african development fund

38
AFRICAN DEVELOPMENT FUND INSTITUTIONAL SUPPORT PROJECT FOR DOMESTIC RESOURCES MOBILIZATION AND NATURAL RESOURCES GOVERNANCE UNITED REPUBLIC OF TANZANIA ECGF/ECNR DEPARTMENTS March 2017 Public Disclosure Authorirzed Public Disclosure Authorirzed

Upload: others

Post on 25-Oct-2021

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: AFRICAN DEVELOPMENT FUND

AFRICAN DEVELOPMENT FUND

INSTITUTIONAL SUPPORT PROJECT FOR DOMESTIC

RESOURCES MOBILIZATION AND NATURAL RESOURCES

GOVERNANCE

UNITED REPUBLIC OF TANZANIA

ECGF/ECNR DEPARTMENTS

March 2017

Pu

bli

c D

iscl

osu

re A

uth

ori

rzed

Pu

bli

c D

iscl

osu

re A

uth

ori

rzed

Page 2: AFRICAN DEVELOPMENT FUND

TABLE OF CONTENTS

Acronyms and Abbreviations

Currency Equivalents, Fiscal Year, Weights and Measures

Loan Information

Project Executive Summary

Results-based Logical Framework

Project Time-frame

I - PROJECT STRATEGIC THRUST AND RATIONALE

1.1 Project Linkages with Country Strategy and Objectives

1.2 Rationale for Bank’s Involvement

1.3 Development Partners Coordination

II – PROJECT DESCRIPTION

2.1 Project Components

2.2 Technical Solution retained and other alternatives explored

2.3 Project Type

2.4 Project Cost and Financing Arrangements

2.5 Project’s Target Area and Population: Beneficiaries

2.6 Participatory Process for Project Identification, Design and Implementation

2.7 Bank Group Experience and Lessons reflected in Project Design

2.8 Project’s Key Performance Indicators

III – PROJECT FEASIBILITY AND IMPACTS

3.1 Economic and Financial Performance

3.2 Environmental and Social Impacts

IV – IMPLEMENTATION

4.1 Implementation Arrangements

4.2 Financial Management, Disbursement and Audit

4.3 Procurement Arrangement

4.4 Monitoring and Evaluation

4.5 Governance

4.6 Sustainability

4.7 Risk Management

4.8 Knowledge- building

V – LEGAL INSTRUMENTS AND AUTHORITY

5.1 Legal Instruments

5.2. Conditions Associated with Bank’s Intervention

5.3 Compliance with Bank Policies

VI – RECOMMENDATION

i-viii

1

1

2

4

4

4

9

10

10

11

12

12

13

13

13

13

15

15

15

16

17

17

17

18

18

18

18

19

19

19

Page 3: AFRICAN DEVELOPMENT FUND

LIST OF TABLES

Table 2.1 Project Components

Table 2.2 Project alternatives considered and reasons for rejection

Table 2.3 Project Cost Estimates by Component

Table 2.4 Sources of Financing

Table 2.5 Project Cost by Category of Expenditure

Table 2.6 Expenditure Schedule by year

Table 2.7 Lessons learned from Previous Operations and Other Analytical Reports

Table 4.1 Project Implementation Schedule

Table 4.2 Risks and Mitigation Measures

Appendices

Appendix I. Tanzania Selected Socio-Economic Indicators

Appendix II. Bank Group Portfolio in Tanzania

Appendix III. Donor Coordination Matrix for Tanzania

Appendix IV. ANRC’s Baseline study on local content in Tanzania

Appendix V. Tanzania Revenue Authority - DPs Technical Assistances and Target Areas

Appendix VI. Analytical Work Underpinnings

Appendix VII. Developments in the gas sector in Tanzania

Appendix VIII. Map of Tanzania

Page 4: AFRICAN DEVELOPMENT FUND

i

Acronyms and Abbreviations

AfDB African Development Bank Group MEM Ministry of Energy and Minerals

ADF African Development Fund MoF Ministry of Finance and Planning

ANRC

BRN

African Natural Resources Centre

Big Results Now

MoU Memorandum of Understanding

CAG Controller & Auditor General MTFF Medium-term Fiscal Framework

CCM Chama Cha Mapidunzi MTR Mid-Term Review

CIDA Canadian International Development Agency NDP National Development Plan

CPI Corruption Perception Index NPS National Panel Survey

CPIA Country Policy and Institutional Assessment

CPPR Country Portfolio Performance Review PA&OB Public Authorities and Other Bodies

CSP Country Strategy Paper PAF Performance Assessment Framework

DfID Department for International Development PBA Performance Based Allocation

DPs Development Partners PBO Program Based Operation

EARC East Africa Regional Resource Centre PE Public enterprises

EIPC Energy Infrastructure Procurement Coordinator PCR Project Completion Report

EPP Emergency Power Plants PEFA Public Expenditure and Financial

Accountability

eSWS

EU

Electronic Single Window System

European Union

PFM Public Financial Management

EWURA Energy and Water Utilities

Regulatory Authority

PFMRP Public Financial Management Reform

programme

FDI Foreign Direct Investment PPP Public private Partnerships

FM Financial Management PPRA Public Procurement Regulatory Authority

FYDP Five Year Development Plan PRSP Poverty Reduction Strategy Paper

GBS General Budget Support PSP Private Sector Participation

GCI Global Competitiveness Index REA Rural Energy Agency

GDP Gross Domestic Product RMC Regional Member Countries

GECSP Governance and Economic

Competitiveness Support Programme

SIDA Swedish International Development

Cooperation Agency

GOT Government of Tanzania SOE State-Owned Enterprises

IFMIS Integrated Public Financial Management

Information System

STAMICO State Mining Corporation

IPP Independent Power Producers TANCIS

TANESCO

Tanzania Customs Integrated System

Tanzania National Electric supply Company

IPTL Independent Power Tanzania Limited TPDC

TRA

Tanzania Petroleum Development

Corporation

Tanzania Revenue Authirity

IPSAS

ISPGG

International Public Sector Accounting Standards

Institutional Support Project for Good Governance

TYS Ten-Year Strategy (AfDB)

JAST Joint Assistance Strategy of Tanzania TZFO

TZS

Tanzania Field Office

Tanzania Shilling

JICA Japan International Cooperation Agency UA Units of Account

KPIs Key Performance Indicators USAID United States Agency for International

Development

LGA Local Government Authorities USD United States Dollars

MDA Ministries, Departments & Agencies VAT Value Added Tax

MDG Millennium Development Goals WB World Bank

ZURA Zanzibar Utility Regulatory Authority

Page 5: AFRICAN DEVELOPMENT FUND

ii

Currency Equivalents

As of February 2017

1 UA = TZS 3,019.33

1 USD = TZS 2,222

1 UA = USD 1.358

Fiscal Year

1st July – 30th June

Weights and Measures

1 metric tonne = 2204 pounds (lbs)

1 kilogramme (kg) = 2.200 lbs

1 metre (m) = 3.28 feet (ft)

1 millimetre (mm) = 0.03937 inch (“)

1 kilometre (km) = 0.62 mile

1 hectare (ha) = 2.471 acres

Loan Information

Client’s information

RECIPIENT: United Republic of Tanzania

EXECUTING AGENCY: Ministry of Finance and Planning

Financing plan

Source Amount (UA) Instrument

ADF 19.58 million Loan

GOT 2.17 million Counterpart Funds

TOTAL COST 21.75 million

Timeframe - Main Milestones (expected)

Concept Note approval

September 2016

Preparation

Appraisal

July, 2016

October, 2016

Project approval March, 2017

Effectiveness April, 2017

Mid-term Review June 2018

Completion December 2018

Last Disbursement December 2019

Page 6: AFRICAN DEVELOPMENT FUND

iii

PROJECT EXECUTIVE SUMMARY Paragraph Topics covered

Project

Overview

Project name: Institutional Support Project for Domestic Resources Mobilization and Natural Resources Governance.

Geographic scope: Entire country

Implementation timeframe: 2017-2019

Project cost: UA 21.75 million

Expected Outcomes and Outputs: The expected outcomes are (i) Effectiveness of tax revenue collection, as measured by

PEFA PI-15 and (ii) improvement in the Resource Governance Index; and (iii) Number of contract negotiated by the

Government Negotiation Team (GNT) within the new framework . This will be achieved through the following output

level results: (i)Enhanced legal and institutional framework;; (ii)Strengthening of negotiation capacity ; (iii) support to

the development of a local content plicy in the mining and gas sectors; (iv) support to gas domestication strategy; (v)

strengthened capacity for tax and non-tax revenue collection and management

Project direct beneficiaries: The direct project beneficiaries are:

on the mainland side, the Ministry of Energy and Minerals (MEM), the Tanzania Petroleum and Development

Corporation (TPDC), the Petroleum Upstream Regulatory Agency (PURA), the Energy and Water Utilities Regulatory

Authority (EWURA), the National Economic and Empowerment Council (NEEC) and Tanzania Revenue Authority

(TRA). On the Zanzibar side the project will support the Ministry of Energy and Minerals as well as the Zanzibar Utility

Regulatory Agency. For Zanzibar: the Ministry of Energy and Minerals the Zanzibar Utility Regulatory Agency (ZURA),

and the Tanzania Revenue Authority (TRA). The indirect beneficiaries are the general population of Tanzania, who will

benefit from the development of a sector that will provide increased revenues, private sector development and jobs, as

well as better access to energy. Benefits will also accrue to women as a result of the project’s support to gender-sensitive

local content policy and regulatory framework. The private sector will also benefit from the development of the sector

and particularly the local content policy developed under the project. Needs

Assessment

In the area of natural resources, the Government needs to develop capacity to fully exploit the large discoveries of natural

gas in Tanzania’s offshore waters, which make the country a potential global player/producer in the natural gas sector.

Proven natural gas resources in the country stand at 57.25 trillion cubic feet, as at May 2016. Based on these resources,

the Government of Tanzania (GoT) has continued promoting a mega Liquefied Natural Gas (LNG) project, to be jointly

implemented by a consortium comprising the 6 major oil companies active in deep-waters gas exploration. The

discussions around this major project entail negotiations of complex agreements between GoT and the consortium on,

among other matters, the implementation of a domestic supply obligation under the Tanzania Petroleum Act 2015. The

Government has recently developed key policy documents that define important orientations in the natural gas sector.

Those are considered relatively sound by the international community and private investors, while their implementation

still requires significant regulatory and institutional upgrade. Thus, the major gas discoveries represent a great opportunity

for promoting economic development, but they also come with capacity challenges for the authorities: challenges related

to effectively negotiating the various projects and delivering on the expectations they have raised. Areas where urgent

capacity needs have been identified include (i) setting up the regulatory and institutional framework, (ii) negotiations and

deal-making skills development; (iii) local content policies formulation, and (iv) skills for designing strategies for

domestication of natural gas. Marketing the gas will also come with skills requirements: owing to the envisaged sizable

gas volumes, and expected robust production capacity, there is an opportunity for Tanzania to supply local and regional

markets, as the global gas demand is expected to remain weak in the foreseeable future. This will enhance intra- regional

trade in gas. Tanzania Revenue Authority also require a boost in both human and systems capacity to effectivement

forecast and manage increased revenues, in particular those linked to the natural resources sector.

Bank’s

Added Value

The project builds upon Bank’s track record of capacity building programs in Tanzania. The Bank has the potential to

become a strategic development partner for Tanzania in the natural resources sector, given the strong collaboration and

constructive dialogue with GoT. Contract negotiations, in large natural resources development scenarios, is a particularly

complex and sensitive issue that requires the establishment of a trust relationship. The Goevrnment has indicated that it

would favour working with the Bank because it is perceived as a neutral and technically sound development partner for

the sector. . The Bank has been advising the Government in the local content sector and conducted a baseline analysis

that provides a diagnostics and road map for support. In addition, the Bank has provided through the African Legal

Support Facility (ALSF), capacity building and advisory support to the Government focused on negotiation of gas

production-sharing agreements and other related gas contracts. The proposed project will represent a scaling up of support

in this area. In addition in the context of the High 5 and the New Deal on Energy the Bank has developed a sound

framework to support the development of the energy sector on the continent, to which that project will be an important

contributor by improving access to energy and developing a gas market at national and regional level.

Knowledge

Management

The proposed project will build knowledge, develop skills in regulating, overseeing and monitoring the natural resources

sector together with accounting and financial management, various forms of audit and public procurement. The

implementation of the project will strengthen governance in the natural resources sector by (i) training staff in regulatory

issues; (ii) enhancing knowledge of the industry to promote knowledge based policy decisions; and (iii) developing

various important regulations, guidelines and manuals to guide and inform the work of public officials. Knowledge will

also be acquired through skill transfer by external experts, and study tours to appropriate institutions in other countries.

In addition, sensitisation and public awareness workshops will be undertaken on issues relating to the development of the

gas sector with specific emphasis on local content policies and domestication of the resources. The Bank will disseminate

knowledge through sharing findings of supervision missions, progress reports, and the Project Completion Report.

Lessons learned will inform future operations.

Page 7: AFRICAN DEVELOPMENT FUND

iv

Results-based Logical Framework

Country and project name: Tanzania: Institutional Support Project for Domestic Resources Mobilization and Natural Resources Governance

Purpose of the project: To promote inclusive growth by enhancing economic and financial governance through improved domestic resources

mobilization and effective natural resources governance.

RESULTS CHAIN PERFORMANCE INDICATORS MEANS OF

VERIFICATI

ON

RISKS/MITIGATION

MEASURES Indicator (including CSI)

Baseline

Target

IMP

AC

T Improved economic performance

through enhanced public finance

management and natural resources governance

FDI in the Natural Resources sector 38% of total

FDI

(2015)

48% of total FDI

(2019)

Bank of

Tanzania and &

IMF

Risk 1: Implementation

capacity constraints

both on the side of GoT and the Bank: Lack of

requisite skills for the

natural resource sector could slow down the

pace of implementation.

Mitigation 1:

GoT is giving a priority to the natural resources

sector and has an

experienced team in MEM dedicated to this

sector.

Mitigation 2:

The Bank will set up a

multi-disciplinary team to supervise project

implementation.

Risk 2:

Fiduciary risk. Although Tanzania has

made good progress in

strengthening institutions and

addressing corruption,

weaknesses still remain,

and these will continue

to pose a risk.

Mitigation 2:

The ISP project will

improve the fiduciary environment with its

compliance with the

Bank’s procurement regulations and annual

audit reports.

Risk 3: Lack of

commitments to

reforms: Sustained support at the highest

level of Government is

required for the success of reforms in the

domestic resources

mobilization and natural resource sector.

Meanwhile, GoT long

processes may impact on the implementation

process.

Tax to GDP Ratio 13

(2015)

14,9

(2019)

MEM reports

OU

TC

OM

ES

Increased domestic resources mobilization

Effectiveness of tax collection PEFA P.I 15

B+(2013) A(2019) MoFP & IMF

Improved natural resources

governance sector

Resource governance index (composite

score)

50/100

(2015)

60/100

(2019)

Natural

Resource

Governance

Institute Report

Number of contract negotiated by

Government Negotiation Team (GNT) within the new framework

None

(2015)

7 contracts

negotiated (2020)

MEM progress

reports

OU

TP

UT

S

Component 1: Support to development of the natural resources sector

1.1 Enhancement of the legal

and institutional framework

Establishment of the Petroleum Upstream Regulatory Agency (PURA)

PURA Created by law but not

operational

PURA established and

functional

Project progress reports

Development of implementing

Regulations, Model Agreements and Guidelines for the gas sector

Regulations

not existing or needing

amendment

Regulations

developed

Availability of

Regulations, Model

Agreements and

Guidelines

1.2 Capacity building for

negotiations in the natural gas

sector

GNT fully operationalised No GNT (2015)

GNT fully operataionlised

(2019)

MEM progress report

Training needs assessments for MEM,

PURA and GNT and development of tailored training programs

(2015)

No training plan in place

(2019)

Training needs assessment report

and training plan

finalised

MEM and

PURA reports

Training in prepararion for negotiations, conducting negotiations, knowledge of

the industry and contractual

arranagements

0 (2015) 40 staff trained -at least 30%

female (2019)

1.3 Support to the development

and implementation of a local

content policy in the mining and

gas sectors

Roadmap for development and implementation of a local content policy

(2015) No roadmap

(2019) Policy guidelines

developed

PURA report

Study of the supply chain in the mining

and gas sectors

(2015) None (2018)

Study completed and validated

PURA report

Monitoring system to track progress by local SMEs in the extractive sector.

(2015) None (2018) System

developed and

operationalized

NEEC progress report

1.4 Support to domestication

strategy

Gas domestication strategy developed (2015)

No strategy in

place

(2018)

Strategy

developed

MEM progress

report

Knowledge sharing & studies on best practices for gas domestication

0 (2015) 20 Government officials – at least

30% female

(2019)

MEM progress report

Technical assistance to key institutions in

charge of gas domestication

(2015)

None

(2019)

50 PURA, MEM

and TPDC staff trained

MEM progress

report

Page 8: AFRICAN DEVELOPMENT FUND

v

Component 2: Enhancing Domestic Resources Mobilization

2.1 Strengthening capacity for

Tax Revenue collection and

management

Training in tax policy, taxation of extractive industry, transfer pricing, tax

treaty and negotiations (at least 30%

female)

No training (2015)

150 TRA,TR, ZRB, staff

trained(2019)

TRA and ZRB progress reports

Mitigation 3:

Constant dialogue

between GoT and the Bank and Development

Partners, should ensure

continued commitment to these important

reforms in this sector.

ZRB’s Revenue forecasting model enhanced

Basic forecasting

model in place

(2015)

Forecasting model enhanced

(2018)

TRA progress reports

Upgrade Tanzania Customs Integrated

Systems (TANCIS) to fully-fledged electronic Single Window System

(eSWS)

TANCIS in

place (2015)

Fully fledged

eSWS operationalized

(2018)

TRA progress

reports

Procurement of two (2) mobile Scanners

No mobile

scanner (2015)

Mobile Scanners

operational (2018)

TRA progress

reports

2.2 Strengthening capacity for

non-tax revenue collection and

management

Enhancement of Revenue Gateway

System for tax and non-tax revenue

collection

Functionality

of system

limited to tax revenue

collection

Functionality

enhanced for

both tax and non-tax revenue

collection (2018)

TRA progress

reports

Training in Programme Based Budgeting No training

(2015)

100 TRA,TR,

ZRB, staff trained(2019)

TRA and ZRB

progress reports

Component 3: Project management

3.1 PIU strengthened and

production of project reports

Number of reports produced (quarterly) None 2019 – 12 reports PIU progress reports

3.2 Project evaluation and

monitoring reports

Steering committee meetings & reports None 2019 – 6 reports PIU progress

reports

KE

Y

AC

TIV

ITIE

S

S

COMPONENTS INPUTS

Component 1: Support to development of the natural resources sector

Component 2 Enhancing Domestic Resources Mobilization

Component 3 : Project management

Inputs : - Funding in million UA

ADF : UA 19.58 million

GoT : UA 2.17 million

Total project cost: UA 21.75 million

Page 9: AFRICAN DEVELOPMENT FUND

vi

Table 1: Project Implementation Schedule

Years

Quarter Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Action By

Activities

Project life cycle

Loan approval AfDB

Fulfilment of conditions for disbursement GoT

Start of the project and launch AfDB & GoT

Supervision and Monitoring AfDB

Mid-term review AfDB/ GoT

Disbursement of Funds AfDB

Aubmission of annual audit reports GoT

Government completion report GoT

AfDB Project Completion Report AfDB

All Components

General Procurement Notice published GoT

Recruitment of contractors GoT

Contract local partner training institute GoT

Procurement of IT equipment and software GoT

Submission of progress reports from contractors GoT

Training and workshops GoT

2017 2018 2019

Page 10: AFRICAN DEVELOPMENT FUND

1

REPORT AND RECOMMENDATION OF MANAGEMENT TO THE BOARD OF

DIRECTORS ON A PROPOSED LOAN TO THE UNITED REPUBLIC OF TANZANIA

TO FINANCE THE INSTITUTIONAL SUPPORT PROJECT FOR DOMESTIC

RESOURCES MOBILIZATION AND NATURAL RESOURCES GOVERNANCE

Management submits the following Report and Recommendation on a proposed ADF Loan of

UA 19.58 million to the United Republic of Tanzania to finance the Institutional Support

Project for Domestic Resource Mobilization and Natural Resources Governance.

I. STRATEGIC THRUST AND RATIONALE

1.1 Project Linkages with Country and Bank Strategies and Objectives

The proposed operation is aligned with Tanzania’s Development Vision 2025, the National

Strategy for Growth and Reduction of Poverty II (NSGRP II), , the Zanzibar Strategy for

Growth and Reduction of Poverty (ZSGRP II)

and the Second Five-Year Development Plan II

(FYDP II, 2016/17-2020/21). The project will

support GoT’s policy objectives in domestic

resources mobilization and in developing the

natural resources sector, through well-targeted

capacity building activities and long term

technical assistance. The Government has

recently developed key policy documents that

define important orientations in the natural gas

sector. Those are considered relatively sound

by international standards, while their

implementation still requires significant

regulatory and institutional upgrade.

These initiatives indicate GoT’s commitments

to strengthening the oil and gas sector. The new

legislation aims to ensure that there is

transparency and accountability in the

extractive industry, and seeks to establish an

effective framework for fiscal rules and

management of oil and gas. Particular emphasis is put on local content policy in the gas sector,

which has also been developed. The overall coordination of local content policy has been vested

in a dedicated directorate at the Prime Minister’s office. Overall, the Government of Tanzania

has prioritized the utilization of natural gas to satisfy the domestic market needs for energy, and

to feed petro-chemical industries. This vision is articulated in the National Energy Policy 2015

and enshrined in the Petroleum Act 2015. It is a priority, and a vision, that could be supported

by targeted intervention under the proposed operation. TPDC, the national oil company,

manages the Government shares in developing the gas projects with the objective of

maxisimising benefits, influencing project development as well as building national expertise

in the sector. The exisiting legal and institutional framework has to be strengthened with

implementating regulations and strategies-tailored to the country vision but aslo meeting the

best international standards in order to attract and retain foreign direct investments in the natural

resources sector.

1.1.2 Alignment with the Bank’s Strategy: The proposed project is also firmly anchored

on the objectives and priorities of the Bank’s Tanzania Country Strategy Paper (CSP)

2016-2020. The CSP places emphasis on strengthening governance and accountability (Pillar II),

Box 1:.Key new provisions in recent policy

documents in the gas sector

Below are some of the key policy orientations

contained in the 2015 Petroleum Act, the 2013

Natural Gas Policy, the draft Natural Gas Utilisation

Master Plan and the 2015 Oil and Gas Revenue

Management Act:

Clarification of the policy objectives and

institutional roles at the upstream, midstream

and downstream levels;

Creation of a Petroleum Upstream Regulatory

Agency and a National Oil Company (the

Tanzania Petroleum Development Corporation,

TPDC ) with clearly separated roles.The two

roles were hitherto carried out by TPDC with

perceived conflicts of interests.

New provisions for the Model Production

Sharing Agreement (PSA);

Confirmation of the conditions for onshore

LNG plants.

Domestic market to be given priority over

exports

To establish a fund to manage gas revenues

Promotion of local firms for contract award in

the extractives sector

Page 11: AFRICAN DEVELOPMENT FUND

2

including in sectors such as energy, oil and gas, as well as in PFM, where domestic resources

mobilization is of critical importance. The proposed project is also aligned with the Bank’s Ten-

Year Strategy (TYS), which has Governance and Accountability as a core operational

priorityand puts specific emphasis on the need for RMCs to enhance domestic resources

mobilization to support their development efforts, in the new global aid architecture

characterized by diminishing Official Development Assistance (ODA). It is also aligned to the

High 5s, particularly the “Light up and Power Africa” objectives that support Transformative

Partnership for Energy in Africa.It will notably support the implementation of the New Deal on

Energy by developing the country’s gas resources with priority given to domestic and regional

markets. Developing these ressources will provide significantly increased access to energy for

public consumption and private sector development at national and regional levels. Furthermore,

the project will support the High5s objective to “Industrialize Africa,” since natural gas will supply

domestic markets, providing sustainable affordable energy source for industrial development. The

proposed operation is also in line with the Governance and Strategic Framework and Action Plan

2014-2018 (GAP II), which supports, among others, institutional capacity development in the public

sector, domestic resources mobilization, sector governance and enhancing accountability and

transparency in the use of public resources.

1.1.3 Complementarity and synergy with past and ongoing Bank operations: This proposed

project will complement and enhance the effectiveness of ongoing Bank operations by

addressing capacity gaps, in the public sector, in domestic resources mobilization and

natural resources governance. It is complementary, and in synergy, with the ongoing ISPGG

III in a number of ways, including: (i) ISPGG III, through improving PFM, will contribute to

further strengthening public sector capacity to generate and manage increased resources from

enhanced domestic resources mobilization; and (ii) ISPGG III, through improving the business

enabling environment, will also render the oil and gas sector more attractive for striking the

required mega deals and attracting private sector investments.

1.1.4 Complementarity and synergy with development partners operations: The proposed

operation will also complement the interventions of other development partners. In the

natural resources sector, under the ongoing multi-donor PFMRP IV, 2014/18, oil and gas is

recognized as an important sub-sector fraught with “emerging public financial management

issues”1; but the sub-sector is not being supported by PFMRP IV. There has, however, been

support from GiZ, NORAD, JICA, the World Bank and the EU focusing on targeted technical

assistance in specific areas of the sector. Consultations were held with concerned parties during

preparation and appraisal missions to avoid duplication, build synergies and enhance

collaboration. An overview of other DPs operations is presented in Appendix 3. In the area of

domestic resources mobilization, the following DPs are supporting TRA: DfID, Denmark,

Norway, the US Treasury, IMF, World Bank and JICA (see Appendix 42). While this list

amounts to a multiplicity of DPs, the assistance envisaged from AfDB under the proposed

project will complement, and not duplicate, the support of the other DPs. The proposed project

will be complementary by focusing on the following identified areas: (i) Domestic Taxes (large

taxpayers); (ii) Domestic Taxes (medium and small taxpayers); (iii) Customs and Excise and

(iv) Research and Planning.

1.2 Rationale for Bank’s Involvement

1.2.1 The socio-economic challenges facing Tanzania in the context of a huge natural

resource base require continued pursuit of institutional capacity building development

1 See “Mid-Term Review for the Public Finance Management Reform Program Phase Four, Tanzania”, Draft Final

Report, Innovex, July 2015 2 Annex 4 indicates the DPs supporting TRA and their areas of focus.

Page 12: AFRICAN DEVELOPMENT FUND

3

of a sound regulatory framework, and enhancement of transparency and accountability in the

management and utilisation of public resources. The country recently developed key policy

documents that define important orientations in the natural gas sector. While these are

considered relatively sound by international standards, their implementation still requires

significant regulatory and institutional upgrade. Addressing governance challenges by

strengthening the policy, legal, regulatory and institutional frameworks in the oil and gas sector

is timely, given that GoT strategic policy orientations in the sector are currently being

formulated, and long-term contract negotiations are contemplated with the private sector. The

quantum of financial and non-financial resources GoT will be able to extract from natural

resources will depend very much on its ability to create the enabling environment and negotiate

favorable deals with investors. The Bank should intervene now, when there is still an

opportunity to make an impact in natural resource governance in Tanzania.

1.2.2 While support to Tanzania’s oil and gas sector is critical and timely, it is also

important to further strengthen the country’s broader revenue mobilization efforts

through institution strengthening. The Government has faced challenges in financing its

fiscal gap, due to low levels of domestic revenue in a context of increasingly unpredictable

external assistance. With tax/GDP ratio of 13%, Tanzania falls behind its peers such as Rwanda

(15,5%), Kenya (18%) and Uganda (14,3%). This poor performance is explained by low VAT

collection, administrative inefficiency and low tax payer compliance. Addressing this requires

a combination of policy and tax administration reforms. These have been identified as a

challenge in the Five Year Development Plan (FYDP II) and steps being taken to address it

include (i) fighting tax evasion; (ii) streamlining exemptions, (iii) widening the revenue base;

and (iv) strengthening the capacity of revenue collecting agencies. More needs to be done to

increase both tax and non-tax revenue collection, including in the areas of upgrading the IT

system, enhancing forecasting capacities, strengthening compliance risk management, and

building capacity for taxation of the extractive industry. Through the proposed project, targeted

support will be provided to Tanzania Revenue Authority, and Zanzibar Revenue Board to deal

with the challenges and weaknesses identified through (i) provision of training and other forms

of capacity-building to the designated beneficiaries; (ii) procurement of ICT and other

equipment and supplies; (iii) review of key policy documents; (iv) financing key studies to pave

the way for further reforms and appropriate policy implementation; and (v) provision of

technical assistance.

1.2.3 An added value of this operation lies in the fact that the Bank is seen by GOT as a reliable

and trusted partner. Hence, the strong basis for policy dialogue built over the years makes it

easy to engage with the government on critical and sensitive issues such as natural resources

management. The Bank’s vast experience in implementing similar projects, across the

continent, is also a source of value addition.

1.2.4 Analytical Works Underpinning: The design of this project is guided by various

analytical and diagnostic reports as well as broad consultations during the preparation

and appraisal missions. A high level mission was undertaken by the Bank in April 2016 to

engage the Minister of Energy and Minerals and other senior officials in discussions on the

sector challenges. The mission was the opportunity to confirm key policy orientations, delineate

the needs in terms of capacity building and identify main areas of support. In addition, the Bank

conducted a study to provide an overview of the main developments, key orientations,

challenges and opportunities in the natural resources sector in Tanzania, and this was notably

used to produce an annex to the Tanzania CSP. The Bank also conducted a baseline study of

the local content sector in order to provide a diagnostic of the sector,provide the Government

with a roadmap and inform the Bank support. Furthermore, the Bank recently developed

Page 13: AFRICAN DEVELOPMENT FUND

4

knowledge tools on local content policy formulation and capacity building for negotiations.

These knowledge tools provide a conceptual approach based on knowledge building and

tailored to country needs to providing support in these two key areas of the project. Furthermore,

the AfDB is conducting a study of the Gas Domestication strategy developed and implemented

in South Korea over the last 30 years in order to delineate lessons learnt that could be used for

RMCs.

Finally, the Bank developed “Guidelines for Women’s Economic Empowerment in Oil and Gas

Industries in Africa” that are used to inform the activities to support the elaboration of the local

content policy as well as the regulatory

framework. These studies and

knowledge tools have constituted

valuable inputs to the design of the key

activities of the project. Those were also

discussed in details with relevant

stakeholders during the prepararation

and appraisal missions. Other documents

underpinning the design of the operation

include the Tanzania Revenue Authority

Fourth Corporate Plan 2013/14 –

2017/18; Fourth Review of the IMF

Policy Support Instrument and IMF

Article IV Consultation Report, July

2016; Tax Administration Diagnostic

Tools Assessment; March 2016.

1.3 Development Partners’ Coordination

1.3.1 Development partners’ support to Tanzania is coordinated by the Ministry of

Finance and Planning, responsible for aid mobilisation, coordination and reporting.

Development partners’ collaboration is generally good, but there is room for improvement of

the aid coordination mechanism particularly in budget support. At the moment there is no

sectoral working group in the gas sector, though there is one in the energy sector. The Bank

mission team has been able to meet relevant development partners during preparation and

appraisal and was able to ensure that the proposed project does not entail duplication of

activities and provides the opportunity for building synergies and collaborations. PFM reform

dialogue is conducted through the PFMRP IV framework, in which the Bank participates

through the Field Office, TZFO, which has been active in institutional capacity and PFM

dialogue between GOT and development partners. II. PROJECT DESCRIPTION

2.1 Project Components

2.1.1 Project Objectives: The overall development objective of the proposed project is to

promote inclusive growth by contributing to supporting the development of the natural

resources sector and enhancing domestic resources mobilization. The two central

pillars/components of the proposed operation are inextricably linked: sound development of the

natural resources sector will make significant contribution to providing Tanzania with

domestically-generated resources to finance its development programme. The enhanced policy

and regulatory framework and related improvements in natural resource governance is expected

to attract large investments to develop the country’s gas resources, while the development of

the local SMEs, boosted by the local content policy, will generate additional tax revenues.

Operationalization of the Government Negotiations Team (GNT) will also boost negotiation

Box 2:.Key Challenges for local procurement in the

extractives sector in Tanzania

The report conducted by the ANRC indentifies six key issues:

1) gaps in the legal framework for regulation, 2) the issue of a

supplier database, 3) SME development and enterprise centres,

4) addressing the lack of capital for Tanzanian entrepreneurs,

5) support and prioritization for larger industries, and 6) soft vs

hard local content regulations. Key findings include a general

weakness in PA2015 and even more so in the Mining Act 2010

in terms of promoting local content. There is confusion about

who is responsible for monitoring and enforcing local content

in the minerals sector and a lack of information about any

enforcement actions taken to date. Unlike in many other

countries, there are no clauses giving companies value-added

activities in-country preference if they are within a certain

margin of the lowest bid for a tender in either petroleum or

mining. Finally, there are multiple definitions of a ‘local

company’ in Tanzania.

Page 14: AFRICAN DEVELOPMENT FUND

5

capacity and ensure good deals for the Government. Thus, development of the gas sector is an

important initiative in domestic resource mobilization, for which the Tanzania Revenue

Authority is expected by Government to develop the requisite capacity to respond to this

challenge. In adition to this, capacity development of Tanzania Revenue Authority, through

enhancement of the revenue gateway system, better forecasting and capacity building of staff,

will enhance its capacity to raise and manage tax and non-tax revenues.

2.1.2 Project Components: The project has three components: (i) enhancing governance in

the natural resources sector (ii) enhancing domestic resources mobilization and (iii) Project

Management.

Component 1: Enhancing governance in the natural resources sector

The interventions in this component will focus on building capacity of the government to

develop the country’s natural gas resources and maximize economic development outcomes. It

will include support to the development of legal and institutional frameworks,building capacity

for negotiations, and support to the formulation and implementation of local content and gas

domestication strategies. These activities are essential as the sector is being developed to ensure

that the country maximizes development benefits from its large gas reserves and avoids the

curses associated with natural resources. It should be underlined that these activities are

preparatory and it is expected that the gas production, and associated fiscal revenues, will take

place after the project implementation phase.

The main beneficiaries are, on the mainland side, the Ministry of Energy and Minerals, the

Tanzania Petroleum and Development Corporation, the Petroleum Upstream Regulatory

Agency, the Energy and Water Utilities Regulatory Authority, and the National Economic and

Empowerment Council. On the Zanzibar side the project will support the Ministry of Energy

and Minerals as well as the Zanzibar Utility Regulatory Agency.

The following activities have been discussed and agreed with the respective institutions;

Support to the legal and institutional framework

The support will aim at developing and reinforcing the institutions in charge of regulating and

monitoring the sector as detailed in the Petroleum Act of 2015. The support will also aim at

developing the necessary regulations under the act to facilitate implementation and provide a

clear legal framework for the sector for both public and private entities.A key institution in that

context is PURA, whose role and mandate are particularly important. However, as a newly

established agency, the capacity building needs are significant. Currently PURA has staff

allocated –mainly drawn from MEM and TPDC – as well as building allocated. However the

staff needs training in regulatory functions and the ICT –based management system is required

among others. NORAD has just conducted a detailed needs analysis for a comprehensive ICT

system for PURA, following consultations with NORAd and the Government it is suggested

that the AfDB will provide the key elements required under the study.

The AfDB support will include design, procurement and installation of ICT infrastructure,

technical Assistant in development of various regulations and operational documents as well

as essential trainings.

Particular attention will be given to gender equality in that sector. The tool developed by the

ANRC “Guidelines for Women’s Economic Empowerment in Oil and Gas Industries in Africa”

will be used as it provides a checklist to identify and promote women economic empowerement.

This will be useful when developing the regulatory framework.

Page 15: AFRICAN DEVELOPMENT FUND

6

Capacity building and support to negotiations

The proposed project will support the capacity enhancement of the Government Negotiations

Team (GNT) to effectively represent the interests of GoT in negotiations with private investors

and regional partners involved in various gas development projects. The GNT is coordinated

by MEM, and its membershipincludes key agencies such as PURA and TPDC, which play an

important role in supporting and advising the team.

The proposed project will support the establishment of the negotiation framework and defining

the operating environment (structure of the GNT, strategy for future negotiations, mandate,

roles, strategic direction, service delivery model, scope of interventions, etc.). It will also

include studies and benchmarks to inform the negotiation strategies and build knowledge of the

industry.

The support will benefit from the recently developed ANRC’s “Negotiations Capacity Building

Support Training Program”. It is a specific response to the need to strengthen the ability of

negotiators. The framework was developed in collaboration with the ALSF. The desired

outcomes are a clear mandate, an empowered team of negotiators, clear lines of authority and

policy, legal and institutional parameters to stabilize the environment for negotiating and

implementing agreements.

Support to the implementation of a local content policy

Tanzania has developed a local content policy for mining and gas, aimed at ensuring that a

high proportion of project inputs are sourced locally without compromising the economic

benefits of the project. The proposed project will support the implementation of the policy to

capture the value of natural resources wealth as quickly and as early in the project life cycle as

possible. The NEEC, PURA, and EWURA are key institutions in the sector. The AfDB support

will include the development of a detailed roadmap for the local content policy, economic

analysis to inform the policy options.

The badeline study of the local content sector, currently underdaken by ANRC, will provide a

diagnostic of the situation that will inform the Bank support. The AfDB support will also rely

on the ANRC’s local content roadmap which assists policymakers in formulating and

implementing effective local content policies by outlining a step-by-step process to guide key

considerations and weigh trade-offs. It is generic in that it can be used in various contexts to

enable governments to optimize the economic value derived from developing natural resources.

The assumption is that in so doing there is an economic multiplier effect that results in greater

value extraction by host countries.

Support for the development and implementation of a Gas domestication strategy

The proposed project will help build the capacity of relevant institutions, particularly MEM,

EWURA and TPDC, to enable them evaluate various alternatives for gas utilization, with

particular focus on the economics of LNG development, based on previous experiences and

best practices. ANRC has conducted a case study on gas domestication in South Korea, from

which key lessons can be drawn for African gas producing countries like Tanzania.The aim is

also to gain negotiation skills in administering and monitoring LNG contract compliance and

performance. The finalisation of the Gas Utilisation Master Plan (NGUMP) is an important

milestone in that regard. The Bank’s support will include technical and market analysis for

domestic and regional markets, studies including on pricing models, technical assistance in

formulating the gas domestication and distribution plan, as well as support to draft regulatory

tools and standards to develop gas transport, storage and distribution.

Page 16: AFRICAN DEVELOPMENT FUND

7

Component 2: Strengthening domestic resources mobilization.

Under this component, the proposed project will provide targeted support to key revenue

collection agencies to complement the natural resources governance intervention. It will focus

on building capacity for both tax and non-tax revenue collection, to complement support already

being provided by other Development partners to the TRA on the Mainland. Beneficiaries on

the Zanzibar side are the Zanzibar Revenue Board, and the Tanzania Revenue Authority.

TRA is the main revenue collection body in Tanzania. Some of the recent achievements include

the implementation of e-filing of VAT; introduction of computerised drivers licence system;

customs modernization through the implementation of import and export commodity database

system; electronic cargo tracking and the implementation of computer forensic laboratories for

tax investigations. It has also succeeded in promoting violuntary compliance by increasing

taxpayer registration through the introduction of electronic fiscal devices; establishment of an

internationaltaxation unit; and the introduction of an enterprise-wide risk management system.

TRA also instituted the Tax Modernization Programme to help implement various initiatives

that were earmarked in the 3rd Corporate Plan, with support from development Partners, such

the World Bank, DFID, Denmark, Norway, IMF, Korea, and Japan.

TRA’s operations are guided by the fourth Corporate Plan 2013/14 – 2017/18, focusing on three

strategic themes: convenience, compliance and continous improvement.

Support to tax revenue enhancement

The project will also finance the acquisition of two mobile X-ray scanners, for containerized

cargo. They wil be used for inspection of medium risk goods as per computerized risk

management (CRMS) selectivity. Since 2008, the volume of importation at Port of Dar es

salaam increased significantly resulting in congestion of the port. To address this challenge the

government introduced Inland Container Deport (ICD). With this arrangement most of

containers were delivered to ICD immediately after discharge from vessel.

Since 2005, the TRA has been using the Tax Revenue Forecasting Model (TRFM) to carry out

its revenue forecasts and establish annual revenue targets for each tax item collected at all levels

and monitor revenue performance. The effectiveness of the model depends on the reliability of

data, which is usually weak and of insufficient quality. This situation has compromised the

quality of revenue forecasting at TRA. The proposed project will provide technical assistance

in reviewing and enhancing the existing revenue forecasting model. The output will be an

upgraded tax revenue forecasting model integrated with the database for data storage and model

performance indicators; enhance the model’s capacity to produce at least five year forecasts

with reasonable level of accuracy; development of a technical and instructional manual for

operating and finetuning the model; and related training in revenue forecasting. A package of

capacity building support geared towards boosting tax revenue collection will also be provided

to beneficiary institutions.

Support to non-tax revenue enhancement

As part of efforts to boost revenue collection, Government has tasked TRA to take steps to

facilitate electronic payment of non-tax revenues across Government institutions. A thorough

evlaution carried out by a team of experts concluded that the existing Revenue Gateway System

should be enhanced to handle the additional capability, instead of establishing a new system

solely focused on non-tax revenues. It will require adding functionalities that will facilitate,

among others, a visibility of reports on revenue collection for both tax and non-tax revenues to

Page 17: AFRICAN DEVELOPMENT FUND

8

the ministry, as well as a customization of the functions of the Revenue Gateway System to

extend their usage to other stakeholders. The proposed project will support this effort.

To achieve this, the project will support TRA’s efforts to enhance voluntary tax compliance

with a view to increasing domestic revenue from 61% of total revenue in 2015 to 70% by 2018.

This is partly necessitated by the declining international trade taxes resulting from regional

integration.

The proposed operation wil help to enhance Tanzania Customs Integrated Systems (TANCIS)

to a fully-fledged electronic Single Window System (eSWS). This will improve

competitiveness of Tanzania in cross borders trading environment in the region. The aim is to

gradually have an integrated solution, which will facilitate application and submission of

relevant documents and single point of getting all information on imports, exports and transit

clearance processes while ensuring the safety and security interests of the country. The single

window environment aims to expedite and simplify information flows between businesses and

the Government. It is a system that allows traders to lodge information to a single platform to

fulfil all import- or export related regulatory requirements.

Component 3: Project Implementation Unit This component will finance the cost of running the Project Implementation Unit (PIU). It will

also cover the cost of annual audits as well as training of PIU staff..

Table 2.1: Project Components and Estimated Cost

Components Component description Estimated

Cost

(UA’000)

Component 1: Enhancing governance in the natural resources sector

Sub-component 1.1:

Support to the legal

and institutional

framework

Under this component, activities will cover the elaboration of the necessary

regulations, rules and guidelines and capacity building for the establishement of

PURA, with the following activities:

Design, procurement and installation of ICT infrastructure,

Technical Assistant in development of various regulations operational

documents including upstream regulations, ‘Model Plan for Development

and Operation Document’, data management and fiscal metering manuals,

Facilitate the benchmark study and development of guidelines for contractual

arrangements with investors including the alignment of the Model

Production Sharing Agreement (MPSA) with the Petroleum Act,

Training on Petroleum resources evaluation.

2,737.2

Sub-component 1.2:

Capacity building and

support for natural

resource management

Through the sub-component, the project will support the government to negotiate

agreements in the gas sector with the following activities:

Support to the establishment of the negotiation framework and defining the

operating environment (structure of the GNT, strategy for future negotiations,

mandate, roles, strategic direction, service delivery model, scope of

interventions, etc.)

Studies and benchmarks to inform the negotiation strategies,

Long course training on the Oil and Gas (Eight (8) geoscientists and engineers will be trained in oil and gas courses at the Masters’ Level. The

course will include Petroleum Geoscience, petroleum Engineering, reservoir

evaluation, Development Geology, Oil and Gas economics, subsurface and

LNG Technology)

Capacity building on processing and interpretation of 3D seismic data

(Capacitate Four (4) geoscientists in 3D seismic data processing and

interpretation. Expected output will be processed (SEGY DATA) 3D seismic

data and interpretation).

4,749.7

Sub-component 1.3:

Support to the

Through the sub-component, the project will support implementation of the

following activities:

Page 18: AFRICAN DEVELOPMENT FUND

9

Components Component description Estimated

Cost

(UA’000)

elaboration and

implementation of a

local content policy

Develop a detailed implementation plan that can be developed using the

ANRC’s toolkit for local content policy formulation,

Develop, install and operationalize monitoring and evaluation system for Local

Content (IT system to register and evaluate local SMEs in the extractive sector,

in collaboration with private sector),

Analysis of the supply chains in the mining and gas sectors,

Analysis of capacity of local SMEs in relation to demand and capacity gap

analysis,

401.1

Sub-component 1.4:

Support to the

elaboration of a gas

domestication strategy

Under this sub-component, the Bank support will include:

Conducting the commercial, technical and market analysis for domestic and

regional market – to inform policy orientations and the negotiation process

Studies including on pricing models,

Technical assistance in formulating the gas domestication and distribution plan,

Support to draft regulatory tools and standards to develop gas transport, storage

and distribution,

Development of a detailed study on structuring the midstream and downstream

gas market,

143.5

Component 1 Sub-total 8,031.5

Component 2: Enhancing Domestic Resources Mobilization

Sub-component

2.1 Enhancing Tax

revenue Collection

This component will help to modernise the tax administration both at Mainland

and Zanzibar level. Under this sub-component, the Project will support:

Procurement of two (2) mobile Scanners

a) Facilitate speedy clearance while supporting optimal revenue collection

and security across sea ports, airports and border stations.

b) Extend the scanning operations across major seaport, airports and land

border stations.

Improve ZRB’s working environment and enforcement functions.

Enhance ZRB’s revenue forecasting model

4,542.9

2.2 Enhancing non-tax

revenue collection

Activities under the second sub-component will focus on:

Enhancement of TRA’s Revenue Gateway System for non-tax revenue

collection;

Training of TRA staff on the non tax functionality of the Revenue Gateway

System;

Upgrade Tanzania Customs Integrated Systems (TANCIS) to fully-fledged

electronic Single Window System (eSWS),

7,576.0

Component 2 Sub-total 12,118.9

Component III: Project Management

The PIU team will be handling and coordinating all activities for the beneficiaries

both in Mainland and Zanzibar. Under this component, the project will support:

Project operating and audits costs

Training activities for the PIU teams

569.2

Contingency (5%) 1,036.0

TOTAL 21,755.55

2.2. Technical Solution Retained and Other Alternatives Explored

2.2.1 During project preparation and appraisal, a number of options were explored regarding

the areas of intervention, the scope of the activities, the number of institutions to support

modality of delivering the capacity building support and implementation arrangements. Based

on these considerations, the recommendations from analytical works, as well as lessons from

the Bank’s and other DPs’ capacity-building operations, it was agreed with GOT to provide

Page 19: AFRICAN DEVELOPMENT FUND

10

balanced intervention targeting both natural resources governance, and domestic revenue

mobilization. The possibility of focusing the project entirely on capacity building for natural

resources was considered, in view of the huge capacity issues in the sector and the challenge of

managing natural resource revenues. However, it was agreed to extend some support to other

agencies such as TRA. The objective is to maximise the impact on the most important

government agencies, as well as facilitate coordination, which can sometimes be a challenge. It

was decided to set up a PIU at TPDC, given the natural resource focus of the project and

TPDC’s capacity to handle reporting and procurement activities, while the Zanzibar side will

use the exisiting PIU set up for ISPGG III. In the past, the use of two PIUs, one for the Mainland

and one for Zanzibar, has ensured that delays in one part of the country do not affect the other

part, while at the same time provding opportunities for experience-sharing. Following

consultations with government agencies and experience from DPs, it was decided to have the

PIU for mainland beneficiaries located at TPDC.

Table 2.2: Project Alternatives Considered and Reasons for Rejection

Alternative Brief Description Reasons for Rejection

Focus entirely on

natural resource

management

The possibility of focusing the project

entirely on capacity building for natural

resources was considered, in view of the

huge capacity issues in the sector and the

challenge of managing natural resource

revenues.

While it is important to give particular attention to

the natural resources sector, its links with the

Government’s wider domestic revenue

mobilization efforts is critical. It is on this basis

that the bulk of the funding is allocated to

component 1, and a smaller amount allocated to

domestic revenue mobilization (both tax and non

tax revenues).

Channel the

resources

through TRA’s

Tax

Modernization

programme,

supported by a

number of

Development

Partners.

The possibility of channeling the project

resources through TRA’s Tax

Modernization programme was

considered. This has the advantage of

maximising harmonization with other

Development Parrners supporting tax

policy and tax revenue administration

reforms in Tanzania.

Given that a large part of the resources provided by

the project is in the area of natural resource

governance, the team found it inappropriate to

channel the resources through TRA. Instead,

TPDC is designated as the PIU for more effective

coordination. However, steps are being taken to

ensure that the limited support to TRA is

coordinated with the Tax Modernization

programme.

2.3 Project Type

The proposed project is an institutional support project designed to complement

ISPGG III, and developcapacityto maximise benefits from the gas sector. It aims at

contributing to building the capacity of GoT to develop its large gas resources to promote

inclusive economic gowth.

2.4 Project Cost and Financing Arrangements

2.4.1 The estimated total cost of the project, net of taxes and duties, is UA21,75 million

(including 10% GoT contribution). A contingency of 5%, has been factored in the project

cost. Tables (2.3) and (2.4) present the estimated project cost by component and sources of

finance, whereas Tables (2.5) and (2.6) present the estimated project costs by Category of

Expenditure. Details of the project cost by component and expenditure category are also

presented in Technical Annex B2. The Bank will finance UA 19.58 million while the GOT

contribution is UA 2.17 million.

Page 20: AFRICAN DEVELOPMENT FUND

11

Table 2.3: Project Cost Estimate by Component

Table 2.4: Sources of Financing

Table 2.5: Project Cost by Category of Expenditure – ADF (in thousand UA)

Table 2.6: Project Cost by Category of Expenditure – GoT (in thousand UA)

Table 2.7: Expenditure Schedule by year (in thousand UA)

%

Total Total Foreign

Component I : Enhancing governance in

the natural resources sector 10,913.4 8,031.5 77%

Component II: Enhancing Domestic

Resources Mobilization16,736.2 12,118.9 96%

Component III: Project Management 773.5 569.2 14%

TOTAL BASE COST 28,423.0 20,719.5 86%

Contingency (5%) 1,421.2 1,036.0

TOTAL PROJECT COST 29,844.2 21,755.5 86%

Total Cost,

'000 US

Total Cost

'000 UA Component

Foreign Local Total

ADF Loan 18,806.2 773.8 19,580.0 90%

GoT Counterpart funding - 2,175.5 2,175.5 10%

TOTAL PROJECT COST 18,806.2 2,949.3 21,755.5 100%

% of total

amount Source of funding

Costs in Thousands UA

Goods 10,264.4 1,140.5 11,404.9

Services 6,986.6 256.3 7,242.8

Operating Costs - - -

TOTAL BASE COST 17,251.0 1,396.8 18,647.7

Contingency (5%) 862.5 69.3 932.3

TOTAL PROJECT COST 18,113.5 1,466.1 19,580.0

Expenditure Account Foreign Local Total

GoT

Goods - -

Services - 2,029.7

Operating Costs - 42.3

TOTAL BASE COST - 2,072.0

Contingency (5%) - 103.6

TOTAL PROJECT COST - 2,175.5

COMPONENT 2017 2018 2019 Total

Enhancing governance

in the natural resources

sector

2,409.4 4,015.7 1,606.3 8,031.5

Enhancing Domestic

Resources Mobilization3,635.7 6,059.4 2,423.8 12,118.9

Project Management 170.8 284.6 113.8 569.2

TOTAL BASE COST 6,215.9 10,359.8 4,143.9 20,719.5

Contingency (5%) 310.8 518.0 207.2 1,036.0

Total Project Cost (incl.

contingency)6,526.7 10,877.8 4,351.1 21,755.5

Page 21: AFRICAN DEVELOPMENT FUND

12

2.5 Project’s Target Area, Population and Beneficiaries

2.5.1 The direct project beneficiaries are: on the mainland side, the Ministry of Finance

and Planning, the Ministry of Energy and Minerals (MEM), the Tanzania Petroleum and

Development Corporation (TPDC), the Petroleum Upstream Regulatory Agency (PURA),

the Zanzibar Utilities Regulatory Authority (ZURA), the Energy and Water Utilities

Regulatory Authority (EWURA), the National Economic and Empowerment Council

(NEEC), Tanzania Revenue Authority (TRA). On the Zanzibar side the project will support

Tanzania Revenue Authority – Zanzibar, Zanzibar Revenue Board. The indirect beneficiaries

are the general population of Tanzania, who will benefit from the development of the gas sector,

that will provide increased revenues, employment oppotunities, private sector developmentand

better access to energy. Benefits will also accrue to women as a result of the project’s support

to gender-sensitive local content policy and regulatory framework. The private sector will also

benefit from the development of the sector and particularly the local content policy developed

under the project.

2.6 Participatory Process for Project Identification, Design and Implementation

2.6.1 Wide stakeholder consultation was carried out with Ministries, Departments &

Agencies (MDAs), development partners, the private sector, NGOs and civil society

during project preparation and appraisal. The preparation mission was preceded by two

high level missions led by the ANRC director that met the Minister of Energy and Minerals and

the Chief Secretary to discuss policy objectives and the key support areas of the project. The

private sector, both local and the international investors, was adequately consulted, mainly

through umbrella bodies, and views expressed guided the selection of several key activities,

notably with regards to the development tof the regulatory framework, support to negotiations

and the elaboration of a local content roadmap.

The appraisal mission held discussions with the key beneficiaries both bilaterally and as a group

to ensure that needs were fully identified. The Bank mission team also met with other DPs

involved in the sector to exchange views on key challenges work towards harmonization and

avoidance of duplication.

The important observations highlighted during these consultations include the need for: country

ownership, gender mainstreaming, sustainability, alignment with the country’s development

priority and harmonization with other DP interventions. These observations and suggestions

informed the design of the proposed project.Thus, the Project is prepared taking into account

the various potential beneficiaries’ strategic/corporate plans, and the Bank’s CSP, which are

products of consultative processes. During the implementation stage, regular consultations will

continue, particularly with private sector bodies and civil society organisations to ensure that

their concerns are addressed. The half yearly supervision missions, and the mid-term review of

project implementation, will ensure continued engagement with all stakeholders, including non-

state actors.

2.7 Bank Group Experience and Lessons Reflected in Project Design

2.7.1 In designing the proposed project, the experience and lessons from previous Bank

interventions in Tanzania were exploited. These sources of experience and lessons include

the Project Completion Reports (PCRs) for ISPGG I and II, and the GECSP budget support

operation; the implementation of the CSP 2011-2015; the findings of the CSP Mid-Term

Review; and of the Country Portfolio Performance Review Report. The PCRs, in particular,

made a number of recommendations, from lessons learned, which have influenced the design

Page 22: AFRICAN DEVELOPMENT FUND

13

of this operation. These recommendations and lessons include (i) care should be taken in the

choice of initiatives/beneficiaries to support, so that the scope, complexity and ambition of the

project or programme is managed to ensure adequate attention to GOT priorities; (ii) in order

to facilitate the measurement of the impact of training programmes, benchmark measurements,

where feasible, should be undertaken to understand the level of staff competences prior to

provision of training; (iii) coordintation among government agencies can also be challenging

and need to be carefully taken into consideration. Those lessons learnt have guided the

elaboration of the proposed project.

2.7.2 As at September 2016, the Bank’s active portfolio in Tanzania amounted to UA 1,361.0

million, comprising 12 national public sector operations of UA 953.2 million and 8

multinational operations of UA 223.3 million and 4 private sector operations of UA 184.4

million (see Appendix 2. for a comprehensive list of ongoing operations). The average

cumulative disbursement rate for the overall portfolio was 21.7% at 30 September, 2016 and

the average age of the portfolio stood at 3.2 years. The portfolio is rated as satisfactory with a

score of 3.2 (on a 0-4 scale) according to the 2016 CPPR. The portfolio has no problem

project or potentially problem project. Key challenges facing the portfolio include the need

to improve performance in areas such as quality at entry, capacity constraints of implementing

agencies, contract management, and slow disbursement. These challenges are being addressed

by GOT and the Bank through the implementation of the Country Portfolio Improvement Plan

2.8 Project Performance Indicators

The key performance indicators identified, and the expected outcomes on project

completion, are set out in the Logical Framework. The expected outcomes from the first

Component “ Support to the development of the Gas sector” are (i) Improved resource

governance index score (ii) Increase in the number of contracts negotiated by the Government

Negotiations Team (GNT) under the new framework.. The expected outcome under Component

2, “Enhancing Domestic Resource Mobilization” are (i) Efectiveness of tax collection, as

measured by PEFA PI-15.

3. PROJECT FEASIBILITY

3.1 Economic and Financial Performance

3.1.1 The economic and financial benefits from the project will be both direct and

indirect. In the long term, assuming the necessary investments are made in the production

phase, natural gas could help provide the fiscal space for investments in infrastructure and other

areas to facilitate fast-tracking social and economic development to transform the living

standards of Tanzanians. However, it should be noted that oil and gas resources are finite, and,

therefore, require the country to build human and institutional capacity to prudently manage

both the resources and the revenue flows in order to maximise impact on economic

development. The benefits of the project will derive from (i) improved regulatory framework

of the natural gas sector, (ii) better capacity to negotiate large and complex investments, (iii)

the development of a local content policy that will provide opportunity for local

(includingwomen) entrepreneurs and (iv) the elaboration of a domestication strategy that will

enhance access to energy at the national and regional level. The project will support the

establishment of a key regulatory body in Tanzania to oversee the development of the gas

sector, create significant job opportunities for local workers and women and facilitate access to

energy for the population of the country and the region. It will also contribute to enhancing the

performance of key revenue collecting agencies through capacity building. In economic and

financial terms, the project has the potential to help increase private investments in the natural

Page 23: AFRICAN DEVELOPMENT FUND

14

resources sector from 38% of total FDI in 2015 to 48% in 2019. Furthermore, it will contribute

to increasing GDP growth rate from 6.9% in 2015 to 7.2% in 2019.

3.2 Environmental and Social Impact

3.2.1 Environment and Climate Change: The proposed project is classified as Category

3 in the Bank’s environmental categorization system. The project will not have a negative

impact on the environment, as its activities are limited to training, technical assistance, studies,

office automation and computer hardware. Project activities that are focused on such human

and institutional capacity building have no negative impact on climate change. The project’s

support to the institutional and regulatory framework has the potential to positively impact on

the environment by increasing the capacity to oversee and monitor developments in a

potentially environmentally sensitive sector such as the natural gas.

3.2.2 Social Impact: The Project will contribute to strengthening governance institutions

and improving the regulatory framework and the business climate. This will eventually

result in a more effective public sector administration, reduction in corruption and an increase

in private investments. This will enhance attractiveness for investments in the natural resources

sector and further unlock the country’s economic growth potential. The impact on poverty

reduction will be indirect, but significant. In addition to promoting women empowerment, the

youth will also benefit indirectly through increased employment and entrepreneurial

opportunities created by an increased FDI flow in the natural resources sector. The increased

revenue collection as a result of the intervention will also help create fiscal space and hence

facilitate investments in critical areas with significant socioeconomic impact.

3.2.3 The proposed project, by supporting the elaboration of a local content policy in a

sector that attracts large FDI inflows, has the potential to boost private sector

development over the medium-term. The support in the elaboration of a roadmap for local

content policy formulation, based on a detailed economic analysis of the supply chain in the

extractives sector, can help the Government to establish guidelines and regulations that will

provide opportunities for the local private sector. In direct support of the industrialisation

strategy of the Bank in the context of the High 5s, the objective is to gradually build capacity

of local SMEs and entrepeneurs to take advantage of the supply chain in the gas servicing

industry, both at construction and operation phases.

3.2.4 The project is expected to contribute to increasing access to energy both at the

national and regional levels in the medium to long term. It will contribute to developing a

domestication strategy for natural gas resources that will inform the drafting of the regulatory

framework and the ongoing negotiations with international investors. In direct support of the

Bank’s “New Deal on Energy” in the context of the High 5s, the objective is to develop a

national and regional gas market that will attract investors, develop a regional distribution

network and improve access to energy for domestic consumption and private sector

development.

3.2.5 Gender Impact: The project is expected to benefit women by improving access to

a safe and clean source of energy for cooking and promoting women entrepeneurship in

the Gas servicing industry. The tool developed by the ANRC “Guidelines for Women’s

Economic Empowerment in Oil and Gas Industries in Africa” will be used as it provides a

checklist to identify and promote women economic empowerement. This will be useful when

developing the regulatory framework and in particular developing a local content policy that

will specifically provide opportunities for women entrepeneurs in the sector. In addition the

development of a natural gas domestication strategy will improve access to energy and in

particular for women provide a safe and clean source of energy for cooking. In the context of

Page 24: AFRICAN DEVELOPMENT FUND

15

supporting the development of local content policies, particular attention will be paid to the

promotion of gender Local content policies provide an important entry point for promoting

women’s economic empowerment in oil and gas industry, for example through (a) Ensuring

that women benefit equally from compensation and community programmes and royalties

(social investments) from these industries; (b) Promotion of women’s direct, waged

employment in the oil and gas sector; (c) Encouraging or mandating suppliers and

subcontractors to the sector to employ women (indirect employment); (d) Enabling also women

entrepreneurs to gain access to oil and gas industries as suppliers.

4. IMPLEMENTATION

4.1 Implementation Arrangements

4.1.1 Project Coordination Unit: As for similar past and ongoing Bank projects, 2 PIUs, one

for Zanzibar beneficiaries and the other for the Mainland beneficiaries, will be used. Experience

suggests that the use of two PIUs, will ensure that delays in one part of the country do not affect

the other part, while at the same time providing opportunities for experience-sharing between

the two PIUs. Following consultations with government agencies and DPs, it was decided to

have the PIU for mainland beneficiaries located at TPDC, mainly because of their capacity to

handle reporting and procurement procedures. The objective is to maximise the impact on the

most important government agencies as well as facilitate coordination, which can sometimes

be a challenge.

4.1.2 Project Steering Committees: For the Tanzania Mainland Component, the overall

implementation of the project will be the responsibility of a Project Steering Committee

(PSC) chaired by the Deputy Permanent Secretary at the Ministry of Energy and

Minerals. The members of the steering committee will include representatives of each

beneficiary agency, i.e. MEM, TPDC, PURA, ZURA, EWURA and the NEED, TRA, and ZRB

. The PSC will meet at least once every quarter to review overall progress in implementation

and take action when necessary to resolve emerging or outstanding issues. A Project

Implementation Unit (PIU) will be set up within TPDC. The PIU will be headed by an

experienced Project Manager, assisted by a Project Accountant, Administrative Assistant/Clerk

and a Secretary. The PIU will coordinate and manage the day-to-day project tasks for each

beneficiary agency, particularly in respect of matters relating to procurement, contract

supervision, monitoring and reporting on project implementation.

4.1.3 For the Zanzibar Component, a similar institutional arrangement will be deployed

for the implementation of the project. The PIU set up for the Institutional Support project for

Good Governance (ISPGG III) will be used for the project. A Project Steering Committee,

under the chairmanship of the MoF Principal Secretary, is in place. Membership of the PSC

will be expanded to include new beneficiaries such as TRA-Zanzibar and Zanzibar Revenue

Board.

4.2 Financial Management, Disbursement and Audit Arrangements

4.2.1 The Bank has conducted an assessment of the adequacy of the financial management

system of the proposed project covering Tanzania Mainland and Zanzibar. The assessment

based on the Bank’s FM Implementation Guidelines-2014 concluded that the overall residual

risk is “Moderate”. The proposed mitigation measures, as per the risk table, Annex 1, when

implemented, will enhance the Project ability to (i) use the funds for the intended purposes in

an efficient and economical way; (ii) prepare accurate, reliable and timely periodic financial

reports, and (iii) safeguard the entities’ assets.

Page 25: AFRICAN DEVELOPMENT FUND

16

4.2.2 In line with the Paris Declaration on Aid Effectiveness and Accra Agenda for

Action, the project will substantially make use of the Country’s financial management

systems. The day to day management will be as per the rules and procedures as stipulated in

the Tanzania (Tanzania mainland) Tanzania Petroleum Development Corporation (TPDC) and

the Zanzibar Ministry of Finance (MoF)) Financial policies and procedures. The Director of

Finance of TPDC and the Accountant General for Zanzibar will be the overall responsible

Officers for the financial management of the Project in their respective organizations/ Ministry.

The Internal Audit Departments (TPDC and Zanzibar) will audit the project financial

transactions regularly. The internal audit reports will be shared with the Bank as needed. Both

institutions are committed to configuring their SAGE Evolution Pastel and Epicor Version 10

respectively to accommodate the Project accounting and reporting requirements. In addition

TPDC will put in place Projects Implementation Manual (including Financial Management) to

guide operations of projects. TPDC will assign Project Accountant while MoF will assign an

Assistant Project Accountant to coordinate or assist the day to day financial management

requirements of the Project.

4.2.3 Disbursement Arrangements: Disbursement will be in accordance with the Bank

Group’s Rules of Procedure for Disbursement, as stipulated in the Disbursement

Handbook (2012 Version). The Executing Agencies will each open two special accounts (one

denominated in US Dollars and the other in Tanzanian Shillings) for the purpose of this project,

at a bank acceptable to ADF. The loan resources will be deposited in the special accounts and

will be operated as a revolving fund. The ADF will replenish the special accounts at the request

of the Executing Agencies, after justifications for the use of at least 50% of the most recent

deposits and 100% of all the other older advances have been provided. The four disbursement

methods will be available for use during project implementation. The Bank will issue a

disbursement letter, which will provide specific guidelines on key disbursement procedures and

practices.

4.2.4 Financial Reporting and Auditing: The Project will follow the Tanzania Mainland

and Zanzibar financial year of 1st July to June 30th. The financial statements will be

audited by the Controller and Auditor Generals (CAG) in Tanzania Mainland) and

Zanzibar in accordance to area of their jurisdiction. The audit will be conducted in

accordance to the terms of reference for Audit of Bank financed projects. Two Separate audit

reports for TPDC and MoF, complete with Management letters, will be submitted to the Bank

within six months of the end of the financial year

4.3 Procurement Arrangements

4.3.1 Procurement of goods (including non-consultancy services) and the acquisition of

consulting services, financed by the Bank under the project, will be carried out in accordance

with the Bank’s“Procurement Policy and Methodology for Bank Group Funded Operations”

(BPM), dated October 2015 and following the provisions stated in the Financing Agreement.

Specifically, Procurement will be carried out as follows:

Bank Procurement Policy and Methodology (BPM): Bank Standard Procurement

Methods and Procedures (PMPs), using the relevant Bank Standard or Model Solicitation

Documents (SSDs) for contracts that are above certain financial thresholds detailed in the

Procurement Technical Annex.

Borrower Procurement System (BPS): Specific Procurement Methods and Procedures

(PMPs) under BPS comprising its Laws and Regulations, Public Procurement Act, 2011

Page 26: AFRICAN DEVELOPMENT FUND

17

revised 2016 and its Directives, or any acceptable revision made thereto and acceptable to

the Bank, using the national Standard Bidding Documents (SSDs) or other Solicitation

Documents agreed during project negotiations” for various group of transactions to be

entailed under the project.

4.3.2 Procurement Risks and Capacity Assessment (PRCA): the assessment of procurement

risks at the Country, Sector, and Project levels and of procurement capacity at the Executing

Agencies (EAs) (i.e. Tanzania Petroleum Development Corporation (TPDC) for the main land

and Ministry of Finance and Planning for Zanzibar), were undertaken for the project and the

findings have informed the decisions on the procurement regimes, Borrower Procurement

System (BPS) and Bank Procurement Methods and Procedures (BPP), be used for specific

transactions or groups of similar transactions under the project. The details of risks, mitigation

measures have been included in the Procurement Technical Annex B5.

4.4 Monitoring and Evaluation

4.4.1 The project is scheduled for implementation over a 36-month period, from

January 2017 to December 2019. This schedule is reasonable, given the scope of activities to

be implemented and project implementation capacity in Tanzania. The project task team on the

Bank side and the 2 PIUs will be responsible for project monitoring and evaluation, using the

Result Monitoring Framework (Technical Annex B7) and the project log frame. The periodic

performance assessment and result reporting will be carried out by the task team in

collaboration with the project Coordinators and the beneficiary institutions. Quarterly and

annual activity reports will also be prepared and submitted to the Bank. The Bank will undertake

monitoring of project implementation, and the use of project resources, through regular contact

with the PIUs, half yearly supervision missions and the mid-term review mission. The Bank

will also sustain regular consultations with DPs supporting GOT capacity-building under the

ongoing PFMRP IV. The Field Office, TZFO, being on the ground, will play an active role in

the coordination, country dialogue, and project supervision and monitoring. A Project

Completion Report will be prepared to evaluate progress against outputs and outcomes and

draw lessons for possible follow-up operations. Table 4.2 presents the Project Implementation

and Monitoring Schedule. Table 4.1: Project Implementation Schedule

Task Responsible Party Start Date

Loan Approval ADF March 2017

Loan Effectiveness ADF/GOT April2017

Project Launching ADF/GOT May 2017

Procurement of goods and services GOT June2017

Technical assistance and training program GOT July2017

Annual Audit Report GOT March 2018

Supervision Mission ADFGOT September 2017

Mid-term Review ADF/GOT June, 2018

Project Completion Report ADF/GOT June, 2020

4.5 Governance

4.5.1 Financial management of the proposed project will be carried out by the PIU under

the supervision of the Chief Executive Officer TPDC for the Mainland Component. For

the Zanzibar Component, this task will be carried out by the PIU under the supervision of the

MoF Principal Secretary. A Steering Committee for the Mainland Component will be

established under Deputy Permanent Secretary of MEM, comprising representatives of the

beneficiaries. Anexisting Steering Committee on the Zanzibar side under the Principal

Page 27: AFRICAN DEVELOPMENT FUND

18

Secretary, Ministry of Finance, will be used. The 2 PIUs will prepare their respective manuals

of administrative, financial and accounting procedures. Accounting records will be kept,

presenting project expenditure by component, category and source of finance. The project

accounts will be audited annually by the Controller and Auditor Generals (CAG).

4.6 Sustainability

4.6.1 The sustainability of the proposed project will, first and foremost, be anchored on

GOT’s strong commitment to developing a stable legal, regulatory and institutional

framework, as well negotiating balanced constracts while undertaking consultations with

private stakeholders as well as civil society. A key element of the project design is a strong

capacity building and knowledge transfer dimension. This will help ensure that adequate

capacity is built across Government during the project’s implementation phase. In addition, the

proposed project will finance certain activities, such as the development of regulations,

guidelines and reference manuals, which will guide and inform the day-to-day work of public

officials. The regulatory body for the petroleum sector (PURA) will also be established in the

context of this project. In addition, achieving a sound and balanced negotiation process will

lead to balanced agreements with international investors that will help sustain the development

of the sector. Finally, the project envisages regular consultations with the private sector and

civil society in order to take their views into account and promote an inclusive decision making

process.

4.7 Risk Management

4.7.1 The potential risks and mitigation measures for the project are summarized in Table 4.2.

below: Table 4.2: Risks and Mitigation Measures

Risks Probability/

Impact

Mitigation Measures

Risk 1: Implementation capacity constraints: Lack of

requisite skills in the natural resources sector could slow down

the pace of implementation.

Medium/high GoT is giving priority to the natural resources sector

and has an experienced team in MEM dedicated to

this sector.

Risk 2: Fiduciary risk. Although Tanzania has made good

progress in strengthening institutions and addressing

corruption, weaknesses still remain, which may pose a risk.

Low/medium The Bank’s on-going ISPGG III, and the PFMRP IV

will improve the fiduciary environment, assist in

addressing institutional weaknesses and contribute to

the fight against corruption.

Risk 3: Lack of commitments to reforms: Sustained support

at the highest level of Government is required for the success

of reforms in the domestic resources mobilization and natural

resource sector. Meanwhile, GoT long processes may impact

on the implementation process.

Low/medium Continuous dialogue between GoT, the Bank and

Development Partners, would help to ensure

sustained commitment to these important reforms

4.8 Knowledge Management

4.8.1 The proposed project will build knowledge, and develop skills, in regulating,

overseeing and monitoring the natural resources sector. The implementation of the project

will strengthen governance in the natural resources sector by (i) training staff in regulatory

issues; (ii) enhancing knowledge of the industry to promote knowledge based policy making;

and (iii) developing various important regulations, guidelines and manuals to guide and inform

the work of public officials. Knowledge will also be acquired through skill transfer by external

experts, and study tours to appropriate institutions in other countries. In addition, sensitisation

and public awareness workshops will be undertaken on issues relating to the development of

the gas sector with specific emphasis on local content policies and domestication of the

Page 28: AFRICAN DEVELOPMENT FUND

19

resources. As a consequence the knowledge base on the sector will increase, not only among

public servants but also the private sector and civil society at large. This is particularly

important in the natural resources sector that creates important expectations which are

sometimes not realistic due to lack of reliable information on the sector.

V – LEGAL INSTRUMENTS AND AUTHORITY

5.1 Legal Instrument

5.1.1 An ADF Loan will be used to finance this proposed project, governed by a Loan

Agreement between the United Republic of Tanzania and the African Development Fund.

5.2 A. Conditions Associated with Bank’s Intervention

5.2.1 Prior Action to be fulfilled before submission of the the Financing Proposal to the Board:

Designation of two Project Coordination Units, one for Tanzania Mainland and the other for

Zanzibar (evidenced by a letter sent to the Bank by the Government).

5.2.2 Conditions Precedent to Entry into Force: The entry into force of the Loan

Agreement shall be subject to the fulfilment by the Borrower of the applicable provisions of

section 12.01 of the General Conditions Applicable to Loan Agreements and Guarantee

Agreements of the African Development Fund.

5.2.3 B. Conditions Precedent to First Disbursement: The first disbursement of the loan

shall be conditional upon the entry into force of the Loan Agreement, and the Borrower

providing evidence of the fulfilment of the following condition, in form and substance satisfactory

to the Fund: Opening by each Executing Agency at a bank or banks acceptable to the Fund of

two Special Accounts (one denominated in USD and the other in Tanzania Shillings). The

opening of such accounts will be evidenced by letters from the bank(s) in which the accounts

have been opened, confirming that the said accounts have been opened, and providing the

account numbers.

5.3 Undertakings of the Borrower

5.3.1 The Borrower undertakes tocarry out and cause its contractors to carry out the Project in

accordance with: (i) the Fund’s rules and procedures; and (ii) national legislation; and (iii)

submit on a quarterly basis a progress report acceptable to the Fund, on the status of

implementation of the Project

5.4 Compliance with Bank Policies

5.4.1 This project complies with all applicable Bank policies.

VI. RECOMMENDATION

6.1.1 Management recommends that the Board of Directors approve an ADF Loan not

exceeding UA 19.58 million to the United Republic of Tanzania for the purposes of, and subject

to, the conditions stipulated in this report.

Page 29: AFRICAN DEVELOPMENT FUND

- 1 -

APPENDIX 1: Tanzania: Selected Macroeconomic Indicators

Indicators Unit 2000 2011 2012 2013 2014 2015 (e) 2016 (p)

National Accounts

GNI at Current Prices Million US $ 10,537 33,929 36,971 42,179 48,195 ... ...

GNI per Capita US$ 310 720 760 840 930 ... ...

GDP at Current Prices Million US $ 10,186 33,562 38,809 44,333 48,030 47,382 51,410

GDP at 2000 Constant prices Million US $ 10,186 21,163 22,251 23,868 25,530 27,329 29,295

Real GDP Growth Rate % 4.9 7.9 5.1 7.3 7.0 7.0 7.2

Real per Capita GDP Growth Rate % 2.3 4.5 1.8 3.9 3.6 3.7 3.9

Gross Domestic Investment % GDP 16.8 33.2 28.5 30.3 31.0 28.7 29.9

Public Investment % GDP 5.7 6.2 6.4 5.5 4.8 4.8 5.4

Private Investment % GDP 11.2 27.1 22.1 24.9 26.2 23.9 24.5

Gross National Savings % GDP 10.8 13.9 13.2 11.6 13.6 15.4 17.2

Prices and Money

Inflation (CPI) % 6.0 12.7 16.0 7.9 6.1 5.6 5.9

Exchange Rate (Annual Average) local currency/US$ 800.4 1,572.1 1,583.0 1,600.4 1,654.0 1,979.7 2,091.2

Monetary Growth (M2) % 61.1 16.0 12.1 10.4 16.7 14.6 ...

Money and Quasi Money as % of GDP % 24.1 34.6 33.3 31.8 33.1 32.2 ...

Government Finance

Total Revenue and Grants % GDP 13.8 15.4 16.1 15.3 15.4 12.4 11.8

Total Expenditure and Net Lending % GDP 15.2 20.2 19.1 20.1 18.7 15.7 15.4

Overall Deficit (-) / Surplus (+) % GDP -1.4 -4.6 -3.0 -4.8 -3.4 -3.9 -4.4

External Sector

Exports Volume Growth (Goods) % 27.5 -11.3 2.3 3.9 6.4 3.9 6.9

Imports Volume Growth (Goods) % -3.0 17.7 11.3 3.9 8.0 4.0 3.3

Terms of Trade Growth % -3.8 262.6 2.5 -3.2 -4.2 -2.9 -1.0

Current Account Balance Million US $ -364 -2,871 -2,396 -4,566 -4,947 -4,453 -4,206

Current Account Balance % GDP -3.6 -8.6 -6.2 -10.3 -10.3 -9.4 -8.2

External Reserves months of imports 5.5 3.9 3.8 4.2 3.9 3.8 ...

Debt and Financial Flows

Debt Service % exports 17.4 3.2 2.8 2.9 3.8 5.0 5.6

External Debt % GDP 70.2 25.7 25.9 25.9 28.7 29.8 29.3

Net Total Financial Flows Million US $ 1,229 2,437 2,848 3,641 3,375 ... ...

Net Official Development Assistance Million US $ 1,064 2,440 2,823 3,431 2,648 ... ...

Net Foreign Direct Investment Million US $ 282 1,229 1,800 2,131 2,142 ... ...

Source : AfDB Statistics Department; IMF: World Economic Outlook, October 2015 and International Financial Statistics, October 2015;

AfDB Statistics Department: Development Data Portal Database, March 2016. United Nations: OECD, Reporting System Division.

Notes: … Data Not Available ( e ) Estimations ( p ) Projections Last Update: April 2016

0.0

1.0

2.0

3.0

4.0

5.0

6.0

7.0

8.0

9.0

200

4

200

5

200

6

200

7

200

8

200

9

201

0

201

1

201

2

201

3

201

4

201

5

201

6

%

Real GDP Growth Rate, 2004-2016

0

2

4

6

8

10

12

14

16

18

2004

2005

2006

2007

2008

2009

2010

2011

2012

2013

2014

2015

2016

Inflation (CPI), 2004-2016

-12.0

-10.0

-8.0

-6.0

-4.0

-2.0

0.0

2,004

2,005

2,006

2,007

2,008

2,009

2,010

2,011

2,012

2,013

2,014

2,015

2,016

Current Account Balance as % of GDP,2004-2016

Page 30: AFRICAN DEVELOPMENT FUND

- 2 -

APPENDIX 2: Bank Group Current Portfolio in Tanzania Nov. 2016

SOURCE OF

FINANCE

APPROVAL

DATE

CLOSING DATE APPROVED

AMOUNT (UA

million)

TOTAL

DISBURSED

DISB RATE (Am t

Dis b /T o ta l Lo a n )

Marketing Infrastructure, Value Addition and Rural Finance Program

(MIVARFP)

ADF Loan 29-Jun-2011 31-Dec-2017 40.00 25.52 63.79

SUB-TOTAL (AGRICULTURE) 40.00 25.52 63.79

Tanzania Road Sector Support Programme I ADF Loan 2-Dec-2009 15-Dec-2017 152.00 126.38 83.15

Tanzania Road Sector Support Programme II ADF Loan 5-Apr-2012 31-Dec-2018 140.00 75.24 53.74

Dar es Salaam Bus Rapid Transport Infrastructure Project ADB Loan 30-Sep-2015 31-Dec-2020 69.74 0.19 0.27

AGTF 30-Sep-2015 31-Dec-2020 31.71 0.16 0.51

Transport Sector Support Program ADF Loan 26-Nov-2015 31-Oct-2021 54.00 0.60 1.11

ADB Loan 26-Nov-2015 31-Oct-2021 193.97 0.00 0.00

SUB-TOTAL (TRANSPORT) 641.42 202.58 31.58

Zanzibar Urban Water & Sanitation Project ADF Loan 19-Dec-2012 31-Dec-2017 14.00 4.36 31.13

Arusha Sustainable Water & Sanitation Delivery Project ADB Loan 16-Sep-2015 30-Jun-2020 102.83 0.06 0.06

ADF Loan 16-Sep-2015 30-Jun-2020 18.00 0.32 1.78

AGTF 16-Sep-2015 30-Jun-2020 30.07 0.04 0.14

SUB-TOTAL (WATER SUP/SANIT) 164.90 4.78 2.90

Iringa-Shinyanga Transmission Line ADF Loan 26-Oct-2010 31-Oct-2018 45.36 18.71 41.24

Scaling-Up Renewable Energy Program SCF Grant 20-Dec-2013 15-Sep-2017 0.50 0.10 20.86

SUB-TOTAL (ENERGY) 45.86 18.81 41.01

Alternative Learning and Skills Development (ALSD) II ADF Loan 29-Jun-2011 31-Dec-2017 15.00 3.74 24.93

Support to Technical Vocational Education and Training & Teacher

Education

ADF Loan 2-Apr-2014 31-Dec-2019 34.00 1.37 4.03

SUB-TOTAL (SOCIAL) 49.00 5.11 10.43

TZS Line of Credit to First National Bank Subsidiary in Tanzania (FRB

Subsidiary in TA)

ADB Loan 12-Dec-2012 31-Dec-2017 34.36 14.32 41.67

CRDB Bank Ltd Line of Credit 2015 ADB Loan 18-05-2016 85.54 0.00 0.00

SUB-TOTAL (FINANCE) 119.90 14.32 11.94

ISP for Good Governance III ADF Loan 3-Feb-2016 30-Jun-2019 12.00 0.80 6.71

SUB-TOTAL (MULTI SECTOR) 12.00 0.80 6.71

TOTAL (NATIONAL) 1073.08 271.92 25.34

East Africa Transport and Trade Facilitation (EAC) ADF Grant 29 Nov. 2006 31-Dec-2016 6.20 4.15 66.98

Arusha-Holili/Taveta-Voi Road Project ADF Loan 16-Apr-2013 31-Dec-2018 79.90 15.84 19.83

Lake Victoria Water Supply & Sanitation Programme Phase II (LVWSSP) ADF Grant 17-Dec-2010 30-Dec-2017 17.48 12.59 72.01

The EAC Payments & Settlement Systems Integration Project (EAC - PSSIP) ADF Grant 5-Dec-2012 30-Jan-2017 15.00 6.09 40.62

Regional Rusumo Hydropower ADF Loan 27-Nov-2013 31-Aug-2019 22.41 0.02 0.09

EAC Railway Sector Enhancement Project NEPAD IPPF

Grant

29-Jun-2012 20-Dec-2016 0.89 0.61 69.02

EAC Centres of Excellence Skills Technology ADF Loan 3-Oct-2014 31-Dec-2019 6.25 0.90 14.42

Kenya -Tanzania Interconnection ADF Loan 18-Feb-2015 31-Dec-2019 75.29 1.06 1.41

SUB TOTAL (MULTINATIONAL) 223.41 41.27 18.47

GRAND TOTAL (NATIONAL/MULTINATIONAL) 1296.50 313.18 24.16

FINANCE

MULTI-SECTOR

B. MULTINATIONAL OPERATIONS:

A. NATIONAL OPERATIONS:AGRICULTURE

TRANSPORT

WATER SUPPLY/SANITATION

ENERGY

SOCIAL

Page 31: AFRICAN DEVELOPMENT FUND

- 3 -

APPENDIX 3: Donor Coordination Matrix for Tanzania

Focus area Phasing IN

Focus area and Current

Chair/co ChairPhasing OUT

Some support Future Chair

FYDP II Sub sectors

AfD

B

Be

lgiu

m

Can

ada

De

nm

ark

EU

Fin

lan

d

Fran

ce (

AFD

)

Ge

rman

y

Ire

lan

d

Ital

y

Jap

an

Ko

rea

Ne

the

rlan

ds

No

rway

Swe

de

n

Swit

zerl

and

UK

(D

FID

)

UN

USA

Wo

rld

Ba

nk

(pe

nd

ing

CA

S

ap

pro

val)

Agriculture

Food and nutrition

Manufacturing

Mining

Construction

Tourism

Business environment

Environmental and Natural

Resources

Urban Planning, Housing

and Human

Settlement

Energy

Transport

Education

Skills development

Water and sanitation

Health

Poverty Reduction and

Social protection

Good Governance

Science Technology and

Innovation

Creative industry

Current Sector/thematic working

group DPG

Agriculture

Infrastructure

Education

Culture

Governance

Social Protection

Industry and Trade (PSD)

Environment, natural ressources and

Climate Change

Water

Health

Ministry for Agriculture, Livestock and

Fisheries

Ministry for Education, Science,

Technology, and Vocational Training

Ministry for

Works, Transport,

and

Communication

Ministry for Energy and

Minerals

Ministry for Water and Irrigation

Ministry in the President's Office - Regional

Administration and Local Government,

Public Service Management, and Good

Governance

Ministry in the Vice President's Office -

Union Affairs and Environment

Ministry for Education, Science,

Technology, and Vocational Training

Ministry for Health, Community

Development, Gender, the Aged, and

Children

Lead Ministry

Ministry for Industry, Trade and Investment

Ministry for Information, Culture, Artists,

and Sports

Innovation and Technology

Page 32: AFRICAN DEVELOPMENT FUND

- 4 -

Appendix IV : ANRC’s Baseline study on local content in Tanzania

In Tanzania, the ANRC is conducting a baseline study of the local content in at the request of the the

National Economic Empowerment Council (NEEC) at the Prime Minister’s office, with the role to be

responsible for local content development and management covering key sectors of the economy. This

will help the Government to identify key gaps and opportunities as well as inform future activities

including the AfDB support in the sector.

The Local Content Situation Analysis is focused on Tanzania’s oil, gas and mining sectors in order to

support NEEC. There are three phases to the situational analysis:

Phase 1 – Gather information available both publicly and privately about legislation,

policies, and key stakeholders and their roles and initiatives to promote local content.

Identify gaps and inconsistencies, drawing examples from successful initiatives that can be

replicated;

Phase 2 - Examine previous public and private work on skills gaps and supply chains. Make

key recommendations based on the gaps identified;

Phase 3 - A validation workshop will be held to confirm key findings and recommendations

and share them with relevant stakeholders.

The information found in the Phase 1 report for the local content situational analysis sets the ground

work for the more detailed Phase 2 report, which will capture more of the available knowledge

regarding local content in Tanzania’s extractive industries identify gaps in legislation and information,

and provide key recommendations to the government of Tanzania. NEEC will play an important role

in verifying the information in this report and providing feedback. After Phase 2, wider consultation

and verification will be conducted to produce the final situational analysis.

Phass 1 has just been completed and provides an overview of the sector and current challenges. While

the Mining Act of 2010 is the more out of date legislation, neither the Mining Act nor the Petroleum

Act contain hard local content policies other than PA2015 Section 219. While local content regulations

for the petroleum sector are now being developed, it is unclear whether regulations will be forthcoming

for mining as well. Additionally, both policies seem to preference Tanzanian ownership as opposed to

in-country value addition by both foreign and domestic firms.

Table 1. Key Legislation for Local Content in the Extractive Industries Mining Act, 2010 Requires that applications for a Special Mining Licence or Mining Licence contain a

procurement plan of goods and services available in the United Republic, a plan with

respect to the employment and training of citizens of Tanzania, and a succession plan for

expatriate employees

Petroleum Act,

2015

Mandates a preference for goods and services available in Tanzania. When those are not

available, they should be delivered by a company that is in joint venture with a local

company whose participating share is not less than 15%. Further requires a recruitment

and training plan and procurement plan be submitted to a newly created Petroleum

Upstream Regulatory Authority (PURA) and updated on a regular basis after the granting

of a licence and Act prescribes a new role to the Energy and Water Utilities Regulatory

Authority (EWURA) in respect to midstream and downstream petroleum and natural gas

activities.

In terms of key actors for local content policy formulation and implementation, Section E breaks these

down into government, international institutions and governments, the private sector, and civil society

(including the media and trade unions, as seen in Table 2.

Page 33: AFRICAN DEVELOPMENT FUND

- 5 -

Table 2. Key Actors for Local Content in the Extractive Industries in Tanzania Government NEEC LCD set up in Sept 2015 to promote and coordinate local content across the

national economy.

MEM Coordinates the development of energy and minerals resources in Tanzania,

setting policies, strategies and laws

TMAA Monitors and audits mining operations

EWURA Monitors and regulates the downstream and midstream petroleum sectors

PURA Monitors and regulates the upstream petroleum industry and advise o=the

Minister on local content policy

TPDC Implements petroleum exploration and development policies and participates

in exploration, development, production and distribution of oil and gas and

related services in partnership with IOCs

STAMICO Vehicle through which the government participates in mining

TNBC Facilitates dialogue between the government and private sector

VETA Coordinates, regulates, finances, promotes and provides vocational education

and training in Tanzania

International

Institutions and

Governments

World

Bank

Conducts studies on local content in Tanzania

European

Union

Funding support to NEEC for local content in non-extractive sectors

UNDP Has several projects related to education and training in Tanzania

UNIDO Works with technical institutes to support education and training programmes;

has done work on building linkages through SMEs

Norway/

Norad

Involved in several education and training initiatives; implements Oil for

Development programme in Tanzania and sponsors CMI’s ‘Tanzania as a

Future Petro-State’ project

Private Sector OGAT Industry association for IOCs in Tanzania. Involved in several local content

studies, lobbies for softer local content regulations

BG and

Statoil

Partners in the proposed Tanzania LNG plant. Together, they have been

conducting other studies of skills gaps, labour needs, and the supply chain for

the LNG plant

Achilles Provides procurement services in the form of an online cloud-based portal that

buyers and suppliers can use for managing tenders

TPSF Umbrella body of private sector in Tanzania

Civil Society VSO Involved in education, training, and skills gap analyses in Tanzania

Oxfam Advocates for transparency of contracts and supports local partners to

advocate for social and environmental safeguards and fair distribution of

natural gas revenues

AKF Operates Coastal Rural Support Programme (CRSP) in Lindi and Mtwara

Regions

ESRF Tanzanian policy research think tank that produced a baseline study in 2016

called Effective Management of the Tanzanian Natural Gas Industry for an

Inclusive and Sustainable Socio-Economic Impact

REPOA Tanzanian research institution with the mandate to contribute to the alleviation

of poverty in its multiple dimensions through research and capacity building

Policy

Forum

Network of 74 Tanzanian civil society organizations doing advocacy on oil

and gas as well as other questions of development

The report makes some preliminary conclusioorganized according to four themes: local employment,

education and training, local procurement and governance. In terms of local employment, the report

collects baseline data for petroleum and mining. The section therefore highlights the lack of clarity

about how NEEC would be able to participate in the monitoring of expatriate labour to ensure that

skills are being transferred to Tanzanians and suggests that there may be a need for NEEC to have a

formal role in the approvals process. Although there are still gaps and inconsistencies in the way data

is collected, the data already demonstrates how significant it could be to reduce Tanzania’s reliance on

foreign skilled labour in the extractive industries—both for reducing costs and encouraging greater

local participation in the sector over time.

Page 34: AFRICAN DEVELOPMENT FUND

- 6 -

For local procurement, the report discusses six key issues: 1) gaps in the legal framework for

regulation, 2) the issue of a supplier database, 3) SME development and enterprise centres, 4)

addressing the lack of capital for Tanzanian entrepreneurs, 5) support and prioritization for larger

industries, and 6) soft vs hard local content regulations. Key findings are that there is a general

weakness in PA2015 and even more so in the Mining Act 2010 in terms of promoting local content.

There is confusion about who is responsible for monitoring and enforcing local content in the minerals

sector and a lack of information about any enforcement actions taken to date. Unlike in many other

countries, there are no clauses giving Tanzanian companies or companies that domicile value-added

activities in-country preference if they are within a certain margin of the lowest bid for a tender in

either petroleum or mining. Finally, there are multiple definitions of a ‘local company’ in Tanzania.

Table 3: Key Issues in Local Content in Tanzania

Information and data

required

NEEC and the other ministries and agencies responsible for local content in the

extractive industries lack the necessary research and data to properly design and

implement local content policies. NEEC in particular lacks a department tasked with

research, data and statistics.

Sectors of economic

activity

The local capacity in various service sectors is not well-known, nor has comparative

work and engagement been done with a view toward prioritizing which sectors to focus

on in local content development. This issue affects questions about to what extent

regulations will involve hard targets, in which areas project sponsors will focus their

local content initiatives, and how to align local content policy with national development

objectives.

Involvement of

stakeholders

Currently there is a lack of coordination of stakeholders from the private sector and

international donors, as well as very little involvement of local and international civil

society in the issue of local content in oil, gas and mining. This issue affects both design

and implementation of local content, particularly on the question of monitoring.

Capacity building of local

companies

Local small and medium-sized enterprises lack the capacity, training, internal processes

and capital to participate in tenders from larger oil, gas and mining companies.

Regional local content On their own, the reserves of hydrocarbon resources in Tanzania and other countries in

East Africa lack the scale to justify the development of certain supporting service sectors

that are particularly specialized or capital intensive. There is a little coordination among

governments and agencies responsible for local content. Regional local content offers

the possibility of better economies of scale for larger Tanzanian companies offering

certain kinds of services.

Page 35: AFRICAN DEVELOPMENT FUND

- 7 -

Appendix 5: Tanzania Revenue Authority - DPs Technical Assistances and Target Areas

S/N AREA DPS AREA OF ASSISTANCE

1 Domestic

Revenue (Large

Taxpayers)

US Treasury a) Transfer Pricing b) Audit of Multinational Companies c) Audit of specialized sectors (tourism Financial

institutions, and telecommunication) d) Development of specialized Audit Guide.

DfID/HMRC* Development of Interstate Automatic information exchange

system for tax purpose

2 Domestic

Revenue

(Medium and

Small Taxpayers

US Treasury a) Review tax returns and filing procedures to simplify self-assessment

b) Audit of construction sector

IMF AFRITAC a) Development of a Compliance Management Strategy b) Development of a National Audit Plan

3 Tax

Investigation

US Treasury Develop Investigation Guide/Manual and Case Inventory

Management Information System (CIMIS)

US Treasury Transitioning of TID form audit work to criminal

investigation

4 Internal Affairs DfID/HMRC External Review of TRA Integrity and Transparency

HMRC Modernize TRA physical and digital Security

5 Internal Audit DfID/HMRC Implement Internal Audit Strategy

6 Information

Technology

DANIDA/SKAT** Design and implement integrated Enterprise Application

Architecture

Key: *HMRC – Her Majesty Revenue & Customs – UK

**SKAT – Danish Tax Authority - Denmark

Source: Tanzania Revenue Authority, June 2016

Page 36: AFRICAN DEVELOPMENT FUND

- 8 -

APPENDIX 6: Analytical Work Underpinnings

Component/Reform

Areas

Analytical Work Institution

Overall Strategic

Context

Tanzania Development Vision 2025; and

National and Zanzibar strategies for growth

and poverty reduction

MoFP

BRN Strategic Documents

Country Strategy Paper (2016-2020) AfDB and GoT

Public Service

Management

The Reforming Tanzania Public Sector

Report: An Assessment of Future Direction

(November, 2013)

GOT

Governance Governance and Corruption Survey (2014) GOT

Public Finance

Management

PFMRP IV and Action Plan (2011) MoF

PFMRP IV Mid-Term Draft Final Report,

July, 2015

GOT and PFMRP

Secretariat

2014 General Budget Support Annual

Review: Final Report, September, 2015

GOT

PEFA Assessments , 2010 and 2013 MoF

OPEV Joint PFM Evaluation Public Finance

Management Reform??? (2011)

AfDB

Development Policy Operation for Tanzania World Bank

Tanzania Revenue Authority Fourth

Corporate Plan 2013/14 – 2017/18

TRA

Fourth & Fifth Review of the IMF Policy

Support Instrument and IMF Article IV

Consultation Report, July & Oct. 2016

IMF

Tax Administration Diagnostic Tools

Assessment; March 2016.

World Bank

Natural Resources

Management

ANRC’s Baseline study on local content in

Tanzania

AfDB

Guidelines for Women’s Economic

Empowerment in Oil and Gas Industries in

Africa

AfDB

ANRC knowledge tool on local content

policy formulation

AfDB

ANRC knowledge tool capacity building for

negotiations.

AfDB

Page 37: AFRICAN DEVELOPMENT FUND

- 9 -

APPENDIX 7: Main projects of other Development Partners in the natural resources sector

NORAD Under the Oil for Development Program, NORAD has supported Tanzania to

develop the Petroleum Act 2015 and build capacity for economic modelling in the

sector. The program is currently in a new programming phase which has enabled

to exchange with AfDB to build synergies and avoid duplications. The role of the

AfDB to develop the regulatory framework is much welcome given that Statoil is

a key investor in Tanzania which creates perceived conflicts of interest for

NORAD.

JICA JICA has support GoT to develop the Natural Gas Utilization Master Plan which

is currently in finalization phase for approval. and approval phase. JICA has also

received request form the GoT to assist in formulating the domestication of gas and

distribution plan. JICA is considering short-term training sessions for different

stakeholders (mainly government officials) in Japan and Tanzania also under the

implementation of the master plan. Several exchanges between the Bank team and

JICA enabled to avoid duplications and build synergies.

World Bank The Energy Sector Capacity Building Project for Tanzania is to strengthen the

capacity of the Government of Tanzania (GoT) to develop its natural gas sub-

sector, and Public Private Partnerships (PPP) for the power generation sector. The

project has five components. Component A is petroleum policy and legal

framework. Component B is strengthening institutional sector management,

coordination and governance. Component C is education and skills development.

Component D is power generation and natural gas PPP projects capacity building.

Regular consultation has been ongoing with the Bank team over the last few years

given the Bank has also been a key DP in the energy sector.

EU The EU supports the GoT to undertake a baseline study of the local content

situation is economic sectors other than extractives, e.g. the agriculture and

tourism sector. Early coordination with the Bank team enabled to build synergies

with the ANRC preparatory study on local content in the mining and gas sectors.

Page 38: AFRICAN DEVELOPMENT FUND

- 10 -

APPENDIX 8: MAP OF TANZANIA