Rev. 06.17 FO-153 Date: March-9-20 To: Bidders for Norfolk County Bid No. PW-E-20-64 Watermain Replacement and Nelson Street West Reconstruction From: Dadean Assam, Project Manager, Public Works Division [email protected] Subject: Addendum No. 1 (4 pages plus 20 pages of attachments) ADDENDUM No. 1 This Addendum shall form part of the Contract Documents. The Bidders should acknowledge receipt of this Addendum on the Submission Form – Appendix A. The date of closing of this tender shall be extended by one week from Tuesday, March-10-20 to: Tuesday, March-17-20 1. Delete: Appendix B – Schedule of Items and Prices Replace With: Revised Appendix B – Appendix B – Schedule of Items and Prices, as attached. Please note the following items have been amended on the Schedule of Items and Prices: Part 1 – B.5 Part 2 – B.9 Part 2 – B.25 Part 2 – B.30 2. Insert: Attachment G – Soil Sampling Report Note: Attachment G – Soil Sampling Report will be emailed to registered Bid Takers of this bidding opportunity. Page 1 of 4 Accessible formats and communication supports available upon request.

Upload: others

Post on 06-Aug-2020

8 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Addendum No. 1 - PW-E-20-64 · Part 1 – B.5 Part 2 – B.9 Part 2 – B.25 Part 2 – B.30 . 2. Insert: Attachment G – Soil Sampling Report . Note: Attachment G – Soil Sampling

Rev. 06.17 FO-153

Date: March-9-20 To: Bidders for Norfolk County Bid No. PW-E-20-64 Watermain Replacement and Nelson Street West Reconstruction From: Dadean Assam, Project Manager, Public Works Division

[email protected] Subject: Addendum No. 1 (4 pages plus 20 pages of attachments)

ADDENDUM No. 1 This Addendum shall form part of the Contract Documents.

The Bidders should acknowledge receipt of this Addendum on the Submission Form – Appendix A.

The date of closing of this tender shall be extended by one week from

Tuesday, March-10-20 to: Tuesday, March-17-20

1. Delete:

Appendix B – Schedule of Items and Prices Replace With: Revised Appendix B – Appendix B – Schedule of Items and Prices, as attached. Please note the following items have been amended on the Schedule of Items and Prices: Part 1 – B.5 Part 2 – B.9 Part 2 – B.25 Part 2 – B.30

2. Insert: Attachment G – Soil Sampling Report Note: Attachment G – Soil Sampling Report will be emailed to registered Bid Takers of this bidding opportunity.

Page 1 of 4

Accessible formats and communication supports available upon request.

Page 2: Addendum No. 1 - PW-E-20-64 · Part 1 – B.5 Part 2 – B.9 Part 2 – B.25 Part 2 – B.30 . 2. Insert: Attachment G – Soil Sampling Report . Note: Attachment G – Soil Sampling

Rev. 06.17 FO-153

3. Question:

Is there a possibility to have an extension for this project? We have a number of projects closing and Pre-Con meetings scheduled for March 10th. Answer: The closing date has been extended to March 17, 2020.

4. Question: Please provide a complete geotechnical report for review and consideration of tender document along with Analytical. Answer: Refer to Attachment C of the Request for Tender for the geotechnical report. Refer to Attachment G for the soil sampling report detailing the “Analytical” results.

5. Question: Please comment on existing condition of existing culvert in detail if possible Answer: Based on a CCTV inspection of the existing 2100mm diameter CSP culvert performed in February 2018, the culvert appears to be in good condition in the area of the proposed storm sewer tie-ins. The staining on the interior, indicative of the normal water level is well below the elevation of the proposed tie-ins. There is some pipe deformation but this is not anticipated to be a concern relative to the connection installation. Please see a screen shot from the inspection record below.

Page 2 of 4

Accessible formats and communication supports available upon request.

Page 3: Addendum No. 1 - PW-E-20-64 · Part 1 – B.5 Part 2 – B.9 Part 2 – B.25 Part 2 – B.30 . 2. Insert: Attachment G – Soil Sampling Report . Note: Attachment G – Soil Sampling

Rev. 06.17 FO-153

6. Question: Propose use of a single structure install by means of cutting and removal of existing CSP section and realignment of 600mm and 375mm to eliminate deflection of connections due to angle of CSP Answer: Alteration of the exiting CSP culvert, other than for the proposed tie-ins will not be permitted. Please price the work based on the scope provided.

7. Question: Provide flow rates of CSP if data is available to allow estimation of potential dewatering if single structure is permitted. Answer: At the time of the CCTV video, in February 2018, the flow was noted to be approximately 10% full in the existing pipe. Under normal conditions, the flow in the pipe is not anticipated to impact the proposed storm tie-ins.

Page 3 of 4

Accessible formats and communication supports available upon request.

Page 4: Addendum No. 1 - PW-E-20-64 · Part 1 – B.5 Part 2 – B.9 Part 2 – B.25 Part 2 – B.30 . 2. Insert: Attachment G – Soil Sampling Report . Note: Attachment G – Soil Sampling

Rev. 06.17 FO-153

8. Question

Full road closure is permitted in this area Answer: Yes. Ten (10) days will be permitted for a full road closure between Mergl Drive and Lakeside Lane to complete all necessary work in that area.

9. Question Is the road to be backfilled with native material displaced from excavations to road granular sub base as per geo-tech report to be issued? Answer: Yes, where the existing materials are suitable for use as backfill. Please note that there is an anticipated volume of 375 cubic metres of excess road base resultant from the Part 1 work on Elm Avenue, Kiwanis Avenue, and Maple Boulevard (see Appendix B – Schedule of Items and Prices – Part 1 – Item B.5) that may also be used for this purpose. Please refer to the Answer to Question 4 for the “geo-tech report”.

End of Addendum Attachments Revised Appendix B – Schedule of Items and Prices

Page 4 of 4

Accessible formats and communication supports available upon request.

Page 5: Addendum No. 1 - PW-E-20-64 · Part 1 – B.5 Part 2 – B.9 Part 2 – B.25 Part 2 – B.30 . 2. Insert: Attachment G – Soil Sampling Report . Note: Attachment G – Soil Sampling

Revised Appendix B - Schedule of Items and Prices - Addendum No. 1 Tender Number: PW-E-20-64 Page 36 of 120 Tender Name: WATERMAIN REPLACEMENT AND NELSON STREET WEST RECONSTRUCTION

APPENDIX B– SCHEDULE OF ITEMS & PRICES

Bidders shall multiply the unit quantity by the unit price to calculate the total for each item. All items must be completed. All totals for each Part before taxes are to be carried forward to the Tender Summary. The tender will be awarded to one Bidder based on the Subtotal of the Tender Summary. L.S. = lump sum, m = metre, m2= square metre; m3= cubic metre, t = tonne

A. GENERAL CONTRACT ITEMS – PART 1

Item Spec Description Est. Qty. Unit Unit Price Amount

A.1 A1 Mobilization, De-Mobilization and Insurance.

1 L.S. $

A.2 G Bonding 1 L.S. $

A.3 A1 Site Trailer 1 L.S. $

A.4 A4 Preconstruction Survey 1 L.S. $

A.5 A3, A5

Construction Layout, including Field Verification of inverts and pipe sizes

1 L.S. $

A.6 A2 Traffic Control 1 L.S. $

A.7 A6 Sediment and Erosion Control Measures

1 L.S. $

A.8 A7 Provide and maintain Tree Protection Zones. Include all signage and fencing as specified and as per the Arborist’s Report appended to this document..

1 L.S. $

A.9 A8 Remove trees as identified on the Contract Drawings and as specified and as per the Arborist’s Report appended to this document..

1 L.S. $

A.10 A9 Remove, store and re-install all street signs, including new posts to match existing.

1 L.S. $

A.11 A2 Protect and provide access to Canada Post community mailboxes.

1 L.S. $

TOTAL A – GENERAL CONTRACT ITEMS – PART 1

$

Page 6: Addendum No. 1 - PW-E-20-64 · Part 1 – B.5 Part 2 – B.9 Part 2 – B.25 Part 2 – B.30 . 2. Insert: Attachment G – Soil Sampling Report . Note: Attachment G – Soil Sampling

Revised Appendix B - Schedule of Items and Prices - Addendum No. 1 Tender Number: PW-E-20-64 Page 37 of 120 Tender Name: WATERMAIN REPLACEMENT AND NELSON STREET WEST RECONSTRUCTION

B. ROAD CONSTRUCTION – PART 1

Item

Spec

Description

Est. Qty.

Unit

Unit Price

Amount

B.1 B1 Remove and lawfully dispose of existing pavement surfaces from roadway.

2500 m2 $

B.2 B1, B7, B12

Saw cut and remove asphalt pavement and granulars from existing driveways and reinstate with 50mm HL3F asphalt surface overlying 150mm Granular A.

40 m2 $

B.3 B1, B7

Remove granular driveways and reinstate with 150mm Granular A.

100 m2 $

B.4 B1, B3, B7

Remove, stockpile and reinstate interlocking brick driveways including new base material.

20 m2 $

B.5 B1, B2

Grade & sub excavation to a depth of 150mm for road base including disposal of excess materials.

375 m3. $

B.6 B7 Supply, place and compact 150mm Granular "A" for roads .

900 t $

B.7 B11 Supply, place and compact 50mm HL3 surface course asphalt for roads (Based on AC Index of $800/t).

330 t $

B.8 B18 Pavement Markings

a) Stop Bars (600mm) 12 m $

B.9 B16 Supply and place 150mm of imported topsoil and sod

800 m2 $

B.10 - Supply and install bollard as per details on the contract drawings.

2 ea $

B.11 B2, B20

Remove and reinstate wooden fencing to match existing

a) Rita Park 1 L.S. $

b) Kiwanis 1 L.S. $

TOTAL B – ROAD CONSTRUCTION – PART 1 $

Page 7: Addendum No. 1 - PW-E-20-64 · Part 1 – B.5 Part 2 – B.9 Part 2 – B.25 Part 2 – B.30 . 2. Insert: Attachment G – Soil Sampling Report . Note: Attachment G – Soil Sampling

Revised Appendix B - Schedule of Items and Prices - Addendum No. 1 Tender Number: PW-E-20-64 Page 38 of 120 Tender Name: WATERMAIN REPLACEMENT AND NELSON STREET WEST RECONSTRUCTION

C. STORM SEWERS – PART 1

Item

Spec

Description

Est. Qty.

Unit

Unit Price

Amount

All supply and install costs are to include the removal of existing infrastructure that is within direct conflict with OR can reasonably be removed with the construction of new infrastructure. (By Vertical Trench, Native Backfill Material)

C.1 B2, C1

Remove and restore 600mm diameter CSP culvert to allow for watermain installation.

1 L.S. $

TOTAL C – STORM SEWERS – PART 1

$

D. SANITARY SEWERS – PART 1

Item

Spec

Description

Est. Qty.

Unit

Unit Price

Amount

All supply and install costs are to include the removal of existing infrastructure that is within direct conflict with OR can reasonably be removed with the construction of new infrastructure. (By Vertical Trench, Native Backfill Material)

D.1 D1 Provide new frames and grates to OPSD 401.010 Type A.

3 each $

TOTAL D – SANITARY SEWERS – PART 1

$

Page 8: Addendum No. 1 - PW-E-20-64 · Part 1 – B.5 Part 2 – B.9 Part 2 – B.25 Part 2 – B.30 . 2. Insert: Attachment G – Soil Sampling Report . Note: Attachment G – Soil Sampling

Revised Appendix B - Schedule of Items and Prices - Addendum No. 1 Tender Number: PW-E-20-64 Page 39 of 120 Tender Name: WATERMAIN REPLACEMENT AND NELSON STREET WEST RECONSTRUCTION

E. WATERMAINS – PART 1

Item

Spec

Description

Est. Qty.

Unit

Unit Price

Amount

All supply and install costs are to include the removal of existing infrastructure that is within direct conflict with OR can reasonably be removed with the construction of new infrastructure.

E.1 E1 Connect to Existing Watermain (includes couplings/fittings as required and also includes removal of all types of watermain, fittings and appurtenances.

a) Elm Avenue at Nelson Street 1 L.S. $

b) Kiwanis Avenue at Nelson Street (west connection)

1 L.S. $

c)Kiwanis Avenue at Nelson Street (east connection)

1 L.S. $

E.2 E1 200mm dia. PVC Class 150, DR 18 c/w all fittings, Typical Mechanical Thrust Restraint for PVC Pipe, anodes and tracer wire for connection to existing, PVC W/M, deflections noted on drawings, backflow preventer and testing complete. Complete with granular bedding and select native backfill.

410 m $

E.3 E1 Supply and install 200mm valve and valve boxes complete. Includes thrust restraints, zinc anode, and corrosion protection

5 each

E.4 E1 Supply and install 19mm (3/4") soft K copper water services complete including saddles, main stops, anodes and curb stops at property line and connections to existing services. (OPSD 1104.010)

24 each $

Page 9: Addendum No. 1 - PW-E-20-64 · Part 1 – B.5 Part 2 – B.9 Part 2 – B.25 Part 2 – B.30 . 2. Insert: Attachment G – Soil Sampling Report . Note: Attachment G – Soil Sampling

Revised Appendix B - Schedule of Items and Prices - Addendum No. 1 Tender Number: PW-E-20-64 Page 40 of 120 Tender Name: WATERMAIN REPLACEMENT AND NELSON STREET WEST RECONSTRUCTION

Item

Spec

Description

Est. Qty.

Unit

Unit Price

Amount

E.5 E1 Supply and install new hydrant with top flange 150mm above finished grade complete including secondary valve, 150mm lead, tracer wire and tracer wire termination box as detailed. Include thrust restraints, zinc anode and corrosion protection, and hydrant extension, if necessary.

1 each $

E.6 E1 Supply and install 50mm rigid insulation

15 m2 $

E.7 B2 Pressure grout and cap existing 100mm diameter watermain to be abandoned in place.

375 m $

E.8 E4 Supply, install, commission and maintain temporary water system complete.

1 L.S. $

E.9 E3 Commission new watermain. 1 L.S. $

TOTAL E – WATERMAINS – PART 1

$

Page 10: Addendum No. 1 - PW-E-20-64 · Part 1 – B.5 Part 2 – B.9 Part 2 – B.25 Part 2 – B.30 . 2. Insert: Attachment G – Soil Sampling Report . Note: Attachment G – Soil Sampling

Revised Appendix B - Schedule of Items and Prices - Addendum No. 1 Tender Number: PW-E-20-64 Page 41 of 120 Tender Name: WATERMAIN REPLACEMENT AND NELSON STREET WEST RECONSTRUCTION

F. PROVISIONAL ITEMS - PART 1

Item

Spec

Description

Est. Qty.

Unit

Unit Price

Amount

PROVISIONAL ITEMS ARE TO BE USED ONLY UPON AUTHORIZATION OF THE ENGINEER

F.1 A8 Tree Removal:

a) Trees less than 100mm in diameter

5 each $

b) Trees less than 250mm in diameter but greater than 100mm

5 each $

c) Trees greater than 250mm in diameter

3 each $

F.2 B19, D4, A5

Test Holes to Verify Location and Elevation of Existing Utilities:

a) Test Hole to 3m ‐ asphalt 3 each $

b) Test Hole to 3m ‐ grass 3 each $

F.3 B2 Supply, place and compact select subgrade material for trench backfill, including removal and disposal of material excavated from the trench and deemed unsuitable (organic material) as backfill.

20 m3 $

F.4 D2, A5

Reconnect existing sanitary service connections removed for watermain installation.

8 each $

F.5 - Supply and Application of Water for Dust Control

5 m3 $

F.6 C4 Supply, Place & Compact granular in lieu of Native Material

50 t $

F.7 E1 Supply & Place 19mm Clear Stone for Sewer and Watermain Pipe Bedding

50 t $

TOTAL F – PROVISIONAL ITEMS – PART 1

$

Page 11: Addendum No. 1 - PW-E-20-64 · Part 1 – B.5 Part 2 – B.9 Part 2 – B.25 Part 2 – B.30 . 2. Insert: Attachment G – Soil Sampling Report . Note: Attachment G – Soil Sampling

Revised Appendix B - Schedule of Items and Prices - Addendum No. 1 Tender Number: PW-E-20-64 Page 42 of 120 Tender Name: WATERMAIN REPLACEMENT AND NELSON STREET WEST RECONSTRUCTION

PART 2

A. GENERAL CONTRACT ITEMS – PART 2

Item Spec Description Est. Qty. Unit Unit Price Amount

A.1 A1 Mobilization, De-Mobilization and Insurance.

1 L.S. $

A.2 A4 Preconstruction Survey 1 L.S. $

A.3 A1 Site Trailer 1 L.S. $

A.4 A3, A5

Construction Layout, including Field Verification of inverts and pipe sizes

1 L.S. $

A.5 A2 Traffic Control 1 L.S. $

A.6 A6 Sediment and Erosion Control Measures

1 L.S. $

A.8 A7 Provide and maintain Tree Protection Zones. Include all signage and fencing as specified and as per the Arborist’s Report appended to this document..

1 L.S. $

A.9 A8 Prune and/or remove trees as identified on the Contract Drawings and as specified and as per the Arborist’s Report appended to this document..

1 L.S. $

A.10 A9 Remove, store and re-install all street signs, including new posts to match existing.

1 L.S. $

TOTAL A – GENERAL CONTRACT ITEMS – PART 2

$

Page 12: Addendum No. 1 - PW-E-20-64 · Part 1 – B.5 Part 2 – B.9 Part 2 – B.25 Part 2 – B.30 . 2. Insert: Attachment G – Soil Sampling Report . Note: Attachment G – Soil Sampling

Revised Appendix B - Schedule of Items and Prices - Addendum No. 1 Tender Number: PW-E-20-64 Page 43 of 120 Tender Name: WATERMAIN REPLACEMENT AND NELSON STREET WEST RECONSTRUCTION

B. ROAD CONSTRUCTION – PART 2

Item

Spec

Description

Est. Qty.

Unit

Unit Price

Amount

B.1 B1 Remove and lawfully dispose of existing pavement surfaces from roadway.

7700 m2 $

B.2 B1, B2

Saw cut and remove asphalt pavement from existing driveways.

970 m2 $

B.3 B1, B2

Saw cut and remove concrete pavement from existing driveways.

70 m2 $

B.4 B1 Remove interlocking brick driveway.

45 m2 $

B.5 B1 Remove granular driveways. 700 m2 $

B.6 B1, B2

Saw cut and remove existing concrete sidewalks.

280 m $

B.7 B2 Remove existing culverts and associated headwalls and dispose of all materials off site unless indicated otherwise.

26 ea $

B.8 B2 Remove existing landscaping features and return to homeowner as indicated on the Contract Drawings.

a) 660 Nelson Street 1 LS $

b) 710 Nelson Street 1 LS $

b) 712 Nelson Street 1 LS $

c) 726 Nelson Street 1 LS $

B.9 B1, B2

Excavation and Fill Placement

Excavate and grade to finished road subgrade including stockpiling of excavated materials.

3800 m3 $

Place and compact suitable existing materials as fill outside the limits of the new roadway to

1600 m3 $

Page 13: Addendum No. 1 - PW-E-20-64 · Part 1 – B.5 Part 2 – B.9 Part 2 – B.25 Part 2 – B.30 . 2. Insert: Attachment G – Soil Sampling Report . Note: Attachment G – Soil Sampling

Revised Appendix B - Schedule of Items and Prices - Addendum No. 1 Tender Number: PW-E-20-64 Page 44 Tender Name: WATERMAIN REPLACEMENT AND NELSON STREET WEST

of 120

RECONSTRUCTION

the limits of work. Compact to 95% SPMDD in vegetated areas and to 98% SPMDD under sidewalks and driveways in maximum 200mm thick lifts. Remove and dispose of excess 2200 m3 $ materials as specified and in accordance with all applicable legislation.

B.10 B2 Remove all existing curbs as 36 m $ required for the completion of the works.

B.11 B10 Supply and install 100mm sub 2000 m $ drains including Granular "A" bedding and all connections.

B.12 B6 Supply, place and compact 10100 t $ 400mm Type 2 Granular "B".

B.13 B7 Supply, place and compact 3800 t $ 150mm Granular "A" for roads, and driveways.

B.14 B5 Construct concrete curb and 1980 m $ gutter as per OPSD 600.040.

B.15 B11 Asphalt Milling 40mm deep at all 60 m2 $ joints to existing streets

B.16 B11 Supply, place and compact 80mm 2300 t $ HL8 base asphalt for roads (based on AC Index of $800/t).

B.17 B11 Supply and Application of Tack 60 m2 $ Coat

B.18 B11 Supply, place and compact 40mm 1150 t $ HL3 surface asphalt (based on AC Index of $800/t).

B.19 B7 Supply, 1 Granular A for driveway 1200 m2 $ reinstatement (150mm thick) for gravel, asphalt, and concrete driveways.

B.20 B12 Supply, place and compact 1050 m2 $ asphalt surface for driveway reinstatement. (50mm HL3F).

B.21 B14 Supply, place concrete surface for 25 m2 $ driveway reinstatement (150mm thick)

B.22 B13 Reinstate interlocking brick 10 m2 $ driveway.

B.23 B3 Concrete Sidewalk (OPSD 1250 m2 $ 310.010 - 310.050) Ramps must be 1.5 metres wide (North Side of Nelson)

Page 14: Addendum No. 1 - PW-E-20-64 · Part 1 – B.5 Part 2 – B.9 Part 2 – B.25 Part 2 – B.30 . 2. Insert: Attachment G – Soil Sampling Report . Note: Attachment G – Soil Sampling

Revised Appendix B - Schedule of Items and Prices - Addendum No. 1 Tender Number: PW-E-20-64 Page 45 of 120 Tender Name: WATERMAIN REPLACEMENT AND NELSON STREET WEST RECONSTRUCTION

B.24 B15, C2

Retaining Wall including handrail, river stone, geofabric, sub drain, and storm pipe penetrations including header pipe. Connection to storm sewer to be paid under item C.4

1 L.S. $

B.25 B21 Pedestrian Barricade including extended sidewalk (150mm) and slab thickening per OPSD 980.101

North Side of Nelson – Approximately 76m.

1 L.S. $

B.26 B4 Tactile Warning Plates – North Side of Nelson

4 each $

B.27 B18 Pavement Markings

a) Stop Bars (600mm) 28 m $

b) Yellow Centreline (Continuous) 930 m $

c) Crosswalk (2.5m) 80 m $

d) Bike Lanes (Continuous) 1745 m $

e) Bike Lanes (Dashed) 120 m $

f) Reserved Bike Lane Symbol 13 ea $

B.28 B22 Supply and installation of all new signage including posts.

1 LS $

B.29 B23 Removal and reinstatement of existing mailboxes.

3 ea $

B.30 B16 Stripping, stockpiling topsoil, and placement of topsoil and sod.

Strip existing vegetated areas and stockpile suitable topsoil for reuse. Remove and dispose of excess materials as specified and as per all applicable legislation.

10500 m2 $

Supply and place 150mm of topsoil and sod

6000 m2 $

TOTAL B – ROAD CONSTRUCTION – PART 2 $

Page 15: Addendum No. 1 - PW-E-20-64 · Part 1 – B.5 Part 2 – B.9 Part 2 – B.25 Part 2 – B.30 . 2. Insert: Attachment G – Soil Sampling Report . Note: Attachment G – Soil Sampling

Revised Appendix B - Schedule of Items and Prices - Addendum No. 1 Tender Number: PW-E-20-64 Page 46 of 120 Tender Name: WATERMAIN REPLACEMENT AND NELSON STREET WEST RECONSTRUCTION

C. STORM SEWERS – PART 2

Item

Spec

Description

Est. Qty.

Unit

Unit Price

Amount

All supply and install costs are to include the removal of existing infrastructure that is within direct conflict with OR can reasonably be removed with the construction of new infrastructure. (By Vertical Trench, Native Backfill Material)

C.1 C2 Supply and install 375mm PVC or 320 kPa HDPE storm sewer.

a) STM MH 15 to STM MH 14 25 m $

b) STM MH 14 to STM MH 13 41 m $

C.2 C2 Supply and install 525 mm Concrete Storm sewer

a) STM MH 1 to STM MH 2 26 m $

b) STM MH 2 to STM MH 3 100 m $

c) STM MH 3 to STM MH 4 100 m $

d) STM MH 4 to STM MH 5 112 m $

C.3 C2 Supply and install 600 mm Concrete Storm sewer

b) STM MH 5 to STM MH 7 106 m $

c) STM MH 7 to STM MH 8 103 m $

d) STM MH 8 to STM MH 9 100 m $

e) STM MH 9 to STM MH 10 100 m $

f) STM MH 10 to STM MH 11 74 m $

g) STM MH 11 to STM MH 12 76 m $

h) STM MH 12 to STM MH 16 4 m $

C.4 C2 Supply and install 250mm leads to new CBs. Include connection to main and to structure.

210 m $

Page 16: Addendum No. 1 - PW-E-20-64 · Part 1 – B.5 Part 2 – B.9 Part 2 – B.25 Part 2 – B.30 . 2. Insert: Attachment G – Soil Sampling Report . Note: Attachment G – Soil Sampling

Revised Appendix B - Schedule of Items and Prices - Addendum No. 1 Tender Number: PW-E-20-64 Page 47 of 120 Tender Name: WATERMAIN REPLACEMENT AND NELSON STREET WEST RECONSTRUCTION

Item

Spec

Description

Est. Qty.

Unit

Unit Price

Amount

C.5 C2 Supply and install 300mm leads to new DCBs. Include connection to main and to structure.

50 m $

C.6 C1 Supply and install 1200 mm precast concrete maintenance hole (OPSD 701.010) to finish asphalt elevation. The Contractor shall confirm and provide appropriate sizes to satisfy the OPSD requirements.

a) STM MH 1 1 each $

b) STM MH 2 1 each $

c) STM MH 3 1 each $

d) STM MH 4 1 each $

d) STM MH 8 1 each $

e) STM MH 9 1 each $

f) STM MH 10 1 each $

f) STM MH 14 1 each $

g) STM MH 15 1 each $

C.7 C1 Supply and install 1500 mm precast concrete maintenance holes (OPSD 701.012) to finish asphalt elevation. The Contractor shall confirm and provide appropriate sizes to satisfy the OPSD requirements.

a) STM MH 5 1 each $

c) STM MH 7 1 each $

g) STM MH 11 1 each $

h) STM MH 12 1 each $

C.8 C1 Supply and install 600mm x 600mm precast concrete CB (OPSD 705.010). Include all connections to leads. Setback where noted. Frame and Grate to be OPSD 400.100 (roadway) or OPSD 400.120 (grassed areas).

23 each $

Page 17: Addendum No. 1 - PW-E-20-64 · Part 1 – B.5 Part 2 – B.9 Part 2 – B.25 Part 2 – B.30 . 2. Insert: Attachment G – Soil Sampling Report . Note: Attachment G – Soil Sampling

Revised Appendix B - Schedule of Items and Prices - Addendum No. 1 Tender Number: PW-E-20-64 Page 48 of 120 Tender Name: WATERMAIN REPLACEMENT AND NELSON STREET WEST RECONSTRUCTION

Item

Spec

Description

Est. Qty.

Unit

Unit Price

Amount

C.9 C1 Supply and install 1450mm x 600mm precast concrete twin inlet CB (OPSD 705.020). Include all connections to leads. Setback where noted. Frame and Grate to be OPSD 400.110

6 each $

C.10 C1 Supply and install 600mm x 1200mm precast concrete Ditch Inlet (OPSD 705.060). Include all connections to leads. Setback where noted. Honeycomb Grate to be OPSD 403.010

3 each $

C.11 C1 Adjust existing STM MH A to meet new finished grade and provide new catchbasin frame and grate.

1 L.S.

C.12 C1, C2, C3, C4

Connection to Existing 2100mm diameter CSP Culvert including MH 13, MH 16, and the associated sewer pipes, drop structures, etc, as detailed on DWG DS.1.

1 L.S.

C.13 C2 Connect 100mm diameter drainage tile to new private sewer connection to storm sewer at approximately 0+800.

1 L.S. $

C.14 C2 Flush, CCTV inspection and report. 1 L.S. $

TOTAL C – STORM SEWERS – PART 2

$

Page 18: Addendum No. 1 - PW-E-20-64 · Part 1 – B.5 Part 2 – B.9 Part 2 – B.25 Part 2 – B.30 . 2. Insert: Attachment G – Soil Sampling Report . Note: Attachment G – Soil Sampling

Revised Appendix B - Schedule of Items and Prices - Addendum No. 1 Tender Number: PW-E-20-64 Page 49 of 120 Tender Name: WATERMAIN REPLACEMENT AND NELSON STREET WEST RECONSTRUCTION

D. SANITARY SEWERS – PART 2

Item

Spec

Description

Est. Qty.

Unit

Unit Price

Amount

All supply and install costs are to include the removal of existing infrastructure that is within direct conflict with OR can reasonably be removed with the construction of new infrastructure. (By Vertical Trench, Native Backfill Material)

D.1 D3 Supply and install 1200 mm precast concrete maintenance hole (SAN MH A) (OPSD 701.010) to finished grade elevation. The Contractor shall confirm and provide appropriate sizes to satisfy the OPSD requirements. Reconnect existing service connections.

1 each $

D.2 D1 Provide new frame and grates to OPSD 401.010 and riser sections as required to adjust existing sanitary maintenance hole structures to new finished grades. Remove and reinstall tapered tops as required.

a) SAN MH 1 1 each $

b) SAN MH 2 1 each $

c) SAN MH 3 1 each $

d) SAN MH 4 1 each $

e) SAN MH 5 1 each $

f) SAN MH 6 1 each $

g) SAN MH 7 1 each $

h) SAN MH 8 1 each $

i) SAN MH 9 1 each $

j) SAN MH 10 1 each $

Page 19: Addendum No. 1 - PW-E-20-64 · Part 1 – B.5 Part 2 – B.9 Part 2 – B.25 Part 2 – B.30 . 2. Insert: Attachment G – Soil Sampling Report . Note: Attachment G – Soil Sampling

Revised Appendix B - Schedule of Items and Prices - Addendum No. 1 Tender Number: PW-E-20-64 Page 50 of 120 Tender Name: WATERMAIN REPLACEMENT AND NELSON STREET WEST RECONSTRUCTION

k) SAN MH 11 1 each $

l) SAN MH 12 1 each $

m) SAN MH 13 1 each $

TOTAL D – SANITARY SEWERS – PART 2

$

E. WATERMAINS – PART 2

Item

Spec

Description

Est. Qty.

Unit

Unit Price

Amount

All supply and install costs are to include the removal of existing infrastructure that is within direct conflict with OR can reasonably be removed with the construction of new infrastructure.

E.1 E1 Connect to Existing Watermain (includes couplings/fittings as required and also includes removal of all types of watermain, fittings and appurtenances, including AC watermain.)

a) 150mm Connection at Coast Road at STA 0+178

1 ea $

b) 200mm Connection at Elm Avenue at STA 0+536

1 ea $

c) 200mm Connection at Kiwanis Avenue at STA 0+681

1 ea $

d) 200mm Connection at Kiwanis Avenue at STA 0+762

1 ea $

e)150mm Connection at Lakeview Crescent at STA 0+831

1 ea $

e)150mm Connection at Lakeview Crescent at STA 0+864

1 ea $

f) 300mm Connection at Mergl Drive at STA 1+033

1 ea $

g) 400m Connection at East Limit at STA 1+036

1 ea $

h) 300mm Connection at Water Treatment Plant

1 ea $

h) 400mm Connection at Water Treatment Plant

1 ea $

Page 20: Addendum No. 1 - PW-E-20-64 · Part 1 – B.5 Part 2 – B.9 Part 2 – B.25 Part 2 – B.30 . 2. Insert: Attachment G – Soil Sampling Report . Note: Attachment G – Soil Sampling

Revised Appendix B - Schedule of Items and Prices - Addendum No. 1 Tender Number: PW-E-20-64 Page 51 of 120 Tender Name: WATERMAIN REPLACEMENT AND NELSON STREET WEST RECONSTRUCTION

Item

Spec

Description

Est. Qty.

Unit

Unit Price

Amount

E.2 E1 400mm dia. PVC Class 150, DR 25 c/w all fittings, Typical Mechanical Thrust Restraint for PVC Pipe, anodes and tracer wire, PVC W/M, deflections noted on drawings, backflow preventer and testing complete. Complete with granular bedding and select native backfill.

940 m $

E.3 E1 500mm dia. PVC Class 150, DR 25 c/w all fittings, Typical Mechanical Thrust Restraint for PVC Pipe, anodes and tracer wire, PVC W/M, deflections noted on drawings, backflow preventer and testing complete. Complete with granular bedding and select native backfill.

46 m $

E.4 E1 Supply and install valve and valve boxes complete. Includes thrust restraints, zinc anode, and corrosion protection

b) 400mm 9 each $ c) 500mm 2 each $

E.5 E1, E2

Supply and install 19mm (3/4") soft K copper water services complete including saddles, main stops, anodes and curb stops at property line and connections to existing services. (OPSD 1104.010)

35 each $

E.6 E1, E2

Supply and install 25mm (1") soft K copper water services complete including saddles, main stops, anodes and curb stops at property line and connections to existing services. (OPSD 1104.010)

1 each $

E.7 E4 Supply, install, commission and maintain temporary water system complete as required for all tie-ins and maintenance of service throughout the work.

1 LS $

E.8 E3 Commission new watermains 1 LS $

TOTAL E – WATERMAINS – PART 2 $

Page 21: Addendum No. 1 - PW-E-20-64 · Part 1 – B.5 Part 2 – B.9 Part 2 – B.25 Part 2 – B.30 . 2. Insert: Attachment G – Soil Sampling Report . Note: Attachment G – Soil Sampling

Revised Appendix B - Schedule of Items and Prices - Addendum No. 1 Tender Number: PW-E-20-64 Page 52 of 120 Tender Name: WATERMAIN REPLACEMENT AND NELSON STREET WEST RECONSTRUCTION

F. PROVISIONAL ITEMS – PART 2

Item

Spec

Description

Est. Qty.

Unit

Unit Price

Amount

PROVISIONAL ITEMS ARE TO BE USED ONLY UPON AUTHORIZATION OF THE ENGINEER

F.1 A8 Tree Removal:

a) Trees less than 100mm in diameter

12 each $

b) Trees less than 250mm in diameter but greater than 100mm

6 each $

c) Trees greater than 250mm in diameter

6 each $

F.2 B19, D4, A5

Test Holes to Verify Location and Elevation of Existing Utilities:

a) Test Hole to 3m ‐ asphalt 10 each $

b) Test Hole to 3m ‐ grass 10 each $ F.3 B2 Supply, place and compact select

subgrade material for trench backfill, including removal and disposal of material excavated from the trench and deemed unsuitable (organic material) as backfill.

50 m3 $

F.4 - Supply and Application of Water for Dust Control

250 m3 $

F.5 C4 Supply, Place & Compact granular in lieu of Native Material

50 t $

F.6 E1 Supply & Place 19mm Clear Stone for Sewer and Watermain Pipe Bedding

50 t $

F.7 D2, A5

Reconnect existing sanitary service connections removed for watermain or storm sewer installation.

20 each $

F.8 E1 Supply and install 50mm rigid insulation as directed by the Engineer.

50 m2 $

Page 22: Addendum No. 1 - PW-E-20-64 · Part 1 – B.5 Part 2 – B.9 Part 2 – B.25 Part 2 – B.30 . 2. Insert: Attachment G – Soil Sampling Report . Note: Attachment G – Soil Sampling

Revised Appendix B - Schedule of Items and Prices - Addendum No. 1 Tender Number: PW-E-20-64 Page 53 of 120 Tender Name: WATERMAIN REPLACEMENT AND NELSON STREET WEST RECONSTRUCTION

Item

Spec

Description

Est. Qty.

Unit

Unit Price

Amount

F.9 E1, Watermain Offset for vertical separation as per details on drawings

1 each $

F.10 B21 Pedestrian Barricade including extended sidewalk (150mm) and slab thickening per OPSD 980.101

South Side of Nelson – Approximately 46m.

1 L.S. $

F.11 B3 Concrete Sidewalk (OPSD 310.010 -1 310.050) Ramps must be 1.5 metres wide (South Side of Nelson)

1425 m2 $

F.12 B4 Tactile Warning Plates – South Side of Nelson

20 each $

F.13 B24 Supply and place imported fill 150 m3 $

F.14 B17 Calcium Chloride for Dust Control 1 t $

F.15 E1 Supply and install new hydrants with top flange 150mm above finished grade complete including secondary valve, 150mm lead, tracer wire and tracer wire termination box as detailed. Include thrust restraints, zinc anode and corrosion protection, and hydrant extension.

5 each $

F.16 E1 Adjust existing fire hydrant so base is maximum 150mm above finished grade.

1 each $

F.17 C2 Connect existing drainage tile to new private sewer connection to storm sewer (based on 15m length and connection to main).

10 ea $

TOTAL F – PROVISIONAL ITEMS – PART 2

$

Page 23: Addendum No. 1 - PW-E-20-64 · Part 1 – B.5 Part 2 – B.9 Part 2 – B.25 Part 2 – B.30 . 2. Insert: Attachment G – Soil Sampling Report . Note: Attachment G – Soil Sampling

Revised Appendix B - Schedule of Items and Prices - Addendum No. 1 Tender Number: PW-E-20-64 Page 54 of 120 Tender Name: WATERMAIN REPLACEMENT AND NELSON STREET WEST RECONSTRUCTION

PART 1 – ELM AVENUE, MAPLE BOULEVARD, AND KIWANIS AVENUE SUMMARY

A. GENERAL CONTRACT ITEMS

$

B. ROAD CONSTRUCTION

$

C. STORM SEWER

$

D. SANITARY SEWERS

$

E. WATERMAINS

$

F. PROVISIONAL ITEMS

$

PART 1 - TOTAL (IN CANADIAN FUNDS)

$

PART 2 – NELSON STREET WEST RECONSTRUCTION SUMMARY

A. GENERAL CONTRACT ITEMS

$

B. ROAD CONSTRUCTION

$

C. STORM SEWER

$

D. SANITARY SEWERS

$

E. WATERMAINS

$

F. PROVISIONAL ITEMS

$

PART 2 - TOTAL (IN CANADIAN FUNDS)

$

Page 24: Addendum No. 1 - PW-E-20-64 · Part 1 – B.5 Part 2 – B.9 Part 2 – B.25 Part 2 – B.30 . 2. Insert: Attachment G – Soil Sampling Report . Note: Attachment G – Soil Sampling

Revised Appendix B - Schedule of Items and Prices - Addendum No. 1 Tender Number: PW-E-20-64 Page 55 of 120 Tender Name: WATERMAIN REPLACEMENT AND NELSON STREET WEST RECONSTRUCTION

TENDER SUMMARY – PART 1 + PART 2

PART 1 - TOTAL

$

PART 2 - TOTAL

$

SUBTOTAL (PART 1 + PART 2)

$

HST (13%)

$

TOTAL INCLUDING TAX (ALL PARTS)

$