adapting operational test to rapid acquisition programs · minimum viable product (mvp) • minimum...

41
1 Adapting Operational Test to Rapid Acquisition Programs Mr. Dave Beyrodt Mr. Dave Bisaillon Mr. Jacob Warren Mr. Dan Telford Lt Stu Corbett 11 Apr 2019

Upload: others

Post on 20-Jun-2020

7 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Adapting Operational Test to Rapid Acquisition Programs · Minimum Viable Product (MVP) • Minimum Operational Product (MOP) • Program increment (PI) • Release • Retrospective

1

Adapting Operational Testto Rapid Acquisition Programs

Mr. Dave BeyrodtMr. Dave BisaillonMr. Jacob WarrenMr. Dan Telford Lt Stu Corbett

11 Apr 2019

Page 2: Adapting Operational Test to Rapid Acquisition Programs · Minimum Viable Product (MVP) • Minimum Operational Product (MOP) • Program increment (PI) • Release • Retrospective

2

Overview

• Rapid Acquisition Terminology (5 min) − Mr. Dan Telford (AFOTEC)

• AFOTEC perspective on rapid acquisition (15 min) − Mr. Dan Telford, Lt Stu Corbett

• MCOTEA perspective on rapid acquisition (15 min) − Mr. Jacob Warren

• COTF perspective on rapid acquisition (15 min) − Mr. Dave Beyrodt, Mr. Dave Bisaillon

• ATEC perspective on rapid acquisition (15 min) • Panel Q&A session (25 min) − Mr. Beyrodt, Mr. Bisaillon, Mr. Warren, Mr. Telford, Lt

Corbett

Page 3: Adapting Operational Test to Rapid Acquisition Programs · Minimum Viable Product (MVP) • Minimum Operational Product (MOP) • Program increment (PI) • Release • Retrospective

3

Rapid Acquisition Terminology

Daniel TelfordAFOTEC/A-2/911 Apr 2019

Page 4: Adapting Operational Test to Rapid Acquisition Programs · Minimum Viable Product (MVP) • Minimum Operational Product (MOP) • Program increment (PI) • Release • Retrospective

4

• Clarify terminology• Differentiate between Acquisition (traditional, 804 )

programs and Agile (software) development

Overview• DoDI 5000.02 Traditional and Rapid acquisitions• NDAA Section 804 Middle Tier Rapid Prototyping/Fielding

acquisitions • Agile (software) development

Purpose

Page 5: Adapting Operational Test to Rapid Acquisition Programs · Minimum Viable Product (MVP) • Minimum Operational Product (MOP) • Program increment (PI) • Release • Retrospective

5

DoDI 5000.02 Traditional AcquisitionWaterfall (aka traditional)

Requirements and CONOPS

• Follows rules defined by DoDI 5000.02 with six basic models• May be accelerated when schedule is dominant (model 4) • May have competitive prototypes to support down select decisions• May include agile software development approach

Model Guidance DecisionsTraditional• ACAT I MDAPs• ACAT II/III• Timeline: > 5 yrs

• DoDI 5000.02• USC Title 10 (139, 2399,

2366)

• Traditional MS A, B, C• LRIP/FRP/FDD/IOC Note: Model 4

is concurrent production/ development with early fielding of LRIP articles prior to IOT&E

Development and DT

Operational Test

Field and Sustain

Page 6: Adapting Operational Test to Rapid Acquisition Programs · Minimum Viable Product (MVP) • Minimum Operational Product (MOP) • Program increment (PI) • Release • Retrospective

6

Middle Tier Acquisitions (aka 804s)

• NDAA 16, Section 804 provides authority − Rapidly prototype and/or rapidly field capabilities under a new pathway− Distinct from the traditional acquisition system

• USD A&S, the DOD Comptroller and VCJCS, shall establish guidance for a middle tier of acquisition programs

• Interim authority from USD A&S to implement Section 804, 16 Apr 18− Start policy development NLT 1 Jan 19− Direction to the services to establish processes/procedures by 30 Sep 19

Page 7: Adapting Operational Test to Rapid Acquisition Programs · Minimum Viable Product (MVP) • Minimum Operational Product (MOP) • Program increment (PI) • Release • Retrospective

7

Section 804 Rapid Prototyping and Fielding

Approved Requirements

Rapid Fielding

Sustain

Model Guidance DecisionsMiddle Tier Acquisition “Rapid Acquisition” of “Proven Technologies”

Timeline: 2 to 5 yrs

Can be any ACAT equivalent

NDAA 16 Section 804, PL 114-92USD A&S memo, 16 Apr 18

• Requirement Definition (non-JCIDS)• Production Decision w/in 6 months of

requirement definition• Operational performance demo/evaluation—

timing TBD• Production/fielding complete w/in 5 yrs of

requirement definitionMiddle Tier Acquisition“Rapid Prototyping and Fielding” of “Innovative Technologies”

Timeline: 2 to 5 yrs

Can be any ACAT equivalent

• Requirement Definition (non-JCIDS)• Prototype Production/Qty Decision - ASAP• Fielding decision following “Demo of Field-

able Prototypes in Ops Environment” w/in 5 yrs of defined requirement

• Follow-on transition decision to proceed • Rapid Acquisition Pathway• Traditional Acquisition Process

Rapid Prototyping5000.02 Acquisition804 Rapid Fielding

Page 8: Adapting Operational Test to Rapid Acquisition Programs · Minimum Viable Product (MVP) • Minimum Operational Product (MOP) • Program increment (PI) • Release • Retrospective

8

Agile is an Approach • FY18 NDAA (H.R. 2810) defines the term “Agile Acquisition”− “acquisition using agile or iterative development.”

• Agile or Iterative Development, with respect to software:− …acquisition pursuant to a methodology for delivering multiple, rapid, incremental

capabilities to the user for operational use, evaluation, and feedback; and …incremental development and fielding of capabilities, commonly called spirals, spins, or

sprints, which can be measured in a few weeks or months; and …continuous participation and collaboration by users, testers, and requirements

authorities

• Taken from commercial practices for software-based product development− Continuous collaboration between operations/development− Continuous integration, delivery, and deployment

• Programs titled “Agile” are part of other acquisition models• Numerous programs identify as agile acquisitions, they may be: − DoDI 5000.02 acquisitions, such as Model 3, Incrementally Deployed Software

Intensive Systems (e.g., DCGS)− NDAA Section 804 (e.g., PTES)

Page 9: Adapting Operational Test to Rapid Acquisition Programs · Minimum Viable Product (MVP) • Minimum Operational Product (MOP) • Program increment (PI) • Release • Retrospective

9

Agile Terminology• Agile: Describes a set of principles for software development under which

requirements and solutions evolve through the collaborative effort of self-organizing cross-functional teams

• Agile Release Train (ART)• Backlog• Capability• Continuous development• DevOps• Epic • Iteration• Minimum Viable Product (MVP)• Minimum Operational Product (MOP)• Program increment (PI)• Release• Retrospective• Scrum• Spiral

• Sprint

• Sustainment Readiness Gate (SRG)

• Use Cases

• User stories

• Value Stream

• …

• Start with Scaled Agile Framework (SAFe) definitions

• Program offices are modifying and adding new terms, so review within program context

Page 10: Adapting Operational Test to Rapid Acquisition Programs · Minimum Viable Product (MVP) • Minimum Operational Product (MOP) • Program increment (PI) • Release • Retrospective

10

Summary

• Acquisition terms can have different meanings and often misused • Agile terms varied and often misused• Different rules apply depending on the actual authority• We still have limited experience—we’re all learning as we go

Questions

Page 11: Adapting Operational Test to Rapid Acquisition Programs · Minimum Viable Product (MVP) • Minimum Operational Product (MOP) • Program increment (PI) • Release • Retrospective

11

Adapting Operational Testto Rapid Acquisition Programs

AFOTEC Examples

Daniel Telford1st Lt Stuart CorbettAFOTEC/A-2/911 Apr 2019

Page 12: Adapting Operational Test to Rapid Acquisition Programs · Minimum Viable Product (MVP) • Minimum Operational Product (MOP) • Program increment (PI) • Release • Retrospective

12

AFOTEC Adaptive Relevant Testing (AART)

Key Principles1. Early OT Involvement2. Tailor to Situation3. Continuous Feedback4. Streamline Processes & Products5. Integrate & Synchronize Test6. Adaptive

AART

Section 804Agile SW Dev

SAF/AQ ResponseSpeed of

Relevance

FasterAnd

Smarter

Enhanced/Integrated Partnership

Acq Ktr

OTDT

User

Page 13: Adapting Operational Test to Rapid Acquisition Programs · Minimum Viable Product (MVP) • Minimum Operational Product (MOP) • Program increment (PI) • Release • Retrospective

13

Steps for Designing a Test

0. Define the product and processes to be tested(the SUT and the COIs/Operations)

1. State the purpose or goals of the test2. Select the response variables3. Choice of factors, levels, and ranges (conditions)4. Choice of test design (test event matrix or TEM)5. Perform the test (test execution)6. Analysis of the data7. Conclusions and recommendations (test report)

Page 14: Adapting Operational Test to Rapid Acquisition Programs · Minimum Viable Product (MVP) • Minimum Operational Product (MOP) • Program increment (PI) • Release • Retrospective

14

Current AFOTEC Efforts

• Advanced Pilot Trainer (APT)• F-35 Continuous Capability Development & Delivery (C2D2)• B-2 Defensive Management System Modernization (DMS)• B-21 Raider• Protected Tactical Enterprise Service (PTES)• Nuclear Planning and Execution System (NPES)• Kessel Run (KR) Air Operations Center (AOC)• Integrated Strategic Planning and Analysis Network (ISPAN)• Distributed Common Ground System (DCGS)• …

Page 15: Adapting Operational Test to Rapid Acquisition Programs · Minimum Viable Product (MVP) • Minimum Operational Product (MOP) • Program increment (PI) • Release • Retrospective

15

APT

Transfer of skills

Reliability

Syllabus Availability

Supportability

A/C & GBTSMission tasks

• OT Strategy (Original)– “How well can it train?”

Transfer of skills

A/C Mission Tasks

Reliability

Availability

Supportability

GBTS Mission Tasks

• OT Strategy (Change)– “How well can it accomplish

training (mission) tasks?”

Page 16: Adapting Operational Test to Rapid Acquisition Programs · Minimum Viable Product (MVP) • Minimum Operational Product (MOP) • Program increment (PI) • Release • Retrospective

16

APT AART

• Scope of Test – Changed focus to capabilities• Test Design− Individual capability (operations) designs, characterize− Targets IOT&E, complete set early, but adaptable

• Measures – Established early, complete as test progresses

Periodic/Event-DrivenReports

Synchronized Test Phase Report

IOT&E Report

OM – Observation memoSTU – Synchronized Test UpdateOTRR – OT Readiness ReviewOA – Operational Assessment

Page 17: Adapting Operational Test to Rapid Acquisition Programs · Minimum Viable Product (MVP) • Minimum Operational Product (MOP) • Program increment (PI) • Release • Retrospective

17

NPES

AcquisitionPhases &Milestones

Deliveries

Alpha Phase Beta Phase

Rel 1

FY19Q1 Q2 Q3 Q4

FY20Q1 Q2 Q3 Q4

FY21Q1 Q2 Q3 Q4

FY22Q1 Q2 Q3 Q4

Rel 5Rel 6

Rel 7Rel 8

Continuous Prototyping Continuous Fielding

MOP

Rel 9

Rel 10

Rel 11

Rel 12

Rel 13

Rel 14

Rel 15

Rel 16

Rel 2Rel 3

Rel 4

PIG

Ded.OT&E

DT/OT

DT/OT

DT/OT

DT/OT

DT/OT

DT/OT

DT/OT

DT/OT

MVP

DT/OT

DT/OTDT/OT

DT/OT

DT/OT

DT/OTDT/OT

DT/OT

Anticipate first capabilities accepted and fielded by USSTRATCOM at MOP

Page 18: Adapting Operational Test to Rapid Acquisition Programs · Minimum Viable Product (MVP) • Minimum Operational Product (MOP) • Program increment (PI) • Release • Retrospective

18

Sub-System / Component / Module

Performance

SystemAttributes

Scope-Measure Pyramid

Desired Effects

Mission-scope

Capability-scope

Feature/Function-scope

Page 19: Adapting Operational Test to Rapid Acquisition Programs · Minimum Viable Product (MVP) • Minimum Operational Product (MOP) • Program increment (PI) • Release • Retrospective

19

NPES AART

FY 19

R1 R2

Sprint involvementassessment during

planning meetings @ start of each sprint

R3

Sprint review @ end of each sprint (written feedback if relevant)

R4 R5 R6 R7 R8 R9 R10 R11 R12 R14 R15 R16 R13

Sprint 3

Minimum Operational

Product (MOP)

Sustainment Readiness Gate (SRG)

FY 20 FY 21 FY 22

OTOT

Master OT

Plan

MasterOT

ConceptFinal SRG

ReportMOP Report

OT Key OT TouchpointSprint 2Sprint 1 Sprint 4

Observation Report

Observation Plan

Observation report (memo) @ end of each release

Page 20: Adapting Operational Test to Rapid Acquisition Programs · Minimum Viable Product (MVP) • Minimum Operational Product (MOP) • Program increment (PI) • Release • Retrospective

20

Infrastructure Value Stream

DCGS Program Predictability Required

• Must synchronize planning effectiveness, predictability, and resource economies-of-scale by:− Synchronizing and fixing deployment (release/fielding) schedules− Synchronizing deployment locations on a fixed schedules− Slipping deployment into the next release when slips occur

GEOINT Value Stream

SIGINT Value Stream

MultiINT Value Stream

When a slip is required, moves to next release cycle

Schedule driven synchronized releases enable planning

effectiveness, predictability, and resource economies

Notional alignment

14-week cycle

Page 21: Adapting Operational Test to Rapid Acquisition Programs · Minimum Viable Product (MVP) • Minimum Operational Product (MOP) • Program increment (PI) • Release • Retrospective

21

AFOTEC DCGS Agile Response

• AFOTEC executed a DCGS process improvement effort: − Eliminated numerous products (documents)− Modified document formats (plans/reports, RALOT

analysis) − Significantly cut internal and external coordination

timelines− Delegated some decision making to lower levels− Prioritized resources to support DCGS fielding tempo− Project a rigorous 2-week OUE for each release to schedule

assets− Prove much of the AFOTEC approach on the first DCGS HA

OUE

Rigorous 2-week OUE for each release to manage warfighter risk

Page 22: Adapting Operational Test to Rapid Acquisition Programs · Minimum Viable Product (MVP) • Minimum Operational Product (MOP) • Program increment (PI) • Release • Retrospective

22

Fixed OT&E Dates and DurationChallenges

• DCGS Agile Pathfinder offers four OT&E periods a year• OT&E duration from test start to report is 5 weeks− 14 calendar days for execution− 10 calendar days for analysis & reporting− 9 calendar days for reviews and approval

• Platforms, Sensors, and Ranges difficult to secure every quarter− Open Air Exercises and Unit Training Events used as

mitigation (when aligned)− Sensor Modeling and Simulation and Emulations − Mission Play Backs; Real World Missions and Shadowing

of operational missions

Page 23: Adapting Operational Test to Rapid Acquisition Programs · Minimum Viable Product (MVP) • Minimum Operational Product (MOP) • Program increment (PI) • Release • Retrospective

23

Summary

• How we test (meet the challenge) depends on:− How capability is developed

• Implications for test design and measurement− What are the test design goal(s)?

What test designs are “adequate” for the goal− When are test designs developed?− What / when are measures developed?

Level of conflict (test)• Resources and schedule to execute

Page 24: Adapting Operational Test to Rapid Acquisition Programs · Minimum Viable Product (MVP) • Minimum Operational Product (MOP) • Program increment (PI) • Release • Retrospective

Marine Corps Operational Test and Evaluation Activity

Adapting Operational Test to Rapid-Acquisition Programs

Page 25: Adapting Operational Test to Rapid Acquisition Programs · Minimum Viable Product (MVP) • Minimum Operational Product (MOP) • Program increment (PI) • Release • Retrospective

Agenda

• MCOTEA’s Mission• Rapid Background• Marine Corps Rapid Capabilities Office• What it means for MCOTEA

25

Page 26: Adapting Operational Test to Rapid Acquisition Programs · Minimum Viable Product (MVP) • Minimum Operational Product (MOP) • Program increment (PI) • Release • Retrospective

MCOTEA’s Mission

MCOTEA provides operational testing and evaluation for the Marine Corps and conducts additional testing and evaluation as required to support the Marine Corps mission to man, train, equip, and sustain a force in readiness.

• We exist because Marine Corps decision makers need information that is independent, objective, and most importantly . . . defensible for critical resource and acquisition decisions.

• Don’t Guess

26

Page 27: Adapting Operational Test to Rapid Acquisition Programs · Minimum Viable Product (MVP) • Minimum Operational Product (MOP) • Program increment (PI) • Release • Retrospective

Rapid Background

• Marine Corps has not designated any Middle Tier Acquisition (MTA) programs– MTA authorized by section 804 of 2016 NDAA– MTA not subject to JCIDS or DODI 5000.02

• SECNAVINST 5000.42 established the Rapid Prototyping, Experimentation and Demonstration (RPED) process– The preferred path to find a solution for a fleet or force priority needs

for which a suitable materiel solution cannot be readily identified– RPED rapidly trials solutions and assesses performance and

operational utility– RPED conducts a demonstration and user evaluation as quickly as

feasible27

Page 28: Adapting Operational Test to Rapid Acquisition Programs · Minimum Viable Product (MVP) • Minimum Operational Product (MOP) • Program increment (PI) • Release • Retrospective

Marine Corps Rapid Capability Office

• In October 2016, the Commandant of the Marine Corps (CMC) directed the formation of the Marine Corps Rapid Capabilities Office (MCRCO) to:– accelerate the identification, development, and assessment of

emergent and disruptive technology• emergent - newer, cheaper, evolutionary• disruptive - replaces existing technology, revolutionary

– provide operational assessments that inform requirement development and investment planning

• The MCRCO has no program of record responsibility, but rather limited authority to provide capability to equip forces for operational assessments

28

Page 29: Adapting Operational Test to Rapid Acquisition Programs · Minimum Viable Product (MVP) • Minimum Operational Product (MOP) • Program increment (PI) • Release • Retrospective

Marine Corps Rapid Capability Office

• Identifies select prototypes demonstrating military utility and affordability

• Matches operational needs to emergent technologies• Equips Marine Corps units for operational assessment

• MCRCO work culminates with a Capability Assessment Report (CAR) which informs the decisions to:– Pursue the technology as a Program of Record (POR) (accelerated

or deliberate)– Return the technology to the Marine Corps Warfighting Lab (MCWL)

Science and Technology for further development– Stop pursuit altogether

29

Page 30: Adapting Operational Test to Rapid Acquisition Programs · Minimum Viable Product (MVP) • Minimum Operational Product (MOP) • Program increment (PI) • Release • Retrospective

MCRCO Process Flow

30

Page 31: Adapting Operational Test to Rapid Acquisition Programs · Minimum Viable Product (MVP) • Minimum Operational Product (MOP) • Program increment (PI) • Release • Retrospective

What this means for MCOTEA

• Nirvana– Gets OTAs involved early and upfront– Help establish requirements and drive initial testing

towards the metrics that really mean something to the warfighter

– We become part of team, when before we weren’t, so we get to be added value – whatever we’re doing, we’re helping make it better than it was

31

Page 32: Adapting Operational Test to Rapid Acquisition Programs · Minimum Viable Product (MVP) • Minimum Operational Product (MOP) • Program increment (PI) • Release • Retrospective

What this means for MCOTEA

• Customer based approach– What’s our level of involvement?– What do we deliver?

• Full Test vs Demonstration (minimum viable product)– Provide a product with just enough features to learn how the

system aligns with user needs, and provide feedback for future product development

– Manage expectations

32

Evaluation Planning

Concept Planning

Detailed Planning

Event Execution

Data Reporting

Evaluation Reporting

MCOTEA Six-step Process

Page 33: Adapting Operational Test to Rapid Acquisition Programs · Minimum Viable Product (MVP) • Minimum Operational Product (MOP) • Program increment (PI) • Release • Retrospective

What this means for MCOTEA

• Rapid is a good way to build experience• Move fast but don’t sacrifice too much quality

– Experienced, well-trained people– Conflict resolution– Minimize Rework

• Make our organization more flexible, more agile– “MCRCO has the necessary resources and processes to

enable it to effectively execute 12 innovative projects per year by the end of FY 2020”

33

Page 34: Adapting Operational Test to Rapid Acquisition Programs · Minimum Viable Product (MVP) • Minimum Operational Product (MOP) • Program increment (PI) • Release • Retrospective

Programs

• TEMSOS – Tactical Electro-Magnetic Spectrum Operations and Support– RCO sponsored project to enhance small unit situational awareness, capability to communicate,

provide EA, etc.– Full Large Scale Test

• TFT – Total Force Translator– RCO sponsored to provide automatic two-way translation capabilities in operational setting– Full Small Scale Test

• LEON – Littoral Explosive Ordnance Neutralizer– RCO sponsored project to Marines’ ability to search, detect, locate, and confirm explosive hazards

and obstacles in the littoral zone– Small scale demonstration of various different platforms

• SPS – Shooting Performance System– Special interest project, non RCO. WFTBn Parris Island effort to decrease number of Marines

failing to qualify with their combat rifle. Close training “gap,” aid coaches in training their shooters, and create more lethal Marines

– < 2 months from contact to execution• LMMG – Lightweight Medium Machine Gun• ITIW – Integrated Tactical Information Warfare

34

Page 35: Adapting Operational Test to Rapid Acquisition Programs · Minimum Viable Product (MVP) • Minimum Operational Product (MOP) • Program increment (PI) • Release • Retrospective

Questions

Jacob [email protected]

35

Visit our website at https://hqmc.usmc.afpims.mil/Agencies/MCOTEA.aspx

Page 36: Adapting Operational Test to Rapid Acquisition Programs · Minimum Viable Product (MVP) • Minimum Operational Product (MOP) • Program increment (PI) • Release • Retrospective

BACKUP SLIDES

36

Page 37: Adapting Operational Test to Rapid Acquisition Programs · Minimum Viable Product (MVP) • Minimum Operational Product (MOP) • Program increment (PI) • Release • Retrospective

Recent Guidance

• Per SECNAVINST 5000.2F 26 Mar 2019– DoN T&E/OPNAV N94 will publish a SECNAVINST 5000.2TE

instruction that will apply to all USN/USMC ACAT programs, the various Accelerated and Rapid Acquisition Programs, Non-Developmental Items (NDI) and Commercial Off-the-Shelf (COTS) items

– QRAs are abbreviated OT&E events in support of the DoN Accelerated/Rapid Acquisition Process. There is no assessment of effectiveness or suitability.

37

Page 38: Adapting Operational Test to Rapid Acquisition Programs · Minimum Viable Product (MVP) • Minimum Operational Product (MOP) • Program increment (PI) • Release • Retrospective

Backup

Rapid Prototyping, Experimentation and Demonstration (RPED):An approach to fast-track the development, fielding, and assessment of prototypes to: demonstrate solutions to capability needs; inform concepts of operations and requirements development; and inform acquisition and resource planning, and, if necessary, provide limited fielding until a formal program can be established and a full system acquired. RPED initiatives are not formal acquisition programs, but may be used to support urgent needs processes in cases where a suitable material solution cannot be identified through the Service’s urgent need process.

38

Page 39: Adapting Operational Test to Rapid Acquisition Programs · Minimum Viable Product (MVP) • Minimum Operational Product (MOP) • Program increment (PI) • Release • Retrospective

Mission Based Test Design

11 April 2019Mr. Dave Beyrodt

COTF Director for Test Design

UNCLASSIFIED

UNCLASSIFIED

Page 40: Adapting Operational Test to Rapid Acquisition Programs · Minimum Viable Product (MVP) • Minimum Operational Product (MOP) • Program increment (PI) • Release • Retrospective

40

Mission Based Test Design

Page 41: Adapting Operational Test to Rapid Acquisition Programs · Minimum Viable Product (MVP) • Minimum Operational Product (MOP) • Program increment (PI) • Release • Retrospective

41

Questions