STEPS TO ADD TRX 1. Click to the CM Express and select open current area 2. Riht click to the root and select s!nchroni"e #E o$ %hich the %indo% &elo% %ith ' can choose the one !ou need to %ork %ith to '! case M()SC1* is ticked +. A$ter ha,in ticked !ou %ill &e re-uired to click O( and then es to con$ir'

Upload: ali-ali

Post on 04-Oct-2015

5 views

Category:

Documents


0 download

DESCRIPTION

CALL DROPS ANALYSIS

TRANSCRIPT

STEPS TO ADD TRX1. Click to the CM Express and select open current area

2. Right click to the root and select synchronize NE of which the window below with multiple of NEs that you can choose the one you need to work with to my case MKBSC17 is ticked

3. After having ticked you will be required to click OK and then Yes to confirm

4. Having confirmed below is the window that will appear

5. Next step go back to the CM Express click and open planned area , highlight E1 and then click OK

6. After having clicked OK the window below will appear

7. Right click to the root and select synchronize planned area and tick the planned area to my case MKBSC17, then click OK

8. Extend your selection (MKBSC17) to see all the BTSs that are configured and find the BTS you want to add TRX of which to my case(Mgololo) then right click to Mgololo and select device panel the window below will appear9. The right click to your selection then select show BTS topology then the window below will appear10. Go to the particular cell (I mean cell1/cell2/cell3 .) and right click to that cell and select add TRX then add binding

11. Then add binding

12. Double click to jump to CA configuration and assign the frequency then OK

13. Then click bind TRX and then after execution close

14. Having closed to the Set TRX property window click ok to the other window that will remain and you will see the window below of which Mgololo_1 has 4TRXs instead of three

15. Next stage activate the added TRX (to this case 8_173 TRX) by right clicking that TRX and select activate and wait for execution16. Once it is done go to the CM Express again and select planned area and expand down to synchronise planned area data as you can see here below

17. Select export Incremental script

18. The window below will appear and you have to click OK and wait for execution