ahmed10
TRANSCRIPT
Page 1 of 6 (Ahmed El Sawy) CV. Updated on 15.07.2016
Ahmed Mahmoud El Sawy
Mechanical Engineer
CSWIP Welding Inspector (Level II) – API 570 Piping Inspector
Personal Information:
Date of Birth 01 November 1986.
Marital Status Single.
Contacts: [email protected]
+20-1225333500
+966-593094488
Educational
Qualification:
Degree Speciality Institute/University
Bachelor's degree of
Mechanical Power Engineering
Specialized in construction and welding inspection of steel tanks, piping and pipelines.
Alexandria University
June-2010.
Languages:
Arabic: (Native) Reading Writing Speaking
English: (V.Good) Reading Writing Speaking
Other(s): N/A N/A N/A
Executive Summary:
Total Years of Experience More than 5 Years
Designation Mechanical Engineer (Piping & Welding)
Design, fabrication and construction of steel tanks for oil storage.
Preparation and erection of mechanical skids in the power plants.
Erection of all piping systems in gas turbine including lube oil system, hydraulic oil
system, fuel oil system, cooling water system, draining system, ignition gas
system, N2 system, blow off system, pressure measuring piping system… etc.
Fabrication, erection, welding, testing and flushing of piping systems in and balance
of plant (BOP) including black start diesel generator, DFO system, crude oil system,
compressor air system, service air system, CO2 system and fire fighting system.
Review all engineering / fabrication drawings (P&ID, layout and isometric).
Applying all NDE (VT, PT, interpretation of RT films) according to ASME Code.
Perform material receiving inspection according to EN 10204 (3.1).
Monitor WQT in line with client reference specification.
Surveillance of all fit-up and welding activities and make visual inspection for
welded joints before, during and after welding.
Preparation of WPS, PQR, WPQ, ITP, method statement, welding book, all NDE
procedures and all other QC documentations and reports.
Perform daily and comprehensive reports to line supervisor.
Provision of Quality Assurance input to Inspection & Test Plans / Quality Plans.
Page 2 of 6 (Ahmed El Sawy) CV. Updated on 15.07.2016
Professional Experience:
EXECUTIVE PROJECT EXPERIENCE
Company: SADELMI Power s.r.l.
Project name: QAPCO Project – State of Qatar.
Position : Mechanical Commissioning Engineer
Period : Start: May/2016 End: To Present
Client : Qatar Petrochemical Company.
Project Budget: 69 Million Euro
Project description : Engineering, Design, Supply, Installation, Commissioning & Testing of Gas Turbines (Replacement of GT1 & GT2, Refurbishment of GT3, GT4 & GT5 and installation of new GT6) on Turn-key basis.
Employee’s role & responsibility in the project:
Responsible for pre-commissioning and commissioning for all mechanical activities in GT and BOP
area, in-line with different vendors.
Technologies and methodologies used by the employee in the project: xxxxx.
Company: SADELMI Power / Al Ayuni Contracting and Investment Company.
Project name: ARAR POWER PLANT EXT. IV – Saudi Arabia.
Position : Mechanical Engineer – Welding Inspector
Period : Start: June 2014 End: May 2016
Client : Saudi Electricity Company – Kingdom of Saudi Arabia.
Project Budget: 309 Million SAR
Project description : Design, construct, erect, test, commission, and put into service two new Power Plant Units (55-70 MW each Unit).
Employee’s role & responsibility in the project:
Responsible for erection, welding and testing of all tanks and piping systems, plus mechanical
installation in GT and BOP area.
Page 3 of 6 (Ahmed El Sawy) CV. Updated on 15.07.2016
Company: Arab Contracting Company (ARCONS) – Egypt.
Project name: Zero Liquid Discharge - Misr Fertilizers Co.(MOPCO) - Egypt.
Position : QA/QC Engineer
Period : Start: December 2013 End: May 2014
Client : Veolia Water Solution Egypt (VWSE).
Project Budget: N/A.
Project description :
Design, Fabrication, Erection, Welding, Painting and Testing of two carbon steel tanks in ZLD.
Employee’s role & responsibility in the project:
Responsible for steel fabrication and mechanical construction and testing of Tanks.
Company: Arab Contracting Company (ARCONS) – Egypt.
Project name: Egyptian Indian Polyester Company (EIPET)- Egypt.
Position : Construction Engineer
Period : Start: July 2012 End: December 2013
Client : Oerlikon BARMAG / EIPET.
Project description :
Erection of four Tanks with 6200 cubic meter capacity per tank & made of special material cladded carbon steel (double layer CS/SS), also our scope include the Installation of Tankage Piping Network 2000 inch of welded joints.
Employee’s role & responsibility in the project:
Responsible for steel fabrication, mechanical construction and testing of Tanks.
Page 4 of 6 (Ahmed El Sawy) CV. Updated on 15.07.2016
Company: Water Dynamics – Egypt.
Project name: Marina sewage water treatment station - Egypt.
Position : Mechanical Engineer
Period : Start: February 2011 End: June 2012
Client : METITO Company.
Project description :
Installation of treatment station for sewage water.
Employee’s role & responsibility in the project:
Responsible for installation activities of mechanical equipment and piping.
Membership:
1. Saudi Council of Engineers For Life Member Since June/2014
2. Egyptian For Life Member Since September/2010
Training & Certificates:
No. Training name Organization Expiration Date Exams or certificates
1 CSWIP – Level II TWI Ltd. June 2017 CSWIP Welding Inspector
Certificate # 66420.
2 API 570 API April 2019 API 570 Piping Inspector
Certificate # 64720
3 ASNT-NDT - II STE December 2018 VT – PT – MT - RT
Page 5 of 6 (Ahmed El Sawy) CV. Updated on 15.07.2016
Page 6 of 6 (Ahmed El Sawy) CV. Updated on 15.07.2016