be taken after following the usual store procedure abd

    necessary purchase order issued. Payment of capital expenditure would be made on the strength

    of the sanction request form (SRF), purchase order, and goods received not or in its absence

    certification by the person responsible for the receipt of such capital items. Payments made in

    this fashion world require to be debited to the respective asset account head as per the description

    of the item and as given in the accounts code books.

    1. Property control procedures:

    41

  • 8/7/2019 AIR_INDIA_PROJECT rr

    42/50

    Property control i.e. accounting, recording, inventory and vouching is primarily accounts

    responsibility. Tag no. Should be affixed to all assets of the corporation as per the tag no.

    Indicated in the SRF. Each sanction is allotted a block of tag no. By the property control

    division and metal tags duly embossed with the prefix and Sr. No. Is supplied from the

    Santacruz, if required then the tag no are assigned. Motor vehicles are identified by their

    registration no. And buildings are identified by their registration no. And buildings are

    identified by the municipal door no.

    2. Property purchase Advice

    Stations are required to send a monthly list of capital asset purchased by the 10th of the

    following month to the property control division, accounts department, santacruz as per

    specimen enclosed (attachment C).

    3. Asset/Inventory register

    Wide format D encloses stations that may maintain an up to date record of capital assets

    location-wise and category-wise, annually as per the directions issued in this regard every

    year. Certified inventories of not only those items which are taken up for physically

    verification but also of all assets held at the station are required to be forwarded to the

    property control division by the 30 th may of every year. It may be noted that the furniture

    in office premises need not be physically verified. Physical inventory of residential furniture

    etc. Is compulsory, every year.

    4. Need for proper asset inventory control

    Maintenance of asset record location-wise and item-wise, apart from the necessity of

    keeping a proper record of the fixed assets which largely represents the net worth of the

    company vis-a-vis creditors and lending financial institutions, it is also an audit requirement

    as usually the auditors have to satisfy themselves about the correctness and completeness of

    42

  • 8/7/2019 AIR_INDIA_PROJECT rr

    43/50

    the asset records maintained by the company and record their remarks to this effect in the

    published annual accounts and auditors report.

    Asset inventory helps proper evaluation of capital expenditure proposals either for replacing

    an existing item or procuring a new/additional item. It further helps retirement and write-off

    of assets in a systematic way.

    From our far-flung stations in the network, we usually ensure receipt of certified physical

    inventories each year and biannually cover the physical verification of the considerably

    large quantum of assets held at the headquarters base on a selective basis.

    5. Retirement of property and scrap page

    Before any asset is retired or disposed off, approval for scrap page of the same has to be

    obtained from the departmental head concerned. After receipt of the scrap page approval

    stations may arrange to dispose may arrange to dispose of the items after following the usual

    stores property and not to asset account. When the disposal involves a huge lot of items upon

    a closure of a station or off-line office or due to renovation or moving to new premises, and

    in case of disposal of major equipments as well as motor vehicles, the bits received should be

    put to controller of stores and purchases for his prior clearance before the sale is affected. In

    such case usually it is advisable to have a local committee consisting of the managers,

    accounts manager and representative of the user division to go into all aspect of sale and

    make the appropriate tender noting. Scrap page advice worlds require to be issued as per

    format E attached. It should also be noted that the disposal of an item would not

    automatically entitle replacement of the same, as the normal process of budgeting, executive

    sanction and other process would require to be gone through before items can be replaced.

    43

  • 8/7/2019 AIR_INDIA_PROJECT rr

    44/50

    NATIONAL AVIATION COMPANY OF INDIA LIMITED

    CAPITAL BUDGET OF 2010-2011

    1. The Annual Plan Outlay for the year 2010-11 was framed at Rs 4434.80 crores.

    However, approval of the Annual Plan 2010-11 from Ministry of Civil Aviation has been

    received for Rs 5634.80 crores i.e. after adding Rs 1200 crores as Gross Budgetary

    Support (GBS) in the form of Equity Infusion during the year by the Govt of India.

    2. The Capital Budget for the year 2010-11 has accordingly been made within the

    Annual Plan Outlay of Rs 4434.80 crores submitted to the Ministry of Civil Aviation.

    The details of the Capital Budget 2010-11 are as follows:

    (Rs in Crores)(A) Aircraft Projects

    i) Payments to Aircraft Manufacturers for new Boeing Aircraft 3330.36

    ii) Payments to Aircraft Manufacturers for new Airbus aircraft 204.97

    iii) Interest to be capitalized for new Boeing Aircraft 251.52

    iv) Payment for Spare Engines for new Boeing aircraft 261.22

    v) Payment towards infrastructure for new Airbus aircraft 116.81 4164.88

    (B) Non-Aircraft Projects

    i) Other Capital Expenditure 269.92

    TOTAL 4434.80

    3. The total outgo under Aircraft Projects is estimated to be Rs 4164.88 crores as

    detailed above. During the year, 5 new aircraft are to be received by the company

    comprising of 1 A-321 aircraft from Airbus Industrie and 4 B 777-300 ER aircraft from

    Boeing. The total payments to aircraft manufacturers during the year for these aircraft is

    estimated to be Rs 3786.85 crores. In addition, 3 GE spare engines shall be received from

    GE Aircraft Engines during 2010-11 at an estimated outgo of Rs 261.22 crores. The outgo

    on account of infrastructural support payments for induction of new aircraft, which

    includes payment for spare parts, ground handling, engineering workshop equipment etc,is estimated to be Rs 116.81 crores during the year.

    4. The non aircraft projects include an outgo of Rs 269.92 crores under the head of

    Other Capital Expenditure which includes Rs 82.73 crores for New Schemes and

    Rs.187.19 crores for Continuing Schemes. The expenditure under this head represents the

    payments to be made towards other capital projects such as Building Projects, Computer

    44

  • 8/7/2019 AIR_INDIA_PROJECT rr

    45/50

    & Communication Equipment, IT Projects, Ground Support Equipment, Workshop

    Equipment Plant & Machinery and Other Miscellaneous Assets etc.

    5. Apart from the above outgo of Rs 4434.80 crores, the Miinistry of Civil

    Aviation has made a provision of Rs 1200 crores as budgetary support in the form of

    equity infusion in the company during the year 2010-11.

    I) New Schemes Rs. 82.73 crores

    The new projects to be undertaken and capital expenditure thereon required to be

    incurred during the financial year 2010-11 are as under:

    45

  • 8/7/2019 AIR_INDIA_PROJECT rr

    46/50

    Outgo

    2010-11

    1) Buildings & Workshopsa) Northern Region

    i) Civil/Interior & allied works at Terminal 3 New Delhi 27.43 10.00

    ii) Satellite Hangar/Workshop at Terminal 3 New Delhi 10.40 4.00

    b) Eastern Region

    i) Construction of GSE Complex Workshop at Kolkata. 3.80 0.10

    c) SBU-Cargo

    i) Drop Box Outlets at six metros 3.00 0.30

    ii) Warehouse at Mumbai & Chennai 5.00 0.50

    iii) Sales Offices at six metros 1.20 0.20

    d) MRO-Engine & Components

    i) Merging of APU Centre Module I & II at Kolkata 5.00 1.00

    ii) Construction of 3rd & 4th Floor over Annexure Building in

    New Hangar Complex at Kolkata

    1.30 0.10

    e) Other Departments/SBUs 4.85 2.06

    Total of (1) 61.98 18.26

    2) Ground Handling & Ramp Equipment

    a) SBU Ground Handling

    i) GH Equipment viz AC Unit, GPUs, Tractors etc 10.00 10.00

    b) Other Departments(SBU-Cargo) 1.00 1.00

    Total of (2) 11.00 11.00

    3) Workshop Equipment, Plant & Machinery

    a) Engine Overhaul

    i) CNC Milling Machine at OAP 2.00 0.50

    b) MRO-Engine & Components

    i) Setting up of CFM 56-5B engine servicing facility at

    JEOC New Delhi

    41.00 10.00

    ii) Test Bench for CIDS Director 5.04 1.00

    iii) Universal Hydraulic Component Test Stand for

    Accessory Overhaul Mumbai

    9.00 2.00

    iv) Renovation and upgradation of Hi-Flow facility 5.00 0.50v) APU Testing Facility Kolkata 21.32 3.00

    vi) Setting up of servicing facility for A-320 Kolkata 4.55 2.00

    c) Other Departments/SBUs 28.07 10.87

    Total of (3) 115.98 29.87

    4) Computer Facilities/Equipment

    a) Information Technology

    i) Centralized Oracle DB Server 1.00 0.10

    ii) New SAN Box 1.20 0.10

    iii) New PROS Project 6.00 0.50

    b) Quality Management System (QMS)

    i) Fuel & Operational Efficiency Management 10.00 5.00

    c) Other Departments/SBUs 4.45 1.90

    Total of (4) 22.65 7.60

    5) Office Equipment - Block Provision 8.00 8.006) Vehicles - Block Provision 4.00 4.00

    7) Unforeseen Expenditure - Block Provision 4.00 4.00

    Total New Schemes-Non Aircraft 227.61 82.73

    Particulars Project Cost

    (Rs in Crores)

    46

  • 8/7/2019 AIR_INDIA_PROJECT rr

    47/50

    II-a) Continuing Schemes Rs. 187.19 crores

    The Capital Expenditure on Continuing Schemes for 2010-11 is placed at Rs. 187.19 crores.These Continuing Schemes also include an additional cost of Rs.32.62 crores due to

    operational requirements as under, for which specific approval of the Board is required:

    (Rs in Crores)Particulars Additional

    Cost

    1) Buildings & Workshops

    a) Southern Region

    i) Setting up of common booking offices at various stations 0.10

    2) Workshop Equipment, Plant & Machinery

    a) Materials Managementi) Automated Storage Retrieval System for aircraft spares 0.50

    b) Engine Overhaul

    i) Aviation Software Package for Maintenance including MRO

    Management & Operations

    25.00

    ii) Video Boroscope 0.15

    3) Computer Facilities/Equipment

    a) Information Technology

    i) Network Up gradation 0.37

    b) Central Planning & Control Systems

    i) Setting up of Central Planning & Control Systems (CPCS) 6.50

    Total (1 to 3) 32.62

    II-b) Under Continuing Schemes, certain old projects/schemes where there had been no

    expenditure/outgo for two years or more have been dropped from Continuing Schemes and the

    same can be reinstated as New Schemes in future as and when operational necessity arises. The

    total Project Cost of such Continuing Schemes which have been dropped is Rs 40.16 crores.

    47

  • 8/7/2019 AIR_INDIA_PROJECT rr

    48/50

    CONCLUSION

    The Scope of our project was limited to capital budgeting for the Non-Aircraft section.

    Air india like every other airlines has been making losses due to

    Excess capacity

    Lower yield

    Drop in passenger numbers

    An increase in fuel prices

    The Effects of the global slowdown

    Though It has shown good sign as its operating loss has decreased by 39 per cent from `5,672

    crore in 2008-09 to `3,472 crore in 2009-10, while the net loss dipped by 23 per cent from `7,189

    crore in 2008-09 to `5,551 crore in 2009-10. However still a lot needs to be done as the company

    is struggling to cover even its total variable costs.

    The role of capital budgeting section is very significant in such scenario as fixed assets and lease

    expenses form major source of cash outflow in an airline industry. The expenditure for workshop

    equipment, plant and machinery and Computer facilities/equipments has been increased over the

    previous year. This indicates that the efforts are being made to improve the productivity of

    existing business by the application of improved modern and technological applications.

    48

  • 8/7/2019 AIR_INDIA_PROJECT rr

    49/50

    RECOMMENDATION

    Equity of Air India should be restricted so that they can have a much wider equity on

    which they can build up debt.

    The government should immediately provide some amount as equity as per AI estimates,

    for financial restructuring of Air India which would raise the paid-up share capital of Air

    India.

    A priority based capital budgeting with the cash inflows from one project be reinvestedinto another project will reduce its capital demand on long run.

    Management information system (MIS) and Database management system needs to be in

    place in order to increase efficiency and should be effectively enforced via capital

    budgeting process.

    As Voluntarily retirement schemes and very few recruitment, the workforce is likely to

    decrease in the coming years and it will lead to decrease in expenses however to maintain

    the productivity the employees need to be provided with additonal training in computers

    and its cost vs beneefit needs to be considered.

    49

  • 8/7/2019 AIR_INDIA_PROJECT rr

    50/50

    BIBLIOGRAPHY

    http://www.air-india.com

    Financial Management by Khan & Jain.

    Nacil capital budget annual handbook.

    Various magazines and reports published by Air-India