african development bank group · appendix 1: comparative socio-economic indicators ... afdb...
TRANSCRIPT
AFRICAN DEVELOPMENT BANK GROUP
REPUBLIC OF LIBERIA
ADB’S SUPPORT TO THE INTEGRATED PUBLIC FINANCIAL
MANAGEMENT REFORM PROJECT - PHASE II
ECGF DEPARTMENT
January 2017
Pu
bli
c D
iscl
osu
re A
uth
ori
zed
Pu
bli
c D
iscl
osu
re A
uth
ori
zed
TABLE OF CONTENTS
Currency Equivalents
Fiscal Year
Weights and Measurements
Acronyms and Abbreviations
Financing Information
Project Milestones and Timelines
Project Summary
Results-Based Logical Framework
Project Implementation Timeframe
I – STRATEGIC THRUST AND RATIONALE
1.1. Project linkages with country strategy and objectives
1.2. Rationale for the Bank's involvememt
1.3. Donor coordination
II – PROJECT DESCRIPTION
2.1. Project objectives and components
2.2. Technical solution retained and other alternatives explored
2.3. Project type
2.4. Project cost and financing arrangements
2.5. Project’s target area and beneficiaries
2.6. Participatory process for project identification, design, and implementation
2.7. Bank Group experience, lessons reflected in project design
2.8. Key performance indicators
III – PROJECT FEASIBILITY
3.1. Economic and financial performance
3.2. Environmental and social impact
3.3 Fragility analysis
IV – IMPLEMENTATION
4.1. Implementation arrangements
4.2. Monitoring and evaluation
4.3. Governance
4.4. Sustainability
4.5. Risk management
4.6. Knowledge building
V – LEGAL INSTRUMENTS AND AUTHORITY 5.1. Legal instrument
5.2. Conditions associated with Bank’s intervention
5.3. Compliance with Bank policies
VI – RECOMMENDATION
i
i
i
ii
iii
iii
iv
v
viii
1
1
2
4
5
5
7
8
9
10
11
11
13
14
14
14
15
15
15
17
18
18
18
19
19
19
19
20
20
LIST OF TABLES
Table 1.1: Development Partners’ Interventions and Complementarity with the Project
Table 2.1: Summary of Project Activities by Component
Table 2.2: Project Alternatives Explored
Table 2.3: Project Cost Estimates by Component
Table 2.4: Project Cost Estimates by Sources of Financing
Table 2.5: Expenditure Schedule by Components
Table 2.6: Lessons learned from previous operation and other analytical reports
Table 2.7: Selected PEFA Scores for Improved Performance under IPFMRP Phase II
Table 4.2: Project Implementation Schedule
Table 4.5: Summary of Risks and Mitigation Measures
LIST OF APPENDICES
Appendix 1: Comparative Socio-Economic Indicators
Appendix II: AfDB Projects in the Bank’s Portfolio in Liberia
Appendix III: Similar Projects Financed by the Bank and other Development Partners
Appendix IV: Letter of Request from the Government of Liberia
Appendix V: The Bank’s Value Addition under IPFMRP Phase I
Appendix VI: Map of the Republic of Liberia
i
Currency Equivalents
(as of September 20, 2016)
UA 1 = US$ 1.39
US$ 1 = LRD 97.50
UA 1 = LRD 135.95
Fiscal Year
July 1 – June 30
Weights and Measurements
1metric tonne = 2204 pounds (lbs)
1 kilogramme (kg) = 2.200 lbs
1 metre (m) = 3.28 feet (ft)
1 millimetre (mm) = 0.03937 inch (“)
1 kilometre (km) = 0.62 mile
1 hectare (ha) = 2.471 acres
ii
Acronyms and Abbreviations
ADF African Development Fund AfDB African Development Bank APRM African Peer Review Mechanism CAG Comptroller and Accountant General COA Chart of Accounts CPIA Country Policy and Institutional Assessment CPPR Country Portfolio Performance Review CSP Country Strategy Paper DeMPA Debt Management Performance Assessment EU European Union FIU Financial Intelligence Unit FC Foreign Costs GAC General Auditing Commission GC Governance Commission GDP Gross Domestic Product GoL Government of Liberia HIPC Highly Indebted Poor Countries IAA Internal Audit Agency IFMIS Integrated Financial Management Information System IMF International Monetary Fund IPFMRP Integrated Public Financial Management Reform Project ISP Institutional Support Project JAS Joint Assistance Strategy LBO Legislative Budget Office LC Local Costs LEITI Liberia Extractive Industry and Transparency Initiative LICPA Liberian Institute of Certified Public Accountants LIPA Liberian Institute of Public Administration LRA Liberia Revenue Authority LRD Liberian Dollar MDAs Ministries, Departments and Agencies MFDP Ministry of Finance and Development Planning MFF Macro Fiscal Framework MTEF Medium Term Expenditure Framework NRTU Natural Resource Tax Unit PAR Project Appraisal Report PBA Performance Based Allocation PCR Project Completion Report PEFA Public Expenditure and Financial Accountability PEMFAR Public Expenditure Management and Financial Accountability Review PFM Public Financial Management PFM RS&AP Public Financial Management Reform Strategy and Action Plan PFMSC Public Financial Management Steering Committee PFMU Public Financial Management Unit PIMA Public Investment Management Assessment PIU Project Implementation Unit PRS Poverty Reduction Strategy RCU Reform Coordination Unit SDG Sustainable Development Goal SIDA Swedish International Development Agency SIGTAS Single Integrated Tax Administration System SoE State Owned Enterprise TA Technical Assistance TADAT Tax Administration Diagnostic Assessment Tool
iii
TSA Treasury Single Account TSF Transition Support Facility UA Unit of Account UNDP United Nations Development Program USAID United States Agency for International Development WB World Bank
Financing Information
Client Information
BORROWER: Republic of Liberia
EXECUTING AGENCY: Ministry of Finance and Development Planning
Financing Plan
Source Amount
(UA m)
Amount
(US$ m)
ADF-13 Grant PBA 3.19 4.43
ADF-13 TSF Grant - Pillar III Grant 1.00 1.39
ADF-10 Grant PBA (Unused Balance Reallocation)* 0.88 1.22
ADF-10 TSF Grant - Pillar I (Unused Balance Reallocation)* 1.07 1.49
ADF-10 TSF Grant - Pillar III (Unused Balance Reallocation)* 0.12 0.171
World Bank / IDA Grant and Credit (expected) 14.34 20.00
Government Counterpart In-kind Contribution (10%) 0.69 0.969
TOTAL FINANCING AMOUNT 21.29 29.67
*The unused balances reflected here in the amount of UA 2.07 m (US$ 2.88m) include the funds reallocated
from the Liberia: Labor-Based Public Works Project approved on December 8, 2007 for ADF Grant Number
2100155010817.
Project Milestones and Timelines
Project Milestones Timelines
Preparation April 2016
Appraisal September 2016
Peer Review September 2016
Regional Director Clearance October 2016
Negotiation November 2016
Board approval December 2016
Grant Signature December 2016
Effectiveness December 2016
Mid-Term Review June 2018
Completion June 2019
Last disbursement December 2019
iv
Project Summary
Project
Overview
Project Name: ADB’s Support to the Integrated Public Financial Management Reform Project
- Phase II (IPFMRP II)
Project Objective: To strengthen transparency and accountability in public financial management and
enhance domestic revenue mobilization from the natural resource sector.
Expected Outputs: Strengthened PFM capacity; improved PFM processes and accountability; and
more efficient domestic revenue mobilization from the natural resource sector.
Geographical Scope: Nationwide
Overall Timeframe: 36 months (January 2017 – December 2019)
Grant Amount: UA 6.26 million / US$ 8.72 (AfDB contribution)
Project Direct Beneficiaries: There are two direct beneficiary institutions for this project: (i) the
Ministry of Finance and Development Planning’s (MFDP) PFM Reform Coordination Unit (RCU);
and (ii) the Liberian Revenue Authority (LRA). The RCU will coordinate the activities of all the other
targeted entities. Within MFDP, the targeted units include the Aid Management Unit and the State-
Owned Enterprise Financial Reporting and Coordination Unit. Outside MFDP, entities to benefit from
this ISP include the Internal Audit Agency, Legislative Budget Office, Public Accounts Committee,
Comptroller and Accountant General’s Office, Public Procurement and Concessions Commission,
Liberian Anti-Corruption Commission, and the General Audit Commission. Three professional PFM
institutions will also be supported: the Liberian Institute of Public Administration, Liberia Institute of
Certified Public Accountants, and the Financial Management Training Program. This project will also
promote gender balance in its activities and ensure that women’s participation in the training sessions
reach at least 50% of eligible female staff (i.e., 50% of women professionals in PFM).
Project Components: This project has three components: (i) strengthening transparency and
accountability in public financial management; (ii) enhancing domestic revenue mobilization from
the natural resource sector; and (iii) project management. Activities will include: Upgrade of the
Integrated Financial Management Information System (IFMIS) platform, strengthening the capacity
of institutions in PFM, strengthening debt management, macroeconomic forecasting, financial
reporting, and better domestic revenue mobilization.
Needs
Assessment
The project is needed to address some of the deficiencies in PFM based on scores of D/D+ in the
recently completed 2016 PEFA exercise and the key priorities specified in the Public Financial
Management Reform Strategy and Action Plan (2017-2020). The project is needed at this point in
time to address the fiscal challenges resulting from the low commodity prices and the need for critical
investments in infrastructure, particularly in the power, transport, agriculture and the health sectors.
The health sector needs to be rebuilt in view of the recent Ebola epidemic. The support is therefore
focussed on capacity building, particularly for institutions that are involved in public financial
management; developing improved revenue collection systems; improving budget and expenditures
tracking; and accounting surveillance systems. Support will also be provided to institutions that are
involved in commodity product pricing, taxation administration, accounting, surveillance and process
monitoring in the natural resource sector.
Bank’s
Added Value
The Bank has played a central role in the PFM reform efforts in Liberia. The previous policy-based
operations and institutional support projects have positioned the Bank as a main partner in this area.
The Bank has supported the Customs Office in Liberia by rolling out ASYCUDA in ports of entry.
The Bank has developed a strong relationship with the GoL and other development partners. Efforts
have been made for improved alignment, harmonization, and coordination with other development
partners, as demonstrated by IPFMRP I. This project will be complemented by other DP interventions
in PFM in the years ahead, notably the World Bank and SIDA that have already indicated their interest
in supporting PFM reforms under the new PFM Reform Strategy and Action Plan (2017-2020).
Knowledge
Management
New knowledge will be delivered through: (i) Capacity building initiatives that will help government
officials to produce PFM products (PFM strategy, PFM progress reports); (ii) Development of tailor
made manuals, working practices and tools for continued use; (iii) Procurement information system
and (iv) knowledge transfer from long and short-term technical assistance.
v
Results-Based Logical Framework
Country and Project Name: ADB’s Support to the Integrated Public Financial Management Reform Project
- Phase II (IPFMRP II) Project Objective: To strengthen transparency and accountability in public financial management and enhance domestic
revenue mobilization from the natural resource sector.
RESULTS CHAIN
PERFORMANCE INDICATORS
MEANS OF
VERIFICATI
ON
RISKS/
MITIGATION
MEASURES Indicator (including CSI)
Baseline Target
IMP
AC
TS
Improved PFM performance, more efficient revenue collection, and enhanced governance of natural resources
Increased tax revenue as a % of GDP Improved resource governance index Improved CPIA Score (Cluster D)
22 % of tax revenue as a % of GDP (2015) Partially satisfactory score of 62% (2015) CPIA Score (Cluster D) of 3.5 (2015)
24% of tax revenue as a % of GDP (2019) Fully satisfactory score > 71% (2019) CPIA Score (Cluster D) of 3.7 (2019)
IMF Article IV Reports and LRA Reports Natural resource governance institute scores AfDB CPIA
Risk 1: Capacity
constraints: Weak
institutional and
human
resources capacity
could cause delays
or hamper
implementation
Mitigation
measure: This
proposed support
is based on a
recent and realistic
assessment of
implementation
capacity in general
and clearly
sequenced PFM
Reform Strategy.
The project will
provide additional
project
management
capacity.
Risk # 2:
Fiduciary risks:
Government has
made notable
progress in
improving PFM,
but there are still
weaknesses in the
fiduciary and
control
OU
TC
OM
ES
Outcome 1:
Improved PFM efficiency, transparency, and accountability
Improved PEFA scores on fiscal discipline, efficiency, and oversight1
10 PEFA Scores of D/D+ (2016)
5 or less PEFA Scores of D/D+ (PI-2, 4, 11,15,22) (2019)
2019 PEFA Report
Outcome 2: Enhanced knowledge in tax audit techniques in the natural resource sector
Increased proportion of trained tax auditors in the natural resource sector
25% of NRTU staff trained in tax audit techniques in the natural resource sector (2015)
50% of NRTU staff trained in tax audit techniques in the natural resource sector (2019)
Annual PFMU Project Progress Reports
OU
TP
UT
S
Component 1: Strengthening transparency and accountability in public financial management
Output 1: Strengthened efficiency, transparency and accountability in PFM
Increased number of counties on IFMIS Increased timeliness and quality of production of financial statements
IFMIS deployed in 4 counties (2016)
Financial statements produced 5 months of end of FY (2015), with disclaimer audit opinion
IFMIS deployed in 8 counties (2019) IPSAS cash-basis compliant Financial statements produced 4 months of end of FY (2019)
Annual PFMU Progress Reports
1 PI-2: Composition of actual expenditure compared to the approved budget.
PI-4: Stock and monitoring of expenditure payment arrears.
PI-11: Orderliness and participation in the annual budget process.
PI-15: Effectiveness in collection of tax payments.
PI-22: Timelines and orderliness of account reconciliation.
vi
Increased public oversight of government accounts Increased implementation of internal and external audit recommendations
Public Accounts Committee (PAC) has held 21 public hearings (total) on GAC audit reports (2013-16) 10% of internal and external audit recommendations implemented (2015)
PAC holds 12 public
hearings annually
(2019)
>50% of internal and
external audit
recommendations
implemented (2019)
environment. The
weaknesses are
especially in the
area of corruption
due to weak
prosecution
capacity and
sanctions regime.
Mitigation:
Government has
put in place a PFM
Act (2009), and
PFM Reform
Strategy and
Action Plan
(FY2012-FY2016)
that present a
broadly credible
program for
improvement.
Plans are also
underway
implement a new
PFM Reform
Strategy and
Action Plan
(FY2017-FY2020)
and to grant
prosecutorial
power to the
Liberian Anti-
Corruption
Commission. The
Government’s
commitment to,
and ownership of,
reforms is high.
Risk 3:
Implementation
risk. The risk of
delayed project
take off.
Mitigation: To
mitigate the
negative impact of
this risk, the
project will
continue to be
managed by the
same RCU which
has been
instrumental in the
successful
implementation of
IPFMRP and the
government is
centralizing the
implementation of
all institutional
support projects on
PFM through this
RCU.
Increased number of cases investigated and concluded by the Liberian Anti-Corruption Commission (LACC)
12 cases investigated and concluded (2015)
20 cases investigated and concluded (2019)
Annual LACC reports
Component 2: Enhancing domestic revenue mobilization from the natural resource sector
Output 2 : Sector specific training on tax audits for NRTU staff resource sector
Increased # tax audits in the natural resource sector
No tax audits in the natural resource sector (2015)
8 tax audits undertaken annually in the natural resource sector (2019)
LRA/NRTU Progress Reports
Tax audit training conducted for NRTU staff
Less than 25% of tax auditors trained in NRTU (2015)
50% of NRTU staff undergo tax audit training, ensuring 50% female representation (2019)
Tax compliance monitoring templates for natural resources developed, deployed, and staff trained on their use
None (2015) Tax compliance monitoring templates for natural resources developed, deployed, and staff trained on their use, ensuring 50% female representation (2019)
Benchmarking visits and secondment of NRTU staff to other revenue administrations to facilitate peer to peer learning, draw lessons and develop applicable solutions for Liberia
None (2015)
At least two NRTU staff seconded annually to other revenue administrations in Africa for further hands-on training of which one is female (2019)
Production of Manuals on Policies and Procedures in tax audits for the natural resource sector
None (2015)
Manuals on Policies and Procedures in tax audits for the natural resource sector produced (2019)
Component 3: Project management
vii
Enhanced Project
Administration and
Management with
timely preparation
and submission of
reports, and annual
work and procurement
plans
- # of project
progress reports
submitted # of financial audit report
None - 4 progress reports
/ year
1 financial report within 6 months after end of each fiscal year
RCU generated reports
COMPONENTS
INPUTS
Component 1: Strengthening transparency and accountability in public financial management (UA 3.40 m / US$ 4.73 m) Component 2: Enhancing domestic revenue mobilization from the natural resource sector (UA 2.67 m / US$ 3.70 m) Component 3: Project management (UA .200 / US$ 0.280)
ADF Grant : UA 6.27 million (US$ 8.72 m) World Bank /IDA Grant: UA 14.34 / US$20 m Government (in kind): UA 0.697 / US$ 0.969
Total Project Financing: UA 21.30 m / US$29.67 m
viii
Liberia: Integrated Public Financial Management Reform Project - Phase II
Project Implementation Timeframe (2017-2020)
YEAR 2016/2017 2017/2018 2018/2019 2019/2020 ACTION
BY
Quarter Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Project Cycle
Activities
Grant approval AfDB
Effectiveness GoL
Launching workshop
AfDB
&GoL
Joint supervision and monitoring (IPRs)
AfDB
Mid-term review
AfDB
Disbursement of funds
AfDB
Submission of annual audit reports
GoL
AfDB project completion report (PCR)
AfDB
All Components
General procurement notice published
GoL
Procurement of goods and technical assistance
GoL
Provision of training
GoL
Submission of progress reports
GoL
PEFA update
GoL
1
REPORT AND RECOMMENDATION OF MANAGEMENT OF THE
ADB BOARD OF DIRECTORS FOR A PROPOSED GRANT TO LIBERIA
TO SUPPORT THE INTEGRATED PUBLIC FINANCIAL MANAGEMENT
REFORM PROJECT - PHASE II (IPFMRP II)
Management submits the following report and recommendation for a proposed ADF grant of
UA 6.27 million (US$ 8.72 m) to finance the Integrated Public Financial Management Reform
Project - Phase II (IPFMRP II). The project will help to consolidate the gains achieved from
the two previous ISPs and will strengthen the capacity of institutions that promote governance,
accountability, and transparency, with an added focus on domestic resource mobilization in the
natural resource sector.
I – STRATEGIC THRUST & RATIONALE
1.1. Project linkages with country strategy and priorities
1.1.1 The proposed operation is fully aligned with Liberia’s development agenda, the
Agenda for Transformation (2012-2017), in particular, Pillars 2-Economic Transformation
and 4-Governance and Public Institutions, which are key measures for the achievement of the
long-term national vision of Liberia Rising by 2030, as well as the Economic Stabilization and
Recovery Plan (ESRP) developed following the Ebola Virus Disease (EVD) outbreak, which
also focuses on strengthening public financial management (Pillar III). It is also consistent
with the PFM Reform Strategy and Action Plan (2012-2016)2 which seeks to consolidate PFM
reforms while ensuring coordination and alignment of donor interventions to GOL priorities,
as well as the emerging PFM Reform Strategy for 2017-2020.
1.1.2 The intervention is in line with the Bank’s Ten-Year Strategy (2013-2022) and
aligned with the core operational priority of Governance and Accountability. It is also
aligned with Sustainable Development Goal 16 on promoting peaceful and inclusive societies
for sustainable development, provide access to justice for all and build effective, accountable
and inclusive institutions at all levels. Sound public financial management also cuts across all
of the Bank’s High-5 priority areas of Light Up and Power Africa, Feed Africa, Industrialize
Africa, Integrate Africa, and Improve the Quality of Life for the People of Africa. The operation
seeks to improve PFM and natural resource governance as well as Pillar 1 of the Governance
Strategic Framework and Action Plan (2014-2018) on enhanced PFM. The project is also
aligned with Pillar 2 of the Country Strategy Paper 2013-2017, notably on enhancing
governance and the efficient management of resources, and has cross-cutting support for Pillar
I on promoting inclusive economic growth through transformative infrastructure investments.
This project also has a focus on women economic empowerment and aligned with the Bank
Group’s Gender Strategy 2014-2018.
1.1.3 The project is consistent with the ADF 13 operational priorities on governance and
accountability, the Bank’s strategy for Addressing Fragility and Building Resilience in Africa
(2014-2019),3 the Bussan New Deal for Engagement in Fragile States. Through this project,
the Bank will contribute to addressing the country’s economic capacity to address the root
2 Liberia’s PFM Reform Strategy and Action Plan (2012-2016) will expire on December 31, 2016 and work is in progress on the
development of the new PFM Reform Strategy and Action Plan (2017-2020). 3 The focus areas of the strategy on fragile states are strengthening state capacity and support institutions and promoting inclusive and equitable
patterns of growth and development.
2
causes of conflict, such as: (i) youth unemployment; (ii) rural under-development; and (iii)
over-exploitation of natural resources. This project is also linked with the West Africa Regional
Integration Strategy Paper (2011-2017) pillar on institutional capacity building particularly
through the provision of cross-licensing opportunities for public financial management
professionals in Liberia, e.g., cross-licensing of Liberian CPAs in Ghana and Nigeria .
1.2. Rationale for the Bank’s involvement
1.2.1 With lower economic growth in Liberia following the EVD crisis and the drop in
international commodity prices, continued progress on public financial management
(PFM) reforms and particularly in domestic revenue mobilization is needed to ensure that
limited resources are used efficiently. Although Liberia has made notable progress in PFM
reforms and capacity in recent years, particularly with donor support including through the
Integrated Public Financial Management Reform Program (IPFMRP), there is a need to
consolidate progress made and continue to address challenges to improve transparency and
accountability in the PFM system. Strengthened capacity and institutions will be necessary to
manage efficiently and transparently government resources in line with its development
strategies, to ensure the society benefits from the country’s resources, and to increase stability.
Improving transparency and accountability is further needed to address perceptions of
corruption. Although civil service capacity has improved and numerous sector and reform
strategies have been developed, capacity is still weak, and the strategies need to be effectively
implemented.
1.2.2 The GoL has made significant progress across a range of PFM reforms in recent
years with the support of development partners including the AfDB through the
IPFMRP. These reforms have sought to restore and embed the PFM systems to enable GoL to
better implement its development agendas. As presented in Technical Appendix XI, some of
the reforms include: the introduction of the Free Balance integrated financial information
management system (IFMIS) at the Ministry of Finance and Development Planning (MFDP),
with a roll- out to 36 line Ministries and Agencies (M&As); the introduction of elements of a
Medium-Term Expenditure Framework (MTEF); enhanced budget transparency through on-
line access to budget documents and quarterly fiscal reports; the establishment of the semi-
autonomous Liberia Revenue Authority (LRA); the automation of the collection and
administration of taxes; the transitioning from an Internal Audit Secretariat into a full Internal
Audit Agency that is active in 43 M&As; the establishment of a State-Owned Enterprise (SOE)
reporting unit within MFDP; the launch of Treasury Bill auctions; the adoption of a
decentralized Treasury Management Framework and county treasuries; and the passage of the
GAC Act in 2014, increasing its stability and independence.
1.2.3 Despite this progress, Liberia still faces serious capacity challenges in PFM. The
2016 PEFA indicated improvement since 2012 in 14 of 31 categories, but ten indicators were
still D or D+. A number of key areas still need to be addressed. These include improving budget
comprehensiveness to include donor financing; improving the consultative and orderly
processes around the budgeting process; institutionalization of the MTEF in line M&As;
improving revenue forecasting; strengthening public investment management and monitoring
of project execution; improving debt management and coordination; improving fiscal oversight
of SOEs; improving fiscal reporting across M&As; full operationalization of a robust cash
management framework under a Treasury Single Account; optimizing institutional and
business processes to fully benefit from IFMIS and deepening its implementation to cover
budget planning, treasury management, and pension management; strengthening the role of the
3
Controller and Accountant General (CAG) to oversee controllers in M&As; increasing payroll
controls; improving functioning of county treasuries; improving the skills, full integration and
utilization of internal auditors in M&As; improving performance of external audit and
legislative oversight functions and follow up on audit recommendations. Other PFM capacity
challenges include improving public procurement processes; appropriately integrating gender
perspectives into PFM; increasing the capacity to investigate corruption cases; strengthening
the Financial Intelligence Unit (FIU) to counteract anti-money-laundering and counter-
terrorism financing; improving regional governance oversight and accountability through the
African Peer Review Mechanism (APRM); and continuing institutional reforms and capacity
building.
1.2.4 Improved public financial management and revenue mobilization from natural
resources are important for the achievement of the GoL’s national development agenda.
The natural resource sector contributes approximately 14% of Liberia’s GDP and, despite
recent downturn in revenues, will continue to be a critical sector of the economy. The LRA has
limited capacity to conduct audits and effectively monitor compliance. The delay in resolving
some of the regulatory and institutional issues (transfer pricing and beneficial ownership)
continue to challenge revenue mobilization. There is a need to strengthen tax compliance,
enhance transparency in revenue collection, streamline regulatory policies, build skills for tax
and tariff assessments, knowledge on institutional factors affecting natural resource revenue
mobilization, as well as knowledge in transfer pricing. Additionally, there is a need to enhance
Liberia’s progress in transparency of natural resources revenues which has been achieved
through the Liberia Extractive Industry Transparency Initiative (LEITI).
1.2.5 The proposed IPFMRP II will build on IPFMRP Phase I and pave the way for
deeper implementation of the PFM reform agenda through 2020. The main achievements
under IPFMRP Phase I included enhanced budget planning systems with elements of an MTEF,
expanding the coverage of IFMIS to 35 M&As; the preparation, audit, and publication of the
Consolidated Fund financial statements; increased consistency in fiscal outturn publication; the
expansion of internal auditors into 43 M&As; the Public Accounts Committee (PAC) holding
its first seven public hearings on audit reports; and increased transparency of SOEs. The
establishment of the LRA in July 2014 has supported improved tax administration, but key
capacity challenges continue, with a particular gap relating to natural resource sector taxation
which will be addressed by this project. The Bank and other Development Partners’ value
addition under IPFMRP Phase I are detailed in Appendix V.
1.2.6 Development partners are supporting the finalization of the Government’s PFM
Strategy for 2017-2020, which will deepen existing reforms and sustain reform momentum into
the new administration. The proposed operation will contribute to these efforts and support
implementation of the strategy, and address identified weaknesses in the PFM system in
Liberia. The proposed operation has been guided by various analytical and diagnostic reports
which have identified challenges in the PFM systems, revenue administration, investment
management, and debt management, as well broadly identified how to focus support. These
studies have included the 2016 PEFA report, the 2016 Public Investment Management
Assessment (PIMA), and the 2016 Debt Management Performance Assessment (DeMPA). The
Technical Appendix includes a more complete list of all the Analytical Works and
Underpinnings used to inform the design of this ISP.
4
1.2.7 Social context. The EVD crisis slowed the gains that Liberia had made in reducing
poverty and vulnerability during the aftermath of a 10-year civil war. In 2014, GDP
growth was 0.7% down from the estimated 8.7% in 2013. Iron ore and rubber production which
had already slowed down due to lower international prices, were also affected by the ebola-
related quarantines and curfews implemented by the GOL in the bid to contain the ebola crisis.
The epidemic resulted in the disruption of production processes across several sectors. Growth
in manufacturing continued to be constrained by inadequate electricity and the generally weak
business environment. Household incomes suffered from the substantial loss of jobs as
businesses were shut down. The fear associated with the ebola outbreak considerably slowed
down economic activities with large concession companies suspending their investment plans
and relocating some of their expatriate staff out of Liberia. Central to reviving the economy of
Liberia is strengthening the capacity of the tax administration to mobilize domestic resources
and support government investment in critical infrastructure to spur economic growth. The
improved capacity to mobilize domestic revenues will play a central role in reviving the
economy, and reduce poverty and vulnerability in Liberia. Improving the efficiency and
transparency of PFM is also key to addressing fragility by increasing the ability of the state to
deliver services to the people, while also helping to address the negative perceptions about the
incidence of corruption. The proposed operation has been guided by various analytical and
diagnostic reports such as the recent PFM diagnostic identified in the 2016 PEFA report. The
Technical Annexes to this PAR provides the list of the Appendices
1.3. Donor coordination
1.3.1 A significant number of development partners currently provide assistance to
Liberia through budget support, project funding, pooled funds, and multi-donor trust
funds. A PFM Donor Coordination Group, currently chaired by the AfDB, meets monthly with
partners including the IMF, World Bank, European Union, USAID, Embassy of Sweden,
UNDP, GIZ, Embassy of Norway, the MFDP Reform Coordination Unit (RCU) and other
concerned M&As. The existing IPFMRP has integrated support from 5 donors—European
Union, USAID, Sweden, World Bank, and AfDB—in a coordinated PFM reform support
program. This has increased the efficiency of support through coordinated supervision
missions, project administration, and thereby increasing the efficiency of support for
Government and donors while reducing overlap. There is a strong need for building upon this
coordinated approach to continue PFM reform. A common monitoring and evaluation
framework and operational plan has been developed to guide implementation and coordination
of the PFM reforms in Liberia. GoL is committed to improving the effectiveness of aid, by
prioritizing coordinated donor financing through a clear institutional arrangement and
integrating donor funds into the GoL budget. The different thematic areas of support by the
PFM contributing development partners, by funding status, and the areas of complementarity
with IPFMRP II are presented in the table below.
Table 1.1: Development Partners’ Intervention and Complementarity with the Project
Sources of
Financing
Total
(US$ million)
Fiscal
Year (s)
Funding
Status
Areas of
Complementarity with
IPFMRP II
EU 3.00 2016/2017 Ongoing E-procurement
Sweden 15.10 2016/2017 Ongoing Inclusive financial
governance
USAID 7.00 2016/2017 Ongoing IFMIS upgrade
5
1.3.2. During the appraisal mission for IPFMRP II, technical consultations were also
organized with the relevant development partners in terms of their commitments and
prospective areas of future support under the new PFM Reform Strategy (2017-2020). The
IMF expressed future capacity building support through LIPA on the MTEF. The EU is likely
to support GAC’s new professionalization strategy by providing funds for the certification of
more auditors, the fiscal decentralization effort through strengthening of the country treasuries,
and linking the IFMIS platform with the planned aid management platform. The EU, World
Bank, and OECD are also considering design of a transfer pricing scheme for Liberia. With
respect to the bilateral agencies, GIZ will be supporting strengthening the interface between
the Ministry of Lands and Mines with LRA, by providing systems to connect the monitoring
and valuation processes of minerals and precious metals undertaken by the two entities. SIDA
also agreed to maintain its commitment to strengthening PFM reforms in Liberia under the new
PFM Reform Strategy (2017-2020).
II – PROJECT DESCRIPTION
2.1. Project Objective and Components
2.1.1 Project Objectives: The overarching objective of the project is to strengthen
transparency and accountability in public financial management; and enhance revenue
mobilization from the natural resource sector. The project objectives are to be achieved
through: (i) Upgrade of IFMIS infrastructure to better track budget implementation, revenue
collection and government expenditures; (ii) Strengthening the capacity of institutions in PFM;
(iii) Capacity building for Debt Management, Macroeconomic Forecasting and Fiscal
reporting; (iv) Support to revenue mobilization and Administration; and v) Support to Liberia’s
integrity and anti-corruption agencies and CSOs involved in promoting accountability through
monitoring of PFM processes and Governance in general for more efficient use of national
resources.
2.1.2 Project Components: The project has three components: i) Strengthening efficiency,
transparency, and accountability in public financial management; ii) Enhancing domestic
revenue mobilization from the natural resource sector; and iii) Project management. The major
activities under the components are summarized in Table 2.1.
ADF Grant 5.84 2017/18/19 New Budget and expenditure
management, IFMIS,
revenue management, and
inclusive financial
governance
World Bank/IDA Exp. 20.00 2017/18/19 New All of the above
6
Table 2.1: Summary of Project Activities by Component
Components Description of Project Activities by Sub-Component
1.
Strengthening
efficiency,
transparency,
and
accountability
in public
financial
management
UA 3.40 m
(US$ 4.73 m)
Sub-component 1.1: IFMIS infrastructural upgrade
Assessment of the data centre infrastructure upgrade needs
Procurement and installation of hardware: servers, local area network, microwave
radios, switches in counties with high transaction volumes.
Procurement and installation of software: operating system’s business
productivity, virtualization, network management and security applications
Sub-component 1.2: Strengthen the PFM capacity of beneficiary institutions
Development of HR manual for operationalization of the Comptroller and
Accountant General’s office and provide hardware and software
Conduct refresher training for 50 internal auditors and procure equipment for
Internal Audit Agency
Increase the capacity of State-Owned Enterprise Financial Reporting Unit and
develop an asset registry to consolidate State-Owned Assets
Support capacity building programs for Liberian Institute for Public
Administration (LIPA)
Support professional accounting credentialing programs with emphasis on
International Financial Reporting Standards at the Liberian Institute of Chartered
Public Accountants (LICPA)
Procure office equipment and conduct public hearings led by the Legislative
Budget Office (LBO)
Procure hardware and software for use by the Public Accounts Committee (PAC) Provide training in anti-corruption programs at the Liberian Anti-Corruption
Commission (LACC) and undertake asset verification of existing government
officials
Increase capacity in macro-economic analysis and forecasting, debt management
and sustainability analysis, and aid management
Roll out the Aid Management Platform (AMP) to donors, and undertake training
in Project Management
2. Enhancing
domestic
revenue
mobilization
from the
natural
resource sector
UA 2.67 m
(US$ 3.70 m)
Sub-component 2.1. : Strengthen revenue mobilization from the natural resource
sector
Pay subscription to mineral price and cost data bases to Platts Data base Via
Thomson Reuters Eikon platform, as well as Baltic exchange
Develop Terms of reference and procure the services of the mineral valuation
expert to conduct training for staff at the Liberian Revenue Authority (LRA)
Procure equipment to facilitate grading and sorting of minerals by the Office of
precious minerals at the Ministry of Lands, Mines & Energy
Procure the services of a technical expert to conduct specialized training and
technical support in the natural resource sector
Organize peer to peer learning visits and secondments on tax administration
systems in the natural resource sector (Botswana, South Africa and Ghana)
Procure the services of the external professional firms to conduct effective tax
audits in the natural resource sector
Support audits for selected companies in the natural resource sector
Sub-component 2.2 Enhancing transparency and monitoring of PFM processes for
more efficient use of national resources
Recruit a consultant to conduct scoping of LEITI’s transition to the new 2016 EITI
Standards
Recruit LEITI consultant to examine the licensing and revision processes of
concession agreements & Beneficial Ownership Disclosure
7
Produce the 9th, 10th, and 11th EITI reconciliation report for Liberia on royalties
and tax payments to government and the receipt thereof
Town Hall meetings in the 15 counties to promote sensitization on the importance
of Tax Payments and GOL Revenue Mobilization (APRM)
Train 10 staff of APRM Secretariat staff and 3 National Governing Council
members in effective sensitization and community outreach on revenue
mobilization
Organize and host 6 policy dialogues to strengthen policies on the natural resource
sector with stakeholders and publish policy briefs on the GC website (GC)
Conduct two public policy studies on issues regarding the natural resource sector
(GC)
Support the Financial Intelligence Unit (FIU) gather intelligence and conduct
investigation on illicit financial activities in the natural resource industries
Design and develop software, database and hosting services for FIU
Conduct training sessions on the effective use of software and database (FIU)
Organize awareness and sensitization sessions on anti-money laundering and
counter-terrorism financing regimes (FIU)
3.. Project
management
UA 0.20 m
( US$ 0.28 m)
Preparation of annual work plans and procurement plans
Procurement of project goods and services
Project Supervision, monitoring and reporting
Preparation of Annual Project Audits and Project Completion Reporting
2.2. Technical solution retained and other alternatives explored
2.2.1 During project preparation and appraisal, four options were explored regarding
the modality for delivery of the support to Liberia’s Integrated Public Financial
Management Reform Project. The first option considered was the delivery of the grant as a
budget support; the second was the delivery of the project as a standalone investment project
to be managed as ADF portfolio; the third was Grant delivery under a Technical Assistance
Arrangement; and the fourth was as a Grant support delivery under existing the MoU
arrangement with the World Bank and Government. Option 4 was retained due its advantage
over the first three options. The preferred option in which Partners funds are pooled to pursue
the same objective can benefit from portfolio management and implementation synergy. It also
promotes aid coordination. The option also better addresses Government’s programmatic
approach to addressing the PFM reform challenges as identified in the recent PFM reform
Country Concept Paper 2016 (See Appendix XII). Unlike the first three options, the selected
option provides better opportunity for national capacity building in PFM and monitoring and
implementation. The selected option was also based on lessons learnt in project implementation
in Liberia, including the need to minimise project coordinating units through more efficient use
of available in-country expertise and the need to build capacity of existing institutions; and
place more focus on ensuring program sustainability and improve coordination with other
development partners.
2.2.2 In terms of the funding modality, the proposed operation has adopted the pooled
fund arrangement including use of the existing Reform Coordination Unit in MFDP to
minimise transaction costs and improve development effectiveness. In 2011, to minimise
the burden of having a large number of individual projects, GOL developed the comprehensive
PFM Reform Strategy and requested donors to provide support on a harmonised basis into a
single reform project. The World Bank, USAID, SIDA, and AfDB led the way in the
development and implementation of the IPFMRP Phase I multi-donor support on which the
8
first operation was based. Consistent with the Bank’s commitment to provide a coordinated
and harmonised donor support to PFM reform, the proposed operation will use the existing
modality for channelling funds through the pooled funding arrangement and the special account
maintained at the Central Bank of Liberia. The relative advantages and disadvantages of
different funding modalities are summarized below.
Table 2.2: Project Alternatives Explored
2.3. Project type
2.3.1 IPFMRP II is designed to strengthen the capacity of key public institutions
engaged in public financial management under the existing MOU arrangement with the
Modality Advantages Disadvantages
Option 1
Delivery of the grant as
a budget support
Fast disbursing and ease of access
of funds to the Government of
Liberia
The disbursement of funds
into the Consolidated
Revenue Fund would not
necessarily address the PFM
challenges in Liberia
Option 2
Delivery of the project
as a standalone
investment project to be
managed as ADF
portfolio
High degree of control and
accountability of funds provided
Will use the Bank’s disbursement,
supervision, financial management
and procurement processes
Will create significant
administrative burden for the
Government of Liberia
May lead to weakened aid
coordination and synergy
with the overall reform
program
Not in line with current good
practice donor harmonization
and maximizing aid
effectiveness in fragile states
Option 3
Grant delivery under a
Technical Assistance
Arrangement
High degree of control and
accountability of funds
Significant administrative
burden for the Government
of Liberia
Option 4
Grant support delivery
under the existing MoU
arrangement with the
World Bank and
Government
In line with current good donor
practice
Substantially reduced
administrative burden on the
Government of Liberia
Greater assurance that key parts of
the PFM strategy will be funded
Supports effective coordination of
the reform program and common
approaches to implementation
High level of control over the use
of project funds
Relatively reduced level of
direct control over project
funds although AfDB would
be a key player in the joint
donor working group
9
World Bank and Government. It will help in consolidating the gains from the previous two
phases and address the new emerging challenges. The project will deliver improved capacity
and institutional development through a range of interventions including focussed skills
transfer from technical advisors, delivery of a range of training and skills development courses
and strengthening of local training capacity.
2.4. Project cost and financing arrangements
2.4.1 The AfDB shall provide a grant of UA 6.27 million (US$ 8.72) to finance IPFMRP
Phase II. The GoL will contribute 10% of the total cost of the project (UA 0.627 m) in-kind, as
counterpart fund to pay the salaries of project management staff deployed from the Ministry of
Finance and other government Departments, making the overall project cost of UA 6,897
million (US$ 9,337). GoL contribution will also include the cost of running and maintaining
project vehicles that have been provided by the government, and the cost of office utilities. The
tables presented below provide the summary cost tables for the project.
2.4.2 Detailed Cost Estimates: Tables 2.3 to 2.5 provide the categories of eligible
expenditures that will be financed over the project life.
Table 2.3: Project Cost Estimates by Component
Table 2.2: Project Cost Estimates by Component (in Thousand UA)
(USD Thousands) (UA Thousands)
COMPONENT LC FC Total LC FC Total % of
Total
1. Strengthening transparency and
accountability in public financial
management
1,892 2,838 4,730 1,360 2,040 3,400 54%
2. Enhancing domestic revenue
mobilization from natural resource
sector
1,480 2,220 3,700 1,068 1,602 2,670 42%
3. Project management 0,280 0,000 0,280 0,200 0,000 0,200 0.3%
Total Baseline Costs 3,372 5,058 8,430 2,628 3,642 6,270 99%
Physical contingencies 0,05 0,100 0,150 0,050 0,50 0,1000
Price contingencies 0,040 0,100 0,140 0,050 0,050 0,1000
Total Project Cost 3,462 5,258 8,720 2,728 3,742 6,270 100%
GoL in-kind contribution of 10% 0,627 0,627
Overall Project Cost 3,462 5,258 8,720 3,355 3,742 6,897 FC: Foreign Costs: LC: Cost Costs
10
Table 2.4: Project Cost Estimates by Sources of Financing
Table 2.3: Sources of Financing (in million UA)
Sources of Financing Foreign Local Total % of total
ADF and TSF 3,642 2,628 6,270 90%
GoL in-kind contribution of 10% - 0,627 0,627 10%
Overall Project Cost 6,897 100%
Table 2.5: Expenditure Schedule by Component (in UA million): ADF financing
Table 2.5: Expenditure Schedule by Component (in million UA) (ADF financing
COMPONENTS PY1 PY2 FY2 Total
1. Strengthening transparency and accountability in public
financial management 0,884 1,700 0,816 3,400
2. Enhancing domestic revenue mobilization from natural
resource sector 0,667 1,335 0,668 2,670
3. Project management 0,050 0,100 0,050 0,200
Total Baseline Cost 1,595 3,135 1,534 6,270
Contingencies 0,0050 0,01 0,0050 0,020
Total Project Cost 1,600 3,136 1,536 6,270
GoL in-kind contribution of 10% 0,209 0,209 0,209 0,627
Overall Project Cost 1,809 3,345 1,745 6,897
2.5. Project’s target area and immediate beneficiaries
2.5.1 This ISP shall confer benefits to the entire country, but there are two direct
beneficiary institutions for this project: (i) the Ministry of Finance and Development Planning’s
(MFDP) PFM Reform Coordination Unit (RCU) which coordinates PFM reform activities
within MFDP, line M&As; and oversight and integrity institutions; and (ii) the Liberian
Revenue Authority (LRA). The RCU will coordinate the activities of all targeted entities.
Within MFDP, the targeted units include, amongst others, the Department of Economic
Management, Debt Management Unit, Macroeconomic Policy Unit, Aid Management Unit,
the Budget Department, the Fiscal Affairs Department, the Comptroller and Accountant
General’s Office, the State-Owned Enterprise Financial Reporting and Coordination Unit.
Outside MFDP and line M&As, entities to benefit from this ISP include the Internal Audit
Agency, Legislative Budget Office, Public Accounts Committee, Public Procurement and
Concessions Commission, the Liberian Anti-Corruption Commission, and the General Audit
Commission. Some professional institutions will also be supported: the Liberian Institute of
Public Administration, Liberia Institute of Certified Public Accountants, Financial
Management Training Program, Liberian Extractive Industry and Transparency Initiative, the
Governance Commission, and the African Peer Review Mechanism Secretariat.
11
2.6. Participatory process for project identification, design, and implementation
2.6.1 During the preparation mission of the project, consultations were held with the
beneficiary institutions and the donors listed above. To ensure that a harmonized and
collaborative approach was undertaken to support the government’s PFM reform strategy,
consultations were also held with civil society organizations and other relevant stakeholders to
solicit their views on their engagement in this operation.
2.7. Bank Group experience and lessons reflected in project design
2.7.1 As of June 30, 2016 the overall rating of the Bank’s portfolio in Liberia was
satisfactory, with an overall rating of 3.0. The performance rating for Implementation
Progress (IP) and Development Objectives (DO) had average scores of 3.01, and were
satisfactory. The main recommendations that emerged from the 2016 Country Portfolio
Improvement Plan (CPIP) for Liberia relate to the following: i) need to improve quality at entry
to accelerate project effectiveness after approval and project take-off; ii) need to ensure that all
operations are appraised based on recent feasibility and design studies; iii) need to build the
capacity of PIU staff in procurement and contract management; iv) need to closely follow up
on annual work implementation, and budget and procurement plans preparation; v) need to
reduce implementation slippages through desk and field supervision; and vi need to hold
monthly review meeting on outcome of monitoring of project performance, including the
performance of contractors and other service providers. In designing this project, the above key
lessons learnt were taken into account. To accelerate project effectiveness, the existing Project
Implementing Unit with experience in Bank procedures shall be retained to coordinate the
project. Joint supervision will be undertaken based on the pooled fund arrangement and the
MoU between the AfDB and the World Bank. The project as designed has provided adequate
resources to beneficiary institutions for project staff training to enhance the delivery of the
expected outputs. The project design was also guided by the GoL concept paper on the expected
thrust of the GoL 2017-2020 strategy on PFM that is under preparation.4 The new PFM strategy
is being developed by the MFDP in close collaboration with the IMF and World Bank, taking
into account the specific circumstances of Liberia and its fragility. The lessons learned are
summarized below.
12
Table 2.6: Lessons learned from previous operation and other analytical reports
2.7.2 IPFMRP Phase I Pooled Fund Implementation Arrangements – Specific Lessons
Learned
The ongoing IPFMRP is being implemented using a pooled co-financed Multi-Donor
Trust Fund arrangement of US$ 28.6 m that includes the World Bank/IDA (US$ 5 m), SIDA
(US$ 15.1 m), and USAID (US$ 3.85 m). Under the current joint MOU, the GOL and the co-
Lessons Learned Actions taken to integrate lessons into the project
Low levels of in-country capacity had a
negative impact on implementation,
and serious attention should be given to
the design and staffing of the structures
established to coordinate and manage
PFM reforms
This project will be directly based on the Government
of Liberia’s PFM Reform Strategy and Action Plan
which includes detailed work plans taking into
account both technical and human resource
requirements and limitations.
The importance of strong coordination
arrangements for PFM reform is critical
for successful delivery. Fragmented
donor interventions and project
management requirements have placed
a huge burden on scare budgetary
resources and diverted very limited
PFM expertise to servicing donor
requirements as opposed to
contributing to improving the PFM
reform agenda.
This ISP will contribute to a multi-donor support
program to the PFM Reform Strategy and Action
Plan. There is broad consensus on reform priorities as
well as mechanisms to improve donor coordination.
A detailed Operational Manual and Cooperation
Framework has been developed to improve coherence
and coordination among donors and between the PFM
donor working group and the Government of Liberia.
This will greatly reduce the reporting and project
management burden on government. The Liberia
Field Office will enhance further country dialogue
and donor coordination.
The piecemeal approach to capacity
development and separate donor
funding and reporting arrangements
creates unacceptable administrative
burdens on limited PFM capacity in
fragile states
This proposed operation will provide joint funding to
a multi-donor, integrated and coordinated PFM
reform program in which every attempt has been
made to minimize the burden of multiple reporting
and monitoring arrangements and reduces the risk of
uncoordinated interventions.
The joint evaluation of African PFM
reforms identified institutional and
contextual factors that contribute to
successful PFM reforms. One of the
key messages is that donors should
align support as closely as possible to
the government program and avoid
pursuing independent initiatives.
Externally financed support to PFM
reform was most efficient and
effective, when identified explicitly
within the government’s PFM reform
program.
This program is directly aligned with the PFM
Reform Strategy and Action Plan. It is designed
around the needs and priorities identified by the
government through an extensive review,
consultation and planning exercise. As one of the
largest donors in Liberia and as signatory to the Paris
Declaration and Busan New Deal for Engagement in
Fragile States, the proposed operation will be
delivered through the pooled funding arrangement.
13
financiers agreed to use World Bank procurement rules and procedures, with the World
Bank/IDA Task Team Leader serving as the main administrator of the Multi-Donor Trust Fund.
So far, the project implementation arrangement under the pooled account has been satisfactory.
2.7.3 The main lessons that emerged from IPFMRP Phase I pooled fund implementation
arrangements include: (i) the pooled fund leveraged AfDB’s investment into a broader,
coordinated PFM plan that harmonized programs from several donors and reduced the
implementation cost on donors and government, particularly for small grants aimed at
achieving similar objectives; and (ii) ADB’s participation in the pooled fund enhanced donor
coordination in Liberia. To improve the existing collaboration under the pooled fund, it was
agreed during the project appraisal that the existing reporting format of the pooled fund will be
improved to highlight the contributions of all partners to Liberia’s PFM reform program.
2.8. Key performance indicators
2.8.1 The key performance indicators and the expected outcomes at project completion
are outlined in the results-based logical framework. In the short to medium-term, the
expected project outcomes are: (i) improved fiscal discipline, efficiency, and oversight based
on 5 PEFA scores of better than D/D+; and (ii) enhanced domestic revenue mobilization based
on improved governance of the natural resource sector. The table below provides a list of the
selected PEFA scores to be monitored for improved performance under IPFMRP Phase II.
Table 2.7: Selected PEFA scores to be monitored for improved performance
under IPFMRP Phase II
2.8.2 Progress will be measured on a regular basis, through joint supervision missions,
review of Quarterly Progress Reports, review of specific outputs such as audit reports, and
Minutes of meetings from the RCU, which will also be an important vehicle for donor
coordination across the whole PFM Reform Strategy. Objectively verifiable evidence of
progress against meeting the targets will be obtained from World Bank and IMF Mission
Reports, and governance indicators. Collection and analysis of information to monitor
performance will be the responsibility of the RCU. The RCU is responsible for ensuring that
information is collected to assess all targets and indicators against the logframe and for
preparing the comprehensive program performance reports.
Selected PEFA Scores 2007
Score
2012
Score
Score
2016
Score
Score
PI-2 Composition of actual expenditure compared to approved
budget
D D+ D+
PI-4 Stock and monitoring of expenditure payment arrears D+ B D+
PI-11 Orderliness and participation in the annual budget process B B D+
PI-15 Effectiveness in collection of tax payments D+ D+ D+
PI-22 Timelines and orderliness of account reconciliation D C D+
14
III – PROJECT FEASIBILITY
3.1. Economic and financial performance
3.1.1 As an ISP, identifying and quantifying the direct and indirect economic and financial
benefits of capacity building interventions is complicated and it is often difficult to carry out
rigorous cost-benefit economic and financial analysis. While the costs are quantifiable, the
benefits are indirect, and ultimately achieved in the improved public financial governance,
service delivery and better performance of the targeted public financial management
institutions.
3.1.2 The economic justification of the proposed operation is its contribution to a better
functioning government through improved PFM and capacity to implement the national
development strategy. The benefits of the project will flow from improved domestic revenue
mobilization, strengthened budget credibility, budget execution, improved internal controls,
enhanced oversight, and increased transparency in the management of public resources. The
project will also support the development of human resource capacity, thereby ensuring that
the benefits will be sustained over time.
3.2. Environmental and social impact
3.2.1 Environment. Given that the project is an institutional support project, providing
capacity building to government institutions, the operation is not expected to have any direct
adverse environmental impact. The project is classified as Category 3.
3.2.2 Climate Change. The project activities, which focus on building human and
institutional capacity, have no adverse impact on climate change.
3.2.3 Gender. The Government of Liberia is committed to gender mainstreaming by
promoting adherence to the United Nations Security Council Resolution 1325 (2000) on
rebuilding institutions in post-conflict societies. This ISP will also support the implementation
of the 2009 National Gender Policy and Civil Service Reform Strategy by training more
females in PFM. IPFMRP II will ensure that the training program provided through this
operation will be made available to all middle to senior level women in beneficiary institutions.
The project will promote gender balance in its activities and ensure that women’s participation
in training reach at least 50% of all eligible female employees (i.e. 50% of middle to senior
women professionals in PFM).
3.2.4 Social. The aim of the project is to enhance government capacity to implement reform
and manage public resources efficiently and effectively. This will strengthen and leverage the
impact of the national budget on delivery of services, and poverty reduction through increasing
efficiency and effectiveness of resource allocation and budget execution in line with the
national economic growth and poverty reduction strategy. A sound PFM system matters to help
ensure that budget planning are compatible with macroeconomic stability, and that there is a
firm basis for high quality services to be provided to the public.
3.2.5 Private Sector. The project will contribute positively to private sector development
through improved fiscal management. Improved financial governance, particularly creating
15
greater clarity on the level of tax liability of companies operating in the natural resource sector
will improve investor confidence and the future of the Liberian economy.
3.3 Fragility Analysis
3.3.1 Despite progress since the end of the civil war in 2003, Liberia remains a fragile
state with limited access to basic social services and infrastructure development. The country’s
economic capacity to address the root causes of fragility still persists, such as: (i) high youth
unemployment; (ii) negligence of rural development; and (iii) over exploitation of natural
resources. In addition to the above challenges, GoL would need to step up its efforts at national
reconciliation that is essential for sustainability of peace.
3.3.2 The alleviation of fragility can be addressed through the expansion of
opportunities, devolution of power, and inclusion of majority views into decision making
processes. With many of these factors complementary and overlapping, progress must be made
to simultaneously address these issues for sustainability and consolidation of existing peace.
While the country has enjoyed peace and stability for over ten years, the citizens blame
government inability to deliver on social services as well as the high youth unemployment.
This situation could get worse if the current fiscal deficit persists. Hence this ISP is timely and
essential to support the key PFM challenges, and revenue mobilization from the natural
resource sector. More details on the country’s fragility analysis is presented in Appendix XV.
IV – IMPLEMENTATION
4.1. Implementation arrangements
Institutional Arrangements
4.1.1 The project will be managed by the existing PFM Reform Coordination Unit
(RCU), under the current IPFMRP arrangement. The unit is managed by a Project
Coordinator and comprises other staff including a Deputy Coordinator, a Financial
Management Specialist, M&E Officer and an International Procurement Specialist. The unit is
further assisted by Financial Management Officers. There is a Project Technical Committee
that meets monthly to discuss issues affecting project implementation. The Project Steering
Committee is chaired by the Minister of Finance and Development Planning and meets
quarterly. The Project Financial Management Unit at the Ministry of Finance and Development
Planning will handle all fiduciary matters. The coordination with the other DPs will take place
through the joint PFM Working Group that meets quarterly to review plans and implementation
progress. A common monitoring and evaluation framework, and an operational plan have been
developed to guide implementation and coordination of the reforms. One key element of this
operation is the Memorandum of Understanding (MOU) in relation to the Pooled Account
between the Government of the Republic of Liberia, the African Development Bank and the
World Bank. A new MOU that is aimed at extending the current collaboration under the pooled
fund has been prepared.
4.1.2 Financial Management
The Ministry of Finance and Development Planning (MFDP) which has responsibility for
the PFM Reform Coordination Unit, will lead the delivery of all project components
except those under the General Auditing Commission (GAC) related to GAC staff capacity
16
building under Sub-component 1.3 on Support to Integrity and Oversight Institutions, whereby
the GAC will manage its own activities. Financial management of the MFDP managed
components will be handled by the Project Financial Management Unit (PFMU) while the
GAC Finance Department will manage accounting for the GAC component. The PFMU and
RCU handled the IPFMRP Phase I, and currently provides financial management services for
more than eighty AfDB, World Bank, and other donor-financed projects in the country. The
GAC has a stand-alone Finance Department headed by a Chief Financial Officer that manages
GAC’s own budget. The GAC Finance Department was also responsible for the successful
financial management of the GAC component of IPFMRP Phase I. The GAC was set up in
2005, while the PFMU was established by the World Bank in 2006 and both have been in
existence for a considerable period of time. Both MFDP and GAC have controls in place that
provide reasonable assurance on the accuracy and timeliness of reports generated by both.
Technical Annex VII provides more details on the financial management and the fiduciary risk
analysis undertaken for IPFMRP Phase II.
The assessment of both the MFDP and the GAC concluded that there is sufficient FM capacity
to ensure: (a) that project funds are used only for the intended purposes in an efficient and
economical way; (b) the preparation of accurate, reliable and timely periodic and annual
financial reports; (c) that any assets purchased using project funds are adequately safeguarded.
The project FM Risk was assessed as moderate.
4.1.3 Disbursement
Disbursement will make use of the Special Account modality with a segregated USD
‘pooled’ account to be domiciled in the Central Bank of Liberia for use by the co-
financing partners. In line with the MOU, the partners will contribute to the pooled fund. The
Special Account will disburse only towards meeting eligible expenditures for the project.
Replenishments will be in accordance with the Bank’s Disbursement Handbook and the
applicable guides in the MOU with the co-financiers. The reimbursement guarantee may be
used for imports. Technical Annex VII provides details of the financial management and joint
financing arrangements.
4.1.4 Audit
The proposed project will continue to use the GAC to audit project funds, although a
private professional firm of auditors will still be required to audit the GAC component of
the project. The private audit firm will be hired on TORs approved by the co-financing
partners, using selection procedures agreed upon in the signed MOU. Both audit reports,
supported by the relevant management letters, will be required to be submitted to the Bank and
the other co-financing partners annually and within six months of the end of the year audited.
The details of the audit arrangements are set out in Technical Annex VII.
4.1.5 Procurement Arrangements
The RCU will have overall responsibility to carry out the procurement management functions
including preparing procurement plans, contract administration and the procurement
monitoring process. In line with the Paris Declaration on Aid Effectiveness (2005), Accra
Agenda for Action (2008), and Busan High Level Forum on Development Effectiveness
(2011), the proposed operation will adopt the common implementation and procurement
arrangement with IDA as the implementing partner for the pooled account. Thus, procurement
17
will be carried out using the World Bank procurement guidelines and joint supervision missions
will be undertaken. To that end, IDA will serve as primary focal point regarding procurement
matters, in consultation with the AfDB. The modalities followed in using the World Bank
Procurement Guidelines in lieu of the Bank’s are described in the Technical Appendices. In
addition, the MOU provides details of the joint implementation arrangement and Bank’s
fiduciary oversight responsibility.
Under IPFMRP Phase I, use of the World Bank Procurement was justified based on the
following reasons: (i) AfDB and World Bank have harmonized their procurement policies,
procedures and standard bidding documents; (ii) The World Bank’s operational framework for
dealing with complaints is reliable and similar to that of AfDB; (iii) AfDB and IDA are both
signatories of the Cross-Debarment Agreement aimed at ensuring, beyond the mutual
recognition of sanctions, the application by each participating institutions of core principles in
its internal mechanism for addressing and sanctioning violations of its anti-corruption policies.
4.2. Monitoring and Evaluation
4.2.1 MFDP will be responsible for the overall monitoring and evaluation activities in
collaboration with the project component managers and beneficiary institutions. AfDB
and other partners will undertake bi-annual supervision missions as part of the common
implementation framework. Project implementation is scheduled to span 3 years, from January
2017 to December 2019. The government will have to submit quarterly progress reports on the
implementation of the project. The quarterly progress reports will present the status of physical
and financial implementation and highlight any problems that might hamper smooth project
implementation. The reports will review progress made in light of the project’s Results-Based
Logical Framework and include a clear presentation of activities undertaken during the period
under review. The reports will also analyze to what extent the activities undertaken have
contributed to the realization of the anticipated project development objectives. RCU will also
be required to prepare and submit to AfDB, a Project Completion Report within six months of
the final disbursement.
Table 4.2: Project Implementation Schedule
Timeframe Milestone Monitoring process
November 2016 Grant approval AfDB
December 2016 Effectiveness GoL
December 2016 Launching workshop AfDB & GoL
December 2016-December 2019 Procurement of goods and services GoL, AfDB, World Bank
March 2017 Joint supervision and monitoring AfDB
June 2018 Mid-term review AfDB
December 2016-December 2019 Disbursement of funds AfDB
December 2019 Project completion report AfDB
18
4.3. Governance
4.3.1 The project will significantly contribute to good fiscal and public financial governance,
particularly through human resource development and technical assistance provided to RCU.
The project will improve the quality and timeliness of public accounting and auditing and
contribute to improved domestic and international confidence in institutions of governance in
general. Furthermore, strengthened financial management institutions and processes will lead
to increased accountability, reduced public sector corruption and more efficient use of public
resources for poverty reduction. The main risks to project governance arise in procurement
decisions, use of project assets and selection of persons to attend training and capacity building
events. Risks will be mitigated through the preparation of a detailed procurement plan, robust
processes for contractors and participant selection and application of the agreed procurement
rules and procedures. Procurement plans will be prepared by the RCU on the basis of agreed
program plans. Financial management of procurement related expenditure will be carried out
by the PFMU. Further training will be provided to RCU and PFMU staff to ensure that they
are fully aware of all requirements and regulations. Compliance with these controls will be
reviewed during supervision missions. An independent audit will be undertaken every year.
4.4 Sustainability
4.4.1 Sustainability is ensured through a number of factors included in the project design and
approach. These factors comprise: (i) Capacity building initiatives that will help government
officials to produce high PFM products on time (PFM strategy, PFM progress reports); (ii)
Development of tailor made manuals, working practices and tools for continued use. In
addition, the project will help create conditions for macroeconomic stability by contributing to
increased revenue and enhanced fiscal discipline.
4.5 Risk management
4.5.1 The table below outlines the residual risks and mitigation measures.
Table 4.5: Summary of Risks and Mitigation Measures
Risks Level Mitigation measures
Risk 1: Capacity constraints: Weak
institutional and human resources
capacity could cause delays or hamper
implementation.
Moderate Mitigation 1: This support is based on a recent
assessment of implementation capacity in
general and the sequenced PFM Reform
Strategy. The project will provide additional
project management capacity and technical
assistance.
Risk 2: Fiduciary Risks: Government
has made notable progress in improving
PFM, but there are still weaknesses in
the fiduciary and control environment.
The weaknesses are especially in the
area of corruption due to weak
prosecution capacity and sanctions
regime.
Moderate Mitigation 2: Government has put in place a
PFM Act (2009), and PFM Reform Strategy and
Action Plan (FY2012-FY2016) that present a
broadly credible program for improvement.
Plans are also underway implement a new PFM
Reform Strategy and Action Plan (FY2017-
FY2020) and to grant prosecutorial power to the
Liberian Anti-Corruption Commission. The
Government’s commitment to, and ownership of,
reforms is high.
19
Risk 3: Implementation Risk: The
risk of delayed project take off.
Low Mitigation 3: To mitigate the negative impact of
this risk, the project will continue to be managed
by the same RCU which has been instrumental in
the successful implementation of IPFMRP and
the government is centralizing the
implementation of all institutional support
projects on PFM through this RCU.
4.6. Knowledge building
The project will strengthen public financial management. Knowledge will be acquired through
skills transfer from technical assistance, as well as through formal and informal training on the
job, locally and regionally. Knowledge will also be built through direct hands on support from
program advisors to enable beneficiaries to undertake their day to day work. The project will
also help to develop guidance manuals, automated financial management systems and various
reporting tools and models, such as the MTFF and macroeconomic models, internal audit
manuals and IFMIS reporting tools. It will support knowledge and diagnostic work through
training on PEFA self-assessment and monitor the quality of public financial governance in
Liberia. Specific arrangements to ensure that knowledge is transferred will include assigning
counterpart staff to work with external consultants, evaluating technical assistance based on
performance on knowledge transfer, and building local capacity in Liberia.
V – LEGAL INSTRUMENTS AND AUTHORITY
5.1. Legal instrument
The bilateral Protocol of Agreements between the Government of Liberia, ADF, and TSF will
be signed by the parties concerned. The instrument is an ADF-13 PBA Grant of UA 3.19 m,
and ADF-13 TSF Pillar III Grant of UA 1.00 m. It also includes the unused balances re-
allocated from the Liberia: Labor-Based Public Works Project and these funds include the
ADF-10 PBA Grant of UA 0.88 m; ADF-10 TSF Pillar I Grant of UA 1.07 m; and ADF-10
TSF Pillar III Grant of UA 0.12 million.5
5.2. Conditions associated with Bank’s intervention
5.2.1 The Protocol of Agreements will come into effect on the date of its signature by the
Government of Liberia and the African Development Fund. The first disbursement of grant
resources will be contingent on the effectiveness of the Protocol Agreement and subject to
entry into force of the Protocol of Agreement.
5 The unused balances reflect the reallocated funds from the Liberia: Labor-Based Public Works Project
approved on December 8, 2007 under ADF-10 (Grant Number 2100155010817).
20
5.3. Compliance with Bank Policies
5.3.1 In view of the need to adopt a joint financing modality and harmonized implementation
arrangements, it is recommended that the Board of Directors approves a waiver to apply the
World Bank Rules and Procedures for procurement of all eligible expenditures specified in this
Appraisal Report. The project complies with all applicable Bank policies.
VI – RECOMMENDATION
Management recommends that the Board of Directors approves UA 6.27 m (US$ 8.72 m),
including the ADF-13 PBA Grant of UA 3.19 m, and ADF-13 TSF Pillar III Grant of UA 1.00
m. Management also recommends that the Board of Directors approves the utilization of the
unused balances from the Liberia: Labor-Based Public Works Project for utilization under
IPFMRP Phase II for the purposes and conditions stipulated in this report, i.e., ADF-10 PBA
Grant of UA 0.88 m; ADF-10 TSF Pillar I Grant of UA 1.07 m; and ADF-10 TSF Pillar III
Grant of UA 0.12 million.
I
APPENDIX 1
COMPARATIVE SOCIO-ECONOMIC INDICATORS 2000 2011 2012 2013 2014 2015 2016
LBR
Indicators Unit 2000 2011 2012 2013 2014 2015 (e) 2016 (p)
National Accounts
NY.GNP.MKTP.CDNY.GNP.MKTP.CDGNI at Current Prices Million US $ 549 1,305 1,508 1,589 1,627 ... ...
NY.GNP.PCAP.CD.ADBN
YGNI per Capita US$ 190 320 360 370 370 ... ...
NY.GDP.MKTP.CD.ADBNY.GDP.MKTP.CDGDP at Current Prices Million US $ 661 1,538 1,802 2,603 2,053 2,750 2,869
NY.GDP.MKTP.KD.ADBNY.GDP.MKTP.KDGDP at 2000 Constant prices Million US $ 661 887 961 1,045 1,052 1,057 1,086
NY.GDP.MKTP.KD.ZG.ADBNY.GDP.MKTP.KD.ZGReal GDP Growth Rate % 0.0 7.9 8.3 8.7 0.7 0.4 2.8
NY.GDP.PCAP.KD.ZG.ADBNY.GDP.PCAP.KD.ZGReal per Capita GDP Growth Rate % -5.2 4.6 5.4 6.1 -1.7 -1.9 0.3
NE.GDI.TOTL.ZS.WEON
EGross Domestic Investment % GDP 23.5 37.0 41.0 42.5 22.7 29.6 44.2
NE.GDI.FPUB.ZS.WEON
E Public Investment % GDP 12.7 4.9 4.0 5.2 7.6 8.5 8.9
DeductionN
E Private Investment % GDP 10.8 32.1 36.9 37.3 15.1 21.1 35.3
NY.GNS.TOTL.ZS.WEON
YGross National Savings % GDP ... ... ... ... ... ... ...
Prices and Money
FP.CPI.TOTL.ZG.ADBF
PInflation (CPI) % 5.3 8.5 6.8 7.6 9.9 7.7 7.0
PA.NUS.FCRF.ADBPA.NUS.FCRFExchange Rate (Annual Average) local currency/US$ 41.0 72.2 73.5 77.5 83.9 84.5 84.7
FM.LBL.MONY.ZG.ADBF
MMonetary Growth (M2) % -97.1 49.5 15.9 21.8 5.2 ... ...
FM.LBL.GDP.MQMY.ZS.ADBF
MMoney and Quasi Money as % of GDP % 0.2 10.8 10.5 8.4 10.3 ... ...
Government Finance
GB.RVC.IGRT.ZS.WEOG
CTotal Revenue and Grants % GDP 17.1 26.5 29.0 41.9 27.3 33.0 31.6
GB.XPD.TOTL.ZS.WEOG
CTotal Expenditure and Net Lending % GDP 16.8 27.1 32.1 42.4 30.2 45.2 38.0
GB.FIS.IGRT.ZS.WEOG
COverall Deficit (-) / Surplus (+) % GDP 0.3 -0.6 -3.0 -0.3 -2.9 -9.9 -5.6
External Sector
TX.QTY.MRCH.ZG.WEOTG.WEO.TXG_R.ZGExports Volume Growth (Goods) % ... ... 75.1 20.4 -3.3 -13.4 13.5
TM.QTY..MRCH.ZG.WEOTG.WEO.TMG_R.ZGImports Volume Growth (Goods) % ... ... 2.9 11.7 10.7 30.7 -6.9
TT.PRI.MRCH.ZG.WEOTG.WEO.TTT.ZGTerms of Trade Growth % ... ... -26.7 -3.1 -19.2 -19.8 7.1
BN.CAB.FUND.CD.WEOBG.CAB.CDCurrent Account Balance Million US $ -93 -519 -647 -721 -495 -1,014 -917
BN.CAB.GDP.ZS.WEOBG.WEO.ADB.CAB.GDP.ZSCurrent Account Balance % GDP -14.0 -33.7 -35.9 -27.7 -24.1 -36.9 -32.0
FI.RES.IGLD.MM.ADBFI.RES.TOTL.MOExternal Reserves months of imports 0.0 3.0 2.9 2.8 2.9 ... ...
Debt and Financial Flows
DT.SRV.ANTE.ZS.WEODT.WEO.TDS.PAI.EXP.ZSDebt Service % exports 0.0 3.8 4.6 2.1 6.2 8.1 4.8
DT.DOD.DECT.GDP.ZSG.WEODT.WEO.ADB.DOD.GDP.ZSExternal Debt % GDP 712.3 10.7 10.4 11.9 17.8 24.3 28.3
DT.NFL.TOTL.CD.ADBDC.DAC.NTF.CDNet Total Financial Flows Million US $ 632 617 2,086 -1,841 842 ... ...
DT.ODA.ALLD.CD.ADBDC.DAC.ODA.CDNet Official Development Assistance Million US $ 67 761 566 535 744 ... ...
BN.KLT.DINV.CD.ADBDC.UNC.PVF.FDI.CDNet Foreign Direct Investment Million US $ 21 785 985 1,061 302 ... ...
Source : AfDB Statistics Department; IMF: World Economic Outlook, October 2015 and International Financial Statistics, October 2015;
AfDB Statistics Department: Development Data Portal Database, March 2016. United Nations: OECD, Reporting System Division.
Notes: … Data Not Available ( e ) Estimations ( p ) Projections Last Update: April 2016
LiberiaSelected Macroeconomic Indicators
0.0
2.0
4.0
6.0
8.0
10.0
12.0
14.0
200
4
200
5
200
6
200
7
200
8
200
9
201
0
201
1
201
2
201
3
201
4
201
5
201
6
%
Real GDP Growth Rate, 2004-2016
0
5
10
15
20
20
04
20
05
20
06
20
07
20
08
20
09
20
10
20
11
20
12
20
13
20
14
20
15
20
16
Inflation (CPI),
2004-2016
-40.0
-35.0
-30.0
-25.0
-20.0
-15.0
-10.0
-5.0
0.0
2,0
04
2,0
05
2,0
06
2,0
07
2,0
08
2,0
09
2,0
10
2,0
11
2,0
12
2,0
13
2,0
14
2,0
15
2,0
16
Current Account Balance as % of GDP,
2004-2016
Goal 1: Eradicate extreme poverty and hunger 19901 20002 20133
Employment to population ratio, 15+, total (% ) 57.3 57.7 59.2
Malnutrition prevalence, weight for age (% of children under 5) ... 22.8 20.4
Poverty headcount ratio at $1,25 a day (PPP) (% of population) ... ... 83.8
Prevalence of undernourishment (% of population) 39.2 30.1 31.4
Goal 2: Achieve universal primary education
Literacy rate, youth female (% of females ages 15-24) ... ... 37.2
Literacy rate, adult total (% of people ages 15 and above) ... ... 42.9
Primary completion rate, total (% of relevant age group) ... ... 65.2
Total enrollment, primary (% net) ... ... 40.6
Goal 3: Promote gender equality and empower women
Proportion of seats held by women in national parliaments (% ) ... 5.3 11.0
Ratio of female to male primary enrollment ... 73.6 91.6
Ratio of female to male secondary enrollment ... 72.7 82.0
Goal 4: Reduce child mortality
Immunization, measles (% of children ages 12-23 months) ... 41.0 80.0
Mortality rate, infant (per 1,000 live births) 143.9 88.0 59.8
Mortality rate, under-5 (per 1,000) 216.5 125.5 83.2
Goal 5: Improve maternal health
Births attended by skilled health staff (% of total) ... 50.9 46.3
Contraceptive prevalence (% of women ages 15-49) 8.1 10.4 14.8
Maternal mortality ratio (modeled estimate, per 100,000 live births) 1900.0 1300.0 770.0
Goal 6: Combat HIV/AIDS, malaria, and other diseases
Incidence of tuberculosis (per 100,000 people) 219.0 261.0 304.0
Prevalence of HIV, female (% ages 15-24) ... ... 0.3
Prevalence of HIV, male (% ages 15-24) ... ... 0.1
Prevalence of HIV, total (% of population ages 15-49) ... 2.5 1.0
Goal 7: Ensure environmental sustainability
CO2 emissions (kg per PPP $ of GDP) 3.2 1.0 0.7
Improved sanitation facilities (% of population with access) 10.3 15.4 18.2
Improved water source (% of population with access) 58.0 67.3 74.4
Goal 8: Develop a global partnership for development
Net total ODA/OA per capita (current US$) 59.2 67.0 187.6
Internet users (per 1000 people) ... 0.3 37.9
Mobile cellular subscriptions (per 1000 people) ... 29.6 571.2
Telephone lines (per 1000 people) 2.2 2.2 0.0
Sources : ADB Statistics Department Databases; World Bank: World Development Indicators; last update :
UNAIDS; UNSD; WHO, UNICEF, WRI, UNDP; Country Reports,
Note : n,a, : Not Applicable ; … : Data Not Available,1 Latest year available in the period 1990-1995; 2 Latest year available in the period 2000-2004; 3 Latest year available in the period 2005-2013
PROGRESS TOWARD ACHIEVING THE MILLENNIUM DEVELOPMENT GOALS
Liberia
May , 2014
0
100
200
300
400
1990 2000 2013
Incidence of tuberculosis (per 100,000 people)
SH.TBS. INCD
0
20
40
60
80
1990 2000 2013
Employment to population ratio, 15+, total (%)
SL.EMP.TOTL.SP.ZS
0
20
40
60
80
1990 2000 2013
Primary completion rate, total
SE.PRM.CMPT.ZS
0
20
40
60
80
100
1990 2000 2013
Ratio of female to male primary enrollment
SE.ENR.PRIM.FM.ZS
0
50
100
150
200
1990 2000 2013
Mortality rate, infant (per 1000 live births)
SP.DYN.IMRT.IN
0
500
1000
1500
2000
1990 2000 2013
Maternal mortality ratio (modeled estimate, per 100,000 live births)
SH.STA.MMRT.NE
0
200
400
600
1990 2000 2013
Mobile cellular subscriptions (per 1000 people)
IT.CEL.SETS.P3
0
20
40
60
80
1990 2000 2013
Improved water source(%)
SH.H2O.SAFE.TO.ZS
III
APPENDIX 1I
(A) AFDB PROJECTS IN THE BANK’S PORTFOLIO IN LIBERIA
(AS OF JULY 30, 2016)
No Project Name Approval date Closing
date
Amount (UA mil)
Agriculture and Rural Development
1 Agriculture Sector Rehabilitation Project (ASRP) 29.04.2009 30.12.2016 12.50
2 Smallholder Agriculture Productivity Enhancement and
Commercialization (SAPEC) 02.05.2012 30.06.2018 34.54
3 Maryland Oil Palm Plantation (MOPP) 12.02.2014 31.12.2018 14.50
Transport
4 Paving Fish Town-Harper Road Project Phase I 04.09.2013 31.12.2017 42.04
5 MRU Road Construction & Trade Facilitation Project 18.12.2014 30.06.2020 52.08
Governance
6 Integrated Public Financial Management Reform Project 10.09.2012 30.03.2017 3.00
7 Supplementary WAMZ Payment System Development
Project 09.11.2010 31.12.2016 5.00
Water and Sanitation
8 Urban Water and Sanitation Project 18.05.2010 31.05.2017 26.09
9 Fostering Innovative Sanitation and Hygiene in Monrovia 11.01.2013 31.12.2016 0.90
Energy
10 CLSG Electricity Networks Interconnection Project 06.11.2013 31.12.2018 8.10
11 CLSG Electricity Project - Rural Electrification 06.11.2013 31.12.2018 16.8
Banking
12 Equity in Access Bank (& supplementary Equity) 04-08/ 12-12 31.12.2018 0.3
Health Sector- Responding to Ebola
13 Regional Project to Strengthen West Africa’s Public Health
Systems in Response to Ebola Crisis 18.08.2014 31.03.2017 12.0
14 Ebola Budget Support – Fight Back Program (EFBP) / Cote
d’Ivoire, Guinea, Liberia and Sierra Leone 01.10.2014 31.12.2016 40.2
15 Post Ebola Recovery Social Investment Fund 21.10.2015 31.12.2019 1.98
Multi-Sector Capacity Building
16 Capacity Building and Technical Support to the National
Housing Authority 21.03.2014 31.06.2016 0.24
17 Technical Assistance and Capacity Building to LISGIS 11.11.2013 30.06.2016 0.78
18 Programme of Assistance to Trade Support Institution in
Liberia (PASTIL) 10.10.2013 31.12.2016 0.66
IV
(B) SUMMARY OF THE BANK’S PORTFOLIO PERFORMANCE IN
LIBERIA (AS OF DECEMBER 31, 2015)6
6Due to the EVD outbreak in Liberia, the formal supervision of Bank projects in the country was temporarily
suspended due to health security concerns of Bank staff, and this negatively affected the indicator on the
number of operations formally supervised twice a year in comparison to the Bankwide supervision
performance. Nevertheless, desk supervision of Bank projects was undertaken to maintain the
implementation rate and to follow up on necessary project related activities.
Indicator 2013 2014 2015 Bankwide
Average size of Project (UA million) 16.5 14.1 14.5 29.2
Operations formally supervised twice a year (%) 67 60 29 82
Time from approval to 1st Disbursment (no. months) 7.4 14 16 10.8
Annual Disbursments Ratio(%) 13 15.5 14 24
Aging operations total number of operations (%) 0 0 0 6.6
Problem Projects (%) 0 0 0 8
Projects at Risk (%) 8 0 0 9
Commitment at Risk (%) 3 0 0 1
Value of Private Sector % (of approved amount) 16 5.3 5 22
Table ….: Portfolio Performance Indicators- 2015
V
APPENDIX III: SIMILAR PROJECTS FINANCED BY THE BANK AND OTHER
DEVELOPMENT PARTNERS IN LIBERIA
Oth
er
En
erg
y
Ro
ad
s
AfDB
China
EU*
France
Denmark
DFID/UK
Germany
Ireland
Norway
SIDA/Sweden
JICA
United States
World Bank**
UN Systems
UNDP
UNMIL
UNICEF
UNHCR
WFP
WHO
FAO
UNWomen
UNESCO
UNAIDS
Economic Transformation Human DevelopmentGovernance and Public
InstitutionsPeace, Security, and Rule of Law
Infrastructure
Partner Se
cu
rit
y
Pe
ac
e a
nd
Re
co
nc
illi
ati
on
Justi
ce
an
d
Ru
le o
f La
w
Jud
icia
l
Re
form
Priv
ate
Se
cto
r
De
ve
lop
me
nt
Ma
cro
ec
on
om
i
c I
ssu
es
Ag
ric
ult
ure
an
d F
oo
d
Se
cu
rit
y
Po
liti
ca
l
Go
ve
rn
an
ce
Pillar I Pillar II Pillar III Pillar IV
Donor Partnerships in Liberia - Agenda for Transformation 2012-2017 (updated October 2012)
Pu
bli
c S
ec
tor
Mo
de
rn
iza
tio
n
& R
efo
rm
Ec
on
om
ic
Go
ve
rn
an
ce
Ed
uc
ati
on
Fo
re
str
y
He
alt
h a
nd
So
cia
l W
elf
are
So
cia
l
Pro
tec
tio
n
Wa
ter a
nd
Sa
nit
ati
on
Min
era
l
De
ve
lop
me
nt
&
Ma
na
ge
me
nt
VI
APPENDIX IV: LETTER OF REQUEST FROM THE
GOVERNMENT OF LIBERIA
VII
APPENDIX V: THE BANK’S VALUE ADDITION UNDER IPFMRP - PHASE I
The Bank’s Board approved US$4.6 m (UA 3m) for the Integrated Public Financial
Management Reform Project (IPFMRP) on September 18, 2012 representing part of its
contribution towards strengthening Liberia’s PFM reform effort. IPFMRP had five inter-
related components each supporting the advancement of seven thematic areas embodied
within the PFM Reform Strategy and Action Plan (FY2012-FY2016): (i) comprehensive
and credible budgeting; (ii) robust IT systems to support PFM operations; (iii) revenue
mobilization; (iv) enhanced transparency and accountability; (v) enhanced controls and
respect of the PFM legal framework; (vi) strengthening treasury management and; (vii)
fiscal decentralization.
(1) Enhanced budget planning systems, coverage and credibility. Based on the 2016
PEFA, PI 1-3 scores representing enhanced budget credibility recorded marked
improvement. Revenue forecasting capacity improved despite the Ebola outbreak. This
improvement was due to increased collaboration between the macro forecasting units in
MFDP and LRA. As part of the effort to transition to MTEF, MFDP prepared and published
an MTEF budgeting manual to guide forecasting estimations. Public investment programs
have now been centralized and controlled through Cabinet, while recurrent expenditures
are budgeted at the level of ministries and agencies. With regard to enhanced budget
coverage, efforts have advanced in migrating 15 donor-financed projects in PFMU into
IFMIS thereby bringing donor-funded expenditure to the scrutiny of the budget preparation
process.
(2) Review of the PFM legal framework, budget execution, accounting and reporting.
The PFM Law (2009) was reviewed and proposed amendments accepted by the MFDP
authorities. IFMIS has also been upgraded to a higher version with better features. As of
FY 2014/15, 69% of the budget was executed in the system. The GoL also prioritized
security ensuring that the current IFMIS platform is more secure. Notable accomplishments
in this area include the first ever adoption of an Information Security Policy that was
promulgated by the Minister of Finance and Development Planning across IFMIS-
connected ministries and agencies. An independent international security firm was hired to
undertake a security audit of the system and provide recommendations on best security
practices that have been implemented. The Civil Service Module of IFMIS was also
deployed thereby establishing better controls between personnel records and payroll
management. The electronic document management system was launched in January 2016,
the objective being to serve as a repository of supporting documentation for transactions.
The project has also completed the development of a system requirement document for e-
procurement. There have also been steady improvements with the preparation and
publication of the Consolidated Fund financial statements by the Comptroller and
Accountant General Department (CAGD).
(3) Revenue Mobilization and Administration. The objective of the third component of
IPFMRP on Revenue Mobilization and Administration was to complement efforts
aimed at improving the efficiency and integrity of revenue administration and
increase domestic revenue of central government entities. This component had three
VIII
sub-components: (a) Capacity Development of Customs; (b) Tax Automation (SIGTAS);
and (c) Establishment of Revenue Authority. The most relevant achievement of the three
sub-components was the establishment of the Liberia Revenue Authority (LRA). LRA was
established in July 2014, but the initiation of recruitment was delayed until January 2015
due to the EVD crisis. The allotted resources for LRA have improved, with a budgetary
allocation of US$ 13.1 m provided in FY2014/15 increasing to US$ 16.1 m in FY2015/16.
Since the establishment of LRA, national revenue performance has improved significantly,
particularly for customs revenues, but the key capacity challenge relates to taxation within
the natural resource sector which will be addressed by this project.
(4) Enhancing transparency and accountability. Scrutiny of the budget has improved
through the analytical reviews conducted by the Legislative Budget Office (LBO). The
budget for FY 2015/16 was passed into law only 2 months later than the statutory deadline
of June 30 (i.e., August 25, 2015), an improvement in comparison to the previous fiscal
years. With regards to ex-post legislative budget oversight, several public hearings have
been held, with 2 consolidated reports covering 11 General Auditing Commission (GAC)
reports tabled before the President of Liberia for action, based on the improved efficiency
of the Public Auditing and Accounts Secretariat.
(5) Other notable achievements under IPFMRP include the fact that the General
Auditing Commission (GAC), having attained enhanced financial and operational
autonomy via the new GAC Act passed December in 2014, GAC completed and
published 18 audits as of FY 2014/15, including the Consolidated Fund financial
statements for FY 2012/13. The Internal Audit Agency (IAA) has also begun to focus on
systemic issues undermining the internal control environment in MD&As, while the use of
the audit tracker has helped create improvements in the implementation of audit
recommendations. The Internal Audit Agency (IAA) now covers more than 70% of
budgeted expenditure in terms of its establishment across MD&As. The non-state actors’
sub-component also continues to make impact in terms of enhancing the public drive for
transparency and accountability on the use of state resources.
The June 2016 joint supervision of the Integrated Public Financial Management Reform
Project (IPFMRP) found that this institutional support project (ISP) was generally on track,
despite some of the activities that were delayed due to the ebola crisis. The likelihood of
the project achieving its development objectives during the remaining implementation
period remains positive and satisfactory. Implementation progress, impaired by the Ebola
outbreak, is also rated moderately satisfactory. In consideration of the remaining project
period and available financial resources, the key priority of the ongoing ISP for the
remaining period is the use of IFMIS as comprehensively as possible, especially at the
county level. The Bank’s contribution to IPFMRP is fully disbursed and the project is
scheduled to close on June 30, 2017.
IX
APPENDIX VI: MAP OF THE REPUBLIC OF LIBERIA