adb-project-39595023

Upload: prabhu0487

Post on 03-Apr-2018

214 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/28/2019 ADB-Project-39595023

    1/5

    PROJECT DATA SHEETProject Data Sheets (PDS) contain summary information on the project or program: Because the PDS is a work in progress,some information may not be included in its initial version but will be added as it becomes available. Information aboutproposed projects is tentative and indicative.

    In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the AsianDevelopment Bank does not intend to make any judgments as to the legal or other status of any territory or area.

    FINANCING

    Type/Modality of Assistance Approval Number Source of FundingApproved Amount (US$

    thousand)

    Loan 2353 Ordinary capital resources 27,860

    Counterpart 16,150

    TOTAL US$ 44,010

    SAFEGUARD CATEGORIESFor more information about the safeguard categories, please see http://www.adb.org/site/safeguards/safeguard-categories

    PDS Creation Date 24 Mar 2008

    PDS Updated as of 07 Nov 2012

    Project Name Mong Duong 1 Thermal Power Project - Project 1

    Country Viet Nam

    Project/Program Number 39595-023

    Status Approved

    Geographical Location Northern Vietnam

    Sector and/or SubsectorClassification

    Energy / Conventional Energy

    Thematic Classification Economic growth

    Gender MainstreamingCategories

    Environment A

    Involuntary Resettlement

  • 7/28/2019 ADB-Project-39595023

    2/5

    SUMMARY OF ENVIRONMENTAL AND SOCIAL ISSUES

    The environmental impact assessment (EIA) conducted for Mong Duong 1 has identified and thoroughly assessed theanticipated project impacts on the physical, biological, and social aspects during the pre-construction, construction, andoperation phases. Alternatives pertaining to different project aspects were also examined. An environmental managementplan (EMP) has been developed, which includes (i) mitigation measures; (ii) monitoring program, (iii) associated costsbased on a 5-year pre-construction/construction period and 30 years of operation; and (iv) clear definition ofimplementation responsibilities. Land acquisition requirements have been minimized by locating the thermal power planton a site at the mouth of the Mong Duong River. The area is already in use for coal transport and storage. Based onpreliminary design available, it was estimated that 40 households, 10 companies, 390 farm/company workers, and 13fisherfolks will experience resettlement impacts and will have to be compensated and assisted. A full Resettlement Plan(RP) was prepared and the full RP have been updated following detailed design.

    STAKEHOLDER COMMUNICATION, PARTICIPATION, AND CONSULTATION

    DESCRIPTION

    The main objective of the proposed project is to expand the generating capacity of Electricity of Viet Nam (EVN) in orderto help mitigate shortage of power in Northern Viet Nam and to support industrial and economic growth. The Projectprovides for the construction of four units of 250 MW circulatory fluidized bed (CFB) generating units and the commonfacilities for another 1,000 MW to 1,200 MW installed generating capacity utilizing domestic coal as fuel. This constitutesas Phase 1 of the first stage development program envisaged to establish in two phases and increase the generatingcapacity of this new power station to 2,200 MW. The 2,000 MW Mong Duong Thermal Power Project will a mine mouth

    based power plant. The Project will include all works and equipment required for the development of 250 MW x 4 units ofCFB generating units. The Project will consist of the following components: (a) civil works for site preparation and commonworks, namely: (b) foundations, the power station building and cooling water circulation and other systems; (c) 250 MW x4 CFB coal-fired CFB boiler complete with all auxiliaries; (d) two reheat steam turbine generators each with a ratedcapacity of 500 MW, complete with auxiliaries; (e) instrumentation and control systems; (f) coal and ash handling systems;(g) water treatment and other miscellaneous mechanical plants; (h) transformers, switchyeard equipment and othermiscellaneous electricial equipment; and (i) consulting services

    PROJECT RATIONALE AND LINKAGE TO COUNTRY/REGIONAL STRATEGY

    The construction of the 1,000 MW Mong Duong 1 thermal power plant , together with site preparation and the common

    facilities for Mong Duong 2, will provide reliable electricity supply throughout the year in northern Vietnam. The mainbeneficiaries of the Project will be the industrial, commercial, residential, and rural consumers in northern Vietnam.

    A

    Indigenous Peoples C

    Environmental Aspects

    Involuntary Resettlement

    Indigenous Peoples

    During Project Design

    During Project Implementation

  • 7/28/2019 ADB-Project-39595023

    3/5

    DEVELOPMENT IMPACT

    PROJECT OUTCOME

    OUTPUTS AND IMPLEMENTATION PROGRESS

    BUSINESS OPPORTUNITIES

    Adequate and reliable supply of power to meet Viet Nam's electricity demand in anenvironmentally sustainable manner. Diversified generation fuel mix.

    Description of Outcome Progress Towards Outcome

    Households and industries in northern Viet Nam haveaccess to reliable, stable electricity supply

    Project is on track.

    Description of Project Outputs Status of Implementation Progress (Outputs, Activities,and Issues)

    Project completed: 1000 MW CFB technology coal-firedpower plant. Project is completed under Loan 2610-Tranche2: 1000 MW CFB technology coal-fired power plant; UnderTranche 1, Loan 2353: completion of site preparation forturnover to the construction contractors.

    All works and services completed. Pending outstandingpayment. Loan to close as scheduled.

    Date of First Listing 13 Nov 2006

    Consulting Services All consulting services to be financed under the Facility shall be procured inaccordance with ADB;s Guidelines on the Use of Consultants by the AsianDevelopment Bank and its Borrowers (2007), as amended from time to time.Consulting services shall be required for (i) reviewing the technical designs anddrawing (prepared by EVN); (ii) preparing bidding documents for selection of the EPCcontractor and other civil works packages in accordance with ADB tguidelines, toconstruct MD1 of the Investment Program; (iii) assisting EVN in bid evaluation,contract negotiations with the EPC contractor and other civil works contractor; (iv)supervising the site preparation and leveling works, and civil works; (v) preparing and

    environmental management plan (EMP), updating the resettlement plan, andsupervising the implementation of the EMP and resettlement plan by EVN; (vi)supervising work of the EPC contractor, reviewing operation and maintenancemanuals; (vii) preparing completion reports of the EPC package; (viii) capacitybuilding for counterpart staff and other EVN staff in new technology such ascirculating fluidized-bed (CBFB) technnlogoy; and (ix) overall project managmeent,procurement, invoicing and paand payments. the services will be provided throughconsulting firms appointed following international competition using the quality-and-cost-based selection (QCBS) method.

    Procurement All equipment and materials to be financed under the MFF shall be procured in

    accordance with ADB's Procurement Guidelines (2007). International competitivebidding (ICB) shall be used for the engineering, procurement and constructioncontract of the power plant and common facilities, for supply contracts estimated tocost the equivalent of or more than $1.0 million, and for civil works contracts more

  • 7/28/2019 ADB-Project-39595023

    4/5

    TIMETABLE

    MILESTONES

    Approval No. Approval Signing EffectivityClosing

    Original Revised Actual

    Loan 2353 02 Oct 2007 09 Oct 2007 27 Mar 2008 30 Jun 2013

    STATUS OF COVENANTSCovenants are categorized under the following categoriesaudited accounts, safeguards, social, sector, financial, economic, and others.Covenant compliance is rated by category by applying the following criteria: (i) Satisfactoryall covenants in the category are being compliedwith, with a maximum of one exception allowed, (ii) Partly Satisfactorya maximum of two covenants in the category are not being compliedwith, (iii) Unsatisfactorythree or more covenants in the category are not being complied with. As per the 2011 Public Communications Policy,covenant compliance ratings for Project Financial Statements apply only to projects whose invitation for negotiation falls after 2 April 2012.

    ApprovalNo.

    Category

    Sector Social Financial Economic Others Safe ProjectFinancial

    Statements

    Loan 2353 Satisfactory Satisfactory Satisfactory Satisfactory Satisfactory

    CONTACTS AND UPDATE DETAILS

    than $3 million. The national competitieittive bidding or limtied international biddingshall be used for supply contracts valued at less than $1.0 million. Civil workscontracts estimated at less than $3.0 million shall be procured following NCBprocedures acceptable to ADB. Miscellaneous goods and civil works contracts lessthan $100,000 shall be procured using shopping procedures. Contract packages shallbe prpeared to ensure maximum competition under ICB. Contract packages shall beprepared to ensure maximum competition under ICB. The relevant sections of ADB'sAnticorruption Policy shall be incorporated in bidding documents for all ADB-financedcontracts.

    Procurement and ConsultingNotices

    http://www.adb.org/projects/39595-023/business-opportunities

    Concept Clearance 29 Sep 2005

    Fact-finding 20 Jun 2006 to 03 Jul 2006

    Management Review Meeting 15 Aug 2006

    Approval 02 Oct 2007

    Last Review Mission

    Responsible ADB Officer Takafumi Kadono ([email protected])

    Responsible ADB Department Southeast Asia Department

  • 7/28/2019 ADB-Project-39595023

    5/5

    LINKS

    Responsible ADB Division Infrastructure Division, SERD

    Executing Agencies Viet Nam ElectricityMr. Le Duc Chan

    Project Website http://www.adb.org/projects/39595-023/main

    List of Project Documents http://www.adb.org/projects/39595-023/documents