adw 2: downstream analysis...downstream analysis basin. • onsite basin is 8.95 acres so 10% basin...
TRANSCRIPT
![Page 1: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/1.jpg)
ADW 2:Downstream Analysis
Source: NCDOT
![Page 2: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/2.jpg)
WHY ARE WE HERE?
…to discuss the reasoning and methodology for downstream analysis
![Page 3: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/3.jpg)
POINTS OF DISCUSSION
What is a downstream analysis?Why is a downstream analysis important?How is a downstream analysis performed?
When is a downstream analysis not required?
![Page 4: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/4.jpg)
DOWNSTREAM ANALYSISWhy do we do it?
– to ensure no adverse impacts to downstream structures or properties arising from project related post-developed discharges
When is it required?– all projects with a “significant” post-
developed flow increase (not all increases require detention)
– to evaluate effects of water quantity control structures (detention)
CPv, Qp25, and Qf can be waived where discharge locations drain directly to channels that have a drainage area larger than 5 square miles.
![Page 5: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/5.jpg)
DOWNSTREAM ANALYSIS
What is it?Comparison of hydrographs at:• Each project outfall• End of project’s zone of influence in the
downstream watershed, either:– point where drainage area is 10 times the project
site drainage area, or– large receiving water (lake, river, estuary)
• Intermediate locations of concern (downstream confluences, structures, conveyances)
Project site’s drainage area
Downstream 10% point
Typical analysis points
![Page 6: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/6.jpg)
Importance & Advantages• Reduce high velocity runoff that causes
stream erosion• Analysis can reveal potential downstream
flood impacts• Prevent harmful and unnecessary
detention
DOWNSTREAM ANALYSIS
![Page 7: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/7.jpg)
Tributary to Snake Creek, near Whitesburg, Georgia, showing a washed out bridge. Heavy rain caused flooding in and around the Atlanta area. (Photo from USGS)
DOWNSTREAM ANALYSISImportance & Advantages• Identifies necessary downstream improvements
- Bridges/culverts- Increase existing pipe capacity
![Page 8: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/8.jpg)
DOWNSTREAM ANALYSIS
Importance & Advantages• Avoid potential legal issues
- Protect both owner and engineer
• Document and Record Analysis- Record Downstream Analysis in MS4 Post-
Construction Stormwater Report
![Page 9: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/9.jpg)
DOWNSTREAM ANALYSIS PROCESS FLOWCHART
![Page 10: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/10.jpg)
DOWNSTREAM ANALYSIS PROCESS FLOWCHART
![Page 11: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/11.jpg)
DOWNSTREAM ANALYSIS PROCESS FLOWCHART
• Determine pre- and post-developed basin characteristics (area, CN, Tc)
• Obtain precipitation depth from NOAA website
• Compute pre- and post-developed peak discharges
Qp25 = Overbank Flood Protection = 25 year storm
Qf = Extreme Flood Protection = 100 year storm
![Page 12: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/12.jpg)
DOWNSTREAM ANALYSIS PROCESS FLOWCHART
• Determine pre- and post-developed basin characteristics (area, CN, Tc)
• Obtain precipitation depth from NOAA website
• Compute pre- and post-developed peak discharges
Qp25 = Overbank Flood Protection = 25 year storm
Qf = Extreme Flood Protection = 100 year storm
![Page 13: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/13.jpg)
DOWNSTREAM ANALYSIS PROCESS FLOWCHART
NOAA’s Website Link: https://hdsc.nws.noaa.gov/hdsc/pfds/index.html
![Page 14: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/14.jpg)
DOWNSTREAM ANALYSIS PROCESS FLOWCHART
• Determine pre- and post-developed basin characteristics (area, CN, Tc)
• Obtain precipitation depth from NOAA website
• Compute pre- and post-developed peak discharges
Qp25 = Overbank Flood Protection = 25 year storm
Qf = Extreme Flood Protection = 100 year storm
![Page 15: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/15.jpg)
DOWNSTREAM ANALYSIS PROCESS FLOWCHART
![Page 16: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/16.jpg)
• If Qp25POST increased, stormwater management facility likely required
• Use software for efficient iterative facility design process (Hydraflow Hydrographs, PondPack, HydroCAD, etc.)
DOWNSTREAM ANALYSIS PROCESS FLOWCHART
![Page 17: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/17.jpg)
DOWNSTREAM ANALYSIS PROCESS FLOWCHART
• Determine downstream 10% point
• Note downstream confluences, structures and conveyances and include analysis point at these locations
![Page 18: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/18.jpg)
DOWNSTREAM ANALYSIS PROCESS FLOWCHART
• Compute Qp25PRE and QfPRE at these locations
• Determine hydrographs of downstream basins using software
• Use reach routing to accurately model hydrograph timing
![Page 19: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/19.jpg)
DOWNSTREAM ANALYSIS PROCESS FLOWCHART
• Develop post-developed conditions model (with detention)
• Compare to pre-developed model at confluences, structures and conveyances
![Page 20: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/20.jpg)
DOWNSTREAM ANALYSIS PROCESS FLOWCHART
• Check hydrographs for downstream adverse impacts
• Pond designed to meet outflow requirements at site…
At project outfallPre-developed
Post-developed(with detention)
![Page 21: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/21.jpg)
DOWNSTREAM ANALYSIS PROCESS FLOWCHART
At project outfall
At downstream culvert
• Check hydrographs for downstream adverse impacts
• Pond designed to meet outflow requirements at site…
Pre-developedPost-developed
(with detention)
![Page 22: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/22.jpg)
At project outfall
DOWNSTREAM ANALYSIS PROCESS FLOWCHART
At downstream culvert
At 10% analysis point
• Check hydrographs for downstream adverse impacts
• Pond designed to meet outflow requirements at site…
Pre-developedPost-developed
(with detention)
![Page 23: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/23.jpg)
DOWNSTREAM ANALYSIS PROCESS FLOWCHART
• If adverse impacts exist, consider alteration of pond outlet control structure to mimic pre-development conditions
![Page 24: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/24.jpg)
DOWNSTREAM ANALYSIS PROCESS FLOWCHART
Consider the following to mitigate impacts of detention:
• Upgrade of downstream infrastructure
• Additional drainage easements from affected property owners
Evaluate for adverse effects on FEMA-regulated floodplain
![Page 25: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/25.jpg)
EXAMPLE1.4 MILE ROADWAY WIDENING AND RECONSTRUCTION PROJECT IN CHEROKEE COUNTY
Project includes:
• intersection improvements,
• addition of turn lanes,
• urban roadway section, and
• sidewalks.
![Page 26: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/26.jpg)
EXAMPLEPre-Developed Basin
Basin Outfall
Drainage Basin
![Page 27: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/27.jpg)
EXAMPLEPost-Developed Basin
Basin Outfall
Drainage Basin
![Page 28: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/28.jpg)
EXAMPLE1. Determine pre- and post-developed basin characteristics2. Compute pre- and post-developed peak discharges3. Determine if detention is needed4. Design detention as required5. Determine the basins of the 10% analysis point and all intermediate locations of
concern6. Determine basin physical parameters7. Determine pre-developed peak flows at desired study point8. Determine post-developed peak flows at desired study point without detention9. Determine post-developed peak flows at desired study point with detention10. Compare hydrographs11. Redesign pond Outlet Control Structure (OCS) as necessary
Repeat steps 6-11 for each study point
![Page 29: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/29.jpg)
EXAMPLE
Step #1 – Determine pre- and post-developed basin characteristics
Basin Characteristics:
• Drainage Area: LIDAR, USGS topo maps, DEM
• Land Use: Aerial Photography, GIS datasets, StreamStats
• NRCS Soil Type: Web Soil Survey: http://websoilsurvey.sc.egov.usda.gov/App/WebSoilSurvey.aspx
![Page 30: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/30.jpg)
EXAMPLEStep #1 – Determine pre- and post-developed basin
characteristics
![Page 31: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/31.jpg)
EXAMPLEStep #2 – Compute pre- and post-developed peak discharges
![Page 32: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/32.jpg)
EXAMPLE
Step #3 – Determine if detention is needed
• Compare pre and post: Drainage areas CNs Flows Tc
![Page 33: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/33.jpg)
EXAMPLE
Detention pond design and the downstream analysis can be facilitated using software programs such as Hydraflow Hydrographs and PondPack
Step #4 – Design detention
![Page 34: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/34.jpg)
EXAMPLE
• Detention pond design and the downstream analysis can be facilitated using software programs such as Hydraflow Hydrographs and PondPack
• Spreadsheet tools are available for computation of required volumes (WQv and CPv)
Step #4 – Design detention
![Page 35: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/35.jpg)
EXAMPLE
Create Pre- and Post-Developed basin inputsStep #4 – Design detention
![Page 36: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/36.jpg)
EXAMPLE
Create Pre- and Post-Developed basin inputsStep #4 – Design detention
![Page 37: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/37.jpg)
EXAMPLE
Create Pre- and Post-Developed basin inputsStep #4 – Design detention
![Page 38: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/38.jpg)
EXAMPLE
Create Pre- and Post-Developed basin inputsStep #4 – Design detention
![Page 39: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/39.jpg)
EXAMPLE
Create Pre- and Post-Developed basin inputsStep #4 – Design detention
![Page 40: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/40.jpg)
EXAMPLEStep #4 – Design detention
![Page 41: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/41.jpg)
EXAMPLE
Using L=2W plan layout coupled with volume estimation, you can design your detention pond.
Step #4 – Design detention
![Page 42: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/42.jpg)
EXAMPLEStep #4 – Design detention
Hydrograph output below shows that the 25-year pond routed outflows are less than or equal to pre-developed rates.
![Page 43: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/43.jpg)
EXAMPLE
100-yr peak discharge from pond is much higher than pre-developed
Step #4 – Design detention
![Page 44: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/44.jpg)
EXAMPLE
Redesign the OCS for 100-yr Pre vs Post
Step #4 – Design detention
![Page 45: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/45.jpg)
EXAMPLE
• Point downstream where project basin is ~10% of the downstream analysis basin.
• Onsite basin is 8.95 acres so 10% basin is ~89.5 acres
• Delineation can be done by hand or using USGS StreamStats website tool.
Step #5 – Determine the basins of the 10% analysis point & intermediate locations of concern
https://streamstats.usgs.gov/ss/
![Page 46: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/46.jpg)
EXAMPLEStep #5 – Determine the basins of the 10% analysis point &
intermediate locations of concern
![Page 47: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/47.jpg)
EXAMPLEStep #5 – Determine the basins of the 10% analysis point &
intermediate locations of concern
![Page 48: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/48.jpg)
EXAMPLEStep #5 – Determine the basins of the 10% analysis point &
intermediate locations of concern
Project Outfall
![Page 49: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/49.jpg)
EXAMPLEStep #5 – Determine the basins of the 10% analysis point &
intermediate locations of concern
Project Outfall
![Page 50: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/50.jpg)
EXAMPLEStep #5 – Determine the basins of the 10% analysis point &
intermediate locations of concern
![Page 51: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/51.jpg)
EXAMPLE
• The downstream analysis point should be taken downstream
of the project site just upstream of the next confluence point if
moving the downstream analysis point to the confluence point
increases the size of the downstream analysis basin too
much.
• This may result in the downstream analysis basin to be less
than 10 times the size of the onsite area
Step #5 – Determine the basins of the 10% analysis point & intermediate locations of concern
![Page 52: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/52.jpg)
EXAMPLE
Note: 10% basin is comprised of 2 stream basins
Step #5 – Determine the basins of the 10% analysis point & intermediate locations of concern
![Page 53: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/53.jpg)
EXAMPLE
1: Southern segment of the confluence that the proposed project outfalls into directly
Step #5 – Determine the basins of the 10% analysis point & intermediate locations of concern
![Page 54: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/54.jpg)
EXAMPLE
2: Northern stream segment of the confluence.
Step #5 – Determine the basins of the 10% analysis point & intermediate locations of concern
![Page 55: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/55.jpg)
EXAMPLE
Sub-basin 1
Sub-basin 2
Project Outfall
10% analysis point @
confluence
Study point just upstream of confluence
Step #5 – Determine the basins of the 10% analysis point & intermediate locations of concern
![Page 56: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/56.jpg)
EXAMPLE
StreamStats allows for a shapefile of the drainage basin and its longest flow path (Tc computation) to be downloaded
Step #6 – Determine basin characteristics of desired study point
![Page 57: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/57.jpg)
EXAMPLE
To retrieve basin characteristics, select “Continue”.
Step #6 – Determine basin characteristics of desired study point
![Page 58: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/58.jpg)
EXAMPLE
Step #6 – Determine basin characteristics of desired study point
![Page 59: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/59.jpg)
EXAMPLE
Step #6 – Determine basin characteristics of desired study point
![Page 60: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/60.jpg)
EXAMPLE
![Page 61: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/61.jpg)
EXAMPLE
• Tc – Lag Method• Used for drainage basins where a large segment of
the area is rural in character and has a long hydraulic length
• Can be adjusted to smaller urban watersheds
Step #6 – Determine basin characteristics of desired study point
![Page 62: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/62.jpg)
EXAMPLE
Tc = 𝑳𝑳𝟎𝟎.𝟔𝟔
, and 𝑳𝑳 = {𝒍𝒍0.8(S+1)0.7}/1900Y0.5
where:• L = Lag, hr • Tc = Time of Concentration, hr• 𝑙𝑙 = flow length, ft• Y = average watershed land slope, %• S = maximum soil retention, in• S = 1000
𝐶𝐶𝐶𝐶- 10
• CN = NRCS curve number
Step #6 – Determine basin characteristics of desired study point
![Page 63: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/63.jpg)
EXAMPLE
Step #6 – Determine basin characteristics of desired study point
![Page 64: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/64.jpg)
EXAMPLEModeling Scenarios:
• Determine the pre-developed peak flows at the desired study point
• Determine post-developed peak flows at desired study point without detention
• Determine post-developed peak flows at desired study point with detention
![Page 65: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/65.jpg)
EXAMPLE
Use the same process for on-site basin to input the physical parameters of the downstream basin
Step #7 – Determine the pre-developed peak flows at the desired study point
![Page 66: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/66.jpg)
EXAMPLE
Perform channel reach routing to the downstream study point.
Step #7 – Determine the pre-developed peak flows at the desired study point
![Page 67: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/67.jpg)
EXAMPLE
Combine previous hydrographs• downstream basin (sub-basin 1)• pre-developed basin reach routing
Step #7 – Determine the pre-developed peak flows at the desired study point
![Page 68: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/68.jpg)
EXAMPLE
The resulting hydrograph reflects pre-developed conditions at the downstream study point
Step #7 – Determine the pre-developed peak flows at the desired study point
![Page 69: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/69.jpg)
EXAMPLE
Combine previous hydrographs
• downstream basin (sub-basin 1)
• post-developed basin reach routing
Step #8 – Determine post-developed peak flows at desired study point without detention
![Page 70: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/70.jpg)
EXAMPLEStep #8 – Determine post-developed peak flows at desired study
point without detention
![Page 71: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/71.jpg)
EXAMPLE
Combine previous hydrographs
• routed pond• post-developed basin
reach routing
Step #9 – Determine post-developed peak flows at desired study point with detention
![Page 72: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/72.jpg)
EXAMPLEStep #9 – Determine post-developed peak flows at desired
study point with detention
![Page 73: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/73.jpg)
EXAMPLE
Below are the comparison hydrographs for the study point upstream of the confluence (25-year)
Step #10 – Compare hydrographs
![Page 74: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/74.jpg)
EXAMPLE
Below are the comparison hydrographs for the study point upstream of the confluence (100-year)
Step #10 – Compare hydrographs
![Page 75: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/75.jpg)
EXAMPLE
Over-detention may be required to mitigate adverse effects at the study point.
This step is not applicable for our example.
Step #11 – Redesign pond OCS as necessary
![Page 76: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/76.jpg)
EXAMPLETo review:
1. Analyzed pre- and post-developed onsite basins and determined basin needs detention.
2. Designed a detention pond that meets the 25- and 100-yr requirements at the site and at the downstream study point upstream of the confluence.
3. Now, we need to check the same requirements at the 10% study point. To accomplish this, repeat steps 6-11 for the secondary downstream basin that drains to the 10% point.
![Page 77: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/77.jpg)
EXAMPLEStep #6 – Determine basin characteristics of desired study point
![Page 78: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/78.jpg)
EXAMPLE
• Modeling the 10% basin, including the northern stream segment of the confluence
• Model with physical parameters from StreamStats
Step #7 – Determine the pre-developed peak flows at desired study point
![Page 79: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/79.jpg)
EXAMPLE
Combine the hydrographs
• Northern downstream basin hydrograph (sub-basin 2)
• Pre-developed conditions upstream of the confluence
Step #7 – Determine the pre-developed peak flows at desired study point
![Page 80: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/80.jpg)
EXAMPLEStep #7 – Determine the pre-developed peak flows at desired study
point
![Page 81: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/81.jpg)
EXAMPLE
Combine the hydrographs • Northern downstream basin hydrograph (sub-basin 2)• Post-developed conditions without detention at the
study point upstream of the confluence
Step #8 – Determine post-developed peak flows at the desired study point without detention
![Page 82: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/82.jpg)
EXAMPLEStep #8 – Determine post-developed peak flows at the desired study
point without detention
![Page 83: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/83.jpg)
EXAMPLE
Combine the hydrographs
• Northern downstream basin (sub-basin 2)
• Post-developed conditions with detention at the study
point upstream of the confluence
Step #9 – Determine post-developed peak flows at desired study point with detention
![Page 84: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/84.jpg)
EXAMPLEStep #10 – Compare hydrographs
![Page 85: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/85.jpg)
EXAMPLEStep #10 – Compare hydrographs
![Page 86: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/86.jpg)
EXAMPLE
Re-design pond to over-detain further to mitigate adverse effects at the 10% pointFirst trial reduces weir length in half
Step #11 – Redesign pond OCS as necessary
![Page 87: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/87.jpg)
EXAMPLE
![Page 88: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/88.jpg)
EXAMPLE
![Page 89: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/89.jpg)
EXAMPLE
Need to reduce the weir length even further…Step #11 – Redesign pond OCS as necessary
…until a good design is achieved.
![Page 90: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/90.jpg)
EXAMPLE
![Page 91: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/91.jpg)
EXAMPLE
![Page 92: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/92.jpg)
Detention Outfall
Study Point above confluence
Study Point at confluence
EXAMPLE
![Page 93: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/93.jpg)
SUMMARY
1. Determine pre- and post-developed basin characteristics
2. Compute pre- and post-developed peak discharges
3. Determine if detention is needed
4. Design detention as required
5. Determine the basins of the 10% analysis point and all intermediate locations of concern
6. Determine basin physical parameters
![Page 94: ADW 2: Downstream Analysis...downstream analysis basin. • Onsite basin is 8.95 acres so 10% basin is ~89.5 acres • Delineation can be done by hand or using USGS StreamStats website](https://reader030.vdocuments.us/reader030/viewer/2022040610/5ed28917f7ab5212a71c5dcf/html5/thumbnails/94.jpg)
SUMMARY7. Determine pre-developed peak flows at desired study point
8. Determine post-developed peak flows at desired study point without detention
9. Determine post-developed peak flows at desired study point with detention
10.Compare hydrographs
11.Redesign pond OCS as necessary
Repeat steps 6-11 for each study point