0© 2009 Wellesley Information Services. All rights reserved.
Advanced Subcontracting Tips and Techniques to Model Vendor Capacity (and Material Constraints)
Matt CampbellK2 Professional Services
What We’ll Cover …
• The subcontracting scenario• Master data setup• Subcontracting process flow• Options for modeling subcontracting in SAP APO SNP• Modeling vendor capacity and material constraints• Tips and tricks for solving challenging design issues• Wrap-up
2 3
A Standard Subcontracting Process
Plant for A Subcontractor for B
A
B
A
B
Packaging
4
A Standard Subcontracting Process (cont.)
Plant for A Subcontractor for B
A
B
A
B
ExternalProcurementOrder – ItemCategory “L”
A
B In-HouseProduction
Order
Stock Transfer
Reservation
5
Subcontracting — Provision of Materials by a Third Party
Plant Subcontractor for B
A
B
B
Packaging
Vendor for A
A
6
Subcontracting — Provision of Materials by a Third Party (cont.)
Plant Subcontractor for B
A
B
B
Packaging
Vendor for AA
ExternalProcurementOrder – ItemCategory “L”
ExternalProcurement
Order
What We’ll Cover …
• The subcontracting scenario• Master data setup• Subcontracting process flow• Options for modeling subcontracting in SAP APO SNP• Modeling vendor capacity and material constraints• Tips and tricks for solving challenging design issues• Wrap-up
7
8
Master Data Setup: Example
• Example:
Plant for A Subcontractor for B
A
B
A
B
Label (SAP R/3 Planned)
36082CF – 8 Count Pack Markers (12)
43042C – 96 Count Promotional Pack Markers
Small Bin (SAP R/3 Planned)
9
Master Data Setup: Example (cont.)
• Header material master set up for subcontracting• Transaction MM03
Procurement Type is “F” and the special procurement key set to “30” (subcontracting)
10
Master Data Setup: Example (cont.)
• SAP R/3 BOM exists• Transaction CS03
11
Subcontracting Master Data Setup
1) Create work center for sub-contracting plant (created at the plant where subcontracting is performed — one for each plant)
2) Create routing for subcontract material at the plant
3) Create production version (PV) for subcontract material at plant
4) Add the production version to the subcontract purchasing info record (PIR)
5) Generated and activated the Integration Models to send over the required master data to SAP Advanced Planner and Optimizer (APO)
6) Verify that all relevant APO Master Data is created via the Core Interface (CIF)
7) Add the means of transport to the transportation lanes in APO
12
1. Subcontracting Master Data Setup: Work Center
• Create work center SUBC for sub-con plant (created at the plant where subcontracting is performed — one for each plant)
• SAP ERP transaction CR01
13
1. Subcontracting Master Data Setup: Work Center (cont.)
• Create Work Center (Transaction – CR01)• Can create one work center for all subcontractors if same
formulas are used
Enter formula for “duration” if you want all routings to have a generic duration not based on
quantity producedEnter “DAY” to default unit in routing
14
2. Subcontracting Master Data Setup: Routing
• Create routing for subcontract material at plant• SAP ERP transaction CA01
15
2. Subcontracting Master Data Setup: Routing (cont.)
• Create routing for subcontract material at plant• SAP ERP transaction CA01
Enter the number of days that it takes to produce at the subcontractor. The formula duration does not consider
base quantity.
16
3. Subcontracting Master Data Setup: Production Version
• Create production version for subcontract material at plant• SAP ERP transaction C223• Must check the production version to successfully create Product
Data Structures (PDS) or Production Process Models (PPM) when activating the Integration Models
17
3. Subcontracting Master Data Setup: Production Version (cont.)• If you have multiple vendors that subcontract a material, you will
need to create a separate production version for each vendor• Best to use a naming convention that will allow you to create an
Integration Model that pulls in only subcontracting production versions
• Production version “S001” for vendor 1• Production version “S002” for vendor 2
4. Subcontracting Master Data Setup: Purchasing Info Record• Add the production version to the subcontract purchasing info
record (PIR)• SAP ERP transaction ME12
Enter the production version number. Make sure to use a naming convention to filter all subcontracting PVs
19
5. Master Data Setup: Generate and Activate the Integration Models• Generate and activate each Integration Model and then validate
that the APO master data has been successfully created• SAP ERP transactions CFM1 (Generate), CFM2 (Activate)
20
5. Master Data Setup: Generate and Activate the Integration Models (cont.)• Separate Integration Models are generally created for each of the
following:Purchasing Info Records (including vendors)SAP APO SNP subcontracting PDSPP/DS subcontracting PDS
21
5. Master Data Setup: Generate and Activate the Integration Models (cont.)• Integration Model for Subcontracting Purchasing Info Records
Check “Include Dependent Vendors and Issuing Plants”and all vendors from subcontracting PIRs will be created as locations in APO
Select PIR
Select Subcontracting PIRs
22
5. Master Data Setup: Generate and Activate the Integration Models (cont.)• Integration Model for SNP Subcontracting PDS
Check “SNP Subcontracting”
Select PDS ([SAP] R/3)
In the Production Version field, enter S* to only select subcontracting PVs 23
5. Master Data Setup: Generate and Activate the Integration Models (cont.)• Integration Model for PP/DS Subcontracting PDS
Check “PP/DS Subcontracting”
Select PDS (SAP R/3)
In the Production Version field, enter S* to only select subcontracting PVs
6. Master Data Setup: Verify That All APO Master Data Is Created• Verify that all of the following have been automatically created
via CIF:The vendor is created as a location in APO The subcontract product is extended in APO to the vendor location The input components are extended in APO to the vendor location The transportation lane from the vendor to the plant is created and the subcontract product is assigned to the T-laneThe transportation lane from the plant to the vendor is created and the input components are assigned to the T-laneBoth the SNP and PP/DS PDS have been created
24 25
6. Master Data Setup: Verify That All APO Master Data Is Created (cont.)• Verify that the vendor is created as a location in APO • APO transaction SAPAPO/LOC3 • Location type will be 1011 (Vendor)
26
6. Master Data Setup: Verify That All APO Master Data Is Created (cont.)• Verify that the subcontract header product is extended in APO to
the vendor location • APO transaction SAPAPO/MAT1
27
6. Master Data Setup: Verify That All APO Master Data Is Created (cont.)• Verify that the subcontract input component products are
extended in APO to the vendor location • APO transaction SAPAPO/MAT1
28
6. Master Data Setup: Verify That All APO Master Data Is Created (cont.)• Verify that the transportation lane from the vendor
to the plant is created and the subcontract product is assigned to the transportation lane
• APO transaction SAPAPO/SCC_TL1
The header subcontract product will be assigned to the transportation lane, but there will not be a means of transport assigned yet
29
6. Master Data Setup: Verify That All APO Master Data Is Created (cont.)• Verify that the transportation lane from the
plant to the vendor is created and the input components are assigned to the transportation lane
• APO transaction SAPAPO/SCC_TL1
The input components will be assigned to the transportation lane, but there will not be a means of transport assigned yet
30
6. Master Data Setup: Verify That All APO Master Data Is Created (cont.)• Verify that the SNP PDS is created in APO• APO transaction SAPAPO/CURTO_SIMU
PDS is created at the vendor location in APO
31
6. Master Data Setup: Verify That All APO Master Data Is Created (cont.)• APO transaction SAPAPO/CURTO_SIMU
Fixed Duration set to 21 Days
Resource Consumption
32
6. Master Data Setup: Verify That All APO Master Data Is Created (cont.)• Verify that the PP/DS PDS is created in APO• APO transaction SAPAPO/CURTO_SIMU
33
7. Master Data Setup: Add the Means of Transport to the Transportation Lanes in APO• APO transaction SAPAPO/SCC_TL1
Create the means of transport and include a duration to move products to and from your plant to the subcontractor
What We’ll Cover …
• The subcontracting scenario• Master data setup• Subcontracting process flow• Options for modeling subcontracting in SAP APO SNP• Modeling vendor capacity and material constraints• Tips and tricks for solving challenging design issues• Wrap-up
34 35
Subcontracting Process
• Demand for the Subcontracted Product at our own plant or DC
36
Subcontracting Process (cont.) • Planning run generates a distribution receipt (subcontracting
planned)
37
Subcontracting Process (cont.)
• At the Subcontract Plant, there is a distribution Demand (subcontracting)
• The Demand is met with a Production (Subcontracting Planned)
SNP order takes 21 days to produce
38
Subcontracting Process (cont.)
• At the Subcontract Plant, there is dependent Demand for the components (12 inputs for 1 output)
• Demand date is aligned with the start date for the production• Stock Transfer Reservation created to meet demand
39
Subcontracting Process (cont.)
• At our plant or DC, there is distribution Demand for the component that is meet with a Requisition (or Planned Order)
• Receipt Date is 1/8, in time for shipping it to the subcontractor
40
Subcontracting Process (cont.)
• In SAP ERP, the subcontracting Purchase Requisition will be created
Item Category is set to “L” for subcontracting
41
Subcontracting Process (cont.)
• Component requirements for SAP ERP planned materials added to the requisition
Click on the component button to see the dependent requirements for the components in SAP ERP
42
Subcontracting Process
• In SAP ERP, Requisitions converted into a Purchase Order (PO)
The Distribution Receipt (planned) moves to (TLB- Confirmed)
43
Subcontracting Process (cont.)
• In APO, the Planned Order at the Subcontractor has moved to the Production (Confirmed) key figure
44
Subcontracting Process (cont.)
• Components are transferred to the Subcontractor• SAP ERP transaction ME2O
Component availability can be checked and the Quantity required at the subcontract vendor can be Post Goods Issued
45
Subcontracting Process (cont.)
• Once the subcontractor completes the production, the subcontracted product is send to our plant or DC
• The product is Goods Receipted into inventory
Plant for A Subcontractor for B
A
B
A
B
Label (SAP R/3 Planned)
36082CF – 8 Count Pack Markers (12)
43042C – 96 Count Promotional Pack Markers
Small Bin (SAP R/3 Planned)
What We’ll Cover …
• The subcontracting scenario• Master data setup• Subcontracting process flow• Options for modeling subcontracting in SAP APO SNP• Modeling vendor capacity and material constraints• Tips and tricks for solving challenging design issues• Wrap-up
46 47
Modeling Options in SNP
• SNP heuristics without Capacity Leveling• Capable-to-Match (CTM)• Optimizer
SAP SCM Version Comparison for Subcontracting
SAP SCM 4.0 SAP SCM 4.1 SAP SCM 5.0 SAP SCM 2007 (5.1)
SAP SNP Planning Engines Supported
Only SAP SNP Heuristic and CTM supported with integration to R/3
SAP SNP Heuristic, CTM and the SNP Optimizer
Same as 4.1 Same as 4.1
Processes Not Supported
Capacity Leveling, Deployment and TLB (from subcontractor)
Same as 4.0 Same as 4.0 Same as 4.0
Master Data Set-Up for Subcontracting with Source Location in SAP SNP
T-lane from plant to subcontractor manually created and components manually assigned
If PPMs used, T-lane from plant to subcontractor manually created and components manually assigned
Same as 4.1 Same as 4.1
Master Data Set-Up for Subcontracting with Third-Party Provision in SAP SNP
T-lane from plant to subcontractor manually created and components manually assigned
Same as 4.0 Same as 4.0 Same as 4.0
Optimizer Constraints
Production capacity at the subcontractor or the transport capacity can be a constraint but not both
Same as 4.1 Same as 4.1
What We’ll Cover …
• The subcontracting scenario• Master data setup• Subcontracting process flow• Options for modeling subcontracting in SAP APO SNP• Modeling vendor capacity and material constraints• Tips and tricks for solving challenging design issues• Wrap-up
49
Constraints in Subcontracting
• Can be difficult to obtain accurate capacity information at subcontractor plants
Plant configuration may not be known to plannerAlternate lines may be availableAlternate plants may be available
Workload may not be known to plannerSubcontractor could also be manufacturing for other customers
Capacity information may be withheldCould be treated as commercially sensitive information
50 51
Modeling Vendor Capacity
• If capacity information is obtained, can use the following planning engines using standard SAP subcontracting processes:
CTMOptimizer
• Or set up subcontractor as a dummy plant and use heuristics and Capacity Leveling
If you want integration to SAP ERP, this approach will result in some CIF modifications to generate subcontract orders in SAP ERP
Constraints in Subcontracting
• Constraint information passed as material availabilityStandard Rosetta Net confirmation
Confirmed supply per time periodConfirmed by Material Code
• A material constraint is usually a capacity constraint somewhereBut you may not control the relevant part of the supply chain
Real constraint could be at subcontractor’s supplier
52
Challenges in Modeling Material Constraints in SAP SNP
• All SAP SNP planning engines will plan the net requirements for components
Create Stock Transfer Requisitions from plants modeled in the network, or Purchase Requisitions for the required quantity
• If insufficient supply is found, more will be plannedStandard lead time is used to plan deliveries
Unlike capacity, system does not have concept that supply is limited
53
Approaches to Modeling Material Constraints
• Change master data for planning runChange lead timeUse GI time
• Model materials as resourcesUse capacity profile to model material availability
54
Change Master Data for Planning Run
• ScenarioExisting POs for materialConfirmations/Supplier Response/ASNs are for constrained amount
• For CTM, modify lead time for receipt of materialBAdI/SAPAPO/IF_EX_CTM_MATLOC-MATLOC_MODIFY
• For optimizerModify data when reading and writingBAdI/SAPAPO/SDP_OPT_LOG
• Planning run can only use materials that are actually availableWill create receipts for shortfall, but in far future
55
Considerations for Modifying Material Master Data
• Receipts will be generated for shortage materialWill need to be removed eventually from system
• SAP SNP heuristics not constrained by materialMust use constrained planning engine to model constraints
56
Model Material as Resource
• Create resource to represent material supplyMaintain capacity as available supply
This will require manual entry or custom maintenance• Constraint will be recognized only by CTM and Optimizer planning
enginesHeuristics will indicate material shortage as “overloads”
Must be corrected manually for heuristicsHard to handle multiple constraints with heuristicsCapacity leveling not supported at subcontractors
57
Considerations for Modeling Materials as Capacity
• Allows materials with true shared capacity to be modeled If this information is available
• Must create “dummy” master data objectsResourcesIf using PDS, must create in SAP R/3 as well
Issue to create work centers at vendors• Must build mechanism to maintain capacity
58
What We’ll Cover …
• The subcontracting scenario• Master data setup• Subcontracting process flow• Options for modeling subcontracting in SAP APO SNP• Modeling vendor capacity and material constraints• Tips and tricks for solving challenging design issues• Wrap-up
59
• Difficult to substitute components on the fly (one-time substitution) when converting subcontract requisitions into a PO
• If a component is not in the BOM, it will not be extended to thevendor location in SAP APO
• As a result, the PO will fail in CIF and the requisition will bedriving demand on the wrong component
Component Substitution Issue
60
Component Substitution Potential Solutions
61
• Can manually extend the component to the vendor location and add it to the transportation lane (plant to subcontractor)
This is a lot of work• Can create a dummy subcontracting BOM that contains all
potential components that could be used (maintain a validity date on the BOM that will not come into effect)
This is also a lot of initial setup and it still does not automatically add new components to the super-BOMs
• Create a custom program to allow the user to enter the plant, vendor, and component, and the system will automatically extend the component to the vendor location in SAP APO and add it to the transportation lane
Small development worth the effort if lots of on-the-fly substitution occurs
Other Enhancements — Multiple Production Versions per Subcontractor• As of SAP SCM 5.1, it is possible to have more than one
production version at the location of the subcontractor Available with SAP ERP 7.0 (at least SAP ERP 2005 with EhP03)
• Can assign the source of supply for the subcontracting planned order via order processing or the Detailed Scheduling Planning Board
• New indicator set in customizing “Transfer multiple selection of PDS”
• Transaction CMPDS1 (in SAP ERP) is used to assign the relevant production versions to the purchasing info records
62
What We’ll Cover …
• The subcontracting scenario• Master data setup• Subcontracting process flow• Options for modeling subcontracting in SAP APO SNP• Modeling vendor capacity and material constraints• Tips and tricks for solving challenging design issues• Wrap-up
63
64
Resources
• Subcontracting Release Restrictions for SAP SCMSAP Note 654312 (4.0)SAP Note 713429 (4.1)SAP Note 832393 (5.0)SAP Note 1021662 (SAP SCM 2007)
• CTM Planning FAQSAP Note 855229
65
7 Key Points to Take Home
• You can use SNP functionality to model subcontracting with source location or subcontracting with third-party provision processes
• If using PDS, subcontracting Master Data in SAP ERP will CIF to SAP APO and automatically create transportation lanes and assign products to the lanes
• The SAP APO planning run will generate external procurement orders in SAP R/3 with item category “L” for subcontracting
• As of SAP SCM 4.1, Heuristics, CTM, and the SNP Optimizer support the subcontracting process
• CTM and the Optimizer can be used to plan with subcontractor capacity constraints
66
7 Key Points to Take Home (cont.)
• Material capacity constraints can be modeled using a BAdI to change planned delivery lead times to prevent the CTM or Optimizer planning engines from creating replenishments
• Manual component substitutions to purchase orders in SAP ERP can cause issues if components are not extended to the vendor location in SAP APO
67
Your Turn!
How to contact me:Matt Campbell
68
DisclaimerSAP, SAP R/3, mySAP, mySAP.com, xApps, xApp, SAP NetWeaver®, Duet™, PartnerEdge, and other SAP products and services mentioned herein as well as their respective logos are trademarks or registered trademarks of SAP AG in Germany and in several other countries all over the world. All other product and service names mentioned are the trademarks of their respective companies. Wellesley Information Services is neither owned nor controlled by SAP.
Notes: ______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
Notes: ______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
Notes: ______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
Wellesley Information Services, 20 Carematrix Drive, Dedham, MA 02026
Copyright © 2009 Wellesley Information Services. All rights reserved.