african development fund burkina faso ... development fund burkina faso electrification of...

30
AFRICAN DEVELOPMENT FUND BURKINA FASO ELECTRIFICATION OF SEMI-URBAN AREAS OF OUAGADOUGOU AND BOBO-DIOULASSO ONEC/ORWA/BFO DEPARTMENTS August 2016 Translated Document Public Disclosure Authorized Public Disclosure Authorized

Upload: lytram

Post on 14-Mar-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: AFRICAN DEVELOPMENT FUND BURKINA FASO ... DEVELOPMENT FUND BURKINA FASO ELECTRIFICATION OF SEMI-URBAN AREAS OF OUAGADOUGOU AND BOBO-DIOULASSO ONEC/ORWA/BFO DEPARTMENTS August 2016

AFRICAN DEVELOPMENT FUND

BURKINA FASO

ELECTRIFICATION OF SEMI-URBAN AREAS OF

OUAGADOUGOU AND BOBO-DIOULASSO

ONEC/ORWA/BFO DEPARTMENTS

August 2016

Translated Document

Pu

bli

c D

iscl

osu

re A

uth

ori

zed

Publi

c D

iscl

osu

re A

uth

ori

zed

Page 2: AFRICAN DEVELOPMENT FUND BURKINA FASO ... DEVELOPMENT FUND BURKINA FASO ELECTRIFICATION OF SEMI-URBAN AREAS OF OUAGADOUGOU AND BOBO-DIOULASSO ONEC/ORWA/BFO DEPARTMENTS August 2016

TABLE OF CONTENTS

I. STRATEGIC THRUST AND RATIONALE 1

1.1. Project Linkages with Country Strategy and Objectives 1

1.2. Rationale for Bank Intervention 1

1.3. Aid Coordination 2

II. PROJECT DESCRIPTION 3

2.1. Project Description and Components 3

2.2. Technical Solution Adopted and Alternatives Explored 4

2.3. Project Type 5

2.4. Project Cost and Financial Arrangements 5

2.5. Project Area and Beneficiaries 6

2.6. Participatory Approach in Project Identification, Design and Impementation 7

2.7. Bank Group Experience and Lessons Reflected in Project Design 8

2.8. Key Perfrmance Indicators 9

III. PROJECT FEASIBILITY 9

3.1. Economic and Financial Performance 9

3.2. Environmental and Social Impact 10

IV. PROJECT IMPLEMENTATION 11

4.1. Implementation Arrangements 11

4.2. Monitoring 14

4.3. Governance 15

4.4. Sustainability 16

4.5. Risk Management 16

4.6. Knowledge Building 16

V. LEGAL FRAMEWORK 17

5.1. Legal Instrument 17

5.2. Conditions for Bank Intervention 17

5.3. Compliance with Bank Policy 18

VI. RECOMMENDATIONS 18

Annex I: Burkina Faso’s Comparative Socio-Economic Indicators

Annex II: Table of Bank Portfolio in Burkina Faso (March 2016)

Annex III: Main Related Ongoing Projects in Burkina Faso Financed by the Bank and other

Development Partners

Annex IV: Map of Project Area

Page 3: AFRICAN DEVELOPMENT FUND BURKINA FASO ... DEVELOPMENT FUND BURKINA FASO ELECTRIFICATION OF SEMI-URBAN AREAS OF OUAGADOUGOU AND BOBO-DIOULASSO ONEC/ORWA/BFO DEPARTMENTS August 2016

i

CURRENCY EQUIVALENTS March 2016

1 Unit of Account = XOF 832.1864

1 Unit of Account = EUR 1.26866

1 Unit of Account = USD 1.38131

FISCAL YEAR 1 January to 31 December

WEIGHTS AND MEASURES

1 kilometre (km) = 1,000 m

1 km² = 1,000,000 m²

1 hectare (ha) = 10 ,000 m²

1 ton = 1,000 kg

1 kilojoule (kJ) = 1,000 Joule (J)

1 kilovolt (kV) = 1,000 Volt (V)

1 kilovolt-ampere (kVA) = 1,000 Volt – Ampere (VA)

1 kilowatt (kW) = 1,000 Watt

1 Megawatt (MW) = 1,000,000 W = 1,000 kW

1 Gigawatt (GW) = 1,000,000 kW = 1,000 MW

1 kilowatt/hour (kWh) = 1,000 Watt/hour = 3,600,000 Joules (J)

1 Megawatt/hour (MWh) = 1,000,000 Wh = 1,000 kWh

1 Gigawatt/hour (GWh) = 1,000,000 kWh = 1,000 MWh

1 tonne of oil equivalent (ToE) = 41,868 Joules = 11,630 kWh

1 million tonnes of oil equivalent (MToE) = 1,000,000 ToE

Page 4: AFRICAN DEVELOPMENT FUND BURKINA FASO ... DEVELOPMENT FUND BURKINA FASO ELECTRIFICATION OF SEMI-URBAN AREAS OF OUAGADOUGOU AND BOBO-DIOULASSO ONEC/ORWA/BFO DEPARTMENTS August 2016

ii

ACRONYMS AND ABBREVIATIONS

ADF African Development Fund

AFD French Development Agency

AfDB African Development Bank

AGSDS Accelerated Growth and Sustainable Development Strategy

BD Bidding Documents

BFFO AfDB Field Office in Burkina Faso

BOAD West African Development Bank

CSD-MCE Mines, Quarries and Energy Sector Dialogue Framework

CSP Country Strategy Paper

DG-CMEF General Directorate of Control of Public Procurement and Financial Commitments

EBID ECOWAS Bank for Investment and Development

EIB European Investment Bank

ERR Economic Rate of Return

ESIA Environmental and Social Impact Assessment

ESMP Environmental and Social Management Plan

EU European Union

FD Final Design

FDE Electrification Development Fund

GDP Gross Domestic Product

HV High Voltage

ICB International Competitive Bidding

IEC Information, Education and Communication

INSD National Institute of Statistics and Demography

IPP Independent Power Producer

IRR Internal Rate of Return

IsDB Islamic Development Bank

LV Low Voltage

MCE Energy Consumption Control

MEMC Ministry of Power, Mines and Quarries

MINEFID Ministry of the Economy, Finance and Development

MV Medium Voltage

MW Megawatt

MWp Megawatt-Peak

NGO Non-Governmental Organization

NPV Net Present Value

ONEC Department of Power, Environment and Climate Change

OPsCOM Bank Operations Committee

PIU Project Implementation Unit

PNDES National Economic and Social Development Plan

POSEN Energy Sector Policy

PRIELER Grid Reinforcement and Rural Electrification Project

RMC Regional Member Country

SME Small and Medium-sized Enterprise

SMI Small and Medium-sized Industry

SONABEL National Electricity Corporation of Burkina Faso

SONABHY National Hydrocarbons Corporation of Burkina Faso

TOE Tonne of Oil Equivalent

UA Unit of Account

UNDP United Nations Development Programme

UNEV Updated Net Economic Value

USD United States Dollar

WAEMU West African Economic and Monetary Union

WB World Bank

Page 5: AFRICAN DEVELOPMENT FUND BURKINA FASO ... DEVELOPMENT FUND BURKINA FASO ELECTRIFICATION OF SEMI-URBAN AREAS OF OUAGADOUGOU AND BOBO-DIOULASSO ONEC/ORWA/BFO DEPARTMENTS August 2016

iii

PROJECT INFORMATION SHEET

BORROWER: BURKINA FASO

DONEE: BURKINA FASO

EXECUTING AGENCY: MINISTRY OF POWER, MINES AND QUARRIES

Financing Plan

Sources Amounts (in UA Million) Instrument

ADF 20.60 Loan

ADF 6.63 Grant

SONABEL 5.70 Counterpart contribution

GOVERNMENT 4.83 Counterpart contribution

TOTAL 37.76

Key ADF Financing Information

Loan Currency Unit of Account

Type of Interest Not applicable

Interest Rate Margin Not applicable

Service Commission 0.75% per year on loan amount disbursed but yet reimbursed.

Commitment Fee 0.50% of undisbursed loan amount, calculated as from 120 days after

signature of the Loan Agreement

Other Charges Nil

Maturity 40 years

Grace Period 10 years

IRR, NPV (Baseline scenario) UNEV: 3.42% ; NPV : CFAF 4.78 billion

ERR, UNEV (Baseline Scenario) ERR: 21.19% ; UNEV : CFAF 19.95 billion

Time Frame – Key Milestones (Expected)

Concept Note Approval February 2016

Project Approval September 2016

ADF Grant Effectiveness October 2016

ADF Loan Effectiveness November 2016

Completion June 2020

Closing Date/Last Disbursement December 2020

Last Repayment December 2056

Page 6: AFRICAN DEVELOPMENT FUND BURKINA FASO ... DEVELOPMENT FUND BURKINA FASO ELECTRIFICATION OF SEMI-URBAN AREAS OF OUAGADOUGOU AND BOBO-DIOULASSO ONEC/ORWA/BFO DEPARTMENTS August 2016

iv

EXECUTIVE SUMMARY

Project Overview: The Electrification Project for Semi-Urban Areas of Ouagadougou and

Bobo-Dioualasso (PEPU) is an investment project that seeks to expand the electrical networks

and establish electrical connections. The project objective is to increase the electricity access

rate in Burkina Faso, especially in the outlying districts of the above towns. Although these

towns have recorded significant population growth over the last decade, they still do not have

access to electricity. The project therefore aims to restructure and expand the medium and low-

voltage distribution networks in the country’s two largest towns, install transformer sub-

stations, and establish 17,500 connections to households. The project also comprises several

activities intended to strengthen SONABEL’s operational capacity through the procurement of

logistic resources, operating equipment, and electricity calculation software, as well as through

the training of field workers and staff in charge of conducting studies. Two studies are

scheduled under this project so as to prepare for future Bank interventions in the sector; the

total cost of the studies are estimated at UA 37.76 million. The project will be co-financed by

ADF (72%), SONABEL (15%) and the State (13%). Implementation will span a period of 48

months from 2017 to 2020.

Needs Assessment: Electricity access1 in Burkina Faso is one of the lowest in the world, with

a national rate of 18.83% in 2015 compared to the African average of 40%. The national

electricity coverage rate2 was 33.32% in 2015 and the Government intends to get out of this

situation by 2035. Indeed, the Energy Sector Policy (POSEN) 2014-2025 adopted in 2013 by

Government is built on a vision: “the energy sector of Burkina Faso, which is based on

indigenous resources and regional cooperation, provides universal access to modern energy

services and confirms its role as driver of sustainable development”. It is also based on the

vision charted by the prospective study on energy in Burkina Faso. If achieved, this vision will

lead to universal access to energy services through low-cost energy supply to the country,

greater supply of modern, environmentally-friendly and generally affordable energy to rural

areas, as well as the development of renewable sources of energy.

Bank’s Value Added: The project is largely based on the Ouagadougou Power Networks

Restructuring and Extension Study conducted in 2015. The study was financed by the Bank

with resources from an ADF grant approved in July 2010, as part of the Grid Reinforcement

and Rural Electrification Project (PRIELER) which is near completion. The study proposed

appropriate technical solutions for better structuring of the Ouagadougou power network and

best options for its expansion to satisfy the steadily-growing demand in semi-urban areas. Apart

from documents treating technical and economic aspects, the final design and bidding

documents for the electrification works in the semi-urban areas of Ouagadougou were prepared

and delivered, and this facilitated early start-up, with Bank approval, through the Advanced

Procurement Action (APA).

Knowledge Building: A monitoring-evaluation baseline situation will be established by the

executing agency to enable the Bank and other stakeholders to draw lessons from the project

implementation. The executing agency will prepare an inventory, and update information/data

sources to serve as performance or warning indicators in quarterly progress reports. Information

obtained from the monitoring-evaluation system will be compared to the results of socio-

economic surveys so as to assess the project impacts. This information will be processed by the

country and the Bank during monitoring and supervision missions.

1 Ratio between population served and the total population of the country. 2 Ratio between population living in electrified localities and the total population of the country.

Page 7: AFRICAN DEVELOPMENT FUND BURKINA FASO ... DEVELOPMENT FUND BURKINA FASO ELECTRIFICATION OF SEMI-URBAN AREAS OF OUAGADOUGOU AND BOBO-DIOULASSO ONEC/ORWA/BFO DEPARTMENTS August 2016

v

RESULTS-BASED LOGICAL FRAMEWORK Project Country and Name: Burkina Faso - Electrification Project for Semi-Urban Areas of Ouagadougou and Bobo-Dioulasso

Project Goal: To increase sustainable access to electricity so as to improve the living conditions of the population living in semi-urban areas

RESULTS CHAIN

PERFORMANCE INDICATORS Means of

Verification RISKS AND MITIGATION MEASURES

Indicators (including CSI) Baseline

Situation (2015) Targets (2020)

IMP

AC

T

Contribute to improve the living

standards of the Burkinabe

population

1. National electrification rate

2. Urban electrification rate

18.83%

59.88%

25%

71%

Reports :

MEMC

SONABEL

PNDES

OU

TC

OM

ES

1. Improvement of electricity

access in Ouagadougou and Bobo

Dioulasso

2. Jobs created

1.1 National electricity coverage rate

1.2 Number of subscribers connected to the Ouagadougou

network

1.3 Number of subscribers connected to the Bobo-Dioulasso

network

2.1 Number of permanent jobs created in the operational phase

2.2 Number of temporary jobs during the works phase

33.32%

270,306

91,692

-

-

44%

284,806

94,692

60 (15% of them

women)

350 (10% of them

women)

Reports :

MEMC

SONABEL

PNDES

Risk: Insufficient supply of electrical power to meet the additional demand generated by the

project through the new households connected to the electrical network.

Mitigation Measures: Increase in supply thanks to (i) the commissioning in 2017 of the 225-

kV Bolgatanga (Ghana) - Ouagadougou (Burkina) line with significant capacity of over 100

MW; (ii) the commissioning in 2017 of the 33MWc Zagtouli solar power plant; (iii) the

rehabilitation of existing generation plants to recover 30MW by 2017 and procurement of two

25-MW thermal generators to be installed in existing plants in Ouagadougou; (v) the

recruitment of independent power producers for the development of five solar projects of total

power of 100 MW and a thermal plant of 100 MW

OU

TP

UT

S

1. MV networks constructed

2. LV networks constructed

3. MV/LV sub-stations created

4. MV/LV sub-stations reinforced

5. Connections realized

6. Studies undertaken

7. Training sessions

8. Sundry reports

1.1. Length of underground MV networks constructed

1.2. Length of overhead MV networks constructed

2.1. Length of LV networks constructed

3.1 Number of overhead pole-mounted MV/LV sub-stations

3.2 Number of kiosk MV/LV substations

4.1 Number of MV/LV sub-stations reinforced

4.2 Number of kiosk substations upgraded to looped system

5.1 Number of connections made

6.1 Number of studies conducted

7.1 Number of workers trained

8.1 Number of project progress reports produced

8.2 Number of consulting engineer’s reports

8.3 Number of project financial audits

8.4 Number of procurement audits

-

-

-

-

-

-

-

-

-

-

-

-

-

218 km

171 km

1,147 km

189

152

20

90

17,500

2

15 including 5

women

48

15

3

2

Reports: consulting

engineer, project

progress,

supervision

missions, financial

audits, procurement

audit, etc.

Risk: SONABEL’s financial difficulties which can prevent the mobilization of its

contribution to the project financing.

Mitigation Measure: SONABEL’s financial contribution primarily consists of the

salaries/allowances of workers seconded to the project, the PIU’s operating costs (water,

electricity, telephone, fuel, vehicle maintenance, etc.) and connection works undertaken on

hired labour. Its direct financial contribution to works will be through payments spread over

about 25 months.

AC

TIK

EY

AC

TIV

ITIE

S

Components Resources/Uses

1. Electricity Infrastructure: (i) construction of underground MV networks (15 kV and 30kV); (ii) construction of overhead kiosk MV/LV

substations and strengthening of existing ones; (iii) connections with installation of prepaid metres.

2. Studies: (i) restructuration, electricity network extension and creation of Mains Control Office (BCC) at Bobo Dioulasso, including

environmental and social impact assessments; (ii) creation of a Load Dispatching Centre (CC) for the Ouagadougou distribution network.

3. Capacity building:(i) training of distribution network operators; (ii) update of PLS-CADD (electricity calculation software) and training of

studies and planning staff; (iii) procurement of network operation and maintenance equipment.

4. Project Administration and Management: (i) supervision and surveillance of network restructuring and extension works, (ii) external

financial audits ; (iii) procurement audits; (iv) procurement of supervision and operations vehicles, (iv) procurement of IT equipment and office

furniture for the project; (v) PIU operating costs, and (vi) environmental and social management of the project.

Resources (UA 37.76 million) :

ADF : UA 27.23 Million

SONABEL : UA 5.70 million

Government : UA 4.83 million

Uses (UA 37.76 million) :

Component 1 : UA 33.89 million

Component 2 : UA 1.03 million

Component 3 : UA 0.38 million

Component 4 : UA 2.46 million

Page 8: AFRICAN DEVELOPMENT FUND BURKINA FASO ... DEVELOPMENT FUND BURKINA FASO ELECTRIFICATION OF SEMI-URBAN AREAS OF OUAGADOUGOU AND BOBO-DIOULASSO ONEC/ORWA/BFO DEPARTMENTS August 2016

vi

PROJECT IMPLEMENTATION SCHEDULE

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60

APPROVAL AND EFFECTIVENESS

Board Approval of the ADF Loan and Grant

Signature of ADF Loan and Grant

Effectiveness of ADF Loan Agreement

ELECTRICAL INFRASTRUCTURE

Extension and Restructuring of Ouagadougou MV/LV networks

Recruitment of contractors

Supply of equipment, assembly and restructuring of electrical networks

Extension and restructuring of MV/LV networks of Bobo-Dioulasso

Recruitment of contractors

Supply of equipment, assembly and restructuring of networks

Connections in Ouagadougou & Bobo Dioulasso

Recruitment of suppliers and delivery of materials and metres

Installation of connections and metres

STUDIES

Recruitment of a consultancy firm

Studies on network extension and structuring and a CLDC in Bobo-Dioulasso

Study on a load dispatching centre (LDC) of the Ouagadougou distribution network

CAPACITY-BUILDING

Training

Recruitment of consultants

Supply of operating and maintenance equipment and materials

PROJECT ADMINISTRATION AND MANAGEMENT

Works control and supervision

Recruitment of Consultant Engineer

Control and supervision of restructuring and extension works

External audit of project financial statements

Recruitment of the external auditor

Performnace of financial audits

Procurement audit

Recruitment of the external auditor

Performnace of procurement audits

Procurement of IT equipment and office furniture

Procurement of 2 supervision vehicles

Environmental management of the project

Project completion

Monitoring of project implementation by the project implementation unit

D

A

B

C

2019 2020DESCRIPTION

2016 2017 2018

Page 9: AFRICAN DEVELOPMENT FUND BURKINA FASO ... DEVELOPMENT FUND BURKINA FASO ELECTRIFICATION OF SEMI-URBAN AREAS OF OUAGADOUGOU AND BOBO-DIOULASSO ONEC/ORWA/BFO DEPARTMENTS August 2016

1

REPORT AND RECOMMENDATIONS BY MANAGEMENT TO THE BOARD OF

DIRECTORS CONCERNING A PROPOSAL TO AWARD AN ADF LOAN AND AN

ADF GRANT TO BURKINA FASO TO THE FINANCE THE ELECTRIFICATION

PROJECT FOR SEMI-URBAN AREAS OF OUAGADOUGOU AND BOBO-

DIOULASSO (PEPU)

Management hereby submits this report and recommendations concerning a proposal to award

an ADF loan of UA 20.60 million and an ADF grant of UA 6.63 million to the Government of

Burkina Faso to finance the Electrification Project for Semi-Urban Areas of Ouagadougou and

Bobo-Dioulasso (PEPU).

I. STRATEGIC THRUST AND RATIONALE

1.1. Project Linkages with Country Strategy and Objectives

1.1.1. The project is in line with the Accelerated Growth and Sustainable Development

Strategy (AGSDS) 2011-20153 adopted end-2010, whose objective is to achieve robust,

sustained and quality growth that will not only have a bandwagon effect on the level of

improvement of incomes and overall living standards, but will also comply with the principles

of sustainable development. The project is also consistent with Burkina Faso’s new reference

framework for development – the National Economic and Social Development Plan (PNDES)

2016-2020 that is being adopted. The PNDES focuses on three (3) strategic areas, with the

overall goal of structural transformation of the national economy for strong inclusive growth.

Furthermore, the project is specifically aligned on the strategic area which targets the

development of infrastructure that can structurally transform the economy and foster job-

creation, especially in the energy sector. It is also consistent with the Bank’s Country Strategy

Paper (CSP 2012-2016) for Burkina Faso, whose first pillar is the development of

transformative infrastructure that supports growth.

1.1.2. Electricity access in Burkina Faso is one of the lowest in Africa, with about 18.83% at

national level, compared to the average of 40% in Africa and 32% in Sub-Saharan Africa.

Electricity is still inaccessible to the vast majority of people in Burkina Faso, especially those

living in semi-urban and rural areas where over 73% of the country’s total population is

concentrated as against 23% in urban areas. The Energy Sector Policy (POSEN), adopted by

the Government in 2013 with the overall goal of making energy accessible to all the people, is

built on a vision: “the energy sector of Burkina Faso, which is based on indigenous resources

and regional cooperation, provides universal access to modern energy services and confirms

its role as driver of sustainable development”. The vision is also based on the vision charted

by the prospective study on energy conducted in Burkina Faso in 2009, which outlines the

country’s major plans for the sector by 2035. The project will help to achieve the POSEN

objective of increasing the electricity access rate to 60% by 2025.

1.2. Rationale for Bank Involvement

1.2.1 The first rationale for Bank involvement is that of ensuring project compliance with

the Bank’s 2012-2016 CSP for Burkina Faso. It is included in the Bank’s indicative operations

programme for the country during the 2012-2016 CSP period. It will contribute not only to

achieving the goals of the CSP’s first pillar related to the development of growth-support

infrastructure, but also to achieving the goals expected under the second pillar related to

governance, taking into account its inclusive scope. Indeed, it will help to satisfy an ever-

growing, pressing social demand in the semi-urban districts of Ouagadougou and Bobo-

3 The implementation of AGSDS 2010-2015 was extended to the first half of 2016 until finalization at end-July 2016 of the new reference

framework for development – the National Economic and Social Development Plan (PNDES) 2016-2020.

Page 10: AFRICAN DEVELOPMENT FUND BURKINA FASO ... DEVELOPMENT FUND BURKINA FASO ELECTRIFICATION OF SEMI-URBAN AREAS OF OUAGADOUGOU AND BOBO-DIOULASSO ONEC/ORWA/BFO DEPARTMENTS August 2016

2

Dioulasso which, despite the significant population growth recorded over the last decade, still

do not benefit from basic social services, including electricity. Since the project stems from a

Bank-financed study nearing completion, it ensures continuity and complementarity with the

Bank’s energy sector interventions in Burkina Faso.

1.2.2 The project is consistent with the Bank’s Ten-Year Strategy 2013-2022 as it is in line

with its operational pillar for development of durable infrastructure capable of improving

energy security. The project is also in line with the “High-5” – five major priority objectives

defined by the Bank in 2015 to reinforce and accelerate the impacts obtained from the

implementation and development of the Bank’s Ten-Year Strategy. Specifically, it will

contribute to the achievement of the following three (3) priority objectives: (i) light up and

power Africa; (ii) industrialize Africa (making electrical power available for the creation of

small and medium-sized industries); and (iii) improve the quality of life of Africans. It will also

help to implement the Bank’s Energy Sector Policy approved in 2012, which has a two-fold

objective: (i) support efforts of Regional Member Countries (RMC) to improve access for the

population and production sectors to modern, reliable and affordable energy infrastructure and

services; and (ii) assist RMCs to develop an energy sector that is viable at the social, economic

and environmental levels. This financing proposal by the Bank is also justified because it is

aligned on the Bank’s Strategy for a New Deal on Energy for Africa approved in 2016 and

mainly aimed at ensuring universal access to energy by 2025. The project will also help to

achieve the objectives of flagship Programme No. 7 of this Strategy to promote access

programmes at the bottom of the pyramid.

1.2.3 In synergy with the Energy Sector Budget Support Programme (PASE), this operation

will help to implement the commitments contained in the performance contract signed in June

2015 by the State and SONABEL for the 2015-2019 period, which was one of the measures

precedent to the Bank’s approval of the programme in July 2015. The main commitments are:

(i) improvement of the technical performance; (ii) continuation of power network extension to

rural and semi-urban areas; (ii) improved access to electricity through 250,000 new connections

during the contract period ; and (iii) State onlending of grants and loans under the same

conditions stipulated in agreements signed between the State and Technical and Financial

Partners. Apart from expanding the power network to semi-urban areas, the project will also

build the capacity of SONABEL staff in charge of network management, operation and

maintenance. Two studies will be conducted to create two (2) remotely-controlled load

dispatching centres for the networks in Ouagadougou and Bobo-Dioulasso. These centres,

which are the best technical network management tools, will help to significantly boost service

quality in terms of electric power supply.

1.3. Aid Coordination

1.3.1 Several development partners (bilateral and multilateral) are involved in the energy

sector in Burkina Faso. Apart from the AfDB Group, the main development partners are AFD,

WB, EIB, IsDB, BOAD, EU and India. The table below summarizes the volume of power sector

investments over the past five years.

Page 11: AFRICAN DEVELOPMENT FUND BURKINA FASO ... DEVELOPMENT FUND BURKINA FASO ELECTRIFICATION OF SEMI-URBAN AREAS OF OUAGADOUGOU AND BOBO-DIOULASSO ONEC/ORWA/BFO DEPARTMENTS August 2016

3

UA 303.96 M

(100%)

Sub-sector Scale

GDP Exports Manpower

Electric Power N.A. 0% N.A.

Stakeholders – Annual Public Expenditure (average) 2010-2015

Government Donors - AfDB

- World Bank

- AFD

- EIB

- European Union

- Eximbank India

- IsDB

- Others

15%

23%

19%

12%

6%

5%

2%

1%

UA 50.67 M

(17%)

UA 253.29 M

(83%)

Aid Coordination Level

Existence of thematic working groups Yes

Existence of a global sector programme Yes

Bank’s role in aid coordination Member

1.3.2 In compliance with the mechanism for coordinating and supervising the

implementation of Burkina Faso’s Accelerated Growth and Sustainable Development Strategy

(AGSDS) 2011-2015, a Mines, Quarries, Energy Sector Dialogue Framework (CSD-MCE) has

been established to supervise the implementation of Mining Sector Policies (POSEM) and

Energy Sector Policies (POSEN). It is chaired by the Minister of Energy, Mines and Quarries,

and brings together all stakeholders operating in these sectors, namely: Government

departments at central and decentralized levels, the private sector, civil society, local

authorities, and Technical and Financial Partners (TFP).

1.3.3 Since its establishment in 2006, the Burkina Faso Field Office (BFFO) has played a

key role in strengthening dialogue with the Government and development partners in the

country. The Field Office participates in CSD-MCE activities. To ensure coherence and

complementarity of interventions, project preparation and appraisal missions held meetings

with the sector TFPs represented at Ouagadougou.

II. PROJECT DESCRIPTION

2.1 Project Description and Components

2.1.1 The project development objective is to increase electricity access in Burkina Faso,

specifically in the semi-urban areas of Ouagadougou and Bobo Dioulasso. The project aims to

restructure and strengthen electricity distribution networks in these two towns and expand them

to semi-urban areas by: (i) constructing new MV and LV lines; (ii) creating new MV/LV

transformer sub-stations and strengthening existing ones; (iii) upgrading kiosk sub-stations

from the radial (single power supply) to the loop (dual power supply) distribution system; and

(iv) establishing 17,500 connections to new households.

2.1.2 The project has four components as detailed below.

Table 2.1

Project Components (Amounts in UA Million)

No. Component

Name

Cost

Estimate Description of Components

A Infrastructure 33.89

A Ouagadougou :

(i) Installation of 217 km MV underground network; (ii) Construction of

150-km overhead network ; (iii) Construction of 996-km LV overhead

network; (iv) Creation of 184 pole-mounted MV/LV overhead sub-stations;

(v) Creation of 148 pad-mounted kiosk MV/LV sub-stations ; (vi)

Page 12: AFRICAN DEVELOPMENT FUND BURKINA FASO ... DEVELOPMENT FUND BURKINA FASO ELECTRIFICATION OF SEMI-URBAN AREAS OF OUAGADOUGOU AND BOBO-DIOULASSO ONEC/ORWA/BFO DEPARTMENTS August 2016

4

Reinforcement of 20 existing kiosk MV/LV sub-stations; (vii) Upgrade of

90 kiosk sub-stations from the radial to the loop distribution system; and

(viii) Establishment of 14,500 connections

A Bobo-Dioulasso :

(i) Installation of 0.5-km MV underground network; (ii) Construction of 21-

km MV overhead network; (iii) Construction of 151-km LV overhead

network; (iv) Creation of 5 pole-mounted MV/LV overhead sub-stations;

(v) Creation of 4 kiosk MV/LV sub-stations; and (vi) Establishment of 3,000

connections.

B Studies 1.03

(i) Conduct of study on restructuring and extension of electricity networks

and creation of a central load dispatching office (CLDO) in Bobo-Dioulasso

(including ESIAs); and (ii) Conduct of study on a load dispatching centre

(LDC) in Ouagadougou.

C Capacity

building 0.38

(i) Staff training on the operation of distribution networks; (ii) Update of

SONABEL’s calculation software (PLS – CADD) and training of staff in

charge of studies and planning; and (iii) Procurement of operating and

network maintenance equipment.

D

Project

Administration

and

Management

2.46

(i) Works control and supervision; (ii) External audit of project financial

statements; (iii) External audit of procurements; (iv) Procurement of IT

equipment and office furniture; (v) Procurement of two project supervision

vehicles; (vi) Environmental and social management of the project; (vii)

Operating costs of the Project Implementation Unit; and (viii) Project staff

costs and allowances; and (ix) Monitoring-evaluation of the project’s socio-

economic impact.

Total Project Cost 37.76

2.2 Technical Solution Adopted and Alternatives Explored

2.2.1 With respect to electricity supply, given the nature of infrastructure to be constructed

in semi-urban areas, the option selected was to connect these areas to the existing power

networks in Ouagadougou and Bobo-Dioulasso. This solution is consistent with the option

taken by Burkina Faso to develop transport and electricity distribution networks. The aim is to

ensure gradual coverage of the national territory by a unified national grid that is linked to those

of neighbouring countries. This power network development strategy will allow for further

pooling and sharing of available electric power among the regions of the country, as well as

reduce the relatively high KWh cost price by using a more economical energy mix, placing in

cold reserve all large heavy fuel thermal plants and downgrading small isolated diesel

generation plants. This energy mix will comprise cheap energy: (i) imported from neighbouring

countries mainly Cote d’Ivoire and Ghana, which accounted for 36% of the supply mix in 2014;

(ii) generated locally by the Kompienga (14 MW) and Bagré (16 MW) hydropower dams; and

(iii) generated by the Zagtouli (33 MWp) and Ziga (1.3 MWp) photovoltaic solar plants being

developed, in addition to five solar power projects with total power of 100 MWp, through the

recruitment of private power producers.

2.2.2 With regard to works design, the option selected was the construction of MV (medium

voltage) overhead lines with “flag-shaped” arms using consoles or vertically arranged inclined

arms. Configuration variants were envisaged, but not selected for the following reasons.

Table 2.2

Alternatives Explored and Reasons for their Rejection

Alternative Solution Brief Description Reasons for Rejection

MV overhead blanket

vault lines

Construct MV overhead lines using

blanket vault outfittings

Makes it impossible to reduce the works right-

of-way at ground level and to facilitate

compliance with the safety distances to

buildings situated close to the passage corridor

of lines.

MV overhead

alternating lines

Construct MV overhead lines using

alternately arranged inclined arms

Page 13: AFRICAN DEVELOPMENT FUND BURKINA FASO ... DEVELOPMENT FUND BURKINA FASO ELECTRIFICATION OF SEMI-URBAN AREAS OF OUAGADOUGOU AND BOBO-DIOULASSO ONEC/ORWA/BFO DEPARTMENTS August 2016

5

2.3 Project Type

2.3.1 The electrification project for semi-urban areas in Ouagadougou and Bobo-Dioulasso

is an investment operation which concerns the construction of power distribution networks in

these two towns. The financing instrument proposed comprises an ADF loan and an ADF grant

to be awarded to the Government of Burkina Faso.

2.4 Project Cost and Financing Arrangements

2.4.1 The total project cost, exclusive of tax and customs duty, is estimated at UA 37.76

million, comprising UA 32.28 million in foreign exchange (85%) and UA 5.48 million in local

currency (15%). The estimate is based on updated unit prices of similar supplies and works in

recent bid invitations published by SONABEL. It includes 5% provision for physical and

technical contingencies, and 5% for price escalation. The project costs by component, source

of financing, and expenditure category are presented in the tables below. The conversion rates

used are those indicated on page (i).

Table 2.3

Project Cost Estimate by Component (in UA Million)

Components Foreign

Exchange

Cost

Local Currency

Cost

Total Cost % Foreign

Exchange

Infrastructure 27.73 3.08 30.81 90%

Studies 0.65 0.28 0.94 70%

Capacity building 0.24 0.10 0.34 70%

Project administration and management 0.72 1.52 2.24 32%

Total Base Cost 29.34 4.98 34.32 85%

Physical contingencies 1.47 0.25 1.72 85%

Price escalation 1.47 1.47 1.72 85%

Total Project Cost 32.28 5.48 37.76 85%

2.4.2 The project is cofinanced by the Bank, the State and SONABEL. The Bank’s financing

amounting to UA 27.23 million, or 72% of the total project cost, will comprise an ADF loan of

UA 20.60 million and an ADF grant of UA 6.63 million. Key ADF financing information is

given on page (iii). The rest of the project financing, equivalent to UA 10.53 million, will come

from SONABEL and the Government.

Table 2.4

Project Sources of Financing (in UA Million)

Sources of Financing Foreign

Exchange

Local Currency Total % total

ADF 24.01 3.22 27.23 72%

SONABEL 4.06 1.64 5.70 15%

GOVERNMENT 4.21 0.62 4.83 13%

Total Project Cost 32.28 5.48 37.76 100%

2.4.3 The project cost by expenditure category is as follows:

Table 2.5

Project Cost by Expenditure Category (UA Million)

Expenditure Categories Foreign

Exchange Cost

Local

Currency

Cost

Total Cost % Foreign

Exchange

Works 25.78 2.86 28.65 90%

Goods 2.20 0.33 2.53 87%

Services 1.36 0.58 1.94 70%

Operating costs 0.00 1.07 1.07 0%

Others 0.00 0.14 0.14 0%

Total Base Cost 29.35 4.98 34.33 85%

Physical contingencies 1.47 0.25 1.72 85%

Price escalation 1.47 0.25 1.72 85%

Total project cost 32.28 5.48 37.76 85%

Page 14: AFRICAN DEVELOPMENT FUND BURKINA FASO ... DEVELOPMENT FUND BURKINA FASO ELECTRIFICATION OF SEMI-URBAN AREAS OF OUAGADOUGOU AND BOBO-DIOULASSO ONEC/ORWA/BFO DEPARTMENTS August 2016

6

2.4.4 The project’s provisional expenditure schedule by component is as follows:

Table 2.6

Expenditure Schedule by Component (UA Million)

Components 2016 2017 2018 2019 2020 Total

Infrastructure 3.39 11.86 8.47 6.78 3.39 33.89

Studies 0.00 0.51 0.41 0.10 0.00 1.03

Capacity building 0.04 0.11 0.13 0.09 0.00 0.38

Project administration and

management

0.25 0.62 0.62 0.62 0.37 2.46

Total project cost 3.67 13.10 9.63 7.59 3.76 37.76

% of total 9.7% 34.7% 25.5% 20.1% 10.0% 100%

2.4.5 ADF resources will be used to finance part of the components related to infrastructure

and project management and all components linked to studies and capacity building. The ADF

resource allocation by expenditure category is attached as Annex B2. The total ADF loan

resources will be used for infrastructure, exclusively for the “works” expenditure category.

ADF grant resources will be used to finance all study and capacity building-related costs, and

part of the infrastructure costs.

2.5 Project Area and Beneficiaries

2.5.1 The project will be implemented in Ouagadougou and Bobo-Dioulasso municipalities,

as well as a buffer zone belonging to Saaba rural commune, close to the capital. Ouagadougou

currently has a population of about 1,906,004 people based on INSD estimates, comprising

48% male and 52% female. The urban population represents 95% of the total population. The

population growth rate is estimated at 9.8% per year, with a population density of more than

6,249 inhabitants per km². The last ten years witnessed a population explosion in Ouagadougou

compared to other localities in the region. The main cause of rural exodus, which prompts a

significant number of mostly young people to migrate to urban centres, is the search for paid

jobs or simply the attractiveness of city life. The age distribution of the population shows that

41% of the population is aged below 15 years, while the potentially active age-group (15 to 65

years) represents 66%, evidence of the capital’s youthful population. The age group above 65

years accounts for only 2.49% of the population. The population of Bobo-Dioulasso is currently

estimated at 537,728 inhabitants, 50.40% of them women. The youths (below 35 years) are in

the majority, and account for close to 57% of the population.

2.5.2 The project area (PA) covers the semi-urban areas of the above towns which, despite

the significant population growth over the past ten years, still do not have access to the electric

power network. This situation puts mounting social pressure on the public authorities and

SONABEL to electrify the well-to-do inhabited semi-urban areas. The PA covers 34,998

households, with 26,248 in Ouagadougou and 8,750 in Bobo Dioulasso, or a minimum of

222,000 potential beneficiaries, including at least 115,000 women.

2.5.3 The project’s direct beneficiaries are the 17,500 households that will be directly

connected to the electric power network thanks to the project and have access to electricity.

Several scores of schools and apprenticeship/training centres in the PA will also be directly

connected to the electricity network by the project. Furthermore, some of the many health units

in these semi-urban neighbourhoods have small conservation and sterilization equipment

(refrigerators, heaters, etc.) run intermittently on kerosene. Electricity supply to health centres

will help to significantly improve the preservation of pharmaceutical products, vaccines, blood

and other medical products. It will also facilitate the installation of new health equipment like

laboratory apparatus, minor surgery materials, and x-ray equipment. This will lead to

Page 15: AFRICAN DEVELOPMENT FUND BURKINA FASO ... DEVELOPMENT FUND BURKINA FASO ELECTRIFICATION OF SEMI-URBAN AREAS OF OUAGADOUGOU AND BOBO-DIOULASSO ONEC/ORWA/BFO DEPARTMENTS August 2016

7

improvement in staff working conditions, better conservation of medical products, and better

healthcare, that will in turn increase the attendance rate of health units.

2.5.4 In addition to the above-mentioned direct beneficiaries, the entire population living in

the semi-urban areas of Ouagadougou and Bobo Dioulasso will benefit from the project’s

indirect spinoffs, thanks especially to the improved quality of basic public social services in

these neighbourhoods (education, training, health, hygiene and sanitation, and drinking water).

Modern and more reliable energy will also be available for their proper operation. The same

also applies to small enterprises, trading stores, administrative and municipal services,

workshops and processing units (grinding mills). Introducing electricity in these

neighbourhoods will also facilitate the emergence of new income-generating activities in agro-

food processing, new information and communication technologies, masonry, maintenance and

services.

2.5.5 SONABEL will also be a direct beneficiary of the project thanks to the expansion of

its distribution network in the two major towns of the country. Its operational capacity will also

be strengthened through: (i) the training of its workers in charge of network operation, studies

and planning; and (ii) the procurement of logistical resources, as well as network operation

equipment and appliances. The expansion of electricity networks will also benefit factories and

industries established in the project area. Lastly, local enterprises specialized in electricity, fifty

(50) of which are listed in the database of the Burkina Faso Chamber of Commerce and

Industry, will also benefit from the project through works contracts and sub-contracting.

2.6 Participatory Approach in Project Identification, Design and Implementation

2.6.1 The stakeholders were consulted during the conduct of the Environmental and Social

Impact Assessment (ESIA). Public meetings were held during project preparation and appraisal

missions in the presence of local authorities (prefects, service heads and regional directors),

SONABEL, municipal authorities, local chiefs and representatives of the beneficiary

population. These sessions were organized specifically in Ouagadougou’s 3rd and 7th

administrative districts, Saaba and Boulmiougou municipalities, and Bobo-Dioulasso’s 2nd

district. The meetings showed the very high level of stakeholder support for the project. The

following concerns were expressed: (i) strengthen power generation to avoid aggravating

outages already observed; (ii) guarantee service on all roads in the districts concerned; (iii)

adopt special social connection prices to enable access for all households, especially the

vulnerable ones; (iv) equip health centres and public schools situated in less well-to-do parts of

the project area (supply of solar kits) ; (v) establish and maintain stakeholder dialogue,

consultation and negotiation; (vi) involve municipalities and associations in project

management through information, sensitization and mobilization of the population concerned,

and facilitate works implementation; and (vii) provide public lighting on all roads in the project

area.

2.6.2 SONABEL will ensure that the participatory process is maintained throughout the

project implementation. Therefore, project-related information and communication campaigns

will be organized before SONABEL starts the works and contractors will be recruited on themes

related to worksite safety. Other information campaigns on the risks associated with the use of

electricity will be organized by SONABEL prior to powering the various neighbourhoods.

Lastly, information-gathering campaigns and new subscriber censuses will be organized during

promotional household connection operations. The concerns and expectations of the population

will be gathered during these campaigns, and appropriate action taken.

Page 16: AFRICAN DEVELOPMENT FUND BURKINA FASO ... DEVELOPMENT FUND BURKINA FASO ELECTRIFICATION OF SEMI-URBAN AREAS OF OUAGADOUGOU AND BOBO-DIOULASSO ONEC/ORWA/BFO DEPARTMENTS August 2016

8

2.7 Bank Group Experience and Lessons Reflected in Project Design

2.7.1 As at 31 March 2016, the Bank’s active portfolio in Burkina comprised fifteen (15)

operations for a total amount of UA 340.81 million, with eleven (11) national projects

(including one private sector project) for UA 191.76 million (56.3%), and four (4) regional

projects for UA 149.04 million (43.7%). The infrastructure sector [(transport (46%); energy

(14%); water and sanitation (10%)] absorbs a predominant share of ongoing investments,

representing 70% of the portfolio, or UA 238.56 million. It is followed by the agricultural sector

(20%) for UA 68.16 million, and the social sector (10%) for UA 34.08 million.

2.7.2 During the last review on 30 March 2016, the performance of the Bank’s national

public portfolio was deemed satisfactory. In a portfolio of 15 operations, only one project – an

agricultural project (classified forest participatory management project) - is deemed

problematic. The energy sector recorded the best performance, followed by the transport and

social sectors. On the whole, national operations performed better than regional ones, which are

also the oldest projects in the portfolio. The cumulative portfolio disbursement rate stands at

32% with an average age of 3.1 years, indicating a relatively young portfolio. The energy sector

records the highest disbursement rate with 98%, followed by the social sector (80%), the

transport sector (22%), water and sanitation (10%), and agriculture and development (2%). No

Bank-financed energy sector operation in Burkina is behind schedule.

2.7.3 Since the start of its operations in Burkina Faso in 1970, the Bank has financed a total

of four (4) energy-sector operations. The first, approved in February 1984, concerned the

Kompienga hydropower plant (14 MW), a project whose completion report was submitted in

1991 and whose performance evaluation report was prepared in 1992. The second operation,

approved in 2002, concerned a rural electrification study that served as basis for the Grid

Reinforcement and Rural Electrification Project (PRIELER), approved by the Bank in 2010.

The latter project is near completion and will be closed in 2016. The outcomes and performance

of this project, which allowed for the electrification of 159 localities and connection to the

electricity network for 12,500 rural households, 34 health centres and 54 schools across all

regions of the country, are deemed satisfactory by the Bank and the Government. Given that

project is based on the Ouagadougou electricity network restructuring and extension study

financed by the Bank as part of the above project, there is some synergy in the Bank’s energy

sector interventions in Burkina. Lastly, the Bank’s fourth sector operation is the Energy Sector

Budget Support Programme (PASE) approved in July 2015. This emergency operation has

enabled SONABEL to have a fuel reserve today that can run its thermal plants for over 20 days.

2.7.4 The main lessons generally learned from the implementation of infrastructure projects

in Burkina Faso and similar countries are reflected in this project. Due regard has been given

to the need for an investment operation to have good quality data at entry, and specifically

ensure that appropriate studies have been conducted to facilitate project implementation. The

experience acquired during the PRIELER implementation was also taken into consideration. In

fact, although the outcomes were deemed satisfactory, the PRIELER works started behind

schedule due to the lack of some design studies during project appraisal. This delayed

preparation of BDs for electricity network supplies and works. Furthermore, the related bids

were published nearly two years after project approval. On the other hand, all the design studies

for the present project, including the BDs, were completed and available since end-2015,

allowing for early start of: (i) the process of recruitment of the Consulting Engineer for works

control and supervision in April 2016; and (ii) competitive bidding for electricity network

supplies and works in the semi-urban areas of Ouagadougou, in June 2016. Furthermore, delays

in establishing project entities, including the recruitment of key project implementation unit

staff, identified as a major constraint on project implementation in the country, were taken into

account. Indeed, this project will be implemented by the team that was already in place during

Page 17: AFRICAN DEVELOPMENT FUND BURKINA FASO ... DEVELOPMENT FUND BURKINA FASO ELECTRIFICATION OF SEMI-URBAN AREAS OF OUAGADOUGOU AND BOBO-DIOULASSO ONEC/ORWA/BFO DEPARTMENTS August 2016

9

PRIELER. The project will not only benefit from staff that are already in place and acquainted

with Bank Procedures in project management, but also from the existing offices, furniture and

operational facilities.

2.8 Main Performance Indicators

2.8.1 Project performance will be measured using results-based logical framework

indicators. The output indicators are: (i) linear distance of MV underground networks

constructed; (ii) linear distance of MV overhead networks constructed; (iii) number of kiosk

MV/LV sub-stations constructed ; (iv) number of MV/LV pole-mounted transformer sub-

stations constructed; (v) number of MV/LV sub-stations reinforced; (vi) linear distance of LV

networks constructed; (vi) number of connections established; (vii) number of studies

conducted; (viii) number of workers trained; and (ix) number of audits conducted. The outcome

indicators are: (a) the number of subscribers connected in Ouagadougou; (b) number of

subscribers connected in Bobo-Dioulasso. The project impact indicators comprise the

electricity access rate and the access rate in urban areas, to be indicated in country reports:

SONABEL, Ministries in charge of Energy and the Economy, and in periodic PNDES reviews

(performance matrix).

2.8.2 The executing agency will monitor progress towards achieving project outcomes

through the PIU. Data on project performance indicators will be submitted in: (i) periodic

progress reports that will be prepared by the consulting engineer in charge of works control and

supervision; (ii) PIU’s quarterly progress reports; (iii) SONABEL’s activity reports; (iv) Bank

supervision mission reports; and (v) project completion reports (of the Borrower and the Bank).

An analysis of the indicators will help to measure their progress and make appropriate

adjustments, if necessary, to achieve the target values.

III. PROJECT FEASIBILITY

3.1 Economic and Financial Performance

3.1.1 Project Financial and Economic Performance: This performance was analyzed

based on the internal rate of return (IRR) and economic rate of return (ERR). The IRR is

calculated using the project’s financial costs and the percentage of revenue linked to electricity

sales to new subscribers allocated to it. The ERR, on the other hand, is calculated using

economic costs (corrected capital costs of conversion factors) compared to the expected

economic benefits from electricity sales to new subscribers and the potential savings made over

the other energy sources they were using (gasoil-powered generators) prior to the project

implementation.

3.1.2 Sensitivity of the Project Financial and Economic Performance: It was analyzed

based on: (i) a 10% increase in investment costs; (ii) a 10% rise in the cost price of electricity;

and (iii) a 10% decrease in the average selling price of electricity. This analysis shows that

although the economic rate of return is sensitive to variations in a number of factors, it remains

higher than the economic capital cost estimated at 10% in the country, thus confirming the

economic viability of the project. The project performance is more sensitive to a drop in the

electricity selling prices than to the other factors studied (details attached as Annex B.7).

Table 3.1

Main Project Economic and Social Data

Baseline scenario IRR 3.42 % NPV CFAF 4.78 billion

ERR 21.19 % NPV CFAF 19.95 billion

Page 18: AFRICAN DEVELOPMENT FUND BURKINA FASO ... DEVELOPMENT FUND BURKINA FASO ELECTRIFICATION OF SEMI-URBAN AREAS OF OUAGADOUGOU AND BOBO-DIOULASSO ONEC/ORWA/BFO DEPARTMENTS August 2016

10

3.2 Environmental and Social Impact

3.2.1 Environment: On 1 June 2015, the project was classified in Category 2 given the

negative, but averagely low, environmental and social impacts identified. The Environmental

and Social Management Plan (ESMP) was completed in March 2016 and submitted for

validation, at national level, to the National Environmental Assessment Office (BUNEE) which

issued an environmental compliance certificate on 16 May 2016. The summary ESMP was

published on the Bank’s website on 1 July 2016. The main negative environmental and social

impacts concern: (i) traffic disruptions and impediments (access to residential areas,

commercial installations, etc.); (ii) the nuisance generated (atmospheric emissions,

wastes/particles, noise, etc.) by civil engineering works (trenches for underground cables,

layout of substation sites, etc.); (iii) risks of desecration or destruction of cultural heritage and

archeological remains; (iv) health and safety risks for workers and the local population during

the works and during the operation and maintenance of electricity structures to be constructed

by the project. Mitigation measures are proposed in the ESMP to avoid or, if not, minimize

these impacts; the measures are: (i) installation of construction site signs, information of the

population of the areas concerned, re-establishment of local population’s access, etc.; (ii)

implementation of measures outlined in the works site waste management plan, compliance

with working hours, etc.; (iii) implementation of proposed measures to ensure safety and

protection for workers and the local population during the works and operation phase; and (iv)

compensatory planting of trees. The cost of the ESMP measures is estimated at UA 0.15 million.

3.2.2 ESMP Implementation Monitoring and Capacity: SONABEL’s Department of

Standards, Environment and Safety (DNES) will work closely with the project control and

coordination mission to monitor the ESMP implementation. SONABEL will also ensure that

semi-annual ESMP implementation reports are submitted to the Bank. As regards capacity,

SONABEL currently has ten (10) senior officials: (i) four (4) Officers in charge of the

environmental component; (ii) three (3) for the safety component; (iii) two (2) for quality and

standards; and (iv) one (1) Head of Department. However, two senior officials of the entity will

retire in 2017, that is, during the project implementation. SONABEL has taken appropriate

steps to replace them before their departure so as to maintain the project monitoring capacity.

There are also plans under this project to increase the personal protective and safety gear of

DNES workers. Lastly, health and safety training will be offered to at least 30 SONABEL

employees who will work during the PEPU activities.

3.2.3 Climate Change: The project’s main positive environmental impact stems from the

benefits to be derived by households that have access to electricity in the semi-urban areas. The

benefits include: (i) less polluting alternatives to the use of fuelwood (firewood, charcoal) and

kerosene lamps, which currently represent the main energy source for lighting and cooking; (ii)

opportunities for processing and conserving perishable products, and thereby optimize the use

of natural resources for their production. In addition, the project will help to reduce polluting

gases generated by the many small individual generators used in the project areas. The project

will supply electricity to users (households, businesses, workshops, processing units,

administrative and municipal services, schools and health centres) from a less polluting

electricity-mix generated by: (i) the Kompienga and Bagré hydropower plants; (ii) the Zagtouli

and Ziga solar photovoltaic plants being constructed and those envisaged in the coming years

in Burkina Faso; and (iii) hydropower or gas-powered electricity imported mainly from Côte

d’Ivoire and Ghana.

3.2.4 The project is not vulnerable to climatic risks, hence its classification in Category 3 at

the climate change level. Similar installations closest to the project area (Ouagadougou and

Bobo-Dioulasso) were not affected during the flooding of September 2009. Although the risk

is low, special attention was or will be given to: (i) the choice of installation sites for kiosk sub-

Page 19: AFRICAN DEVELOPMENT FUND BURKINA FASO ... DEVELOPMENT FUND BURKINA FASO ELECTRIFICATION OF SEMI-URBAN AREAS OF OUAGADOUGOU AND BOBO-DIOULASSO ONEC/ORWA/BFO DEPARTMENTS August 2016

11

stations, avoiding floodable and submersible zones; (ii) the size of kiosk sub-station platforms

so that they will remain above water; and (iii) electric poles size to withstand the dominant

winds. As mentioned above, the less-polluting alternatives offered by the project to households

will contribute to reducing greenhouse gas emissions.

3.2.5 Gender: Women represent 52% of the population of the target districts. The

availability and affordability of energy (electricity and modern fuels) are a major concern for

women and men in the PA. The heavy dependence on traditional biomass, mainly firewood, is

compounded by unsustainable practices linked to the use of forest resources. At least 99% of

the population of the project area lack access to electricity. As such, a key priority for the

Burkinabe Authorities is to equitably and adequately empower women and men to solve the

energy poverty crisis. In that regard, they have adopted the ECOWAS Programme for Gender

Mainstreaming in Energy Access. (ECOW-GEN). The project will have no negative impact on

gender. Rather, its implementation will help to improve women’s living conditions, especially

through: (i) the access of at least 115,000 women to electricity; (ii) fewer losses of foodstuffs

and perishable products; (iii) lightening of burdensome domestic chores, especially the

processing of certain foodstuffs (cereals, cassava or yam) into flour thanks to grinding mills;

(iv) the potential of creating small handicraft units (sewing, transformation of agricultural

produce, etc.); and (v) improved study conditions for children. Furthermore, the project will

help to improve the working conditions of business operators in the area and create temporary

jobs that require unskilled labour from which women and youths can benefit.

3.2.6 Social: The project will directly connect 17,500 households to the electricity network.

Connections to households will be established at social promotional rates. In the semi-urban

areas of Ouagadougou and Bobo-Dioulasso, the project will benefit small and medium-sized

enterprises, petty traders, administrative and municipal services, and all basic social services

(education, training, health, hygiene and sanitation, drinking water). Social infrastructure

(schools, training centres, health centres, etc.) situated in project areas will be connected to the

electricity network, affording them access to more reliable electric power for various uses

(domestic, industrial, commercial, pumping, cultural, security, etc.). The quality of social

services in the project area will improve thanks to electricity. The project will contribute to the

promotion of recreational activities for enhanced well-being of families. People and their

property will also be safer thanks to available lighting in homes and on the streets. Introducing

electricity in these neighbourhoods will facilitate the emergence of new job-generating

activities in various fields, particularly agro-food processing, the information and

communication technologies, masonry, maintenance, sewing, embroidery, handicrafts, petty

trade and services. The project will have significant socio-economic benefits in the zones

covered. Three hundred and fifty (350) temporary jobs (10% of them for women) will be

generated during the electricity network installation and connection works. It is expected that

sixty (60) full-time jobs (15% for women) will be created in SONABEL to operate the structures

and ensure customer services for new subscribers.

3.2.7 Involuntary Resettlement: The project will not lead to any involuntary population

displacement. All works will be undertaken on public land.

IV. PROJECT IMPLEMENTATION

4.1. Implementation Arrangements

4.1.1 Institutional Implementation Arrangements: The Ministry of Energy, Mines and

Quarries will be the project executing agency, while SONABEL, to which the ADF resources

have been transferred by the Government, will be the implementation unit. SONABEL will

establish a project implementation unit identical to that of PRIELER, whose completion is

Page 20: AFRICAN DEVELOPMENT FUND BURKINA FASO ... DEVELOPMENT FUND BURKINA FASO ELECTRIFICATION OF SEMI-URBAN AREAS OF OUAGADOUGOU AND BOBO-DIOULASSO ONEC/ORWA/BFO DEPARTMENTS August 2016

12

expected in June 2016. The unit will be attached to the General Management of SONABEL.

All the PIU’s technical, administrative and financial staff will be provided by SONABEL and

seconded to it, with the exception of the internal auditor who will be appointed by the Ministry

in charge of Finance. The unit will comprise a Coordinator, two Electrical Engineers, a

Computer Engineer, a Procurement Expert, a Financial Officer, an Environmentalist, an

Administrative Clerk, an Internal Auditor, a Monitoring-Evaluation Expert, a Secretary, a

Messenger and a Driver. The Procurement Expert will be transferred to the project, where

he/she will be in charge of procurement. He/she will not perform project-related duties activities

concurrently with other activities of SONABEL as this might weigh heavily on his/her

workload.

4.1.2 The Government will transform the PIU/PRIELER into PIU/PEPU, and maintain the

project implementation staff who not only have the capacity and good knowledge of Bank Rules

and Procedures, but have also implemented the previous project (PRIELER) to the satisfaction

of the Bank and the Government. The project staff will receive allowances provided for by

national regulations. Furthermore, the Government will endeavour to transfer to PEPU, the

movable and immovable property (premises, office furniture and functional IT equipment) of

PRIELER upon its closure.

4.1.3 Pursuant to General Regulations on development projects or programmes in Burkina

Faso, Ministerial orders will be issued after signature of the project financing agreements with

the Bank. The Ministerial Orders are: (i) a joint MEMC/MINEFID Order on the creation,

purpose, classification, administration and operation of the project; (ii) an MEMC Order on the

creation, composition, duties, organization and functioning of the Project Steering Committee;

and (iii) an MEMC Order on the creation, composition, duties, organization and operation of

the Project Implementation Unit which will be located within SONABEL; and (iv) an MEMC

Order to appoint the Project Coordinator. The Steering Committee will be chaired by the

representative of the Ministry in charge of Energy, and will comprise representatives from

Ministries involved in the project implementation, namely the Ministries in charge of Finance

and Territorial Administration, as well as SONABEL. Submission to the Bank of the above

draft orders will be a condition for the presentation of PEPU to the ADF Board. Submission to

the Bank of the final orders and evidence of appointment of the project management team will

be a condition precedent to the first disbursement of ADF resources.

4.1.4 Under the supervision of SONABEL General Management, the Project Coordinator

will implement and regularly monitor project activities, as well as manage various contracts.

He/she will be provided with the technical and management resources required for the technical,

administrative and financial management of the project. The Steering Committee will meet on

a semi-annual basis to: (i) consider the project implementation plan, periodic progress and

financial reports, programmes of activities, the project’s budget and the procurement plan; (ii)

ensure the implementation of its recommendations and those of project supervision, monitoring

and audit missions; (iii) assess the Project Coordinator’s performance, in line with his/her

mission letter; (iv) make recommendations for the attention of the Project Coordinator; (v)

approve the financial statements of the project; and (vi) examine any matter submitted for its

consideration.

4.1.5 Procurement Arrangements: Goods, works and services financed by the Bank under

this project will be procured in accordance with the new Bank Procurement Policy approved on

14 October 2015 and effective as from 1 January 2016, as follows:

national procurement system: Some clearly defined procurements will be

made in accordance with national procurement legislation (Decree No. 2008-

173/PRES/PM/MEF of 16 April 2008 to define the general regulations

Page 21: AFRICAN DEVELOPMENT FUND BURKINA FASO ... DEVELOPMENT FUND BURKINA FASO ELECTRIFICATION OF SEMI-URBAN AREAS OF OUAGADOUGOU AND BOBO-DIOULASSO ONEC/ORWA/BFO DEPARTMENTS August 2016

13

governing public procurement and public service delegations, as amended by

Decrees No. 2012-123/PRES/PM/MEF of 2 March 2012 and No. 2013-

1148/PRES/PM/MEF of 12 December 2013) using the country’s standard

bidding documents. The procurement activities will concern: (i) extension and

restructuring works on the Bobo-Dioulasso electricity networks; (ii)

procurement of connection materials, metres, operating and maintenance

equipment, supervision vehicles, IT equipment, and office furniture; and (iii)

training programmes. Connection works, including the installation of metres,

will be undertaken by SONABEL using hired labour.

Bank’s procurement system: Some procurements above thresholds defined by

the project will be made in compliance with the Bank’s procurement methods

and procedures, using standard Bank bidding documents. Following a

Government request, approved by the Bank on 10 November 2015, the

electricity network construction works and consultancy services related to works

control and supervision will be procured through Advanced Procurement Action

(APA) in compliance with the Bank’s Procurement Rules and Procedures. The

procurement activities will concern: (i) extension and restructuring works on the

Ouagadougou electricity networks; (ii) control and supervision of extension and

restructuring works on the Ouagadougou and Bobo-Dioulasso electricity

networks; (iii) studies on electricity network restructuring and extension works,

and establishment of a central load dispatching office (CLDO) in Bobo-

Dioulasso, including ESIAs; (iv) study on the establishment of a load

dispatching centre (LDC) for the Ouagadougou distribution network; (vi)

external audits of project accounts; and (v) procurement audits.

Procurement risks and capacity building: Procurement risk at country, sector

and project levels and the executing agency’s capacity were assessed for this

project. The results of the assessment helped to determine what procurement

methods and procedures (country or Bank) to use. Appropriate impact mitigation

measures were included in this project procurement capacity building action plan

(CDAP).

4.1.6 The risk assessment, mitigation measures, procurement arrangements and the

procurement plan (PP) have been developed and attached as Annex B5.

4.1.7 Financial Management Arrangements: The PIU-PEPU’s financial management

components comprising the budget, internal audit, accounts, financial reports, flow of funds

and external audit, will be already in place at PRIELER. They will be used alongside

SONABEL’s management system so as to produce separate and enhanced financial statements

based on lessons learned from implementation of the above-mentioned project, the review of

the organizational chart and the administrative, financial and accounting procedures manual,

the complementary configuration of the management software, and staff training. The project

budget featuring all activities will be consolidated into that of the corporation, specifying the

sources of financing (ADF, State and SONABEL). Furthermore, a complete assessment of

PIU’s operating costs borne by the corporation will be conducted and charged to the project.

The project implementation unit will each year produce: (i) a work plan and an annual budget

(PTBA) to be submitted to the Steering Committee’s approval and the Bank’s no-objection

opinion; (ii) an annual budget implementation statement; and (iii) annual financial statements

to be submitted to the Steering Committee’s approval after consideration by auditors and to be

presented to the annual General Meeting for consideration of development projects and

programmes implemented in Burkina Faso. After each quarter, the project implementation unit

Page 22: AFRICAN DEVELOPMENT FUND BURKINA FASO ... DEVELOPMENT FUND BURKINA FASO ELECTRIFICATION OF SEMI-URBAN AREAS OF OUAGADOUGOU AND BOBO-DIOULASSO ONEC/ORWA/BFO DEPARTMENTS August 2016

14

will submit a financial monitoring report indicating the progress of activities, disbursements

and the general financial situation to the Bank.

4.1.8 Disbursement Arrangements: ADF resources will be disbursed pursuant to Bank rules

and procedures. Disbursements will be made using the following three methods: (i)

reimbursement method; (ii) direct payment method; and (iii) reimbursement guarantee method.

The reimbursement method will only be used in case SONABEL needs to be reimbursed

eligible expenses on ADF resources it pre-financed with the Bank’s agreement. The direct

payment method will be used for expenses incurred for works and consultancy services. The

reimbursement guarantee method, for its part, will be used exclusively for the financing of

goods imports of substantial amounts.

4.1.9 External Audit Arrangements: An independent auditor will be recruited for a non-

renewable period of three (3) years to audit project accounts on an annual basis. Audit fees will

be financed by the project’s ADF resources. The terms of reference of the audit will be approved

beforehand by the Bank. The auditor will be recruited no later than six (6) months following

project start-up. The auditor’s annual reports will be forwarded to the Bank within six (6)

months following the close of the fiscal year.

4.2. Monitoring

4.2.1 Throughout implementation, starting from the baseline situation established by

MEMC and SONABEL, all project activities will be subject to regular monitoring-evaluation:

(i) The Project Coordination will regularly monitor the implementation of all

project activities (procurement, management of various contracts, coordination

between the consulting engineer in charge of works control and supervision and

the contractor, coordination between all public structures and services

concerned, the population and other stakeholders, approval of works progress

reports, acceptance and commissioning of works undertaken, etc.) and, where

applicable, make recommendations to the Steering Committee to ensure proper

implementation of the project within specified time frames.

(ii) The project will submit progress reports to the Bank on a quarterly basis. The

reports will detail the project’s physical implementation status, its financial

implementation including commitments approved and disbursements by

component and source of financing, the main problems or constraints likely to

affect its timely implementation, as well as solutions proposed. The reports will

also include the logical framework outcomes progressively obtained and the

project indicator trends. Bank supervision mission reports, the Government’s

monitoring mission reports, the consulting engineer’s works control and

supervision monitoring reports, and the various audit reports will help to ensure

proper implementation of the project or identify constraints or delays and

undertake appropriate action for the project to be implemented on schedule and

meet its overall objectives.

(iii) Bank monitoring of the project will be through activities summarized in the table

below. These activities will be based on the implementation schedule presented

in page (vi). The project will be subject to at least two Bank supervision missions

every year. It will also be closely monitored by the Burkina Faso Field Office

(BFFO).

Page 23: AFRICAN DEVELOPMENT FUND BURKINA FASO ... DEVELOPMENT FUND BURKINA FASO ELECTRIFICATION OF SEMI-URBAN AREAS OF OUAGADOUGOU AND BOBO-DIOULASSO ONEC/ORWA/BFO DEPARTMENTS August 2016

15

(iv) At the end of the project, the Project Coordination will prepare and submit a

completion report to the Bank. In turn, the Bank will prepare its own project

completion report. A project performance assessment report will also be

prepared by the Bank to assess the project’s impacts.

Period Milestones Monitoring Activities/Feedback Loop

September 2016

– December 2016

Approval and effectiveness

of ADF Loan and Grant

- Approval and General Information Note on the project

- Notification to the Government

- Signing of ADF Loan and Grant Agreements

- Grant and Loan effectiveness

- Lifting of conditions precedent to effectiveness and first

disbursement of ADF Loan

- Project start-up

April 2016 to

December 2016

Recruitment of Consulting

Engineer for works control

and supervision

- Publication of expression of interest

- Approval of shortlist and consultation file

- Approval of bids evaluation report

- Signing of the contract

April 2016 to

March 2017

Recruitment of works

contractors

- Approval of bidding documents

- Publication of competitive bidding notice

- Approval of bids evaluation reports

- Signature of contracts

April 2017 to

September 2019

Works control and

supervision

- Approval of technical documents

- Approval of implementation-related design studies

- In-factory acceptance of electrical equipment

- Supervision of works sites and technical controls

- Technical acceptance and commissioning of works

- Preparation of periodic progress reports

April 2017- April

2019

Construction works of

electrical infrastructure

- Supply of electrical equipment and materials

- Installation of electricity networks and sub-stations

- ESMP implementation

December 2017 –

December 2018

Recruitment of suppliers and

delivery of connection

equipment and power metres

- Preparation of bidding documents

- Publication of competitive bidding notices

- Bids evaluation and signing of works contracts

- Delivery of connection materials and metres

January 2019 –

March 2020

Installation of connections in

Ouagadougou and Bobo-

Dioulasso

- State-supervised works by SONABEL

January 2017 –

December 2018

Recruitment of other

suppliers and delivery of

electricity network operation

and maintenance materials,

IT equipment, office

furniture, and vehicles

- Preparation of bidding documents

- Publication of competitive bidding notices

- Bids evaluation and signing of contracts

- Delivery of equipment, materials and vehicles

February 2017 –

June 2020

Recruitment of other

consultants and service

providers for studies,

training, financial audits and

procurement audits

- Publication of expression of interest

- Approval of shortlists and consultation files

- Approval of bids evaluation report

- Signing of the contracts

- Service provision (studies, training, audits)

June 2020 to

December 2020 Completion of project

- Borrower’s project completion report

- Bank’s project completion report

4.3. Governance

4.3.1 The socio-political events that occurred in Burkina Faso in 2014 had a negative impact

on public finance management. Dwindling budgetary resources were compounded by a

slowdown in reforms implemented under the Economic and Financial Sector Policy Action

Plan. Nevertheless, WAEMU Directives on the modernization and transparency of financial

Page 24: AFRICAN DEVELOPMENT FUND BURKINA FASO ... DEVELOPMENT FUND BURKINA FASO ELECTRIFICATION OF SEMI-URBAN AREAS OF OUAGADOUGOU AND BOBO-DIOULASSO ONEC/ORWA/BFO DEPARTMENTS August 2016

16

governance were adopted by a 2015 law. What remains is to issue enabling instruments (decrees

and orders) for their effective implementation as from 1 January 2017.

4.3.2 During project implementation, the public finance management system will

exclusively be used for including the project’s counterpart funds in the State budget. Since

SONABEL is the project executing agency, its management mechanisms will be applied, as

with the previous project (PRIELER), which was satisfactorily implemented. SONABEL is a

State-owned corporation with a Board of Directors, and applies the OHADA Uniform Acts on

commercial companies and financial and accounting management. Pursuant to the Paris

Declaration on Aid Effectiveness, especially with respect to the use of beneficiary country’s

systems, SONABEL’s financial and accounting management instruments will be used.

4.4. Sustainability

4.4.1 Project sustainability will depend on SONABEL’s ability to maintain and service the

equipment and installations that will be installed during the project, with due regard for its

financial situation in a context wherein electricity rates dating back to 2006 are lower than the

cost price of electricity. The electricity sub-sector’s financial stability is guaranteed by State

subsidies. Thanks to the PASE, which was approved by the Bank in 2015, a programme contract

for the 2015-2019 period has been signed by the State and SONABEL. It specifies the

commitments of both parties to achieve the goal of improving the electricity sub-sector status

in Burkina Faso by increasing cheap electricity imports from neighbouring countries, boosting

sales, keeping costs under control, and maintaining the financial stability of the corporation.

The corporation has enough competent technical staff to operate and regularly maintain its

electricity networks. The cost of maintaining and operating the networks (lines and sub-

stations), estimated at an average of 2.5% of the investment cost each year as from the second

year after commissioning, will be covered by the project’s expected profits (see Annex B7).

4.5. Risk Management

4.5.1 The project’s potential risks are as follows :

Risks Mitigation Measures

Insufficient supply of

electric power to meet the

additional demand

generated by the project

with the connection of

new households to the

electricity network

Increase in electricity supply thanks to the commissioning in 2017 of : (i) the 225

kV Bolgatanga (Ghana) - Ouagadougou (Burkina Faso) line, which offers the

capacity to import over 100 MW; and (ii) the 33MWp Zagtouli solar plant. In

addition, an emergency programme will be implemented to rehabilitate

SONABEL’s existing generation facilities so as to recover about 30 additional

MW, alongside procuring and installing two new thermal generators each with a

capacity of 25 MW, making a total of 50MW, and recruiting independent power

producers for five solar power projects of total power of 100 MW, and a 100MW

thermal power plant

SONABEL’s financial

difficulties, which can

prevent it from

mobilizing counterpart

funds for project

financing.

SONABEL’s financial contribution consists primarily in salaries and allowances

for its workers transferred to the project, the PIU’s operating costs (water,

electricity, telephone, fuel, vehicle maintenance, etc.), and connection-related hired

labour. The direct financial contribution to the works will be spread over about 25

months.

4.6. Knowledge Building

4.6.1 The project has made arrangements for knowledge building through training activities

for SONABEL staff in charge of operating and maintaining the electricity distribution

networks. There are also plans to update SONABEL’s calculation software (PLS-CADD) and

train workers in charge of studies and planning.

Page 25: AFRICAN DEVELOPMENT FUND BURKINA FASO ... DEVELOPMENT FUND BURKINA FASO ELECTRIFICATION OF SEMI-URBAN AREAS OF OUAGADOUGOU AND BOBO-DIOULASSO ONEC/ORWA/BFO DEPARTMENTS August 2016

17

4.6.2 Project quarterly/annual progress reports, as well as financial and procurement audit

reports, constitute sources of information on the project. The same applies to Bank supervision

mission reports and the Government’s monitoring mission reports. These reports and the project

completion report will help to draw and share lessons on the PEPU implementation. Publication

by the Bank of the project completion report and the performance review report will help to

share the knowledge acquired during implementation of the project with the Bank staff and the

public. The lessons learned will be reflected in the design of future similar Bank operations in

its Regional Member Countries.

V. LEGAL FRAMEWORK

5.1 Legal Instrument

5.1.1 For the project financing, the Bank will use an ADF loan and an ADF grant which will

be awarded to the Government of Burkina Faso.

5.2 Conditions for Bank Intervention

A) Conditions precedent to Effectiveness 5.2.1 Effectiveness of the Grant Agreement shall be subject to its signature by the Fund and

the Donee. The effectiveness of the Loan Agreement shall be subject to fulfilment, by the

Borrower and to the satisfaction of the Fund, of the conditions stipulated in Section 12.01 of

the General Conditions applicable to Loan Agreements and Guarantee Agreements of the Fund.

B) Conditions precedent to first disbursement of ADF Resources

5.2.2 In addition to effectiveness of the Grant Agreement and the Loan Agreement, the first

disbursement of ADF resources shall be subject to fulfilment, by the Borrower/Donee and to

the satisfaction of the Fund, of the following conditions :

(i) Provide the Fund with evidence of the signing, in accordance with the General

Regulations of development projects or programmes in Burkina Faso, of

Ministerial Orders or documents on: (i) the establishment of PEPU; (ii) the

establishment of the PEPU Implementation Unit (IU/PEPU); (iii) the

establishment of the Steering Committee (SC/PEPU) and appointment of its

members; and (iv) the appointment of the PEPU Coordinator and PIU/PEPU

members;

(ii) Provide the Fund with evidence of the opening of an account in the name of the

project to receive the Government counterpart contributions in the Public

Treasury.

C) Other Conditions

5.2.3 The Borrower/Donee shall, to the satisfaction of the Fund, also fulfill the following

conditions.

(i) Provide the Fund, within six months following the signing of the Loan/Grant

Agreement, with evidence of the signing of the loan/grant onlending agreement

between the State and SONABEL, based on terms and conditions similar to the

Agreement signed with the Fund.

Page 26: AFRICAN DEVELOPMENT FUND BURKINA FASO ... DEVELOPMENT FUND BURKINA FASO ELECTRIFICATION OF SEMI-URBAN AREAS OF OUAGADOUGOU AND BOBO-DIOULASSO ONEC/ORWA/BFO DEPARTMENTS August 2016

18

D) Commitments

5.2.4 The Borrower undertakes to:

(i) Implement the project and the Environmental and Social Management Plan

(ESMP), and have same implemented by the contracting parties in accordance

with national law and the recommendations, prescriptions and procedures

contained in the ESMP, as well as the relevant rules and procedures of the Fund;

and

(ii) Submit to the Fund quarterly ESMP implementation reports, including where

necessary, any deficiencies and corrective actions undertaken or to be

undertaken ; and

(iii) Submit to the Fund any document that is reasonably necessary for the project

monitoring.

5.3 Compliance with Bank Policies

5.3.1 The project complies with all the applicable Bank policies.

VI. RECOMMENDATIONS

Management recommends that the Board of Directors approve the proposal to grant an ADF

Loan of UA 20.60 million and the proposal to award an ADF Grant of UA 6.63 million to the

Government of Burkina Faso to finance the Electrification Project for Semi-Urban Areas of

Ouagadougou and Bobo-Dioulasso (PEPU), under the terms and conditions set out in this

report.

Page 27: AFRICAN DEVELOPMENT FUND BURKINA FASO ... DEVELOPMENT FUND BURKINA FASO ELECTRIFICATION OF SEMI-URBAN AREAS OF OUAGADOUGOU AND BOBO-DIOULASSO ONEC/ORWA/BFO DEPARTMENTS August 2016

I

Annex I: Burkina Faso’s Comparative Socio-Economic Indicators

YearBurkina

FasoAfrica

Develo-

ping

Countries

Develo-

ped

Countries

Basic Indicators

Area ( '000 Km²) 2014 274 30 067 80 386 53 939Total Population (millions) 2014 17,4 1 136,9 6,0 1,3Urban Population (% of Total) 2014 29,0 39,9 47,6 78,7Population Density (per Km²) 2014 63,5 37,8 73,3 24,3GNI per Capita (US $) 2013 670 2 310 4 168 39 812Labor Force Participation - Total (%) 2014 83,3 66,1 67,7 72,3Labor Force Participation - Female (%) 2014 47,3 42,8 52,9 65,1Gender -Related Dev elopment Index Value 2007-2013 0,924 0,801 0,506 0,792Human Dev elop. Index (Rank among 187 countries) 2013 181 ... ... ...Popul. Liv ing Below $ 1.25 a Day (% of Population)2008-2013 44,5 39,6 17,0 ...

Demographic Indicators

Population Grow th Rate - Total (%) 2014 2,8 2,5 1,3 0,4Population Grow th Rate - Urban (%) 2014 5,8 3,4 2,5 0,7Population < 15 y ears (%) 2014 45,3 40,8 28,2 17,0Population >= 65 y ears (%) 2014 2,4 3,5 6,3 16,3Dependency Ratio (%) 2014 89,7 62,4 54,3 50,4Sex Ratio (per 100 female) 2014 99,0 100,4 107,7 105,4Female Population 15-49 y ears (% of total population) 2014 23,2 24,0 26,0 23,0Life Ex pectancy at Birth - Total (y ears) 2014 56,7 59,6 69,2 79,3Life Ex pectancy at Birth - Female (y ears) 2014 57,3 60,7 71,2 82,3Crude Birth Rate (per 1,000) 2014 40,3 34,4 20,9 11,4Crude Death Rate (per 1,000) 2014 10,8 10,2 7,7 9,2Infant Mortality Rate (per 1,000) 2013 64,1 56,7 36,8 5,1Child Mortality Rate (per 1,000) 2013 97,6 84,0 50,2 6,1Total Fertility Rate (per w oman) 2014 5,5 4,6 2,6 1,7Maternal Mortality Rate (per 100,000) 2013 400,0 411,5 230,0 17,0Women Using Contraception (%) 2014 19,3 34,9 62,0 ...

Health & Nutrition Indicators

Phy sicians (per 100,000 people) 2004-2012 4,7 46,9 118,1 308,0Nurses (per 100,000 people)* 2004-2012 56,5 133,4 202,9 857,4Births attended by Trained Health Personnel (%) 2009-2012 65,9 50,6 67,7 ...Access to Safe Water (% of Population) 2012 81,7 67,2 87,2 99,2Healthy life ex pectancy at birth (y ears) 2012 50,0 51,3 57 69Access to Sanitation (% of Population) 2012 18,6 38,8 56,9 96,2Percent. of Adults (aged 15-49) Liv ing w ith HIV/AIDS 2013 0,9 3,7 1,2 ...Incidence of Tuberculosis (per 100,000) 2013 54,0 246,0 149,0 22,0Child Immunization Against Tuberculosis (%) 2013 96,0 84,3 90,0 ...Child Immunization Against Measles (%) 2013 82,0 76,0 82,7 93,9Underw eight Children (% of children under 5 y ears) 2005-2013 26,2 20,9 17,0 0,9Daily Calorie Supply per Capita 2011 2 655 2 618 2 335 3 503Public Ex penditure on Health (as % of GDP) 2013 3,7 2,7 3,1 7,3

Education Indicators

Gross Enrolment Ratio (%)

Primary School - Total 2011-2014 86,9 106,3 109,4 101,3 Primary School - Female 2011-2014 85,3 102,6 107,6 101,1 Secondary School - Total 2011-2014 28,4 54,3 69,0 100,2 Secondary School - Female 2011-2014 26,0 51,4 67,7 99,9Primary School Female Teaching Staff (% of Total) 2012-2014 39,5 45,1 58,1 81,6Adult literacy Rate - Total (%) 2006-2012 28,7 61,9 80,4 99,2Adult literacy Rate - Male (%) 2006-2012 36,7 70,2 85,9 99,3Adult literacy Rate - Female (%) 2006-2012 21,6 53,5 75,2 99,0Percentage of GDP Spent on Education 2009-2012 3,4 5,3 4,3 5,5

Environmental Indicators

Land Use (Arable Land as % of Total Land Area) 2012 21,9 8,8 11,8 9,2Agricultural Land (as % of land area) 2012 0,4 43,4 43,4 28,9Forest (As % of Land Area) 2012 20,2 22,1 28,3 34,9Per Capita CO2 Emissions (metric tons) 2012 0,1 1,1 3,0 11,6

Sources : AfDB Statistics Department Databases; World Bank: World Development Indicators; last update :

UNAIDS; UNSD; WHO, UNICEF, UNDP; Country Reports.

Note : n.a. : Not Applicable ; … : Data Not Available.

Burkina FasoCOMPARATIVE SOCIO-ECONOMIC INDICATORS

0

20

40

60

80

100

120

20

00

20

05

20

08

20

09

20

10

20

11

20

12

20

13

Infant Mortality Rate( Per 1000 )

Burkina Faso Africa

0

500

1000

1500

2000

2500

20

00

20

05

20

07

20

08

20

09

20

10

20

11

20

12

20

13

GNI Per Capita US $

Burkina Faso Africa

0,0

0,5

1,0

1,5

2,0

2,5

3,0

3,5

20

00

20

05

20

08

20

09

20

10

20

11

20

12

20

13

20

14

Population Growth Rate (%)

Burkina Faso Africa

01020304050607080

20

00

20

05

20

08

20

09

20

10

20

11

20

12

20

13

20

14

Life Expectancy at Birth (years)

Burkina Faso

Africa

Page 28: AFRICAN DEVELOPMENT FUND BURKINA FASO ... DEVELOPMENT FUND BURKINA FASO ELECTRIFICATION OF SEMI-URBAN AREAS OF OUAGADOUGOU AND BOBO-DIOULASSO ONEC/ORWA/BFO DEPARTMENTS August 2016

II

Annex II: Table of Bank Portfolio in Burkina Faso (March 2016)

No. Project Name Project Code Sector

Performance

(Status)

Approval

Date

Completion

Date

Age (in

years)

Disburs.

Rate

Amount

Disburs.

Loan/Grant

Amount

1

PROJECT TO DEVELOP INTERNAL ACCESSIBILITY ROADS P-BF-DB0-017 Transport PP 13/11/2013 31/12/2019 2.28 8.6% 3 993 206 46 438 000.00

2

PROJECT TO REHABILITATE ROADS AND

FACILITATE TRANSIT ON THE LOME-OUAGADOUGOU CORRIDOR P-Z1-DB0-097 Transport NPP 27/06/2012 31/12/2017 3.66 20.8% 22 255 912 107 041 392.41

4

GRID REINFORCEMENT AND RURAL

ELECTRIFICATION PROJECT (PRIELER) P-BF-FA0-006 Energy

NON PP / NON

PPP 07/07/2010 30/06/2016 5.63 96.7% 24 326 932 25 150 000.00

5

ENERGY SECTOR BUDGET SUPPORT PROGRAMME (PASE) P-BF-FA0-008 Energy

NON PP / NON

PPP 10/07/2015 30/06/2016 0.62 100.0% 20 000 000 20 000 000.00

6 BAGRE GROWTH POLE SUPPORT PROJECT P-BF-AA0-025 Agriculture NPP 29/04/2015 30/04/2021 0.82 0.5% 103 324 21 000 000.00

7

MULTINATIONAL- PROGRAMME TO BUILD

RESILIENCE FOR ENHANCING FOOD SECURITY

AND NUTRITION (P2RS) P-Z1-AAZ-017 Agriculture NPP 15/10/2014 30/06/2020 1.36 2.0% 201 007 10 000 000.00

8

BURKINA FASO-PROGRAMME TO BUILD RESILIENCE FOR ENHANCING FOOD SECURITY

AND NUTRITION (P2RS) P-Z1-AAZ-019 Agriculture NPP 15/10/2014 30/06/2020 1.36 0.5% 117 836 25 450 000.00

9

CLASSIFIED FORESTS PARTICIPATORY

MANAGEMENT PROJECT PGFC/RED P-BF-AAD-003 Agriculture NON PP / NON PPP 28/11/2013 30/06/2018 2.24 4.5% 379 009 8 394 834.62

10 PREPARATION PPG PGFC/REDD+ FIP BURKINA

P-BF-AAD-004 Agriculture

NON PP / NON

PPP 22/03/2013 30/06/2016 2.92 3.3% 11 893 364 992.81

11

ECONOMIC TRANSFORMATION AND JOB-

CREATION SUPPORT PROJECT (PATECE) P-BF-KF0-009

Multi-

Sector

NON PP / NON

PPP 17/09/2014 31/10/2018 1.43 0.5% 45 855 10 000 000.00

12

HIGHER EDUCATION SUPPORT IN MEMBER

STATES OF THE WEST AFRICAN ECONOMIC AND MONETARY UNION (WAEMU) P-Z1-IAD-002 Social

NON PP / NON

PPP 24/07/2006 15/09/2016 9.59 73.0% 14 602 860 20 000 000.00

13

MULTINATIONAL ECOWAS: SUPPORT PROJECT FOR A NETWORK OF AFRICAN SCIENCE AND

TECHNOLOGY INSTITUTIONS P-Z1-IAD-004 Social

NON PP / NON

PPP 18/03/2009 31/05/2016 6.94 90.5% 10 856 720 12 000 000.00

14

PROJECT FOR CLEANING UP THE SUBURBS OF

OUAGADOUGOU TOWN P-BF-EB0-001 Water/San. NPP 09/10/2013 30/06/2018 2.37 9.0% 2 972 217 33 020 000.00

15 LINE OF CREDIT PROJECT AT FIDELIS

P-BF-HB0-001 Finance NON PP / NON PPP 19/06/2014 30/07/2017 1.68 100.0% 1 947 420 1 947 419.67

TOTAL 3.17 29.3% 99 866 771 340 806 640

Page 29: AFRICAN DEVELOPMENT FUND BURKINA FASO ... DEVELOPMENT FUND BURKINA FASO ELECTRIFICATION OF SEMI-URBAN AREAS OF OUAGADOUGOU AND BOBO-DIOULASSO ONEC/ORWA/BFO DEPARTMENTS August 2016

III

Annex III: Main Related Ongoing Projects in Burkina Faso financed by the Bank and Other Development Partners

N

°

Project Title Total Project Cost Approval Year Donors and Amounts Remarks Implementation

Status

1 Grid Reinforcement and Rural

Electrification Project (PRIELER) UA 36.17 million 2010

ADF UA 25.15 million Grant

Near Completion

2 Rural Electrification Project Team-9 CFAF 13.04 billion 2012

Eximbank

India CFAF 12.5 billion Loan Ongoing

3 Connection of Isolated Centres to the

Main Network EUR 32.5 million 2010

AFD EUR 32 million Loan

Ongoing

4 225 kV Bolgatanga (Ghana) –

Ouagadougou (Burkina)

Interconnection Project

CFAF 36.1 billion

2011

2012

2011

WB

AFD

EIB

CFAF 8 billion

CFAF 11.1 billion

CFAF 15.3 billion

Grant

Loan

Loan

Ongoing

5 Project to Construct a 33 MWp Solar

Power Plant at Zagtouli EUR 70.5 million

2013

2014

2014

EU

AFD

EIB

EUR 25 million

EUR 22.5 million

EUR 23 million

Grant

Loan

Loan

Start-up phase

6 Electricity Sector Support Project

(PASEL) USD 87.87 million 2014

World

Bank USD 85 million Loan

Ongoing

7 Energy Sector Budget Support

Programme (PASE) UA 20 million 2015

ADF UA 20 million Grant

Near completion

8 Project to Construct a 1.1 MWp Solar

Power Plant at Ziga EUR 2.8 million 2014

China EUR 2.8 million Grant

Ongoing

9 Programme to Electrify 87

Headquarters of Rural Communes CFAF 30.3 billion 2012

Burkinabè

State CFAF 30.3 billion

Investment

subsidy

Ongoing

10 Decentralized Rural Electrification

Project by Photovoltaic System for 41

Localities

CFAF 6.7 billion 2015

IDB

USD 12 million Loan

Ongoing

Page 30: AFRICAN DEVELOPMENT FUND BURKINA FASO ... DEVELOPMENT FUND BURKINA FASO ELECTRIFICATION OF SEMI-URBAN AREAS OF OUAGADOUGOU AND BOBO-DIOULASSO ONEC/ORWA/BFO DEPARTMENTS August 2016

IV

Annex IV: Map of Project Area

This map is provided by the African Development Bank Group staff exclusively for the use of the readers of the report

to which it is attached. The names used and the borders shown do not imply on the part of the Bank and its members

any judgment concerning the legal status of a territory nor any approval or acceptance of these borders.