aera & shell westcarb annual meeting portland, or october 2004 ventura green electricity, h 2...
TRANSCRIPT
AERA & SHELL
WESTCARB Annual Meeting Portland, OR October 2004
Ventura Green Electricity, H2 and CO2 EOR
Scott L. Wellington, PhD
Research Advisor
Shell International E&P
Representing AERA and SHELL
AERA & SHELL
Presentation Outline:
• Vision
• Ventura Phase II Project Outline
• Key Elements
• Scope, Scaling and Cost
• Stakeholder Participation
• Future Technology Improvements
• Discussion
AERA & SHELL
Vision Clean Efficient and Responsible Fossil Fuel Usage
Capture, Reuse and/or Sequester CO2 and other Contaminants
Increase Efficiency and the use of Renewable Energy Sources
Bio, Wind and Wave .......
Include All Stakeholders
Success Depends on Public and Private Support
Develop a Real, Transparent and Measurable Plan
“Staircase” the Project to communicate timing and goals
Get Going Today on Making the Plan into Reality
Phase II Should Demonstrate a Significant Step Toward the Vision
AERA & SHELL
Green power for localuse and to grid
H2
CO2
Oil topipeline
Gas
HydrogenUnit
SeparatorCom-
pressor
Ventura Oil Reservoir
GasTurbine
Hydrogen to highway
CO2 EOR / storage
Green Power, HGreen Power, H22 and Oil minus CO and Oil minus CO22
AERA & SHELL
Scope, Scaling, Cost and Opportunity:
• Demonstrate the Integrated Clean Power System
• Use “Catalogue-Ready”Components
• The Project Scale must be Credible
• Large Enough to Confidently Scale Expansions
• Small Enough that it is Manageable in Phase II
• Publish (Share) the Project Data
• Future Technology Improvements to Cut Costs
• Expand and Apply in US and Beyond
AERA & SHELL
Green power for localuse and to grid
H2
CO2
Oil topipeline
Gas
HydrogenUnit
SeparatorCom-
pressor
Ventura Oil Reservoir
GasTurbine
Hydrogen to highway
CO2 to Storage
Power plus HPower plus H22 and Oil minus CO and Oil minus CO22
AERA & SHELL
Scaling Discussion:
Fuel Composition & Volume
H2 Purity & Volume
H2 Manufacturing
Technology
Oil Recovery Volume
CO2 Purity & Volume
Power Gen. Capacity
H2 Turbine Availability
AERA & SHELL
H2 Volume to CO2 Volume Relationship
The Majority of H2 is Produced by Steam Methane Reforming
CH4 + 2H2O = CO2 + 4H2
The method Ideally produces 4 H2 for every CO2
Relative Demand Example:
~ 6 Mscf CO2 / bbl of Light Oil Recovered
On a Recovered Oil Basis one obtains:
24 (= 6 X 4) times as much H2 as CO2
AERA & SHELL
CO2 Oil Recovery Scaling Example:
• Assume Oil Production = 15,000 bbl/day
1% CO2 EOR Increase is Too Small
10% is Probably Acceptable
> 10% more like 30% is Desirable
• Assume 6 Mscf CO2 / bbl of Oil
10% Increase ( 1,500 bbl/d ) Requires 9,000 Mscf / day of CO2 injection
AERA & SHELL
Steam Reforming the 5.3 MMscfd of Associated Gas (74% methane, 8% ethane, 8% propane, …)
Yields 17 MMscf/d of Hydrogen
23,000 kWe of “Green” Power
6,600 Mscf/d CO2 and 1,100 bbl/d Oil
HMU with CO2 Capture ~ $10 million
H2 Turbine ~ $10 million
CO2 Compressor Cost ~ $15 million
HMU = Hydrogen Manufacturing Unit
AERA & SHELL
Future Improvements Post Phase II:
The Ventura Project could be Expandedin the Future using New Technologies:
Less Expensive H2/CO2 Manufacture and Separation –
• Membrane Air Separation?
• Hydrogen/CO2 Membrane Separation?
Less Expensive Compression – “Thermal Compression”?
More Efficient Electrical Generation – Fuels Cells?
Gasification of Bio-Sourced HCs to Produce H2 and CO2?
AERA & SHELL
Green power for localuse and to grid
H2
CO2
Oil topipeline
Gas
HydrogenUnit
SeparatorCom-
pressor
Ventura Oil Reservoir
GasTurbine
Hydrogen to highway
CO2 EOR / storage
Green Power, HGreen Power, H22 and Oil minus CO and Oil minus CO22
AERA & SHELL
Ventura Phase II Green Power & CO2 EOR Do we Agree to Proceed?
Refine Equipment List, Cost and Timing
Add Field Implementation Requirements
Share Results with all Stakeholders – Proceed?
Appoint Project Manager and Team
Prepare Project Grant/Funding Request
Develop Detailed Project Plan – Proceed?
Execute Build Plan with Report Schedule
Operate Project including Periodic Documentation
Complete with Final Reports and Recommendations
AERA & SHELL
Challenges and Opportunities:
• Technical
Scope and Scale
Complete Detailed Equipment and Field Engineering Cost Analysis
• WESTCARB Decision on Phase II Project
Project Leader and Team to Develop Plan
Alignment with DoE
Stakeholder Acceptance
Permitting
Timing