aggregate pier design & construction - microsoft pier design & construction wentworth...

26
haywardbaker.com Aggregate Pier Design & Construction Wentworth Institute of Technology | Beatty Hall | Boston, MA Kevin Dawson, PE, Vice President, New England Area Manager

Upload: duongque

Post on 17-Apr-2018

222 views

Category:

Documents


7 download

TRANSCRIPT

haywardbaker.com

Aggregate Pier Design &

ConstructionWentworth Institute of Technology | Beatty Hall | Boston, MA

Kevin Dawson, PE, Vice President, New England Area Manager

90

Presentation Outline

What

Why

WhenHow

•Design

•Installation

Wrap Up

91

What

92

Vibro Piers = Aggregate Piers

• Also known by names such as GeoPier, Rammed

Aggregate Pier, Short Aggregate Pier, Compacted

Aggregate Piers, Stone Column and others

• Piers or columns of dense aggregate installed as

foundation elements to support light to medium

loads

• Often referred to as an intermediate foundation

system, i.e. not shallow but also not deep

• Usually about 24 to 42 inches in diameter and

about 10 to 30 feet deep

93

94

Aggregate Piers: How they work

• Aggregate piers form a composite

system with the surrounding soil

• When confined laterally, the

aggregate pier is much stronger

and stiffer than the surrounding

soil

• Higher modulus columns attract

load and dissipate it gradually

with depth

95

This Not This

96

Why

97

reduce total & differential settlement

Increase allowable bearing capacity

98

When

99

Selection of Ground Improvement Techniques

Soil Type Governs the Ground Improvement Technique

Mine Spoils

Loose Sand

Undocumented

Fill

Low Strength

Cohesive Soils

100

Commercial & Industrial Historic Land Use

101

Filled Land & Former Industrial &

Commercial Land Use

102

Private Industrial Site Redevelopment

103

Public Redevelopment – Filled Industrial Land

104

When Summary

• Undocumented fill or loose soil less than 30’ thick

• Appropriate loads (deep foundations or alternate ground improvement technique not required)

• Less expensive alternate ground improvement techniques not viable

• Cost/schedule impact of excavation and replacement not viable

105

How; Design

106

Aggregate Pier Design Methodology

Design based on spring analogy:

– Rigid footing: aggregate pier deflection equals

matrix soil deflection

– Stiff spring (aggregate pier) takes more load than

the soft spring (matrix soil)

107

www.HaywardBaker.com

108

Total Settlement = Settlement from the Improved Zone +

Settlement from the Unimproved Zone

IMPROVED ZONE

UNIMPROVED

ZONE

109

Pier Testing: Modulus Verification Test

Testing done either with a load frame and

anchors or utilizing the vibratory rig as a

counterweight

110

How; Installation

111

112

113

114

Wrap Up

• Cost effective intermediate foundation solution for fill & loose native soil sites

• Know the limits of the system

• Alternate ground improvement systems or deep foundations may be best match for thick soft soil deposits or if improvement depth > 30’

• Market is extending the use of aggregate piers

• Understand the risk/reward relationship