AIDA FEE64 production report June 2011
•LYCCA tests and MBS•Production of FEE64•Preparation for October test.
13th June 2011 1
LYCCA test and MBSA single FEE64 card with mezzanine was mounted on the central
aluminium support and along with top cooling plate was plugged via the LYCCA adaptors into a LYCCA silicon detector in the LYCCA chamber at GSI. The cooling was provided by a fan and aluminium cooling blocks.
The MBS interface was used, successfully, to integrate data with the MBS system.
13th June 2011 2
Production of FEE64
• Electronics testing is proceeding.• Cooling pads for the AIDA modules
are being manufactured. A modified set of pads has been ordered.
• Mechanical parts for the modules are in stock.
13th June 2011 3
Preparation for the October test
• 6th June , meeting to discuss installation of a system inT4 that will be shipped to GSI for the October experiment.
• Designing the MACB to integrate the 12 FEE64 cards ( 6 modules ) into a system.
• Problem with HDMI connection.