agenda: overview of bond/ballot proposal - technology technology progress to date
DESCRIPTION
LIVONIA PUBLIC SCHOOLS 2013 BOND PROJECT. AGENDA: Overview of Bond/Ballot Proposal - Technology Technology Progress to Date Technology Projects Overview. OVERVIEW OF BOND/BALLOT PROPOSAL . GOALS AND OBJECTIVES Why Now: Critical upgrades/renovations needed - PowerPoint PPT PresentationTRANSCRIPT
AGENDA: Overview of Bond/Ballot Proposal - Technology
Technology Progress to Date
Technology Projects Overview
LIVONIA PUBLIC SCHOOLS2013 BOND PROJECT
GOALS AND OBJECTIVES Why Now:
• Critical upgrades/renovations needed
• Technology improvements for 21st century learning
• Inefficient buildings – 50-60 years old
• Favorable interest rates Benefits of the bond:
• Improve educational opportunities
• Create modern learning environment through technology
• School safety enhancements• Reduce maintenance and energy
costs• Equity among buildings
Cost:• $195,000,000• 30 year millage• Projected average millage rate:
2.0 mills over life of the bond
OV E RV I E W O F BO N D / B A L LO T P R O P O S A L
SCOPE OF WORK• Information Technology
$ 30.6 Million
• Facility Improvements
$ 147.0 Million (2.9 million square feet)
• New Buses & Maintenance
$ 5.9 Million Equipment
• Furniture and
$ 7.5 MillionInstructional Equipment
• Closing / Other Costs
$ 4.0 Million
Total
$ 195.0 Million
OV E RV I E W O F BO N D / B A L LO T P R O P O S A L
O V E RV I E W O F B O N D / B A L LO T P R O P O S A L
SCOPE OF WORK
Information Technology
• Classroom Technology Tools• Mobile Learning Devices• Computers• Wireless Networks• Network Upgrades • New Phone Systems• Printers & Copiers• Servers & Infrastructure • Surveillance Systems• Technology Cabling • Community Rooms
OV E RV I E W O F BO N D / B A L LO T P R O P O S A L
AGENDA: Overview of Bond/Ballot Proposal - Technology
Progress to Date
Technology Projects Overview
LIVONIA PUBLIC SCHOOLS2013 BOND PROJECT
T E C H N O LO GY
ACTIVITIES TO DATE• Selected Technology Designer• Completed Planning Activities:
– Site visits to all buildings– Meetings with District committees:
• Instructional Technology Committee• Safety, Security, Communication Committee• Administrative Technology Committee• Technology Infrastructure Committee
– Meetings with Phase 1 buildings to review schematic design drawings
– Drafted plans and budget for major projects (wireless, PA, security, etc.)
– Identified preliminary timeline when each major project (wireless, PA, security, etc.) will be implemented
– Coordination meeting with architects / engineers
P R O G R E S S T O DAT E
T E C H N O LO GY
ACTIVITIES TO DATE (CONTINUED)• Finalized requirements for Phase 1 buildings• Finalized program for the major projects over
5 years• Finalized timeline of major projects• Drafted specifications and Request for
Proposal for:– Cabling– Wireless– Phone system– PA system– Network electronics– Sound amplification system
P R O G R E S S T O DAT E
T E C H N O LO GY
NEAR TERM ACTIVITIES• Present technology scope and phases to
Board of Education• Obtain proposals for phase 1 projects• Evaluate and recommend solutions / vendors• Board Committee review of initial phase of
technology – March 3, 2014• Board action on initial phase – March 17,
2014• Implementation
P R O G R E S S T O DAT E
T E C H N O LO GY
PHASE 1 PROJECTS - TECHNOLOGY
The following technologies are anticipated for Summer / Fall 2014 implementation at Cleveland, Coolidge, Rosedale, Frost, Cooper:
• PA system• Cabling infrastructure • Phone system for Phase 1 buildings• Wireless services initial implementation • Network upgrades necessary for wireless district-wide• Sound amplification• Re-install existing video surveillance cameras and door
access systems (new security equipment will be installed in 2015)
• Prep for initial classroom technology (actual equipment, such as projectors, document cameras, and classroom computers are anticipated to be installed in 2015)
Note – the construction scope of work includes new marker boards in classrooms
P R O G R E S S T O DAT E
T E C H N O LO GY
PHASE 1 PROJECTS - TECHNOLOGY
The following technologies are anticipated for Summer / Fall 2014 implementation district-wide:
• Cabling infrastructure for wireless • Wireless services initial implementation • Network upgrades necessary for wireless
P R O G R E S S T O DAT E
AGENDA: Overview of Bond/Ballot Proposal
Progress to Date
Technology Projects Overview
LIVONIA PUBLIC SCHOOLS2013 BOND PROJECT
DESIGN PROGRESS OVERVIEW
• Programming / scope verification• Design • Owner review at 50%, 90% • Final owner approval at 100%• Finalize Request for Proposal (RFP)• Issue RFP
T E C H N O LO GY P R O J E C T S OV E RV I E W
TECHNOLOGY SCOPE
T E C H N O LO GY P R O J E C T S OV E RV I E W
Name DescriptionDesign/Bidding
timingPreliminary
Implementation timingClassroom presentation technology and community rooms
Projection systems, document cameras, sound amplification
Winter 2015 except for sound amplification for phase 1
Starting in 2015, follow construction schedule. Phase 1 buildings will be installed in 2015
Mobile learning devices
TBD Winter 2015 Phasing TBD
Network infrastructure Network electronics, wireless, phone system, cabling
Winter 2014 Wireless and network upgrades to support wireless in 2014; balance will be phased with construction.There may be a wireless expansion in a later phase to incorporate new advancements
PA systems Cabling and speakers in each school
Winter 2014 Phased with construction
Computers Teacher, lab, media center and administrative computers
TBD TBD. Teacher computers will be coordinated with classroom presentation technology
TECHNOLOGY SCOPE - CONTINUED
Name DescriptionDesign/Bidding
timing
Preliminary Implementation
timingSecurity Video surveillance
camerasWinter 2015 Starting in 2015, follow
construction schedule. Restoring cameras in 2014 for phase 1 buildings
Printers / copiers Printers and multi-function digital copiers
Winter 2017 Spring/Summer 2017
Servers / storage Servers and storage area network
Winter 2015 Phased from Summer 2015 - 2018
Indoor digital displays Displays and low voltage infrastructure
Infrastructure – 2014Displays - TBD
Infrastructure – follow construction schedule; Displays - TBD
T E C H N O LO GY P R O J E C T S OV E RV I E W
AGENDA: Overview of Bond/Ballot Proposal
Progress to Date - Technology
Technology Projects Overview
LIVONIA PUBLIC SCHOOLS2013 BOND PROJECT
Paul Theriault, PEOffice: 248.223.3380
Fax: 248.233.7384Paul.Theriault@plantemoran.
com
For more updates, access the website linkbelow:
LIVONIA PUBLIC SCHOOLS2013 BOND PROJECT