aerial view of valdez marine terminal · 1/23/2014 · east tank farm – 14 500,000-bbl tanks ....
TRANSCRIPT
![Page 1: Aerial View of Valdez Marine Terminal · 1/23/2014 · East Tank Farm – 14 500,000-BBL Tanks . Tanks 2, 4, and 3 at Valdez Marine Terminal . Wintertime Operations May Require Manual](https://reader033.vdocuments.us/reader033/viewer/2022042004/5ea663b1fee1e921c1091b51/html5/thumbnails/1.jpg)
Aerial View of
Valdez Marine Terminal
![Page 2: Aerial View of Valdez Marine Terminal · 1/23/2014 · East Tank Farm – 14 500,000-BBL Tanks . Tanks 2, 4, and 3 at Valdez Marine Terminal . Wintertime Operations May Require Manual](https://reader033.vdocuments.us/reader033/viewer/2022042004/5ea663b1fee1e921c1091b51/html5/thumbnails/2.jpg)
Valdez Marine Terminal
• Currently 2 Berths in service
– 200,000 bph loading capacity, both with Vapor Recovery
• 18 Storage Tanks built originally - 510,000 bbl. each or 9.18 million bbl. total capacity
• Currently 14 tanks in service in east tank farm
![Page 3: Aerial View of Valdez Marine Terminal · 1/23/2014 · East Tank Farm – 14 500,000-BBL Tanks . Tanks 2, 4, and 3 at Valdez Marine Terminal . Wintertime Operations May Require Manual](https://reader033.vdocuments.us/reader033/viewer/2022042004/5ea663b1fee1e921c1091b51/html5/thumbnails/3.jpg)
Tankers Loading at Berths 4 and 5
![Page 4: Aerial View of Valdez Marine Terminal · 1/23/2014 · East Tank Farm – 14 500,000-BBL Tanks . Tanks 2, 4, and 3 at Valdez Marine Terminal . Wintertime Operations May Require Manual](https://reader033.vdocuments.us/reader033/viewer/2022042004/5ea663b1fee1e921c1091b51/html5/thumbnails/4.jpg)
Cathodic Protection—Berth Platform Legs
• OK
Causeway to Berth 5
![Page 5: Aerial View of Valdez Marine Terminal · 1/23/2014 · East Tank Farm – 14 500,000-BBL Tanks . Tanks 2, 4, and 3 at Valdez Marine Terminal . Wintertime Operations May Require Manual](https://reader033.vdocuments.us/reader033/viewer/2022042004/5ea663b1fee1e921c1091b51/html5/thumbnails/5.jpg)
![Page 6: Aerial View of Valdez Marine Terminal · 1/23/2014 · East Tank Farm – 14 500,000-BBL Tanks . Tanks 2, 4, and 3 at Valdez Marine Terminal . Wintertime Operations May Require Manual](https://reader033.vdocuments.us/reader033/viewer/2022042004/5ea663b1fee1e921c1091b51/html5/thumbnails/6.jpg)
East Metering Facility Including Pig Trap and Back Pressure Control System
![Page 7: Aerial View of Valdez Marine Terminal · 1/23/2014 · East Tank Farm – 14 500,000-BBL Tanks . Tanks 2, 4, and 3 at Valdez Marine Terminal . Wintertime Operations May Require Manual](https://reader033.vdocuments.us/reader033/viewer/2022042004/5ea663b1fee1e921c1091b51/html5/thumbnails/7.jpg)
East Tank Farm – 14 500,000-BBL Tanks
![Page 8: Aerial View of Valdez Marine Terminal · 1/23/2014 · East Tank Farm – 14 500,000-BBL Tanks . Tanks 2, 4, and 3 at Valdez Marine Terminal . Wintertime Operations May Require Manual](https://reader033.vdocuments.us/reader033/viewer/2022042004/5ea663b1fee1e921c1091b51/html5/thumbnails/8.jpg)
Tanks 2, 4, and 3 at Valdez Marine Terminal
![Page 9: Aerial View of Valdez Marine Terminal · 1/23/2014 · East Tank Farm – 14 500,000-BBL Tanks . Tanks 2, 4, and 3 at Valdez Marine Terminal . Wintertime Operations May Require Manual](https://reader033.vdocuments.us/reader033/viewer/2022042004/5ea663b1fee1e921c1091b51/html5/thumbnails/9.jpg)
Wintertime Operations May Require Manual Removal of Snow from Tank Tops
![Page 10: Aerial View of Valdez Marine Terminal · 1/23/2014 · East Tank Farm – 14 500,000-BBL Tanks . Tanks 2, 4, and 3 at Valdez Marine Terminal . Wintertime Operations May Require Manual](https://reader033.vdocuments.us/reader033/viewer/2022042004/5ea663b1fee1e921c1091b51/html5/thumbnails/10.jpg)
Interior of Crude Oil Storage Tank
![Page 11: Aerial View of Valdez Marine Terminal · 1/23/2014 · East Tank Farm – 14 500,000-BBL Tanks . Tanks 2, 4, and 3 at Valdez Marine Terminal . Wintertime Operations May Require Manual](https://reader033.vdocuments.us/reader033/viewer/2022042004/5ea663b1fee1e921c1091b51/html5/thumbnails/11.jpg)
Roof Structure of Crude-Oil Storage Tank
![Page 12: Aerial View of Valdez Marine Terminal · 1/23/2014 · East Tank Farm – 14 500,000-BBL Tanks . Tanks 2, 4, and 3 at Valdez Marine Terminal . Wintertime Operations May Require Manual](https://reader033.vdocuments.us/reader033/viewer/2022042004/5ea663b1fee1e921c1091b51/html5/thumbnails/12.jpg)
![Page 13: Aerial View of Valdez Marine Terminal · 1/23/2014 · East Tank Farm – 14 500,000-BBL Tanks . Tanks 2, 4, and 3 at Valdez Marine Terminal . Wintertime Operations May Require Manual](https://reader033.vdocuments.us/reader033/viewer/2022042004/5ea663b1fee1e921c1091b51/html5/thumbnails/13.jpg)
Four loading arms and
one vapor arm are
visible on Berth 4.
The tees at which
ballast water piping
separates from oil
piping are also visible.
Counter-weights are
used to balance the
arms during loading
operations
![Page 14: Aerial View of Valdez Marine Terminal · 1/23/2014 · East Tank Farm – 14 500,000-BBL Tanks . Tanks 2, 4, and 3 at Valdez Marine Terminal . Wintertime Operations May Require Manual](https://reader033.vdocuments.us/reader033/viewer/2022042004/5ea663b1fee1e921c1091b51/html5/thumbnails/14.jpg)
Row of Five Large Vapor Compressors
![Page 15: Aerial View of Valdez Marine Terminal · 1/23/2014 · East Tank Farm – 14 500,000-BBL Tanks . Tanks 2, 4, and 3 at Valdez Marine Terminal . Wintertime Operations May Require Manual](https://reader033.vdocuments.us/reader033/viewer/2022042004/5ea663b1fee1e921c1091b51/html5/thumbnails/15.jpg)
Power Vapor Facility
![Page 16: Aerial View of Valdez Marine Terminal · 1/23/2014 · East Tank Farm – 14 500,000-BBL Tanks . Tanks 2, 4, and 3 at Valdez Marine Terminal . Wintertime Operations May Require Manual](https://reader033.vdocuments.us/reader033/viewer/2022042004/5ea663b1fee1e921c1091b51/html5/thumbnails/16.jpg)
![Page 17: Aerial View of Valdez Marine Terminal · 1/23/2014 · East Tank Farm – 14 500,000-BBL Tanks . Tanks 2, 4, and 3 at Valdez Marine Terminal . Wintertime Operations May Require Manual](https://reader033.vdocuments.us/reader033/viewer/2022042004/5ea663b1fee1e921c1091b51/html5/thumbnails/17.jpg)
Firewater Pumps Building
Firewater intake PWSRCAC consultant confers with Alyeska in main pumps building
![Page 18: Aerial View of Valdez Marine Terminal · 1/23/2014 · East Tank Farm – 14 500,000-BBL Tanks . Tanks 2, 4, and 3 at Valdez Marine Terminal . Wintertime Operations May Require Manual](https://reader033.vdocuments.us/reader033/viewer/2022042004/5ea663b1fee1e921c1091b51/html5/thumbnails/18.jpg)
Fire Protection on Berths
Firefighting monitors on Berth 4 Tank of firefighting foam on Berth 4
Foam Pumping Shed on Berth 4 Close up of berth monitor
![Page 19: Aerial View of Valdez Marine Terminal · 1/23/2014 · East Tank Farm – 14 500,000-BBL Tanks . Tanks 2, 4, and 3 at Valdez Marine Terminal . Wintertime Operations May Require Manual](https://reader033.vdocuments.us/reader033/viewer/2022042004/5ea663b1fee1e921c1091b51/html5/thumbnails/19.jpg)
Tank Farm Fire Protection
Tanks that hold foam at East Tank Farm
Foam Shed that feeds the tire suppression spiders in crude oil tanks
Fire hydrant above West Tank Farm
Spiders are in the bottom of crude oil storage tanks. Foam would be ejected from spiders and rise to the top of the oil to smother a fire if needed
![Page 20: Aerial View of Valdez Marine Terminal · 1/23/2014 · East Tank Farm – 14 500,000-BBL Tanks . Tanks 2, 4, and 3 at Valdez Marine Terminal . Wintertime Operations May Require Manual](https://reader033.vdocuments.us/reader033/viewer/2022042004/5ea663b1fee1e921c1091b51/html5/thumbnails/20.jpg)
Trailer mounted, high volume foam /water monitor
Portable Fire Protection Assets
Fire engine in Alyeska Fire House, with hose ready to deploy
![Page 21: Aerial View of Valdez Marine Terminal · 1/23/2014 · East Tank Farm – 14 500,000-BBL Tanks . Tanks 2, 4, and 3 at Valdez Marine Terminal . Wintertime Operations May Require Manual](https://reader033.vdocuments.us/reader033/viewer/2022042004/5ea663b1fee1e921c1091b51/html5/thumbnails/21.jpg)
Gleason pressure reducing valve
With water pressure around 250 psi at VMT fire hydrants, some fire engines like most from the City of Valdez need a Gleason Valve to reduce the water pressure. There are three Gleason Valves at the VMT.
![Page 22: Aerial View of Valdez Marine Terminal · 1/23/2014 · East Tank Farm – 14 500,000-BBL Tanks . Tanks 2, 4, and 3 at Valdez Marine Terminal . Wintertime Operations May Require Manual](https://reader033.vdocuments.us/reader033/viewer/2022042004/5ea663b1fee1e921c1091b51/html5/thumbnails/22.jpg)
Berth fire protection
Secondary water supply to berths Protection of Cable trays to fire monitors on berth
![Page 23: Aerial View of Valdez Marine Terminal · 1/23/2014 · East Tank Farm – 14 500,000-BBL Tanks . Tanks 2, 4, and 3 at Valdez Marine Terminal . Wintertime Operations May Require Manual](https://reader033.vdocuments.us/reader033/viewer/2022042004/5ea663b1fee1e921c1091b51/html5/thumbnails/23.jpg)
One of the Three Main Diesel-Powered Fire Water Pumps
![Page 24: Aerial View of Valdez Marine Terminal · 1/23/2014 · East Tank Farm – 14 500,000-BBL Tanks . Tanks 2, 4, and 3 at Valdez Marine Terminal . Wintertime Operations May Require Manual](https://reader033.vdocuments.us/reader033/viewer/2022042004/5ea663b1fee1e921c1091b51/html5/thumbnails/24.jpg)
![Page 25: Aerial View of Valdez Marine Terminal · 1/23/2014 · East Tank Farm – 14 500,000-BBL Tanks . Tanks 2, 4, and 3 at Valdez Marine Terminal . Wintertime Operations May Require Manual](https://reader033.vdocuments.us/reader033/viewer/2022042004/5ea663b1fee1e921c1091b51/html5/thumbnails/25.jpg)
Interior of a Large Ballast Water Treatment Tank
![Page 26: Aerial View of Valdez Marine Terminal · 1/23/2014 · East Tank Farm – 14 500,000-BBL Tanks . Tanks 2, 4, and 3 at Valdez Marine Terminal . Wintertime Operations May Require Manual](https://reader033.vdocuments.us/reader033/viewer/2022042004/5ea663b1fee1e921c1091b51/html5/thumbnails/26.jpg)
Biological Treatment Tank Microbial Treatment of Ballast Water
![Page 27: Aerial View of Valdez Marine Terminal · 1/23/2014 · East Tank Farm – 14 500,000-BBL Tanks . Tanks 2, 4, and 3 at Valdez Marine Terminal . Wintertime Operations May Require Manual](https://reader033.vdocuments.us/reader033/viewer/2022042004/5ea663b1fee1e921c1091b51/html5/thumbnails/27.jpg)
Gravity Separation Tanks for Treatment of Ballast Water in Winter
![Page 28: Aerial View of Valdez Marine Terminal · 1/23/2014 · East Tank Farm – 14 500,000-BBL Tanks . Tanks 2, 4, and 3 at Valdez Marine Terminal . Wintertime Operations May Require Manual](https://reader033.vdocuments.us/reader033/viewer/2022042004/5ea663b1fee1e921c1091b51/html5/thumbnails/28.jpg)
Gravity Separation and Biological Treatment Tanks
![Page 29: Aerial View of Valdez Marine Terminal · 1/23/2014 · East Tank Farm – 14 500,000-BBL Tanks . Tanks 2, 4, and 3 at Valdez Marine Terminal . Wintertime Operations May Require Manual](https://reader033.vdocuments.us/reader033/viewer/2022042004/5ea663b1fee1e921c1091b51/html5/thumbnails/29.jpg)
![Page 30: Aerial View of Valdez Marine Terminal · 1/23/2014 · East Tank Farm – 14 500,000-BBL Tanks . Tanks 2, 4, and 3 at Valdez Marine Terminal . Wintertime Operations May Require Manual](https://reader033.vdocuments.us/reader033/viewer/2022042004/5ea663b1fee1e921c1091b51/html5/thumbnails/30.jpg)
Valdez Marine Terminal from the Water
![Page 31: Aerial View of Valdez Marine Terminal · 1/23/2014 · East Tank Farm – 14 500,000-BBL Tanks . Tanks 2, 4, and 3 at Valdez Marine Terminal . Wintertime Operations May Require Manual](https://reader033.vdocuments.us/reader033/viewer/2022042004/5ea663b1fee1e921c1091b51/html5/thumbnails/31.jpg)
500-2 Response Barge
Quick Time™ and aTIFF (Uncompress ed) dec ompres sor
are needed to s ee this picture.
![Page 32: Aerial View of Valdez Marine Terminal · 1/23/2014 · East Tank Farm – 14 500,000-BBL Tanks . Tanks 2, 4, and 3 at Valdez Marine Terminal . Wintertime Operations May Require Manual](https://reader033.vdocuments.us/reader033/viewer/2022042004/5ea663b1fee1e921c1091b51/html5/thumbnails/32.jpg)
Heavy Snow at the Valdez Marine Terminal
![Page 33: Aerial View of Valdez Marine Terminal · 1/23/2014 · East Tank Farm – 14 500,000-BBL Tanks . Tanks 2, 4, and 3 at Valdez Marine Terminal . Wintertime Operations May Require Manual](https://reader033.vdocuments.us/reader033/viewer/2022042004/5ea663b1fee1e921c1091b51/html5/thumbnails/33.jpg)
Control Console at Operational Control Center