Page 1: Agile metrics   what is... riga-version

© 2015 Accenture. All rights reserved. Accenture, its logo, and 'High Performance. Delivered.' are trademarks of Accenture.

Agile Day Riga 2015

Alex Birke, May 23, 2015

Essential Metrics for Agile Project Management

Page 2: Agile metrics   what is... riga-version

Why Metrics?

“they help […] to make decisions” (Eric Ries, Lean Startup)

2© 2015 Accenture. All rights reserved.

Page 3: Agile metrics   what is... riga-version

What makes a good metric?

As many as required, as less as possible

Leading indicators over trailing indicators

Measure results, not activity

Assess trends, not snapshots

Easy to collect

4© 2015 Accenture. All rights reserved.

Page 4: Agile metrics   what is... riga-version

But wait!

What about Scrum’s metrics asthe Burndown and the Velocity!

5© 2015 Accenture. All rights reserved.

Page 5: Agile metrics   what is... riga-version

A Set of Core Metrics for Agile Project management*

Scope Cost

Schedule Productivity

� Story Point Effort Performance Indicator� Scope Volatility

� Release Slippage Risk Indicator

� Sprint BurndownPerformance Indicator

� Release BurnchartPerformance Indicator

Quality

� Sprint Productivity

� Required Productivity

© 2015 Accenture. All rights reserved.

*) Metrics are agnostic of technology or domain where Agile Project Management is used

� Running Tested Features

� Delivered Defect Rate

Page 6: Agile metrics   what is... riga-version

Sprint Productivity (P)

Definition

Productivity is measured as generated value in story points that can be completed per person day.

Calculation

# story points [SP] of a sprint

P =

# person days of a sprint

8© 2015 Accenture. All rights reserved.

Page 7: Agile metrics   what is... riga-version

Required Productivity (RP)

Definition

RP is the productivity that the team would require in the remaining sprints, to complete at least remaining “Must-Have” user stories, so that a Minimal Viable Release (MVR) can be deployed to production.

Calculation

# of SP estimate of remaining “Must-Have” stories

RP =

Total planned effort in remaining sprints

9© 2015 Accenture. All rights reserved.

Page 8: Agile metrics   what is... riga-version

Required Productivity

10© 2015 Accenture. All rights reserved.

Required Velocity =

(3 [SP] + 3 [SP] +8 [SP] + 3 [SP]

) / 3

= 5.66 [SP]

Assuming 105 hours per upcoming Sprint:

RP = 5.66 [SP] / 105 [hours] = 0.054 [SP / hours]

Page 9: Agile metrics   what is... riga-version

Release Slippage Risk Indicator (RSRI)

Definition

RSRI indicates whether at least a minimal viable release (MVR) can be deployed to production on the scheduled date.

Calculation

“Past” Sprint Productivity (P)

RSRI =

Required Sprint Productivity for release date (RP)

= 1 : as planned

RSRI < 1 : delayed

> 1 : ahead of plan

11© 2015 Accenture. All rights reserved.

Page 10: Agile metrics   what is... riga-version

Release Slippage Risk Indicator

12© 2015 Accenture. All rights reserved.

Required Productivity = ( 3 [SP] + 3 [SP] + 8 [SP] + 3 [SP] ) / (3 [Sprints] * 105 [hours] ) =

= 0.054 [SP / hours]

Past Productivity = 5 [SP] / 90 [hours] = 0.055 [SP / hours]

Release Slippage Risk = 1.02

Page 11: Agile metrics   what is... riga-version

Release BurnChart Performance Indicator (RBPI)

Definition

RBPI indicates if a project is on schedule by showing the variation in the amount of completed work compared to amount of work planned.

Calculation

Story points fully completed so far in the release

RBPI =

Story points planned so far in the release

= 1 : as planned

RBPI < 1 : delayed

> 1 : ahead of plan

13© 2015 Accenture. All rights reserved.

Page 12: Agile metrics   what is... riga-version

0 20 60160

280400

560

720820

9201015

11101210

1330

490

0

200

400

600

800

1000

1200

1400

1600

1800

0 1 2 3 4 5 6 7 8 9 10 11 12 13

Wo

rk (

Sto

ry P

oin

ts)

Sprint #

Release Burn Up Chart

Must-Have Scope Must-Have + Should-Have ScopePlanned Dev Complete or Accenture Scope CompleteIdeal Burn-Up Required Burn

2 new “Billing” epics added“Summary Reports” added

“Rating” epics de-scoped

In the example above, at the end of Sprint 7: RBPI = 490 / 720 = 0.68,

which indicates that the amount of user stories done was less than expected.

Release BurnChart Performance Indicator

© 2015 Accenture. All rights reserved.

Page 13: Agile metrics   what is... riga-version

Sprint Burndown Performance Indicator (SBPI)

Definition

SBPI shows the deviation in completed work compared to work planned, for the current sprint.

Calculation

Ideal remaining work

SBPI =

Actual remaining work

= 1: as planned

SBPI < 1: delayed

> 1: ahead of plan

15© 2015 Accenture. All rights reserved.

Page 14: Agile metrics   what is... riga-version

Sprint Burndown Performance Indicator = 120 [hours] / 160 [hours] = .75

(i.e. -25% deviation)

Sprint Burndown Performance Indicator= 40 [SP] / 50 [SP] = .80

Fig. 1: Task Burndown (effort based) Fig. 2: User Story Burndown (Story Point based)

Sprint Burndown Performance Indicator

© 2015 Accenture. All rights reserved.

Page 15: Agile metrics   what is... riga-version

Scope Volatility (SV)

Definition

Scope Volatility depicts the amount of change in size of the release scope, comparing the release scope size measured at start of the release and after the last completed sprint.

Calculation

Current Size of Must-Have Scope – Initial Size of Must-Have Scope

SV = * 100

Initial Size of Must-Have Scope

> 0: Scope creep

SV < 0: Scope drop

= 0: Planned scope size retained (often corridor)

17© 2015 Accenture. All rights reserved.

Page 16: Agile metrics   what is... riga-version

11431228

Must-Have Scope 1237

1273 1330

0

200

400

600

800

1000

1200

1400

1600

1800

0 1 2 3 4 5 6 7 8 9 10 11 12 13

Wo

rk (

Sto

ry P

oin

ts)

Sprint #

Release Burn Up Chart

Must-Have Scope Must-Have + Should-Have ScopePlanned Dev Complete or Accenture Scope CompleteIdeal Burn-Up Required Burn

2 new “Billing” epics added

“Rating” epics de-scoped

In the example above, Scope Volatility = (1273 [SP] – 1143 [SP] ) / 1143 [SP] * 100 = .11

Scope Volatility

© 2015 Accenture. All rights reserved.

Page 17: Agile metrics   what is... riga-version

Story Point Effort Performance Indicator (SPEPI)

Definition

SPEPI (aka CPI, sprint-wise) indicates if the ongoing project release is currently on budget, depicting deviation in planned effort per story point to the actual effort per story point.

Calculation

Planned Effort to be spent in the release so far

Planned Story points delivered in the release so far

SPEPI =

Actual Effort spent on the release so far

Actual Story points delivered in the release so far

= 1 : as planned

SPEPI < 1 : cost overrun

> 1 : under budget

19© 2015 Accenture. All rights reserved.

Page 18: Agile metrics   what is... riga-version

Story Point Effort Performance Indicator

“per”

20

Value

Effort / money

SPEPI = (875 / 630 ) / ( 957 / 490 ) = 0.71, which indicates a cost overrun.

© 2015 Accenture. All rights reserved.

Page 19: Agile metrics   what is... riga-version

Running Tested Features* (RTF)

Definition

RTF depicts the variance of working (running) features over total features built to date.

Calculation

# completed user stories that still pass all acceptance tests

RTF = x 100

total # of completed user stories to date

21© 2015 Accenture. All rights reserved.

*) “A Metric leading to Agility”, Ron Jeffries

Page 20: Agile metrics   what is... riga-version

Running Tested Features

22© 2015 Accenture. All rights reserved.

Sprint 6 RTF rate was 71%.

This indicates that the remaining 29% of the user stories built and tested are not working and cannot be deployed to production.

Page 21: Agile metrics   what is... riga-version

Delivered Defect Rate (DDR)

Definition

DDR indicates the effectiveness of the review and testing activities, thus ensuring that fewer defects are identified on the delivered product (increment).

Calculation

Defects identified after Done-ness of user stories

DDR =

Total effort spent in all tasks till date

Alternative metric: Defect Density is # of defects identified in completed user stories per size of Done user stories.

23© 2015 Accenture. All rights reserved.

Page 22: Agile metrics   what is... riga-version

Delivered Defect Rate

24© 2015 Accenture. All rights reserved.

DDR Sprint 1 Sprint 2 Sprint 3 Sprint 4

Defects Identified 7 12 19 25

SPE Effort 400 831 1262 1685

Defect Rate 0,018 0,014 0,015 0,015

Engineering effort includes effort from Agile Lifecycle tool for design, build, test, defect fix tasks. Includes PO & SM time as % of completed stories

Count only the defects logged after the story is marked complete by the developer

In the example above, DDR trend is stable. Therefore the delivered quality is stable.

Page 23: Agile metrics   what is... riga-version

A Set of Core Metrics for Agile Project management*

Scope Cost

Schedule Productivity

� Story Point Effort Performance Indicator� Scope Volatility

� Release Slippage Risk Indicator

� Sprint BurndownPerformance Indicator

� Release BurnchartPerformance Indicator

Quality

� Sprint Productivity

� Required Productivity

© 2015 Accenture. All rights reserved.

*) Metrics are agnostic of technology or domain where Agile Project Management is used

� Running Tested Features

� Delivered Defect Rate

Page 24: Agile metrics   what is... riga-version

Some further sometimes helpful metrics

26

% Stories accepted

Stakeholder Involvement Index

% Changed Scope

Average Time to Market

(Retrospective) Process improvement

Customer Satisfaction

Test Automation

Coverage

Employee Engagement

Epic Progress Report

Page 25: Agile metrics   what is... riga-version

Questions & Answers