advanced higher national building and … · dimensioned plan of the room is provided in the data...
TRANSCRIPT
[C021/SQP155] 1 ©
100 marks are allocated to this paper.
Attempt questions in each of the Sections as follows:
Section A – Answer questions 1, 2 and 3 (10 marks each)andeither question 4 or question 5 (10 marks).
Section B – Answer any two questions (18 marks each).
Section C – Answer one question only (24 marks).
Worksheets are provided for Questions 7, 8, 9 and 10 (Sections B and C).
Hand these in with your Answer Book.
The following design data booklets are provided with the paper:
Data Booklet for Question 9 (Section C);Data Booklet for Question 10 (Section C).
You will only need to use one of the booklets.
Advanced Higher Ti m e : 3 h o u r s
Building andArchitectural TechnologySpecimen Question Paper
NATIONALQUALIFICATIONS
[C021/SQP155]
Page two[C021/SQP155] 2
SECTION A
Attempt questions 1, 2, 3 and EITHER question 4 OR question 5 in this Section
(total 40 marks)
1. A new six-storey framed building, with a 4 metre deep basement, is to be
constructed on a city centre site which is close to a river.
(a) Identify four aspects of the ground investigation report which would be of
interest to the engineer in the design of the foundations for the building.
(b) Study the borehole log shown in Figure Q1(b). Describe, with the aid of
annotated sketches, an appropriate ground water control system which may
be adopted by the contractor during the excavation and the construction of
the basement. Give reasons for your choice of system.
Marks
4
6
(10)
GROUND LEVEL
TOP SOIL
MADE GROUND (sand,gravel, ash, brick and pottery)
COMPACT SANDY SOIL
DENSE BROWN COURSEGRAVEL
END OF BOREHOLE 86.00
89.00
91.00
91.80
92.00
moisture present at2.0 metres
water present in theborehole at 2.50 metres
REMARKSLEGENDREDUCEDLEVEL
DESCRIPTION
Figure Q1(b)
Page three[C021/SQP155] 3
2. A developer proposes to construct a six-storey framed building on a city centre
corner site. The ground floor will be used for commercial shops and the
remaining floors for luxury residential apartments.
(a) Compare the benefits of specifying a steel frame for the building rather than
a precast concrete or an in-situ concrete frame.
(b) Describe, with the aid of annotated sketches, two methods of providing fire
protection to the structural steelwork.
(c) Describe, with the aid of a sketch, the precautions necessary in the design of
the steel frame to resist wind loading.
3. The external wall construction for a framed building is to include aluminium
rainscreen cladding panels.
(a) Prepare a vertical section through a wall, to an approximate scale of 1:10, to
illustrate the relationship between the rainscreen cladding and the internal
wall finish. Include all necessary notes and critical dimensions to ensure
compliance with current standards.
(b) Explain the meaning of the term “pressure equalisation” in the design of
a curtain wall or rainscreen cladding system and state two detail design
features which attain it.
Marks
4
4
2
(10)
6
4
(10)
Page four[C021/SQP155] 4
Answer Question 4 OR Question 5
4. (a) (i) Briefly explain why the house shown in Figure Q4(a)(i) may be said to
have correct visual scale.
(ii) What makes the group of buildings shown in Figure Q4(a)(ii) appear
to be out of proportion?
(iii) Illustrate graphically, the difference between scale and proportion.
Marks
1
2
2
Figure Q4(a)(i)
Figure Q4(a)(ii)
Page five[C021/SQP155] 5
4. (continued)
(b) (i) Briefly explain what is meant by each of the following terms as used in
architectural design:
(1) form;
(2) function;
(3) mass.
(ii) Produce a sketch to show the relationship between form, function and
mass as used in architectural design.
5. (a) Identify four items of spatial information which would be collected during a
measured survey of an existing building.
(b) A church in the centre of an historic county town is being considered for
re-development as a nightclub. As a member of the design team, you are
asked to consider the factors that could affect decisions on the project. State
one factor in each of the following categories:
(i) social factors;
(ii) functional factors;
(iii) technical factors.
(c) The walls of the church building are constructed of 600 mm thick sandstone
and the internal lath and plaster finish will require to be removed. Explain,
with the aid of an annotated sketch, how a suitable replacement finish,
providing better thermal insulation, could be provided.
Marks
1
1
1
2
(10)
4
3
3
(10)
Page six[C021/SQP155] 6
SECTION B
Attempt any TWO questions in this Section (total 36 marks)
6. (a) Explain what is meant by the following terms relating to foundation design:
(i) settlement;
(ii) subsidence.
(b) An extract from a surveyor’s field notes is shown in Figure Q6(b). This
provides details of cracking on the elevation of a building. Describe possible
causes for the cracks in each of the locations indicated.
(c) An existing masonry wall of a three-storey building, which is showing signs
of serious failure, is to be underpinned with mass concrete.
Describe, with the aid of a sketch, a suitable sequence of operations for the
underpinning.
Marks
2
2
6
8
(18)
11 000 30 000
VERTICAL CRACK
FACING BRICK
DIAGONALCRACK
DIAGONALCRACK
FRONT ELEVATION
Figure Q6(b)
Page seven[C021/SQP155] 7
7. A small office development is to be constructed on a city centre site adjacent to
existing buildings. The site is over a deep bed of sandy gravel.
(a) Explain the following terms as they relate to types of pile foundations:
(i) replacement pile;
(ii) displacement pile.
(b) (i) Select a suitable type and system of pile for the project, giving reasons
for your choice.
(ii) Describe, with the aid of annotated sketches, the construction sequence
for the pile system selected.
(c) Worksheet Q7 shows an incomplete vertical section through a single-storey
basement wall. The internal accommodation of the basement is to be used
for offices.
Using the worksheet, complete the drawing to an approximate scale, to
show:
(i) a suitable system of waterproofing the basement;
(ii) a suitable basement floor construction;
(iii) a suitable basement wall construction.
8. A new prestige high-rise city centre office development is to be constructed
using a steel frame.
(a) Discuss the performance standards that would need to be satisfied in the
design and specification of the flooring element of the project.
(b) (i) Select an appropriate system of floor construction for the building and
clearly justify your selection.
(ii) Worksheet Q8 shows an incomplete section through the steel frame.
Using the worksheet, complete the drawing to an approximate scale to
show the construction of the floor and ceiling, including finishes for a
typical office. Include notes to ensure compliance with current
standards.
(c) The flat roof of the building is to be of “warm roof” construction and is to
be finished with a flexible PVC waterproofing system, mechanically fastened
through to a steel deck.
Prepare a fully annotated section through the roof to illustrate the
construction and the detail fixing of the roof finish.
Marks
1
1
2
6
8
(18)
4
2
7
5
(18)
Page eight[C021/SQP155] 8
SECTION C
Attempt ONE question in this Section (24 marks)
9. You have been asked to design a layout for the bedroom of a 16 year old. A
dimensioned plan of the room is provided in the Data Booklet for Question 9
along with ergonomic and anthropometric data and typical sizes of furniture for
the room. Worksheet Q9 shows a plan of the room to an approximate scale of
1:20.
Using the worksheet where possible, and the data booklet:
(a) complete the plan of the bedroom showing the layout of furniture, etc. You
may use the furniture shown in the data booklet or any furniture of your
choice;
(b) dimension the plan, indicating spaces in the room as well as furniture sizes;
(c) present the plan in a clear and attractive manner;
(d) specify if the room is designed for a boy or a girl. Explain your choice of
furniture with particular reference to the sex of the occupant and use of the
room;
(e) explain, with the aid of sketches if necessary, how you used the ergonomic
and anthropometric details in making decisions regarding the layout of the
room and the choice of furniture;
(f) using an appropriate medium, produce a three-dimensional illustration to
display your room layout to best advantage.
All graphical work should be freehand.
A4 sheets of tracing paper are available if you require them to develop
your layout. You DO NOT need to hand these in. Hand in the final
layout on the worksheet.
Marks
5
3
2
3
4
7
(24)
Page nine[C021/SQP155] 9
10. A measured survey has been completed of a church which is to be converted into
a nightclub. Details of the survey are provided in the Data Booklet for
Question 10.
As a member of the design team, you are working for the client on proposals for
the conversion.
Worksheet Q10 shows the upper floor plan to a scale of 1:200.
Complete the following tasks.
(a) Prepare a brief report on two problems which might be encountered with
the Planning Authority and how the scheme may be designed to avoid such
problems.
(b) Sketch, on Worksheet Q10, how you would divide the upper-floor Area 2
into a disco dance floor, a bar and a seating area. Indicate approximate
dimensions and prepare a short report explaining your decisions.
(c) Produce instrument-aided sketches of the following at approximately 1:5
scale:
(i) a method of supporting the proposed steel I-beams which will support
the new upper floor, at the existing external walls;
(ii) the junction of the slated roof and the external walls, showing the
provisions for thermal insulation and ventilation of the roof.
(d) Describe a suitable method of treating the rising damp in the existing walls.
[END OF QUESTION PAPER]
Marks
4
7
5
5
3
(24)
[C021/SQP155] 11 ©
Advanced Higher Ti m e : 3 h o u r s
Building andArchitectural TechnologySpecimen Question PaperWorksheets for Questions 7, 8, 9 and 10
NATIONALQUALIFICATIONS
[C021/SQP155]
Fill in these boxes and read what is printed below.
Full name of centre Town
First name and initials Surname
Date of birth
To be inserted inside the front cover of the candidate’s answer book and returned with it.
Day Month Year Number of seat Candidate number
FOR OFFICIAL USE
Page two[C021/SQP155] 12
rein
forc
ed
con
cre
te b
ase
con
stru
cti
on
join
t
tem
pora
ry
sheet
pil
ing
gro
un
d l
evel
rein
forc
ed
con
cre
te f
loor
slab
SE
CT
ION
TH
RO
UG
H B
AS
EM
EN
T
WO
RK
SH
EE
T Q
7
con
stru
cti
on
join
t
rein
forc
ed
con
cre
te b
ase
men
t w
all
3000
Page three[C021/SQP155] 13
un
ivers
al
beam
ere
cti
on
cle
at
WO
RK
SH
EE
T Q
8
SE
CT
ION
TH
RO
UG
H T
HE
ST
EE
L F
RA
ME
un
ivers
al
colu
mn
scale
of
mil
lim
etr
es
1000
500
0
Page five[C021/SQP155] 15
WORKSHEET Q10
Are
a 2
PLAN OF AREA 2 Approx 1:200 Scale
[END OF WORKSHEET]
UP U
P
[C021/SQP155] 17 ©
Advanced Higher Ti m e : 3 h o u r s
Building andArchitectural TechnologySpecimen Question PaperData Booklet for Question 9
NATIONALQUALIFICATIONS
[C021/SQP155]
Page two[C021/SQP155] 18
BEDROOM
1550
mm
1100
mm
200
mm
800
mm
3200
mm
2800 mm
1550
mm
DIMENSIONS OF ROOM
QUESTION 9
DATA SHEET 1
4200
mm
Page three[C021/SQP155] 19
400mm 900mm
2000
mm
Spacerequired
round bed
250
mm
Single Bed Double Bed
700mm 1500mm
Spacerequired
round bed
550
mm
450
mm
400mm
500
mm
800mm
500
mm
1000mm
Distance from front of drawers approx 1000mm
3 Drawer 4 Drawer 6 Drawer
400mm 500mm 1000mm
BedsideCabinet
SingleWardrobe
DoubleWardrobe
Distance from front of drawers approx 1000mm
QUESTION 9
DATA SHEET 2 for furniture sizes and bedroom ergonomics
900mm
1550
mm
1750
mm
500mm
1550
mm
600mm
800mm
Typical Male
Typical Female
600mm
500mm
Page four
[END OF DATA BOOKLET FOR QUESTION 9]
[C021/SQP155] 20
QUESTION 9
DATA SHEET 3
ANTHROPOMETRIC DATA
[C021/SQP155] 21 ©
Advanced Higher Ti m e : 3 h o u r s
Building andArchitectural TechnologySpecimen Question PaperData Booklet for Question 10
NATIONALQUALIFICATIONS
[C021/SQP155]
Page two[C021/SQP155] 22
QUESTION 10
DATA SHEET 1
St Andrews Church, High Street
Drawings produced from measured survey on further Data Sheets.
FABRIC REPORT
RECOMMENDATIONS
Completely strip out all internal structure and finishes—floors, roof, internal walls
and lath and plaster finish.
Treat walls for dry rot.
Make building secure until renovation.
ELEMENT/CONSTRUCTION CONDITION
External Walls
600 mm sandstone
Painted outside
Lath and plaster inside
Internal Walls
Timber stud partitions
Lath and plaster finish
Non-loadbearing
Ground Floors
Suspended timber on dwarf walls
No solum treatment
Roof
Traditional purlin and rafter
construction with lath and plaster
ceiling
Slate covering on sarking
Services
Gas, water, electricity and drainage
on site
Upper Floor
Timber flooring on joists
Structurally sound
Paint in poor condition
Dry rot in lath
Poor condition
Some traces of dry rot
Rising damp and no under floor
ventilation
Dry rot in joists
Very poor condition due to failure
in roof covering and roof drainage
Some collapse in central areas
All services in need of replacement
Damage to flooring and joists due
to roof collapse
Page three[C021/SQP155] 23
Are
a 1
Fo
ye
r
UP
UP
UP
GROUND FLOOR PLAN OF CHURCH
GR
OU
ND
FL
OO
R P
LA
N
QUESTION 10
DATA SHEET 2
Page four[C021/SQP155] 24
QUESTION 10
DATA SHEET 3
Are
a 2
Up
pe
r F
oy
er
UP
UP
UPPER FLOOR PLAN OF CHURCH
UP
PE
R F
LO
OR
PL
AN
12000mm
3000
mm
2375
mm
3000
mm
7750
mm
3000m
m
21
500
mm
4000mm
2375
mm
4000mm
20000mm
Page five[C021/SQP155] 25
QUESTION 10
DATA SHEET 4
FRONT ELEVATION
SIDE ELEVATION
CHURCH ELEVATIONS
[END OF DATA BOOKLET FOR QUESTION 10]
[CO21/SQP155]
Advanced HigherBuilding andArchitectural TechnologySpecimen Marking Instructions
NATIONAL QUALIFICATIONS
©
[CO21/SQP155] 27
[C021/SQP155] 28 Page two
Advanced Higher Building and Architectural Technology
Specimen Paper
Marking instructions and Specimen Answers
SECTION A
Marks1. A new six-storey framed building with a 4 metre deep basement, is to be
constructed on a city centre site which is close to a river.
(a) Identify four aspects of the ground investigation report which wouldbe of interest to the engineer in the design of the foundations for thebuilding.
Description of each stratumDepth and level of change of each stratumLocation of samples, disturbed and undisturbedLocation and results of field tests: eg penetration tests, vane test etcResults of laboratory tests: eg chemical analysis (sulphates), pH value etcWater levels and a record of each water strike
Any 4 from the above, 1 mark each. 4
(b) Study the borehole log shown in Figure Q1(b). Describe, with theaid of annotated sketches, an appropriate ground water controlsystem which may be adopted by the contractor during theexcavation and the construction of the basement. Give reasons foryour choice of system.
Wellpoint system with suction pumps.
This is because water is present at 2.5m and the depth of the basement is4.0m, and therefore the water level requires to be lowered duringconstruction of the basement. The wellpoint system is known to be ideal innon-cohesive soils such as sandy gravels shown on the borehole log.
The wellpoint system consists of a number of small diameter vertical wells(normally disposable) connected to a header pipe which is under vacuumfrom a pump. The ground water is forced out of the soil by atmosphericpressure into the header pipe, via the wellpoints, and discharged by thepump.
1
1
2
Sketch shown on the following page. 2(10)
[C021/SQP155] 29 Page three
The 'Wellpoint' system.
ΡΕΙΝΦΟΡΧΕ∆ ΧΟΝΧΡΕΤΕΒΑΣΕΜΕΝΤ
ΗΕΑ∆ΕΡ ΠΙΠΕ
4000
ΩΕΛΛΠΟΙΝΤ
ΦΛΕΞΙΒΛΕ ΧΟΝΝΕΧΤΙΟΝ
ΝΕΩ ΩΑΤΕΡ ΛΕςΕΛ
REINFORCED CONCRETEBASEMENT
HEADER POINT FLEXIBLE CONNECTION
WELLPOINT
NEW WATER LEVEL
[C021/SQP155] 30 Page four
2. A developer proposes to construct a six-storey framed building on a citycentre corner site. The ground floor will be used for commercial shops andthe remaining floors for luxury residential apartments.
Marks
(a) Compare the benefits of specifying a steel frame for the buildingrather than a precast concrete or an in-situ concrete frame.
The principle factors influencing the choice between steel andconcrete are:Speed of erectionCostFloor constructionSize and nature of siteSpans and grid sizesAccuracyAdaptability/Late changesFire resistanceServices integration Any 4 points, one mark
each.4
(b) Describe, with the aid of annotated sketches, two methods ofproviding fire protection to the structural steelwork.
Methods of fire resistance: sprayed materialsintumesent coatingsclad steel in a board based system.encase steel in concrete.
Any two from four. 4
ΣΠΡΑΨΕ∆ ΜΑΤΕΡΙΑΛ
ΒΟΑΡ∆ ΒΑΣΕ∆ ΣΨΣΤΕΜ
BOARD BASEDSYSTEM
SPRAYEDMATERIAL
[C021/SQP155] 31 Page five
(c) Describe, with the aid of a sketch, the precautions necessary in thedesign of the steel frame to resist wind loading.
Marks
Adequate lateral resistance must be provided and this may beachieved by diagonal bracing to provide stiff vertical elementscapable of resisting wind pressure. 2
(10)
ΣΤΕΕΛ Λ ΦΡΑΜΕ
ΣΤΕΕΛ Λ ΦΡΑΜΕ
∆ΙΑΓΟΝΑΛ Λ ΒΡΑΧΙΝΓ ΤΟΡΕΣΙΣΤ ΩΙΝ∆ ΠΡΕΣΣΥΡΕ
STEEL FRAME
STEEL FRAME
DIAGONAL BRACING TORESIST WIND PRESSURE
[C021/SQP155] 32 Page six
3. The external wall construction for a framed building is to includealuminium rainscreen cladding panels.
Marks
(a) Prepare a vertical section through a wall, to an approximate scaleof 1:10, to illustrate the relationship between the rainscreencladding and the internal wall finish. Include all necessary notesand critical dimensions to ensure compliance with currentstandards. 6
(b) Explain the meaning of the term “pressure equalisation” in thedesign of a curtain wall or rainscreen cladding system and state twodetail design features which attain it.
Widely used technique, where the presence of an air space isexploited as a means of controlling the effects of wind action. Theeffects of kinetic energy, surface tension etc. are controlled byincorporating baffles, labyrinths, drips and upstands in the joints inthe cladding assembly.
Design features are: protected openings, horizontal cavity closers;vertical cavity closers and an air barrier on the internal side of thecavity.Any two. 4
(10)
ΑΙΡ ΒΑΡΡΙΕΡε.γ. ΧΟΝΧΡΕΤΕ ΒΛΟΧΚΩΟΡΚ
ΠΡΟΤΕΧΤΕ∆ ΟΠΕΝΙΝΓΣ
ΙΝΣΥΛΑΤΙΟΝ
ΙΝΤΕΡΝΑΛ Λ ΩΑΛΛ Λ ΦΙΝΙΣΗε.γ. ΠΛΑΣΤΕΡΒΟΑΡ∆ ΦΙΞΕ∆ΩΙΤΗ ΠΛΑΣΤΕΡ ∆ΑΒΣ.
ΡΑΙΝΣΧΡΕΕΝ ΧΛΑ∆∆ΙΝΓ ΠΑΝΕΛΣ
130
200
INTERNAL WALL FINISHEG PLASTERBOARD FIXEDWITH PLASTER DABS
RAINSCREEN CLADDING PANELS
INSULATION
PROTECTED OPENINGS
AIR BARRIEREG CONCRETE BLOCK WORK
[C021/SQP155] 33 Page seven
4. (a) (i) Briefly explain why the house shown in Figure Q4(a)(i) may besaid to have correct visual scale.
The candidate’s answer should cover the substance of the following:
A house should not be intimidating to normal users, so the scaleshould be related to an average human.The figure shows human forms beside the house at a size to suit thedoor, steps etc. This gives the building correct visual scaleprovided the human forms are in the same plane as the building. 1
(ii) What makes the group of buildings shown in Figure Q4(a)(ii) appear to be out of proportion?
The group shows a tall tower block beside lower buildings.The tower block seems to be crushed by the lower buildings and thelower buildings seem to be dominated by the tower block. 2
(iii) Illustrate graphically, the difference between scale and proportion.
This building shows all the elements, doors, windows and over-allshape to be reasonably in proportion and the scale would normallybe assumed to be domestic. However the inclusion of the figure infront shows that the building is much larger scale than domestic andmay indicate a much larger building.
Other examples are acceptable. 2
Marks
[C021/SQP155] 34 Page eight
(b)(i) Briefly explain what is meant by each of the following terms as usedin architectural design:
(1) form;(2) function;(3) mass.
Form is the structural system used e.g. framed, load bearing wall,cross wall, space frame etc. 1Function is what the building will be used for expressed in thedesign e.g. school, offices, flats, church etc. 1Mass is the relationship between the design and the apparent 'weight'of the building. This is related to the size or volume of the buildingand can be offset by use of openings, windows or different finishes. 1
(ii) Produce a sketch to show the relationship between form, function andmass as used in architectural design.
The sketch shows an aircraft hanger beside a domestic scale building.The hanger is massive beside the smaller building and the shape of thehanger expresses the structural form from which it was created andalso the functional requirement of large uninterrupted space internally.
Any other suitable example will be acceptable. 2 (10)
5. (a) Identify four items of spatial information which would be collectedduring a measured survey of an existing building.
Any four items will be acceptable, such as:
Position of wallsPosition of doors and windowsPosition of servicesHeights of sills, heads, ceilings etc. 4 x 1 4
Marks
[C021/SQP155] 35 Page nine
(b) A church in the centre of an historic county town is being considered forre-development as a nightclub. As a member of the design team, youare asked to consider the factors that could affect decisions on theproject. State one factor in each of the following categories:
(i) social factors;(ii) functional factors;(iii) technical factors.
The candidate’s answer must cover one relevant factor in each category.Acceptable factors are as follows:
(i) Social factors could include the special memories a church mighthave for those of the public married or baptised etc in the church.The objectors would have to be appeased in some way. 1
(ii) Functional factors could include the shape of the existing building,the floor to floor/ceiling heights, the position of openings etc. 1
(iii) Technical factors could include the cost to upgrade the fabric tocurrent standards e.g. thermal insulation, damp proofing, requirementfor new opening may not be allowed etc. 1
(c) The walls of the church building are constructed of 600mm thicksandstone and the internal lath and plaster finish will require to beremoved. Explain, with the aid of an annotated sketch, how a suitablereplacement finish, providing better thermal insulation, could beprovided.
One solution would be to strap the walls and add insulation betweenthe straps, with all necessary vapour protection.External insulation would not be acceptable as the outside appearancewould be altered.
3 (10)
Polythene vapour barrieron stone inner face100mm insulation between 100 50mm battens12·5mm foil backed plasterboard
Marks
[C021/SQP155] 36 Page ten
SECTION B
Marks
6. (a) Explain what is meant by the following terms relating to foundationdesign:
(i) settlement;(ii) subsidence.
(i) Settlement is downward movement brought about by thepressure from a foundation causing compression of the ground. Itis the differential settlement of one part of a building relative toanother that produces distortion and cracking. 2
(ii) Subsidence is the sudden downward movement of the groundbrought about by an activity in the ground such as mining, soilerosion, removal of water from the ground (particularly in claysoils), compression of loose or man-made fill etc. 2
(b) An extract from a surveyor’s field notes is shown in Figure Q6(b). Thisprovides details of cracking on the elevation of a building. Describepossible causes for the cracks in each of the locations indicated.
Diagonal cracksSubsidence caused by:Mining below groundSoil erosionFrost heaveShrinkage of clay soil caused by removal of water either by trees orprolonged hot weather.Man-made fill at that corner of the building. Any three for 3 marks 3
Vertical crackTension cracks caused by thermal and moisture movements. Lack ofany movement joints in masonry.Swelling of a clay subsoil in prolonged wet weather.Moisture expansion of clay bricks. 3
[C021/SQP155] 37 Page eleven
(c) An existing masonry wall of a three-storey building, which is showingsigns of serious failure, is to be underpinned with mass concrete.Describe, with the aid of a sketch, a suitable sequence of operationsfor the underpinning.
Marks
Excavate to the required depth systematically in adjoining baysbeneath the existing foundation.Fill the excavation with concrete and then pin up the small gapbetween the old and new foundation with slate and dense mortar.The sequence is indicated by the numbers on the sketch below. 4
Sketch 4(18)
[C021/SQP155] 38 Page twelve
7. A small office development is to be constructed on a city centre siteadjacent to existing buildings. The site is over a deep bed of sandygravel.
Marks
(a) Explain the following terms as they relate to types of pilefoundations:
(i) replacement pile;(ii) displacement pile.
(i) A replacement pile is constructed by removing ground(normally by boring) and replacing it with reinforcedconcrete or grout. 1
(ii) A displacement pile is constructed by displacing theground laterally by driving in a preformed pile or tube. 1
(b) (i) Select a suitable type and system of pile for the project,giving reasons for your choice.
Continuous flight auger (CFA)Displacement pile such as driven precast or driven cast-in-place piles should not be used near existing buildingsas the displacement may disturb the adjacentfoundations. Vibrations may be a problem together withnoise polution from driving. CFA is a replacement pilewhich is relatively quiet and will not disturb adjacentfoundations. These piles are also suitable in a widevariety of soils 2
(ii) Describe, with the aid of annotated sketches, theconstruction sequence for the pile system selected.
6
[C021/SQP155] 39 Page thirteen
(c) Worksheet Q7 shows an incomplete vertical section through asingle-storey basement wall. The internal accommodation ofthe basement is to be used for offices.
Using the worksheet, complete the drawing to an approximatescale to show:
(i) a suitable system of waterfproofing the basement; (ii) a suitable basement floor construction;(iii) a suitable basement wall construction.
Marks
Worksheet Q7 attached. 8
(18)
[C021/SQP155] 40 Page fourteen
reinforced concrete base
ground level
30
00
reinforced concrete floor slab
reinforced concrete basement wall
construction jointconstruction joint
temporary sheet piling
SECTION THROUGH BASEMENT
W ORKSHEET Q7
ΒΛΙΝ∆ΙΝΓ ΧΟΝΧΡΕΤΕ ( )
∆.Π.Μ. ( 1)
ΡΑΙΣΕ∆ ΑΧΧΕΣΣ ΦΛΟΟΡ ΩΙΤΗΙΝΣΥΛΑΤΙΟΝ ΒΕΛΟΩ ΤΗΕ ΦΛΟΟΡ ( 1)
ΩΑΤΕΡ ΒΑΡ ΩΑΤΕΡ ΒΑΡ ( )
ΤΑΝΚΙΝΓ ΜΕΜΒΡΑΝΕ ( 1)
ΧΟΝΧΡΕΤΕ ΗΟΛΛΟΩ ΒΛΟΧΚΣ ΛΑΙ∆ ∆ΡΨ ( 1)
ΓΡΑΝΥΛΑΡ ΦΙΛΛ
ΠΕΡΦΟΡΑΤΕ∆ ΛΑΝ∆ ∆ΡΑΙΝ ( 1)
ΣΥΣΠΕΝ∆Ε∆ ΧΕΙΛΙΝΓ
ΛΙΓΗΤΩΕΙΓΗΤ ΧΟΝΧΡΕΤΕ ΒΛΟΧΚ
ΙΝΣΥΛΑΤΕ∆ ΠΛΑΣΤΕΡΒΟΑΡ∆ ∆ΡΨ ΛΙΝΙΝΓ ( 2)
M arks awarded shown in brackets. Total 8 marks
ΝΟΤΕΟΤΗΕΡ ΣΟΛΥΤΙΟΝΣ ΩΙΛΛ ΒΕ ΑΧΧΕΠΤΑΒΛΕ.ΣΤΥ∆ΕΝΤΣ ΣΗΟΥΛ∆ ΒΕ ΑΩΑΡΕ ΤΗΑΤ ΤΗΙΣ ΙΣ Α ΓΡΑ∆Ε 3 ΒΑΣΕΜΕΝΤ ΤΟ ΒΣ 8102:1990 ( Χοδε οφ πραχτιχε φορ Προτεχτιον οφ στρυχτρεσ αγαινστ ωατερ φροµ τηε γρουνδ) ΡΕΘΥΙΡΙΝΓ Α ∆ΡΨ ΕΝς ΙΡΟΝΜΕΝΤ.
NOTEOTHER SOLUTIONS WILL BE ACCEPTABLESTUDENTS SHOULD BE AWARE THAT THIS IS A GRADE 3 BASEMENT TOBS 8102 1990 (CODE OF PRACTICE FOR PROTECTION OF STRUCTURES AGAINSTWATER FROM THE GROUND) REQUIRING A DRY ENVIRONMENT
CONCRETEHOLLOWBLOCKS LAIDDRY (1)
TANKING MEMBRANE (1)
GRANULAR FILL
PERFORATED LAND DRAIN (1)BLINDING CONCRETE (½)
WATER BAR WATER BAR (½) D.P.M. (1)
RAISED ACCESS FLOOR WITHINSULATION BELOW THE FLOOR (1)
INSULATED PLASTERBOARDDRY LINING (2)
LIGHTWEIGHT CONCRETE BLOCK
SUSPENDED CEILING
[C021/SQP155] 41 Page fifteen
8. A new prestige high-rise city centre office development is to be constructedusing a steel frame.
Marks
(a) Discuss the performance standards that would need to be satisfiedin the design and specification of the flooring element of the project. Provide a level surface with sufficient strength to support the
dead and imposed loads as set down in current standards. Provide compartmentation and fire resistance between offices
on different floors to comply with current standards. Provide a level surface to receive the chosen finish. Provide resistance to the passage of sound between floors. 4
(b)(i) Select an appropriate system of floor construction for the buildingand clearly justify your selection.
Composite floor comprising a profiled metal deck and in-situreinforced concrete. This floor system uses the profiled metal deckas permanent formwork for an in-situ concrete slab and hencespeeds up construction work. The metal deck also acts as bottomreinforcement to the slab. Good sound insulation and fire resistanceis also achieved. 2
(ii) Worksheet Q8 shows an incomplete section through the steel frame.
Using the worksheet, complete the drawing to an approximate scaleto show the construction of the floor and ceiling, including finishesfor a typical office. Include notes to ensure compliance with currentstandards.
Solution on the attached Worksheet Q8. 7
[C021/SQP155] 42 Page sixteen
1000 500 0scale of millimetres
universal column
universal beamerection cleat
SECTION THROUGH THE STEEL FRAME
ΣΥΣΠΕΝ∆Ε∆ ΧΕΙΛΙΝΓ
ΙΝ−ΣΙΤΥ ΧΟΝΧΡΕΤΕ ΣΛΑΒ ( 1 )
ΣΤΕΕΛ Λ ΡΕΙΝΦΟΡΧΕΜΕΝΤ ( 1 )
ΣΗΕΑΡ ΣΤΥ∆Σ ( 1)
ΠΡΟΠ Π ΦΛΟΟΡ
ΠΡΟΦΙΛΕ∆ ΜΕΤΑΛ Λ ∆ΕΧΚ ( 1)
ΒΟΑΡ∆ ΣΨΣΤΕΜ ΦΙΡΕ ΠΡΟΤΕΧΤΙΟΝ
ΜΑΡΚΣΣΥΙΤΑΒΛΕ ΦΛΟΟΡ ΦΙΝΙΣΗ ( 1 µ αρκ)ΣΥΙΤΑΒΛΕ ΧΕΙΛΙΝΓ ΦΙΝΙΣΗ ( 1 µ αρκ)ΑΠΠΡΟΠΡΙΑΤΕ ΦΛΟΟΡ ΧΟΝΣΤΡΥΧΤΙΟΝ ( 5 µ αρκσ)ΟΤΗΕΡ ΦΛΟΟΡ ΧΟΝΣΤΡΥΧΤΙΟΝ ΣΨΣΤΕΜΣ ΩΟΥΛ∆ ΒΕ ΑΧΧΕΠΤΑΒΛΕ
WORKSHEET Q8
SOLUTION
BOARD SYSTEM FIRE PROTECTION
PROP FLOOR
IN-SITU CONCRETE SLAB (1½)
STEEL REINFORCEMENT (1½)
SHEAR STUDS (1)
PROFILED METAL DECK (1)
SUSPENDED CEILING
MARKSSUITABLE FLOOR FINISH (1 MARK)SUITABLE CEILING FINISH (1 MARK)APPROPRIATE FLOOR CONSTRUCTION (5 MARKS)OTHER FLOOR CONSTRUCTION SYSTEMS WOULD BEACCEPTABLE
[C021/SQP155] 43 Page seventeen
(c) The flat roof of the building is to be of “warm roof” constructionand is to be finished with a flexible PVC waterproofing system,mechanically fastened through to a steel deck.
Marks
Prepare a fully annotated section through the roof to illustrate theconstruction and the detail fixing of the roof finish.
Marks awarded for the sketch shown in brackets, total 5
ΣΤΕΕΛ Λ ΥΝΙςΕΡΣΑΛ Λ ΒΕΑΜ
ΠςΧ ΩΑΤΕΡΠΡΟΟΦ Φ ΜΕΜΒΡΑΝΕΜΕΧΗΑΝΙΧΑΛΛΛΛΨ Ψ ΦΑΣΤΕΝΕ∆ ( 1)
ΒΑΡΡΙΕΡ ΛΑΨΕΡ
ΙΝΣΥΛΑΤΙΟΝ ( 1)
ςΑΠΟΥΡ ΒΑΡΡΙΕΡ ( 1)
ΣΤΕΕΛ Λ ∆ΕΧΚ ( )
ΠςΧ ΣΤΡΙΠ Π ΗΟΤ ΑΙΡ ΩΕΛ∆Ε∆ ( )
ΠΡΟΠΡΙΕΤΑΡΨ Ψ ΜΕΤΑΛ Λ ΒΑΡ ΣΧΡΕΩ ΦΙΞΕ∆ ΤΟ ∆ΕΧΚ ( 1)
PVC WATERPROOF MEMBRANEMECHANICALLY FASTENED (1)
PROPRIETARY METAL BARSCREW FIXED TO DECK (1)
PVC STRIP HOT AIR WELDED (½)
INSULATION (1)
VAPOUR BARRIER (1)
STEEL DECK (½)
STEEL UNIVERSAL BEAM
(18)
BARRIER LAYER
[C021/SQP155] 44 Page eighteen
SECTION C
9. Design of layout for the bedroom of a 16 year old.
(a) Layout of furniture.
The design layout should show:
a suitable bed in an acceptable position storage for clothes storage for books etc a work area (desk) an area for TV/Video/games.
An exemplar layout is provided at the end of this section. 5
(b) Dimensions of furniture and spaces.
All important dimensions should be shown on the plan.Furniture sizes should allow reasonable circulation space. 3
(c) Presentation of plan.
A clear free-hand plan, with neat annotation should be provided. 2
(d) Explanation of choice of furniture.
Boys and girls may have different activities in their rooms.The candidate should explain the choice of furniture with reference tothe sex of the occupant.
3
(e) Use of ergonomic and anthropometric details.
The candidate should explain, using sketches if necessary, how theanthropometric and ergonomic data were used in the design of thelayout.
4
(f) Three-dimensional illustration.
The standard of sketching, especially the 3-D view, will besubjectively marked but will be a good indicator of the more ablecandidate.
An exemplar 3-D view is provided at the end of this section. 7
(24)
Marks
[C021/SQP155] 47 Page twenty-one
10. Conversion of church into nightclub.
(a) Problems which might be encountered with the Planning Authority.
Candidate’s answer must cover two likely problems such as thefollowing:
The church may be a listed building or an important buildingin the locality. This may rule out some alterations to frontagesetc. The problem may be resolved through consultation withplanning and local interest groups.
Neighbours may object for a number of reasons. A resolutionmay be found by discussion of the issues with the objectorsand by consideration of ways to accommodate the objectors.
Noise may be a problem with a nightclub. It may becontrolled by sensors or by provision of a high standard ofinsulation.
Parking and access to the nightclub may need to be improved.
2 x 2 4
(b) Design layout on worksheet and explanation of the design.
Any properly presented reasonable design solution will beaccepted. The access to the bar for customers and servicing mustbe considered along with the positions of the dance floor andseating. The explanation must clearly justify the chosen design.
An example of a suitable design solution is shown at the end ofthis section.
Sketch 4Explanation 3
(c) Instrument-aided sketches.
(i) A method of supporting the proposed steel I-beams whichwill support the new upper floor.
The candidate must provide a 1:5 sketch of an appropriatemethod of support, such as one the following:
Corbelled stone Padstones on columns Columns and beams Hangers 5
Marks
[C021/SQP155] 48 Page twenty-two
(ii) The junction of the slated roof and the external walls,showing the provisions for thermal insulation andventilation of the roof.
The candidate must provide a 1:5 sketch showing theinsulation between rafters (probably leaving the raftersexposed) with slate vents at the eaves to provideventilation between the insulation and the underside of thesarking. 5
(d) Describe a suitable method of treating the rising damp in theexisting walls.
The candidate should describe either:
Chemical injection or Cutting in a physical DPC 3
(24)
Marks