agenda 6:30 – 7:00 p.m. open house 7:00 – 7:20 p.m. presentation welcome introductions project...

13
Agenda 6:30 – 7:00 p.m. Open House 7:00 – 7:20 p.m. Presentation • Welcome • Introductions • Project Overview • Meeting Purpose • Environmental Review Process • Other Opportunities for Public Comment 7:20 – 8:30 p.m. Public Comment • Closing Remarks

Upload: lesley-lawson

Post on 13-Jan-2016

212 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Agenda 6:30 – 7:00 p.m. Open House 7:00 – 7:20 p.m. Presentation Welcome Introductions Project Overview Meeting Purpose Environmental Review Process Other

Agenda• 6:30 – 7:00 p.m. Open House• 7:00 – 7:20 p.m. Presentation

• Welcome• Introductions • Project Overview• Meeting Purpose• Environmental Review Process• Other Opportunities for Public

Comment• 7:20 – 8:30 p.m. Public Comment

• Closing Remarks

Page 2: Agenda 6:30 – 7:00 p.m. Open House 7:00 – 7:20 p.m. Presentation Welcome Introductions Project Overview Meeting Purpose Environmental Review Process Other

Who Are We?• Bureau of Land Management (BLM)

– Rich Burns, Ukiah Field Office Manager– Ashley Conrad-Saydah, State Office Project

Manager

• AltaGas Renewable Energy Pacific– Peter Eaton, Project Manager

• Ecology and Environment, Inc.– Dave Plumpton, consultant on behalf of AltaGas

Page 3: Agenda 6:30 – 7:00 p.m. Open House 7:00 – 7:20 p.m. Presentation Welcome Introductions Project Overview Meeting Purpose Environmental Review Process Other

Introduction to AltaGas• Established in 1994 in Calgary, Alberta• We have built a diverse foundation of natural gas and

power infrastructure• AltaGas Renewable Energy LP committed to

developing renewable energy in western North America• Approximately 1,500 MW of wind projects under

development• Approximately 400 MW of run-of-river projects under

development or construction• Bear Mountain Wind Park 102-MW became operational

in October 24, 2009

Page 4: Agenda 6:30 – 7:00 p.m. Open House 7:00 – 7:20 p.m. Presentation Welcome Introductions Project Overview Meeting Purpose Environmental Review Process Other

Project Overview

Purpose and Need

• Consider right-of-way (ROW) to construct project

• Assist the State in meeting the Renewable Portfolio Standard

Page 5: Agenda 6:30 – 7:00 p.m. Open House 7:00 – 7:20 p.m. Presentation Welcome Introductions Project Overview Meeting Purpose Environmental Review Process Other

Project OverviewProject Location

• 1,500 acres, on BLM land

• Unincorporated areas of Lake and Colusa counties

• North of State Highway 20 between the towns of Williams and Clearlake

Page 6: Agenda 6:30 – 7:00 p.m. Open House 7:00 – 7:20 p.m. Presentation Welcome Introductions Project Overview Meeting Purpose Environmental Review Process Other

<Large Map>

6

Page 7: Agenda 6:30 – 7:00 p.m. Open House 7:00 – 7:20 p.m. Presentation Welcome Introductions Project Overview Meeting Purpose Environmental Review Process Other

7

Project Statistics

• Up to 70 megawatts of renewable wind energy

• 29 Siemens wind turbine generators

• Construction to begin Q2 2012

• $240 million project

• Peak construction workforce of 170 workers

• Average onsite workforce of 150 workers

• Permanent workforce of 2-3 workers

Page 8: Agenda 6:30 – 7:00 p.m. Open House 7:00 – 7:20 p.m. Presentation Welcome Introductions Project Overview Meeting Purpose Environmental Review Process Other

Why Are We Here?

• BLM is preparing an Environmental Impact Statement (EIS)

• Present project overview• Allow the public to provide BLM information and

identify concerns• Use this information to develop and analyze the

project• BLM will utilize and coordinate the NEPA

commenting process to satisfy the public involvement process for Section 106 of the National Historic Preservation Act (NHPA)

Page 9: Agenda 6:30 – 7:00 p.m. Open House 7:00 – 7:20 p.m. Presentation Welcome Introductions Project Overview Meeting Purpose Environmental Review Process Other

Environmental Review

• The Bureau of Land Management (BLM) is the National Environmental Policy Act (NEPA) lead agency

Page 10: Agenda 6:30 – 7:00 p.m. Open House 7:00 – 7:20 p.m. Presentation Welcome Introductions Project Overview Meeting Purpose Environmental Review Process Other

Preparation of the EIS

1. Notice of Intent (June X, 2010)

2. Scoping Period (from June X to July

22, 2009)

3. Draft EIS and Public Comment Period

(90 days; anticipated Q2 2011)

4. Final EIS (to be determined)

5. Record of Decision (60 days after final

EIS)

Page 11: Agenda 6:30 – 7:00 p.m. Open House 7:00 – 7:20 p.m. Presentation Welcome Introductions Project Overview Meeting Purpose Environmental Review Process Other

NEPA Objectives

• Allow the public to provide BLM with information and identify concerns

• Identify reasonable alternatives for analysis• Analyze environmental impacts of proposed

project and alternatives• Identify ways to avoid or reduce

environmental impacts• Provide BLM with information so a decision

can be made after the EIS is complete

Page 12: Agenda 6:30 – 7:00 p.m. Open House 7:00 – 7:20 p.m. Presentation Welcome Introductions Project Overview Meeting Purpose Environmental Review Process Other

General Guidelines for the Comment Session

This session is to hear from you…

• Please:– Submit speaker cards in order to speak– Wait until your name is called– State your name and speak clearly– Limit your comments to 3 minutes; you may ask

questions after all comments have been made– Use comment forms for more extensive input

Page 13: Agenda 6:30 – 7:00 p.m. Open House 7:00 – 7:20 p.m. Presentation Welcome Introductions Project Overview Meeting Purpose Environmental Review Process Other

Where to Send Your Comments• Scoping comments will be accepted through

July X, 2010

• Send comments to:BLM Ukiah Field Office

attn: Rich Burns, Field Office Manager,

2550 North State Street

Ukiah, CA 95482

Submit by email to: [email protected]

Thank you!