air quality analysis report: i-75 managed...

60
NOISE TECHNICAL REPORT I-75 Managed Lanes: From SR 155 to SR 138 CSNHS-0009-00(156) and CSNHS-0009-00(157) PI Nos. 0009156 and 0009157 Henry and Clayton Counties Prepared by: Edwards-Pitman Environmental, Inc. Prepared for: FEDERAL HIGHWAY ADMINISTRATION and GEORGIA DEPARTMENT OF TRANSPORTATION

Upload: dangphuc

Post on 09-Apr-2018

215 views

Category:

Documents


1 download

TRANSCRIPT

NOISE TECHNICAL REPORT

I-75 Managed Lanes: From SR 155 to SR 138

CSNHS-0009-00(156) and CSNHS-0009-00(157)

PI Nos. 0009156 and 0009157

Henry and Clayton Counties

Prepared by:

Edwards-Pitman Environmental, Inc.

Prepared for:

FEDERAL HIGHWAY ADMINISTRATION and

GEORGIA DEPARTMENT OF TRANSPORTATION

October 2012

NOISE TECHNICAL REPORT: I-75 MANAGED LANES October 2012

TABLE OF CONTENTSEXECUTIVE SUMMARY........................................................................................................................E-1

1. INTRODUCTION............................................................................................................................1-11.1 Project Background................................................................................................................1-11.2 Project Alternatives................................................................................................................1-2

1.2.1 Build Alternatives......................................................................................................1-21.2.2 No Build Alternative..................................................................................................1-6

2. EXISTING NOISE ENVIRONMENT...................................................................................................2-12.1 Background.............................................................................................................................2-1

2.1.1 Noise Fundamentals.................................................................................................2-12.1.2 Typical Hourly Leq Sound Levels.................................................................................2-12.1.3 Factors Affecting Traffic Noise Levels.......................................................................2-3

2.2 FHWA Noise Prediction Methodology....................................................................................2-32.3 Definition of Type I Projects....................................................................................................2-42.4 FHWA Noise Criteria...............................................................................................................2-42.5 Assignment of Activity Categories..........................................................................................2-62.6 Existing Noise Measurements.................................................................................................2-8

2.6.1 Existing Measurement Location, Methodology and Results.....................................2-82.6.2 Model Validation......................................................................................................2-9

2.7 Existing Sound Levels..............................................................................................................2-9

3. NOISE IMPACT ASSESSMENT..........................................................................................................3-13.1 FHWA Noise Impact Assessment Methodology......................................................................3-13.2 Noise Impact Assessment.......................................................................................................3-33.3 Noise Analysis Findings...........................................................................................................3-3

3.3.1 Analysis result by Receptor Location........................................................................3-33.3.2 Projected Sound Levels for Undeveloped Land Without a Permit............................3-4

4. NOISE ABATEMENT.........................................................................................................................4-14.1 Land Use and Zoning...............................................................................................................4-14.2 Traffic Management...............................................................................................................4-14.3 Alignment Alterations.............................................................................................................4-14.4 Structural Barriers..................................................................................................................4-1

5. CONSTRUCTION NOISE...................................................................................................................5-1

6. CONCLUSION/STATEMENT OF LIKELIHOOD....................................................................................6-1

CSNHS-0009-00(156) and CSNHS-0009-00(157)PI Nos. 0009156 and 0009157Henry and Clayton Counties

Page i

NOISE TECHNICAL REPORT: I-75 MANAGED LANES October 2012

ATTACHMENTS

Attachment 1 Figures Related to Noise ModelingAttachment 2 Field Measurement Data Sheets and ValidationAttachment 3 Sound Level ResultsAttachment 4 TNM Input/Output DataAttachment 5 Study Area InformationAttachment 6 Traffic Data

LIST OF FIGURES

Figure 1-1. Project Location................................................................................................................1-3Figure 2-1. Common Indoor and Outdoor Noise Levels......................................................................2-2

LIST OF TABLES

Table 2-1. FHWA Noise Abatement Criteria.......................................................................................2-5Table 2-2. Existing Field Measurements and TNM Results (dBA Leq).................................................2-9Table 3-1. Summary of Receiver Impacts By NAC...............................................................................3-4Table 3-2. Projected Sound Levels to Aid Local Officials.....................................................................3-5Table 4-1. Noise Wall Design..............................................................................................................4-2Table 4-2. Cost Effectiveness Summary..............................................................................................4-4

CSNHS-0009-00(156) and CSNHS-0009-00(157)PI Nos. 0009156 and 0009157Henry and Clayton Counties

Page ii

NOISE TECHNICAL REPORT: I-75 MANAGED LANES October 2012

GDOT Projects CSNHS-0009-00(156) and CSNHS-0009-00(157)Henry and Clayton Counties, PI No. 0009156 and 0009157October 2012

Project Name: I-75 MANAGED LANES: FROM SR 155 TO SR 138

MPO and TIP Number: This project is identified in the Plan 2040 Regional Transportation Plan and FY 2012-2017 Transportation Improvement Program by reference numbers: AR-ML-630 and AR-ML-640.

Project Description: Project numbers CSNHS-0009-00(156) and CSNHS-0009-00(157) involve the construction of a reversible, barrier-separated, managed lane system along southbound I-75 in Henry County and Clayton County. The project begins at the I-75 bridge over SR 155 and ends approximately 600 feet north of the I-75 southbound off ramp to SR 138 (Stockbridge Highway) at the Henry/Clayton County line and at SR 138 along I-675 in Clayton County, for a total length of 12.24 miles. There are two alternatives (express toll lanes [ETL] and high occupancy toll 3+ [HOV 3+]) currently being evaluated within the project corridor. Each alternative would construct a new managed-lane only interchange connection to provide access into the managed lane system. This interchange would be located just south of the existing I-75 interchange with Jonesboro Road. The roadway footprint would be identical for each alternative. Therefore, the findings in this report associated with the build alternative are applicable to both alternatives.

Modeling Assumptions: Estimation of traffic-related sound levels associated with the existing, no-build and build alternatives was conducted using the Federal Highway Administration (FHWA) Traffic Noise Model (TNM), version 2.5. Inputs to the model include existing and future roadway alignments, area terrain, and the shielding effects of structures within the corridor.

To provide a “worst case” analysis of the existing and future conditions, traffic volumes were based on a level of service (LOS) C capacity for each travel lane operating at the posted speed limit. Truck percentages (%) were based on traffic data provided by Parsons Transportation Group. Existing truck percentages of 9% (3% medium truck, 6% heavy truck) were used along I-75 while future condition truck percentages were modeled at 10% (3% medium truck, 7% heavy truck). The distribution of these truck percentages in travel lanes for medium and heavy trucks was based on field reconnaissance of the project corridor.

Summary of Findings: In accordance with GDOT’s Noise Policy (July 2011) and FHWA Regulations (23 CFR Part 772), it is anticipated that construction of the proposed alternative would result in traffic related noise impacts to 237 of the 708 receivers (representing 606 of 2,343 receptors) in the study area. Noise abatement measures were evaluated. A detailed barrier analysis determined that noise barrier walls would be reasonable and feasible at nine locations along the project corridor.

Prepared By: Drew Pitman QC/QA: Josh Earhart

November 2, 2012 November 2, 2012 Date Date

Approved By:

Date

CSNHS-0009-00(156) and CSNHS-0009-00(157)PI Nos. 0009156 and 0009157Henry and Clayton Counties

Executive SummaryPage E-1

NOISE TECHNICAL REPORT: I-75 MANAGED LANES October 2012

1. INTRODUCTION

In compliance with 23 USC Section 109(h) and (i), the Federal Highway Administration (FHWA) established guidelines for the assessment of highway traffic-generated noise. These guidelines, published as Part 772 of Title 23 of the Code of Federal Regulations (23 CFR Part 772), provide procedures to be followed in conducting noise analyses that will protect the public health and welfare. In accordance with the Noise Control Act of 1972, coordination of this regulation with the Environmental Protection Agency (EPA) has been completed. The following assessment has been prepared in accordance with 23 CFR Part 772.

This report documents the results of a noise analysis completed for the proposed project, in order to:a. Provide baseline noise levels that will be used in determining project impact. b. Predict the effects that the proposed project would have on the noise environment. c. Identify impacted locations where noise abatement is feasible and reasonable and likely to be included in the

project and locations where impacts will occur and abatement is not feasible and reasonable.

1.1 Project Background

An efficient, accessible, and safe transportation network that provides reliable travel times is vital to an urban region’s ability to move people, goods, and services effectively. Interstate 75 (I-75) south of Atlanta is one of the most traveled highways in the Atlanta region. As Henry County’s population grew 63 percent between 2000 and 2009, from 119,341 to 195,370 (US Census 2010), traffic volumes on I-75 between State Route (SR) 155 and SR 138 have been growing at a rate of between 3 and 6.4 percent per year, and the current average daily traffic volume ranges between 104,060 and 147,880 vehicles per day. This section of I-75 has become increasingly congested during the AM peak northbound and the PM peak southbound due to the rapid growth of development and traffic volumes. Because of the increasing congestion, travel time reliability has deteriorated and travel speeds and mobility have declined. Moreover, transit services and ride-sharing are no more reliable than single-occupant automobile travel because there are no dedicated high-occupancy vehicle (HOV) facilities on which comparatively higher reliability of travel times could provide inducements to greater usage of transit and ridesharing.

On June 21, 2007, the Georgia State Transportation Board adopted a resolution stating that:

• All new capacity lanes within limited access corridors in Metro-Atlanta shall be managed,• Mobility shall be guaranteed in the managed lane,• Lane management relies on eligibility, congestion pricing, and/or accessibility, and• Within the context of a system-wide plan, each solution will be tailored to individual corridor needs.

On December 10, 2009, the Georgia State Transportation Board approved the Atlanta Regional Managed Lane System Plan (MLSP) to be used as a guide for the Georgia Department of Transportation (GDOT) in developing individual managed lane projects within Metro-Atlanta. The justification for a managed lanes approach includes the following:

• Traditional capacity expansion has become increasingly expensive, and over time, this capacity would likely be consumed, resulting again in congested travel conditions.

• There is a value that people place on the ability to reach their destination in a reliable manner. The existing infrastructure in Metro-Atlanta does not provide a system that meets that goal in peak periods. Implementing a system of managed lanes would create the means to meet transportation consumers’

CSNHS-0009-00(156) and CSNHS-0009-00(157)PI Nos. 0009156 and 0009157Henry and Clayton Counties

Section 1Page 1-1

NOISE TECHNICAL REPORT: I-75 MANAGED LANES October 2012

demand for reliable travel time, either through paying a toll, utilizing transit services that would travel the managed lanes, or by participating in ridesharing (HOV).

The purpose of the I-75 managed lanes project is to implement a link in the Atlanta Regional MLSP, thereby providing more reliable mobility, expanding travel choices, and furthering sustainability of the transportation system within the corridor. The managed lane system would extend from the SR 155 (Zack Hinton Parkway) interchange in Henry County north to the SR 138 (Stockbridge Highway) interchange in Henry and Clayton Counties (Figure 1-1). The project would add managed lanes that would be restricted by the number of occupants per vehicle and/or by tolls.

The section of I-75 covered by the proposed project is among the Tier 1 projects in the MLSP. The tiering of projects provides a systematic implementation plan for ultimate completion of the regional system of managed lanes. Tier 1 projects include the most critical corridors to be implemented earliest in the development of the overall system.

The Atlanta Regional Commission (ARC) adopted the PLAN 2040 Regional Transportation Plan (RTP) for the 18-county Atlanta metropolitan area in July 2011. The RTP was approved by US DOT on September 6, 2011. The plan addresses current and expected travel demands on the region’s transportation system through the year 2040. The RTP is the direct result of a comprehensive, cooperative, and continuous process conducted by ARC, local governments, and GDOT in cooperation with the Federal Highway and Federal Transit Administrations.

The FY 2012-2017 Transportation Improvement Program (TIP) is developed in conformity with the RTP and the I-75 managed lanes project is included in the conforming FY 2012-2017 TIP. The project is identified by the following reference numbers: AR-ML-630 (PI Number 0009157, I-75 from SR 138 to Eagles Landing Parkway) and AR-ML-640 (PI Number 0009156, I-75 from Eagles Landing Parkway to SR 155).

The project is also consistent with the Joint Henry County/Cities Comprehensive Transportation Plan adopted in 2007.

1.2 Project Alternatives

1.2.1 Build AlternativesProject numbers CSNHS-0009-00(156) and CSNHS-0009-00(157) involve the construction of a reversible, barrier-separated, managed lane system along southbound I-75 in Henry County and Clayton County. There are currently two alternatives under consideration for the proposed project. Both alternatives would allow registered transit vehicles, emergency vehicles, military vehicles, maintenance vehicles and school buses to use the managed lanes without paying a toll. Trucks would not be permitted in the managed lane system under either alternative. Both alternatives considered for the proposed project are located within the same corridor and have an identical roadway footprint.

Alternative 1 - ETLAlternative 1 includes the construction of reversible, barrier-separated, express toll lanes (ETL) and Intelligent Transportation System (ITS) infrastructure along I-75 in Henry County and Clayton Counties. The ITS component of the project begins and ends approximately two miles on either end of the proposed express toll lanes. In Henry County, the ITS improvements begin 2.1 miles south of the I-75 bridge over SR 155 and continue north along both I-75 and I-675 into Clayton County. Along I-75, the ITS component of the project ends 2.1 miles north of the I-75 southbound off-ramp to SR 138 (Stockbridge Highway) and along I-675, it ends 2.1 miles north of SR 138. The total project length including the ITS component is 17.94 miles.

CSNHS-0009-00(156) and CSNHS-0009-00(157)PI Nos. 0009156 and 0009157Henry and Clayton Counties

Section 1Page 1-2

NOISE TECHNICAL REPORT: I-75 MANAGED LANES October 2012

CSNHS-0009-00(156) and CSNHS-0009-00(157)PI Nos. 0009156 and 0009157Henry and Clayton Counties

Section 1Page 1-3

NOISE TECHNICAL REPORT: I-75 MANAGED LANES October 2012

The ETL begin in Henry County at the I-75 bridge over SR 155 and end in Clayton County approximately 600 feet south of the I-75 southbound on-ramp from SR 138, and at SR 138 on I-675, for a total length of 12.24 miles. From SR 155 to approximately one mile south of Mt. Carmel Road, a single ETL will be constructed. The single lane will then transition to two reversible lanes, which will continue to the northern terminus of the facility, where they will diverge, providing access to the I-75 general purpose lanes and a direct single-lane connection to the median of I-675, where the lane will then connect to the I-675 general purpose lanes.

To accommodate the new lanes within the median of I-75, the southbound general purpose lanes will be shifted approximately 19 to 31 feet to the west. The new lanes will match existing asphalt and concrete sections of the corridor and provide paved inside and outside shoulders. The proposed widening will occur within existing GDOT right-of-way, and retaining walls will be constructed along southbound I-75 to minimize right-of-way impacts.

The following additional improvements are also proposed as part of the project: Replacement of existing Mt. Carmel Road bridge with a new two-lane, two-span bridge. The bridge

replacement would require partial acquisition of four parcels for right-of-way and a detour. A dedicated access ramp that will allow connection to the managed lanes from Jonesboro Road at

Foster Drive, just east of the Jonesboro interchange with I-75. The ramp will require partial acquisition of three parcels for right-of-way.

Addition of a signal and turn lanes to the intersection of Mt. Carmel Road and Jonesboro Road. Widening of the existing I-75 overpass bridge at Flippen Road to accommodate the reversible-lanes

typical section, the widening of the general-purpose lanes, and the addition of a new single span I-675 bridge over the I-75 northbound lanes to provide a dedicated connection to I-675.

Restriping of the intersection of SR 20/81 and I-75 southbound ramp to provide a continuous right-turn off the ramp.

Addition of a right-turn lane at the intersection of Industrial Boulevard and SR 20/81. Addition of right-turn lane at the intersection of Industrial Boulevard and SR 155.

Existing guardrail and overhead signs along the corridor will be removed and replaced as necessary along with construction of noise barriers as determined by noise studies.

OperationsGDOT is applying to FHWA for authority to implement tolls on the facility under the Express Lanes Demonstration Program (ELDP) established by Section 1604(b) of the Safe, Accountable, Flexible, Efficient Transportation Equity Act: A Legacy for Users (SAFETEA-LU).1 Toll rates for the lanes vary according to traffic conditions to regulate demand for the lanes and keep them congestion-free, even during peak hour periods. When traffic volume increases, tolls increase with demand. When traffic volume decreases, tolls similarly decrease.

1 The program allowed up to 15 toll projects aimed at managing congestion and financing highway capacity expansion by tolling new lanes added to an existing facility. However, ELDP expired on September 30, 2012. The five tolling agreements that were executed by FHWA and project sponsors under this program will continue in force under the Moving Ahead for Progress in the 21st Century Act (MAP-21). Projects for which slots were allocated under ELDP but still not subject to an agreement will proceed under Section 129 of MAP-21 (see FHWA September 24, 2012 Memorandum, Guidance on Section 129 General Tolling Program).CSNHS-0009-00(156) and CSNHS-0009-00(157)PI Nos. 0009156 and 0009157Henry and Clayton Counties

Section 1Page 1-4

NOISE TECHNICAL REPORT: I-75 MANAGED LANES October 2012

Fully electronic tolling allows customers to pay tolls automatically, eliminating the need for toll booths. Electronic signs display toll rates to help drivers decide whether to access the lanes. Drivers lock in their toll rate when they enter the ETL system.

The managed lanes are proposed to operate northbound in the morning peak period and southbound in the afternoon peak period. The reversible facility is expected to be closed twice a day for a total of 1 to 1.5 hours to allow for maintenance and the reversal of the direction of travel. To maximize use of the reversible lanes, analysis would be conducted to identify the specific times of day directional flow of the reversible lanes would change. Following typical operational patterns, it would be expected that the reversible lanes would likely operate in a northbound direction from very early in the morning to about mid-day. The operational flow would change to southbound and continue from mid-day to the early hours of the morning. As such, the reversible lanes would be operational all day (with the exception of the two periods each day when the direction of operation of the lanes is switched), not just during the peak periods.

During peak periods, contra-flow traffic, i.e., morning southbound traffic and evening northbound traffic, would not be able to use the proposed reversible-lane system. The contra-flow traffic would use existing highway general purpose lanes or alternate arterial roadways. Mechanical arms and/or barriers would prevent contra-flow traffic from accessing the managed lane system. These barriers would be raised and lowered manually and would be observable through real-time video cameras.

Alternative 2 – HOT 3+Alternative 2, High Occupancy Toll (HOT) lanes, includes the same lane configuration and physical footprint as the express toll lanes in Alternative 1. The ARC travel demand model 2040 was run for both alternatives. The projected total traffic volumes for both alternatives are the same. There is a small difference in projected traffic volumes between the managed lanes and general purpose lanes of each Build alternative. Alternative 1 is projected to have between 0.1% and 0.25% less traffic in the express toll lanes than the HOT lanes in Alternative 2 and therefore, 0.1-0.25% more traffic on the general purpose lanes than the general purpose lanes in Alternative 2.

The key difference between HOT lanes and ETL is the toll policy and physical operations of the toll collection due to the occupancy requirements of HOT lanes. Those vehicles that contain three or more passengers are designated as a high occupancy vehicle (HOV 3+) and are exempt from paying the toll. Single occupant vehicles and HOV-2 vehicles will be required to pay a toll. Therefore, Alternative 2 is defined as HOT 3+. The ITS component and the lanes begin and end in the same locations as Alternative 1. Because the lane configuration is the same under Alternatives 1 and 2, the additional improvements proposed for Alternative 1 are also proposed for Alternative 2. The replacement of the Mt. Carmel Road bridge over I-75 and a detour would be required.

OperationsAs described above, GDOT is applying to FHWA for authority to implement tolls on the facility under the Express Lanes Demonstration Program established by Section 1604(b) of the SAFETEA-LU (see Footnote 1). All vehicles that are designated as HOV-3 are exempt from paying a toll, as well as transit vehicles, emergency vehicles, and motorcycles. Toll rates for the single occupant vehicles and HOV-2 vehicles will vary according to traffic conditions to regulate demand for the lanes and keep them congestion-free, even during peak hour periods. When traffic volume increases, tolls increase with demand. When traffic volume decreases, tolls similarly decrease. Therefore, the daily operations are relatively similar to those described under Alternative 1.CSNHS-0009-00(156) and CSNHS-0009-00(157)PI Nos. 0009156 and 0009157Henry and Clayton Counties

Section 1Page 1-5

NOISE TECHNICAL REPORT: I-75 MANAGED LANES October 2012

Implementing a HOT system requires more complex system operations than an ETL system. The transponder mode under the ETL system is universal, except for specifically designated vehicles, such as transit vehicles, registered vanpools, and emergency vehicles. Transponder mode under the HOT system is not universal, therefore, the public education for transponder use for HOT lanes can be more complicated. The drivers must make a choice in declaring their transponder mode, i.e. switching the mode as to whether a driver is using it as an SOV or HOV. In addition, this alternative requires additional enforcement, since occupancy must be monitored to ensure that the transponder mode of individual vehicles is accurate. Violation rates are likely to be higher on an HOT system than an ETL system. There is added capital and operation and maintenance costs with HOT lanes versus ETL lanes due to additional signs and enforcement. An HOT 3+ system is already in place in the Atlanta region on I-85 north of Atlanta. The toll operations have already been established through the Peach Pass system. The toll mode is either non-toll (if in a 3+ carpool) or toll (if in a 2+carpool or driving alone). The toll mode can be changed on-line at the Peach Pass homepage or using a free application for smart phones. All changes take at least 15 minutes to process before the customer is able to use the roadway. As with Alternative 1, the tolling is fully electronic, eliminating the need for toll booths. Electronic signs display toll rates to help drivers decide whether to access the lanes. Drivers lock in their toll rate when they enter the managed lanes. Under provisions of 23 USC 166(d), annual certification must be made that operational performance monitoring programs and enforcement programs are in place to ensure that the performance of the facility is not degraded and that the facility is operated in accordance with the restrictions and requirements of 23 USC 166.

The roadway footprint would be identical for each alternative. Therefore, the findings in this report associated with the Build alternative are applicable to both alternatives.

1.2.2 No Build AlternativeThe No Build Alternative is required by the National Environmental Policy Act (NEPA) of 1969, as amended and includes all existing highways along the I-75 corridor. Under the No Build Alternative, the proposed managed lanes are not constructed and I-75 remains in its present configuration with three basic through lanes in each direction from SR 155 in Henry County to SR 138 in Clayton County plus auxiliary lanes between the I-675 interchange and Eagles Landing Parkway/Hudson Bridge Road.

CSNHS-0009-00(156) and CSNHS-0009-00(157)PI Nos. 0009156 and 0009157Henry and Clayton Counties

Section 1Page 1-6

NOISE TECHNICAL REPORT: I-75 MANAGED LANES October 2012

2. EXISTING NOISE ENVIRONMENT

The principal source of noise in the study area is vehicular traffic, including automobiles and trucks. As an existing transportation corridor, most adjacent land uses are exposed to at least moderate noise levels. This chapter presents background information on the characteristics of sound and sound levels, the criteria used by the FHWA and GDOT to measure noise impacts, and the results of noise measurements conducted in the study area at noise-sensitive sites.

2.1 Background

2.1.1 Noise FundamentalsNoise is typically defined as unwanted or undesirable sound. The basic parameters of noise that affect humans are:

(1) intensity or level,(2) frequency content, and(3) variation with time.

The first parameter is determined by the level of sound, which is expressed in units of decibels (dB). By using this scale, the range of normally encountered sound can be expressed by values between 0 and 120 dB. On a relative basis, a 3-dB change in sound level generally represents a barely perceptible change. A 5-dB positive change presents a “noticeable” change, and a 10-dB positive change is typically perceived as a doubling in the loudness while a 10-dB decrease in noise levels is perceived as a 50 percent reduction in loudness.

The frequency of noise is related to the tone or pitch of the sound and is expressed in terms of cycles per second called hertz (Hz). The human ear can detect a wide range of frequencies from about 20 Hz to 17,000 Hz. However, because the sensitivity of human hearing varies with frequency, the A-weighting system is commonly used. Sound levels measured using this weighting system are called “A-weighted” sound levels and are expressed in decibel notation as “dBA.” The A-weighted sound level is widely accepted as a proper unit for describing environmental noise.

Because environmental noise fluctuates from moment to moment, it is common practice to condense all of this information into a single number called the “equivalent” sound level (L eq). The Leq is a measure of the average sound energy during a specified period of time (typically 1 hour or 24 hours). The L eq is defined as the constant level that, over a given period of time, transmits the same amount of acoustical energy to the receiver as the actual time-varying sound. Studies have shown that L eq is well correlated with human annoyance to sound, and therefore, this descriptor is widely used for environmental noise impact assessment. The Leq measured over a 1-hour period is the hourly Leq (1-hour), which is used to analyze highway noise impacts and abatement.

2.1.2 Noise Typical Hourly Leq Sound LevelsFigure 2-1 provides examples of typical noise environments in terms of noise levels. The range of noise levels spans from 0 dBA to 130 dBA. However, noise levels are generally found to range between 55 dBA and 75 dBA in most communities. This spans the range between a typical quiet residential environment and a noisy residential environment.

CSNHS-0009-00(156) and CSNHS-0009-00(157)PI Nos. 0009156 and 0009157Henry and Clayton Counties

Section 2Page 2-1

NOISE TECHNICAL REPORT: I-75 MANAGED LANES October 2012

CSNHS-0009-00(156) and CSNHS-0009-00(157)PI Nos. 0009156 and 0009157Henry and Clayton Counties

Section 2Page 2-2

NOISE TECHNICAL REPORT: I-75 MANAGED LANES October 2012

2.1.3 Factors Affecting Traffic Noise LevelsIn urban communities, adjacent land uses are exposed to at least moderate noise levels. Traffic noise level at a site depends on both site geometry and traffic characteristics (volume, vehicle type, and speed) of proposed roadways near the site. For a straight, at-grade roadway with a steady stream of vehicles, the Leq noise level decreases with distance from the roadway. Generally, in areas where the land between the roadway and the receptor site is primarily grass, lawn, or other sound absorptive material, the noise level decreases at a rate of 4.5 dBA per a doubling of the distance. Conversely, in more urban areas with concrete, the noise level drops off at a much slower rate—typically around 3 dBA per a doubling of the distance. These drop-off rates assume vehicle travel speeds remain constant and flat open terrain occurs between the receptor and the roadway. Higher drop off rates will typically occur in areas where there is excess shielding caused by building rows or variations in the terrain.

Assuming similar vehicle mix and travel speeds, a doubling in traffic volume over a given period of time produces a doubling in the sound energy. A doubling in sound energy corresponds to a barely perceptible 3-dBA increase in noise level. At locations where traffic volumes and noise levels are already high, a large change in traffic volume is required to cause a perceptible change in the noise level.

Noise levels from trucks are much greater than noise levels from automobiles. The noise generated by a single heavy truck is as loud as 10 automobiles. Consequently, at a given constant travel speed, noise level fluxuations are more sensitive to the distance to nearby truck lanes and/or to changes in truck volumes than changes in overall traffic flow. However, travel speeds do play a factor, and on a roadway that is carrying a given volume of traffic, road-traffic noise levels increase by approximately 5 to 6 dBA as the speed increases from 30 to 45 mph, and by another 3 dBA as the speed increases to 55 mph.

2.2 FHWA Noise Prediction Methodology

The FHWA Traffic Noise Model (TNM) Version 2.5 was used to predict Leq (1-hour) traffic noise levels. The TNM model is used to obtain reasonable estimates of traffic noise at discrete locations by considering interactions between different noise sources and the effects of topographical features on altering predicted noise levels. A receiver is a discrete point modeled in the TNM program where as a receptor is a defined as a representative location of a noise sensitive area for various land uses. In areas where there is a common noise environment, one modeled TNM receiver can be considered representative of many receptors. This occurs in places like multi-family buildings where noise level estimates at one modeled TNM receiver on a given floor may be representative of noise conditions for all the receptors on that floor. For this project, 708 receivers, representing 2,343 receptors, were modeled.

The TNM model estimates the total sound energy perceived at a modeling receiver by determining the logarithmic sum of the sound energy generated from each of the adjacent roadway segments. The total noise level estimated at a given receiver is a function of the number of automobiles, medium trucks, heavy trucks and travel speed at which these vehicles are moving on each roadway segment. Moreover, roadway segments with higher number of heavy trucks generate more noise than those with lower truck percentages. In the TNM model, these factors are combined in an empirical formula governing the relationship of the reference mean noise emission level of each vehicle type as a function of travel speed. In general, roadway segments located further away contribute less to the estimated total noise level than those roadway segments closer to the receiver. In addition, the TNM model also considers attenuating effects of distance, building rows, topography, type of roadway surface, ground surface CSNHS-0009-00(156) and CSNHS-0009-00(157)PI Nos. 0009156 and 0009157Henry and Clayton Counties

Section 2Page 2-3

NOISE TECHNICAL REPORT: I-75 MANAGED LANES October 2012

conditions outside the roadway boundary, trees zones, atmospheric absorption and any existing sound barriers. Noise generated from sources other than traffic is not included in the model.

Major roadways and sensitive receivers were modeled in TNM by importing Microstation based roadway design files into ArcGIS 10 and then importing the roadway and receiver data into the TNM program. Elevations for the TNM model runs were established from Henry County’s digital elevation model in ArcGIS 10. Lastly, the number of automobiles, medium trucks, and heavy trucks and their associated travel speeds for each modeled roadway segment were input into the model. The TNM model preparation was completed and the program executed. Upon completion, noise level estimates at the receivers were provided in an output summary table. Traffic data used for the noise modeling were based on the level of service (LOS) C conditions, which generates the loudest (worst case) traffic noise condition consisting of high traffic volume and travel speeds.

2.3 Definition of Type 1 Projects

“Highway Traffic Noise Policy and Guidance,” was issued in July 2010 (revised January 2011) by the FHWA. In compliance with this guidance, a Type I project is defined below:

(1) The construction of a highway on new location; or, (2) The physical alteration of an existing highway where there is either:

(i) Substantial Horizontal Alteration. A project that halves the distance between the traffic noise source and the closest receptor between the existing condition to the future build condition; or, (ii) Substantial Vertical Alteration. A project that removes shielding therefore exposing the line-of-sight between the receptor and the traffic noise source. This is done by either altering the vertical alignment of the highway or by altering the topography between the highway traffic noise source and the receptor; or,

(3) The addition of a through-traffic lane(s). This includes the addition of a through-traffic lane that functions as a (high occupancy vehicle (HOV) lane, High-Occupancy Toll (HOT) lane, bus lane, or truck climbing lane; or,

(4) The addition of an auxiliary lane, except for when the auxiliary lane is a turn lane; or, (5) The addition or relocation of interchange lanes or ramps added to a quadrant to complete an

existing partial interchange; or, (6) restriping existing pavement for the purpose of adding a through-traffic lane or an auxiliary lane,

except for when the auxiliary lane is a turn lane; or, (7) The addition of a new or substantial alteration of a weigh station, rest stop, ride-share lot or toll

plaza.

The proposed I-75 managed lanes project would include the addition of a through-traffic lane and, therefore, would be classified as a Type I project.

2.4 FHWA Noise Criteria

NEPA provides broad authority and responsibility for evaluating and mitigating adverse environmental effects, including highway traffic noise. Implementation of NEPA requires federal government agencies use all practical means and measures to promote the general welfare and foster a healthy environment. A more important federal law that specifically involves abatement of highway traffic noise is the Federal-

CSNHS-0009-00(156) and CSNHS-0009-00(157)PI Nos. 0009156 and 0009157Henry and Clayton Counties

Section 2Page 2-4

NOISE TECHNICAL REPORT: I-75 MANAGED LANES October 2012

Aid Highway Act of 1970. This law mandates the FHWA to develop noise standards for mitigating highway traffic noise.

In response to the problems associated with highway traffic noise, the United States Code of Federal Regulations Part 772 (23 Code of Federal Regulations [CFR] 772) “Procedures for Abatement of Highway Traffic Noise and Construction Noise” establishes standards for the impact determination and abatement feasibility of highway traffic noise. The FHWA has developed regulations for the mitigation of highway traffic noise in federally aided highway projects. The regulation contains traffic noise-level criteria for various land use activities. FHWA will not approve the plans and specifications for a federally aided highway project, unless the project includes an adequate evaluation of potential noise abatement measures to comply with the standards.

The FHWA regulations contain noise abatement criteria (NAC), which if approached or exceeded on Type I roadway improvement projects require consideration for noise abatement. In addition to these absolute limits, noise impacts can occur if there is a substantial increase in future build noise levels over comparable existing noise levels. The GDOT defines a substantial noise level increase as 15 dBA or greater. The regulations do not require that the NAC be met in every instance. Rather, the regulations require noise abatement where impacts occur and abatement is determined feasible and reasonable in accordance with 23 CFR Part 772.13 and the GDOT noise policy.

Table 2-1 provides a summary of the FHWA traffic NAC for each type of land use activity category based on the noisiest hourly Leq value. The GDOT defines a noise impact as occurring when design-year build noise levels approach or exceed the NAC thresholds listed in Table 2-1 or when predicted design-year build noise levels result in a substantial noise level increase over existing noise levels. The GDOT considers approach levels as 1 dBA less than the noise levels shown in Table 2-1 and defines a substantial noise level increase as being 15 dBA or greater. For example, the approach noise level for Category B land use activities is 66 dBA. The approach noise levels for all NAC categories represent absolute noise impact thresholds, which exceeded constitutes an impact. For example, for NAC land use Category B, a noise level of 65.9 dBA at residential property is not considered an impact, but a noise level of 66.0 dBA or greater is considered a noise impact.

Table 2-1FHWA Noise Abatement Criteria (NAC)

Hourly A-Weighted Sound Level - decibels (dBA)Activity

Category Leq(h) Description of Activity Category

A 57(Exterior)

Lands on which serenity and quiet are of extraordinary significance and serve an important public need and where the preservation of those qualities is essential if the area is to continue to serve its intended purpose.

B 67(Exterior) Residential

CSNHS-0009-00(156) and CSNHS-0009-00(157)PI Nos. 0009156 and 0009157Henry and Clayton Counties

Section 2Page 2-5

NOISE TECHNICAL REPORT: I-75 MANAGED LANES October 2012

Table 2-1FHWA Noise Abatement Criteria (NAC)

Hourly A-Weighted Sound Level - decibels (dBA)Activity

Category Leq(h) Description of Activity Category

C 67(Exterior)

Active sport areas, amphitheaters, auditoriums, campgrounds, cemeteries, day care centers, hospitals, libraries, medical facilities, parks, picnic areas, places of worship, playgrounds, public meeting rooms, public or nonprofit institutional structures, radio studios, recording studios, recreation areas, Section 4(f) sites, schools, television studios, trails, and trail crossings.

D 52(Interior)

Auditoriums, day care centers, hospitals, libraries, medical facilities, places of worship, public meeting rooms, public or nonprofit institutional structures, radio studios, recording studios, schools, and television studios

E 72(Exterior)

Hotels, motels, offices, restaurants/bars, and other developed lands, properties, or activities not included in A-D or F

F -

Agriculture, airports, bus yards, emergency services, industrial, logging, maintenance facilities, manufacturing, mining, rail yards, retail facilities, shipyards, utilities (water resources, water treatment, electrical), and warehousing

G - Undeveloped lands that are not permittedSource: FHWA,23 CFR Part 772

Once the study area has been defined and land use categories determined, each property in the study is assigned an Activity Category in accordance with Table 2-1. The basis for these assignments must be included in the noise study. A detailed description of each type of land use included in each of the seven NAC Activity Categories is outlined in Section 2.5.

2.5 Assigning Activity Categories

For purposes of noise analysis modeling, study area noise receptors were assigned one of seven different land use or activity category—Activity Category A through G. These are described in the following paragraphs.

Activity Category A: This category includes exterior activities and relates to lands, as stated in 23 CFR Part 772, “on which serenity and quiet are of extraordinary significance and serve an important public need, and where the preservation of those qualities is essential for the area to continue to serve its intended purpose.” Some examples of land uses designated as Activity Category A include the Tomb of the Unknown Soldier, a monastery, and an amphitheater. There are no receivers of this activity category located within the study area.

Activity Category B: This category includes exterior activities for single-family and multi-family residences. Consistent with regulatory guidance, the TNM modeling completed for residential properties assumed the following:

CSNHS-0009-00(156) and CSNHS-0009-00(157)PI Nos. 0009156 and 0009157Henry and Clayton Counties

Section 2Page 2-6

NOISE TECHNICAL REPORT: I-75 MANAGED LANES October 2012

A single-family residence was generally considered a single TNM receiver. As previously explained in Section 2.2, a receiver is a discrete point modeled in the TNM program where as a receptor is a defined as a representative location of a noise sensitive area for any of the land uses listed in Table 2-1.

A single TNM modeling receiver can represent many equivalent receptors or dwellings. For example, each floor of a multi-family building was modeled using one TNM receiver point per floor, but each floor consisted of multiple receptors. Each residential unit of a multi-family dwelling (e.g., apartment building, condo) was considered a single receptor. Noise impacts identified at the one TNM modeling receiver point were assumed to occur at all receptors on that floor that shared a common noise environment.

It was assumed that each floor of the multi-family dwelling facing the proposed roadway improvements share a common noise environment. Therefore, one TNM receiver would be representative of future noise conditions of multiple receptors. A common noise environment consists of receptors that front the same roadway exposures.

In the case of multi-family buildings, exterior balconies of these dwellings were considered the primary noise sensitive area.

There are 534 receivers, representing 1,167 receptors, of this activity category located within the study area.

Activity Category C: This category includes exterior activities for nonresidential public and private facilities that tolerate less noise (e.g., recording studios, amphitheaters, libraries) than Activity Category E (see below). Each structure generally was considered one receptor site for discrete areas of frequent human use such as hospitals, libraries, and public meeting rooms.

For cemeteries, parks, and other expansive Category C activities, the number of required receptors shall be determined as follows: 1) determine the typical linear highway frontage of residences in the surrounding community; and 2) divide the proposed highway frontage length of the Category C site by the amount determined in step 1 above with any remainder counting as an additional receptor. One Activity Category C Receiver, Receiver 303, is a common outdoor space that represents a common shared noise environment for the guests of an RV park. Using the method outlined above, it was determined that Receiver 303 represented a total of 50 receptors.

There are three receivers, representing 52 receptors, of this activity category located within the study area.

Activity Category D: This category includes interior impacts for Activity Category C facilities that may have a noise-sensitive interior use. An indoor analysis is typically done only after exhausting all outdoor analysis options. In situations where no exterior activities would be affected by the traffic noise, or where the exterior activities are far from or physically shielded from the roadway in a manner that prevents an impact on exterior activities, Activity Category D is typically used as the basis of determining noise impacts. As a result of the detailed analysis provided later in this document, it was determined that there are no receivers of this activity category associated with this project.

Activity Category E: This category includes exterior activities for certain commercial and developed lands (e.g., restaurants, offices, and hotels) that are less sensitive to highway noise. Each structure generally was considered one receptor for the purpose of disclosure. For receptors in this category that CSNHS-0009-00(156) and CSNHS-0009-00(157)PI Nos. 0009156 and 0009157Henry and Clayton Counties

Section 2Page 2-7

NOISE TECHNICAL REPORT: I-75 MANAGED LANES October 2012

contain lodging units (e.g., hotels), each room where sleep occurs that has a balcony or ground-level patio was considered one receptor. Multiple receivers for each floor were placed around the hotels to accurately assess noise levels as the receiver distance from the roadway varied. It was assumed each hotel room on each floor of the hotel shares a common noise environment. In the case of hotels or motels, exterior balconies of rented rooms were considered the primary noise sensitive area. There are 116 receivers, representing 1,069 receptors, of this activity category located within the study area.

Activity Category F: This category includes land use activities that are generally not sensitive to highway noise. No noise analysis is required for this activity category. There are 55 receivers, representing 55 receptors, of this activity category located within the study area.

Activity Category G: This category addresses future noise levels on undeveloped lands without a building permit and undeveloped lands with a building permit. For permitted, undeveloped land, the site would be evaluated based on the Activity Category that is consistent with the permitted land. A review of available on-line Geographic Information System (GIS) databases provided by the Clayton and Henry County Planning and Zoning Departments was undertaken to identify any parcels within the corridor that are currently vacant/undeveloped but permitted for future development. The review of GIS databases confirmed that no permitted developments are located along the project corridor’s vacant/undeveloped parcels. Additionally, coordination with the Henry County Environmental Compliance and Plan Review Office confirmed that no parcels within the corridor are permitted for future development. Therefore, none of the receivers analyzed for this assessment represent vacant/undeveloped parcels that are permitted for development.

For undeveloped lands without a building permit, noise contours were developed on vacant lands using the TNM. In accordance with 23 CFR Part 772 (772.17) and as outlined in the GDOT Noise Abatement Policy, information is to be provided to local officials “that can help them to be aware of incompatible land uses near state highways.” Large undeveloped lands without permitted/anticipated future development along the project corridor were modeled at 50-foot intervals from the nearest edge of pavement.

Seven large undeveloped sites (Study Area A through Study Area G) where noise conditions are anticipated to change were identified along the corridor. The detailed results of this analysis are provided in Section 3.3.2 (Projected Sound Levels for Undeveloped Land Without a Permit) of this document.

2.6 Existing Noise Measurements

Existing noise levels within the study area were assessed based on noise measurements taken at noise sensitive sites during October 2012. These noise measurements were used to validate the noise prediction model.

2.6.1 Existing Measurement Location, Methodology and ResultsField measurements were collected on October 10, 2012 from five locations within the study area. These noise monitoring sites are scattered along the entire length of the project corridor and are depicted on Figures D, I, J, O, and P (see Attachment 1). Noise measurement sites included residential dwellings, a church, and hotels. They were considered representative of typical land uses within the

CSNHS-0009-00(156) and CSNHS-0009-00(157)PI Nos. 0009156 and 0009157Henry and Clayton Counties

Section 2Page 2-8

NOISE TECHNICAL REPORT: I-75 MANAGED LANES October 2012

study area and were selected based on a review of the proposed transportation improvements. Copies of the field measurement data sheets are provided in Attachment 2.

Noise measurements for each site were performed in accordance with procedures described in Measurement of Highway-Related Noise (FHWA, 1996). The measurements were recorded using a laboratory calibrated Bruel & Kjaer Model 2238 sound level meter. All measurements were performed under acceptable weather and street surface conditions consistent with GDOT policy guidelines. These measurements were taken for 15 minutes at each location. Field measurements indicate existing noise levels between 55.9 and 68.9 dBA. The locations of field measurements and the observed sound levels are provided in Table 2-2.

Table 2-2Existing Field Measurements and TNM Results (dBA Leq)

Field Receiver Location Figure Location

Field Measurement TNM Calculation Difference

Receiver 89 (Single family residence) D 68.9 68.8 0.1Receiver 300 (Single family residence) I 63.1 65.3 2.2Receiver 304 (Church) J 68.0 65.3 2.7Receiver 460 (Hotel) O 67.6 70.5 2.9Receiver 482 (Hotel) P 55.9 58.9 3.0

2.6.2 Model ValidationField measurements were compared with TNM-modeled noise levels to confirm the applicability of the model for this analysis. Traffic counts were taken along the project corridor during each field measurement using video recording. Total traffic counts were then gathered from the video and input to TNM to validate the model. The comparisons of field measurements to modeled levels are shown in Table 2-2. The TNM modeled results for the field measurements indicated existing noise levels between 58.9 and 70.5 dBA.

A difference of approximately three decibels is generally considered acceptable. Because each of the field measurements were within the accepted three-decibel range of the model, the modeled results are considered applicable for use in analysis of noise levels within the study area. Therefore, existing noise levels for the receivers within the study area were calculated with TNM for comparison with the build and no build alternatives.

2.7 Existing Sound Levels

Validation results indicate that TNM is appropriate for use in determining existing traffic-related sound levels at the 708 receivers (representing 2,343 receptors) located within the project corridor. As previously noted, major roadways and sensitive receivers were modeled in TNM by importing Microstation based roadway design files into ArcGIS 10 and then importing the roadway and receiver data into the TNM program. Terrain lines, building rows, and existing noise walls were also input into the TNM program using this same method. Figures provided in Attachment 1 show the locations of the receivers relative to the project study area. Elevations for the TNM model runs were established from Henry County’s digital elevation model in ArcGIS 10.

CSNHS-0009-00(156) and CSNHS-0009-00(157)PI Nos. 0009156 and 0009157Henry and Clayton Counties

Section 2Page 2-9

NOISE TECHNICAL REPORT: I-75 MANAGED LANES October 2012

Lastly, the number of automobiles, medium trucks, and heavy trucks and their associated travel speeds for each modeled roadway segment were input into the model. Traffic data used for the noise modeling of I-75 were based on the LOS C conditions, which generates the loudest (worst case) traffic noise condition consisting of high traffic volume and travel speeds. There is no standard for LOS C traffic volumes for intersections; therefore, peak hour traffic data was input into the model at these locations. Truck percentages (%) were based on a traffic study of the project corridor provided by Parsons Transportation Group. As a result, existing truck percentages of 9% (3% medium truck, 6% heavy truck) were used for the project area. The distribution of this truck percentage for medium and heavy trucks was based on field reconnaissance of the project corridor.

Upon completion, existing noise level estimates at the receivers were compiled in an output summary table. This summary table is provided in Attachment 3. According to the TNM analysis of existing conditions, existing traffic-related sound levels within the project study area are between 55.5 dBA and 75.2 dBA.

Copies of the input and output files from the TNM modeling associated with this analysis are provided in Attachment 4 of this document. Attachments 5 and 6 provide background data associated with the study area and traffic, respectively.

CSNHS-0009-00(156) and CSNHS-0009-00(157)PI Nos. 0009156 and 0009157Henry and Clayton Counties

Section 2Page 2-

10

NOISE TECHNICAL REPORT: I-75 MANAGED LANES October 2012

3. NOISE IMPACT ASSESSMENT

This chapter presents the results of the assessment that was conducted to determine potential noise impacts of the build alternatives. As previously noted, because the roadway footprint would be identical for each alternative, the findings in this report associated with the build alternative are applicable to both alternatives.

3.1 FHWA Noise Impact Assessment Methodology

The proposed project involves construction of new travel lanes on an existing highway, and therefore would be classified as a Type I project under the FHWA regulations. For Type I projects, the consideration of noise impact and potential mitigation is mandatory during the project development process.

The traffic noise impacts were assessed in accordance with FHWA procedures published in 23 CFR Part 772. The GDOT uses FHWA procedures for impact assessment and abatement analysis. These procedures involve performing the following steps:

Identify existing land uses and activities, developed lands, and undeveloped lands which could be affected by traffic-related noise. This effort is discussed in greater detail in Section 2.5 of this report, while the sound level results table provided in Attachment 3 provides information specific to land use for each of the 708 receivers.

Determine existing year measured noise levels and modeled noise levels. This effort is discussed in greater detail in Section 2.6 and Section 2.7 of this report.

Predict future noise levels, which would occur for the No Build Alternative. Predict future noise levels for the Build Alternative. Compare future noise levels for the Build Alternative with existing noise levels to determine if a

substantial increase of 15 dBA or greater occurs at any noise sensitive site. Compare future noise levels for the Build Alternative against the FHWA NAC to identify the

properties where noise levels are predicted to approach or exceed the NAC impact thresholds for each Activity Category.

In accordance with the GDOT traffic noise policy requirements identify properties where noise abatement consideration is warranted.

Evaluate the feasibility and reasonableness of sound barrier effectiveness to reduce or eliminate traffic noise impacts. The abatement provisions of 23 CFR Part 772 limit mitigation measures under consideration to those listed in Section 4 of this report.

The methodology for predicting future noise levels used the FHWA TNM® Version 2.5. The TNM model incorporates sound emission and sound propagation algorithms for each vehicle type category that are based on well-established theory and accepted international standards. In general, sound propagation beyond the travel lanes takes place over acoustically “soft” ground conditions, such as a lawn or other types of vegetation surfaces. This type of ground surface was assumed throughout the study area. The model also addresses ground terrain physical features, roadway geometry, receptor distance, vehicle volumes, and vehicle operating speeds.

CSNHS-0009-00(156) and CSNHS-0009-00(157)PI Nos. 0009156 and 0009157Henry and Clayton Counties

Section 3Page 3-1

NOISE TECHNICAL REPORT: I-75 MANAGED LANES October 2012

As previously noted, major roadways and sensitive receivers were modeled in TNM by importing Microstation based roadway design files into ArcGIS 10 and then importing the roadway and receiver data into the TNM program. Figures provided in Attachment 1 show the locations of these receivers relative to the project study area. Each travel lane within the project corridor was modeled as an individual roadway. Inside and outside shoulders were also individually modeled as roadways with no traffic. Elevations for the TNM model runs were established from Henry County’s digital elevation model in ArcGIS 10. Lastly, the number of automobiles, medium trucks, and heavy trucks and their associated travel speeds for each modeled roadway segment were input into the model. Traffic data used for the noise modeling of I-75 were based on the LOS C conditions, which generates the loudest (worst case) traffic noise condition consisting of high traffic volume and travel speeds. There is no standard for LOS C traffic volumes for intersections; therefore, peak hour traffic data was input into the model at these locations. Truck percentages (%) were based on a traffic study provided by Parsons Transportation Group. As a result, future condition truck percentages were modeled at 10% (3% medium truck, 7% heavy truck).

At three locations within the corridor, two TNM modeling runs were prepared for the same location. These two runs were prepared to account for variation in the AM and PM peak traffic operations in close proximity to adjacent receivers. For example, at the proposed interchange of the project with I-675 and I-75, the managed lane would contain a split that provides access to the northbound or southbound general purpose lanes, depending on the time of day. LOS C traffic was placed on the northbound ramp to reflect AM peak operating conditions to accurately reflect the sound levels at this location. Conversely, LOS C traffic was placed on the travel lanes of the southbound ramp to reflect travel conditions during the PM peak. At locations that would be affected by these conditions, the higher of the two noise results (the “worst case” condition) was presented as the build alternative result. Similar modeling was employed at the project’s access rampage to Jonesboro Road and at the southern terminus where vehicles access/exit the managed lane system.

Four noise walls currently exist along the project corridor. Three of these noise walls would remain under the build alternative. One of the walls that would remain is located along the west side of I-75 just south of the Walt Stephens Road overpass. The other two walls are located directly across from each other, just north of the Eagles Landing Parkway/Hudson Bridge interchange. All existing walls are shown on Figures A through P in Attachment 1.

All four existing walls were included in the TNM models to evaluate their effectiveness; however, the existing noise wall located north of Walt Stephens Road on the west side of I-75 would be removed to provide adequate space for the managed lanes. Therefore, this noise wall was removed from the modeling associated with the build alternative. Noise wall #2 is proposed to replace this noise wall. A detailed analysis on noise wall #2 is provided in Section 4 (Noise Abatement) of this document.

Three of the existing noise walls were constructed as abatement measures for previously completed GDOT projects. The fourth wall, located along the east side of I-75 just north of the Eagles Landing Parkway/Hudson Bridge interchange, was constructed by a private developer. As shown later in Section 4 of this document, this wall does not provide sufficient abatement to the receivers located behind it. Noise wall #6 is proposed to provide abatement to these receivers.

Additionally, GDOT Project PI 0010126, which consists of the addition of a northbound auxiliary lane between Eagles Landing Parkway/Hudson Bridge and Walt Stephens Road, is scheduled to be completed CSNHS-0009-00(156) and CSNHS-0009-00(157)PI Nos. 0009156 and 0009157Henry and Clayton Counties

Section 3Page 3-2

NOISE TECHNICAL REPORT: I-75 MANAGED LANES October 2012

by April 2013. Noise modeling for this project has resulted in construction of a noise wall located along the east side of I-75 at Flippen Road. Because this noise wall is currently under construction, the dimensions of this wall have been included as an existing noise wall in both the build and no build TNM modeling.

3 .2 Noise Impact Assessment

The FHWA regulations identify NAC levels at which noise impact occurs and abatement must be considered for feasibility and reasonableness. Under these regulations, the proposed project would result in noise impacts if the future noise levels approach or exceed the NAC thresholds for the appropriate Activity Category (A, B, C, D, and E as described in Table 2-1).

Furthermore, FHWA regulations indicate that, “noise impacts occur when the predicted traffic noise levels approach or exceed the NAC levels, or when the predicted design year traffic noise levels substantially exceed the existing noise levels.” As such, substantial noise level increases (15 dBA or more) constitute noise impacts of equal weight as those impacts identified from NAC exceedances. For example, a residential property with existing peak-hour noise levels of 50 dBA projected to increase by 15 dBA is considered impacted, even though the absolute predicted build noise level of 65 dBA is below 66 dBA NAC.

At locations where noise impacts were identified, GDOT traffic noise policy guidelines were used to evaluate and determine the feasibility and reasonableness of noise mitigation measures. The noise abatement findings are contained in Section 4 of this report.

3.3 Noise Analysis Findings

3.3.1 Analysis Results By Receptor LocationThe future traffic-related sound levels at each of the 708 receivers are provided in the sound level results table in Attachment 3. Copies of the input and output files from the TNM modeling associated with this analysis are provided in Attachment 4 of this document. Attachments 5 and 6 provide background data associated with the study area and traffic, respectively.

The predicted no build noise levels in the project corridor would range from 55.9 to 75.4 dBA. The predicted build noise levels along the proposed project corridor would range from 55.3 to 75.5 dBA. It should be noted that traffic-related sound levels in the no build alternative would be higher than the build alternative at some receiver locations. The managed lanes would be constructed along the existing southbound travel lanes in some locations and along the existing northbound travel lanes at others. Therefore, the proposed project would move some traffic away from receiver locations in the build alternative which would result in decreased noise levels.

There are 237 receivers, representing 606 receptors, along the project corridor predicted to be impacted in the build alternative based on the NAC established by 23 CFR Part 772. The receivers that would experience such impacts are identified in the sound level results table in Attachment 3 as well as highlighted in yellow in Figures A through P (see Attachment 1). Table 3-1 summarizes the impacts according to their corresponding NAC by activity category.

CSNHS-0009-00(156) and CSNHS-0009-00(157)PI Nos. 0009156 and 0009157Henry and Clayton Counties

Section 3Page 3-3

NOISE TECHNICAL REPORT: I-75 MANAGED LANES October 2012

TABLE 3-1SUMMARY OF RECEIVER IMPACTS BY NAC

NAC/Threshold Existing Build No BuildA - 57 0 0 0B - 67 182 221 180C - 67 0 2 1D - 52 0 0 0E - 72 9 14 12

No receiver/receptor sites along the project corridor would experience noise level increases of greater than 15 dBA under either alternative. Therefore, no receivers/receptors are considered impacted based on the substantial increase criterion.

3.3.2 Projected Sound Levels for Undeveloped Land Without a PermitIn accordance with 23 CFR Part 772 (772.17) and as outlined in the GDOT Noise Abatement Policy (July 2011), information is to be provided to local officials “that can help them to be aware of incompatible land uses near state highways.” At a minimum, this information is to include “an estimation of future design year noise levels at various distances from the edge of the nearest travel lane of the proposed project where future noise levels are within one decibel of the corresponding exterior values shown in [Table 2-1].”

The data provided in Table 3-2 provides information to aid local officials with jurisdiction over properties in proximity to the project. Large undeveloped lands without permitted/anticipated future development along the project corridor were modeled at 50-foot intervals from the nearest edge of pavement. Sites were selected for this analysis at each location along the corridor where noise conditions are anticipated to change.

As previously noted, for the purposes of this project, seven locations (Study Area A through Study Area G) were identified for this analysis. The locations of these study areas relative to the proposed projects are provided in Figures A through P (see Attachment 1). The study areas depicted on the graphics represent large sample areas.

Study Area A covers vacant parcels located along I-75 from the project begin point at SR 138 south to the I-675 south merge with I-75.

Study Area B covers vacant parcels along I-75 from the I-675 merge with I-75 south to Flippen Road.

Study Area C covers vacant parcels from Flippen Road south to the Eagles Landing Parkway/Hudson Bridge interchange.

Study Area D covers vacant parcels from the Eagles Landing Parkway/Hudson Bridge interchange south to the Jodeco Road interchange.

Study Area E covers vacant parcels from the Jodeco Road interchange south to the managed lanes merge with the general purpose lanes just south of Mt. Carmel Road.

Study Area F covers vacant parcels from this merge south to the SR 20/SR 81 interchange. Study Area G covers vacant parcels from the SR 20/SR 81 interchange south to the project

terminus at SR 155.

CSNHS-0009-00(156) and CSNHS-0009-00(157)PI Nos. 0009156 and 0009157Henry and Clayton Counties

Section 3Page 3-4

NOISE TECHNICAL REPORT: I-75 MANAGED LANES October 2012

Local officials with jurisdiction over the development of parcels along the project corridor are encouraged to consider the information provided in Table 3-2 when considering future land use and development changes. The information is provided by GDOT to discourage development that would be incompatible with the sound levels that are anticipated along the project corridor at these locations.

Table 3-2Projected Sound Levels to Aid Local Officials

Study Area

Distance From Edge

Of Pavement

Projected dBA Study AreaDistance From

Edge Of Pavement

Projected dBA

STUDY AREA A

50 Feet 69.9

STUDY AREA B

50 Feet 83.3100 Feet 67.4 100 Feet 79.2150 Feet 65.9 150 Feet 756200 Feet 65.3 200 Feet 72.1250 Feet 64.7 250 Feet 69.9300 Feet 64.3 300 Feet 68.6350 Feet 63.6 350 Feet 67.3400 Feet 63.0 400 Feet 66.1450 Feet 62.2 450 Feet 65.4500 Feet 61.6 500 Feet 64.5550 Feet 60.9 550 Feet 63.7600 Feet 60.7 600 Feet 63.0650 Feet 60.1 650 Feet 63.3700 Feet 59.7 700 Feet 63.3750 Feet 59.0 750 Feet 63.3800 Feet 58.5 800 Feet 63.2

STUDY AREA C

50 Feet 78.5

STUDY AREA D

50 Feet 81.4100 Feet 75.2 100 Feet 77.9150 Feet 73.1 150 Feet 75.1200 Feet 71.6 200 Feet 73.1250 Feet 70.3 250 Feet 71.3300 Feet 68.9 300 Feet 69.8350 Feet 67.7 350 Feet 68.8400 Feet 66.6 400 Feet 67.9450 Feet 65.5 450 Feet 67.2500 Feet 64.5 500 Feet 66.3550 Feet 63.6 550 Feet 65.4600 Feet 62.7 600 Feet 64.4650 Feet 61.9 650 Feet 63.8700 Feet 61.4 700 Feet 63.0750 Feet 60.8 750 Feet 62.5800 Feet 60.3 800 Feet 61.8

CSNHS-0009-00(156) and CSNHS-0009-00(157)PI Nos. 0009156 and 0009157Henry and Clayton Counties

Section 3Page 3-5

NOISE TECHNICAL REPORT: I-75 MANAGED LANES October 2012

STUDY AREA E

50 Feet 82.2

STUDY AREA F

50 Feet 85.3100 Feet 79.1 100 Feet 80.0150 Feet 77.4 150 Feet 77.8200 Feet 75.5 200 Feet 75.9250 Feet 74.1 250 Feet 73.9300 Feet 72.7 300 Feet 72.5350 Feet 71.6 350 Feet 71.1400 Feet 70.4 400 Feet 70.2450 Feet 69.4 450 Feet 69.4500 Feet 68.5 500 Feet 68.7550 Feet 67.6 550 Feet 68.0600 Feet 66.9 600 Feet 67.5650 Feet 66.2 650 Feet 66.8700 Feet 65.4 700 Feet 66.2750 Feet 64.9 750 Feet 65.7800 Feet 64.2 800 Feet 65.2

STUDY AREA G

50 Feet 79.9100 Feet 76.8150 Feet 74.5200 Feet 72.6250 Feet 71.1300 Feet 69.8350 Feet 68.8400 Feet 67.6450 Feet 66.8500 Feet 65.8550 Feet 65.0600 Feet 64.4650 Feet 63.3700 Feet 62.6750 Feet 62.1800 Feet 61.7

CSNHS-0009-00(156) and CSNHS-0009-00(157)PI Nos. 0009156 and 0009157Henry and Clayton Counties

Section 3Page 3-6

NOISE TECHNICAL REPORT: I-75 MANAGED LANES October 2012

4. NOISE ABATEMENT

Based on the analysis in the previous section and in accordance with GDOT and FHWA Noise Policy, it is anticipated that construction of the proposed project would result in traffic-related noise impacts to 237 receivers, representing 606 receptors, all predicted to be impacted based on the NAC established by 23 CFR Part 772. Therefore, in accordance with 23 CFR Part 772, noise abatement measures must be considered for reducing or eliminating noise impacts to the impacted receiver locations. The following narrative details the abatement options considered.

4.1 Land Use and Zoning

One noise abatement measure is the application of land use controls to minimize impacts to future development. In particular, land use controls can be used to create buffer zones. Although GDOT is typically not able to acquire land to create buffer zones, it is sometimes possible to relocate an impacted property outside of the potential noise impact zone. This approach is sometimes applied to mobile home parks where relocation of the homes to a location outside the impact zone is possible. Typically, this approach would be made in consultation with the owner of the mobile home. However, none of the receivers to be impacted are of the type that such relocation is practical. Therefore, such action is not appropriate for consideration for this project.

4.2 Traffic Management

Traffic management techniques such as the restriction of truck traffic, use by only certain types of vehicles, restricting use to certain times of the day, traffic calming devices, and reduction in operating speeds were considered for noise abatement measures to the impacted receivers. Given that the noise source is I-75, traffic control devices and prohibition of certain types of vehicles would not be consistent with the interstate system’s intended purpose.

4.3 Alignment Alterations

A change in alignment was considered to reduce noise impacts. Based on the level of development along I-75, an alignment shift to reduce impacts to these receivers would likely result in additional impacts to other receivers. In addition, a shift significant enough to achieve a required reduction level in noise impacts could result in displacements. The proposed alignment utilizes the existing ROW along the inside shoulder of I-75 in order to avoid displacements necessary to construct the improvements. Therefore, a shift in alignment is not considered a reasonable noise abatement measure.

4.4 Structural Barriers

The use of structural barriers (freestanding walls) was considered for impacted receivers. The optimum situation for the use of freestanding noise wall exists when a dense concentration of impacted sites is located directly adjacent to (and parallel with) the highway right-of-way. In these instances, one wall can protect many residences at a relatively low cost per impacted site. Guidelines adopted by GDOT to ensure that the maximum number of persons benefit from each dollar spent on noise abatement limit the cost of noise walls to $55,000 per benefited receptor based on a $20 per square foot construction cost. A benefited receptor is defined as the recipient of an abatement measure that receives a noise

CSNHS-0009-00(156) and CSNHS-0009-00(157)PI Nos. 0009156 and 0009157Henry and Clayton Counties

Section 4Page 4-1

NOISE TECHNICAL REPORT: I-75 MANAGED LANES October 2012

reduction at or above the minimum threshold of 5 dBA. Where cost per unit for an effective noise wall (one that would reduce noise levels by at least seven decibels) would exceed this amount, the wall is not considered a reasonable use of public funds and no abatement is proposed.

For impacted receiver 690, driveway access to SR 155 would reduce barrier effectiveness. Noise walls are not considered reasonable for receptors where driveway access must be maintained. Therefore, a noise wall would not be a feasible abatement measure at this location.

A study for the remaining impacted receivers based on the standard evaluation criteria for feasibility and reasonableness described in GDOT Noise Policy has been completed. The results of this study are provided below.

FeasibilityThe first step for evaluating the benefit of a noise wall is feasibility. The criteria below are considered for each noise abatement measure to evaluate feasibility:

1. Noise reduction: a calculated noise reduction of at least 5 dBA must be achievable for a minimum of one impacted receptor. Each noise receptor which receives a 5 dBA reduction (whether classified as impacted or not) is considered to be a benefited receptor,

2. Constructability: a noise abatement measure must be able to be constructed using reliable and common engineering practices,

3. Safety and maintainability: an exterior noise abatement measure should conform to the AASHTO Green Book and Roadside Design Guide and should be accessible to maintenance personnel and not prevent access to other highway appurtenances (e.g., drainage structures). The maximum barrier height that can feasibly be maintained is 30 feet, and

4. Access: an abatement measure must allow sufficient access to adjacent properties.

Table 4-1 includes information related to wall design, the location of impacted receivers protected by the wall, and a feasibility determination. Each noise wall location would achieve a noise reduction of at least 5 dBA for a minimum of one impacted receptor. No walls would exceed the maximum barrier height of 30 feet, and the walls could be constructed using reliable and common engineering practices.

Table 4-1Noise Wall Design

Wall Identification

Figure Location Impacted Receivers

Wall Length (feet)

Wall Height (feet)

Decibel Reduction

(Maximum)Feasible?

1 B 13,17,18,594-598,600,603-610,665,696 3,204 18 to 30 9.5 Yes

2 D 31-34,45-68,71-105,109,137 5,010 18 to 28 11.9 Yes

3 D 125-132,134 1,392 30 6.9 Yes

4 E 180-185,187,188,207 2,069 12 to 28 9.6 Yes

CSNHS-0009-00(156) and CSNHS-0009-00(157)PI Nos. 0009156 and 0009157Henry and Clayton Counties

Section 4Page 4-2

NOISE TECHNICAL REPORT: I-75 MANAGED LANES October 2012

Wall Identification

Figure Location Impacted Receivers

Wall Length (feet)

Wall Height (feet)

Decibel Reduction

(Maximum)Feasible?

5 F 616,634-636,638-640 1,783 18 to 30 7.0 Yes

6 I, J 283-288,292-302,499-509,536-561,571-581 4,198 16 to 28 9.2 Yes

7 J 303 1,451 12 to 18 7.0 Yes

8 K 320-332,334,584-587 1,423 22 to 28 10.6 Yes

9 L 361,362,372-375,588-593 1,795 16 to 20 7.2 Yes

10 N384-386,395-398,

400-402,414-417,424,425,649-654

2,193 20 to 30 13.5 Yes

11 N 457,660,661,697,698,700,702,704,706,708 1,003 20 to 30 7.8 Yes

ReasonablenessA reasonableness study is performed for any noise abatement measure considered to be feasible. Based on the feasibility criteria above, eleven noise walls should be assessed for reasonableness using the criteria below. The first two must be satisfied before contacting property owners and residents.

1. Noise reduction: at least one benefited receptor must receive a minimum noise level reduction of 7 dBA – i.e., the noise reduction design goal,

2. Cost effectiveness: using a $20 per square foot cost for the required noise wall, the total cost must not exceed a $55,000 average allowance per benefited receptor, and

3. Property owners and residents: the decision to provide abatement will be made in collaboration with the property owner and tenants of a benefited receptor. The outreach strategy will be customized for maximum effectiveness on each project. The minimum outreach method shall be a certified letter survey provided to both property owners and tenants whose facility or home is identified as a benefited receptor. A noise wall will only be constructed if at a minimum 50% plus one of the respondents vote in favor of noise abatement. Both property owners and dwellers get a vote and their vote must be returned within 30 days to receive consideration. Property owners will receive one vote per unit owned and an additional vote if they reside in the unit, and tenants will receive one vote for the benefited unit they occupy. For some projects, individual meetings, community meetings or other outreach efforts may also be utilized to determine a majority consensus.

The final abatement measures cannot be determined until the design plans have sufficiently progressed to a point where the wall analysis can be conducted; after which, the outreach above can be completed. GDOT will strive for a decision on abatement as soon as possible after this information is available, but no later than the final environmental document that is required for construction authorization.

CSNHS-0009-00(156) and CSNHS-0009-00(157)PI Nos. 0009156 and 0009157Henry and Clayton Counties

Section 4Page 4-3

NOISE TECHNICAL REPORT: I-75 MANAGED LANES October 2012

As shown previously in Table 4-1, a total of 10 wall locations would achieve a noise reduction goal of at least 7 dBA for a minimum of one receptor. The noise reduction goal was not satisfied for any receptor protected by wall #3. The required access break associated with the Walt Stephens Bridge over I-75 limits extending the wall further south. In attempting to attain a 7 dBA reduction, the maximum wall height allowed by GDOT Noise Policy was used (30 feet). Finally, extending wall #3 further north than the current length would increase the overall wall cost (currently $835,348), which with the current design significantly exceeds the reasonable cost ($330,000). Therefore, 10 proposed noise wall locations would satisfy the noise reduction criterion for reasonableness.

The second criterion for reasonableness is cost effectiveness. The following formula is used to calculate the reasonable cost to each receptor:

Reasonable Cost = A x $55,000.00.

Variable A is the number of benefited receptors receiving a minimum 5 dBA reduction. A construction cost of $20.00 per square foot of barrier wall was used to estimate construction cost. The reasonable cost is compared to the estimated construction cost of the noise wall. If the cost of the construction of the wall exceeds the reasonable cost, then the wall is not considered cost effective. Table 4-2 compares the reasonableness cost to the construction cost of barriers for each location.

Table 4-2Cost Effectiveness Summary

Wall Identification

Number of Benefited Receptors

Reasonable Cost Construction Cost Reasonable?

1 155 $8,525,000 $1,801,634 Yes2 77 $4,235,000 $2,442,256 Yes3 6 $330,000 $835,348 No4 10 $550,000 $948,823 No5 48 $2,640,000 $976,669 Yes6 71 $3,905,000 $1,860,954 Yes7 50 $2,750,000 $486,621 Yes8 15 $825,000 $715,467 Yes9 16 $880,000 $700,137 Yes

10 74 $4,070,000 $1,214,082 Yes11 166 $9,130,000 $526,507 Yes

Nine noise walls would be reasonable and feasible to construct under each alternative. The locations of the nine reasonable and feasible walls are shown on Figures A through P (See Attachment 1).

CSNHS-0009-00(156) and CSNHS-0009-00(157)PI Nos. 0009156 and 0009157Henry and Clayton Counties

Section 4Page 4-4

NOISE TECHNICAL REPORT: I-75 MANAGED LANES October 2012

5. CONSTRUCTION NOISE

GDOT recognizes that minimizing construction noise is important; however, in the absence of standardized federal criteria for assessing construction noise impacts related to transportation projects (FHWA Construction Noise Handbook, 2006), it is necessary to primarily rely on the standards and requirements developed by local governments to determine the criteria to which contractors must adhere.

In Georgia, contractors on all highway construction projects are required to adhere to GDOT Standard Specification Section 107.01 – Laws to Be Observed, which states in part, “The Contractor shall at all times observe and comply with all such laws, ordinances, codes, regulations, orders and decrees…” unless the necessary variance is obtained. Additionally, night time construction is proposed for the proposed project. All construction activities would adhere to Special Provision 150.11.

In order to further minimize construction noise, GDOT’s Office of Environmental Services will give the Project Manager and the design team the noise sensitive receptor information as early as possible during project development. This information would be used for the incorporation of construction noise control strategies in the project layout and design. For example, haul roads could be relocated to areas that would minimize construction vehicle noise exposure to noise sensitive receivers. The sequencing of construction activities and techniques could also be developed to minimize construction noise impacts. For example, permanent noise barriers included in project design could be constructed as early as possible, and daytime (or specified) hours could be required for certain activities.

CSNHS-0009-00(156) and CSNHS-0009-00(157)PI Nos. 0009156 and 0009157Henry and Clayton Counties

Section 5Page 5-1

NOISE TECHNICAL REPORT: I-75 MANAGED LANES October 2012

6. CONCLUSION/STATEMENT OF LIKELIHOOD

As previously noted, four noise walls currently exist along the project corridor. Three of these noise walls would remain under the build alternative. One of the walls that would remain is located along the western side of I-75 just south of the Walt Stephens Road. The other two walls are located directly across from each other just north of the Eagles Landing Parkway/Hudson Bridge interchange. The existing noise wall located north of Walt Stephens Road on the west side of I-75 would be removed to provide adequate space for the managed lanes; therefore, this noise wall was removed from the build condition. Noise wall #2 is proposed to replace this noise wall.

Based on the studies completed to date using preliminary design criteria, 237 impacted receivers, representing 606 receptors, have been identified in build alternative. All impacts would be due to exceeding the NAC. Existing noise levels along the project range from 55.5 to 75.2 dBA. The predicted build noise levels along the proposed project would range from 55.3 to 75.5 dBA. The predicted no build noise levels in the area would range from 55.9 to 75.4 dBA.

Noise abatement for the impacted receiver sites was considered. Based on the results of the abatement analysis, noise walls would be considered a feasible and reasonable abatement measure. The locations of these walls are described as follows:

Proposed noise wall #1 would be constructed in the northwest quadrant of the I-75 and I-675 merge. The wall would follow the existing tree line and the location would range between 14 and 44 feet from the existing edge of pavement. The wall would be approximately 3,204 feet in length,

Proposed noise wall #2 would begin at the Walt Stephens Road overpass and extend north along the western side of I-75 for approximately 5,010 feet. The wall placement would range between 20 and 53 feet from the edge of pavement,

Proposed noise wall #5 would begin approximately 2,100 feet north of the Eagles Landing Parkway/Hudson Bridge Road overpass and continue north along the eastern side of I-75 for approximately 1,783 feet. The wall placement would range between 22 and 35 feet from the edge of pavement,

Proposed noise wall #6 would begin approximately 4,450 feet south of the Jodeco Road overpass and extend north along the eastern side of I-75 and up the I-75 Northbound off-ramp to Jodeco Road for a total length of approximately 4,198 feet. The wall placement would range between 12 and 57 feet from the edge of pavement,

Proposed noise wall #7 would begin approximately 1,630 feet south of the Jodeco Road overpass and extend south along the western side of I-75 for approximately 1,451 feet. The wall placement would range between 8 and 12 feet from the edge of pavement,

Proposed noise wall #8 would begin approximately 60 feet north of the Mt. Carmel Road overpass and continue north along the western side of I-75 for approximately 1,423 feet. The wall placement would be approximately 8 feet from the edge of pavement.

Proposed noise wall #9 would begin approximately 540 feet south of the Mt. Carmel Road overpass and continue south along the western side of I-75 for approximately 1,795 feet. The wall placement would range between 6 and 15 feet from the edge of pavement.

CSNHS-0009-00(156) and CSNHS-0009-00(157)PI Nos. 0009156 and 0009157Henry and Clayton Counties

Section 6Page 6-1

NOISE TECHNICAL REPORT: I-75 MANAGED LANES October 2012

Proposed noise wall #10 would begin approximately 2,250 feet north of the SR 20 overpass and continue north along the eastern side of I-75 for approximately 2,193 feet. The wall placement would range between 50 and 80 feet from the edge of pavement.

Proposed noise wall #11 would begin approximately 1,250 feet south of the SR 20 overpass and continue north along the eastern side of I-75 and up the I-75 northbound off-ramp to SR 20 for a total length of approximately 1,003 feet. The wall placement would range between 20 and 50 feet from the edge of pavement.

The proposed noise wall locations were chosen based on the topography of the surrounding area to optimize wall height. Locating walls in areas where the topography adjacent to the road shoulder is below the roadway would not optimize the wall height and provide sufficient abatement to impacted receivers. Any noise wall constructed within the clear zone of the roadway would be protected by barrier to provide safety to the traveling public.

Two locations were evaluated for noise abatement but determined not to be reasonable. Noise wall #3 was evaluated for impacted receivers 125-132, and 134 along the eastern side of I-75 just north of the Walt Stephens Road overpass. The required noise reduction goal of 7 dBA was not satisfied for any receiver located in the vicinity of noise wall #3. Noise wall #4 was evaluated for impacted receivers 180-185, 187, and 207 along the eastern side of I-75 just north of the I-75 bridge over Flippen Road. The construction cost of noise wall #4 would exceed the cost per benefited receptor. Therefore, no noise wall is proposed at these locations. For impacted receiver 690, driveway access to SR 155 would reduce noise wall effectiveness and, therefore, a noise wall would not be a feasible abatement measure.

A reevaluation of the noise analysis may occur during final design if changes to the project warrant a reevaluation. If, during final design, it has been determined that conditions have changed such that noise abatement is not feasible and reasonable, the abatement measures might not be provided. The final decision on the installation of any abatement measure will be made upon completion of the project’s final design and the public involvement processes.

CSNHS-0009-00(156) and CSNHS-0009-00(157)PI Nos. 0009156 and 0009157Henry and Clayton Counties

Section 6Page 6-2

NOISE TECHNICAL REPORT: I-75 MANAGED LANES October 2012

CSNHS-0009-00(156) and CSNHS-0009-00(157)PI Nos. 0009156 and 0009157Henry and Clayton Counties

Attachment 1Figures Related to

Noise Modeling

NOISE TECHNICAL REPORT: I-75 MANAGED LANES October 2012

CSNHS-0009-00(156) and CSNHS-0009-00(157)PI Nos. 0009156 and 0009157Henry and Clayton Counties

Attachment 2Field Measurement Data

Sheets and Validation

NOISE TECHNICAL REPORT: I-75 MANAGED LANES October 2012

CSNHS-0009-00(156) and CSNHS-0009-00(157)PI Nos. 0009156 and 0009157Henry and Clayton Counties

Attachment 3Sound Level Results

NOISE TECHNICAL REPORT: I-75 MANAGED LANES October 2012

CSNHS-0009-00(156) and CSNHS-0009-00(157)PI Nos. 0009156 and 0009157Henry and Clayton Counties

Attachment 4TNM Input/Output Data

NOISE TECHNICAL REPORT: I-75 MANAGED LANES October 2012

CSNHS-0009-00(156) and CSNHS-0009-00(157)PI Nos. 0009156 and 0009157Henry and Clayton Counties

Attachment 5Study Area Information

NOISE TECHNICAL REPORT: I-75 MANAGED LANES October 2012

CSNHS-0009-00(156) and CSNHS-0009-00(157)PI Nos. 0009156 and 0009157Henry and Clayton Counties

Attachment 6Traffic Data