additional general conditions (revision … will document observations made each day by their...

44
UT Austin 111511 AGC-1 ADDITIONAL GENERAL CONDITIONS (Revision Effective 11/15/2011) FOR ALL UNIVERSITY OF TEXAS AT AUSTIN UTILITIES AND ENERGY MANAGEMENT BUILDING CONSTRUCTION CONTRACTS NOTE: These Additional General Conditions are a part of the Contract Documents and have precedence over the Uniform General Conditions and Supplementary General Conditions and are the standard procedures and contract administration requirements of The University of Texas at Austin, Utilities and Energy Management Department, for all building construction contracts, unless further modified by the specific project Special Conditions. They replace or are added to [if below indicated] the correspondingly numbered paragraphs of the Uniform General and Supplementary General Conditions. The paragraphs and subparagraphs of said Uniform General and Supplementary General Conditions not thus replaced continue in force, unaltered. Newly added numbered paragraphs below are added to the requirements of the Uniform General and Supplementary General Conditions and are a part of the Contract Documents. ARTICLE 1. DEFINITIONS 1.7 Close-out Documents… REVISE “…, record documents ...” to read “…as-constructed record documents…” 1.25 Owner: [Add the following] The agency for the State of Texas (Owner) for this project is The University of Texas at Austin. 1.26 [Add] Direction from the ODR shall be confirmed by the contractor in written form. 1.47 [Add the following] Additional General Conditions means the documents containing terms and conditions, which may be unique to The University of Texas at Austin. Additional General Conditions are a part of the Contract Documents and have precedence over the Uniform General Conditions and Supplementary General Conditions. 1.48 [Add the following] Accident - An undesired event or sequence of events that causes injury, ill-health or property damage. 1.49 [Add the following] Confined Space - A space that is large enough and so configured that: An employee can bodily enter; Open top spaces more than 4’ deep; Has limited or restricted means for entry or exit (for example, tanks, vessels, vaults, pits); and, Is not designed for continuous occupancy (Re: 29 CFR 1910.146 and 1926.21). 1.50 [Add the following] Contract Administrator - The UEM representative that manages all phases of contracting on behalf of UEM. This person ensures contract compliance with the administrative and contractual requirements of the contract.

Upload: dinhminh

Post on 18-May-2018

217 views

Category:

Documents


1 download

TRANSCRIPT

UT Austin 111511 AGC-1

ADDITIONAL GENERAL CONDITIONS (Revision Effective 11/15/2011)

FOR ALL

UNIVERSITY OF TEXAS AT AUSTIN

UTILITIES AND ENERGY MANAGEMENT

BUILDING CONSTRUCTION CONTRACTS NOTE: These Additional General Conditions are a part of the Contract Documents and have precedence over the Uniform General Conditions and Supplementary General Conditions and are the standard procedures and contract administration requirements of The University of Texas at Austin, Utilities and Energy Management Department, for all building construction contracts, unless further modified by the specific project Special Conditions. They replace or are added to [if below indicated] the correspondingly numbered paragraphs of the Uniform General and Supplementary General Conditions. The paragraphs and subparagraphs of said Uniform General and Supplementary General Conditions not thus replaced continue in force, unaltered. Newly added numbered paragraphs below are added to the requirements of the Uniform General and Supplementary General Conditions and are a part of the Contract Documents. ARTICLE 1. DEFINITIONS 1.7 Close-out Documents… REVISE “…, record documents ...” to read

“…as-constructed record documents…” 1.25 Owner: [Add the following] The agency for the State of Texas (Owner) for this project

is The University of Texas at Austin. 1.26 [Add] Direction from the ODR shall be confirmed by the contractor in written form. 1.47 [Add the following] Additional General Conditions means the documents containing

terms and conditions, which may be unique to The University of Texas at Austin. Additional General Conditions are a part of the Contract Documents and have precedence over the Uniform General Conditions and Supplementary General Conditions.

1.48 [Add the following] Accident - An undesired event or sequence of events that causes

injury, ill-health or property damage. 1.49 [Add the following] Confined Space - A space that is large enough and so configured

that: An employee can bodily enter; Open top spaces more than 4’ deep; Has limited or restricted means for entry or exit (for example, tanks, vessels, vaults, pits); and, Is not designed for continuous occupancy (Re: 29 CFR 1910.146 and 1926.21).

1.50 [Add the following] Contract Administrator - The UEM representative that manages

all phases of contracting on behalf of UEM. This person ensures contract compliance with the administrative and contractual requirements of the contract.

UT Austin 111511 AGC-2

1.51 [Add the following] Construction - Refer to Uniform General Conditions Section 1.45. “Work”.

1.52 [Add the following] Construction Coordinator - The UEM representative, designated

in writing, responsible for monitoring the execution of the contracted work, including safety and health management of contractor activities and for coordinating University work teams in support of the execution of work. The role of the Construction Coordinator is to act as the Project Manager’s (PM) “eyes and ears” in the field to ensure, by physical oversight, that the technical, safety, and environmental requirements specified in the contract are met by the Contractor.

1.53 [Add the following] Contractor Safety Report: The contractor will complete a daily

site safety report for each of their projects. UEM will issue a form for the purpose of this documentation or the Contractor may submit their report for acceptance by UEM. The report will document observations made each day by their Superintendent, Project Manager or Certified Safety Technician/Professional. The report will be sent via electronic mail to all members of the project team at the completion of the week’s documentation with copies to the UEM Construction Safety Coordinator and UEM Construction Coordination Manager.

1.54 [Add the following] Imminent Danger- Any conditions or practices in any place of

employment which are such that a danger exists which could reasonably be expected to cause death or serious physical harm. An activity or situation that is likely to result in serious injury, death, or significant environmental or property damage.

1.55 [Add the following] Incident - An unintended and undesired event that results in (or has the potential to result in) any number of conditions such as injury or illness, death, environmental impact, or property damage.

1.55.1 Major Incident - An unintended and undesired event that resulted in (or

had the potential to result in) any number of conditions such as a life-threatening injury or illness, broken or severed bone(s), severe bleeding, loss of consciousness, electric shock, overexposure to heat or radiation, fall greater than four feet, explosion, hazardous material spill, or serious property damage.

1.55.2 Minor Incident - Cases involving no treatment, first aid injuries, or an

incident that does not create lost workdays. Examples of these include paper cuts, minor scratches or abrasions, or system failures that have minor consequences, such as a low-pressure hose that ruptures and sprays cool water.

1.56 [Add the following] Job Hazard Analysis (JHA) - A process used for analyzing

hazards an employee or contractor faces and identifying measures to mitigate those hazards. Routine tasks are covered in a routine JHA. A task that is new or performed so infrequently it would not qualify as routine is covered by a non-routine JHA. Both must be completed before work begins by the employee’s supervisor or crew leader, The JHA must be discussed with all employees on the work team, signed by each employee on the work team, and a copy must be kept on site. Non-Routine JHA’s must be submitted to the UEM Project Manager, Construction and the Safety Coordinator no less than 24 hours prior to the start of work.

UT Austin 111511 AGC-3

1.57 [Add the following] Nonconformance - Failure to comply with policies, procedures,

drawings, specifications, contract requirements, design standards, building codes, or federal, state, local regulations and statutes.

1.58 [Add the following] Competent Person - The federal Occupational Safety and Health

Administration (OSHA) defines a competent person as “one who is capable of identifying existing and predictable hazards in the surroundings, or working conditions which are unsanitary, hazardous, or dangerous to employees, and who has authorization to take prompt corrective measures to eliminate them.” (Reference OSHA)

1.59 [Add the following] Qualified Person - A person who -- by possession of a recognized

degree, certificate, or professional standing, or who by extensive knowledge, training, and experience -- has successfully demonstrated an ability and competence to solve or resolve problems relating to the subject matter and work.

1.60 [Add the following] Prime Contractor - The Contractor named in the contract with

UEM. Prime Contractors are responsible for their own, as well as of their subcontractors, compliance with all safety, health, and environmental codes, standards, and regulations.

1.61 [Add the following] Project Manager (PM) – The UEM representative with overall

responsibility for a project. This person ensures the project is in compliance with all requirements and meets its goals including performance, schedule, budget, and safety. The Project Manager may also be referred to as the ODR.

1.62 [Add the following] Utilities and Energy Management (UEM) - One of the UT

organizations responsible for managing and executing renovation construction projects. 1.63 [Add the following] Safety Coordinator - The individual within UEM primarily

responsible for oversight of construction safety. 1.64 [Add the following] Safety Plan / Manual: The Contractor Safety Plan is a general

safety document, required by OSHA, governing the contractor’s approach to safety and work practices for the trades the contractor employees will be using. Contractors are required to submit a current Safety Plan compliant to the following: (via electronic mail?)

1.65 [Add the following] OSHA General Industry Standards – 29 CFR 1910: See

Appendix II for a listing. (Details of the standards can be accessed at http://www.osha.gov):

1.66 [Add the following] OSHA Construction Safety Standards – 29 CFR 1926: See

Appendix II for a listing. (Details of the standards can be accessed at http://www.osha.gov)

UT Austin 111511 AGC-4

1.67 [Add the following] Safe Work Practices - 29 CFR 1926.21(b)(2) requires employers to

instruct each employee in the recognition and avoidance of unsafe conditions and the regulations applicable to his work environment to control or eliminate any hazards or other exposure to illness or injury.

1.68 [Add the following] Subject Matter Expert (SME) - Staff possessing special expertise,

for example: industrial hygiene, confined space entry, Civil/Mechanical/Electrical engineer, Architect, or asbestos/lead abatement consultant/personnel.

1.69 [Add the following] UT Fire Prevention Services - The jurisdiction having authority

for oversight of fire code compliance by conducting plan and specification reviews and on-site inspections.

1.70 [Add the following] UT Environmental, Health, and Safety (EHS) - The University

EHS Division responsible for providing services that promote safe and compliant facilities and ensure environmental quality for the University.

1.71 [Add the following] Work Area- An area where some level of hazard may exist, such as

moving machinery, noise, high voltage, or hazardous materials/waste. Includes all areas within the limits of construction otherwise identified as the construction zone and any staging or storage areas assigned to the project.

ARTICLE 2. WAGE RATES AND OTHER LAWS GOVERNING CONSTRUCTION 2.2 Wage Rates:

2.2.1.1 [Add] The Contractor shall be prepared to submit each worker’s notification and / or certified payroll statements if requested by the Owner. On all federally funded projects, using Davis Bacon Wage Rates, weekly payrolls are required to be submitted. See the project Special Conditions Article 2, to determine if the project requires compliance with the Davis Bacon Act. Also see Paragraph 2.2.5 of these AGC’s (below).

2.2.4 OWNER’S PREVAILING WAGE RATE DETERMINATION

2.2.4.1 In accordance with the UGC, the Prevailing Wage Determination schedule shown below in paragraph 2.2.4.8 identifies the UT System Prevailing Minimum Wage Rate determination for Travis County.

2.2.4.2 The Owner may verify wage rate compliance in the field by interviewing

workers. The Contractor shall assist the Construction Coordinator with this task, including providing translation for non-English speaking workers.

UT Austin 111511 AGC-5

2.2.4.3 The University of Texas at Austin is the contracting agency for this

construction project. The following statute requires the contracting agency to specify the generally minimum rates of wages in contracts that are bid.

Government Code 2258

“Construction of Public Works in State and Municipal or Political Subdivisions; Prevailing

Wage Rates to be maintained” and

The Uniform General and Supplementary General Conditions for University of Texas System Building Construction Contracts

2.2.4.4 Pursuant to the requirements of this statute, we have determined that the

following rates of wages indicated in 2.2.4.8, are to be paid to various classifications of workers in the locality of this project.

2.2.4.5 Total hourly compensations to each worker must equal or exceed the

minimum wage rates stated in the Wage Table in 2.2.4.8. Contributions by a worker toward health, pension, vacation, and the like are part of the worker’s pay; contributions by the employer are not. Any dollar amounts shown in columns for health, pension, and vacation may be paid either in cash or in kind. Workers in classifications where rates are not identified shall be paid not less than the general minimum rate of “laborer” for the various classifications of work therein listed.

2.2.4.6 All hours of work over 40 hours per week are overtime and will be

compensated at the rate of 1 and ½ times the regular wage. 2.2.4.7 Trainees/helpers, where not otherwise specified above, may be

compensated at a rate determined mutually by the worker and employer, commensurate with the experience and skill of the worker but a rate not less than 60% of the journeyman’s wage or less than the Laborers (General) rate. At no time shall a journeyman supervise more than two of apprentices, trainees or helpers. All apprentices/trainees/helpers shall be under the direct supervision of a journeyman working as a crew.

2.2.4.8 The following wage rates are to be used for all projects at The University

of Texas at Austin located in Travis County, Texas.

UT Austin 111511 AGC-6

(1) Wages shown are for entry level, minimum wages for each classification and do not include fringe benefits.

(2) Unlisted classifications needed for work not included within the scope of the classifications listed may not be added after award. The job classifications are not inclusive of all possible trades on the construction project.

(3) It is the responsibility of the contractor to classify the worker in accordance with the published classifications, and demonstrate that workers are paid commensurate with determined rates.

  PREVAILING WAGE DETERMINATION    TRAVIS COUNTY    AUSTIN AREA         The University of Texas System    Office of Facilities Planning And Construction     

DATE of Survey:  December 31, 2009  CONSTRUCTION

TYPE:  BUILDING   

AREA:  TRAVIS COUNTY AUSTIN, AREA

 

  BUILDING CONSTRUCTION TRADE CLASSIFICATION

PREVAILING WAGE RATE

       Carpenter $15.75   Concrete Finisher $14.00   Data-comm/Telecom $13.00   Drywall/Ceiling Installer $14.00   Electrician $17.98   Elevator Mechanic $21.89   Fire Proofing Installer $12.50   Flooring Installer    Glazier $16.00   Heavy Equip Operator $13.56   Iron Worker $13.50   Laborer $10.00   Lather/Plasterer $15.00   Light Equip Operator / Driver $12.88   Mason/Bricklayer $19.25   Painter/Wall-cover $13.00   Pipefitter $17.50   Piping/Ductwork Insulator $16.25   Plumber $17.50   Roofer $12.81   Sheet-metal Worker $19.44   Sprinkler Fitter $15.04   Tile Setter $12.25   Water-proofer $12.00 

UT Austin 111511 AGC-7

2.2.4.9 All other projects administered by and for The University of Texas at

Austin, but located outside of Travis County, shall use the corresponding “Davis Bacon” Wage Rates as discussed in Paragraph 2.2.5 of these AGC’s. This includes projects located at The Marine Science Institute located in Port Aransas, Nueces County, Texas; projects at The McDonald Observatory located near Fort Davis, Jeff Davis County, Texas; projects at the Winedale Historical Complex in Fayette County, Texas; and projects at various other Counties within Texas. Even-though the above “non-Travis County” projects are required to use the most current Davis Bacon Wage Rates, weekly payrolls will not be required UNLESS the projects are federally funded. (See requirements in Paragraph 2.2.5 of these AGC’s). The contractor shall obtain the latest related wage determination from the Davis Bacon web site as of the bid date of the project and shall submit to the owner the wage determination with the execution of the contract (if they are the selected / awarded Contractor).

2.2.5 [Add the following] Projects, where funding is solely or partly from federal funds

or federal grants, shall require the Contractor to use the Davis Bacon “Wage Determinations On Line.gov” for the County of the location of the project, in lieu of the above-referenced table for Travis County. The contractor shall obtain the latest related wage determination from the Davis Bacon web site as of the bid date of the project and shall submit to the owner the wage determination with the execution of the contract (if they are the selected / awarded Contractor). The web page address is:

http://www.wdol.gov/dba.aspx#0

These requirements include all requirements of the Davis Bacon procedures including submission of weekly payroll statements, etc.

2.2.5.1 PROJECTS THAT INCLUDE FEDERAL FUNDING AND

THEREFORE REQUIRE ADHERANCE TO THE ABOVE DAVIS BACON WAGE DETERMINATIONS SHALL BE INDICATED IN THE INDIVIDUAL PROJECTS SPECIAL CONDITIONS PARAGRAPH 2.2.5.2.

NOTE: IN JOB ORDER CONTRACTING (JOC) PROJECTS NOT HAVING SPECIAL CONDITIONS, THE DETERMINATION IF FEDERAL FUNDING APPLIES, MAY BE STATED IN THE REQUEST FOR PROPOSAL.

2.2.5.2 (SEE SPECIAL CONDITIONS FOR DAVIS BACON

REQUIREMENT STATEMENT)

UT Austin 111511 AGC-8

ARTICLE 3. GENERAL RESPONSIBILITIES OF OWNER and CONTRACTOR

3.1.1 Preconstruction Conference:

3.1.1.1 [Add] The Architect / Engineer may call for a Preconstruction Conference. At, or prior to the Preconstruction Conference, or no later than fourteen [14] calendar days after receipt of the Notice to Proceed, the Contractor shall present to the Architect / Engineer for his approval: the Work Progress Schedule; name and experience of the Project Superintendent; equipment proposed; contract price breakdown and schedule of values; materials storage requirements; parking requirements; utility requirements; and all safety related submissions (not previously required).

3.3.7.2 [Add] As soon as practicable after the notice of Intent to Award, and

before the execution of the Contract, the Respondent to be awarded the contract shall submit to the Owner and Architect / Engineer for approval, a list of all subcontractors that the respondent and/or their major subcontractors propose for the construction of the project.

ARTICLE 5. BONDS AND INSURANCE 5.1 Construction Bonds:

5.1.10 [Added paragraph] Time for Bond Submissions: Performance and Payment Bonds shall be submitted by the Contractor to The University of Texas at Austin, Contract Administrator at the same time which the executed contract is due back to the Contract Administrator as indicated in the Proposal and as follows. Completed Bonds shall be received within SEVEN (7) CALENDAR DAYS after receipt of the Contract by the contractor (unless a different number of days is specifically indicated for the project). No contract will be signed without the Owner having received the executed Bonds.

5.2 Insurance Requirements: [Add the following] Certificates of insurance shall be

submitted by the Contractor to The University of Texas at Austin, Contract Administrator at the same time which the executed contract is due back to the Contract Administrator as indicated in the Proposal and as follows. Completed insurance certificates shall be received within SEVEN (7) CALENDAR DAYS after receipt of the contract by the Contractor (unless a different number of days is specifically indicated for the project). No contract will be signed without the Owner having received the executed insurance certificates. The name of the project, project number, contract number, and other information shall appear on each insurance certificate along with expiration date of each policy as may be required by the Owner.

5.2.2.1.3 [Add to this paragraph] This insurance is only required if the project scope includes the abatement of asbestos containing materials. If required, the insurance may be furnished by the abatement subcontractor with the Contractor and Owner listed as additional insured’s.

ARTICLE 6. CONTRACT DOCUMENTS

UT Austin 111511 AGC-9

6.1.1 Copies furnished: [Add the following] The Contractor shall be furnished, if

requested, 10 complete sets of drawings and specifications after the award and execution of the contract at no expense to the contractor. If the Owner has additional sets returned, or sets not used from the bidding process after internal distribution, those will be made available to the contractor, if needed.

6.1.4 [Add] Field measurements govern over small-scale drawings.

6.1.7 [ADD this paragraph] Original Drawings and Specifications: The original

drawings and specifications of existing buildings may be available to the Awarded Contractor. Contact the Project Manager to arrange their review. Owner does not warrant or make any representations as to the current accuracy, suitability or completeness of this information furnished to Contractor by Owner or its representatives.

6.2.4 [Revise this paragraph] Prior to requesting Substantial Completion Inspection,

or no later than submittal of final pay application, Contractor shall furnish for review and approval by the ODR and AE a complete set of “marked-up Record Documents” plans and specifications that reflect all changes to the contract documents [these documents may be annotated by hand or corrected by CAD (preferred) but must be clearly legible]. Concurrently with furnishing these record drawings, furnish: a preliminary copy of each instructional manual, maintenance and operating manual(s); parts catalog; wiring diagrams; spare parts; specified written warranties and like publications; parts for all installed equipment, systems, and like items and as described in the Contract Documents. All items identified in this section shall be scanned and submitted on a CD/DVD, as required by the Contract Documents.

6.2.4.1 [Add] Prior to Substantial Completion Inspection, Contractor must

complete and furnish to ODR and AE the Equipment Add-Delete-Modification Log, documenting all equipment they have added (installed), deleted (demolished), abandoned (left in place but no longer operable), or modified throughout the project. (Format of this log shall be furnished to Contractor.)

6.2.4.2 [Add] Prior to submittal of final payment application, Contractor must

submit warranty information; Contractor Affidavit of Bills Paid; Consent of Surety for Final Payment; evidence that all keys have been returned to the Lock and Key Shop; O&M Manuals; other Final Submittals required by Contract Documents; unused allowance; pending Change Orders; and a notarized Certificate of ‘No Asbestos Containing Materials or Work’ per UGC Article 13.7.

6.2.5 [Revise the paragraph] Once determined acceptable by Paragraph 6.2.4,

Contractor shall provide --in electronic format as specified herein -- all Instructional, Operating and Maintenance manual(s); approved submittals; approved shop drawings; warranties; certificates; test reports; record documents; equipment add-delete-modification logs; and other items as required by the Contract and Paragraph 6.2.4 above.

UT Austin 111511 AGC-10

6.2.5.1 [Add] All small format (11”x17”) or smaller photographs, cut sheets, sketches, instructions, diagrams and graphical literature, shall be scanned at a resolution of at least 300 DPI to produce sufficient quality to allow zoom features and readable prints. Color charts or other documents where color is required to convey full information, shall be scanned in color. Color line drawings shall be scanned at 200 DPI to avoid excessive file size.

6.2.5.2 [Add] All documents shall be scanned into a single file in current version

of Adobe PDF with expandable indexed file structure organized according to CSI format and bookmarked to at least Division and Section level and searchable by keyword.

6.2.5.3 [Add] Proper labeling must appear on the disk and jewel case to include

the Owner’s name (The University of Texas at Austin); project number (CP number); project title; contents of the CD/DVD (O&M Record Documents Div 1-12 as an example); the sequence number of the disk, if part of a multi-disk set (i.e. DVD 1 of 3); and the archive date. CD/DVD labels must not be adhesive labels which can eventually delaminate and “gum up” a reader mechanism.

ARTICLE 7. CONSTRUCTION SAFETY 7.1 General: [Revise second sentence to read] The Contractor shall submit their Company

Safety Manual and prepare a Safety Plan (or Site Health and Safety Plan) specific to the project and submit to the ODR and AE at the Pre-construction Conference or two (2) calendar days prior to commencing work, if there are identified risks for the project in the opinion of the ODR.

7.4.2 [Revise first sentence to read] Supply ODR, A/E, Project Manager and Safety

Coordinator with an Incident report no later than 24 hours after the occurrence of the event.

7.7 [ADD this Section and subsequent subsections] The University of Texas at Austin

Specific Safety Requirements:

7.7.1 Purpose: To ensure that contracted construction work is completed in compliance with Occupational Safety and Health Administration (OSHA) and industry standards. Safety compliance shall be considered at all phases of contracted construction work performed for the University of Texas at Austin (UT). Contracted personnel and their subcontractors at all tiers shall be fully aware of their legal and contractual responsibility to prevent occupational accidents and injuries.

UT Austin 111511 AGC-11

7.7.2 Standards & References: The following standards or references apply to all

construction work performed for UEM:

Title 29, Code of Federal Regulations, “Labor” Part 1904, “Record Keeping” Part 1910, “Occupational Safety and Health Standards” (29 CFR 1910) Part 1926, “Safety and Health Regulations for Construction” (29 CFR 1926)

“The Contractor’s Guide to Working Successfully at the University of Texas at Austin”, 2012

“The Current Uniform General and Supplementary General Conditions for University of Texas System Building Construction Contracts”

7.7.4 (Not Used)

7.7.5 Requirements:

7.7.5.1 Safety Plan / Manual: An OSHA approved Safety Plan is a written

document that describes the process for identifying the physical and health hazards that could harm workers, procedures to prevent accidents, and steps to take when accidents occur. OSHA recommends that each written plan include the following basic elements:

Hazard Communication (29 CFR 1910.1200 (e)- Chemical worker right-to-know plan;

Emergency Action Plan and Fire Prevention Plan (29 CFR 1910.38 and 29 CFR 1910.39))

Bloodborne Pathogens Exposure Control Plan (29 CFR 1910.1030 (c))

HAZWOPER Safety and Health Plan (29 CFR 1910.120 (b)) Respiratory protection; Contractor issued permits for Confined

Space Work and Lock Out/Tag Out of Energized Systems; Process Safety Management; Construction Fall Protection; Construction Trenching and Excavations.

The University of Texas at Austin requires scanning using Ground Penetrating Radar prior to coring, drilling or saw cutting concrete to document locations of rebar, conduit and beams. Contractor must refer to project specifications and plans prior to proceeding with work of this nature or secure specifications from the Structural Engineer of record.

The University of Texas at Austin further requires a general safety document governing a contractor’s approach to safety and work practices for the trades and work activities the contractor employees will be using while under contract to UEM. The Contractor must include a ‘Shelter–in-Place Response Plan outlining how they will report emergencies; the person in their project team who will receive Emergency Text Messages from UTPD; Flow of Information to and from UEM PM & Coordinator; Getting the word out to subcontractors and

UT Austin 111511 AGC-12

workers; Accounting for whereabouts and safety of their personnel; how they will Secure Site Perimeter; Securing Personnel in designated sheltered place location; and identification of key leadership who will be responsible for implementing the plan and training others. The Site Safety Plan must include the procedures, Recordkeeping and Reporting, Policy or goal statement, List of responsible persons, Hazard identification, Hazard controls and safe work practices, Emergency and accident response; Employee training and communication and must demonstrate compliance to 29 CFR, OSHA 1910 and 1926 Occupational Safety and Health Statutes.

7.7.5.2 Planning: Safety requirements and controls shall be part of the project

planning process from inception. How the contractor is expected to demonstrate compliance to these requirements is documented through a series of documents required by UEM, described below as contract deliverables. These documents are intended to ensure the contractor has an OSHA compliant Safety Manual, a Site Safety Plan which is project specific, employs qualified and competent personnel, and that they fully understand the risks and hazards associated with the work to be performed at UT.

7.7.5.2.1 Contractor Reporting of Safe Work Practices: Each industry

recognized shift that work is accomplished by the Prime Contractor, the prime will be responsible for having site observations of each trade accomplished by one of the following personnel in their employment: their Project Manager; Project Superintendent; or, their certified Safety Technician or Safety Professional. UEM will provide a form for this purpose and the report must be submitted once a week for work accomplished the previous week. Copies of the reports must be distributed via electronic mail to the UEM Project Manager; Project Construction Coordinator; the UEM Safety Coordinator and the Manager of Construction Coordination for UEM. Each time the contractor performs work that requires locking out an energized system, the contractor must take a date and time stamped photo of their Lock Out Tag Out and submit these photos to the same UEM personnel identified for weekly safely reports.

7.7.5.2.2 Job Hazard Analysis and Job Briefings: The Job Hazard

Analysis and Job Briefing Process (OSHA Publication 3701) is intended to provide advance planning of project and site specific safety controls, PPE assessments, hazard identification and mitigation strategies, key Points of Contact, and emergency response information for a particular project, job or task.

UT Austin 111511 AGC-13

7.7.5.2.2.1 Performing Job Hazard Analysis (JHA) is critical to emergency planning, defining safety controls, selecting PPE, identifying hazards of the job or task, and communicating the information to all affected workers. There are two types of JHA’s that may be performed:

The Routine Job Hazard Analysis and Job Briefing form; and The Non-Routine Job Hazard Analysis and Job Briefing form.

7.7.5.2.2.2 Routine JHA’s shall be prepared by the Contractor as follows below. Non-Routine JHA’s, Rope-Access Work Plan/JHAs, Incidental, Medium, Heavy, and Critical Lift Plans, Trenching Plans shall be submitted to the Construction Coordinator and Project Safety Coordinator for review 5 Work days prior to starting the task:

• Prior to the start of any on-site work; • Before initiating any new phase or task;

and • Before modifying an existing phase or task

resulting in a change in hazards • JHA must be reviewed, acknowledged,

and signed by all affected workers with completed and signed copies retained by the Contractor on the construction site.

7.7.5.2.2.3 Additional project safety requirements shall be addressed using the following documents; Excavation/Trenching Plans, Rope-Access Work Plan/JHA and Routine Job Hazard Analysis, Non-Routine Job Hazard Analysis and Incidental, Medium, Heavy and Critical Lift Plans. The Contractor shall train their employees and subcontractors in the contents of the Article 7, Construction Safety and the project specific Site Safety Plan,. The training shall be documented and made available to UEM upon request.

7.7.5.2.3 Permits (Authorizations)-To-Work (Confined Space,

Welding/Cutting Hot work, Electrical Hot Work) Permits to work in Confined Space; performing Hot Work; Lock out tag out of energized systems or welding/cutting requires the contractor to issue their HOT WORK PERMIT and to post it visibly on the project site. The contractor must also complete the appropriate Job Hazard Analysis for the work that will be performed. These work tasks must be discussed prior to scheduling as part of the project weekly meeting to verify proper University of Texas approval has been secured (Fire

UT Austin 111511 AGC-14

Protective Services/Fire Safety Services Shop, Utility Department, Zone Shop and Building Management). Permits must clearly note the Date, Capital Project number, Specific location and floor including applicable room numbers; The Description of work being performed; the name of the person/company performing the work; and it must be signed off by the Prime Contractor. The permit must have a start date and time and an expiration date and time for the permit.

7.7.5.3 Site Control, Signage and Access:

7.7.5.3.1 Access to Construction Sites: The Project Manager and Contractor will define who is authorized to enter the construction site. Other personnel desiring access to a construction area must do the following:

• Except for emergencies, obtain approval to enter the construction premises from the Contractor’s Superintendent, the UEM Project Manager, Construction Coordinator or emergency personnel.

• Obey all safety regulations and signs, wear appropriate Personal Protective Equipment (PPE) comparable to the PPE requirements for workers on the project, and follow special instructions.

7.7.5.3.2 Minimum Project Signage: All construction projects at UT shall include the following signage and tags as a minimum:

7.7.5.3.2.1 Project and safety signs shall be placed at each

project entrance, in hallways/corridors, mechanical rooms, electrical rooms, fenced parking and storage areas that includes: the contractors company name/logo, building/project number, project description (include job site location (floor, room number, etc.), Contractor’s point of contact/after hours/emergency numbers, UT Police Department emergency contact numbers. Interior project information signs shall be a minimum of 11” X 17” and of a water resistant material. Exterior project information signs shall be a minimum of 24” X 24” and of a waterproof material.

UT Austin 111511 AGC-15

In addition, the following signage shall be posted along with other special notifications and PPE requirements that the Contractor has determined to be required from their OSHA required hazard analysis and PPE assessments. Note: All safety signs shall be OSHA approved formats.

To be posted at the entrances of the site and every 50 feet around the fenced perimeter.

To be posted at the site entrance.

To be posted at the site entrance.

To be posted any time personnel are working aloft and placed on barricades to provide notice to pedestrians.

To be posted at the site entrance.

Company Name/Logo 

Building Name/Capital Project No: XXX‐CPXXXXXX 

Project Description/Title 

Start Date:   

Finish Date: 

Architectural firm name:  

Contractor Name 

PM/Super: phone XXX‐XXX‐XXXX 

PMCS Contact No.:  512‐471‐3042 

Emergency No.: UT Police Dept.: 512‐471‐4441 or 911 from a building landline 

Emergency After  Hours: 512‐471‐2020 

UT Austin 111511 AGC-16

To be used on scaffolds (excluding Baker scaffolds) and special equipment requiring inspections.

Anyone of these signs, as appropriate, shall be placed at switches and breaker panels (Main points of feed) and used with “Lock-Out” tag below along with lock-out device on all energized systems. If breakers are altered or disconnected, a tag/notification indicating “Out of Service” (by breaker number) shall be posted on the breaker panel.

Standard “Lock-Out” Tag or equivalent.

To be used at energized open panels, troughs and switches along with barricades, cones, plastic chain or danger tape to inform unqualified persons of the hazard. Note: all exposed wires shall have wire nuts installed and placed within the

UT Austin 111511 AGC-17

junction box at all times while unattended. If testing circuits, hang tags (“Live Wire” & “Testing in Progress”) at all points of exposed wiring, panels, troughs and switches. A minimum of 36” clearance shall be maintained at all times. For circuits that must remain energized at all times or provide electrical service to areas outside of the construction zone, then hang a “Do Not Open” tag and list the breaker(s)/circuit number(s).

Right and Left

To be used in corridors, hallways, sidewalks or areas where visitors, students, staff and faculty of The University may be working near or passing within close proximity of a construction zone.

7.7.5.4 Observations: Throughout all phases of construction, UEM personnel

overseeing the Work being performed by the Contractors and their subcontractors will monitor field activities on a regular basis to ensure that work is being conducted in a safe and compliant manner.

7.7.5.4.1 Observations by UT EHS and Fire Protection Services may

take place at any time to ensure compliance with applicable codes, standards, and regulations.

7.7.5.4.2 The UEM PM, Construction Coordinator or Safety

Coordinator will formally notify the Contractor of any deficiencies and verify that appropriate corrections are made. A Nonconformance, Preventative, and Corrective Action reporting and tracking procedure will be implemented.

7.7.5.4.3 Safety Inspections: The OSHA standards require the

Contractor: to perform daily inspections of activities, equipment and work site; to ensure that the Contractor and their subcontractor employees are working within identified controls and have effectively controlled immediate hazards; and are wearing appropriate PPE. Contractor will be required by The University of Texas at Austin to submit the results of their daily inspections to the Project Manager, the Construction Coordinator and the Safety Coordinator each week via electronic mail.

UT Austin 111511 AGC-18

7.7.5.4.3.1 The Contractor’s competent person shall conduct regular inspections of the work place and maintain a documented system certifying compliance with Contractor defined safe work practices and safety manual. For example, the scaffolding inspection entries section on contractor-supplied scaffold tags should include evidence of daily inspections and/or configuration change approvals. Other areas of inspection may include rigging inspections, fall protection equipment, Lock-out/Tag-out, confined space, Contractor issued Permits-to-Work, forklifts, heavy equipment, equipment and tools. Contractors shall provide emergency response/egress planning, properly inspected first-aid kits and assure that fire extinguishers are available for their work teams within the designated OSHA distances.

7.7.5.4.3.2 When hazards are identified and when immediate corrective action is not possible:

• The affected workers must be notified,

• Warning signs posted, and • Interim control measures established

to guard against the hazards. 7.7.5.4.3.3 All inspections, findings, and corrective measures

must be documented and kept onsite for review.

7.7.5.5 Performance Based Safety and Escalated Notice of Noncompliance: A defined process for the Escalation of Notice of Noncompliance, defined in Appendix I, will be implemented to ensure performance based compliance with safety provisions and reduce the frequency of safety violations and accidents. 7.7.5.5.1 Repeated safety or health violations will become a matter of

record and will be part of the evaluation of contractor bids on future awards.

7.7.5.6 Unsafe Activities or Conditions: UEM management has granted

authority to its staff to stop an unsafe activity or condition and redirect the contractor to work in a non-hazardous area until such time as the contractor abates the hazard. Hazards must be abated as soon as possible after they have been identified. Imminent-hazard activities must be stopped and corrected immediately.

7.7.5.7 Injuries, Incidents, Equipment Damage: In the event of all injuries,

incidents, or accidents that involve any individual, equipment, property or bystander on or near the Work, the contractor shall notify the UEM Project Manager, the Construction Coordinator, and the Safety Coordinator immediately and follow-up the verbal report with the written Contractors First Report of Injury and the UEM required Incident Reporting and Investigation form within twenty-four (24) hours of the

UT Austin 111511 AGC-19

event. The contractor shall post the following signs at the job site to reinforce incident and unsafe condition reporting requirements:

7.7.5.8 Job Site Binder: Safety related documentation for construction work shall be retained in a job site Binder. The Binder may include and not limited to the following documents:

The Contractor Safety Manual & Site Safety Plan Job Hazard Analysis (JHA) and Job Briefing Sheets Excavation/Trenching Plans Incidental, Medium, Heavy and Critical Lift Plans Rope Access Work Plan and JHA Safety/Daily Inspection Logs (completed by contractor) Contractor training records Project Roster; Contractor and Subcontractor Emergency Contact

Information (Daytime and After Hour phone numbers) Material Safety Data Sheets

7.7.5.9 Equipment: Contractors shall:

Ensure the safety of their equipment by implementing an equipment inspection scheme;

Shall not use shop made or special tools and equipment unless supplied by a sketch or drawing that is stamped/signed by a Professional Engineer (PE); and

Shall not use or alter tools and equipment beyond the manufacturer’s recommendations unless approved by the manufacturer or a PE.

7.7.5.10 Contractor Personnel:

7.7.5.10.1 Qualifications: Contractors are responsible for ensuring

that all workers on-site are trained and qualified according to federal and state requirements. When contracted personnel arrive on-site, they must:

Be equipped with the proper PPE and tools to safely perform their work.

7.7.5.10.1.1 For contracted work when OSHA requires a competent person, the contractor will designate such an individual in writing and be prepared to demonstrate to the UEM PM the basis for the individual’s competency. The following, but not limited to, are activities that typically require a competent person:

UT Austin 111511 AGC-20

Superintendent or designated Safety Officer

Excavation Scaffold erection (This must have a

qualified scaffold erector to assemble, inspect, disassemble or modify any scaffolding)

Fall protection Confined space entry Respiratory protection Hoisting and rigging Rope Access; and Equipment Operators.

7.7.5.10.2 Identification and Badging: All job-site personnel or

visitors shall openly display photo identification or Contractor issued visitor badge.

7.7.5.11 Personal Protective Equipment: UEM requires the following PPE to be

worn by all parties entering a construction site at all times: Hard hat, appropriately tinted safety glasses (clear for indoors and tinted/or clear for outdoors), skid resistant and/or closed or steel toe safety shoes, construction vest for outdoor construction sites, appropriate clothing, and a photo identification badge. The contractor is responsible for enforcing these requirements at all times.

7.7.5.11.1 The minimum requirements for all parties entering a

construction site are the following: Hard Hat (ANSI Z89.1-2003) Non Skid Safety shoes and/or Safety-toe shoes

(ASTM F2412-2005 and F2413-2005) Protective eyewear (ANSI Z87.1-2003) Safety vest (class 2 or class 3, ANSI/ISEA 107-

2004) for outdoor construction projects with heavy equipment.

Work shirt (long or short sleeve and work pants (long). Garments must be free of writing that could be construed as offensive or inappropriate.

7.7.5.11.2 Other PPE requirements apply based on the contractor

hazard assessment of the project and work areas. PPE requirements will be documented in the task-specific JHA and posted at the job site using OSHA approved signs and symbols.

7.7.5.12 ROLES AND RESPONSIBILITIES

7.7.5.12.1 Utilities and Energy Management (UEM): Project

Managers and Construction Coordinators oversee the Contractor construction work performed at UT.

UT Austin 111511 AGC-21

7.7.5.12.2 Safety Coordinator: The Safety Coordinator is responsible

for: Reviews the contractor’s required safety manual,

Site Health and Safety plans and associated documentation;

Reviewing specific contractor safety-related submittals;

Oversees safety, and environmental compliance aspects of all UEM projects (excluding those managed by Construction Services);

Participates in stop activity determinations; and maintaining the incident reporting investigation and behavior based safety observation database for construction projects.

7.7.5.12.4 UT Fire Prevention Services: The UT Fire Prevention

Services is the authority having jurisdiction.

7.7.5.12.5 UEM Contract Administrator: The UEM Contract Administrator is the legal representative for UEM contract issues.

7.7.5.12.6 UEM Project Manager: The UEM Project Manager is the

Owner’s Designated Representative (ODR) and has the responsibility for general administration of the contract. The UEM Project Manager is the primary point of contact between UT UEM and the Contractor.

7.7.5.12.7 UEM Construction Coordinator: The role of the

Construction Coordinator is to act on behalf of the Project Manager in the field to ensure by physical oversight that the technical and safety requirements specified in the contract documents are met by the contractor.

7.7.5.12.8 Contractor: Contractors are responsible for the safety of

their workers, their subcontractors, job site visitors and for meeting all requirements of the contract. The contractor shall assure that all workers on the site are qualified and competent (as defined by OSHA) to perform the duties of the job as assigned.

7.7.5.13 Training: The Contractor’s Project Managers and Superintendents shall

have completed OSHA 30 hour training and submit evidence of the training to UEM prior to the issuance of a Notice to Proceed.

7.7.5.13.1 Site-Specific Safety Orientation: The UT Project

Manager will coordinate a site-specific safety orientation and review of safety requirements at the pre-proposal and pre-construction conferences.

UT Austin 111511 AGC-22

7.7.6 Appendices:

Appendix I, Escalated Notice of Noncompliance Procedure

Appendix II, Tables of 29 CFR OSHA 1910 & 1926 Occupational Safety and Health Standards

7.7.7 Available Forms for Contractor Use (request from the Project Manager or Safety

Coordinator):

Contractor Safety Assessment Form Job Hazard Analysis Training Guideline Routine Job Hazard Analysis and Job Briefing Form Non-Routine Job Hazard Analysis Rope Access Work Plan and Job Hazard Analysis Form Incidental, Medium, Heavy and Critical Lift Plan Documents Contractor Incident Reporting and Investigation Form Nonconformance, Preventative, and Corrective Action Procedure and Form

UT Austin 111511 AGC-23

Appendix I

Escalated Notice of Noncompliance Procedure (Flow Chart)

Safety Coordinator

Project Manager

Contractor/Subcontractor

Project Manager Safety Coordinator

Contractor/Subcontractor

Project Manager

PMCS Identifies Contract Nonconformance Via Observations

Start Nonconformance

Procedure

On-The-Spot Corrective Action

Verified?

Initiate NCR And

Project NCR Log

Fwd NCR to Contractor

Performs Root Cause Analysis

Preventative Action Within 7 Calendar Days

C/A Received And

Accepted?

Recurring major and/or IDLH N/C

Issue?

Stop

Stop

Yes

No

No

Yes

Resolves Issue And/Or Appeals

1st Notice

2nd Notice 3rd Notice

Yes Form No:

Contractor/Subcontractor

Contractor Receives “Notice”

From Regulator & Fwd’s to PMCS

Form No:

2nd Warning CEO/President

Form No:

3rd Warning Insurance & Bonding Co.

1st Warning

Local

Form No:

Form No:

UT Austin 111511 AGC-24

Company Name Address City, State, Zip Subject: Notice of Contract Non-Compliance Capital Project No.: Project Name: Dear (Company Project Manager): Pursuant to Article 7: Construction Safety of the Uniform General Conditions (11/22/09) and Article 7 of the Additional General Conditions (020609), a Notice of Non-Conformance was issued on the project site to your site Superintendent, _______________(name) on ____________ (date), by the Safety Coordinator for at The University of Texas at Austin. To date, there has not been consistent and sustained compliance with the areas cited and additional notice was provided to your site Superintendent, ______________ on _________ (date). The specific areas of non-compliance are listed below. Non-Compliance Items: * * * Your construction contract with the University of Texas at Austin, requires your conformance to all State and Federal laws and to The University of Texas at Austin safety requirements as identified in your contract documents. The violations identified above require immediate and sustained corrective action on your part. Failure to comply within ____________ working days, and to maintain a safe worksite throughout the balance of this project, may result in further action on the part of the UEM Contract Manager which may include notification of non-compliance to your insurance and bonding carriers as well as any and all remedies available pursuant to Article 14 of the Uniform General Conditions which may include Suspension of Work for Cause or Termination by Owner for Cause. Should you have any questions regarding this notice, please contact _______________ (name and title) at (512) ______Monday through Friday between the hours of 7:30 AM and 4:00 P.M. Sincerely, Signature Attachment: Copy of Non-Conformance Reports Company Name Certified Mail, Return Receipt Requested Address Certified Mail No: City, State, Zip

UT Austin 111511 AGC-25

Subject: Second Notice of Contract Non-Compliance Capital Project No: Project Name: Dear (Company Contract authority): Pursuant to Article 7: Construction Safety of the Uniform General Conditions (11/22/09) and Article 7 of the Additional General Conditions (020609), a Notice of Non-Conformance was issued on the project site to your site Superintendent, _______________(name) on ____________ (date), by the Safety Coordinator for at The University of Texas at Austin. A letter of Non-Compliance was issued to your Project Manager, __________, on ______ (date) To date, there has not been consistent and sustained compliance with the areas cited and an additional notice was provided to your site Superintendent and Project Manager, ______________ on _________ (date). The specific areas of non-compliance are listed below. Non-Compliance Items: * * * Your construction contract with the University of Texas at Austin, requires your conformance to all State and Federal laws and to The University of Texas at Austin safety requirements as identified in your contract documents. The violations identified above require immediate and sustained corrective action on your part. Failure to comply within ____________ working days, and to maintain a safe worksite throughout the balance of this project, may result in further action on the part of the UEM Contract Manager which may include notification of non-compliance to your insurance and bonding carriers as well as any and all remedies available pursuant to Article 14 of the Uniform General Conditions which may include Suspension of Work for Cause or Termination by Owner for Cause. Should you have any questions regarding this notice, or you feel this notice was issued in error, please contact _______________ (name and title) at (512) ______Monday through Friday between the hours of 7:30 AM and 4:00 P.M. Sincerely, Signature Attachments: Notice of Non-Conformance dated: Copy of Non-Compliance dated: Company Name Certified Mail, Return Receipt Requested Address Certified Mail No: City, State, Zip

UT Austin 111511 AGC-26

Subject: Third Notice of Contract Non-Compliance Capital Project No: Project Name: Dear (Company Contract Authority): On ________(date) a letter of Contract Non-Compliance to Construction Safety requirements was sent to you via certified mail, return receipt requested citing violations of Article 7: Construction Safety of the Uniform General Conditions (11/22/09) and Article 7 of the Additional General Conditions (020609) in your contract documents for this project. Despite multiple notices and two prior letters to your company, you continue to be in non-compliance. The items we have identified are listed as follow. Non-Compliance Items: * * * Your construction contract with the University of Texas at Austin, requires your conformance to all State and Federal laws and to The University of Texas at Austin safety requirements as identified in your contract documents. Despite our efforts to gain compliance, __________ (company name) continues in violation of this contract. These violations require immediate and sustained corrective action on your part. Failure to comply by this date and to maintain conformance to your contractual obligations may result in further action with may include any and all remedies available pursuant to Article 14 of the Uniform General Conditions of your contract which may include Suspension of Work for Cause or Termination of your contract by Owner for Cause. Should you have any questions regarding this notice, or you feel this notice was issued in error, please contact _______________ (name and title) at (512) ______Monday through Friday between the hours of 7:30 AM and 4:00 P.M. Sincerely, Signature Attachments: Notice of Non-Conformance dated: Copy of Non-Compliance dated: Copy: Insurance Carrier Bonding Company

UT Austin 111511 AGC-27

Appendix II

Tables of 29 CFR OSHA 1910 & 1926 Occupational Safety

And Health Standards

UT Austin 111511 AGC-28

Table of OSHA General Industry Standards 1904 Record Keeping 1910 Subpart A - General 1910.1 - Purpose and scope. 1910.2 - Definitions. 1910.3 - Petitions for the issuance, amendment, or repeal of a standard. 1910.4 - Amendments to this part. 1910.5 - Applicability of standards. 1910.6 - Incorporation by reference. 1910.7 - Definition and requirements for a nationally recognized testing laboratory. 1910.7 App A - OSHA Recognition Process for Nationally Recognized Testing Laboratories. 1910.8 - OMB control numbers under the Paperwork Reduction Act. 1910.9 - Compliance duties owed to each employee. 1910 Subpart B - Adoption and Extension of Established Federal Standards 1910.11 - Scope and purpose. 1910.12 - Construction work. 1910.15 - Shipyard employment. 1910.16 - Longshoring and marine terminals. 1910.17 - Effective dates. 1910.18 - Changes in established Federal standards. 1910.19 - Special provisions for air contaminants. 1910 Subpart C - Adoption and Extension of Established Federal Standards 1910 Subpart D - Walking-Working Surfaces 1910.21 - Definitions. 1910.22 - General requirements. 1910.23 - Guarding floor and wall openings and holes. 1910.24 - Fixed industrial stairs. 1910.25 - Portable wood ladders. 1910.26 - Portable metal ladders. 1910.27 - Fixed ladders. 1910.28 - Safety requirements for scaffolding. 1910.29 - Manually propelled mobile ladder stands and scaffolds (towers). 1910.30 - Other working surfaces. 1910 Subpart E - Means of Egress 1910 Subpart E App - Exit Routes, Emergency Action Plans, and Fire Prevention Plans. 1910.33 - Table of contents. 1910.34 - Coverage and definitions. 1910.35 - Compliance with NFPA 101-2000, Life Safety Code. 1910.36 - Design and construction requirements for exit routes. 1910.37 - Maintenance, safeguards, and operational features for exit routes. 1910.38 - Emergency action plans. 1910.39 - Fire prevention plans. 1910 Subpart F - Powered Platforms, Manlifts, and Vehicle-Mounted Work Platforms 1910.66 - Powered platforms for building maintenance. 1910.66 App A - Guidelines (Advisory) 1910.66 App B - Exhibits (Advisory) 1910.66 App C - Personal Fall Arrest System (Section I - Mandatory; Sections II and III - Non- 1910.66 App D - Existing Installations (Mandatory)

UT Austin 111511 AGC-29

1910.67 - Vehicle-mounted elevating and rotating work platforms. 1910.68 - Manlifts. 1910 Subpart G - Occupational Health and Environment Control 1910.94 - Ventilation. 1910.95 - Occupational noise exposure. 1910.95 App A - Noise exposure computation 1910.95 App B - Methods for estimating the adequacy of hearing protector attenuation 1910.95 App C - Audiometric measuring instruments 1910.95 App D - Audiometric test rooms 1910.95 App E - Acoustic calibration of audiometers 1910.95 App F - Calculations and application of age corrections to audiograms 1910.95 App G - Monitoring noise levels non-mandatory informational appendix 1910.95 App H - Availability of referenced documents 1910.95 App I - Definitions 1910.97 - Nonionizing radiation. 1910.98 - Effective dates. 1910 Subpart H - Hazardous Materials 1910.101 - Compressed gases (general requirements). 1910.102 - Acetylene. 1910.103 - Hydrogen. 1910.104 - Oxygen. 1910.105 - Nitrous oxide. 1910.106 - Flammable and combustible liquids. 1910.107 - Spray finishing using flammable and combustible materials. 1910.108 - Dip tanks containing flammable or combustible liquids. 1910.109 - Explosives and blasting agents. 1910.110 - Storage and handling of liquefied petroleum gases. 1910.111 - Storage and handling of anhydrous ammonia. 1910.112 – 113 [Reserved] 1910.119 - Process safety management of highly hazardous chemicals. 1910.119 App A - List of Highly Hazardous Chemicals, Toxics and Reactives (Mandatory). 1910.119 App B - Block Flow Diagram and Simplified Process Flow Diagram (Non-mandatory).

1910.119 App C - Compliance Guidelines and Recommendations for Process Safety Management (Non-mandatory).

1910.119 App D - Sources of Further Information (Non-mandatory). 1910.120 - Hazardous waste operations and emergency response. 1910.120 App A - Personal protective equipment test methods. 1910.120 App B - General description and discussion of the levels of protection and protective gear. 1910.120 App C - Compliance guidelines. 1910.120 App D - References. 1910.120 App E - Training Curriculum Guidelines - (Non-mandatory) 1910.121 - Reserved 1910.122 - Table of contents 1910.123 - Dipping and coating operations: Coverage and definitions 1910.124 - General requirements for dipping and coating operations 1910.125 - Additional requirements for dipping and coating operations that use flammable or combustible 1910.126 - Additional requirements for special dipping and coating operations 1910 Subpart I - Personal Protective Equipment

UT Austin 111511 AGC-30

1910.132 - General requirements. 1910.133 - Eye and face protection. 1910.134 - Respiratory Protection. 1910.134 App A - Fit Testing Procedures (Mandatory). 1910.134 App B-1 - User Seal Check Procedures (Mandatory). 1910.134 App B-2 - Respirator Cleaning Procedures (Mandatory). 1910.134 App C - OSHA Respirator Medical Evaluation Questionnaire (Mandatory). 1910.134 App D - (Mandatory) Information for Employees Using Respirators When not required Under 1910.135 - Head protection. 1910.136 - Occupational foot protection. 1910.137 - Electrical protective devices. 1910.138 - Hand Protection. 1910 Subpart I App A - References for further information (Non-mandatory)

1910 Subpart I App B - Non-mandatory Compliance Guidelines for Hazard Assessment and Personal Protective Equipment Selection.

1910 Subpart J - General Environmental Controls 1910.141 - Sanitation. 1910.142 - Temporary labor camps. 1910.143 - Non-water carriage disposal systems. 1910.144 - Safety color code for marking physical hazards. 1910.145 - Specifications for accident prevention signs and tags. 1910.145(f) App A - Recommended color coding 1910.145(f) App B - References for further information 1910.146 - Permit-required confined spaces 1910.146 App A - Permit-required Confined Space Decision Flow Chart 1910.146 App B - Procedures for Atmospheric Testing. 1910.146 App C - Examples of Permit-required Confined Space Programs 1910.146 App D - Confined Space Pre-Entry Check List 1910.146 App E - Sewer System Entry. 1910.146 App F - Non-Mandatory Appendix F -- Rescue Team or Rescue Service Evaluation Criteria 1910.147 - The control of hazardous energy (lockout/tagout). 1910.147 App A - Typical minimal lockout procedures 1910 Subpart K - Medical and First Aid 1910.151 - Medical services and first aid. 1910.151 App A - Appendix A to § 1910.151 -- First aid kits (Non-Mandatory) 1910.152 - [Reserved] 1910 Subpart L - Fire Protection 1910.155 - Scope, application and definitions applicable to this subpart. 1910.156 - Fire brigades. 1910.157 - Portable fire extinguishers. 1910.158 - Standpipe and hose systems. 1910.159 - Automatic sprinkler systems. 1910.160 - Fixed extinguishing systems, general. 1910.161 - Fixed extinguishing systems, dry chemical. 1910.162 - Fixed extinguishing systems, gaseous agent. 1910.163 - Fixed extinguishing systems, water spray and foam. 1910.164 - Fire detection systems. 1910.165 - Employee alarm systems.

UT Austin 111511 AGC-31

1910 Subpart L App A - Fire Protection 1910 Subpart L App B - National Consensus Standards 1910 Subpart L App C - Fire Protection references for further information 1910 Subpart L App D - Availability of publications incorporated by reference in section 1910.156 fire brigades 1910 Subpart L App E - Test methods for protective clothing 1910 Subpart M - Compressed Gas and Compressed Air Equipment 1910.166 - 168 [Reserved] 1910.169 - Air receivers. 1910 Subpart N - Materials Handling and Storage 1910.176 - Handling materials - general. 1910.177 - Servicing multi-piece and single piece rim wheels. 1910.177 App A - Trajectory 1910.177 App B - Ordering information for NHTSA charts 1910.178 - Powered industrial trucks. 1910.178 App A - Powered industrial trucks. 1910.179 - Overhead and gantry cranes. 1910.180 - Crawler locomotive and truck cranes. 1910.181 - Derricks. 1910.183 - Helicopters. 1910.184 - Slings. 1910 Subpart O - Machinery and Machine Guarding 1910.211 - Definitions. 1910.212 - General requirements for all machines. 1910.213 - Woodworking machinery requirements. 1910.214 - Cooperage machinery. [Reserved] 1910.215 - Abrasive wheel machinery. 1910.216 - Mills and calendars in the rubber and plastics industries. 1910.217 - Mechanical power presses. 1910.217 App A - Mandatory requirements for certification/validation of safety systems for presence

sensing device initiation of mechanical power presses 1910.217 App B - Non-mandatory guidelines for certification/validation of safety systems for presence sensing device initiation of mechanical power presses 1910.217 App C - Mandatory requirements for OSHA recognition of third-party validation organizations for the PSDI standard

1910.217 App D - Non-mandatory supplementary information 1910.218 - Forging machines. 1910.219 - Mechanical power-transmission apparatus. 1910 Subpart P - Hand and Portable Powered Tools and Other Hand-Held Equipment 1910.241 - Definitions. 1910.242 - Hand and portable powered tools and equipment, general. 1910.243 - Guarding of portable powered tools. 1910.244 - Other portable tools and equipment. 1910 Subpart Q - Welding, Cutting, and Brazing 1910.251 - Definitions. 1910.252 - General requirements. 1910.253 - Oxygen-fuel gas welding and cutting. 1910.254 - Arc welding and cutting. 1910.255 - Resistance welding.

UT Austin 111511 AGC-32

1910 Subpart R - Special Industries 1910.261 - Pulp, paper, and paperboard mills. 1910.262 - Textiles. 1910.263 - Bakery equipment. 1910.264 - Laundry machinery and operations. 1910.265 - Sawmills. 1910.266 - Logging operations. 1910.266 App A - First-aid Kits (Mandatory). 1910.266 App B - First-aid and CPR Training (Mandatory). 1910.266 App C - Comparable ISO Standards (Non-mandatory) 1910.267 - Reserved. 1910.268 - Telecommunications. 1910.269 - Electric Power Generation, Transmission, and Distribution. 1910.269 App A - Flow Charts. 1910.269 App B - Working on Exposed Energized Parts. 1910.269 App C - Protection from Step and Touch Potentials. 1910.269 App D - Methods of Inspecting and Testing Wood Poles. 1910.269 App E - Reference Documents. 1910.272 - Grain handling facilities. 1910.272 App A - Grain handling facilities 1910.272 App B - National consensus standards 1910.272 App C - References for further information 1910 Subpart S - Electrical 1910.301 - Introduction. 1910.302 - Electric utilization systems. 1910.303 - General requirements. 1910.304 - Wiring design and protection. 1910.305 - Wiring methods, components, and equipment for general use. 1910.306 - Specific purpose equipment and installations. 1910.307 - Hazardous (classified) locations. 1910.308 - Special systems. 1910.309 - 330 [Reserved] 1910.331 - Scope 1910.332 - Training 1910.333 - Selection and use of work practices 1910.334 - Use of equipment. 1910.335 - Safeguards for personnel protection. 1910.336 - [Reserved] 1910.337 – 398 [Reserved] 1910.399 - Definitions applicable to this subpart. 1910 Subpart S App A - Reference Documents 1910 Subpart T - Commercial Diving Operations 1910.401 - Scope and application. 1910.402 - Definitions. 1910.410 - Qualifications of dive team. 1910.420 - Safe practices manual. 1910.421 - Pre-dive procedures. 1910.422 - Procedures during dive.

UT Austin 111511 AGC-33

1910.423 - Post-dive procedures. 1910.424 - SCUBA diving. 1910.425 - Surface-supplied air diving. 1910.426 - Mixed-gas diving. 1910.427 - Live boating. 1910.430 - Equipment. 1910.440 - Recordkeeping requirements. 1910 Subpart T App A - Examples of conditions which may restrict or limit exposure to hyperbaric conditions 1910 Subpart T App B - Guidelines for scientific diving

1910 Subpart T App C - Alternative Conditions Under 1910.401(a)(3) for Recreational Diving Instructors and Diving Guides (Mandatory)

1910 Subpart U – Subpart V [Reserved] 1910 Subpart W - Program Standard 1910 Subpart X – Subpart Y [Reserved] 1910 Subpart Z - Toxic and Hazardous Substances 1910.1000 - Air contaminants. 1910.1000 TABLE Z-1 - TABLE Z-1 Limits for Air Contaminants. 1910.1000 TABLE Z-2 - TABLE Z-2 1910.1000 TABLE Z-3 - TABLE Z-3 Mineral Dusts 1910.1001 - Asbestos. 1910.1001 App A - OSHA Reference Method - Mandatory 1910.1001 App B - Detailed procedure for asbestos sampling and analysis - Non-Mandatory 1910.1001 App C - Qualitative and quantitative fit testing procedures - Mandatory 1910.1001 App D - Medical questionnaires; Mandatory 1910.1001 App E - Interpretation and classification of chest roentgenograms - Mandatory

1910.1001 App F - Work practices and engineering controls for automotive brake and clutch inspection, disassembly, repair and assembly -- Mandatory

1910.1001 App G - Substance technical information for asbestos - Non-Mandatory 1910.1001 App H - Medical surveillance guidelines for asbestos - Non-Mandatory 1910.1001 App I - Smoking Cessation Program Information for Asbestos - Non-Mandatory. 1910.1001 App J - Polarized Light Microscopy of Asbestos -- Non-Mandatory 1910.1002 - Coal tar pitch volatiles; interpretation of term. 1910.1003 - 13 Carcinogens (4-Nitrobiphenyl, etc.). 1910.1004 - alpha-Naphthylamine. 1910.1005 - [Reserved] 1910.1006 - Methyl chloromethyl ether. 1910.1007 - 3,3'-Dichlorobenzidine (and its salts). 1910.1008 - bis-Chloromethyl ether. 1910.1009 - beta-Naphthylamine. 1910.1010 - Benzidine. 1910.1011 - 4-Aminodiphenyl. 1910.1012 - Ethyleneimine. 1910.1013 - beta-Propiolactone. 1910.1014 - 2-Acetylaminofluorene. 1910.1015 - 4-Dimethylaminoazobenzene. 1910.1016 - N-Nitrosodimethylamine. 1910.1017 - Vinyl chloride. 1910.1017 App A - Supplemental medical information

UT Austin 111511 AGC-34

1910.1018 - Inorganic arsenic. 1910.1018 App A - Inorganic arsenic substance information sheet 1910.1018 App B - Substance technical guidelines 1910.1018 App C - Medical surveillance guidelines 1910.1020 - Access to employee exposure and medical records.

1910.1020 App A - Sample authorization letter for the release of employee medical record information to a designated representative (Non-mandatory) 1910.1020 App B - Availability of NIOSH registry of toxic effects of chemical substances (RTECS)(Non-mandatory)

1910.1025 - Lead. 1910.1025 App A - Substance data sheet for occupational exposure to lead 1910.1025 App B - Employee standard summary 1910.1025 App C - Medical surveillance guidelines 1910.1025 App D - Qualitative fit test protocols 1910.1026 - Chromium (VI) 1910.1026 App A - Chromium (VI) 1910.1027 - Cadmium 1910.1027 App A - Substance Safety Data Sheet - Cadmium 1910.1027 App B - Substances Technical Guidelines for Cadmium 1910.1027 App C - Qualitative and Quantitative Fit Testing Procedures 1910.1027 App D - Occupational Health History Interview With Reference to Cadmium Exposure 1910.1027 App E - Cadmium in Workplace Atmospheres 1910.1027 App F - Nonmandatory Protocol for Biological Monitoring 1910.1028 - Benzene. 1910.1028 App A - Substance safety data sheet, Benzene 1910.1028 App B - Substance technical guidelines, Benzene 1910.1028 App C - Medical surveillance guidelines for Benzene 1910.1028 App D - Sampling and analytical methods for Benzene monitoring and measurement 1910.1028 App E - Qualitative and Quantitative fit testing procedures 1910.1029 - Coke oven emissions. 1910.1029 App A - Coke oven emissions substance information sheet 1910.1029 App B - Industrial hygiene and medical surveillance guidelines 1910.1030 - Bloodborne pathogens. 1910.1030 App A - Hepatitis B Vaccine Declination (Mandatory) 1910.1043 - Cotton dust. 1910.1043 App A - Air sampling and analytical procedures for determining concentrations of cotton 1910.1043 App B-I - Respiratory questionnaire 1910.1043 App B-II - Respiratory questionnaire for non-textile workers for the cotton industry 1910.1043 App B-III - Abbreviated respiratory questionnaire 1910.1043 App C - Spirometry prediction tables for normal males and females 1910.1043 App D - Pulmonary function standards for cotton dust standard 1910.1043 App E - Vertical elutriator equivalency protocol 1910.1044 - 1,2-dibromo-3-chloropropane. 1910.1044 App A - Substance safety data sheet for DBCP 1910.1044 App B - Substance technical guidelines for DBCP 1910.1044 App C - Medical surveillance guidelines for DBCP 1910.1045 - Acrylonitrile.

UT Austin 111511 AGC-35

1910.1045 App A - Substance safety data sheet for acrylonitrile 1910.1045 App B - Substance technical guidelines for acrylonitrile 1910.1045 App C - Medical surveillance guidelines for acrylonitrile 1910.1045 App D - Sampling and analytical methods for acrylonitrile 1910.1047 - Ethylene oxide. 1910.1047 App A - Substance safety data sheet for ethylene oxide (non-mandatory) 1910.1047 App B - Substance technical guidelines for ethylene oxide (Non-mandatory) 1910.1047 App C - Medical surveillance guidelines for ethylene oxide (Non-mandatory) 1910.1047 App D - Sampling and analytical methods for ethylene oxide (Non-mandatory) 1910.1048 - Formaldehyde. 1910.1048 App A - Substance technical guidelines for formalin 1910.1048 App B - Sampling strategy and analytical methods for formaldehyde 1910.1048 App C - Medical surveillance - Formaldehyde 1910.1048 App D - Nonmandatory medical disease questionnaire 1910.1048 App E - Qualitative and quantitative fit testing procedures 1910.1050 - Methylenedianiline 1910.1050 App A - Substance Data Sheet, for 4,4'-Methylenedianiline 1910.1050 App B - Substance Technical Guidelines, MDA 1910.1050 App C - Medical Surveillance Guidelines for MDA 1910.1050 App D - Sampling and Analytical Methods for MDA Monitoring and Measurement 1910.1050 App E - Qualitative and Quantitive Fit Testing Procedures 1910.1051 - 1,3-Butadiene. 1910.1051 App A - Substance Safety Data Sheet For 1,3-Butadiene (Non-Mandatory) 1910.1051 App B - Substance Technical Guidelines for 1,3-Butadiene (Non-Mandatory) 1910.1051 App C - Medical Screening and Surveillance for 1,3-Butadiene (Non-Mandatory) 1910.1051 App D - Sampling and Analytical Method for 1,3-Butadiene (Non-Mandatory) 1910.1051 App E - Respirator Fit Testing Procedures (Mandatory) 1910.1051 App F - Medical Questionnaires, (Non-mandatory) 1910.1052 - Methylene Chloride. 1910.1052 App A - Substance Safety Data Sheet and Technical Guidelines for Methylene Chloride. 1910.1052 App B - Medical Surveillance for Methylene Chloride. 1910.1052 App C - Questions and Answers - Methylene Chloride Control in Furniture Stripping. 1910.1096 - Ionizing radiation. 1910.1200 - Hazard Communication. 1910.1200 App A - Health Hazard Definitions (Mandatory) 1910.1200 App B - Hazard determination (Mandatory) 1910.1200 App C - Information sources (Advisory) 1910.1200 App D - Definition of "Trade Secret" (Mandatory) 1910.1200 App E - Guidelines for Employer Compliance (Advisory) 1910.1201 - Retention of DOT markings, placards and labels. 1910.1450 - Occupational exposure to hazardous chemicals in laboratories.

1910.1450 App A - National Research Council Recommendations Concerning Chemical Hygiene in Laboratories (Non-Mandatory)

1910.1450 App B - References (Non-Mandatory)

UT Austin 111511 AGC-36

Table of OSHA Construction Standards Subpart A (1926.1 – 1926.5) - General Subpart B (1926.10 – 1926.16) - General Interpretations Subpart C (1926.20 – 1926.35) - General Safety and Health Provisions Subpart D (1926.50 – 1926.66) - Occupational Health and Environmental Controls Subpart E (1926.95 – 1926.107) - Personal Protective and Life Saving Equipment Subpart F (1926.150 – 1926.155) - Fire Protection and Prevention Subpart G (1926.200 – 1926.203) - Signs, Signals and Barricades Subpart H (1926.250 – 1926.252) - Materials Handling, Storage, Use and Disposal Subpart I (1926.300 – 1926.307) - Tools – Hand and Power Subpart J (1926.350 – 1926.354) - Welding and Cutting Subpart K (1926.400 – 1926.449) - Electrical Subpart L (1926.450 – 1926.454) - Scaffold Subpart M (1926.500 – 1926.503) - Fall Protection Subpart N (1926.550 – 1926.555) - Cranes, Derricks, Hoists, Elevators and Conveyors Subpart O 1926.600 – 1926.606) - Motor Vehicles, Mechanized Equipment and Marine Subpart P (1926.650 – 1926.652) - Excavations Subpart Q (1926.700 – 1926.706) - Concrete and Masonry Construction Subpart R (1926.750 – 1926.752) - Steel Erection Subpart S (1926.800 – 1926.804) - Underground Construction, Caissons, Cofferdams, and Subpart T (1926.850 – 1926.860) - Demolition Subpart U (1926.900 – 1926.914) - Blasting and the Use of Explosives Subpart V (1926.950 – 1926.960) - Power Transmission and Distribution Subpart W (1926.1000 – 1926.1003) - Rollover Protective Structures; Overhead Protection Subpart X (1926.1050 – 1926.1060) - Stairways and Ladders Subpart Y (1926.1071 – 1926.1092) - Diving Subpart Z (1926.1100 – 1926.1152) - Toxic and Hazardous Substances

UT Austin 111511 AGC-37

ARTICLE 8. QUALITY CONTROL 8.3 Submittals

8.3.1 Contractor’s Submittals:

8.3.1.1 [Revise first sentence to read] The Contractor shall within SEVEN (7) CALENDAR DAYS of the effective date of the Notice To Proceed of construction submit to the ODR, and the AE, a submittal schedule/register, organized by specification section which lists all items to be furnished for review and approval by the Architect/Engineer and Owner.

8.3.1.2 [Revise fourth and fifth sentences to read] Show and allow a minimum of SEVEN (7) CALENDAR DAYS duration after receipt by the Architect/Engineer and ODR for review and approval. The review time is based on having all related submittals at the same time that may relate to each other or a related assembly in order to approve any individual submittal. If re-submittal is required, allow a minimum of an additional SEVEN (7) CALENDAR DAYS for review.

ARTICLE 9. PROJECT SCHEDULING REQUIREMENTS 9.3 Work Progress Schedule:

[Revise 2nd sentence to read] “Unless indicated otherwise in those documents, Contractor shall submit their initial Work Progress Schedule for the Work in relation to the entire project not later than SEVEN (7) CALENDAR DAYS after the effective date of the Notice to Proceed to the ODR and the AE.”

9.6 Modification of the Contract Time:

9.6.2.1.1 Requests for extension shall meet the following conditions.

9.6.2.1.1.1 Work could not have been done on any other portion of the Project without adverse consequences.

9.6.2.1.1.2 No one day will be counted more than once. 9.6.2.1.1.3 Lost holidays or weekends will not be

counted unless the work day preceding the holiday(s) is lost because of inclement weather and the conditions continue into the non-work days.

9.6.2.1.2 Contractor shall maintain a log of the weather conditions

throughout the Project and this log shall be made available to the Project Manager upon his request.

9.6.2.1.3 If the work cannot be completed during the designated

period due to inclement weather or circumstances beyond the Contractor's control, the Contractor shall make arrangements with the Project Manager to complete the remaining work in a manner which will cause the least interference with the Owner's operations.

UT Austin 111511 AGC-38

9.11.1 [Add] If the Contractor does not complete all work at the time stipulated in the

contract plus any additional time added to the contract by approved change orders, the Owner may assess liquidated damages in the amounts stated in the Special Conditions.

9.11.2 [Add] If the Contractor does not complete all deficiencies within the time limits

indicated in the Substantial Completion Certificate or other items required by the Contract, the Owner may additionally charge liquidated damages (as mentioned above) from the deadline set in the Certificate until all items are completed and accepted.

ARTICLE 10. PAYMENTS 10.1 Schedule of Values:

10.1.1.2 [Add] Costs of the Work referenced  in 10.1.1.1  includes costs for shop drawings,  submittals,  site  investigation,  calculations  etc.  and  shall  be included in its various classification of work. 

10.1.1.3 [Add] In addition to scheduling costs for preparing Close‐Out documents, schedule a value for training when training is required. 

10.3 Owner’s Duty to Pay:

10.3.2 [Add] The Owner shall retain 10% of the amount of each progress pay request’s Total Completed To Date amount until final completion and acceptance of all work covered by this Contract. The Architect / Engineer will not reduce the amount retained below 10%. The above 10% retainage shall be 5% on projects greater than $400,000.

10.3.2.4 [Add] Each progress pay request shall be submitted on the form

“Application and Certificate for Payment ” provided to the Contractor by UEM at the time of Notice to Proceed.

10.3.2.4.1 Each item listed under "Description of Work" shall be

subdivided into "Labor" and “Material" items; each to be calculated as a separate line item across the sheet.

10.3.2.5 [Add] Should a progress payment request include materials stored off-

site, the Contractor shall submit to the Owner an insurance policy for the value of the off-site stored materials which names The University of Texas at Austin as the insured. This is in addition to other insurance requirements of these Specifications. This may be part of the Builders Risk Certificate if name, address and location are specifically named.

UT Austin 111511 AGC-39

10.3.2.6 [Add] Payment for labor and/or materials shall be inclusive of

submittals, shop drawings, etc. as required to commence any Work referenced in 8.3.1 and/or survey, plan and direct the Work. Payment for cost of submittals, shop drawings, site investigation, calculations etc. shall be scheduled with value for installation of the respective materials. Projects having fire sprinkler scope of work valued at 75% or greater of the entire contract amount may schedule a value up to 5% of the total value of the work for payment of approved sprinkler design submittals unless otherwise agreed by the ODR. Payment for Work referenced in 10.2 excludes all off site efforts unless otherwise approved by the ODR and in accordance with 10.5.

ARTICLE 11. CHANGES 11.1 Change Orders:

11.1.3 [Add] The Contractor shall submit change proposals indicating all related costs for the change and indicating the respective allowable percentage mark ups and breakdown (as may be allowed in the UGC). These proposals shall be submitted on a form approved by the Owner or on a layout and form that may be provided by the Owner. All proposals shall be signed by the Contractor’s representative. Request for time extensions for changes shall be made at the same time. Contractor shall submit revised HSP Plan on any new trades added to the project and shall revise the PAR amounts for subcontractors with next Pay Application following the execution of Change Orders.

11.7.2 [Revise last sentence to read] Contractor shall provide written response to

change request within SEVEN (7) CALENDAR DAYS of receipt. ARTICLE 12. PROJECT COMPLETION AND ACCEPTANCE 12.1 Closing Inspections:

12.1.1.1.1 [Add] The Contractor must complete and submit the Equipment Add-Delete-Modification log as required in Paragraph 6.2.3.1. The format of this log shall be furnished to the Contractor and is available through the UEM website.

12.1.2 Final Inspection: [Revise 2nd sentence as bolded] Unless otherwise specified,

or otherwise agreed in writing by the parties as documented on the Certificate of Substantial Completion, the Contractor shall complete and/or correct all work within FOURTEEN (14) CALENDAR DAYS of the Substantial Completion date.

UT Austin 111511 AGC-40

12.3 Acceptance & Payment:

12.3.2 [Revise as bolded] Final Payment Documentation: Prior to or with the Application for Final Payment, Contractor shall submit final electronic copies of all close out documents, maintenance and operating manuals, guarantees and warranties, certification of No Asbestos Containing Materials (art 13.7), MSDS sheets for all materials, certificates of substantial completion, record documents, as constructed drawings, evidence of the Contractor’s return of all keys and access cards, and all other items required by the Contract. Submit original Consent of Surety to Final Payment and an affidavit that all payrolls, bills for materials and equipment, subcontracted work and other indebtedness connected with the Work, except as specifically noted, are paid, will be paid, or otherwise satisfied within the period of time required by Tex. Gov’t Code, Chapter 2251. Furnish documentation establishing payment or satisfaction of all such obligations, such as receipts, releases and waivers of claims and liens arising out of the Contract. The Contractor may not subsequently submit a claim on behalf of a subcontractor or vendor unless the Contractor’s affidavit notes that claim as an exception.

ARTICLE 17. TEMPORARY FACILITIES 17.1 Temporary Utilities: The Owner will provide all necessary utilities free of usage

charges. Temporary connections or extensions of existing utility services shall be provided and removed at the completion of the Work at the Contractor's expense.

17.2 Barricades, Warning Signs and Lights: Comply with recognized standards and code

requirements for the erection of substantial barricades where needed to prevent accidents. Contractor shall provide signage and appropriate barricades to prevent any unsafe condition from developing during the course of the Contract. Contractor shall properly store and secure materials to prevent unauthorized use.

17.3 Temporary Fire Protection: Review fire prevention and protection needs with the

ODR and Owner's Fire Prevention Services officials and establish procedures to be followed in the event of fire. Instruct personnel in procedures and post warnings and information. Maintain unobstructed access to fire extinguishers, temporary fire protection facilities, stairways, and other access routes. Prohibit smoking in hazardous areas. Provide supervision of welding operations, combustion type temporary heating units, and similar sources of ignition.

17.3.1 The Contractor shall be responsible for initiating, maintaining, and supervising

safety precautions and programs associated with the Work. It shall be the duty and responsibility of the Contractor to comply with all pertinent sections of the Occupational Safety and Health Act of 1975, and all amendments thereof. The contractor shall do all things necessary and provide all equipment and labor necessary to protect students, staff, faculty, and the general public from dangers associated with the Contract. Walkways, parking areas, and other areas surrounding the job site will be in use and given priority. The University shall not be held responsible for failure of the Contractor to perform the job in a safe manner.

UT Austin 111511 AGC-41

17.4 Temporary Sanitary Facilities: Contractor shall furnish temporary sanitary facilities for the needs of all construction workers and others performing work or furnishing services on the project with the following limitations:

17.4.1 Sanitary facilities shall be obscured from public view to the greatest practical

extent.

17.4.2 The location shall be acceptable to Owner.

17.4.3 Sanitary facilities shall consist of properly-enclosed, self-contained portable units equipped with reservoirs. Reservoirs shall be maintained in proper sanitary condition by chemical treatment and periodic cleaning.

17.4.4 Contractor shall enforce the use of such sanitary facilities by all personnel at the

site. ARTICLE 18. ADDITIONAL CONDITIONS (THE UNIVERSITY OF TEXAS AT AUSTIN ENVIRONMENTAL HEALTH AND SAFETY) 18.1 CONSTRUCTION SITE PROCEDURES FOR CONTRACTORS

COMMON PROBLEMS FOR CONTRACTORS

♦ Equipment Cleaning Equipment must be cleaned in a manner that does not create any discharge of cleaning agents, paints, oil or other pollutants to a storm sewer or waterway. Soaps and detergents must never be discharged to the ground or off-site. When rinsing painting equipment outside, rinse water must be contained in a bucket or other container. Water-based or latex paint rinse water may be discharged to the sanitary sewer. Oil-based paint wastes, including solvents and thinners, must not be disposed of in the sanitary sewer; they must be collected and disposed of through the Contractor's disposal company in accordance with applicable laws and regulations. Cement handling equipment must be rinsed in a contained area and there must be no drainage off-site.

♦ Pressure Washing Discharges from pressure washing must not be allowed to enter a storm sewer or waterway. Consider vacuuming up the water or berming the process water and allowing it to evaporate. If the rinsate only contains water and dirt or sediment it may be spread on the ground with prior permission from UEM and Environmental Health & Safety, and if it will not enter a storm sewer or waterway. Depending on the content of the material it may also be possible to discharge to a sanitary sewer with prior permission from Environmental Health & Safety. UT project managers must be involved in the discharge request. (Permission to discharge to sanitary sewer may take up to five working days.)

UT Austin 111511 AGC-42

♦ Waste Disposal Any trash or debris must be contained on-site and disposed of in a recycling bin or waste receptacle in accordance with applicable laws and regulations to prevent wind or rain from carrying it off-site into a storm drain or waterway. Petroleum wastes, such as waste oil and used oil filters, must be containerized for recycling or disposal by the Contractor. Non-hazardous solid wastes, such as general construction debris may be recycled or disposed of in the trash container. Never dispose of liquid wastes of any kind in dumpsters.

♦ Packing Lamps Used fluorescent, high intensity discharge (HID), and UV germicidal lamps must be collected in containers that protect the lamps during storage and transportation. The original shipping container is the preferred package for spent lamps. Remove extra cardboard end pieces to assure that lamps fit in the box. Remove any plastic lamp sleeves and tape from spent lamps when packing for waste collection. Environmental Health & Safety also has boxes available for packaging standard four foot and eight foot length fluorescent lamps. To receive a packing box call 512-475-9738. An open top metal drum should be used for other types of lamps such as small lamps, mercury vapor lamps, and other odd shaped fluorescent tubes. In the case of smaller bulbs, additional packing materials such as vermiculite must be added to prevent breakage.

♦ Broken Florescent Lamps When fluorescent lamps and HIDs are broken, mercury is released to the environment, but some mercury still remains on the surfaces of the glass, phosphor, and the metal or plastic. If a fluorescent, HID, or UV germicidal lamp is broken, all the broken parts must be collected as a hazardous material. Dedicate 30 gallon metal drums labeled with the words "broken fluorescent lamps" to collect the broken pieces, and contact EHS for disposal when the drum is full. The drum must be sealed when it is not actively receiving broken bulbs.

♦ Sediment Proper erosion and sedimentation controls must be in place prior to any construction activity to prevent sediment or silt run-off. Sediment (including cement) should never be rinsed off the site; instead it must be cleaned up in a manner that does not allow it to reach a storm drain or waterway. Equipment tires must be rinsed before leaving the site, if necessary, to avoid tracking sediment into the roadway or off the site. Erosion and sediment control plans and/or Storm Water Pollution Prevention Plans shall be submitted to EHS. All erosion and sediment controls are to be maintained through the duration of the construction and until all areas are stabilized. All vehicles must leave the site through a stabilized construction entrance meeting the requirements of the University's Construction Standard regarding Erosion and Sedimentation Controls.

♦ Site Dewatering, Tank, & Pipe Testing Discharges from dewatering, hydrostatic tank testing or pipe pressure testing must be free from sediment, chemicals, and any other pollutants. Some discharges, such as those from underground storage tank pits, may require City of Austin temporary discharge permits and the Contractor is responsible for obtaining such permits. Notify EHS before dewatering and/or discharging.

UT Austin 111511 AGC-43

♦ Petroleum Spills of hydraulic fluid, oil, and other petroleum products must always be immediately cleaned up to prevent discharge of these fluids with storm water run-off. Petroleum-contaminated soil must be cleaned up and disposed of properly in accordance with applicable laws and regulations. Storage containers must be kept closed, clean, and free of oily residue. Containers over 55 gallons (including mobile tanks) must be stored inside secondary containment.

♦ Separators or Traps Before removing oil/water separators or traps connected to storm sewers, the materials in them must have been tested by Toxicity Characteristic Leachate Procedure (TCLP) within the last two years before they are cleaned out. Be aware that this test may take three weeks to complete if a recent test has not been conducted. Contractor is solely responsible for accommodating the time for such testing and no claims for delay arising out of such testing will be permitted. Documentation of the test results must be submitted to EHS staff for review and approval before emptying or removing the trap.

18.2 SPILL PREVENTION, CLEAN-UP AND DISPOSAL

Be prepared to contain spills to prevent spreading. Small areas are easier to clean than large ones. Keep sorbent materials such as clay (kitty litter), polypropylene booms and pads, rags and sawdust on hand for clean-up of spilled liquids.

♦ Clean-Up Sorbent materials can be used to effectively clean-up various materials spilled on pavement, water and soil. Soil or other media which has been contaminated with petroleum or other pollutants must be excavated or remediated in accordance with applicable laws and regulations to prevent contaminated discharges to a storm drain or waterway. Excavated contaminated materials must be stored in containers or on plastic and covered so as to ensure that the contamination is not flushed back onto the ground during a rainstorm.

♦ Contaminated Material Disposal Proper disposal of waste materials depends partly on the type of contaminant. Hazardous wastes (such as flammable petroleum products, solvents, thinners, and materials contaminated with hazardous wastes) are considered regulated wastes, and should be containerized for transport and disposal by a permitted company in accordance with applicable laws and regulations. Disposal also depends on the amount of contaminant.

18.3 CONTRACTOR REQUIREMENTS AND RESPONSIBILITIES

18.3.1 Contractors are solely responsible for cleaning up and properly disposing of all spilled pollutants brought to the site as part of the Contractor's work (including oil, paint, fuels, antifreeze, solvents, etc.), in accordance with applicable laws and regulations. Contractor must keep accurate records (such as receipts, copies of analytical results, etc.), indicating proper disposal of spilled materials in accordance with applicable laws and regulations. Contractor is responsible for ensuring that all discharges from the site are in compliance with all applicable laws and regulations.

UT Austin 111511 AGC-44

18.3.2 No substance may be dumped or leaked onto the ground or allowed to run-off of a construction site that might cause pollution. Be aware that Contractor is responsible for pollutant contaminated run-off and proper disposal of all waste materials generated as a result of Contractor's activities.

18.4 NOTIFICATION REQUIREMENTS AND PROCEDURES

Environmental, Health and Safety office and the ODR should be notified immediately in the event of: • Any spill that threatens to enter a storm sewer or watercourse. • All petroleum spills (e.g., hydraulic fluid, transmission fluid, diesel, gasoline,

etc.). • Any hazardous or unknown material spill (e.g. many solvents, cleaners, etc.). • Any discharge from your site which you suspect may be in violation of City

Code, state regulations, or other applicable laws and regulations (e.g. discharges which are cloudy, foul smelling, colored, contain chemicals, or heavy sediment loads).

Notification can be accomplished by calling the UT-Austin EH&S at 512-471-3511 (after normal working hours, press "0" during the recording).

Environmental Health and Safety acknowledges the assistance of the City of Austin Environment and Conservation Services Department for the use of information in this document.

ARTICLE 19. OPEN ORDER LABOR (OOL) SOLICITATIONS 19.1 OOL: Open Order Labor only solicitations (part of the Job Order Contracting program),

for the most part deal with labor only types of Job Order agreements that supplement UT shop employee labor and are under the direct supervision of UT personnel. OOL agreements do not necessarily relate to conventional project requirements involving drawings and specifications and except for rare occasions do not involve the purchase of materials and do not allow subcontracting labor. For this reason many of the UGC, Supplemental UGC and AGC items do not apply in total or may be modified as applicable. Some examples would be: not requiring bonds and certain insurance coverage; not requiring retainage or schedule of values on payment invoices; temporary facilities; and other miscellaneous items that would be standard requirements for general construction contracts.

END OF SECTION AGC