addendum no. 1 to contract documents for: 10-3-2018...proposal, provided it is in the best interest...
TRANSCRIPT
Addendum No. 1
GROUP 2 BOND PROJECTS for SCHOOL OF THE OSAGE
ADDENDUM NO. 1
TO CONTRACT DOCUMENTS FOR:
GROUP 2 BOND PROJECTS
SCHOOL OF THE OSAGE
OSAGE BEACH, MISSOURI
ARCHITECTS:
SAPP DESIGN ASSOCIATES ARCHITECTS, P.C.
3750 South Fremont Avenue
Springfield, Missouri 65804
October 3, 2018
Bidders are hereby informed that the construction plans and/or specifications are modified as follows:
The following changes, corrections, additions, information and clarification of the Contract Documents are hereby
made a part of the Contract Documents. Acknowledgement of receipt of this Addendum is required as part of this
Contract.
THIS SEAL IS FOR ARCHITECTURAL DISCIPLINES ONLY
ARCHITECT OF RECORD
Sapp Design Associates Architects, P.C.
3750 S. Fremont Ave., Springfield, MO 65804
417-877-9600
Missouri State Certificate of Authority # 000607
Michael J. Sapp, Architect
MO # A-5051
SEAL
10-3-2018
Addendum No. 1
GROUP 2 BOND PROJECTS for SCHOOL OF THE OSAGE
PRODUCT SUBSTITUTIONS and ADDITIONAL MANUFACTURERS:
The following list must be referenced to the appropriate Specification Section, and the manufacturer's name
added to the acceptable manufacturers in each Section. Note: Naming of a manufacturer does not necessarily
certify or warrant that a specific product automatically complies with the contract. The same limitations that
apply to the naming of acceptable manufacturers in the specifications apply to those listed below. The
Contractor must ensure that all products comply with the plans and specification requirements.
(All substitutes must provide work and products to match approved specifications)
1. Section 084113 ALUMINUM-FRAMED ENTRANCES AND STOREFRONTS
• Tubelite Inc.
2. Section 105113 – METAL LOCKERS
• ASI Storage Solutions.
CHANGES TO CONSTRUCTION MANAGER'S MANUAL:
1. See attached revised 003.01 Instructions to Bidders.
2. See attached revised 004.01 Form of Proposal.
3. See attached revised 008.01 Project Schedule.
4. See attached preliminary Schedule 008.02 New Tech Shop, Locker Rooms, and Kitchen Infill 7a-B-C-D
5. See attached preliminary Schedule 008.03 Business Labs Renovations 11 A Room 109
6. See attached preliminary Schedule 008.04 Business Labs Renovations 11 A Rooms 204-205 (DRAMA)
7. See attached preliminary Schedule 008.05 Nurse Station Renovation
8. See attached preliminary Schedule 008.06 Locker room renovations 11D
9. See attached preliminary Schedule 008.07 Auditorium Renovation 10
10. See attached preliminary Schedule 008.08 Band Space Renovation 8
11. See attached preliminary Schedule 008.09 Kitchen Renovation
12. See attached preliminary Schedule 008.10 Choir Space Renovations 10 D
13. See attached 009.02 Bid Packages Index
14. See attached revised 009.02.01 Demolition
15. See attached revised 009.03.01 Concrete
16. See attached revised 009.04.01 Masonry (Supply and Install)
17. See attached revised 009.05.01 Structural-Misc Steel Supply-Install
18. See attached revised 009.07.04 Roofing, Flashing and Sheet Metal
19. See attached revised 009.09.03 Tile and Commercial Flooring
20. See attached revised 009.10.01 Building Specialties (S&I)
21. See attached revised 009.10.08 Lockers (Supply and Install)
22. See attached revised 009.12.02 Audience Seating
23. See attached revised 009.22.01 Plumbing
24. See attached revised 009.23.01 HVAC.
25. See attached revised 009.26.02 Electrical
26. See attached revised 009.28.02 Electronic Safety and Security
CHANGES TO SPECIFICATIONS:
1. Section 042000, UNIT MASONRY
a. REVISE Sub-paragraph 2.3.A.2. as follows: Provide bullnose units for outside corners and opening jambs
unless otherwise indicated.
Addendum No. 1
GROUP 2 BOND PROJECTS for SCHOOL OF THE OSAGE
2. Section 074213.13, FORMED METAL WALL PANELS
a. REVISE Sub-paragraph 2.2.B. as follows: Concealed Fastener Vertical Metal Wall Panels – Type 1.
b. REVISE Sub-paragraph 2.2.B.4 as follows: Panel Height: 1 1/2 inches.
b. ADD Sub-paragraph 2.2.C as follows:
C. Concealed-Fastener Vertical Metal Wall Panels - Type 2
1. Basis-of-Design Product: Subject to compliance with requirements, provide Firestone Flush Panel
UC-500 or comparable product by one of the following:
a. AEP Span; A BlueScope Steel Company.
b. Berridge Manufacturing Company.
c. CENTRIA Architectural Systems.
d. Dimensional Metals, Inc.
e. Fabral.
f. MBCI; a division of NCI Group, Inc.
g. Petersen Aluminum Corporation.
2. Metallic-Coated Steel Sheet: Zinc-coated (galvanized) steel sheet complying with ASTM A 653/A
653M, G90 coating designation, or aluminum-zinc alloy-coated steel sheet complying with ASTM A
792/A 792M, Class AZ50 coating designation; structural quality. Prepainted by the coil-coating
process to comply with ASTM A 755/A 755M.
a. Nominal Thickness: 24 guage .
b. Exterior Finish: Two-coat fluoropolymer.
c. Color: Color to be selected by Architect from Manufacturers standard range.
d. Panel Coverage: 12 inches.
e. Panel Depth: 1 inch.
3. Section 093013, CERAMIC TILING
a. ADD Sub-paragraph 1.2.A 4. Quarry Tile.
b. ADD Sub-paragraph 1.2.A.5. Trowelable Self-Leveling Underlayment and Patching Compound
4. Section 098433, SOUND ABSORBING WALL UNITS
a. OMIT Paragraph 2.1 in its entirety.
b. OMIT Paragraph 2.2 in its entirety
c. OMIT Paragraph 2.3 in its entirety.
d. ADD Paragraph 2.1 back in as follows:
2.1 Geometric Diffuser Sound-Diffusing Panel
A. Constructed from 0.125 inch (3.2 mm) thermo-molded copolymer.
B. Sizes and shapes as indicated on the drawings and as follows:
1. 4 feet x 4 feet x 9.75 inches (1220 x 1220 x 248 mm) radius.
2. 4 feet (actual) x 6 feet (actual) x 9.75 inches (1220 x 1830 x 248 mm) radius.
C. Edge Detail: Rounded pencil edge thermo-molded frame formed on a geometric radius
shaped unit.
D. Finish: Fabric facing: Manufacturer’s standard 100% polyester woven fabric, FR701 Style
2100 by Guilford of Maine.
E. Color: As selected by Architect from manufacturer’s full range of colors.
F. Sound Absorption (ASTM C423): Noise Reduction Coefficient shall be no greater than 0.10
for Type A Mounting (direct mount).
G. Mounting: Wall mount with top of panel angle and Z-clip.
5. Section 126100, FIXED AUDIENCE SEATING (ARM REST AND END PANEL REPLACEMENT ONLY)
Addendum No. 1
GROUP 2 BOND PROJECTS for SCHOOL OF THE OSAGE
a. REVISE Sub-paragraph 3.3.C. and sub-sub paragraph 3.3.C.1 as follows:
C. Row Letter Number Plates.
1. Material: Brass with black embossed characters.
CHANGES TO DRAWINGS: SOTO HS ADDITIONS AND RENOVATIONS
1. Sheet G200, FIRE AREA / CODE PLAN
a. See updated Sheet G200 attached this Addendum.
2. Sheet D102, AREA 11D LOCKER ROOM DEMOLITION PLAN
a. See updated Sheet D102 attached this Addendum.
3. Sheet A104, AREA 11A, 11B AND 11C/7D FLOOR PLANS
a. See updated Sheet A104 attached this Addendum.
4. Sheet A109, ROOF PLANS
a. See updated Sheet A109 attached this Addendum for SCUPPER AND CONDUCTOR HEAD DETAIL 3/A109.
5. Sheet A400, DOOR SCHEDULE
a. See updated Sheet A400 attached this Addendum.
6. Sheet A605, AREA 11D LOCKER ROOM REFLECTED CEILING PLAN
a. See updated Sheet A605 attached this Addendum.
7. Sheet A801 AND A802 FINISH FLOOR PLANS
a. See updated Sheets A801 and A802 attached this Addendum for added note for floor tile pattern in
Corridor 800 and Ensemble Room 402.
MECHANICAL, ELECTRICAL, PLUMBING
SEE ATTACHED DOCUMENTS FROM INTERPRES BUILDING SOLUTIONS, WHICH IS HEREBY MADE A PART OF THIS
ADDENDUM.
STRUCTURAL
SEE ATTACHED DOCUMENTS FROM J&M ENGINEERING, WHICH IS HEREBY MADE A PART OF THIS ADDENDUM.
END OF ADDENDUM 01
003.01 Instructions to Bidders
Page 1 of 3 Instructions to Bidders 003.01 Rev 2 – February 2017
The following instructions apply to all proposals.
1. Proposals from qualified Subcontractors and Suppliers (hereafter called “Bidders”) will
be received at the time and place specified in Section 002.01 Invitation to Bid. Proposals
must be delivered in a sealed envelope.
2. Bidders submitting a proposal for one or more Bid Packages must include the following
information separately for each proposal submitted.
a. Fully executed Form of Proposal
b. Please provide performance and payment bond rate as indicated on the proposal
form.
3. Proposals submitted in a sealed envelope must include the following information on the
front of the envelope.
NABHOLZ CONSTRUCTION CORPORATION
1707 E 123rd Terrace
Olathe, KS 66061
Bid Proposal For: School of the Osage High School Additions
and Renovations
Bid Package .
4. Bidders must fulfill prequalification requirements in accordance with CM’s trade
contractor procurement policy prior to the award of any Bid Package contract.
Prequalification Questionnaires and applicable supporting documents are required
annually, and are available at https://www.nabholz.com/trade-contractors/ or by
contacting the Construction Manager’s (“CM’s”) office at 913.393.6500.
5. Modification to Bid Packages may be cause for rejection of proposal.
6. Bidders warrant they have visited the Project site prior to submission of proposals or
have attended the pre-bid meeting(s) for the purpose of understanding and accepting all
conditions in and around the Project site.
7. Bidders warrant that proposals are submitted in accordance with the requirements of CM
Manual and Contract Documents. Bidders also warrant that proposals are submitted in
accordance with the specification sections and drawings relating to the scope of the Bid
Package.
003.01 Instructions to Bidders
Page 2 of 3 Instructions to Bidders 003.01 Rev 2 – February 2017
8. Bidders must submit questions in writing to the CM no later than seven (7) days prior to
the Bid Date. Use the Request for Information (“RFI”) form found in Section 006.04.
Responses to Bidders’ RFI(s) will be distributed in the form of an Addendum to all
Bidders. Addenda may be issued during the bidding period. Bidders must acknowledge
all Addenda on the Form of Proposal. Addenda become part of the Contract
Documents.
9. Bidders must, immediately notify CM in writing of errors, omissions, discrepancies, or
noncompliance with applicable codes and regulations within the Contract Documents or
any work which will not fit or properly function if installed as indicated in the drawings
and specifications. This requirement in no way relieves Architect of design or
professional service responsibilities.
10. Bidders must comply with all federal, state, local laws, and the rules and regulations of
all authorities having jurisdiction over construction of the Project. Statutes shall apply to
the Subcontract or Purchase Order (“PO”) throughout. Statutes will be deemed to be
included in the Subcontract or PO, the same as though herein written out in full.
11. Subcontracts and PO will be awarded on the basis of the lowest responsible qualified
proposal, provided it is in the best interest of the Owner and/or CM. The Owner and/or
CM reserves the right to reject any and all proposals and to waive any informality in the
proposals.
12. To determine the lowest responsible qualified proposal, the CM will evaluate proposals
based on the following considerations:
a. Total amount of Bidders’ proposal, including Base Bid and Alternate Bids;
b. Acknowledgement of issued Addenda;
c. Bidders’ bonding rate and capacity;
d. Sufficiency of Bidders’ financial resources;
e. Evaluation of Bidders’ labor rates;
f. Bidders’ ability to perform in accordance with the Contract Documents;
g. Bidders’ ability to perform without delay or interference to other trades or scopes
of work;
h. Bidders’ history of performance on previous projects with CM or Owner;
i. Responsibility and reputation of Bidders;
003.01 Instructions to Bidders
Page 3 of 3 Instructions to Bidders 003.01 Rev 2 – February 2017
j. Evaluation of Bidders’ safety record;
k. Bidders’ history of compliance with applicable laws, codes, and regulations;
l. Quality and availability of Bidders’ personnel and resources; and
m. Amount and nature of Bidders’ current or pending litigation.
13. Bidders’ bonding capacity and rate will be evaluated by CM and Owner. The cost of
providing Bidders’ Performance and Payment Bonds may be added to Base Bid to assist
in evaluating the lowest responsible qualified proposal. Bidders will be required to use
the ConsensusDocs 706 and 707 for bonds, as provided in Section 006 of this CM
Manual.
14. CM may perform an investigation of Bidders’ financial condition. Bidders agree to assist
in any such investigation, which may include a request for Bidders’ most recent audited
or reviewed financial statements, a review of Bidders’ “Business Information Report” as
prepared by Dun & Bradstreet, Inc., or discussions with Bidders’ surety and banking
agents.
15. Bidders are required to provide a price for each specified Alternate, Unit Price, or Price
Breakout that affects Bidder’s Bid Package.
16. Bidders are required to provide unit prices for all labor classifications that apply to
Bidder’s Bid Package. Labor unit prices will be used to calculate labor for all change
order requests.
17. Construction Manager will use the Master Contract, which includes specific insurance
requirements, Amendment to Contract, and Project Contract. These documents are
bound in Section 006 of this Manual. In addition, contract documents will include the
following attachments.
a. Exhibit A – Bid Package Description
004.01 Form of Proposal
Page 1 of 4 Form of Proposal 004.01
Rev 2 – February 2017
Project SCHOOL OF THE OSAGE PHASE II HIGH SCHOOL ADDITIONS AND RENOVATIONS
Date of Bid ___________________________________________________________________ Submitted by (“Bidder”) _________________________________________________________
Company Representative _______________________________________________________
Company Representative Cell Phone ______________________________________________
Company Representative Email Address ___________________________________________
Address _____________________________________________________________________
Proposal to Nabholz Construction 1707 E 123rd Terrace Olathe, KS 66061 Fax 913.393.6500
Scope of Work Bid Package Number _______________ Bid Package Description ________________________________________________________
Addenda Bidder acknowledges receipt of the following addenda. Addendum # _____ dated _______________ Addendum # _____ dated _______________ Addendum # _____ dated _______________ Addendum # _____ dated _______________
004.01 Form of Proposal
Page 2 of 4 Form of Proposal 004.01
Rev 2 – February 2017
Base Bid
Bidder submitting this proposal agrees to furnish labor, materials, equipment, and supervision
required to complete the Scope of Work in accordance with all requirements of the
specifications, drawings, Construction Manager’s Manual, and all applicable governing codes
and regulations.
Bidder agrees to complete the Scope of Work for a lump sum of:
High School Additions and Renovations $__________________________________ ALTERNATES
______________________________________________ Add/Deduct $ _____________ ______________________________________________ Add/Deduct $ _____________
______________________________________________ Add/Deduct $ _____________
VOLUNTARY ALTERNATES
______________________________________________ Add/Deduct $ _____________ ______________________________________________ Add/Deduct $ _____________
______________________________________________ Add/Deduct $ _____________
UNIT PRICES _____________________________________________ _____________________________________________ _____________________________________________ HOURLY RATE FOR REGULAR LABOR HOURLY RATE FOR PREMIUM LABOR *INCLUDE ALL OVERHEAD, PROFIT AND BURDEN IN HOURLY RATES
004.01 Form of Proposal
Page 3 of 4 Form of Proposal 004.01
Rev 2 – February 2017
Bonding
Bidder can provide a Performance and Payment Bond and can meet the requirements set forth
in the Project Contract located in Section 006.02 Project Contract – Article V (circle one)
Yes / No
If the Bidder can provide a Bond, indicate the percentage rate for the bond cost. ____________
Name and phone number of Surety Agent.
Name __________________________________________________Phone________________
WORK IN PROGRESS & PROJECT SPECIFIC QUALIFICATIONS
Bidder shall submit with their proposal a Work in Progress (WIP) Report that lists the ten (10)
largest projects currently being constructed. Moreover, final evaluation of Bidder’s proposal
shall be conditional on review of WIP Report, and Bidder’s experience with similar scope and
projects.
COMPLETION TIME
All Work shall be completed within the schedules prepared by and agreed to by Nabholz.
Bidder shall provide adequate manpower and submit documentation for approval necessary to
work within the timeframe scheduled. Estimated time period for construction is January 2018 –
August 2018.
SIGNATURE
Bidder agrees that this proposal remains valid for a period of 60 days. Bidder understands that
Nabholz and the Owner reserve the right to reject any or all bids. Bidder acknowledges
Nabholz minimum insurance requirements and understands that the Master Contract shall be
the basis of any contract offered by Nabholz Construction to Bidder. Proposed modifications of
Master Contract language must be submitted with bid. Attach additional sheets if necessary.
Upon receipt of notice of acceptance of bid, Bidder agrees to execute and return the contract
and required insurance certificates within two weeks of notification.
004.01 Form of Proposal
Page 4 of 4 Form of Proposal 004.01
Rev 2 – February 2017
By _____________________________________________ Title ______________________
Printed name of individual signing this proposal ______________________________________
Contact phone number _________________________________________________________
Email Address ________________________________________________________________
Date _______________________________________________________________________
008.01 Project Schedule
1. Per the Sub-Contractor’s Master Contract with the Construction Manager - Article III, Item 3 (see section 006.01 of this manual), Construction Manager will develop the project schedule with the sub-contractor’s input. Sub-contractor has input in the schedule, but, shall plan accordingly as part of their bid to meet the established project milestones. All activities related to Bidder’s Scope of Work shall be completed within the schedules prepared by and agreed to by Construction Manager as outlined below. All Subcontractors and Suppliers shall procure materials and provide the manpower necessary to meet the Project Construction Schedule. Project milestones are as follows:
Task Name Duration Start Finish
Construction Phase 2 SOTO 215 days Mon 10/22/18
Fri 8/16/19
New Tech Shop, Locker Rooms, and Kitchen Infill 7A,B,C,D.
138 days Mon 10/22/18 Wed 5/1/19
Business Labs Renovations 11 A Room 109
22 days Mon 10/22/18 Tue 11/20/18
Business Labs Renovations 11 A Rooms 204/205 (DRAMA)
34 days Tue 11/20/18 Fri 1/4/19
Nurse Station Renovation 56 days Mon 10/22/18 Mon 1/7/19
Locker room renovations 11 D 90 days Mon 4/15/19 Fri 8/16/19
Auditorium Renovation 10 90 days Mon 4/15/19 Fri 8/16/19
8 Band Space Renovation 78 days Wed 5/1/19 Fri 8/16/19
Kitchen Renovation 62 days Thu 5/23/19 Fri 8/16/19
Choir Space Renovations 10 D 62 days Thu 5/23/19 Fri 8/16/19
Task Name Duration Start Finish
New Tech Shop, Locker Rooms, and Kitchen Infill 7A,B,C,D.
138 days Mon 10/22/18 Wed 5/1/19
Demo Concrete, No utilities 3 days Mon 10/22/18 Wed 10/24/18
Build pad 10 days Wed 10/24/18 Tue 11/6/18
Footers and grade beams 15 days Tue 11/6/18 Mon 11/26/18
Install New underground utilities 15 days Mon 11/26/18 Fri 12/14/18
tie in to existing (Christmas Break) 11 days Fri 12/21/18 Fri 1/4/19
Demo existing underground 8 days Wed 12/26/18 Fri 1/4/19
Pour Pad 5 days Mon 1/7/19 Fri 1/11/19
CMU Exterior 20 days Mon 1/14/19 Fri 2/8/19
Structural Steel 10 days Fri 2/8/19 Thu 2/21/19
Roof curbs / Penetrations 5 days Thu 2/21/19 Wed 2/27/19
Roofing 10 days Wed 2/27/19 Tue 3/12/19
Interior CMU 20 days Mon 2/11/19 Fri 3/8/19
MEP rough in 20 days Mon 2/11/19 Fri 3/8/19
Paint 15 days Mon 3/11/19 Fri 3/29/19
Interior finishes 15 days Mon 4/1/19 Fri 4/19/19
Final clean / Punch 9 days Fri 4/19/19 Wed 5/1/19
Task Name Duration Start Finish
Business Labs Renovations 11 A Room 109
22 days Mon 10/22/18 Tue 11/20/18
Demo 5 days Mon 10/22/18 Fri 10/26/18
Flooring patch / repair / match existing 5 days Mon 10/29/18 Fri 11/2/18
Re work / install new Electrical power and data 3 days Fri 11/2/18 Tue 11/6/18
Paint 2 days Wed 11/7/18 Thu 11/8/18
Interior Finishes 1 day Fri 11/9/18 Fri 11/9/18
Clean / Punch 7 days Mon 11/12/18 Tue 11/20/18
Task Name Duration Start Finish
Business Labs Renovations 11 A Rooms 204/205 (DRAMA)
34 days Tue 11/20/18 Fri 1/4/19
Demo CMU 1 day Tue 11/20/18 Tue 11/20/18
Demo Electrical 2 days Tue 11/20/18 Wed 11/21/18
New CMU Lintel 3 days Wed 11/21/18 Fri 11/23/18
Plumbing install 20 days Mon 11/26/18 Fri 12/21/18
Patch / Repair floor / Match existing 20 days Mon 11/26/18 Fri 12/21/18
Install new door frame 1 day Wed 12/26/18 Wed 12/26/18
Paint 2 days Thu 12/27/18 Fri 12/28/18
Clean / Punch 3 days Wed 1/2/19 Fri 1/4/19
Task Name Duration Start Finish
Nurse Station Renovation 56 days Mon 10/22/18 Mon 1/7/19
Demo 2 days Mon 10/22/18 Tue 10/23/18
Move Electrical Panel / HVAC Controls 2 days Mon 10/22/18 Tue 10/23/18
Locate and demo CMU opening / install Lintel 3 days Wed 10/24/18 Fri 10/26/18
Metal stud framing 2 days Thu 10/25/18 Fri 10/26/18
Plumbing rough 10 days Mon 10/29/18 Fri 11/9/18
Floor patch / repair 2 days Mon 11/12/18 Tue 11/13/18
Mechanical Rough in 2 days Tue 11/13/18 Wed 11/14/18
Interior Finishes 23 days Wed 11/14/18 Fri 12/14/18
Paint 2 days Mon 12/17/18 Tue 12/18/18
Clean / Punch 13 days Wed 12/19/18 Fri 1/4/19
Task Name Duration Start Finish
Locker room renovations 11 D 90 days Mon 4/15/19 Fri 8/16/19
Demo Doors and Specialties 3 days Mon 4/15/19 Wed 4/17/19
CMU demo 5 days Thu 4/18/19 Wed 4/24/19
MEP demo 10 days Thu 4/25/19 Wed 5/8/19
Build CMU walls and Lintels 15 days Thu 5/9/19 Wed 5/29/19
Plumbing rough in 10 days Thu 5/30/19 Wed 6/12/19
Floor patch / repair / match existing 5 days Thu 6/13/19 Wed 6/19/19
Mechanical Install 20 days Thu 6/20/19 Wed 7/17/19
Electrical Power / Data install 20 days Thu 6/20/19 Wed 7/17/19
Lighting install 10 days Wed 7/17/19 Tue 7/30/19
Paint 5 days Tue 7/30/19 Mon 8/5/19
Final Clean / Punch 9 days Tue 8/6/19 Fri 8/16/19
Task Name Duration Start Finish
Auditorium Renovation 10 90 days Mon 4/15/19 Fri 8/16/19
Electrical Demo 10 days Mon 4/15/19 Fri 4/26/19
Stage walls / Control booth ceiling demo 3 days Mon 4/15/19 Wed 4/17/19
Auditorium carpet/seating demo/floor patch-repair 3 days Mon 4/15/19 Wed 4/17/19
Auditorium wall framing / tape / finish 15 days Thu 4/18/19 Wed 5/8/19
New electrical install 15 days Thu 4/25/19 Wed 5/15/19
Auditorium paint 2 days Wed 5/8/19 Thu 5/9/19
Veneer plywood panels (Auditorium) 20 days Fri 5/10/19 Thu 6/6/19
CMU demo Control Booth/cut in new door openings
7 days Thu 5/23/19 Fri 5/31/19
CMU walls / Lintel install 5 days Thu 5/30/19 Wed 6/5/19
Demo existing soffit 2 days Fri 5/24/19 Mon 5/27/19
Frame new Auditorium entrance / Control booth 5 days Thu 6/6/19 Wed 6/12/19
Electrical / Data in Control Booth / Entrance 5 days Wed 6/12/19 Tue 6/18/19
Drywall hang, tape, finish Control Boot /Entrance 10 days Mon 6/18/18 Fri 6/29/18
Paint 5 days Mon 7/1/19 Fri 7/5/19
Flooring in all area 10 5 days Mon 7/8/19 Fri 7/12/19
Veneer plywood panels (Auditorium entrance) 10 days Mon 7/8/19 Fri 7/19/19
Clean / Punch 10 days Mon 7/22/19 Fri 8/2/19
Task Name Duration Start Finish
8 Band Space Renovation 78 days Wed 5/1/19 Fri 8/16/19
Demo CMU / cut new CMU openings 10 days Wed 5/1/19 Tue 5/14/19
Lintels and CMU infills / walls 10 days Tue 5/14/19 Mon 5/27/19
MEP demo 15 days Mon 5/6/19 Fri 5/24/19
Structural Steel framing / reinforcement for 3 RTU's 3 days Mon 5/13/19 Wed 5/15/19
Roof curbs/ roof patch 3 days Thu 5/16/19 Mon 5/20/19
Plumbing rough in 5 days Mon 5/20/19 Fri 5/24/19
Metal stud framing 5 days Mon 5/27/19 Fri 5/31/19
Electrical rough 20 days Mon 6/3/19 Fri 6/28/19
Mechanical rough 20 days Mon 6/3/19 Fri 6/28/19
Drywall tape /hang/finish 15 days Wed 6/26/19 Tue 7/16/19
Interior finishes 20 days Wed 7/10/19 Tue 8/6/19
MEP detailing 5 days Thu 8/1/19 Wed 8/7/19
Ceiling grid 5 days Mon 7/15/19 Fri 7/19/19
Lighting install 10 days Tue 7/16/19 Mon 7/29/19
Flooring 10 days Tue 7/23/19 Mon 8/5/19
Ceiling tile / sound diffusers 5 days Mon 8/5/19 Fri 8/9/19
Clean / Punch 7 days Thu 8/8/19 Fri 8/16/19
Task Name Duration Start Finish
Kitchen Renovation 62 days Thu 5/23/19 Fri 8/16/19
Demo flooring, walls, ceiling, cooler, freezer 10 days Thu 5/23/19 Wed 6/5/19
MEP demo 10 days Thu 5/23/19 Wed 6/5/19
Demo existing slab for added column pads, pour. 4 days Tue 6/4/19 Fri 6/7/19
Plumbing rough in 10 days Tue 6/4/19 Mon 6/17/19
CMU wall erection 12 days Wed 6/5/19 Thu 6/20/19
Electrical Rough in 12 days Thu 6/6/19 Fri 6/21/19
Erect added structural steel 2 days Mon 6/17/19 Tue 6/18/19
Metal stud framing /hang tape finish 7 days Tue 6/18/19 Wed 6/26/19
Concrete floor patch/repair/match existing 5 days Tue 6/18/19 Mon 6/24/19
Mechanical rough in / ANSUL System 10 days Sat 6/22/19 Thu 7/4/19
Interior finishes and specialties 10 days Tue 6/25/19 Mon 7/8/19
Ceiling grid 5 days Wed 7/10/19 Tue 7/16/19
Flooring 10 days Mon 7/8/19 Fri 7/19/19
Kitchen Equipment install / hook up 10 days Mon 7/22/19 Fri 8/2/19
Clean / Punch 11 days Fri 8/2/19 Fri 8/16/19
Task Name Duration Start Finish
Choir Space Renovations 10 D 62 days Thu 5/23/19 Fri 8/16/19
Demo existing flooring, ceiling and selected walls 10 days Thu 5/23/19 Wed 6/5/19
CMU demo / cut in new openings/ install Lintels 5 days Thu 5/23/19 Wed 5/29/19
MEP demo 10 days Thu 5/23/19 Wed 6/5/19
Plumbing rough in 5 days Sat 5/25/19 Thu 5/30/19
Floor patch /repair/match existing 3 days Thu 5/30/19 Mon 6/3/19
Metal stud framing /hang tape finish / build risers 15 days Thu 5/30/19 Wed 6/19/19
Electrical install 5 days Mon 6/3/19 Fri 6/7/19
Interior finishes and specialties 15 days Fri 6/7/19 Thu 6/27/19
Ceiling grid 3 days Thu 6/27/19 Mon 7/1/19
Lighting 5 days Mon 7/1/19 Fri 7/5/19
Flooring 7 days Mon 7/8/19 Tue 7/16/19
Ceiling tile and sound diffusers 3 days Wed 7/17/19 Fri 7/19/19
Clean / Punch 7 days Mon 7/22/19 Tue 7/30/19
009.02 Bid Package Index
009.00.01 Final Cleaning
009.02.01 Demolition
009.03.01 Concrete
009.04.01 Masonry (Supply and Install)
009.05.01 Structural and Miscellaneous Steel (Supply and Install)
009.06.03 Millwork and Cabinetry (Supply and Install)
009.07.01 Waterproofing, Dampproofing, Joint Sealants
009.07.03 Wall Panels
009.07.04 Roofing, Flashing, Sheet Metal
009.08.01 Doors, Frames, Hardware (Supply and Install)
009.08.03 Storefront, Glass, Glazing
009.09.01 Framing, Drywall, Acoustical Ceilings
009.09.03 Tile and Commercial Flooring
009.09.05 Painting and Wall Covering
009.10.01 Building Specialties (Supply and Install)
009.10.02 Visual Display Surfaces (Supply and Install)
009.10.03 Signage (Supply and Install)
009.10.08 Lockers (Supply and Install)
009.11.01 Food Service Equipment (Supply and Install)
009.12.02 Audience Seating
009.21.01 Fire Suppression (Supply and Install) 009.22.01 Plumbing
009.23.01 Heating, Ventilation, Air Conditioning (HVAC) 009.26.02 Electrical 009.28.02 Electronic Safety and Security 009.31.01 Earthwork, Storm Drainage, and Site Utilities 009.32.06 Site Concrete
Rev 1__September 2018 Bid Package Index 009.02.00
009.02.01 Demolition Exhibit A
As noted below, Subcontractor shall be responsible for the following project-related activities and
Scope of Work in accordance with the requirements of the specifications, drawings, and CM Manual.
Furnish all labor and supervision required to complete the work of this package. Unless noted otherwise,
furnish all equipment, materials, supplies, tools, scaffolding, hoisting, transportation, unloading, and
handling necessary for the proper installation and completion of this work.
APPLICABLE SPECIFICATIONS Include work normally associated with trade whether referenced in these sections or not:
• DIVISION 0
• DIVISION 1
• SECTION 024113 - SITE DEMOLITION
• SECTION 024119 - SELECTIVE DEMOLITION
SCOPE OF WORK Includes, but is not necessarily limited to:
Section A: Reference Section 009.01 General Scope Requirements
Section B: Trade-Specific Requirements
1. Subcontractor must comply with all environmental laws during demolition.
2. Subcontractor must provide containers and transportation for all demo debris removal for all
demolition.
3. Include all road clean-up required by demolition activities.
4. Provide all barricades, traffic control, and flagmen required by demolition activities.
5. All asbestos materials will be abated and removed by Owner outside of this contract.
6. All materials removed under this scope of work will be disposed of on a daily basis. Any materials
to be salvaged shall be turned over the Owner, delivered to a location on site as designated by
Owner. Reasonable care shall be exercised in removing any and all items to be retained.
7. Protect adjacent materials, finishes and structures. Damage of such will be repaired at the
expense of the demolition contractor.
8. Ensure utilities are disconnected prior to the commencement of demolition activities.
9. Coordinate demolition sequence with project superintendent.
10. Include all necessary temporary waterproofing for exterior walls and roof to prevent entry of water
into existing building. Temporary shelters and partitions must be maintained under this Bid
Package until new construction allows for removal, or as dictated by Construction Manager.
11. Include all means and measures to protect existing finishes, materials, and equipment from
damage and dust due to demolition activities.
12. Remove building foundations below grade as required by contract documents. Backfill and
compact to bring up to the elevation of the surrounding grade.
13. Include all temporary shoring and bracing of any structures or devices which are affected by
demolition activities.
14. Demolition must be performed in strict coordination with Mechanical and Electrical trades, and in
strict accordance with Owner to minimize disturbances or interruptions to operations. Note that
demolition of electrical, plumbing, mechanical, fire sprinkler systems, is not included in this bid
package, and is included with those trades in their respective Bid Packages.
15. Leave job site “shovel clean” in areas of building demolition.
16. Leave jobsite “broom clean” in areas of interior demolition.
Rev 1__September 2018 Bid Package: Demolition 009.02.01
009.02.01 Demolition Exhibit A
Section C: Project-Specific Requirements
C-1: High School Additions and Renovations
• Compliance with governmental regulations regarding demolition of walls containing
leadbased paint shall be included in the scope of work and responsibility of this bidder.
• Maintain all SWPPP during construction.
• Notify Nabholz immediately of any damage to existing utilities, building or irrigation.
• Demo contractor to provide floor protection, install and remove.
• Provide dust protection/control required for completion of scope.
• Leave behind any brick as a result of demolition.
• Exclude demo of shop dust collector. Removal by owner.
Section B: Project-Specific Exclusions
1. None
Section E: Alternate Pricing
1. Provide alternate price on Lump Sum Proposal form for XXX.
Section F: Unit Pricing
1. Not applicable
END OF PACKAGE
009.03.01 Concrete Exhibit A
As noted below, Subcontractor shall be responsible for the following project-related activities and
Scope of Work in accordance with the requirements of the specifications, drawings, and CM Manual.
Furnish all labor and supervision required to complete the work of this package. Unless noted otherwise,
furnish all equipment, materials, supplies, tools, scaffolding, hoisting, transportation, unloading, and
handling necessary for the proper installation and completion of this work.
APPLICABLE SPECIFICATIONS Include work normally associated with trade whether referenced in these sections or not:
• Division 0
• Division 1
• SECTION 033000 - CAST-IN-PLACE CONCRETE
• SECTION 072100 - THERMAL INSULATION
• SECTION 313116 – TERMITE CONTROL
• SECTION 321373 – CONCRETE PAVING JOINT SEALANTS
SCOPE OF WORK Includes, but is not necessarily limited to:
Section A: Reference Section 009.01 General Scope Requirements
Section B: Trade-Specific Requirements
1. Prepare and construct all building concrete assemblies, including but not limited to drilled piers,
wall and column foundations, pile caps, footings and mats, grade beams, slabs on grade, ramps,
trenches, pits, equipment pads, below-grade walls, structural slabs, columns, beams, and slabs
on deck as indicated in the construction documents.
2. Prepare and construct all site concrete assemblies, including but not limited to concrete paving,
drainage swales, curbs and gutters, curb inlet caps, pedestrian paving, steps, ramps, stoops,
mow strips, equipment and transformer pads, light pole bases, light bollard bases, flag bases, site
foundations and slabs as indicated in the construction documents.
3. Furnish and install all expansion and construction joints including keyways, dowels and saw
cutting as required.
4. Include all associated excavation, backfill, and compaction (both interior and exterior perimeters).
Move spoils off-site or to area designated by Contraction Manager.
5. Backfill compaction must meet requirements of specifications.
6. Include formwork, bedding and leveling materials, reinforcing steel and mesh, tie wire, bolsters
and supports, void forms, board insulation, concrete ready-mix, methods of conveyance (i.e.
pumps, buggies), admixtures, curing and hardening compounds, concrete accessories, joints and
weeps, sleeves, drain boxes and covers, filter fabrics and moisture membranes, finishing, and
rubbing.
7. Install all embedded items (including bollards, sleeves, bolts) furnished by others.
8. Furnish, install, and compact gravel base at concrete flatwork where required.
9. Provide and install truncated warning devices if required.
10. Provide integrally colored concrete if required by construction documents.
11. Provide termite treatment in accordance with specifications.
12. Grout all base plates as required.
13. Install and maintain a designated concrete wash down area.
14. Provide all cold weather and/or hot weather protection as required to maintain Project Schedule
in accordance with ACI standards.
15. Provide generator power if electric is not readily available.
Rev 1__September 2018 Bid Package: Concrete 009.03.01
009.03.01 Concrete Exhibit A
16. Unless more stringent requirements are specified, maintain maximum flatness tolerance of 1/8
inch in 10 feet for all floor slabs.
17. Final surfaces shall be as specified and free from cracks, voids, and spalls. Positive drainage of
water shall be provided on traffic surfaces, without ponds or water stands. Should final surfaces
contain any of the above mentioned, items shall be repaired at no additional cost to the Owner.
18. Replace grades to original condition in affected areas adjacent to work performed.
19. Concrete curing shall be in accordance with the construction documents and ACI.
20. Include temporary shoring of metal deck as required to support concrete materials.
21. Include foundation layout with base line established by professional surveyor. Check and
maintain survey control points and layout anchor bolts.
22. Coordinate with plumbing and electrical trades regarding work that is under or in concrete.
23. Coordinate city inspections.
24. Provide ACI certified personnel to take concrete cylinders as required.
Section C: Project-Specific Requirements
C-1: High School Additions and Renovations
• Include GEO foam if required.
• Include all reinforced concrete footings and grade beams, for building foundations, including
those for Exterior Canopy structure.
• Include all reinforced concrete foundation walls / stem walls.
• Include gravel base (leveling course and capillary break) for floor slab per Section 033000
• Exclude: joint sealants (by waterproofing contractor)
• Include moisture vapor reduction admixture per specifications.
• Include all grouting required for structural steel / baseplates.
• Sealed concrete if required, is by the painting contractor.
• Coordinate with Polished Concrete Subcontractor, and all others required prior to submittals and
installation.
• Include Termite Treatment.
• Include any backfill along foundation walls and footings.
• Include setting and supplying of all masonry dowels set in footings. Coordinate with mason for
layout.
Section D: Project Specific Exclusions
1. None
Section E: Alternate Pricing
1. Provide alternate price on Lump Sum Proposal for cold weather provisions, including temporary
heat, enclosures, blankets, tenting, and other means necessary to maintain schedule in cold
weather.
Section F: Unit Pricing
1. Not applicable
009.04.01 Masonry (Supply and Install) Exhibit A
As noted below, Subcontractor shall be responsible for the following project-related activities and
Scope of Work in accordance with the requirements of the specifications, drawings, and CM Manual.
Furnish all labor and supervision required to complete the work of this package. Unless noted otherwise,
furnish all equipment, materials, supplies, tools, scaffolding, hoisting, transportation, unloading, and
handling necessary for the proper installation and completion of this work.
APPLICABLE SPECIFICATIONS Include work normally associated with trade whether referenced in these sections or not:
• Division 0
• Division 1
• SECTION 042000 - UNIT MASONRY
• SECTION 072100 - THERMAL INSULATION
SCOPE OF WORK Includes, but is not necessarily limited to:
Section A: Reference Section 009.01 General Scope Requirements
Section B: Trade-Specific Requirements
1. Provide and construct all masonry assemblies as indicated and specified in the construction
documents.
2. Provide standard and special shaped masonry units, mortar, grout, knock-out panels, reinforcing
steel, precast, masonry joint reinforcing, anchors, ties, embedded flashing, and other masonry
accessories as may be required to complete the masonry assemblies as detailed and specified.
3. Provide block outs and framed openings in masonry as required by work of other trades.
4. Install steel lintels and embed plates furnished by others.
5. Provide all anchor and attachment to structural members as required per the contract documents.
6. Set hollow metal frames furnished by others. Including grouting of frames as required.
7. Furnish and install cavity wall insulation when shown in contract documents.
8. Perform all work from approved shop drawings and/or product data. Confirm that you have the
latest approved “field use” drawings prior to start of work.
9. Coordinate location and placement of steel embeds with structural steel erection subcontractor.
10. Provide a sample mock-up panel as soon as possible, in a location as directed by the Project
Superintendent. The panel will clearly show all CMU, grout, reinforcing, anchoring, seismic (if
required) ties, flashing, brick and mortar (per required color selection(s), and other materials as
required for a complete review and approval of the quality of finished product.
11. Provide all layout and field measurements for this work including layout for embedded items.
12. Layout, drill, and epoxy reinforcing at masonry walls when shown on the contract documents.
13. Cover and protect all slab areas that will receive special finishes as directed by Construction
Manager.
14. Provide shoring and bracing of walls, masonry lintels, and bond beams to facilitate this work.
15. Provide all cold-weather and hot-weather protection per construction documents necessary to
maintain Project Schedule.
16. Coordinate all lay down and staging areas with Project Superintendent at least 48 hours in
advance of all material deliveries.
17. Prepare and clean footings (as required) prior to starting masonry work.
18. Repair divots bigger than 1/2” in diameter and patch block as directed by Construction Manager.
19. Include rubbing of exposed unit masonry and final cleaning.
20. Include flue liners, ash dumps and fireplace units if required.
21. Include all rigid insulation behind masonry as required.
Rev 1__September 2018 Bid Package: Masonry 009.04.01
009.04.01 Masonry Exhibit A
22. Include all drilling and epoxy of all dowels required for masonry.
23. Coordinate with other trades as required for block outs, cutouts, and the installation of access
doors and plumbing fixture chairs.
24. Include protection of masonry cells and cavity between masonry walls from infiltration of moisture
at the end of each work day. Protect space between masonry and sheathing.
25. Install weather barrier flashing provided by others at each masonry tie or penetration.
Section C: Project-Specific Requirements
C-1: High School Additions and Renovations
• Provide all integral water repellants for masonry as required.
• Include patching and toothing of brick and block as required at the existing building after
demolition. Use existing brick left over from demolition for this work.
• Include expansion joints in masonry assemblies.
• Include masonry washing / cleaning and protect adjacent finished products.
• Grout all masonry set doorframes as required.
• Provide all through wall flashing as required.
• Re-Use existing brick to tooth back in new openings.
• Install all lintels and embeds (provided by steel subcontractor).
• Install new lintels in all renovated masonry openings including the opening in the nurse room 11B.
Lintels to be supplied by steel contractor.
Section D: Project-Specific Exclusions
1. None
Section E: Alternate Pricing
1. Provide alternate price on Lump Sum Proposal for cold weather provisions, including temporary
heat, enclosures, blankets, tenting, and other means necessary to maintain schedule in cold
weather.
2. Provide alternate price on Lump Sum Proposal form for XXX.
Section F: Unit Pricing
1. Not applicable
END OF PACKAGE
009.05.01 Structural and Miscellaneous Steel (Supply and Install) Exhibit A
As noted below, Supplier shall be responsible for the following project-related activities and Scope of
Work in accordance with the requirements of the specifications, drawings, and CM Manual. Unless noted
otherwise, furnish all equipment, materials, supplies, and transportation necessary for the proper
installation and completion of this work.
APPLICABLE SPECIFICATIONS Include work normally associated with trade whether referenced in these sections or not:
• Division 0
• Division 1
• SECTION 051200 - STRUCTURAL STEEL FRAMING
• SECTION 052100 - STEEL JOIST FRAMING
• SECTION 053100 - STEEL DECKING
• SECTION 054000 - COLD-FORMED METAL FRAMING
• SECTION 055000 - METAL FABRICATIONS
• SECTION 055213 - PIPE AND TUBE RAILINGS
SCOPE OF WORK Includes, but is not necessarily limited to:
Section A: Reference Section 009.01 General Scope Requirements
Section B: Trade-Specific Requirements
1. Fabricate and deliver all structural steel columns, beams, tube framing, brace frames, gusset
plates, bridging, joists, decking, edge and other angles, bent plates, connectors, studs, and
fasteners as indicated in the construction documents.
2. Furnish miscellaneous framing/support for mechanical, plumbing, and electrical equipment.
3. Fabricate and deliver all rough hardware, bearing and leveling plates, miscellaneous steel trim,
shelf and relief angle, tread plate and supports, railings and handrails and metal pan stairs.
4. Fabricate and supply anchor bolts, loose lintels, wheel guards, railings, and pipe bollards as
indicated in the construction documents.
5. Provide all sleeve anchors and any anchors that connect steel to other materials.
6. All steel work shall be fabricated from approved shop drawings. Confirm that you have the latest
approved “field use” drawings prior to start of work.
7. All steel exposed to view shall be oil free, have welds ground smooth, and be of sufficient quality
for an exposed and finished surface.
8. Include prime painting (galvanized where required by the bid documents) and touch-up (where
required) as indicated in the construction documents.
9. Include all freight to jobsite. Coordinate all lay down and staging areas with Project
Superintendent at least 48 hours in advance of all material deliveries. Coordinate delivery
schedule with steel erection subcontractor for offloading.
10. Provide copies of current welder’s certifications prior to the start of any work. Keep those records
on file at the job trailer and keep them current at all times.
11. Fabricate and deliver metal deck closures.
12. Fabricate and deliver elevator pit ladder, hoist beam, and sump pit grate.
Rev 1__September 2018 Structural and Miscellaneous Steel (Supply and Install) 009.05.01
009.05.01 Structural and Miscellaneous Steel (Supply and Install) Exhibit A
Section C: Project-Specific Requirements
C-1: High School Additions and Renovations
• Include all delegated design requirements, including but not limited to: pipe and tube railings, KSP
joists, connection design calcs.
• Include seismic requirements.
• Include metal railings, bollards, stair nosing’s, column covers, mechanical roof screen and
masonry lintels and embeds, etc. for all new and renovated areas. Be sure to include a lintel for
Nurse 11B opening.
• Supply all misc. fasteners required for complete installation.
• Include roof curbs required for roof top equipment screen walls.
• Include roof accessories- ladders. Roof hatch will be provided and installed by roofing contractor.
• Provide flute insulation for roof decking if indicated in CD’s. Install by roofing contractor.
• Provide and install all metal stairs and roof ladders.
D: Project-Specific Exclusions
1. EXCLUDE applicable Sales & Use Tax from bid. Taxes will be applied to invoices.
Section E: Alternate Pricing
Section F: Unit Pricing
1. Not applicable
END OF PACKAGE
009.07.04 Roofing, Flashing, Sheet Metal Exhibit A
As noted below, Subcontractor shall be responsible for the following project-related activities and
Scope of Work in accordance with the requirements of the specifications, drawings, and CM Manual.
Furnish all labor and supervision required to complete the work of this package. Unless noted otherwise,
furnish all equipment, materials, supplies, tools, scaffolding, hoisting, transportation, unloading, and
handling necessary for the proper installation and completion of this work.
APPLICABLE SPECIFICATIONS Include work normally associated with trade whether referenced in these sections or not:
• Division 0
• Division 1
• SECTION 076200 – SHEET METAL FLASHING AND TRIM
• SECTION 075423 – THERMOPLASTIC POLYOLEFIN (TPO) ROOFING
• SECTION 077200 – ROOF ACCESSORIES
• SECTION 072100 – THERMAL INSULATION
SCOPE OF WORK Includes, but is not necessarily limited to:
Section A: Reference Section 009.01 General Scope Requirements
Section B: Trade-Specific Requirements
1. Provide a complete watertight roof system with related tapered insulation, flashing and counter
flashing, coping, scuppers, expansion joints, ballast, gutters and downspouts, and caulking.
2. Provide a complete insulation system to provide positive drainage to roof drain, and to prevent
ponding of water on roof surface. Provide tapered crickets at rooftop units, equipment, and roof
perimeter.
3. Provide roof system that meets minimum insulation value as specified. Clearly confirm the
minimum “R” value rating on shop drawings.
4. Review, approve, and accept all subsurfaces prior to installation.
5. Comply with all wind uplift requirements of Owner and Owner agents.
6. Provide roof expansion joints and covers.
7. Provide all miscellaneous roof accessories.
8. Confirm that materials furnished for this Bid Package are compatible with other materials
furnished for other Bid Packages.
9. Coordinate all metal flashing and trim so that metal products match in color to the metal roof
copings, flashing and trim.
10. All work shall, as a minimum, comply with industry accepted “best practices” and with the
SMACNA “Architectural Sheet Metal Manual” criteria.
11. Provide pitch pockets and flashing for miscellaneous penetrations of the roof.
12. Install roof drains provided by plumbing subcontractor and set clamping rings. Coordinate with
plumbing subcontractor for the proper installation of this work.
13. Provide walk-pads at the HVAC equipment as required to properly access all rooftop equipment.
14. Provide hoisting for materials provided in this Bid Package.
15. Coordinate all deliveries of material with Project Superintendent. Secure, store, and protect all
materials from weather.
16. Cover all insulation installed each day. Do not shake out or leave unprotected any insulation
which may become wet with dew or rainfall.
17. Provide manpower or safety barriers below all roof penetrations for protection of others during
kettle discharge operation. Provide daily reports showing kettle discharge temperatures.
Rev 1__September 2018 Bid Package: Roofing, Flashing, Sheet Metal 009.07.04
009.07.04 Roofing, Flashing, Sheet Metal Exhibit A
18. Immediately clean all areas or surfaces soiled by roofing operations.
19. Should the roofing product manufacturer require standard details that conflict with the contract
documents, drawings, details, or notes, Subcontractor must immediately notify Construction
Manager in writing with a proposed method of resolution.
20. Coordinate with the HVAC and plumbing subcontractors to ensure that proposed locations of
plumbing vents and rooftop equipment do not conflict with roofing manufacturer warranty
requirements.
21. All warranties must be signed by the roofing manufacturer’s representative.
22. Prior to demobilization, Subcontractor agrees to coordinate with Project Superintendent for the
purpose of conducting a waterproof test.
Section C: Project-Specific Requirements
C-1: High School Additions and Renovations
• All metal work, flashing, coping, scuppers, gutters, downspouts and trim shall be pre-finished as
indicated in the specifications and included in this scope as/ if indicated in the construction
documents (wall panels, soffits and associated trim by others).
• Include roof demolition as shown in the construction documents.
• Provide and install roof hatch.
• Include roof expansion joints, flashing, sheet metal, gutters, downspouts.
• Tie-in at existing roof per construction documents. Maintain existing roof warranty.
• Include all flashing and finishing around roof curbs, installed by others.
• Install roof drains supplied by plumbing contractor.
• Install flute insulation at roof deck, supplied by structural steel contractor.
• Include final, above ground, downspout connections to storm water piping.
• Remove existing downspouts as shown as key note 3 on sheet C101. Install temporary collection
and discharge system.
Section D: Project-Specific Exclusions
1. None
Section E: Alternate Pricing
Section F: Unit Pricing
1. Not applicable
END OF PACKAGE
009.09.03 Tile and Commercial Flooring Exhibit A
As noted below, Subcontractor shall be responsible for the following project-related activities and
Scope of Work in accordance with the requirements of the specifications, drawings, and CM Manual.
Furnish all labor and supervision required to complete the work of this package. Unless noted otherwise,
furnish all equipment, materials, supplies, tools, scaffolding, hoisting, transportation, unloading, and
handling necessary for the proper installation and completion of this work.
APPLICABLE SPECIFICATIONS Include work normally associated with trade whether referenced in these sections or not:
• Division 0
• Division 1
• SECTION 093013 – CERAMIC TILING
• SECTION 096513 – RESILIENT BASE AND ACCESSORIES
• SECTION 096519 – RESILIENT TILE FLOORING
• SECTION 096813 – TILE CARPETING
• SECTION – SEAMLESS RESINOUS FLOORING SYSTEM
SCOPE OF WORK Includes, but is not necessarily limited to:
Section A: Reference Section 009.01 General Scope Requirements
Section B: Trade-Specific Requirements
1. Furnish and install all resilient flooring and resilient base including treads and risers, transition
strips, and stair nosings.
2. Furnish and install all carpet and padding.
3. Furnish and install porcelain, ceramic, quarry, stone and marble tile.
4. Provide all surface preparation, leveling, bonding agents and adhesive, carpet tack strips,
patterns, transition strips, and other accessories required.
5. Provide “extra stock” materials as identified in the construction documents.
6. Inspect substrates prior to installation. The start of installation of floor covering will be construed
as the applicators acceptance of the finish floor surface conditions.
7. Provide and install all floor-to-floor expansion joint covers as required.
8. Provide initial cleaning of resilient materials, carpet, and tile upon completion of installation in strict
accordance with the manufacturer’s recommendations.
9. Provide and install pre-formed cove base outside corners.
10. Protect flooring against mars, marks, indentations, and other damage from construction. Use
protection methods indicated or recommended by tile manufacturer.
11. Remove visible adhesive, seam sealer, and other surface blemishes using cleaner recommended
by carpet manufacturer. Remove protruding yarns from carpet surface.
12. Include waterproofing at showers or shower pans.
13. Furnish and install thin brick pavers.
14. Surface preparation, provide and install up to 1 lb. of floorstone per 30SF of flooring. Floorstone
not used in one area may be added to another area. Prime surfaces per mfg.’s directions if
required.
15. Perform moisture test and give results to construction manager prior to commencement of work.
16. Furnish and install elevator cab flooring.
Rev 1__September 2018 Bid Package: Tile and Commercial Flooring 009.09.03
009.09.03 Tile and Commercial Flooring Exhibit A
Section C: Project-Specific Requirements
C-1: High School Additions and Renovations
• Provide moisture testing as required prior to installation of all flooring.
• If required, provide Topical Concrete Vapor Sealer at Slab on Grade Installation locations of
Carpet Tile, as recommended by Carpet Tile Manufacturer.
• Provide Manufacturer Special (10) ten year Warranty for Carpet Tile per specifications.
• Furnish and Install Walk-Off Mat Carpet.
• Level floors before flooring installation.
Section D: Project-Specific Exclusions
1. None
Section E: Alternate Pricing
1. Provide alternate price on Lump Sum Proposal form for XXX.
Section F: Unit Pricing
1. Not applicable
END OF PACKAGE
009.10.01 Building Specialties (Supply and Install) Exhibit A
As noted below, Subcontractor shall be responsible for the following project-related activities and
Scope of Work in accordance with the requirements of the specifications, drawings, and CM Manual.
Furnish all labor and supervision required to complete the work of this package. Unless noted otherwise,
furnish all equipment, materials, supplies, tools, scaffolding, hoisting, transportation, unloading, and
handling necessary for the proper installation and completion of this work.
APPLICABLE SPECIFICATIONS Include work normally associated with trade whether referenced in these sections or not:
• Division 0
• Division 1
• SECTION 102113.19 - PLASTIC TOILET COMPARTMENTS
• SECTION 102800 – TOILET, BATH AND LAUNDRY ACCESSORIES
• SECTION 104413 – FIRE PROTECTION CABINETS
• SECTION 104416 – FIRE EXTINGUISHERS
• SECTION 109900 -- MISCELLANEOUS SPECIALTIES
SCOPE OF WORK Includes, but is not necessarily limited to:
Section A: Reference Section 009.01 General Scope Requirements
Section B: Trade-Specific Requirements
1. THIS IS AN ALL-INCLUSIVE BID PACKAGE. Contractor agrees to install ALL items covered by
the Sections referenced above and describe herein.
2. Coordinate material delivery at the time of installation. Provide adequate labor and equipment to
off load.
3. Provide all labor, equipment, incidental materials, supervision, and insurance to install the work.
4. Unless noted otherwise, all items for each section should be installed level, plumb, and true.
5. Subcontractor takes responsible for all materials in this bid package when delivered for
installation.
6. Install items in locations and at mounting heights indicated on construction documents.
Section C: Project-Specific Requirements
C-1: High School Additions and Renovations
• Install all curtain tracks, curtain carriers, cubicle curtains, toilet compartments, urinal screens,
shower dividers, grab bars, sanitary-napkin vendor, sanitary-napkin disposal unit, mirror unit,
fold down purse shelf, shower curtain rod, shower curtain, folding shower seat, surface soap
dish, towel pin, utility shelf, and mop and broom holders.
• Coordinate layout and installation of projection screens with adjacent construction, including
ceiling suspension systems, light fixtures, HVAC equipment, fire-suppression system, and
partitions.
• Install fire extinguishers and cabinets. Coordinate type and capacity of fire extinguishers with
fire protection cabinets to ensure fit and function.
• Install all toilet accessories
Rev 1__September 2018 Bid Package: Building Specialties (Installation) 009.10.01
009.10.01 Building Specialties (Supply and Install) Exhibit A
• Install fire extinguishers and cabinets. Coordinate type and capacity of fire extinguishers with
fire protection cabinets to ensure fit and function.
• If metal lockers require wood bases, materials, fasteners and installation shall be part of this
scope of work.
• Provide all misc. fasteners required to complete installation.
Section D: Project-Specific Exclusions
1. None
Section E: Alternate Pricing
Section F: Unit Pricing
1. Not applicable
END OF PACKAGE
Rev 1__September 2018 Bid Package: Building Specialties (Installation) 009.10.01
009.10.08 Lockers (Supply and Install) Exhibit A
As noted below, Supplier shall be responsible for the following project-related activities and Scope of Work in
accordance with the requirements of the specifications, drawings, and CM Manual. Unless noted otherwise, furnish all
equipment, materials, supplies, and transportation necessary for the proper installation and completion of this work.
APPLICABLE SPECIFICATIONS Include work normally associated with trade whether referenced in these sections or not:
• Division 0
• Division 1
• SECTION 105113 – METAL LOCKERS
• SECTION 105213 – METAL GRID ATHLETIC LOCKERS
• SECTION 116001 – MUSIC INSTRUMENT STORAGE LOCKERS
SCOPE OF WORK Includes, but is not necessarily limited to:
Section A: Reference Section 009.01 General Scope Requirements
Section B: Trade-Specific Requirements
1. Supply and deliver lockers as indicated and specified in the construction documents.
2. All accessories shall meet the performance specifications in the construction documents.
3. All warranties shall commence on the date of Substantial Completion of the Project.
Section C: Project-Specific Requirements
1. Supply and Install all lockers as shown.
2. Proved adequate labor and/or equipment to offload lockers.
Section D: Project-Specific Exclusions
1. None
Section E: Alternate Pricing
Section F: Unit Pricing
1. Not applicable
END OF PACKAGE
Rev 1__September 2018 Bid Package: Lockers (Supply and Install) 009.10.08
009.12.02 Audience Seating Exhibit A
Rev 1 – January 2013 Bid Package: Audience Seating and Telescoping Stands 009.12.02
As noted below, Subcontractor shall be responsible for the following project-related activities and Scope of Work in accordance with the requirements of the specifications, drawings, and CM Manual. Furnish all labor and supervision required to complete the work of this package. Unless noted otherwise, furnish all equipment, materials, supplies, tools, scaffolding, hoisting, transportation, unloading, and handling necessary for the proper installation and completion of this work.
APPLICABLE SPECIFICATIONS
Include work normally associated with trade whether referenced in these sections or not:
• Division 0
• Division 1
• SECTION 126100 – FIXED AUDIENCE SEATING (ARM-REST AND END PANEL REPLACEMENT ONLY)
SCOPE OF WORK Includes, but is not necessarily limited to:
Section A: General Scope Requirements
▪ Refer to Section 3, Instructions for Procurement, for general requirements. ▪ Smoking, the use of tobacco, or the use of products containing tobacco in any form is prohibited on
any property owned or leased by a public school district. ▪ Subcontractor agrees to follow all safety procedures and safety regulations of Nabholz, including
those that are more stringent than Subcontractor’s own safety policy or OSHA standards. ▪ All employees must wear hard hats, eye protection, and high visibility vests at all times on site. ▪ Deliveries of building materials will give right of way to school bus traffic during drop-off and pick-up
times. ▪ Subcontractor is responsible for the protection of the SWPPP devices in place. ▪ Construction Manager will provide layout to building corners. Subcontractor is responsible for
layout beyond these points. ▪ Coordinate on-site employee parking with Project Superintendent. ▪ Coordinate location of on-site storage containers with Project Superintendent. ▪ Employees shall avoid harassment of students, faculty, or staff. Employees who violate this
requirement may be removed from the jobsite by Project Superintendent. ▪ Subcontractor will actively participate in the Nabholz Quality Management System. ▪ Subcontractor agrees to follow the Project Schedule and meet the milestone dates. Certain areas
may be made earlier than originally indicated on Schedule. Subcontractor must be prepared for any minor adjustments to the Schedule as work progresses.
▪ Subcontractor must attend weekly coordination meetings. Employees attending meetings must have the authority to make commitments on manpower to maintain Project Schedule or meet milestone dates.
Section B: Trade-Specific Requirements
▪ Furnish and install fixed audience seating systems. ▪ Include all material, equipment, and associated hardware to provide a complete installation. ▪ Installer Qualifications: Manufacturer's authorized representative who is trained and approved for
installation of units required for this Project. ▪ Provide special warranty for each section of this package, as specified; commencing on the date of
substantial completion of the project.
Section C: Project-Specific Requirements
009.12.02 Audience Seating Exhibit A
Rev 1 – January 2013 Bid Package: Audience Seating and Telescoping Stands 009.12.02
▪
Section D: Alternate Pricing
▪ Provide alternate price on Lump Sum Proposal form for XXX.
END OF PACKAGE
009.22.01 Plumbing Exhibit A
Rev 1__September 2018 Bid Package: Plumbing 009.22.01
As noted below, Subcontractor shall be responsible for the following project-related activities and
Scope of Work in accordance with the requirements of the specifications, drawings, and CM Manual.
Furnish all labor and supervision required to complete the work of this package. Unless noted otherwise,
furnish all equipment, materials, supplies, tools, scaffolding, hoisting, transportation, unloading, and
handling necessary for the proper installation and completion of this work.
APPLICABLE SPECIFICATIONS Include work normally associated with trade whether referenced in these sections or not:
• Division 0
• Division 1
• SECTION 220500 – COMMON WORK RESULTS FOR PLUMBING
• SECTION 220519 – METERS AND GAUGES
• SECTION 220523 – VALVES FOR PLUMBING PIPING
• SECTION 220529 – HANGERS, SUPPORTS AND VIBRATION ISOLATION FOR PLUMBING
PIPING AND EQUIPMENT
• SECTION 220553 – IDENTIFICATION FOR PLUMBING PIPING AND EQUIPMENT
• SECTION 220700 – PLUMBING INSULATION
• SECTION 221100 – FACILITY PIPING AND SPECIALTIES
• SECTION 223300 – ELECTRIC DOMESTIC WATER HEATERS
• SECTION 224000 – PLUMBING FIXTURES
SCOPE OF WORK Includes, but is not necessarily limited to:
Section A: Reference Section 009.01 General Scope Requirements
Section B: Trade-Specific Requirements
1. Furnish and install complete plumbing system per construction documents.
2. Include complete sanitary sewer system.
3. Include any utility company fees, impact costs, metering or vault costs Include penetration
sleeves, saw cutting, and coring required for this scope of work.
4. Because of the drawing scales it is not possible to indicate all fittings and accessories that may
be required. Include any and all fittings, offset, valves, etc., for a complete system.
5. In the case of discrepancy between drawings, specifications, codes, local and state laws,
ordinances, or contract documents, the most stringent governs.
6. Include documented instructional training to the owner’s representative regarding the operation
and maintenance of the plumbing systems.
7. All warranties for fixtures, devices, and equipment begin at date of Substantial Completion of
Project.
8. Furnish on site storage as required by the construction manager for the storage of fixtures and
equipment.
9. Include all hoisting and scaffolding as required.
10. Clean up waste and debris generated by this scope of work and dispose on a daily basis and as
directed by the construction manager.
009.22.01 Plumbing Exhibit A
Rev 1__September 2018 Bid Package: Plumbing 009.22.01
11. Furnish and install all plumbing fixtures including but not limited to urinals, urinal carriers, toilets,
sinks and drinking fountains.
12. Include shower and bath units including shower pans as required.
13. Include backflow preventers and tests.
14. Include temporary water supply.
15. Furnish and install all domestic water piping required to complete this scope of work. Tie new
sanitary sewer lines in the existing sanitary sewer system per construction documents.
16. Include water and sewer connections to the job trailer as required.
17. Include selective demolition required to install work in existing building. Remove plumbing items
per plumbing plans shown to be removed and legally dispose of off site. Cap existing lines.
18. Include all associated blocking, anchors, stenciling and tagging for this scope of work.
19. Include pipe supports associated with this scope of work. All miscellaneous steel, uni-strut, all
thread rod and accessories required for pipe support, wall or floor penentrations and blocking as
required.
20. Coordinate with other trades to locate sleeves and to ensure plumbing does not interfere with any
other items.
21. Include all plumbing identification including color coding, stencil, labels tags, etc. per construction
documents.
22. Include cutting, coring and patching required for plumbing installations.
23. Supply any access doors (24” x 24” min.) needed for access to plumbing equipment.
24. Include removal and replacement of concrete and masonry as required to tie into existing
services and utilities. Verify locations of services prior to submitting a bid proposal.
25. Install flashing or sealant at each exterior weather barrier penetration per weather barrier
manufacturer’s recommendation.
26. Include final plumbing connections to laboratory equipment, food service equipment and
casework. Coordinate with those trades for tie-in of plumbing items relating to those trade.
27. Furnish and install all appliance related plumbing as required.
28. Include fire-stopping for penetrations created by this scope of work.
29. Include sealants (color selected by Architect) around all plumbing fixtures, sinks and lavatories.
30. Provide video scoping of all sanitary sewer lines to the outside of building prior to substantial
completion and correct any blockages or deficient piping found.
31. Include cleaning, purging and flushing of all lines when complete as related to this scope of work.
32. Plumbing contractor is to lay out all lines and elevations associated with this scope of work.
33. Prior to placement of the concrete slab, all stub ups are to be capped to prevent any concrete
debris from falling into sanitary waste and vent lines. After installation of all concrete slabs on
grade provide camera inspections of all sanitary sewer and vent lines to verify that lines are free
and clear of debris.
34. Ensure all equipment has adequate maintenance access when in place.
35. Include a plumbing representative to be on site during slab pours to ensure plumbing lines remain
in place.
36. It is the responsibility of the plumbing contractor to verify the locations of all existing utilities and
services as indicated on the drawings that are to be tied into prior to submitting a bid proposal.
Failure to do so will result in the plumbing contractor assuming responsibility for any deviations of
existing utilities from the construction documents.
37. Furnish all pipe bedding, cushion materials and thrust blocks per construction documents.
38. Provide gradation plan if required. Check all sewer line gradations with existing utilities prior to
installation to ensure the required flow is achieved.
009.22.01 Plumbing Exhibit A
Rev 1__September 2018 Bid Package: Plumbing 009.22.01
39. Upon completion of plumbing contactor’s underground work, plumbing contractor is responsible
to re-grade area, back fill and compaction to restore slopes and elevations to prevent standing
water. Remove all spoils off site. Restore areas to the same state or better before work was
commenced.
40. Dewater excavations associated with this trade as required to preserve structural integrity and
workability.
Section C: Project-Specific Requirements
C-1: High School Additions and Renovations
• Include any seismic requirements.
• Include grease interceptors and acid waste items as required
• Include all-natural gas piping, including for HVAC equipment
• Hydronic piping, if required, for HVAC systems is by others
• Provide condensate drains for mechanical equipment, as required
• Supply roof drains to be installed by roofing contractor. Include roof drain piping and connection
to roof drains
• Include all final connections to Owner-furnished equipment.
• Include water, sanitary, roof drain and/ or gas lines to 5’ outside of building, exterior. Plumbing
assemblies beyond that point are by others.
• All utility fees are by others.
• Provide and install all access doors and panels for this scope
• Equipment pads are by others
• Provide all haul off and disposal as required for this scope of work
• Patch and level all disturbed concrete related to plumbing work.
Section D: Project-Specific Exclusions
1. None
Section E: Alternate Pricing
Section F: Unit Pricing
1. Not applicable
END OF PACKAGE
009.23.01 Heating, Ventilation, Air Conditioning Exhibit A
Rev 1__September 2018 Bid Package: Heating, Ventilation, Air Conditioning 009.23.01
As noted below, Subcontractor shall be responsible for the following project-related activities and
Scope of Work in accordance with the requirements of the specifications, drawings, and CM Manual.
Furnish all labor and supervision required to complete the work of this package. Unless noted otherwise,
furnish all equipment, materials, supplies, tools, scaffolding, hoisting, transportation, unloading, and
handling necessary for the proper installation and completion of this work.
APPLICABLE SPECIFICATIONS Include work normally associated with trade whether referenced in these sections or not:
• Division 0
• Division 1
• SECTION 230500 – COMMON WORK RESULTS FOR HVAC
• SECTION 230529 – HANGERS, SUPPORTS AND VIBRATION SECTION ISOLATION FOR
HVAC PIPING AND EQUIPMENT
• SECTION 230553 – IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT
• SECTION 230593 – TESTING AND BALANCING
• SECTION 230700 – HVAC INSULATION
• SECTION 230701 – HVAC PIPING INSULATION
• SECTION 203902 – BUILDING MANAGEMENT CONTROLS SYSTEM
• SECTION 230903 – VARIABLE REGRIGERANT SPLIT SYSYEM CONTROLS
• SECTION 232113 – HVAC PIPING AND SPECIALTIES
• SECTION 233113 – HVAC DUCTEORK
• SECTION 233300 – AIR DUCT ACCESSORIES
• SECTION 233423 – POWER VENTILATORS
• SECTION 233713 – GRILLES, REGISTERS AND DIFFUSORS
• SECTION 237200 – ENERGY RECOVERY UNITS
• SECTION 237413 – PACKAGED ROOFTOP UNITS
• SECTION 238127 – VARIABLE REFRIGERANT SPLIT SYSTEMS
• SECTION 239000 – LOUVERS AND VENTS
• SECTION 233814 – KILN HOODS
• SECTION 233816 – DUST COLLECTION SYSTEM
• SECTION 237433 – DEDICATED OUTSIDE AIR UNITS
SCOPE OF WORK Includes, but is not necessarily limited to:
Section A: Reference Section 009.01 General Scope Requirements
Section B: Trade-Specific Requirements
009.23.01 Heating, Ventilation, Air Conditioning Exhibit A
Rev 1__September 2018 Bid Package: Heating, Ventilation, Air Conditioning 009.23.01
1. Furnish and install a complete HVAC system.
2. All warranties for fixtures, devices, and equipment begin at date of Substantial Completion of
Project.
3. Include warranty per construction documents on all equipment regardless if used temporarily
during construction for climatization.
4. HVAC contractor to provide equipment and ductwork shop drawings for coordination with other
trades. Shop drawings are to include the locations and sizes of all duct work, equipment and
equipment maintenance access.
5. Provide layout locations as needed for roof curb, exhaust fans, vents etc. during steel erection
phase.
6. In the case of discrepancy between drawings, specifications, codes, local and state laws,
ordinances, or contract documents, the most stringent governs.
7. Include testing, adjusting and balancing per contract documents.
8. Include Commissioning per construction documents as required.
9. Scope includes, but is not limited to equipment, supports, anchors, curbs, flashings, piping, duct
work, insulation, controls, stenciling and labeling, VFD’s, equipment disconnect switches, air
venting devices, air exhausting devices, flow switches, condensation lines, dampers, diffusers,
detectors, interconnection of instrumentation I/O control wiring systems, fuels, refrigerants and
lubricants, supports for mechanical equipment, and other materials and devices as required for a
complete HVAC system as per plans and specifications.
10. Supply any access doors (24” x 24” min.) needed for access to HVAC equipment.
11. Include all selective demolition required to install work in the existing building. Remove all HVAC
items per HVAC or demolition plans and legally dispose of off site.
12. Provide all sleeves, blocking, coring, and other associated caulking required for this scope of
work.
13. Provide the necessary temporary air filters materials over permanent return air grills at all
entrances to return air ducts weekly or as needed.
14. Include concrete cutting, coring and patching as required for the mechanical scope of work.
15. Include Automatic Temperature Controls and interlock wiring including control components and
complete control wiring system in strict accordance with construction documents.
16. Furnish and install motor controllers and starters for mechanical equipment as specified.
17. Include roof curbs and penetration enclosures as required and per the roofing manufacturer’s
requirements to preserve the roof warranty.
18. Furnish and install louvers, access doors, grilles, and vents as required for this scope of work.
19. Include condensate piping.
20. Duct detectors are to be furnished by the HVAC contractor, installed by this scope of work, and
terminated by the HVAC contractor. Coordinate with the fire alarm contractor for wiring and
terminations.
009.23.01 Heating, Ventilation, Air Conditioning Exhibit A
Rev 1__September 2018 Bid Package: Heating, Ventilation, Air Conditioning 009.23.01
21. Provide air filters including spare air filters for HVAC equipment. Furnish, install and maintain
temporary filters during construction operations.
22. Provide conditioned air at the earliest possible date, as directed by Construction Manager,
including all temporary and final air filters as required.
23. Furnish, install and maintain all roof penetrations, openings and curbs associated with this scope
of work until all equipment has been installed and flashed in permanently. Remove and dispose of
covers at the completion of work.
24. Include fire-stopping, fire sealing and caulking for penetrations created by this scope of work.
25. Because of the drawing scales it is not possible to indicate all fittings and accessories that may be
required. Include any and all fittings, offset, valves, etc., for a complete system.
26. Include documented instructional training to the owner’s representative regarding the operation
and maintenance of the plumbing systems.
27. Coordinate with the electrical contractor for the location, size and installation of disconnects. The
electrical contractor is to furnish and install disconnects. The locations are to be provided by the
HVAC contractor.
28. Coordinate with food service or laboratory contractor for tie-in locations of mechanical items
relating to their equipment.
Section C: Project-Specific Requirements
C-1: High School Additions and Renovations
• Include HVAC demolition as indicated in the Construction Documents
• Provide disconnects for demolition and any new work in existing areas required for completion of
new HVAC system.
• Cut all openings required to complete this scope of work, protecting all adjacent finished surfaces,
new and existing
• Relocate diffusers, grills, etc. as required in existing areas.
• In the existing building, this contractor is responsible for any removals, replacement, repairs,
needed for this contractor to perform their work (e.g. ceiling grid, ceiling tile, etc.) • Include
any seismic requirements
• Include all hydronic piping.
• Supply and install roof curbs and curb caps. Coordinate with roofing contractor.
• All controls associated with HVAC Equipment shall be part of this scope of work.
• Required to condition space prior to substantial completion, for material acclimation purposes.
• Include required filters and replacements of filters until substantial completion.
• Test and Balance, Owner Training and Controls Commissioning shall be part of this scope of
work.
• Equipment pads by concrete contractor
• Provide and install access panels and doors required for this scope
009.23.01 Heating, Ventilation, Air Conditioning Exhibit A
Rev 1__September 2018 Bid Package: Heating, Ventilation, Air Conditioning 009.23.01
• Include diffuser in Room 400C, and an exhaust fan in room 400D. Section D: Project-Specific
Exclusions
• Provide Kiln flue vent up to flue roof cap according to kiln manufacturer instructions. Owner
furnished kiln to be installed by contractor.
• Include all compressed air piping.
1. None
Section E: Alternate Pricing
Section F: Unit Pricing
1. Not applicable
END OF PACKAGE
009.26.02 Electrical Exhibit A
Rev 1__September 2018 Bid Package: Electrical 009.26.02
As noted below, Subcontractor shall be responsible for the following project-related activities and
Scope of Work in accordance with the requirements of the specifications, drawings, and CM Manual.
Furnish all labor and supervision required to complete the work of this package. Unless noted otherwise,
furnish all equipment, materials, supplies, tools, scaffolding, hoisting, transportation, unloading, and
handling necessary for the proper installation and completion of this work.
APPLICABLE SPECIFICATIONS Include work normally associated with trade whether referenced in these sections or not:
• Division 0
• Division 1
• SECTION 260500 – COMMON WORK RESULTS FOR ELECTRICAL
• SECTION 260519 – CONDUCTORS AND CABLES
• SECTION 260533 – RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS
• SECTION 260553 – IDENTIFICATION FOR ELECTRICAL EQUIPMENT AND WIRING
• SECTION 260923 – LIGHTING CONTROL DEVICES
• SECTION 262416 – PANELBOARDS
• SECTION 262726 – WIRING DEVICES
• SECTION 265100 – LIGHT FIXTURES
• SECTION 262200 -- TRANSFORMERS
SCOPE OF WORK Includes, but is not necessarily limited to:
Section A: Reference Section 009.01 General Scope Requirements
Section B: Trade-Specific Requirements
1. Provide all site power and/or lighting electrical work.
2. Provide all site trenching and duct banks needed for electrical and communication underground
raceways and/or cables.
3. Provide any electrical meter fees or impact cost required by the local electrical service provider.
4. Provide any conduit, pull strings, j-boxes etc. for any Division 26, 27, or 28 empty raceway
systems as required per plans and specifications.
5. Provide any building primary/secondary electrical switchgear, panels, emergency power and/or
generator systems as per plans and specifications.
6. Provide all raceway, wiring and terminations of VFD’s, motor controllers, dampers and/or starters
that are furnished and installed by HVAC Subcontractor.
7. Provide any grounding systems, lightning protection systems, and certifications as required per
plans and specifications.
8. Provide all temporary lighting and power distribution in buildings as required for construction
activities.
9. Provide all final connections and terminations for Owner Furnished Equipment.
10. Provide all final electrical connections and terminations as required to equipment furnished and
installed by other bid packages.
11. Provide equipment and device testing, checkout and/or load studies as required per plans and
specifications.
009.26.02 Electrical Exhibit A
Rev 1__September 2018 Bid Package: Electrical 009.26.02
12. Provide training of Owner’s staff on electrical equipment.
13. Provide all raceway, wire, termination, poles, light fixtures, and grounding for site lighting.
Concrete pole bases will be provided by others.
14. Deposit dirt spoils in area on site designated by the Project Superintendent.
15. In the case of difference between drawings, specification, codes local & state laws, ordinances or
contract documents, the most stringent governs.
16. All warranties for fixtures, devices, equipment and gear begin at the date of the Project’s
Substantial Completion.
17. Include primary and secondary electrical service with manholes or pullboxes as required, regrade
area, back fill and compaction to restore slopes and elevations to prevent standing water.
Remove all spoils off site. Restore areas to the same state or better before work was
commenced.
18. Furnish and install concrete where required to encase electrical services or other electrical items.
19. Include utility fees for new or relocated transformers.
20. Include all back boxes. For owner equipment per this scope.
21. Include emergency generator including fuel.
22. Include uninterruptable power supply system.
23. Provide electrical for infrared flush valves and hand dryers.
24. Furnish and install disconnects at HVAC units and fans as indicated on mechanical drawings.
Coordinate with HVAC contractor for disconnect locations.
25. Make electrical connections to lab equipment, food service equipment, casework, mechanical
equipment, A/V equipment, cubicles and owner furnish equipment.
26. Furnish, install, maintain and remove temporary electrical services in accordance with OSHA
requirements. Include temporary power to job trailer.
27. Include fire stopping and/or fire sealing at all fire walls and caulking of all electrical penetrations.
28. Include all sleeves and core drilling required.
29. Include all electrical identification including color coding, stencil, labels tags, etc. per construction
documents.
30. Include the demolition of all electrical items shown to be removed and legally dispose of off site.
Disconnect power to areas to be renovated as directed by superintendent.
31. Include temperature control wiring and auxiliary interlock control wiring.
32. Verify breaker and wire size for HVAC equipment within the equipment manufacturers
specifications, notify the electrical engineer and adjust as needed.
33. Make required electrical connections and install conduit in slab at own risk as plumbing coring
later of lab casework may cut conduit.
34. Install flashing or sealant at each exterior weather barrier penetration per weather barrier
manufacturer’s recommendation.
Section C: Project-Specific Requirements
C-1: High School Additions and Renovations
• Include any seismic requirements
• Include electrical demolition as indicated in the Construction Documents
• Provide disconnects for demolition and any new work in existing areas required for completion of
new electrical system
• Cut all openings required to complete this scope of work, protecting all adjacent finished surfaces,
new and existing
009.26.02 Electrical Exhibit A
Rev 1__September 2018 Bid Package: Electrical 009.26.02
• Provide all conduit and backboxes for Telecommunications Systems where located either (A.)
under finished slab or grade or (B.) concealed in finished walls or ceilings. This does not include
specialty outlet boxes.
• Provide all conduit and backboxes for Division 28 Electronic Safety and Security Systems where located either (A.) under finished slab or grade or (B.) concealed in finished walls or inaccessible ceilings
• Furnish and install two (2) minimum support wires from building structure to each electrical
recessed fixture located in tee bar grid system.
• Provide power to all electrified door hardware/ components as required.
• Concrete pole bases, transformer pads, and housekeeping pads will be provided by others.
• Provide and install bollard lights
• Protect existing all floors during your work.
• Include temporary lighting and maintain. Reference milestone schedule for duration.
• Provide and install access panels and doors required for this scope
• Fire stopping will be by the waterproofing/firestopping contractor
• Incorporate materials that are compatible with utility monitoring as specified
• Supply and Install all electrical hand dryers noted in construction documents.
Section D: Project-Specific Exclusions
1. None
Section E: Alternate Pricing
Section F: Unit Pricing
1. Not applicable
END OF PACKAGE
009.27.02 Electronic Safety and Security (Supply & Install) Exhibit A
As noted below, Subcontractor shall be responsible for the following project-related activities and
Scope of Work in accordance with the requirements of the specifications, drawings, and CM Manual.
Furnish all labor and supervision required to complete the work of this package. Unless noted otherwise,
furnish all equipment, materials, supplies, tools, scaffolding, hoisting, transportation, unloading, and
handling necessary for the proper installation and completion of this work.
APPLICABLE SPECIFICATIONS Include work normally associated with trade whether referenced in these sections or not:
• Division 0
• Division 1
• SECTION 280500 – COMMON WORK RESULTS FOR ELECTRONIC SAFETY AND SECURITY
• SECTION 283111 – ADDRESSABLE FIRE ALARM SYSTEM
SCOPE OF WORK Includes, but is not necessarily limited to:
Section A: Reference Section 009.01 General Scope Requirements
Section B: Trade-Specific Requirements
1. Provide any conduit, pull strings, j-boxes etc. for any Division 28 empty raceway systems as
required per plans and specifications.
2. Provide all final connections and terminations for Owner Furnished Equipment.
3. Provide all final electrical connections and terminations as required to equipment furnished and
installed by other bid packages.
4. Provide equipment and device testing, checkout and/or load studies as required per plans and
specifications.
5. Provide training of Owner’s staff on electronic safety and security system or equipment.
6. Provide fire stopping for all penetrations created by this scope.
7. In the case of difference between drawings, specification, codes local & state laws, ordinances or
contract documents, the most stringent governs.
8. All warranties for fixtures, devices, equipment and gear begin at the date of the Project’s
Substantial Completion.
9. Include low voltage wiring at magnetic hold opens (coordinate with door and hardware suppliers).
10. Wire all duct detectors and coordinate with HVAC contractor.
Section C: Project-Specific Requirements
C-1: High School Additions and Renovations
• Provide all Division 28 Electronic Safety and Security Systems.
• Coordinate with Division 26 for pathways and routing of back boxes, conduits, and means of
support.
• Furnish and install all specialty back-boxes as required by equipment manufacturer not covered
under Division 26 scope of work.
• Included all required demolition of Fire-Alarm components, circuits, etc. as indicated in the design
drawings and as required to complete demolition activities. Coordinate with other trades prior to
and during demolition activates.
• All demolished Fire Alarm components and refuse shall be removed from the site and properly
disposed of as part of this scope of work.
Rev 1__September 2018 Bid Package: Electronic Safety and Security 009.27.02
009.27.02 Electronic Safety and Security (Supply & Install) Exhibit A
• Include any seismic requirements.
• Provide all J-Hooks and miscellaneous cable management for circuits concealed in accessible
ceilings. All conduit and back boxes for where located either (A.) under finished slab or grade or
(B.) concealed in finished walls or inaccessible ceilings are provided by Division 26 Electrical
Contractor.
• All fire rated plywood backboards provided by others.
• Provide and install all access panels and doors required for this scope.
Section D: Project-Specific Exclusions
1. None
Section E: Alternate Pricing
Section F: Unit Pricing
1. Not applicable
END OF PACKAGE
PROJECT IDENTIFICATION: ADDITIONS AND RENOVATIONSSCHOOL OF THE OSAGE HIGH SCHOOL OSAGE BEACH, MISSOURI
CODE: 2012 INTERNATIONAL BUILDING CODE2012 INTERNATIONAL MECHANICAL CODE2012 UNIFORM PLUMBING CODE2011 NATIONAL ELECTRIC CODE2012 INTERNATIONAL FIRE CODE
OCCUPANCY: E - EDUCATIONAL
PROPOSED USE: TECH ARTS ADDITION AND RENOVATIONS TO EXISTING
CONSTRUCTION TYPE: TYPE 2B - SINGLE STORY
BUILDING HEIGHT: ALLOWABLE: 75', 3-STORYACTUAL: 30', 1-STORY
ALLOWABLE AREA: (TABLE 503 & SECTION 506)
ALLOWABLE AREA = 14,500 SFFRONTAGE INCREASE
[(362/605) - .25] * 30/30 = .35.35 * 14,500 = 5,075 SF
SPRINKLER INCREASE (300%) = 43,500 SFTOTAL ALLOWABLE = 63,075 SF
GROSS BUILDING AREA:EXISTING HIGH SCHOOL: 124,430 SFNEW ADDITIONS: 14,512 SF
AUTOMATIC SPRINKLER SYSTEM:EXISTING BUILDING IS NOT SPRINKLED
NEW ADDITION IS TO BE SPRINKLED
STORAGE ROOM:FIRE SPRINKLER SYSTEM OR (1) HR FIRE BARRIER REQUIRED FOR ROOMS OVER 100SF
(FIRE SYSTEM PROVIDED)
FIRE ALARM & DETECTION SYSTEMS: REQUIRED PER SECTION 907
MAX. TRAVEL DISTANCE FOR EXITS ALLOWED:250 LF, PER 2012 IBC (TABLE 1016.2)
EXIT SEPARATION - MINIMUM SEPARATION IS 1/3 OF THE MAXIMUM DIAGONAL OF THE AREA OF FLOOR MEASURED BETWEEN EXITS PER SECTION 1015.2.1
DESIGN OCCUPANT LOAD (IBC 2012, SECT 1004):TABLE 1004.1.2
BUILDING OCCUPANCY:TOTAL OCCUPANT LOAD OF NEW ADDITION IS 670 OCCUPANTS
PLUMBING FIXTURES:WATER CLOSETS
REQUIRED 14PROVIDED 69
LAVATORIESREQUIRED 14PROVIDED 45
DRINKING FOUNTAINSREQUIRED 7PROVIDED 8
SERVICE SINKREQUIRED 1PROVIDED 7
16168 SF
EXISTING
FIRE AREA
11850 SF
EXISTING
FIRE AREA
10856 SF
EXISTING
FIRE AREA
59491 SF
EXISTING
FIRE AREA
7199 SF
EXISTING
FIRE AREA
12150 SF
NEW FIRE
AREA
3826 SF
EXP.
LOCKER
RM AREA
4300 SF
EXP. KITCH
AREA
3024 SF
EXIST FIRE
AREA
1365 SF
EXIST'G
FIRE AREA
3928 SF
EXP.
LOCKER
RM AREA
SPRINKLERED
NON-SPRINKLEREDNON-SPRINKLERED
NON-SPRINKLERED
NON-SPRINKLERED
NON-SPRINKLERED
SPRINKLERED
NON-SPRINKLERED
* *
EXIST'G 2 HR F.B.
EXIST'G 2 HR F.B. NEW 2 HR F.B.
7551 SF
EXIST FIRE
AREA -
NEW BAND
NON-SPRINKLEREDNON-SPRINKLERED
EX
ITE
XIT
EXIT
EX
ITE
XIT
EX
IT
EXITEXIT
EXIT
EXIT
EXITEXIT
EX
ITE
XIT
EX
IT
EX
ITE
XIT
EXITEXIT
EXIT EXIT EXIT
EX
IT
EX
IT
EXIT
EXIT
EX
IT
EXIT
NON-SPRINKLERED
EXITEXIT
EXIT
11
EXIST'G 2 HR F.B.
NEW 2 HR F.B.
EXIST'G 2 HR F.B.NEW 2 HR F.B.
NEW 2-HR FIRE BARRIER
EXIST'G 2-HR FIRE BARRIER
NEW ADDITIONS AREA
EXISTING BUILDING AREA
JAMES SAPPMICHAEL
NUMBER
A-5051
ST
ATE
OF M I SSO
UR
I
RE
GI S
T E R E D A RCH
I TE
CT
DateProject No. Drawn
Drawing No.
© Copyright 2018 - Sapp Design Associates, Architects, P.C.
Sapp Design Associates Architects, P.C.Missouri State Certificate of Authority #000607
Architect of Record
Michael James Sapp, Architect MO A-5051
In the event the client consents to, allows, authorizes or approves of changes to any plans, specifications or other construction documents, and these changes are not approved in writing by the design professional, the client recognizes that such changes and the results thereof are not the responsibility of the design professional. Therefore, the client agrees to release the design professional from any liability arising from the construction, use or result of such changes. In addition, the client agrees to the fullest extent permitted by law, to indemnify and hold the design professional harmless from any damage, liability or cost (including reasonable attorney's fees and costs of defense) arising from such changes.
The personal seal of the registered Architect or Engineer shall be the legal equivalent of his signature whenever & wherever used, and the owner of the seal shall authenticate this sheet and the specification sections pertaining to this sheet. Responsibility shall be disclaimed for all other plans, specifications, estimates, reports or other documents or instruments relating to or intended to be used for any part or parts of the architectural project.
SPECIAL NOTICES
Author09-06-201817-0923
G200OVERALL CODE PLAN
CODE SUMMARY
HIG
H S
CH
OO
L6
36 M
O-4
2O
SA
GE
BE
AC
H, M
ISS
OU
RI 65065
CA
MD
EN
CO
UN
TY
RE
NO
VA
TIO
NS
AN
D A
DD
ITIO
NS
TO
SC
HO
OL O
F T
HE
OS
AG
E R
-IICODE SUMMARY
1" = 30'-0"1
FIRE AREA / CODE PLAN
Revision No. Description Date
1 ADDEND #1 10-3-18
CODE PLAN LEGEND
1
10-3-2018
COACHES
OFFICE
701B
OFFICE
701R
TLT
701M
HALL
701K
EXIST SHWR
701J
COACHES
OFFICE
701F
EXIST TLT
701G
EXIST TLT
701E
EXIST SHWR
701D
DRYING
701C
LAUNDRY
701A
EXISTING BOYS
LOCKER
701H
EXIST TLT
702J
EXIST TLT
702G
EXIST SHWR
702F
MAKEUP AREA
702D
COACHES
OFFICE
702H
EXISTING GIRLS
PE LOCKERS
702K
REFS
702BTLT
702C
EXIST DRYING
702E
EXIST SHWR
702L
HALL
702M
PE STOR
702S
COACH OFFICE
702Q
WEIGHT ROOM
502
J
702P
1
11
22
1
1
2
2
3
44
3
33
5
2
6
5
55
33
4
33
2
2
5
GIRLS PE
LOCKER ROOM
702
77
77
PE STORAGE
701L
TLT
702R
J
701T
2
8
1
9
910
10
7
7
2
22
2
8
8
8
2
2
1
2
8
8
77
7
10
10
7
11
11
7
7
12
12
121212
12
121212
1
1
1212
1
1
1
12
12
1
11D
11D
7B 7C
7D
11C
7A
8
10
11A
10D
11B
11A
1. ALL DASHED LINES INDICATE ITEMS OR PORTIONS OF BUILDING TO BE REMOVED. SEE ALSO FLOOR PLAN, OTHER ARCH PLANS AND MEP DEMO PLANS FOR ADDITIONAL DEMO WORK.
2. CONTRACTOR SHALL INSPECT EXISTING BUILDING AND SITE TO REVIEW EXISTING CONDITIONS PRIOR TO BIDDING. NOTIFY ARCHITECT/ENGINEER MINIMUM 10 DAYS PRIOR TO BIDDING TO CLARIFY ANY DEMOLITION WORK AND EXISTING CONDITIONS.
3. ALL REMOVALS SHALL BE MADE WITH LEAST DAMAGE POSSIBLE TO ADJACENT SURFACES AND ASSEMBLIES. SAWCUT ALL EDGES OF WALL FOR SURFACE REMOVALS.
4. NEW WORK SHALL INCLUDE PATCHING AND PREPPING OF ALL POST-REMOVAL SURFACES FOR A FINISHED EXPOSED SURFACE, OR FOR NEW FINISHES, OR TO MATCH ADJACENT SURFACES, AS CONDITIONS REQUIRE. WORK IS NOT REQUIRED WHERE THE REMOVAL SURFACE IS TO BE CONCEALED, EXCEPT THAT IT SHALL BE LEFT NEAT AND COMPLETE AND SAFE.
5. NEW WORK SHALL INCLUDE ALL PENETRATIONS AS MAY BE NECESSARY FOR DUCTS, PIPING, CONDUITS, ETC. AND ACCORDING TO SAME REQUIREMENTS AS IN NOTES 3 AND 4 ABOVE.
6. SEE ELECTRICAL DEMOLITION DRAWINGS FOR DEMO OF EXISTING ELECTRICAL PANELS, LIGHTING, CEILING FANS, ELECTRICAL DEVISES, WIRING, ETC.
7. REMOVE EXISTING MECHANICAL SYSTEMS INCLUDING HEATING PIPING, FAN COIL UNITS, BOILERS, DUCTWORK, ETC. COMPLETELY -ALSO SEE MECH DEMOLITION DRAWINGS
8. AT BUILDING & SIDEWALK REMOVE ALL PAVEMENT, CONCRETE FLOOR SLAB AND BASE ROCK FOR NEW GRASS AREA - SEE SITE PLAN
9. REMOVE ALL UNUSED OR ABANDONED CONDUIT, PIPING, WIRING, DUCTS, ETC. AT EXISTING CEILING
10. WHERE WALLS BEING REMOVED ARE LOADBEARING PROVIDE TEMPORARY SUPPORT/ SHORING TO MAINTAIN STRUCTURAL INTEGRITY OF STRUCTURE UNTIL LINTELS ARE INSTALLED.IF DURING DEMOLITION IT IS DISCOVERED THAT A WALL INDICATED TO BE REMOVED IS LOAD BEARING OR REMOVAL MAY AFFECT INTEGRITY OF WALL OR STRUCTURE AND NO ADDITIONAL SUPPORTS ARE NOTED OR INDICATED ON DRAWINGS, CONTACT ARCHITECT IMMEDIATELY FOR RESOLUTION BEFORE PROCEEDING WITH WORK.
11. PROVIDE PROTECTION OF EXISTING FINISHES THAT ARE TO REMAIN
12. COMPLETE REMOVAL OF ITEMS OR ASSEMBLIES UNLESS OTHERWISE NOTED. I.E. INCLUDING ALL BRACING, PIPING, CONDUITS, TRIM, ETC.
13. OWNER HAS FIRST RIGHT OF REFUSAL ON DEMOLISHED ITEMS - I.E. DOORS, SEATS, HARDWARE, LIGHTS, CABINETS, ETC.
JAMES SAPPMICHAEL
NUMBER
A-5051
ST
ATE
OF M I SSO
UR
I
RE
GI S
T E R E D A RCH
I TE
CT
DateProject No. Drawn
Drawing No.
© Copyright 2018 - Sapp Design Associates, Architects, P.C.
Sapp Design Associates Architects, P.C.Missouri State Certificate of Authority #000607
Architect of Record
Michael James Sapp, Architect MO A-5051
In the event the client consents to, allows, authorizes or approves of changes to any plans, specifications or other construction documents, and these changes are not approved in writing by the design professional, the client recognizes that such changes and the results thereof are not the responsibility of the design professional. Therefore, the client agrees to release the design professional from any liability arising from the construction, use or result of such changes. In addition, the client agrees to the fullest extent permitted by law, to indemnify and hold the design professional harmless from any damage, liability or cost (including reasonable attorney's fees and costs of defense) arising from such changes.
The personal seal of the registered Architect or Engineer shall be the legal equivalent of his signature whenever & wherever used, and the owner of the seal shall authenticate this sheet and the specification sections pertaining to this sheet. Responsibility shall be disclaimed for all other plans, specifications, estimates, reports or other documents or instruments relating to or intended to be used for any part or parts of the architectural project.
SPECIAL NOTICES
Author09-06-201817-0923
D102AREA 11 DEMOLITION PLANS
HIG
H S
CH
OO
L6
36 M
O-4
2O
SA
GE
BE
AC
H, M
ISS
OU
RI 65065
CA
MD
EN
CO
UN
TY
RE
NO
VA
TIO
NS
AN
D A
DD
ITIO
NS
TO
SC
HO
OL O
F T
HE
OS
AG
E R
-II
DEMOLITION KEYNOTES
1 REMOVE EXISTING WALLS AND DOORS AS INDICATED. PATCH, REPAIR ANDPREP EXISTING FLOOR, WALLS AND CEILINGS AS REQUIRED TO MATCHEXISTING
2 REMOVE EXISTING CMU WALL FOR NEW DOOR & FRAME (OR WINDOW)INSTALLATION. PATCH, REPAIR AND PREP EXISTING WALL & FLOOR ASREQ'D FOR NEW FINISHES TO MATCH EXISTING.
3 REMOVE EXISTING LOCKERS. PATCH, REPAIR AND PREP EXISTING WALLPATCH, REPAIR AND PREP EXISTING WALL & FLOOR AS REQ'D FOR NEWFINISHES TO MATCH EXISTING.AS REQ'D FOR NEW FINISHES TO MATCHEXISTING.
4 REMOVE EXISTING CONCRETE LOCKER BENCH. PATCH, REPAIR AND PREPEXISTING WALL & FLOOR AS REQ'D FOR NEW FINISHES TO MATCH EXISTING.
5 REMOVE EXISTING WATERCLOSET - SEE PLUMBING. PATCH, REPAIR ANDPREP EXISTNG WALL & FLOOR AS REQ'D FOR NEW FINISHES TO MATCHEXISTING.
6 REMOVE EXISTING CMU WALL (AND DOOR IF APPLICABLE) AS INDICATEDFOR NEW OPENING (CUT AT EX'G CMU HEAD JTS). PATCH, REPAIR ANDPREP EXISTNG WALL & FLOOR AS REQ'D FOR NEW FINISHES TO MATCHEXISTING.
7 REMOVE EXISTING DOOR ONLY; SEE DOOR SCHEDULE FOR NEW DOORREPLACEMENT
8 REMOVE EXISTING DOOR, FRAME, ETC. COORDINATE WITH NEWCONSTRUCTION FOR REPAIR OR OTHER MODIFICATION AND/OR REMOVAL.PREP AS NECESSARY.
9 REMOVE EXISTING CABINETS AND CASEWORK (INCLUDING ALL BRACES,BRACKETS, BLOCKING , ETC) AND PREP TO RECIEVE NEW WORK/NEWCONSTRUCTION. SEE MEP & STRUCTURAL DOCUMENTS FOR ADDITIONALSCOPE OF WORK AND REQUIREMENTS
10 REMOVE EXISTING TOILET STALLS, PARTITIONS, DOORS, BRACES,BRACKETS AND PREP AREA TO RECEIVE NEW CONSTRUCTION
11 REMOVE AND REPLACE EXISTING COLUMN SHOWER CURTAIN AND RODAPPARATUS HARDWARE AND DIVIDERS WITH NEW TO MATCH ANDCOMPATIBLE WITH EXISTING COLUMN SHOWER
12 REMOVE EXISTING CEILING COMPLETELY (CEILING GRID AND TILE,SUPPORT WIRES, ETC)
1
KEY PLAN
1/8" = 1'-0"1
AREAS 11D LOCKER ROOM DEMOLITION PLANS
PLAN NORTH
GENERAL DEMOLITION NOTES
Revision No. Description Date
1 ADDEND #1 10-3-18
1
1
1
10-3-2018
1. ALL DIMENSIONS INDICATED IN CONTRACT DOCUMENTS ARE FROM FACE OF STUD TO FACE OF STUD FOR INTERIOR PARTITIONS, FACE OF EXISTING STRUCTURE OR FINISH, FACE OF CONCRETE OR BLOCK, OR TO STRUCTURAL LINE, EXCEPT AS NOTED OTHERWISE. EXTERIOR DIMENSIONS ARE TO FACE OF CMU. DIMENSIONS OF EXISTING STRUCTURE, ETC. ARE ± AND SHOULD BE FIELD VERIFIED PRIOR TO COMMENCEMENT OF WORK AND ARCHITECT NOTIFIED OF ANY DISCREPANCIES.
2. SEE GENERAL NOTES ON G100 FOR WORK PERTAINING TO EXISTING CONDITIONS, DIMENSION, ETC.
3. REFER TO DEMOLITION DRAWINGS FOR ADDITIONAL INFORMATION.4. EXISTING LADDER FROM FINISH FLOOR OF ROOM ABOVE EQUIPMENT
REPAIR 402A TO ROOF IS TO REMAIN AS IS.
41' - 3"
29
' -
4"
9
9BUSINESS
109 ENGLISH
107STORAGE
107A
STORAGE
109A
CORRIDOR
920
13
3
14
131313
MB1
TB1
TB1
DRAMA
204
11 12
200
EXIST
8' - 4"
EXIST
DRAMA
STORAGE
205
A7001
131313
TB1
EXISTING MB TO REMAIN. PROTECT DURING CONSTR.
1 2
COT AREA
NEW SMALL FRIG.
4' - 9 3/8" 3' - 0"
ALT ROLL-IN TYPE SHOWER W/O SEAT
4' -
4 7
/8"
8' - 1 5/8"
4' - 11 3/4"
(F-F
OF
GY
P B
D)
4' -
0"
1' -
6 5
/8"
4' -
5 1
/8"
1' -
3"
7' -
8"
7' - 3"
4' -
0"
2' -
10"
1
23
4
5
6
7
8
99
SC
104A
GB1
10 10
P8
P8
P8
104EXIST
NURSE
104
STOR
104B
TOILET
104AST
CAFETERIA/
MULTI-PURPOSE
102
GB1
PTD
M1
SD
P8
P9
13
13
1313
GB2 GB3
21 22
212121
1
1
2
A251
400G
400F
EXIST
400E
400D
1' - 0"
14' - 0"
7' - 9"
6' - 0"
9"
7' - 0"
16' - 1" 11' - 10 5/8" 14' - 0" 14' - 10 1/4" 4' - 0"
1' - 4 1/4"
8' - 8 1/4"
A700
7
A70
0
9
A700
8
BG5
BG5
400A-1400A
400C
7BB
7-H
7-J
7-1
7-1
KITCHEN
400
DISH RETURN
400B
TOILET
400D
OFFICE
400E
RECEIVING
400G
DRY FOOD
400H
LAUNDRY
400F
CONCESSIONS
400C
CAFETERIA/
MULTI-PURPOSE
102
A452 10
A452
9
A452
8
5' -
4"
1' -
6 1
/2"
16
' - 1
"1
2' -
10"
P4
P1
P1
P1
P8
P1
34
' - 3
1/8
"
6' -
0"
FREEZER COOLER
1313
13
13
13
P8P8
P9P8
11
A452
SCRAMBLE
AREA
400A
P1
P1
P1
P1
P1
P8
P8
P8 P8
P1
P1
P8
P1
P1
4' -
0"
3' -
4"
2' -
8"
15
P4
16
FE-3
17
9
10
7/8
"
4' -
4"4' -
3"
13' - 10 13/32" 6' - 8 9/16"
2' -
0"
8' -
0"
8' -
1 1
/2"
135.0
0°
FE-3
A104
3
400B
FE-3
16
20202020
11D
11D
7B 7C
7D
11C
7A
8
10
11A
10D
11B
11A
1' - 3 5/8" 8' - 9 9/16"
1' -
3"
5' -
3"
1' -
6 3
/8"
8' -
0 3
/8"
SD
M3
PTD
GB1
TPD
TPD
GB1
400E
TOILET
400D
2
A251
111' - 8"
STORAGE
2000
P1
P1
P918
2nd FLR
1919
JAMES SAPPMICHAEL
NUMBER
A-5051
ST
ATE
OF M I SSO
UR
I
RE
GI S
T E R E D A RCH
I TE
CT
DateProject No. Drawn
Drawing No.
© Copyright 2018 - Sapp Design Associates, Architects, P.C.
Sapp Design Associates Architects, P.C.Missouri State Certificate of Authority #000607
Architect of Record
Michael James Sapp, Architect MO A-5051
In the event the client consents to, allows, authorizes or approves of changes to any plans, specifications or other construction documents, and these changes are not approved in writing by the design professional, the client recognizes that such changes and the results thereof are not the responsibility of the design professional. Therefore, the client agrees to release the design professional from any liability arising from the construction, use or result of such changes. In addition, the client agrees to the fullest extent permitted by law, to indemnify and hold the design professional harmless from any damage, liability or cost (including reasonable attorney's fees and costs of defense) arising from such changes.
The personal seal of the registered Architect or Engineer shall be the legal equivalent of his signature whenever & wherever used, and the owner of the seal shall authenticate this sheet and the specification sections pertaining to this sheet. Responsibility shall be disclaimed for all other plans, specifications, estimates, reports or other documents or instruments relating to or intended to be used for any part or parts of the architectural project.
SPECIAL NOTICES
Author09-06-201817-0923
A104AREA 11A, 11B AND 11C/7D
FLOOR PLANS
HIG
H S
CH
OO
L6
36 M
O-4
2O
SA
GE
BE
AC
H, M
ISS
OU
RI 65065
CA
MD
EN
CO
UN
TY
RE
NO
VA
TIO
NS
AN
D A
DD
ITIO
NS
TO
SC
HO
OL O
F T
HE
OS
AG
E R
-II
GENERAL NOTES
KEYNOTES
1 EXISTING BASE & UPPER CABINET TO BE REMOVED AND RETURNED TOOWNER. PATCH, REPAIR AND PREP EXISTING WALL & FLOOR AS REQ'D FORNEW FINISHES TO MATCH EXISTING.
2 CUT NEW NARROW LITE OPENING INTO EXIST'G SC WOOD DOOR.
3 EXISTING DOOR TO REMAIN
4 EXISTING ELECTRICAL PANELS TO REMAIN
5 RELOCATE EXISTING ELECTRICAL PANELS - SEE ELECTRICAL
6 NEW OPENING IN EXISTING CMU WALL. PATCH, REPAIR AND PREP EXIST'GWALL & FLOOR AS REQ'D FOR NEW FINISHES TO MATCH EXISTING. EXACTLOCATION OF OPENING DEPENDS ON ELECT PANEL RELOCATION
7 EXISTING BASE AND UPPER CABINETS TO REMAIN
8 EQUIPMENT - BY OWNER
9 NEW STAFF LOCKERS; 12" X 12" 2-TIER LOCKERS TYPE 2, SEE SPEC.PROVIDE WITH SLOPED TOPS AND FILLER PANELS AT CORNER/ENDS. SEE.SPECS/SCHEDULE
10 NEW CUBICAL CURTAINS & CEILING MTD TRACKS - SEE SPECS
11 REMOVE EXISTING DOOR AND HM FRAME
12 REMOVE EXISTING CMU WALL FOR NEW DOOR & FRAME (OR WINDOW)INSTALLATION. PATCH, REPAIR AND PREP EXISTING WALL & FLOOR ASREQ'D FOR NEW FINISHES TO MATCH EXISTING.
13 EXISTING MAS. WALL TO REMAIN; PROTECT DURING CONSTRUCTION
14 REMOVE EXISTING STAGE; PATCH, REPAIR EXISTING FLOORING TO MATCHEXISTING
15 REMOVE EXISTING CMU FOR NEW PASS THRU OPENING; OPENING TO BE32"W. X 16" H. WITH SILL 40" A.F.F.
16 ADD NEW COLUMN & PROTECT EXISTING COLUMN; SEE STRUCTURAL
17 REMOVE EXISTING DOOR AND FRAME AND INFILL EXISTING OPENING WITHCMU - PAINT. TOOTH NEW CMU INTO EXISTING CMU WALL FOR SEAMLESSTRANSITION.
18 REMOVE EXISTING GUARDRAIL THIS SIDE OF WALL PERMANENTLY ANDHANDRAIL AS REQUIRED TO INSTALL NEW GYP BD AND METAL STUD WALL.
19 NEW COLUMN & BEAM BELOW; SEE STRUCTURAL
20 FLOAT AND LEVEL EXISTING FLOOR SLAB WITH LEVELING AND PATCHINGCOMPOUND AS REQ'D AFTER REMOVAL OF EXISTING QUARRY TILE. MATCHLEVEL OF EXISTING ADJACENT REMAINING TERRAZZO FLOOR INPREPARATION FOR NEW QUARRY TILE FLOORING INSTALLATION
21 REMOVE EXISTING CEILING COMPLETELY (CEILING GRID AND TILE,SUPPORT WIRES, ETC)
22 REMOVE EXISTING FLOOR FINISHES AND PREP FOR NEW FINISHINSTALLATION
1
KEY PLAN
1/8" = 1'-0"2 AREA 11A BUSINESS RENO PLAN
1/8" = 1'-0"1 AREA 11A SPEECH DRAMA RENO PLAN
1/4" = 1'-0"4 AREA 11B NURSE RENO PLAN
1/8" = 1'-0"5 AREA 11C KITCHEN FLOOR PLAN
PLAN NORTHPLAN NORTH
PLAN NORTH
PLAN NORTH
SEE 1/A106 FOR KITCHEN EQUIPMENT PLAN
1/4" = 1'-0"3 ENLARGED FLOOR PLAN
PLAN NORTH
1/8" = 1'-0"6 PARTIAL SECOND FLOOR PLAN
PLAN NORTH
Revision No. Description Date
1 ADDEND #1 10-3-18
NOTE:SEE EQUIPMENT SCHEDULE ON SHEET A106 FOR TAGGED EQUIPMENT.
NOTE:SEE PARTITION TYPES SCHEDULE ON SHEET A101 FOR PARTITION TYPES.
1
10-3-2018
1/4" / 1'-0"
3
A251
7B1 7B2
7BB
1
1
1/4
"/F
T1/4
"/F
T1/4
"/F
T1/4
"/F
T
1/4" / 1'-0"
6
77
TYP
7BA
10
10
12
2
22
3
A109
2
A250
2
A250
1
A250
10
A306
4
A301
1
A251
3
A301
2
A302
5
A301
2
A303
1
A303
7-A
7-B
7-C
7-D
7-E
7-F
7-G
7-H
7-J
7-107-7
7-6
7-27-1
2
3
3
4
5
4
4
4
1/4
" / 1
'-0
"
1/ 4
" / 1'- 0
"
1/4
" / 1
'-0
"
3/8" / 1'-0"1/2" / 1'-0"
1/2" / 1'-0"
1/4
" / 1
'-0
"1
/4"
/ 1
'-0
"
3/8" / 1'-0"
3/8" / 1'-0"3
/8"
/ 1'-0"
1/2" / 1'-0"
1/2
" / 1
'-0
"
1/4" / 1'-0" 1/2
" / 1
'-0
"
1/4" / 1'-0"
1/2
" / 1
'-0
"
1/4" / 1'-0" 1/2
" / 1
'-0
"
1/4" / 1'-0"
1/2
" / 1
'-0
"
1/4" / 1'-0" 1/2
" / 1
'-0
"1
/2"
/ 1
'-0
" 1/4" / 1'-0"1/4" / 1'-0" 1
/2"
/ 1
'-0
"1
/2"
/ 1
'-0
"
1/4" / 1'-0" 1/4" / 1'-0"
1/4" / 1'-0"
1/2
" / 1
'-0
"
3/8" / 1'-0"
3/8" / 1'-0"1/2" / 1'-0"
1/4
" / 1
'-0
"
3/8" / 1'-0"
1/2
" / 1'-0"
1/2" / 1'-0"
1/4
" / 1
'-0
"
1/4" / 1'-0"
1/4
" / 1
'-0
"
1/4
" / 1
'-0
"
6
3 3
67
4
7
EXISTING PARAPET TO REMAIN
EXISTING PARAPETTO REMAIN
EXISTING ROOF TO REMAIN
EXISTING PARAPET TO REMAIN
EXISTING ROOF TO REMAIN
3
A303
8
9
7BA 7BA
1/4" / 1'-0"
3
A300
10
10
10
11
2
2
2
22
2
2
22
2
2
13
14
14
14
1414
44
5
4
1010101010
22
2
2
2
2
2
2
15
11D
11D
7B7C
7D
11C
7A
8
10
11A
10D
11B
11A
7B1
1' -
6"
X 1
6"
W.
8"
H.
2"
10"
6"
1"
X 1'-6" W.
1' - 0" D.
PREFIN METAL SCUPPER AND CONDUCTOR HEAD
SEALANT
LAP AND SEAL TO METAL AS PER ROOFING MANUF RECOMMENDATIONS
5" X 5" PREFIN DOWNSPOUT
JAMES SAPPMICHAEL
NUMBER
A-5051
ST
ATE
OF M I SSO
UR
I
RE
GI S
T E R E D A RCH
I TE
CT
DateProject No. Drawn
Drawing No.
© Copyright 2018 - Sapp Design Associates, Architects, P.C.
Sapp Design Associates Architects, P.C.Missouri State Certificate of Authority #000607
Architect of Record
Michael James Sapp, Architect MO A-5051
In the event the client consents to, allows, authorizes or approves of changes to any plans, specifications or other construction documents, and these changes are not approved in writing by the design professional, the client recognizes that such changes and the results thereof are not the responsibility of the design professional. Therefore, the client agrees to release the design professional from any liability arising from the construction, use or result of such changes. In addition, the client agrees to the fullest extent permitted by law, to indemnify and hold the design professional harmless from any damage, liability or cost (including reasonable attorney's fees and costs of defense) arising from such changes.
The personal seal of the registered Architect or Engineer shall be the legal equivalent of his signature whenever & wherever used, and the owner of the seal shall authenticate this sheet and the specification sections pertaining to this sheet. Responsibility shall be disclaimed for all other plans, specifications, estimates, reports or other documents or instruments relating to or intended to be used for any part or parts of the architectural project.
SPECIAL NOTICES
Author09-06-201817-0923
A109ROOF PLAN
HIG
H S
CH
OO
L6
36 M
O-4
2O
SA
GE
BE
AC
H, M
ISS
OU
RI 65065
CA
MD
EN
CO
UN
TY
RE
NO
VA
TIO
NS
AN
D A
DD
ITIO
NS
TO
SC
HO
OL O
F T
HE
OS
AG
E R
-II
1 PREFINISHED LEADER HEAD WITH 5"X5" PREFINISHED DOWNSPOUTS INTOSTORMWATER DRAIN PIPE SYSTEM
2 RTU, EXHAUST FAN, ROOF VENT, ETC - SEE MECHANICAL
3 ROOF DRAIN - SEE PLUMBING (TYPICAL AS SHOWN/INDICATED)
4 PREFINISHED METAL PARAPET CAP OR ROOF EDGE TRIM
5 PREFINISHED SEAMLESS SHEET METAL GUTTER
6 ROOF SYSTEM OVER TAPERED INSUL - SEE SPEC
7 ROOFING SYSTEM ON RIGID INSUL - SEE SPEC
8 ROOF HATCH WITH CRICKET ON HIGH SIDE
9 NEW CHAIN LINK FENCE
10 Existing downspout to remain, cut off at new roof and provide perforated metal splashpan.
11 RETAINING WALL BELOW (AT GRADE LEVEL)
12 WALK PAD - SEE SPEC
13 SCREEN WALL BELOW
14 WALK PADS, SEE SPECIFICATIONS
15
ROOF PLAN KEYNOTES1
1/8" = 1'-0"1
ROOF PLAN - 7B
PLAN NORTH
KEY PLAN
1/8" = 1'-0"2
ROOF PLAN - 7A
PLAN NORTH
Revision No. Description Date
1 ADDEND #1 10-3-18
1 1/2" = 1'-0"3
SCUPPER DETAIL
1
10-3-2018
FINISH FLOORELEV VARIES -SEE PLANS
FSC WOOD/
HOLLOW METAL
FGSC WOOD/GLASS
GL-1
OHCSTAINLESS STEEL
(OVERHEAD COILING)
AL2ALUM & GLASS
NOTE: SOME OVERHEAD COILING DOORS EXTEND TO THE FLOOR OTHERS TO THE COUNTERTOP
OHS-1INSULATED/STEEL
(OVERHEAD SECTIONAL)
FINISH FLOORELEV VARIES -SEE PLANS
NOTE: FOR LOUVER LOCATIONS - SEE DOOR SCHEDULE
NSC WOOD
GL-1
1 2HOLLOW METAL HOLLOW METAL
FINISH FLOORELEV VARIES -SEE PLANS
3HOLLOW METAL
GL-1
SE
E S
CH
ED
ULE
4"
2"
SCHED
SEE 2' - 0" 2"
3' -
4"
4' -
0"
4HOLLOW METAL
SE
E S
CH
ED
ULE
4"
SCHED
SEE 3' - 0"
SE
E S
CH
ED
ULE
4"
2"
SCHED
SEE 2"
SE
E S
CH
ED
ULE
2"
2"
SCHED
SEE 2"
MIN
18"
12" MIN
PULL SIDE
PUSH SIDE
GL-1 = 1/4" FULLY TEMPERED GLASS GL-2 = 1" INSUL SAFETY GLASS (TINTED)GL-3 = 3/8" FULLY TEMPERED GLASS
1. ALL GLAZING FOR EXTERIOR FRAMES & DOORS SHALL BE INSULATED.
2. PATCH, REPAIR AND PREP EXISTING WALL AND FLOOR AS REQ'D FOR NEW FINISHES TO MATCH EXISTING.
3. REMOVE & REPLACE EXISTING DOOR. PAINT EXISTING DOOR FRAME.
4. CUT IN NEW 5" X 20" NARROW LITE INTO EXISTING SC WOOD DOOR. INSTALL NEW GLAZING GL1 IN NEW LIGHT OPENING
AL = ALUM DOOR OR FRAMEFRP = FIBERGLASS REINFORCED POLYESTERHM = HOLLOW METAL DOOR OR FRAMEWD = SOLID CORE WOOD DOOR OR FRAME
F1 = PAINTEDF2 = STAINEDF3 = PREFINISHED - CLEAN & PROTECT
JAMES SAPPMICHAEL
NUMBER
A-5051
ST
ATE
OF M I SSO
UR
I
RE
GI S
T E R E D A RCH
I TE
CT
DateProject No. Drawn
Drawing No.
© Copyright 2018 - Sapp Design Associates, Architects, P.C.
Sapp Design Associates Architects, P.C.Missouri State Certificate of Authority #000607
Architect of Record
Michael James Sapp, Architect MO A-5051
In the event the client consents to, allows, authorizes or approves of changes to any plans, specifications or other construction documents, and these changes are not approved in writing by the design professional, the client recognizes that such changes and the results thereof are not the responsibility of the design professional. Therefore, the client agrees to release the design professional from any liability arising from the construction, use or result of such changes. In addition, the client agrees to the fullest extent permitted by law, to indemnify and hold the design professional harmless from any damage, liability or cost (including reasonable attorney's fees and costs of defense) arising from such changes.
The personal seal of the registered Architect or Engineer shall be the legal equivalent of his signature whenever & wherever used, and the owner of the seal shall authenticate this sheet and the specification sections pertaining to this sheet. Responsibility shall be disclaimed for all other plans, specifications, estimates, reports or other documents or instruments relating to or intended to be used for any part or parts of the architectural project.
SPECIAL NOTICES
Author09-06-201817-0923
A400DOOR SCHEDULE &
ELEVATIONS
HIG
H S
CH
OO
L6
36 M
O-4
2O
SA
GE
BE
AC
H, M
ISS
OU
RI 65065
CA
MD
EN
CO
UN
TY
RE
NO
VA
TIO
NS
AN
D A
DD
ITIO
NS
TO
SC
HO
OL O
F T
HE
OS
AG
E R
-II
DOOR NO.
DOOR FRAME
RATING COMMENTSCONFIG WIDTH HEIGHT THICK ELEV MATL ELEV MATL
DETAIL
HEAD JAMB SILL
104 SINGLE 3' - 0" 7' - 0" 1 3/4" N EXIST EXISTING EXISTING N.A. N.A. N.A. 20 MIN SEE GENERAL NOTE 4 THIS SHEET
104A SINGLE 3' - 0" 7' - 0" 1 3/4" F WD/F2 1 HM/F1 8/A402 9/A402 N.A.
200 PAIR 8' - 0" 8' - 0" 1 3/4" F WD/F2 1 HM/F1 3/A402 4/A402 N.A. 20 MIN SEE GENERAL NOTE 2 THIS DWG
206A SINGLE 4' - 0" 8' - 9" 1 3/4" F WD/F2 2 HM/F1 8/A402 9/A402 N.A.
206B SINGLE 3' - 0" 7' - 0" 1 3/4" F WD/F2 1 HM/F1 10/A402 11/A402 N.A.
206C SINGLE 4' - 0" 8' - 9" 1 3/4" F WD/F2 2 HM/F1 8/A402 9/A402 N.A.
206D PAIR 8' - 0" 8' - 0" 1 3/4" F WD/F2 1 HM/F1 3/A402 4/A402 N.A. 1 1/2 HR SEE GENERAL NOTE 2 THIS DWG
206E 6' - 2 1/2" 6' - 2 7/8" SS/F3 N.A. SS/F3 5/A402 6/A402 7/A402
206F 12' - 10 1/2" 6' - 2 7/8" SS/F3 N.A. SS/F3 5/A402 6/A402 7/A402
207 PAIR 7' - 0" 7' - 0" 1 3/4" F WD/F2 1 HM/F1 3/A402 4/A402 N.A. 1 1/2 HR SEE GENERAL NOTE 2 THIS DWG
400A 14' - 0" 8' - 8" Operator : OHC SS/F3 N.A. SS/F3 20/A402 1/A403 N.A. 1 1/2 HR DOOR ELEV. OHC
400A-1 14' - 0" 8' - 8" Operator : OHC SS/F3 N.A. SS/F3 20/A402 1/A403 N.A. 1 1/2 HR DOOR ELEV. OHC
400B 6' - 0" 5' - 8" Operator : OHC SS/F3 N.A. SS/F3 20/A402 1/A403 1 1/2 HR DOOR ELEV. OHC
400C 8' - 0" 4' - 9" Operator : OHC SS/F3 N.A. SS/F3 20/A402 1/A403 1 1/2 HR DOOR ELEV. OHC
400D SINGLE 3' - 0" 7' - 0" 1 3/4" F WD/F2 1 HM/F1 8/A402 9/A402 N.A.
400E SINGLE 3' - 0" 7' - 0" 1 3/4" F WD/F2 1 HM/F1 1/A402 2/A402 N.A.
400F SINGLE 3' - 0" 7' - 0" 1 3/4" F WD/F2 1 HM/F1 8/A402 16/A402 N.A.
400G SINGLE 4' - 0" 7' - 0" 1 3/4" F WD/F2 1 HM/F1 1/A402 2/A402 N.A. 1 1/2 HR
401C PAIR 6' - 0" 7' - 0" 1 3/4" F WD/F2 1 HM/F1 3/A402 4/A402 N.A. 1 1/2 HR NEW DOOR AND FRAME IN EXISTING MAS. OPENING
402 SINGLE 4' - 0" 7' - 0" 1 3/4" F WD/F2 1 HM/F1 1/A402 2/A402 N.A. 1 1/2 HR PROVIDE SOUND SEALS-SEE HARDWARE SCHEDULE
402-1 SINGLE 4' - 0" 7' - 0" 1 3/4" F WD/F2 1 HM/F1 1/A402 2/A402 N.A. 1 1/2 HR PROVIDE SOUND SEALS-SEE HARDWARE SCHEDULE
402A SINGLE 3' - 0" 7' - 0" 1 3/4" F WD/F2 N.A. EXISTING N.A. N.A. N.A. SEE GENERAL NOTE 3 THIS DWG
402B PAIR 6' - 0" 7' - 0" 1 3/4" F WD/F2 1 HM/F1 10/A402 11/A402 N.A. PROVIDE SOUND SEALS-SEE HARDWARE SCHEDULE
402C PAIR 6' - 0" 7' - 0" 1 3/4" F WD/F2 1 HM/F1 3/A402 4/A402 N.A. SEE GENERAL NOTE 2 THIS DWG
402D SINGLE 4' - 0" 7' - 0" 1 3/4" F WD/F2 1 HM/F1 1/A402 2/A402 N.A.
402E PAIR 7' - 0" 8' - 4" 1 3/4" F IHM/F1 1 HM/F1 12/A402 13/A402 14/A402
402F SINGLE 3' - 0" 7' - 0" 1 3/4" F WD/F2 1 HM/F1 8/A402 9/A402 N.A.
402G SINGLE 3' - 0" 7' - 0" 1 3/4" F WD/F2 1 HM/F1 8/A402 9/A402 N.A.
402H SINGLE 3' - 0" 7' - 0" 1 3/4" F WD/F2 1 HM/F1 3/A402 4/A402 N.A.
402J SINGLE 3' - 0" 7' - 0" 1 3/4" F WD/F2 1 HM/F1 8/A402 9/A402 N.A.
402K SINGLE 3' - 0" 7' - 0" 1 3/4" F WD/F2 EXISTING EXISTING N.A. N.A. N.A. SEE GENERAL NOTE 3 THIS DWG
402L PAIR 6' - 0" 7' - 0" 1 3/4" F WD/F2 1 HM/F1 3/A402 4/A402 N.A.
402M PAIR 6' - 0" 7' - 0" 1 3/4" F WD/F2 1 HM/F1 3/A402 4/A402 N.A. SEE GENERAL NOTE 2 THIS DWG
701 SINGLE 3' - 0" 7' - 2" 1 3/4" F WD/F2 EXISTING EXISTING N.A. N.A. N.A. 1 1/2 HR SEE GENERAL NOTE 3 THIS DWG
701A SINGLE 3' - 0" 7' - 0" 1 3/4" F WD/F2 1 HM/F1 3/A402 4/A402 N.A. 1 1/2 HR SEE GENERAL NOTE 2 THIS DWG
701B SINGLE 3' - 0" 7' - 0" 1 3/4" F WD/F2 EXISTING EXISTING N.A. N.A. N.A. SEE GENERAL NOTE 3 THIS DWG
701C SINGLE 3' - 0" 7' - 0" 1 3/4" F WD/F2 EXISTING EXISTING N.A. N.A. N.A. SEE GENERAL NOTE 3 THIS DWG
701D SINGLE 3' - 0" 7' - 0" 1 3/4" F WD/F2 EXISTING EXISTING N.A. N.A. N.A. SEE GENERAL NOTE 3 THIS DWG
701E SINGLE 3' - 0" 7' - 0" 1 3/4" F WD/F2 EXISTING EXISTING N.A. N.A. N.A. SEE GENERAL NOTE 3 THIS DWG
701F SINGLE 3' - 0" 7' - 0" 1 3/4" F WD/F2 EXISTING EXISTING N.A. N.A. N.A. SEE GENERAL NOTE 3 THIS DWG
701G SINGLE 3' - 0" 7' - 0" 1 3/4" F WD/F2 EXISTING EXISTING N.A. N.A. N.A. SEE GENERAL NOTE 3 THIS DWG
701H SINGLE 3' - 0" 7' - 2" 1 3/4" F WD/F2 EXISTING EXISTING N.A. N.A. N.A. 1 1/2 HR SEE GENERAL NOTE 3 THIS DWG
701J SINGLE 3' - 0" 7' - 0" 1 3/4" F WD/F2 3 HM/F1 8/A402 9/A402 N.A.
701K SINGLE 3' - 0" 7' - 0" 1 3/4" F WD/F2 1 HM/F1 1/A402 2/A402 N.A.
702 SINGLE 3' - 0" 7' - 2" 1 3/4" F WD/F2 EXISTING EXISTING N.A. N.A. N.A. 1 1/2 HR SEE GENERAL NOTE 3 THIS DWG
702B SINGLE 3' - 0" 7' - 0" 1 3/4" F WD/F2 1 HM/F1 3/A402 4/A402 N.A. 1 1/2 HR SEE GENERAL NOTE 2 THIS DWG
702C SINGLE 2' - 8" 7' - 0" 1 3/4" F WD/F2 1 HM/F1 3/A402 4/A402 N.A. SEE GENERAL NOTE 2 THIS DWG
702D SINGLE 3' - 0" 7' - 0" 1 3/4" F WD/F2 1 HM/F1 3/A402 4/A402 N.A. SEE GENERAL NOTE 2 THIS DWG
702E SINGLE 3' - 0" 7' - 2" 1 3/4" F WD/F2 EXISTING EXISTING N.A. N.A. N.A. 1 1/2 HR SEE GENERAL NOTE 3 THIS DWG
702F SINGLE 3' - 0" 7' - 0" 1 3/4" F WD/F2 EXISTING EXISTING N.A. N.A. N.A. SEE GENERAL NOTE 3 THIS DWG
702G SINGLE 3' - 0" 7' - 0" 1 3/4" F WD/F2 EXISTING EXISTING N.A. N.A. N.A. SEE GENERAL NOTE 3 THIS DWG
702H SINGLE 3' - 0" 7' - 0" 1 3/4" F WD/F2 1 HM/F1 3/A402 4/A402 N.A.
702L SINGLE 3' - 0" 7' - 0" 1 3/4" F WD/F2 1 HM/F1 1/A402 2/A402 N.A. 1 1/2 HR
800 PAIR 6' - 0" 7' - 0" AL2 AL/F3 SF15 AL/F3 2/A302 8/A404 2/A302
800A PAIR 6' - 0" 7' - 0" AL2 AL/F3 SF6 AL/F3 2/A302 4/A404 2/A302
801 SINGLE 3' - 0" 7' - 0" 1 3/4" F WD/F2 1 HM/F1 8/A402 2/A402 N.A.
801A PAIR 6' - 0" 7' - 0" 1 3/4" F WD/F2 1 HM/F1 1/A402 2/A402 N.A.
801B SINGLE 3' - 0" 7' - 0" 1 3/4" F WD/F2 1 HM/F1 8/A402 9/A402 N.A.
801C SINGLE 3' - 0" 7' - 0" 1 3/4" FG WD/F2 1 HM/F1 1/A402 2/A402 N.A.
802 SINGLE 3' - 6" 7' - 0" 1 3/4" F WD/F2 1 HM/F1 8/A402 2/A402 N.A.
802A SINGLE 3' - 6" 7' - 0" 1 3/4" F WD/F2 1 HM/F1 8/A402 9/A402 N.A. PROVIDE 18"X18" LOUVER IN DOOR
802B SINGLE 3' - 0" 7' - 0" 1 3/4" FG WD/F2 1 HM/F1 8/A402 9/A402 N.A.
803 SINGLE 3' - 0" 7' - 0" 1 3/4" F WD/F2 1 HM/F1 8/A402 2/A402 N.A.
803A SINGLE 3' - 0" 7' - 0" 1 3/4" F WD/F2 1 HM/F1 8/A402 9/A402 N.A.
803B SINGLE 3' - 0" 7' - 0" 1 3/4" F WD/F2 1 HM/F1 1/A402 2/A402 N.A.
804 SINGLE 3' - 0" 7' - 0" 1 3/4" F WD/F2 1 HM/F1 1/A402 2/A402 N.A.
804A SINGLE 3' - 0" 7' - 0" 1 3/4" F WD/F2 1 HM/F1 8/A402 9/A402 N.A.
804B SINGLE 3' - 0" 7' - 0" 1 3/4" F WD/F2 1 HM/F1 1/A402 2/A402 N.A.
805 SINGLE 3' - 0" 7' - 0" 1 3/4" F HM/F1 1 HM/F1 1/A402 2/A402 N.A.
805A SINGLE 3' - 0" 7' - 0" 1 3/4" F IHM/F1 1 HM/F1 17/A402 18/A402 19/A402
805B 12' - 0" 10' - 0" 1 1/2" N.A. N.A. N.A.
805C PAIR 7' - 0" 7' - 0" 1 3/4" F HM/F1 1 HM/F1 1/A402 2/A402 N.A. 1 1/2 HR
805D 12' - 0" 10' - 0" 1 1/2" N.A. N.A. N.A.
805E SINGLE 3' - 0" 7' - 0" 1 3/4" F WD/F2 1 HM/F1 1/A402 2/A402 N.A.
806 SINGLE 3' - 0" 7' - 0" 1 3/4" F IHM/F1 1 HM/F1 17/A402 18/A402 19/A402
806A 12' - 0" 10' - 0" 1 1/2" N.A. N.A.
806B 10' - 0" 10' - 0" 1 1/2" N.A. N.A.
806C SINGLE 3' - 0" 7' - 0" 1 3/4" F HM/F1 1 HM/F1 1/A402 2/A402 N.A.
806E PAIR 6' - 0" 7' - 0" 1 3/4" F HM/F1 1 HM/F1 1/A402 2/A402 N.A. PROVIDE 18"X18" LOUVER IN DOOR LEAVES
DOOR SCHEDULE
DOOR FRAME ELEVATIONS
DOOR ELEVATIONS
GENERAL NOTES REQUIRED DOOR CLEARANCES DOOR AND FRAME FINISH LEGEND GLAZING SCHEDULE
OHS-2
OHS-1
OHS-1
--
--
--
--
--
--
--
--
--
--
--
OHS-1--
OHS-2STEEL/GLASS
(OVERHEAD SECTIONAL)
Revision No. Description Date
1 ADDEND #1 10-3-18
1 1/2 HR
1 1/2 HR
1 1/2 HR
1 1/2 HR
1
10-3-2018
C1: 2x2 SUSPENDED ACOUSTICAL TILE CEILING (SQUARE EDGE) - SEE SPEC
C2: 2X2 PERFORATED (PLASTIC FINISH) - SEE SPEC
C3: PAINTED GYP BD HEADER, SOFFIT, BULKHEAD, OR CEILING
C4: NO CEILING - EXPOSED STRUCTURE PAINTED WHITE
C5: PYRAMIDAL ACOUSTICAL DIFFUSER PANELS - SEE SPEC
C6: BOTTOM OF STEEL BEAM LINTEL OR STEEL BEARING PLATE (PAINT)
ROOM NAME
101
C1/9'-0"
C3 10'-10"
ROOM NAME
ROOM NUMBER
CEILING HEIGHT
CEILING FINISH
CEILING HEIGHT
CEILING FINISH
NOTE:SEE BUILDING SECTIONS AND INTERIOR ELEVATIONS
1. COORDINATE REFLECTED CEILING PLAN WITH LIGHTING AND MECHANICAL PLANS FOR LIGHT FIXTURE PLACEMENT AND DIFFUSER PLACEMENT. IF DISCREPANCIES OCCUR CONTACT ARCHITECT FOR RESOLUTION. REFER TO FIRE PROTECTION DRAWINGS FOR SPRINKLER HEAD LOCATIONS. SPRINKLER HEADS SHALL BE LOCATED A MINIMUM OF 6" FROM CEILING GRID. COORDINATE LOCATIONS WITH LIGHTS AND DIFFUSERS - LIGHT FIXTURE LOCATION SHALL PREVAIL.
2. DRAWINGS ARE NOT TO BE SCALED. DIMENSIONAL DATA SHALL BE OBTAINED FROM WRITTEN INFORMATION ONLY. VERIFY ALL DIMENSIONS BEFORE PROCEEDING, ANY DIMENSIONAL DEVIATION FROM THAT SHOWN ON THE DRAWINGS, WHICH MAY AFFECT INTENT OF DESIGN OR PROPER INCORPORATION OF ELEMENTS, SHALL BE BROUGHT TO THE ARCHITECTS ATTENTION PROMPTLY AND RESOLUTION OBTAINED BEFORE PROCEEDING.
3. ALL DIMENSIONS INDICATED IN CONTRACT DOCUMENTS ARE FROM FACE OF STUD TO FACE OF STUD FOR INTERIOR PARTITIONS, FACE OF EXISTING STRUCTURE OR FINISH, FACE OF CONCRETE OR BLOCK, OR TO STRUCTURAL LINE, EXCEPT AS NOTED OTHERWISE. EXTERIOR DIMENSIONS ARE TO FACE OF BRICK OR FACE OF EIFS. DIMENSIONS OF EXISTING STRUCTURE, ETC. ARE ± AND SHOULD BE FIELD VERIFIED PRIOR TO COMMENCEMENT OF WORK AND ARCHITECT NOTIFIED OF ANY DISCREPANCIES. PROVIDE SOLID BLOCKING AS REQUIRED TO INSTALL EQUIPMENT, MILLWORK, ETC.
4. CONTRACTOR SHALL COORDINATE ALL MECHANICAL, ELECT. & PLUMBING WORK AND PROVIDE ALL NECESSARY CONSTRUCTION TO FACILITATE SAID WORK INCLUDING, BUT NOT LIMITED TO ROUGH OPENINGS, EQUIPMENT SUPPORTS, BACKING AND COORDINATION OF FINISH WORK, WHETHER OR NOT SPECIFICALLY INDICATED ON CONTRACT DOCUMENTS.
2'-0" x 4'-0" LAY-IN LIGHT FIXTURE (SEE ELECTRICAL PLANS)
2'-0" x 2'-0" LAY-IN LIGHT FIXTURE (SEE ELECTRICAL PLANS)
RECESSED CAN LIGHT FIXTURE (SEE ELECTRICAL PLANS)
4'-0" OR 8'-0" PENDANT OR SURF MTD. LIGHT FIXTURE (SEE ELECTRICAL PLANS)
SUPPLY DIFFUSER (SEE MECHANICAL PLANS)
RETURN AIR GRILLE (SEE MECHANICAL PLANS)
2'-0" x 4'-0" LAY-IN LIGHT FIXTURE (SEE ELECTRICAL PLANS)
4'-0" OR 8'-0" RECESSED LIGHT FIXTURE (SEE ELECTRICAL PLANS)
EXISTING GIRLS
PE LOCKERS
702K
C2/9'-0"
COACHES
OFFICE
702H
C1/9-0"
EXIST TLT
702J
C2/9'-0"
EXIST SHWR
702L
C2/9'-0"
HALL
702M
C2/9'-0"
PE STOR
702S
COACH OFFICE
702Q
GIRLS VARSITY
LOCKER ROOM
702T
C2/9'-0"
EXIST TLT
702G
C2/9'-0"
EXIST SHWR
702F
C2/9'-0"
EXIST DRYING
702E
C2/9'-0"
MAKEUP AREA
702D
C2/9'-0"
GIRLS PE
LOCKER ROOM
702
C2/9'-0"
REFS
702B
C1/9'-0"
TLT
702C
EXIST
LAUNDRY
701A
C4
COACHES
OFFICE
701B
C1/9'0"
EXISTING BOYS
LOCKER
701
C4
DRYING
701C
C4
EXIST SHWR
701D
C4
EXIST TLT
701E
C4
COACHES
OFFICE
701F
C1/9'-0"
EXIST TLT
701G
C4
EXISTING BOYS
LOCKER
701H
C4
EXIST SHWR
701J
C4
HALL
701K
C4
OFFICE
701R
TLT
701M
COACHES
OFFICE
701P
C2/9'-0"
STOR
701Q
C2/9'-0"
VARSITY
LOCKER RM
701N
C2/9'-0"
EXISTING GYM
700
J
702P
TLT
702U
C2/9'-0"
VEST
701S
C4
VEST
701U
C4
VEST
702N
C4
VEST
702A
C4
PE STORAGE
701L
TLT
702RJ
701T
NO WORK THIS AREA
1
1
1
1
1
1
1
1
1
1
2
2
2
1
2
2
1
2
1
11D
11D
7B 7C
7D
11C
7A
8
10
11A
10D
11B
11A
JAMES SAPPMICHAEL
NUMBER
A-5051
ST
ATE
OF M I SSO
UR
I
RE
GI S
T E R E D A RCH
I TE
CT
DateProject No. Drawn
Drawing No.
© Copyright 2018 - Sapp Design Associates, Architects, P.C.
Sapp Design Associates Architects, P.C.Missouri State Certificate of Authority #000607
Architect of Record
Michael James Sapp, Architect MO A-5051
In the event the client consents to, allows, authorizes or approves of changes to any plans, specifications or other construction documents, and these changes are not approved in writing by the design professional, the client recognizes that such changes and the results thereof are not the responsibility of the design professional. Therefore, the client agrees to release the design professional from any liability arising from the construction, use or result of such changes. In addition, the client agrees to the fullest extent permitted by law, to indemnify and hold the design professional harmless from any damage, liability or cost (including reasonable attorney's fees and costs of defense) arising from such changes.
The personal seal of the registered Architect or Engineer shall be the legal equivalent of his signature whenever & wherever used, and the owner of the seal shall authenticate this sheet and the specification sections pertaining to this sheet. Responsibility shall be disclaimed for all other plans, specifications, estimates, reports or other documents or instruments relating to or intended to be used for any part or parts of the architectural project.
SPECIAL NOTICES
Author09-06-201817-0923
A605AREA 11D/7B AND 11D/7C
REFLECTED CEILING PLANS
HIG
H S
CH
OO
L6
36 M
O-4
2O
SA
GE
BE
AC
H, M
ISS
OU
RI 65065
CA
MD
EN
CO
UN
TY
RE
NO
VA
TIO
NS
AN
D A
DD
ITIO
NS
TO
SC
HO
OL O
F T
HE
OS
AG
E R
-II
GENERAL NOTES
KEYNOTES
CEILING TYPES
REFLECTED CEILING LEGEND
1
1 EXIST EXPOSED CONC DECK CEILING - REPAINTED
2 EXISTING SUSPENDED ACOUST TILE CEILING
1/8" = 1'-0"1
AREA 11D/7B &11D/7C REFLECTED CEILING PLAN
KEY PLAN
PLAN NORTH
Revision No. Description Date
1 ADDEND #1 10-3-18
10-3-2018
24x60
24x60
24x48
0202 676704 04 04 04
A7012
A701
3
A7014
A700
17
A700
18
A700
19
A700
20
A701
1
A700
16
METAL LAB
806SC B1PT1
ART STOR
803B
VCT1B1PT1
WOOD STOR
805ASC B1PT1
WOOD LAB
805SC B1PT1
MU STOR
801A
VCT1B1PT1
KILN RM
802A
VCT1B1PT1
ART STORAGE
803A
VCT1B1PT1
ART 3D
802VCT1B1PT1
CORRIDOR
800VCT1B1PT1
ART 2D
803VCT1B1PT1
MULTI-USE LAB
801VCT1B1PT1
CAD LAB
804
VCT1B1PT1
OFFICE
804AVCT1B1PT1
A450
4
A4507
A450
6
A450 5
A45011
A450
8
A450
10
A450 9A45015
A450
12
A450 13
A450
14
A451
1
A451 2
A451
3
A4514
A450
16
A450 17
A450
18
A45019
A451
7
A4518
A451
5
A451 6
A450 3
A450
2
1
3
A303
A200
5
1
VCT2VCT3
PAINT HARD LID TOMATCH ACCENT PT3
PAINT HARD LID TO MATCH ACCENT PT3
PAINT HARD LIDTO MATCH ACCENT PT3
VCT4VCT4
VC
T4
1
2
1 11111
1
1
1
1
2
1. ALL GROUT JOINTS AT PORCELAIN TILE FLOORS AND WALLS TO BE 3mm AS RECOMMENDED BY MFR. APPLY GROUT SEALER TO ALL JOINTS. REFER TO MFR.'S INSTRUCTIONS FOR SETTING TIME, APPLICATION, AND TYPE OF PRODUCT RECOMMENDED.
2. AT TILE, PROVIDE EXPANSION JOINTS AS RECOMMENDED BY MANUFACTURER WITH SEALANT TO MATCH GROUT COLOR.
3. CONTRACTOR SHALL INQUIRE TO ARCHITECT FOR ANY AREAS WITH MISSING INFORMATION, OR WHERE FLOOR MATERIAL IS NOT INDICATED, PRIOR TO BIDDING. IN ALL CASES, ALL SPACES SHALL RECEIVE FINISHES, THE DEFAULT POSITION SHALL BE; SC / B2 / P1
4. THE FLOORING PATTERNS SHOWN ARE PARTIALLY DIAGRAMMATIC. CONTRACTOR MAY MAKE MINOR ADJUSTMENTS TO SIZES AND LOCATIONS OF ACCENT SQUARES, CIRCLES, AND PATTERN FEATURES TO MEET TILE GRID LINES, EXCEPT WHERE SPECIFICALLY ALIGNED OR DIMENSIONED. DRAWINGS MAY BE SCALED IF NECESSARY TO DETERMINE SIZE OR LOCATION OF FEATURES NOT DIMENSIONED. CONTRACTOR MAY SHIFT GRID LINES TO AVOID SMALL PIECES AT WALL EDGES, EXCEPT WHERE LARGER COMMON AREA PATTERNS EXTEND INTO ROOMS. PATTERNS OR ACCENT ELEMENTS INDICATED TO ALIGN WITH EDGES OR CENTER LINES MUST DO SO, AND MAY REQUIRE CUTTING INTO THE GRID PATTERN TO ACHIEVE THE LAYOUT
5. DRAWINGS MAY SHOW MATERIAL GRID LINES (JOINT LINES), IN SOME AREAS FOR CLARITY AND TO LOCATE ACCENT SQUARES ETC. OTHER AREAS MAY NOT SHOW GRID LINES, BUT ARE INTENDED TO BE SIMILAR AND GENERALLY BASED ON REGULAR GRID LAYOUTS
6. LARGE SCALE CHECKER PATTERNS, AND OTHER REPEATED PATTERNS MAY NOT SHOW COLOR NUMBER FOR EVERY PIECE OF THE PATTERN. CONTRACTOR SHALL COMPLETE THE PATTERN WITH APPROPRIATE COLOR(S) AS ESTABLISHED BY THE GIVEN PATTERN.
7. PROVIDE A TRANSITION STRIP AT ALL EDGES OF DISSIMILAR MATERIALS, E.G. TILE TO CARPET, TILE TO SEALED CONCRETE. COLOR AND PROFILE BY ARCHITECT. SEE COLOR SCHEDULE DOCUMENT, AND/OR SUBMIT PRODUCT SAMPLES FOR ARCHITECT'S SELECTION.
11D
11D
7B 7C
7D
11C
7A
8
10
11A
10D
11B
11A
CPT1
VCT1, VCT2, VCT3
MAROON VCT4
ROOM NAME & NUMBER - UPPER NUMBER INDICATES ROOM NUMBER
ROOM NAME
101CPT2B2P12
FLOOR FINISH
BASE
WALL FINISH
JAMES SAPPMICHAEL
NUMBER
A-5051
ST
ATE
OF M I SSO
UR
I
RE
GI S
T E R E D A RCH
I TE
CT
DateProject No. Drawn
Drawing No.
© Copyright 2018 - Sapp Design Associates, Architects, P.C.
Sapp Design Associates Architects, P.C.Missouri State Certificate of Authority #000607
Architect of Record
Michael James Sapp, Architect MO A-5051
In the event the client consents to, allows, authorizes or approves of changes to any plans, specifications or other construction documents, and these changes are not approved in writing by the design professional, the client recognizes that such changes and the results thereof are not the responsibility of the design professional. Therefore, the client agrees to release the design professional from any liability arising from the construction, use or result of such changes. In addition, the client agrees to the fullest extent permitted by law, to indemnify and hold the design professional harmless from any damage, liability or cost (including reasonable attorney's fees and costs of defense) arising from such changes.
The personal seal of the registered Architect or Engineer shall be the legal equivalent of his signature whenever & wherever used, and the owner of the seal shall authenticate this sheet and the specification sections pertaining to this sheet. Responsibility shall be disclaimed for all other plans, specifications, estimates, reports or other documents or instruments relating to or intended to be used for any part or parts of the architectural project.
SPECIAL NOTICES
Author09-06-201817-0923
A801AREA 7 FINISH PLAN
HIG
H S
CH
OO
L6
36 M
O-4
2O
SA
GE
BE
AC
H, M
ISS
OU
RI 65065
CA
MD
EN
CO
UN
TY
RE
NO
VA
TIO
NS
AN
D A
DD
ITIO
NS
TO
SC
HO
OL O
F T
HE
OS
AG
E R
-II
1/8" = 1'-0"1 AREA 7A TECH ARTS ADDITION FINISH FLOOR PLAN
PLAN NORTH
GENERAL NOTES
FINISH TYPESFINISH LEGEND
INSTALL ALL PRODUCTS PER MANUFACTURER'S WRITTEN INSTALLATION INSTRUCTIONS. REFER TO SPECIFICATIONS FOR ADDITIONAL INFORMATION.
CARPET
CPT1: (CARPET TILE) MANUFACTURER: J+J INVISION, PATTERN: INCOGNITO MODULAR 7069, COLOR: OPERATIVE 1837, SIZE: 24" X 24" TILE, INSTALLATION: MONOLITHICCPT2: (BROADLOOM) MANUFACTURER: SHAW, PATTERN: ESCAPE ULTRALOC 5A242, COLOR: PEAK 15506, SIZE: BROADLOOM
SC: SEALED CONCRETE
VCT
VCT1: (VINYL COMPOSITION TILE) MANUFACTURER: JOHNSONITE, STYLE: AZROCK COLLECTION/TEXTILE VCT, COLOR: V-280 RAW SILK, SIZE: 12" X 24" TILEVCT2: (VINYL COMPOSITION TILE) MANUFACTURER: JOHNSONITE, STYLE: AZROCK COLLECTION/TEXTILE VCT, COLOR: V-290 FUR, SIZE: 12" X 24" TILEVCT3: (VINYL COMPOSITION TILE) MANUFACTURER: JOHNSONITE, STYLE: AZROCK COLLECTION/TEXTILE VCT, COLOR: V-289 BERBER GREY, SIZE: 12" X 24" TILEVCT4: MATCH EXISTING MAROON VCT
WALL BASE
B1: (4" RUBBER WALL BASE) MANUFACTURER: JOHNSONITE, COLOR: #29 MOONROCK
PAINT
PT1-3: PAINT COLORS SHALL BE SHERWIN WILLIAMS, EGGSHELL U.N.O
PT1: FIELD COLOR (DISTRICT STANDARD) SW7015 REPOSE GRAYPT2: ACCENT COLOR (DISTRICT STANDARD) SW7014 EIDER WHITEPT3: ACCENT COLOR (DISTRICT STANDARD) CUSTOM TEX A&M AGGIE MAROON
VENEERED WOOD WALL PANELS
VWP: (VENEER WALL PANEL) MANUFACTURER: DOOGE VENEERS, SPECIES: FUMED RIFT WHITE EURO OAK; RIFT CUT; LOG# 53985-1 OR EQUIVALENT AS MAY BE SELECTED BY OWNER
LAMINATE
PLAM1: (PLASTIC LAMINATE) MANUFACTURER: FORMICA, PATTERN: SILVER RIFTWOOD 6413, FINISH: TBDPLAM2: (PLASTIC LAMINATE) MANUFACTURER: FORMICA, PATTERN: NEO CLOUD- 6314-58PLAM3: (PLASTIC LAMINATE) MANUFACTURER: FORMICA, PATTERN: GRAHPITE VEIL M5391
PORCELAIN TILE
PRT1: (PORCELAIN TILE) MANUFACTURER: ATLAS CONCORDE USA, STYLE: FRAY, COLOR: GRAY; SIZE: 12" X 24", INSTALLATION: TBD
QUARRY TILE
QT1: (QUARRY TILE) MANUFACTURER: DALTILE, STYLE: QUARRY TILE, COLOR: ARID GRAY, SIZE: 6" X 6", INSTALLATION TBDQT1: (COVE BASE) MANUFACTURER: DALTILE, STYLE: QUARRY TILE, COLOR: ARID GRAY, SIZE: 6" X 6"
EPOXY
EPX1: (DECORATIVE FLAKE SYSTEM) MANUFACTURER: TENNANT, STYLE: 1/4" FLAKE BLEND, COLOR: ANTIQUE REDWOOD
SOLID SURFACE
SS1: (SOLID SURFACE) MANUFACTURER: CORIAN, COLOR: RAINCLOUDSS2: (SOLID SURFACE) MANUFACTURER: WILSONART, COLOR: DESIGNER WHITE D354SL, NOTE: USE ON TRANSACTION
SURFACE AT CONCESSIONS ONLY
EX: EXISTING VCT OR CONCRETE TO REMAIN - NO WORK.
ACCENT PAINT ON WALLS ANDCEILING PT3
ACCENT PAINT ON WALL AND CEILING PT3
ACCENT PAINT ON WALLAND CEILING PT3
KEYNOTES1
1 PAINT NEW STEEL COLUMN PT-1
2 PAINT EXISTING BRICK PT-1
Revision No. Description Date
1 ADDEND #1 10-3-18
NOTE: FLOOR TILE PATTERN SHALL BE 12" X 24" HERRINGBONE PATTERN WITH 33% RANDOM MIX OF VCT1, VCT2, VCT3
1
10-3-2018
67Front
02Front
05
Front
05
Front
12Front
12Front
02Front
05
Front
11
Front
02Front
05
Front
05
Front
11
Front
67Front
67Front
04Front
04Front
04Front
04Front
67 Front
67 Front
12 Front
30 Front
PERCUSSION
STORAGE
402B
VCT1B1PT1
UNIFORM
STORAGE
402C
VCT1B1PT1
INSTRUMENT
STORAGE
402DVCT1B1PT1EQUIP REPAIR
402A
VCT1B1PT1
CORRIDOR
402EVCT1B1PT1
CORRIDOR
401
CAFETERIA/
MULTI-PURPOSE
102
CORRIDOR
800VCT1B1PT1
A451
9
A45111
A451 10
A451
12
OFFICE
402HVCT1B1PT1
MUSIC LIBRARY
402GVCT1B1PT1
PRACTICE RM
402FVCT1B1PT1
EQUIP
STORAGE
402LVCT1B1PT1
STORAGE
402MVCT1B1PT1
PRACTICE
ROOM
402J
VCT1B1PT1
JANITOR
402K
ENSEMBLE
ROOM
402
VCT1B1PT1
CORRIDOR
401A
A70010
VCT2VCT3
VCT2VCT3
NO WORK
NO WORK
NO WORK
PT3 PAINT HARD LID TO MATCH ACCENT PAINT
1
1
1 1
2
PT1
PT3
PT3
PT3
PT1PT1
PT1
PT3
PT3
PT1
PT3 ACCENT PAINT ON WALLSAND CEILING
NO WORK
1. ALL GROUT JOINTS AT PORCELAIN TILE FLOORS AND WALLS TO BE 3mm AS RECOMMENDED BY MFR. APPLY GROUT SEALER TO ALL JOINTS. REFER TO MFR.'S INSTRUCTIONS FOR SETTING TIME, APPLICATION, AND TYPE OF PRODUCT RECOMMENDED.
2. AT TILE, PROVIDE EXPANSION JOINTS AS RECOMMENDED BY MANUFACTURER WITH SEALANT TO MATCH GROUT COLOR.
3. CONTRACTOR SHALL INQUIRE TO ARCHITECT FOR ANY AREAS WITH MISSING INFORMATION, OR WHERE FLOOR MATERIAL IS NOT INDICATED, PRIOR TO BIDDING. IN ALL CASES, ALL SPACES SHALL RECEIVE FINISHES, THE DEFAULT POSITION SHALL BE; SC / B2 / P1
4. THE FLOORING PATTERNS SHOWN ARE PARTIALLY DIAGRAMMATIC. CONTRACTOR MAY MAKE MINOR ADJUSTMENTS TO SIZES AND LOCATIONS OF ACCENT SQUARES, CIRCLES, AND PATTERN FEATURES TO MEET TILE GRID LINES, EXCEPT WHERE SPECIFICALLY ALIGNED OR DIMENSIONED. DRAWINGS MAY BE SCALED IF NECESSARY TO DETERMINE SIZE OR LOCATION OF FEATURES NOT DIMENSIONED. CONTRACTOR MAY SHIFT GRID LINES TO AVOID SMALL PIECES AT WALL EDGES, EXCEPT WHERE LARGER COMMON AREA PATTERNS EXTEND INTO ROOMS. PATTERNS OR ACCENT ELEMENTS INDICATED TO ALIGN WITH EDGES OR CENTER LINES MUST DO SO, AND MAY REQUIRE CUTTING INTO THE GRID PATTERN TO ACHIEVE THE LAYOUT
5. DRAWINGS MAY SHOW MATERIAL GRID LINES (JOINT LINES), IN SOME AREAS FOR CLARITY AND TO LOCATE ACCENT SQUARES ETC. OTHER AREAS MAY NOT SHOW GRID LINES, BUT ARE INTENDED TO BE SIMILAR AND GENERALLY BASED ON REGULAR GRID LAYOUTS
6. LARGE SCALE CHECKER PATTERNS, AND OTHER REPEATED PATTERNS MAY NOT SHOW COLOR NUMBER FOR EVERY PIECE OF THE PATTERN. CONTRACTOR SHALL COMPLETE THE PATTERN WITH APPROPRIATE COLOR(S) AS ESTABLISHED BY THE GIVEN PATTERN.
7. PROVIDE A TRANSITION STRIP AT ALL EDGES OF DISSIMILAR MATERIALS, E.G. TILE TO CARPET, TILE TO SEALED CONCRETE. COLOR AND PROFILE BY ARCHITECT. SEE COLOR SCHEDULE DOCUMENT, AND/OR SUBMIT PRODUCT SAMPLES FOR ARCHITECT'S SELECTION.
11D
11D
7B 7C
7D
11C
7A
8
10
11A
10D
11B
11A
ACCENT PAINT
VCT1, VCT2, VCT3
MAROON VCT4
ROOM NAME & NUMBER - UPPER NUMBER INDICATES ROOM NUMBER
ROOM NAME
101CPT2B2P12
FLOOR FINISH
BASE
WALL FINISH
JAMES SAPPMICHAEL
NUMBER
A-5051
ST
ATE
OF M I SSO
UR
I
RE
GI S
T E R E D A RCH
I TE
CT
DateProject No. Drawn
Drawing No.
© Copyright 2018 - Sapp Design Associates, Architects, P.C.
Sapp Design Associates Architects, P.C.Missouri State Certificate of Authority #000607
Architect of Record
Michael James Sapp, Architect MO A-5051
In the event the client consents to, allows, authorizes or approves of changes to any plans, specifications or other construction documents, and these changes are not approved in writing by the design professional, the client recognizes that such changes and the results thereof are not the responsibility of the design professional. Therefore, the client agrees to release the design professional from any liability arising from the construction, use or result of such changes. In addition, the client agrees to the fullest extent permitted by law, to indemnify and hold the design professional harmless from any damage, liability or cost (including reasonable attorney's fees and costs of defense) arising from such changes.
The personal seal of the registered Architect or Engineer shall be the legal equivalent of his signature whenever & wherever used, and the owner of the seal shall authenticate this sheet and the specification sections pertaining to this sheet. Responsibility shall be disclaimed for all other plans, specifications, estimates, reports or other documents or instruments relating to or intended to be used for any part or parts of the architectural project.
SPECIAL NOTICES
Author09-06-201817-0923
A802AREA 8 FINISH PLAN
HIG
H S
CH
OO
L6
36 M
O-4
2O
SA
GE
BE
AC
H, M
ISS
OU
RI 65065
CA
MD
EN
CO
UN
TY
RE
NO
VA
TIO
NS
AN
D A
DD
ITIO
NS
TO
SC
HO
OL O
F T
HE
OS
AG
E R
-II
1/8" = 1'-0"1
AREA 8 ENSEMBLE RM RENO
PLAN NORTH
GENERAL NOTES
FINISH TYPESFINISH LEGEND
INSTALL ALL PRODUCTS PER MANUFACTURER'S WRITTEN INSTALLATION INSTRUCTIONS. REFER TO SPECIFICATIONS FOR ADDITIONAL INFORMATION.
CARPET
CPT1: (CARPET TILE) MANUFACTURER: J+J INVISION, PATTERN: INCOGNITO MODULAR 7069, COLOR: OPERATIVE 1837, SIZE: 24" X 24" TILE, INSTALLATION: MONOLITHICCPT2: (BROADLOOM) MANUFACTURER: SHAW, PATTERN: ESCAPE ULTRALOC 5A242, COLOR: PEAK 15506, SIZE: BROADLOOM
SC: SEALED CONCRETE
VCT
VCT1: (VINYL COMPOSITION TILE) MANUFACTURER: JOHNSONITE, STYLE: AZROCK COLLECTION/TEXTILE VCT, COLOR: V-280 RAW SILK, SIZE: 12" X 24" TILEVCT2: (VINYL COMPOSITION TILE) MANUFACTURER: JOHNSONITE, STYLE: AZROCK COLLECTION/TEXTILE VCT, COLOR: V-290 FUR, SIZE: 12" X 24" TILEVCT3: (VINYL COMPOSITION TILE) MANUFACTURER: JOHNSONITE, STYLE: AZROCK COLLECTION/TEXTILE VCT, COLOR: V-289 BERBER GREY, SIZE: 12" X 24" TILEVCT4: MATCH EXISTING MAROON VCT
WALL BASE
B1: (4" RUBBER WALL BASE) MANUFACTURER: JOHNSONITE, COLOR: #29 MOONROCK
PAINT
PT1-3: PAINT COLORS SHALL BE SHERWIN WILLIAMS, EGGSHELL U.N.O
PT1: FIELD COLOR (DISTRICT STANDARD) SW7015 REPOSE GRAYPT2: ACCENT COLOR (DISTRICT STANDARD) SW7014 EIDER WHITEPT3: ACCENT COLOR (DISTRICT STANDARD) CUSTOM TEX A&M AGGIE MAROON
VENEERED WOOD WALL PANELS
VWP: (VENEER WALL PANEL) MANUFACTURER: DOOGE VENEERS, SPECIES: FUMED RIFT WHITE EURO OAK; RIFT CUT; LOG# 53985-1 OR EQUIVALENT AS MAY BE SELECTED BY OWNER
LAMINATE
PLAM1: (PLASTIC LAMINATE) MANUFACTURER: FORMICA, PATTERN: SILVER RIFTWOOD 6413, FINISH: TBDPLAM2: (PLASTIC LAMINATE) MANUFACTURER: FORMICA, PATTERN: NEO CLOUD- 6314-58PLAM3: (PLASTIC LAMINATE) MANUFACTURER: FORMICA, PATTERN: GRAHPITE VEIL M5391
PORCELAIN TILE
PRT1: (PORCELAIN TILE) MANUFACTURER: ATLAS CONCORDE USA, STYLE: FRAY, COLOR: GRAY; SIZE: 12" X 24", INSTALLATION: TBD
QUARRY TILE
QT1: (QUARRY TILE) MANUFACTURER: DALTILE, STYLE: QUARRY TILE, COLOR: ARID GRAY, SIZE: 6" X 6", INSTALLATION TBDQT1: (COVE BASE) MANUFACTURER: DALTILE, STYLE: QUARRY TILE, COLOR: ARID GRAY, SIZE: 6" X 6"
EPOXY
EPX1: (DECORATIVE FLAKE SYSTEM) MANUFACTURER: TENNANT, STYLE: 1/4" FLAKE BLEND, COLOR: ANTIQUE REDWOOD
SOLID SURFACE
SS1: (SOLID SURFACE) MANUFACTURER: CORIAN, COLOR: RAINCLOUDSS2: (SOLID SURFACE) MANUFACTURER: WILSONART, COLOR: DESIGNER WHITE D354SL, NOTE: USE ON TRANSACTION
SURFACE AT CONCESSIONS ONLY.
EX: EXISTING VCT OR CONCRETE TO REMAIN - NO WORK
KEYNOTES1
1 PAINT NEW CMU TO MATCH EXISTING ADJACENT CMU WALLS
2 PAINT EXISTING BRICK
VCT4
VCT4
PT3 ACCENT PAINT ON WALLSAND CEILNG
PT1
PT1
PT1
PT1
Revision No. Description Date
1 ADDEND #1 10-3-18
NOTE: FLOOR TILE PATTERN SHALL BE 12" X 24" HERRINGBONE PATTERN WITH 33% RANDOM MIX OF VCT1, VCT2, VCT3 1
10-3-2018
J&M Engineering, LLC 3045 S Kansas Expressway
Springfield, MO 65807 417.708.9315
MO CofA: E-2011011004
SCHOOL OF THE OSAGE R-II RENOVATIONS AND ADDITIONS TO HIGH SCHOOL 636 MO-42, OSAGE BEACH, MISSOURI 65065 PAGE 1 OF 1
ADDENDUM 1
DATE: October 3, 2018
GENERAL
• This Addendum is incorporated into the Contract Documents for the Project referenced below.
STRUCTURAL ITEMS
ACCEPTED PRODUCT/MANUFACTURER SUBSTITUTIONS
• None this addendum
GENERAL CLARIFICATIONS
• None this addendum
CHANGES TO THE SPECIFICATIONS
• None this addendum
CHANGES TO THE DRAWINGS
• S3.0 o Indicated a new lintel at the new opening in an existing CMU wall at Nurse 11B.
ATTACHMENTS
• S3.0
END OF ADDENDUM
10.3.18
S3.1
1
S3.2
1
S3.3
1
S3.4
1
S3.5
1
S3.6
1
PROVIDE LINTEL PER DTL 6/S4.1 AT NEW OPENING
KEY PLAN
11D
11D
7B7C
7D
11C
7A
8
10
11A
10D
11B
11A
DateProject No. Drawn
Drawing No.
© Copyright 2018 - Sapp Design Associates, Architects, P.C.
Sapp Design Associates Architects, P.C.Missouri State Certificate of Authority #000607
Engineer of Record
In the event the client consents to, allows, authorizes or approves of changes to any plans, specifications or other construction documents, and these changes are not approved in writing by the design professional, the client recognizes that such changes and the results thereof are not the responsibility of the design professional. Therefore, the client agrees to release the design professional from any liability arising from the construction, use or result of such changes. In addition, the client agrees to the fullest extent permitted by law, to indemnify and hold the design professional harmless from any damage, liability or cost (including reasonable attorney's fees and costs of defense) arising from such changes.
The personal seal of the registered Architect or Engineer shall be the legal equivalent of his signature whenever & wherever used, and the owner of the seal shall authenticate this sheet and the specification sections pertaining to this sheet. Responsibility shall be disclaimed for all other plans, specifications, estimates, reports or other documents or instruments relating to or intended to be used for any part or parts of the architectural project.
SPECIAL NOTICES
J&M ENGINEERINGM0 Certificate of Authority # 20110110004
BENJAMIN C. JENNINGS, PE #2003014982
FEM09/06/201817-0923
S3.0OVERALL FRAMING PLAN
HIG
H S
CH
OO
L6
36 M
O-4
2O
SA
GE
BE
AC
H, M
ISS
OU
RI 65065
CA
MD
EN
CO
UN
TY
RE
NO
VA
TIO
NS
AN
D A
DD
TIO
NS
TO
SC
HO
OL O
F T
HE
OS
AG
E R
-II
3/64" = 1'-0"1
OVERALL FRAMING PLAN
PLAN NORTH
Revision No. Description Date
1 ADD 1 10/03/2018
1
10.3.18
SOHS 1
P101,P200,P201,P600,M500,E201,E204
1722 S Glenstone Ave. Suite AA
Springfield, Missouri 65804
417.631.4895
Addendum #1
To: Stephen Telscher
From: Justin Gathright
Date: 10.3.2018
Project Title: School of the Osage – High School Additions and Renovations, Osage Beach, MO
Attachments:
MECHANICAL, ELECTRICAL AND PLUMBING SPECIFICATIONS:
1. Division 23:
a. Section 233113 HVAC Ductwork:
i. Omit Part 1.5 Duct Cleaning. Existing ductwork shall not be required to be cleaned.
ii. Revise Part 2.5 Dust Collection Ductwork to replace existing text with:
A. Dust collection ductwork shall be galvanized steel with smooth inner wall, air
tight longitudinal seams and rolled lip at each fitting.
B. Gasketed clamp fittings, continuous grounding path.
C. -40°F to 150°F service temperature rating.
D. -20”WG pressure classification rating.
E. SMACNA class 3 leakage class.
F. 22 gauge minimum, increase thickness as required for system application.
MECHANICAL, ELECTRICAL AND PLUMBING DRAWINGS:
2. Sheet P101:
a. Revise plans as shown on attached sheet P101.
3. Sheet P200:
a. Revise plans as shown on attached sheet P200.
4. Sheet P201:
a. Revise plans as shown on attached sheet P201.
5. Sheet P600:
a. Revise plans as shown on attached sheet P600.
6. Sheet M500:
a. Revise plans as shown on attached sheet M500.
7. Sheet E201:
a. Revise plans as shown on attached sheet E201.
SOHS 2
8. Sheet E204:
a. Revise plans as shown on attached sheet E204.
END OF ADDENDUM
67Front
02Front
05
Front
05
Front
12Front
12Front
02Front
05
Front
11
Front
02Front
05
Front
05
Front
11
Front
67Front
67Front
04Front
04Front
04Front
04Front
67 Front
67 Front
12 Front
30 Front
67Front
02Front
05
Front
05
Front
12Front
12Front
02Front
05
Front
11
Front
02Front
05
Front
05
Front
11
Front
67Front
67Front
04Front
04Front
04Front
04Front
67 Front
67 Front
12 Front
30 Front
EXISTING
4" WASTE
2
1
2"
WATER HEATER
WH3
2"
DCW
1.5"
1.5"
1.5"
ENSEMBLE ROOM402
PRACTICE ROOM402J
EQUIP STORAGE402L
CORRIDOR401A
1.5"
DCW
3
4
5
6
8
CAP FOR FUTURE
CONSIDERATIONS
7
1. 2" WASTE UP TO SINK
2. MAKE CONNECTION OF NEW 2" SANITARY WASTE TO EXISTING WASTE PIPE IN THIS AREA. MAINTAIN
0.125" PER FOOT SLOPE FOR WASTE PIPING.
3. 0.5" HOT AND COLD WATER AND 1.5" VENT DOWN TO SINK
4. MAKE CONNECTION OF NEW 1.5" VENT TO EXISTING VENT THROUGH ROOF.
5. 0.75" COLD WATER AND 0.75" HOT WATER DOWN TO WATER HEATER. EXTEND HOT AND COLD WATER
TO EXISTING MOP BASIN FAUCET. CONNECT NEW COLD WATER TO EXISTING COLD WATER SUPPLY IN
THIS AREA.
6. PROVIDE WATER HEATER ON WALL-HUNG PLATFORM WITH BOTTOM OF WATER HEATER AT 5'-0" ABOVE
FINISHED FLOOR. SUSPEND WATER HEATER OVER MOP BASIN.
7. REFERENCE TECH ARTS PLUMBING PLAN FOR CONTINUATION.
KEYNOTES: 1
1. ALL PIPING PENETRATIONS THROUGH FIRE WALLS SHALL UTILIZE METALLIC PIPE AND SHALL BE
SEALED WITH FIRE CAULK. REFERENCE ARCHITECTURAL PLANS FOR FIRE WALL INFORMATION.
2. FIELD VERIFY EXACT LOCATIONS OF EXISTING PIPING. EXISTING LOCATIONS SHOWN ARE
APPROXIMATED BASED ON ORIGINAL DESIGN DRAWINGS.
3. VERIFY VENTILATION AIR MECHANICAL INTAKE LOCATIONS PRIOR TO INSTALLING PLUMBING VENT
THROUGH ROOF PIPING. PROVIDE AT LEAST 10'-0" DISTANCE BETWEEN ANY PLUMBING VENT
THROUGH ROOF TERMINATION AND ANY VENTILATION AIR INTAKE.
GENERAL NOTES:
11A
11B
10 10D
11A
11C8
7A7C
7D11D
11D
7B
KEY PLAN
DateProject No. Drawn
Drawing No.
© Copyright 2018 - Interpres Building Solutions, LLC
Sapp Design Associates Architects, P.C.Missouri State Certificate of Authority #000607
Brad Palmer, Engieer MO A-2013039894
In the event the client consents to, allows, authorizes or approves of changes to any plans, specifications or other construction documents, and these changes are not approved in writing by the design professional, the client recognizes that such changes and the results thereof are not the responsibility of the design professional. Therefore, the client agrees to release the design professional from any liability arising from the construction, use or result of such changes. In addition, the client agrees to the fullest extent permitted by law, to indemnify and hold the design professional harmless from any damage, liability or cost (including reasonable attorney's fees and costs of defense) arising from such changes.
The personal seal of the registered Architect or Engineer shall be the legal equivalent of his signature whenever & wherever used, and the owner of the seal shall authenticate this sheet and the specification sections pertaining to this sheet. Responsibility shall be disclaimed for all other plans, specifications, estimates, reports or other documents or instruments relating to or intended to be used for any part or parts of the architectural project.
SPECIAL NOTICES
SC
HO
OL O
F T
HE
OS
AG
E R
-II
RE
NO
VA
TIO
NS
AN
D A
DD
ITIO
NS
TO
Interpres Building SolutionsMissouri Certificate of Authority #E-2013013378
Revision No. Description Date
1 AD#1 10.3.2018
JSG9.4.201817-0920
P101PLUMBING PLANS
HIG
H S
CH
OO
L6
36 M
O-4
2O
SA
GE
BE
AC
H, M
ISS
OU
RI 65065
CA
MD
EN
CO
UN
TY
Scale: 1/8" = 1'-0"1 AREA 8 BAND UNDERGROUND PLUMBING PLAN
Scale: 1/8" = 1'-0"2 AREA 8 BAND PLUMBING PLANNORTH
NORTH
EXISTING SANITARY WASTE SHALL REMAIN
0.5" DCW
0.5" DHW
1.5" VENT
1. 1.5" VENT UP TO 3" VENT THROUGH ROOF
2. 0.5" HOT AND COLD WATER AND 1.5" VENT DOWN TO SINK
3. 0.5" HOT AND COLD WATER AND 1.5" VENT DOWN FOR BACK-TO-BACK SINKS. EXTEND 0.5" HOT AND
COLD WATER TO EACH FAUCET.
4. 0.5" COLD WATER DOWN TO WALL HYDRANT
5. 0.75" HOT AND COLD WATER DOWN TO WATER HEATER. PROVIDE WATER HEATER ON WALL-HUNG
PLATFORM WITH BOTTOM OF WATER HEATER AT 8'-0" ABOVE FINISHED FLOOR.
6. TERMINATE OVERFLOW ROOF DRAIN IN DOWNSPOUT NOZZLE ABOVE CEILING LEVEL AS INDICATED.
KEYNOTES: 1
1. ALL PIPING PENETRATIONS THROUGH FIRE WALLS SHALL UTILIZE METALLIC PIPE AND SHALL BE
SEALED WITH FIRE CAULK. REFERENCE ARCHITECTURAL PLANS FOR FIRE WALL INFORMATION.
2. VERIFY VENTILATION AIR MECHANICAL INTAKE LOCATIONS PRIOR TO INSTALLING PLUMBING VENT
THROUGH ROOF PIPING. PROVIDE AT LEAST 10'-0" DISTANCE BETWEEN ANY PLUMBING VENT
THROUGH ROOF TERMINATION AND ANY VENTILATION AIR INTAKE.
GENERAL NOTES:
WH5
WATER HEATER
ON WALL HUNG PLATFORM
1115
15
7
17
NEW FIRE SPRINKLER RISER
SERVING TECH ARTS AREA
7
WATER HEATER
WH4
WOOD LAB805
METAL LAB806
KILN RM802A
MU STOR801A
ART 3D802 ART 2D
803
ART STOR803B
WOOD STOR805A
OFFICE804A
CAD LAB804
MULTI-USE LAB801
6" ROOF DRAIN
DOWN
6" ROOF DRAIN
DOWN
8" ROOF DRAIN
DOWN
8" ROOF DRAIN
DOWN
8"
8"
8"
16
16
17
17
17 1717
17
1.5"
DCW
1.5"
DCW
1"
DCW
1" DCW
0.75" DHW
0.75" DHW
0.5" DHW
0.5"
DHWR
0.75"
DHW
0.75"
DHW
WHWH
WH
P1
FGCO
FGCO
G 4"FD
A 2"FD
6
66
FFCO
FFCOFFCO
0.5" DCW
1.5" VENT
1.5" VENT0.75" DCW
0.5" DHW
0.5" DCW
1.5" VENT
1.5" VENT
0.75" DCW
0.75" DCW
0.5" DCW
0.75" DCW
0.5" DHW
4"
6"
6"
6"
6"
6" 6" 6" 4" 4"
8"
6"
3
3
3
44
4
5
5
6
6
1.5" VENT
4"
6"
8"
OV
ER
FLO
W
6"
6"
6"
6"
6" 6" 4"
6" OVERFLOW
4"
11A
11B
10 10D
11A
11C8
7A7C
7D11D
11D
7B
KEY PLAN
DateProject No. Drawn
Drawing No.
© Copyright 2018 - Interpres Building Solutions, LLC
Sapp Design Associates Architects, P.C.Missouri State Certificate of Authority #000607
Brad Palmer, Engieer MO A-2013039894
In the event the client consents to, allows, authorizes or approves of changes to any plans, specifications or other construction documents, and these changes are not approved in writing by the design professional, the client recognizes that such changes and the results thereof are not the responsibility of the design professional. Therefore, the client agrees to release the design professional from any liability arising from the construction, use or result of such changes. In addition, the client agrees to the fullest extent permitted by law, to indemnify and hold the design professional harmless from any damage, liability or cost (including reasonable attorney's fees and costs of defense) arising from such changes.
The personal seal of the registered Architect or Engineer shall be the legal equivalent of his signature whenever & wherever used, and the owner of the seal shall authenticate this sheet and the specification sections pertaining to this sheet. Responsibility shall be disclaimed for all other plans, specifications, estimates, reports or other documents or instruments relating to or intended to be used for any part or parts of the architectural project.
SPECIAL NOTICES
SC
HO
OL O
F T
HE
OS
AG
E R
-II
RE
NO
VA
TIO
NS
AN
D A
DD
ITIO
NS
TO
Interpres Building SolutionsMissouri Certificate of Authority #E-2013013378
Revision No. Description Date
1 AD#1 10.3.2018
JSG9.4.201817-0920
P200PLUMBING PLAN
HIG
H S
CH
OO
L6
36 M
O-4
2O
SA
GE
BE
AC
H, M
ISS
OU
RI 65065
CA
MD
EN
CO
UN
TY
NORTHScale: 1/8" = 1'-0"1 AREA 7A TECH ARTS PLUMBING PLAN
1
1
1
2
2
2
2
2
2
2
2
DD
1. CONNECT NEW 2" COLD WATER TO EXISTING 2" OR LARGER COLD WATER SUPPLY IN THIS AREA.
2. 1.25" COLD WATER DOWN TO WATER CLOSET
3. 0.5" HOT AND COLD WATER AND 1.5" VENT DOWN TO SINK
4. 0.5" COLD WATER DOWN TO ICE MAKER. PROVIDE SHUTOFF VALVE SECURED TO WALL APPROXIMATELY
60" ABOVE FLOOR AND PROVIDE UNION CONNECTION ADAPTER TO ICE MAKER HOSE CONNECTION.
COORDINATE EXACT REQUIREMENTS WITH WATER FILTER CONNECTION REQUIREMENTS.
5. PROVIDE CLEANOUT AT PIPE CONNECTION PREVIOUSLY USED AS WATER CLOSET WASTE IN THIS AREA.
MATCH CLEANOUT SIZE TO EXISTING PIPE SIZE. REMOVE AND REPLACE BUILDING FINISH TO
ACCOMODATE CLEANOUT INSTALLATION.
6. CONNECT NEW HOT AND COLD WATER TO EXISTING SUPPLY PIPES OF EQUAL OR GREATER SIZE IN THIS
AREA.
7. CONNECT 1.5" PLUMBING VENT TO EXISTING VENT 1.5" OR LARGER IN THIS AREA.
8. CONNECT 2" PLUMBING VENT TO EXISTING VENT 2" OR LARGER IN THIS AREA. IF ADEQUATE VENTING
DOES NOT EXIST, PROVIDE NEW VENT THROUGH 3" VENT THROUGH ROOF, AND LOCATE AT LEAST 10'-
0" DISTANCE FROM ANY VENTILATION AIR INTAKES.
9. 1.5" VENT DOWN
10. NOT USED
11. INSTALL GARBAGE DISPOSAL SUPPLIED WITH KITCHEN EQUIPMENT. VERIFY WITH ELECTRICIAN THAT
DISPOSAL VOLTAGE MATCHES EXISTING CIRCUIT PRIOR TO INSTALLATION.
12. REFERENCE BAND PLUMBING PLAN FOR CONTINUATION.
KEYNOTES: 1
1. CONTRACTOR SHALL RESTORE WORKING CONDITION OF EXISTING KITCHEN AREA PLUMBING FIXTURES
WHICH ARE REMAINING.
2. ALL PIPING PENETRATIONS THROUGH FIRE WALLS SHALL UTILIZE METALLIC PIPE AND SHALL BE
SEALED WITH FIRE CAULK. REFERENCE ARCHITECTURAL PLANS FOR FIRE WALL INFORMATION.
3. FIELD VERIFY EXACT LOCATIONS OF EXISTING PIPING. EXISTING LOCATIONS SHOWN ARE
APPROXIMATED BASED ON ORIGINAL DESIGN DRAWINGS.
GENERAL NOTES:
KITCHEN400
DRY FOOD400H
LAUNDRY400F
FREEZER400K
COOLER400J
FFCO
5
1
2" DCW
A 3"FD
A 3"FD
FFC0A 3"FD
A 3"FD
A 3"FD
A 3"FD
6
3
2
1
4
2"
DCW
CO
5
1.25"
DCW
3
0.5" DCW
0.5" DHW
7
7
8
6
3
76
1.5" VENT
7
8
3
9
9
9
6
9
2" VENT
1.5"
0.5" DCW
0.5" DHW
11
12
18
18
11A
11B
10 10D
11A
11C8
7A7C
7D11D
11D
7B
KEY PLAN
DateProject No. Drawn
Drawing No.
© Copyright 2018 - Interpres Building Solutions, LLC
Sapp Design Associates Architects, P.C.Missouri State Certificate of Authority #000607
Brad Palmer, Engieer MO A-2013039894
In the event the client consents to, allows, authorizes or approves of changes to any plans, specifications or other construction documents, and these changes are not approved in writing by the design professional, the client recognizes that such changes and the results thereof are not the responsibility of the design professional. Therefore, the client agrees to release the design professional from any liability arising from the construction, use or result of such changes. In addition, the client agrees to the fullest extent permitted by law, to indemnify and hold the design professional harmless from any damage, liability or cost (including reasonable attorney's fees and costs of defense) arising from such changes.
The personal seal of the registered Architect or Engineer shall be the legal equivalent of his signature whenever & wherever used, and the owner of the seal shall authenticate this sheet and the specification sections pertaining to this sheet. Responsibility shall be disclaimed for all other plans, specifications, estimates, reports or other documents or instruments relating to or intended to be used for any part or parts of the architectural project.
SPECIAL NOTICES
SC
HO
OL O
F T
HE
OS
AG
E R
-II
RE
NO
VA
TIO
NS
AN
D A
DD
ITIO
NS
TO
Interpres Building SolutionsMissouri Certificate of Authority #E-2013013378
Revision No. Description Date
1 AD#1 10.3.2018
JSG9.4.201817-0920
P201PLUMBING PLAN
HIG
H S
CH
OO
L6
36 M
O-4
2O
SA
GE
BE
AC
H, M
ISS
OU
RI 65065
CA
MD
EN
CO
UN
TY
NORTHScale: 3/16" = 1'-0"1 AREA 11C, 7D KITCHEN PLUMBING PLAN
MARK
PLUMBING FIXTURE SCHEDULE
AMERICAN
STANDARD
MODELCOLD
PIPING CONNECTION SIZES
ELONGATED BOWL, WHITE, OPEN FRONT SEAT, BACK SPUD, SUPPLY AND STOPS, 1.28 GPF, SLOAN
140 ESS 3771111, HARDWIRED RECESSED SENSOR AND VALVE WITH VALVE ACCESS PLATE.
NOTESOPTIONS AND ACCESSORIESDESCRIPTION
ACCESSIBLE WALL MOUNT FLUSH
VALVE WATER CLOSET
HOT WASTE VENTMANUFACTURER
3353.1011
0.5" -- 4" 2" 2,4
AMERICAN
STANDARD
ELONGATED BOWL, WHITE, TOP SPUD, OPEN FRONT SEAT, SUPPLY AND STOPS, 1.28 GPF, SLOAN
111 ESS 3770009, HARDWIRED RECESSED SENSOR, EXPOSED FLUSH VALVE.
ACCESSIBLE FLOOR MOUNT FLUSH
VALVE WATER CLOSET
2234.660 0.5" -- 4" 2" 2,42
MANUAL FAUCET 1903-DST
WHITE, HANDI-LAV GUARD ADA INSULATION KIT, WALL HANGER, FACUET CENTERS TO MATCH
FAUCET, TRAP AND TAILPIECE
ACCESSIBLE WALL HUNG LAVATORY 0355.012 -- -- 2" 1.5" 1,2,3,4
HARDWIRED, SENSOR, CHROME, ESCUTCHEONS, SUPPLIES AND STOPS, 1.0 GPMSENSOR LAVATORY FAUCET 591T 0.5" 0.5" -- -- 4
TYPE 304 STAINLESS STEEL, 18 GAUGE, LK-6K-H SATIN FINISH, FACUET CENTERS TO MATCH
FAUCET, TRAP AND TAILPIECE, 3.5" DRAIN
SINGLE COMPARTMENT STAINLESS
STEEL SINK
DLR172210 -- -- 2" 1.5" 2,3ELKAY
CHROME, ESCUTCHEONS, SUPPLIES AND STOPS, 8" GOOSENECK SWING SPOUTSINK FAUCET 786-GN8
FCXKABCP
0.5" 0.5" -- -- 2CHICAGO FAUCETS
MOLDED STONE, 3" DRAIN, SS STRAINER, 889-CC MOP HANGER, SS WALL GUARD (PROVIDE
TWO PIECES WHERE LOCATED IN A CORNER)
MOP BASIN MSB-
242410
-- -- 3" 1.5" 2,3FIAT
MOP BASIN FAUCET 830-AA 0.5" 0.5" -- -- 2FIAT INTEGRAL STOPS, HOSE THREAD ON SPOUT
WHEELCHAIR ACCESSIBLE, WRAP AROUND PRESS BAR, ONE PIECE STAINLESS STEEL TOP
WITH DRAIN, FILTER, SAFETY BUBBLER, 120V
ACCESSIBLE DUAL LEVEL ELECTRIC
WATER COOLER
LZST
L8LC
0.5" -- 2" 1.5" 1,2,4ELKAY
BOTTOM OR TOP SUPPLY, (2) 0.5" COMBINATION MPT BRASS SWEAT CONNECTIONS,
QUARTER TURN VALVE
LAUNDRY SUPPLY AND DRAIN BOX B200 0.5" 0.5" 2" 1.5" 1,2GUY GRAY
20 GAUGE STEEL, SHUTOFF VALVE PAINTED TO MATCH WALL, VACUUM BREAKERICE MAKER VALVE BOX BIM875 0.5" -- -- -- 1,2GUY GRAY
PRESSURE BALANCED MIXING VALVE, TEMPERATURE CONTROL, ADJUSTABLE TEMPERATURE LIMIT,
ALL PARTS REPLACEABLE FROM FRONT OF UNIT.
SHOWER VALVE AND
SHOWER HEAD
T13220/
RP38357
DELTA
DELTA
AMERICAN
STANDARD
DELTA
3
11
12
13
14
10
8
5
STAINLESS STEELFLOOR-STANDING SERVICE SINK B1C18X18X -- -- 2" 1.5" 1,2,3,4
MANUAL, SWING SPOUT, CHROME, ESCUTCHEONS, SUPPLIES AND STOPS, 2.2 GPMMANUAL FAUCET 540-LDXK
ABCP
0.5" 0.5" -- -- 4
ELKAY
CHICAGO FAUCETS7
9
6
NOTES:
1. REFER TO ARCHITECTURAL DRAWINGS FOR MOUNTING HEIGHT
2. PROVIDE ACCESSORIES TO SUPPORT FIXTURE AS RECOMMENDED BY MANUFACTURER
3. SINK FAUCET HOLE OPENINGS SHALL MATCH FAUCET.
4. INSTALL ACCESSORIES AS RECOMMENDED BY MANUFACTURER FOR ADA COMPLIANCE.
HAND WASH STATION
15
48" TROUGH, 14GA 304 STAINLESS STEEL, TWO SENSOR FAUCETS, INTEGRATED TEMPERATURE
MIXING VALVE
16EYE WASH
WHITE, TRAP, TAILPIECE, HANDI LAV-GUARD ADA INSULATION KIT WHERE EXPOSEDDROP-IN LAVATORY LT501.4 -- -- 2" 1.5" 2,3TOTO
-- 0.5" 0.5" -- -- 2,4-
EWMA-
4820-
SACMC
ELKAY
S19224-
DCPT
BRADLEY
4 MANUAL FAUCET SINGLE HANDLE, CHROME, COORDINATE HARDWARE TO REPLACE EXISTING FAUCET AS
REQUIRED
501LF-
WFMPU
DELTA 0.5" 0.5" -- -- 2,4
DUST COVER OPTION. PROVIDE THERMOSTATIC MIXING VALVE FOR ANSI/ISEA Z358.1 TEPID WATER
REQUIREMENTS.
0.5" 0.5" 2" 1.5" 2,4
0.5" 0.5" 2" 1.5" 2,4
0.5" 0.5" -- -- 1,2
17
STAINLESS STEELFLOOR-STANDING SERVICE SINK B1C18X18X -- -- 2" 1.5" 1,2,3,4
MANUAL FAUCET 0.5" 0.5" -- -- 4
ELKAY
CHICAGO FAUCETS
64 FL.0Z. REPLACEABLE BOTTLE TRAP. PROVIDE TRAP WITH EACH SINK.PLASTER TRAP TRAP-EZE BTBUFFALO DENTAL
MANUAL FAUCET SINGLE HANDLE, CHROME, COORDINATE HARDWARE TO REPLACE EXISTING FAUCET AS
REQUIRED
501LF-
WFMPU
DELTA
CHROME, ESCUTCHEONS, SUPPLIES AND STOPS, HIGH-ARC SPOUT, COORDINATE
HARDWARE TO REPLACE EXISTING FAUCET AS REQUIRED
0.5" 0.5" -- -- 2,4
MANUAL FAUCET 1903-DSTDELTA CHROME, ESCUTCHEONS, SUPPLIES AND STOPS, HIGH-ARC SPOUT 0.5" 0.5" -- -- 2,4
TYPE 304 STAINLESS STEEL, 18 GAUGE, LK-6K-H SATIN FINISH, FACUET CENTERS TO MATCH
FAUCET, TRAP AND TAILPIECE, 3.5" DRAIN
SINGLE COMPARTMENT STAINLESS
STEEL SINK
LRAD-
131665PD
-- -- 2" 1.5" 2,3ELKAY
MANUAL, SWING SPOUT, CHROME, ESCUTCHEONS, SUPPLIES AND STOPS, 2.2 GPM540-LDXK
ABCP
18 TYPE 304 STAINLESS STEEL, GOOSENECK FACUET, TRAP AND TAILPIECE, BASKET DRAIN, WALL
BRACKET
HAND SINK WITH FAUCET 7-PS-60ADVANCE TABCO 0.5" 0.5" 2" 1.5" 1,2,3,4
ABBREVIATIONS
DIMENSIONS NEXT TO ANY SYMBOL OR FIXTURE INDICATES MOUNTING HEIGHT TO CENTERLINE OF DEVICE
FINISEHD FLOOR CLEANOUT
FINISHED GRADE CLEANOUT
FINISHED WALL CLEANOUT
COLD WATER
1
CO
FGCO
FFCO
WH
RHB
HB
M
S
N20
V
O2
A
ORD
RD
F
G
D
W
PLUMBING SYMBOLSDOMESTIC COLD WATER
DOMESTIC HOT WATER
DOMESTIC HOT WATER RETURN
WASTE PIPING
VENT PIPING
DRAIN
NATURAL GAS
FIRE SERVICE
PRIMARY ROOF DRAIN
OVERFLOW ROOF DRAIN
COMPRESSED AIR
OXYGEN
VACUUM
NITROUS OXIDE
SHUTOFF VALVE
ROOF PIPING SUPPORT
SHOCK ABSORBER
WATER METER
PRESSURE REGULATOR
FLOW CONTROL VALVE
HOSE BIBB
RECESSED HOSE BIBB
WALL HYDRANT
FLUSH FLOOR CLEANOUT
FLUSH GRADE CLEANOUT
WALL CLEANOUT
ELBOW UP WITH SHUTOFF VALVE
ELBOW DOWN WITH SHUTOFF VALVE
TEE UP WITH SHUTOFF VALVE
TEE DOWN WITH SHUTOFF VALVE
END CAP
FLOOR DRAIN, TYPE & SIZE
ROOF DRAIN , TYPE & SIZE
INDICATES CONNECTION TO EXISTING SYSTEMS
PLUMBING FIXTURE TAG
A 2"FD
A 4"RD
HOT WATER
VENT
WASTE
WATER HEATER
60"
FFCO
FGCO
FWCO
CW
HW
V
W
WH
F
MARK
PUMP SCHEDULE
APPLICATION
MODEL
DESIGN HEAD (FT.)
WETTED MATERIAL
WORK. CLASS (PSI)
ABBREVIATIONS:
IL: IN-LINE
WR: WET ROTOR
BMES: BASE MOUNTED END SUCTION
BMHSC: BASE MOUNTED HORIZONTAL SPLIT CASE
BMVSC: BASE MOUNTED VERTICAL SPLIT CASE
BMCCES: BASE MOUNTED CLOSE COUPLED END SUCTION
BR: BRONZE/BRASS
SS: STAINLESS STEEL
IR: IRON
IFC: INTEGRATED FLOW CHECK VALVE
OM: OIL MINDER
P1
DHW
ASTRO 225SU
10
BR,SS
-
TYPE WR
DESIGN FLOW (GPM) 4
MOTOR TYPE -
ACCESSORIES IFC
ABBREVIATIONS:
VSC: VARIABLE SPEED CONTROL
PPC: PROPORTIONAL PRESSURE CURVE CONTROL
CPC: CONSTANT PRESSURE CURVE CONTROL
DTC: DIFFERENTIAL TEMPERATURE CONTROL
BP: HEAVY DUTY BASEPLATE
B&G: BELL AND GOSSETT
DHW: DOMESTIC HOT WATER
AS: AQUASTAT WITH CORD AND PLUG
EFF: EFFLUENT
SP: SUMP PIT AS DETAILED OR PER
MANUFACTURER RECOMMENDATIONS
MANUFACTURER ARMSTRONG
MOTOR POWER 85W
RPM -
VOLTAGE/PHASE 120/1
TRIPLE DUTY VALVE --
SUCTION DIFFUSER --
FLUID TEMP. RANGE (F) 40-180
AREA SERVED TECH. SHOPS
MARK
ELECTRIC WATER HEATER
MANUFACTURER
MODEL NUMBER
TYPE
GALLON CAPACITY
RECOVERY
TEMPERATURE RISE
EFFICIENCY
ABBREVIATIONS:
GPH: GALLONS PER HOUR
GPM: GALLONS PER MINUTE
PTRV: PRESSURE TEMPERATURE RELIEF
VOLTAGE/PHASE
ACCESSORIES
INPUT
WH2
AREA SERVED MUSIC ROOM
EEMAX
EX4208T
ELEC
-
18 GPH
90°F
100%
208/1
-
4.0 kW
STATE
PCE 20 10MSA
ELEC
20
18 GPH
90°F
100%
208/1
PTRV,DP,WHP
4.0 kW
WH3
JANITOR, BAND
WH4
ART
WH5
TECH. SHOPS
ABBREVIATIONS:
DP: DRAIN PAN
WHP: WALL HANGING PLATFORM
STATE
PCE 30 20MSA
ELEC
30
18 GPH
90°F
100%
208/1
4.0 kW
STATE
PCE 20 10MSA
ELEC
20
18 GPH
90°F
100%
208/1
4.0 kW
PTRV,DP PTRV,DP,WHP
TYPE
PIPING MATERIAL SCHEDULE
ABBREVIATIONS:
BF: BUTT FUSION
BZ: BRAZED
CI: CAST IRON
CR: CRIMPED
DWV: DRAINAGE WASTE AND VENT
FSFL: FORGED STEEL FLANGES
MAT: MATERIAL
MI: MALLEABLE IRON
PE: HIGH DENSITY POLYETHYLENE
SIZE MATERIAL MATERIAL TYPE BACKGROUND TEXT
PIPING FITTING LABEL COLOR
ABBREVIATIONS:
NH: NO HUB
RS: RESIN SOCKET
SL: SOLDERED
SW: SOLVENT WELD
TH: THREADED
WC: WROUGHT COPPER
WE: WELDED
WF: WELDED AND FLANGED
WSF: WROUGHT STEEL FITTINGS
WCF: WROUGHT CAST FITTINGS
DOMESTIC COLD WATER ABOVE GRADE ALL TYPE L COPPER TUBING WC SL BLUE WHITE
RED WHITE
DOMESTIC WATER BELOW GRADE ALL SDR11 HIGH DENSITY POLYETHYLENE PE BF -- --
TYPE L COPPER TUBING WC SLDOMESTIC HOT WATER ABOVE GRADE
DOMESTIC HOT WATER RETURN ABOVE GRADE
ALL
TYPE L COPPER TUBING WC SLALL ORANGE WHITE
DWV PIPING ABOVE GRADE DWVALL -- --
DWV PIPING BELOW GRADE SCHEDULE 40 DWV PVC DWV SWALL -- --
TEMPERATURE PRESSURE AND RELIEF TYPE M COPPER DWV/WC DWVALL -- --
CONDENSATE DRAIN SCHEDULE 40 PVC DWV SWALL -- --
FIRE PROTECTION PIPING STEEL PER NFPA 13 &14 PER NFPA PER NFPAALL YELLOW BLACK
PRESSURE TIME
TEST PARAMETERS
PER NFPA PER NFPA
150 PSI 1 HR
150 PSI 1 HR
150 PSI 1 HR
150 PSI 1 HR
5 PSI 1 HR
5 PSI 1 HR
150 PSI 1 HR
150 PSI 1 HR
SCHEDULE 40 DWV PVC SW
DateProject No. Drawn
Drawing No.
© Copyright 2018 - Interpres Building Solutions, LLC
Sapp Design Associates Architects, P.C.Missouri State Certificate of Authority #000607
Brad Palmer, Engieer MO A-2013039894
In the event the client consents to, allows, authorizes or approves of changes to any plans, specifications or other construction documents, and these changes are not approved in writing by the design professional, the client recognizes that such changes and the results thereof are not the responsibility of the design professional. Therefore, the client agrees to release the design professional from any liability arising from the construction, use or result of such changes. In addition, the client agrees to the fullest extent permitted by law, to indemnify and hold the design professional harmless from any damage, liability or cost (including reasonable attorney's fees and costs of defense) arising from such changes.
The personal seal of the registered Architect or Engineer shall be the legal equivalent of his signature whenever & wherever used, and the owner of the seal shall authenticate this sheet and the specification sections pertaining to this sheet. Responsibility shall be disclaimed for all other plans, specifications, estimates, reports or other documents or instruments relating to or intended to be used for any part or parts of the architectural project.
SPECIAL NOTICES
SC
HO
OL O
F T
HE
OS
AG
E R
-II
RE
NO
VA
TIO
NS
AN
D A
DD
ITIO
NS
TO
Interpres Building SolutionsMissouri Certificate of Authority #E-2013013378
Revision No. Description Date
1 AD#1 10.3.2018
JSG9.4.201817-0920
P600PLUMBING SCHEDULES
HIG
H S
CH
OO
L6
36 M
O-4
2O
SA
GE
BE
AC
H, M
ISS
OU
RI 65065
CA
MD
EN
CO
UN
TY
HVAC SYMBOLSCEILING SUPPLY GRILLE
ABBREVIATIONS
60" DIMENSIONS NEXT TO ANY SYMBOL OR FIXTURE INDICATES MOUNTING HEIGHT TO CENTERLINE OF DEVICE.
AFF ABOVE FINISHED FLOOR
AFG ABOVE FINISHED GRADE
HP HEAT PUMP
CEILING RETURN/EXHAUST GRILLE
LINEAR SUPPLY/RETURN GRILLE
WALL SUPPLY/RETURN/EXHAUST GRILLE OR REGISTER
DIFFUSER OR GRILLE WITH FLEX DUCT. SIZE OF FLEX DUCT SHALL EQUAL SIZE OF UPSTREAM DUCT.
INDICATES CONNECTION TO EXISTING SYSTEM
T RTU3 THERMOSTAT
CO2 CO2 SENSOR
T REMOTE AVERAGING TEMPERATURE SENSOR
H HUMIDISTAT
OR TEMPERATURE OVERRIDE SENSOR
AT 8x8100
DIFFUSER TAG - LETTER AND CEILING DESIGNATION, NECK SIZE AND CFM
FIRE DAMPER
SMOKE DAMPER
MOTORIZED DAMPER
AHU AIR HANDLING UNIT
CU CONDENSING UNIT
DN DOWN
EF EXHAUST FAN
OA OUTSIDE AIR
RA RETURN AIR
SA SUPPLY AIR
OFCI OWNER FURNISHED CONTRACTOR INSTALLED
FD
SD
MD
S
S
S
S
ROUTE TRANSITIONS AS REQUIRED TO CONNECT
SUPPLY AND RETURN DUCT SIZES AND ROUTING
AS SHOWN ON PLAN.
SUPPLY DUCT
ROOF DECK. SEE ARCHITECTURAL PLANS
FOR ROOF CONSTRUCTION
ROOF CURB SHALL BE MINIMUM OF 8" ABOVE TOP
OF ROOF CONSTRUCTION. PROVIDE EXTENSIONS AS
REQUIRED.
EXTEND CONDENSATE DRAIN TO NEAREST ROOF
DRAIN OR GUTTER UNLESS OTHERWISE NOTED ON
PLAN .
TRAPPED CONDENSATE DRAIN
ACCESS PANEL
DISCONNECTING MEANS
FLEX DUCT CONNECTION (TYPICAL)
RETURN AIR DUCT. PROVIDE ELBOW AND EXTEND BOOT AS
SHOWN FOR SOUND ATTENUATION. PROVIDE RETURN AIR
DUCT WHERE SHOWN ON PLAN
ELECTRICAL CONDUIT AND CONTROL WIRING SHALL
PENETRATE ROOF INSIDE CURB.
ROOFTOP UNIT
INSULATED SOLID BOTTOM ROOF CURB. MATCH TO
ROOF TYPE AND ROOF WARRANTY. PROVIDE FLASHING
AS REQUIRED FOR WEATHERTIGHT ROOF ASSEMBLY.
EQUIPMENT RAIL
ROOF CONSTRUCTION
SPLIT SYSTEM CONDENSING UNIT
OR HEAT PUMP
COIL GUARD
DISCONNECT SWITCH. VERIFY LOCATION
WITH EQUIPMENT MANUFACTURER
FLEXIBLE WATER TIGHT CONDUIT
STAINLESS STEEL GEAR CLAMPS
PIPING BOOT. PROVIDE SEPARATE
BOOT FOR EACH PENETRATION
THROUGH ROOF.
PIPING PENETRATION CURB
PROVIDE CANT STRIP OR CHAMFERED EDGE
ON ROOF CURBS AND SUPPORTS AS
REQUIRED FOR ROOF FLASHING.
COORDINATE ROOF EQUIPMENT SUPPORT
SELECTION WITH ROOFING CONTRACTOR TO
MAINTAIN ROOF WARRANTY.
PROVIDE ALUMINUM JACKETING COVER
FOR EXTERNAL PIPE INSULATION.
REFERENCE SPECIFICATIONS.
NUT AND WASHER AT
BOTTOM OF ROD
DUCTS LESS THAN 60" IN WIDTH
DUCTS GREATER THAN 60" IN WIDTH OR
MULTIPLE DUCTS
SECURE HANGER STRAP TO STRUCTURE
ABOVE PER SMACNA
RECOMMENDATIONS
GALVANIZED HANGER STRAP
SHEET METAL SCREWS THROUGH
BOTTOM OF DUCT. SHEET METAL
SCREWS MAY BE OMITTED IF HANGER
STRAP IS CONTINUOUS UNDER BOTTOM
OF DUCT.
SECURE HANGER ROD TO STRUCTURE
ABOVE PER SMACNA
RECOMMENDATIONS
THREADED HANGER ROD
ANGLE OR UNISTRUT RATED FOR DUCT
WIDTH
W
L
45 DEGREE TRANSITION IN
DIRECTIONS SHOWN ON PLAN
MITERED ELBOW WITH
TURNING VANES
BELLMOUTH BRANCH DUCT FITTING.
L = 1/4W (4" MINIMUM)
RADIUS ELBOW CENTERLINE RADIUS SHALL
BE MINIMUM 1.5X DUCT WIDTH.
45 DEGREE BRANCH DUCT
FITTING
ALL SUPPLY AIR TAKEOFFS SHALL BE
EQUIPPED WITH BALANCING DAMERS.
BRANCH DUCT SHALL MATCH
DIFFUSER NECK SIZE UNLESS
OTHERWISE NOTED.
TWO WRAPS OF DUCT TAPE AND DRAWBAND
OR METAL SCREW CLAMP AROUND DUCT
CORE.
1.5" WIDE SHEET METAL STRAP WITH
HEMMED EDGES SUPPORT FROM STRUCTURE
ABOVE.
MAXIMUM LENGTH OF FLEX DUCT SHALL BE 6'-0"
EXTENSION DUCT COLLAR
TWO WRAPS OF DUCT TAPE AND DRAWBAND
OR METAL SCREW CLAMP AROUND DIFFUSER
NECK.
DIFFUSER OR GRILLE AS
SHOWN ON PLAN
DOWNBLAST OR UPBLAST EXHAUST FAN
WITH BIRDSCREEN
OVERSIZED GALVANIZED COVER WITH
WEATHER TIGHT SEAL TO EXHAUST FAN
SECURE EXHAUST FAN TO ROOF CURB
PREFABRICATED INSULATED ROOF CURB
WITH TREATED WOOD NAILER
PROVIDE FLASHING AS REQUIRED FOR
WEATHERTIGHT ROOF CONSTRUCTION.
COORDINATE WITH ROOFING CONTRACTOR
TO MAINTAIN ROOF WARRANTY.
INSTALL NEOPRENE GASKET BETWEEN
DUCT AND FAN.
GRAVITY BACKDRAFT DAMPER UNLESS
OTHERWISE NOTED OTHERWISE ON PLANS OR
SCHEDULE. SECURE TO DUCT FROM ABOVE TO
ALLOW SERVICE FROM ROOF.
SECURE CURB TO ROOF WITH SCREWS PINS
OR BOLTS
EXHAUST DUCTWORK UP THROUGH ROOF.
EXTEND DUCT OVER TOP OF CURB AND
SECURE TO CURB NAILER.
ROOF CONSTRUCTION
ROOF VENT
OVERSIZED GALVANIZED COVER WITH
WEATHER TIGHT SEAL TO ROOF VENT
SECURE ROOF VENT TO ROOF CURB
PREFABRICATED INSULATED ROOF CURB
WITH TREATED WOOD NAILER
PROVIDE FLASHING AS REQUIRED FOR
WEATHERTIGHT ROOF CONSTRUCTION.
COORDINATE WITH ROOFING CONTRACTOR
TO MAINTAIN ROOF WARRANTY.
BIRD SCREEN
SECURE CURB TO ROOF WITH SCREWS PINS
OR BOLTS
DUCTWORK UP THROUGH ROOF. EXTEND
DUCT OVER TOP OF CURB AND SECURE TO
CURB NAILER.
ROOF CONSTRUCTION
FRONT ELEVATION REAR ELEVATION
REAR OR SIDE INLET. PROVIDE
GASKETED DUCT FLANGE ON DUCT
TO MATCH UNIT CONNECTION
FAN CHAMBER DOOR
FILTER CHAMBER DOOR
SHAKER MOTOR
ELECTRICAL TERMINAL BOX
FIELD INSTALLED INTERCONNECTING WIRING
AND CONDUIT
REMOVABLE SAFETY LATCH HANDLE
HOPPER
DUST CONNTAINER WITH QUICK
RELEASE SEALER GEAR
TOP FILTERED AIR OUTLET
FACTORY PROVIDED LEGS
REMOTE CONTROL STATION. LOCATE
WHERE INDICATED ON PLAN
MECHANICAL CONTRACTOR SHALL PROVIDE
INTERCONNECTING WIRING FOR INSTALLATION OF
REMOTE CONTROL STATION
PROVIDE WEATHER HOOD
DUCT SYSTEM SHALL BE METALLIC WITH SMOOTH
INNER WALLS AND WELDED OR FLANGED
CONNECTIONS FOR AIR TIGHT OPERATION AND
CONTINUOUS GROUNDING PATH.
DUST
COLLECTOR
CASING
GASKETED FLANGED DUCT CONNECTION.
FASTENERS SHALL BE CONDUCTIVE TO
BOND DUCT SYSTEM TO GROUNDING
SYSTEM OF DUST COLLECTOR.
FLEXIBLE DUCT(S) TO EQUIPMENT
BY OWNER
MANUAL DUST DUCT GATE
ALL ELBOWS SHALL BE
FABRICATED WITH
LONG SWEEP GEOMETRY
SEE PLANS FOR DUCT DROP SIZE
DUCT SUPPORTS SHALL BE SELECTED AND SPACED SO AS TO
SUPPORT ONE HALF OF DUCT VOLUME FILLED WITH CONTAMINANT.
PROVIDE FLANGED REMOVABLE DUCT SECTION
IN EACH STRAIGHT DUCT LENGTH. FLANGED
ELBOW CONNECTIONS SHALL BE ACCEPTABLE
TO MEET ACCESS REQUIREMENTS
BOND DUCT SYSTEM TO GROUNDING
SYSTEM WITH #12 WIRE.
0.5" COMPRESSED AIR
PIPING DROP
SHUTOFF VALVE (TYPICAL)END CAP WITH
THREADED END
FOR CONNECTION
OF NPT FITTING BY
OWNER.DRAIN VALVE WITH
END CAP
DateProject No. Drawn
Drawing No.
© Copyright 2018 - Interpres Building Solutions, LLC
Sapp Design Associates Architects, P.C.Missouri State Certificate of Authority #000607
Brad Palmer, Engieer MO A-2013039894
In the event the client consents to, allows, authorizes or approves of changes to any plans, specifications or other construction documents, and these changes are not approved in writing by the design professional, the client recognizes that such changes and the results thereof are not the responsibility of the design professional. Therefore, the client agrees to release the design professional from any liability arising from the construction, use or result of such changes. In addition, the client agrees to the fullest extent permitted by law, to indemnify and hold the design professional harmless from any damage, liability or cost (including reasonable attorney's fees and costs of defense) arising from such changes.
The personal seal of the registered Architect or Engineer shall be the legal equivalent of his signature whenever & wherever used, and the owner of the seal shall authenticate this sheet and the specification sections pertaining to this sheet. Responsibility shall be disclaimed for all other plans, specifications, estimates, reports or other documents or instruments relating to or intended to be used for any part or parts of the architectural project.
SPECIAL NOTICES
SC
HO
OL O
F T
HE
OS
AG
E R
-II
RE
NO
VA
TIO
NS
AN
D A
DD
ITIO
NS
TO
Interpres Building SolutionsMissouri Certificate of Authority #E-2013013378
Revision No. Description Date
1 AD#1 10.3.2018
JSG9.4.201817-0920
M500MECHANICAL DETAILS
HIG
H S
CH
OO
L6
36 M
O-4
2O
SA
GE
BE
AC
H, M
ISS
OU
RI 65065
CA
MD
EN
CO
UN
TY
Scale: NTS1 ROOFTOP UNIT DETAIL
Scale: NTS2 ROOF CONDENSING UNIT DETAIL
Scale: NTS3 DUCT SUPPORT DETAIL
Scale: NTS4 DUCT CONSTRUCTION DETAIL
Scale: NTS5 FLEX DUCT CONSTRUCTION DETAIL
Scale: NTS6 ROOF EXHAUST FAN DETAIL
Scale: NTS7 ROOF VENT DETAIL
Scale: NTS8 DUST COLLECTION DETAIL
Scale: NTS9 DUST COLLECTION DUCT SYSTEM DETAIL
Scale: NTS10
COMPRESSEDAIR PIPING DROP DETAIL
JJ
D
J J
J J
J
J
J
1. INSTALL KITCHEN HOOD FIRE SUPPRESSION SYSTEM PULL STATION AND MANUAL FIRE ALARM PULL
STATION STACKED ON WALL.
2. REVISE EXISTING KITCHEN HOOD FIRE SUPPRESSION SYSTEM WIRING AS REQUIRED FOR NEW
LOCATION.
3. WIRE SWITCHLEG OF RESTROOM LIGHTING CIRCUIT FOR EXHAUST FAN CONTROL.
4. EVAPORATOR POWER. PROVIDE 2 - #12 AND 1 - #8 GROUND, AND WIRE TO NEW 20A, 2-POLE BREAKER
IN EXISTING KITCHEN PANEL. COORDINATE EXACT REQUIREMENTS WITH COOLER/FREEZER SUPPLIER.
5. PROVIDE POWER AND SWITCHING FOR COOLER/FREEZER LIGHTS AND DOOR HEATER.
6. COOLER/FREEZER CONDENSING UNIT ON ROOF. REFERENCE MEP ROOF PLAN.
7. INSTALL TRANSFORMER TR7 ABOVE CEILING ACCORDING TO MANUFACTURER RECOMMENDATIONS
AND MOUNTED TO WALL WITH BRACKETS RATED FOR TRANSFORMER WEIGHT.
8. PROVIDE WATER TIGHT IN-FLOOR JUNCTION BOX AND WATER TIGHT CONDUIT ASSEMBLY UP TO
RECEPTACLES MOUNTED TO TABLE.
9. JUNCTION BOX FOR PLUMBING FIXTURE POWER. COORDINATE EXACT LOCATION WITH PLUMBING
CONTRACTOR PRIOR TO ROUGH-IN.
10. WIRE TO EXISTING RECEPTACLE POWER IN THIS AREA.
11. COORDINATE EXACT LOCATIONS FOR CONCESSIONS RECEPTACLES WITH OWNER PRIOR TO ROUGH-IN.
12. WIRE NEW DISPOSAL TO EXISTING DISPOSAL POWER. INFORM KITCHEN EQUIPMENT PROVIDER OF
EXISTING VOLTAGE AND AMPERAGE AVAILABLE AND CONFIRM COMPATIBILITY WITH NEW DISPOSAL.
PROVIDE NEW DISCONNECT AS REQUIRED.
13. PROVIDE POWER FOR ROLL-UP DOOR OPERATOR. COORDINATE EXACT LOCATION WITH DOOR
OPERATOR PROVIDER.
14. PROVIDE CONNECTION TO FIRE ALARM FOR ROLL-UP DOOR AS REQUIRED FOR CODE COMPLIANT DOOR
OPERATION.
KEYNOTES: 1
1. ELECTRICAL CONTRACTOR SHALL PROVIDE JUNCTION BOX AND CONDUIT FOR HVAC CONTROL
DEVICES. REFERENCE MECHANICAL PLANS FOR DEVICE LOCATIONS AND COORDINATE EXACT
REQUIREMENTS WITH MECHANICAL CONTRACTOR.
2. ELECTRICAL CONTRACTOR IS RESPONSIBLE FOR COORDINATING ALL KITCHEN EQUIPMENT
REQUIREMENTS WITH KITCHEN EQUIPMENT SUPPLIER. E/C SHALL PROVIDE ALL ACCESSORIES AS
REQUIRED TO MAKE ALL FINAL ELECTRICAL CONNECTIONS TO KITCHEN EQUIPMENT, WHICH INCLUDE
BUT IS NOT LIMITED TO PROVIDING ASSOCIATED OUTLET TYPES AND CORDS/PLUGS AS REQUIRED.
COORDINATE EXACT DEVICE LOCATIONS PRIOR TO ROUGH-IN.
3. ALL KITCHEN AND CONCESSIONS WIRING DEVICES SHALL BE GFI TYPE OR CIRCUITED TO A GFI CIRCUIT
BREAKER.
GENERAL NOTES:
EXISTING
L5
EXISTING
KDP-L
EXISTING
KDP-R
FREEZER400K
COOLER400J
RECEIVING400G
KITCHEN400
LAUNDRY400F
DRY FOOD400H
CONCESSIONS400C
DISH RETURN400B
TOILET400D
AC
AC
RECESSED
FLOOR BOX
FOR CASHIER
10'-3"
EF21
F F1
2
3
44
5 5
L71
TR7
7
8 8
8
AC
AC
AC
AC
10'-3"
10'-3"
F
6 6
L71
19
L71
21
L71
20
L71
1
L71
2
6-30R
L71
3
L14-20R
L71
5
6-30RL71
6
6-30R
L71
10
L71
11
L71
13
6-20R
L71
15
L14-20R
L71
14
L71
22
9
9
10
L71
23
L71
25
L71
27
L71
29
L71
28
L71
26
11
(TYPICAL)
12
F 1
54" DOOR
54" DOOR
54" DOOR
L71
31
L71
33
L71
32
13
1313
14
14
14
11A
11B
10 10D
11A
11C8
7A7C
7D11D
11D
7B
KEY PLAN
DateProject No. Drawn
Drawing No.
© Copyright 2018 - Interpres Building Solutions, LLC
Sapp Design Associates Architects, P.C.Missouri State Certificate of Authority #000607
Brad Palmer, Engieer MO A-2013039894
In the event the client consents to, allows, authorizes or approves of changes to any plans, specifications or other construction documents, and these changes are not approved in writing by the design professional, the client recognizes that such changes and the results thereof are not the responsibility of the design professional. Therefore, the client agrees to release the design professional from any liability arising from the construction, use or result of such changes. In addition, the client agrees to the fullest extent permitted by law, to indemnify and hold the design professional harmless from any damage, liability or cost (including reasonable attorney's fees and costs of defense) arising from such changes.
The personal seal of the registered Architect or Engineer shall be the legal equivalent of his signature whenever & wherever used, and the owner of the seal shall authenticate this sheet and the specification sections pertaining to this sheet. Responsibility shall be disclaimed for all other plans, specifications, estimates, reports or other documents or instruments relating to or intended to be used for any part or parts of the architectural project.
SPECIAL NOTICES
SC
HO
OL O
F T
HE
OS
AG
E R
-II
RE
NO
VA
TIO
NS
AN
D A
DD
ITIO
NS
TO
Interpres Building SolutionsMissouri Certificate of Authority #E-2013013378
Revision No. Description Date
1 AD#1 10.3.2018
JSG9.4.201817-0920
E201ELECTRICAL PLAN
HIG
H S
CH
OO
L6
36 M
O-4
2O
SA
GE
BE
AC
H, M
ISS
OU
RI 65065
CA
MD
EN
CO
UN
TY
NORTHScale: 3/16" = 1'-0"1 AREA 11C, 7D KITCHEN ELECTRICAL PLAN
JJ
1. PROVIDE 2 - #12 AND 1 #12 GROUND, AND WIRE TO NEW 20A, 1-POLE BREAKER IN EXISTING PANEL.
2. PROVIDE VERTICAL FLOOR TO CEILING POWER/DATA POLE AND DEVICES SIMILAR TO THOSE
DEMOLISHED FROM NEW DRAMA ROOM. EXISTING POWER/DATA POLES REMOVED FROM DRAMA
ROOM MAY BE INSTALLED IN NEW BUSINESS ROOM IF IN GOOD CONDITION. REUSE SHALL BE SUBJECT
TO OWNER APPROVAL. SECURE POLES FOR RIGIDITY.
3. MOVE EXISTING HVAC CONTROL PANELS APPROXIMATELY 24" TO ACCOMODATE NEW WALL OPENING.
COORDINATE PANEL WORK WITH THERMAL MECHANICS INC (TMI), AND MECHANICAL CONTRACTOR.
KEYNOTES: 1
1. MAINTAIN FUNCTIONALITY OF EXISTING ELECTRICAL DEVICES NOT DEMOLISHED.
GENERAL NOTES:
STOR104B
TOILET104A
NURSE104
GF
4'
EXISTING
L2L2
1
EXISTING POWER
AND DATA SHALL
REMAIN
EF31
L2
1
T
TS5
3
BUSINESS109
L2
1L2
1L2
1L2
1
RELOCATE EXISTING
PROJECTOR DEVICES
L2
1
2222
11A
11B
10 10D
11A
11C8
7A7C
7D11D
11D
7B
KEY PLAN
DateProject No. Drawn
Drawing No.
© Copyright 2018 - Interpres Building Solutions, LLC
Sapp Design Associates Architects, P.C.Missouri State Certificate of Authority #000607
Brad Palmer, Engieer MO A-2013039894
In the event the client consents to, allows, authorizes or approves of changes to any plans, specifications or other construction documents, and these changes are not approved in writing by the design professional, the client recognizes that such changes and the results thereof are not the responsibility of the design professional. Therefore, the client agrees to release the design professional from any liability arising from the construction, use or result of such changes. In addition, the client agrees to the fullest extent permitted by law, to indemnify and hold the design professional harmless from any damage, liability or cost (including reasonable attorney's fees and costs of defense) arising from such changes.
The personal seal of the registered Architect or Engineer shall be the legal equivalent of his signature whenever & wherever used, and the owner of the seal shall authenticate this sheet and the specification sections pertaining to this sheet. Responsibility shall be disclaimed for all other plans, specifications, estimates, reports or other documents or instruments relating to or intended to be used for any part or parts of the architectural project.
SPECIAL NOTICES
SC
HO
OL O
F T
HE
OS
AG
E R
-II
RE
NO
VA
TIO
NS
AN
D A
DD
ITIO
NS
TO
Interpres Building SolutionsMissouri Certificate of Authority #E-2013013378
Revision No. Description Date
1 AD#1 10.3.2018
JSG9.4.201817-0920
E204ELECTRICAL PLANS
HIG
H S
CH
OO
L6
36 M
O-4
2O
SA
GE
BE
AC
H, M
ISS
OU
RI 65065
CA
MD
EN
CO
UN
TY
NORTH
NORTHScale: 3/16" = 1'-0"2 AREA 11B NURSE ELECTRICAL PLAN
Scale: 3/16" = 1'-0"1 AREA 11A BUSINESS ELECTRICAL PLAN