AD HOC JAIL PLANNING AND SPECIFICATIONS DEVELOPMENT COMMITTEE
MEETING AGENDA
Thursday, October 12, 2017 – 4:00 p.m.
Law Enforcement Center – EOC Room – Lower Level
555 W. Overlook Drive. – Ellsworth, WI
# Action Presenter 1 Call to order
1a. Establish quorum
1b. Approve agenda
Chair
2 Discuss/take action on minutes of 9/14/2017 Members
3 Committee will receive public comment not related to agenda items Members
4 Discuss/Take action to approve Change Order #16 regarding various changes
including additional circuits, drain tile along building, relocated conduit, change to
door 1130E, signage, door sweeps and narrow strips of mirror from below existing
mirror to the backsplash in the restrooms
Randy LaFaive
5 Discuss/Take action on PR #114 regarding furnish and install additional panel and
breaker Randy LaFaive
6 Discuss/Take action on PR #119 regarding chiller heat tape Randy LaFaive
7 Discuss/Take action on PR #121 regarding baby station replacement Randy LaFaive
8 Discuss/Take action on PR #124 regarding signage corrections due to signage issues Randy LaFaive
9 Discuss/Take action on PR #126 regarding additional electrical items Randy LaFaive 10 Discuss/Take action on PR #094 regarding re-painting five pod doors for caulking Randy LaFaive 11 Discuss/Take action regarding possible changes to monument sign Members 12 Review project budget Jo Ann Miller
13 Update on jail project progress Randy LaFaive
14 Transition team update Sheriff Staff
15 Future agenda items Members
16 Next meeting date Members
17 Adjourn Members
Questions regarding this agenda may be made to Jo Ann Miller at 715-273-6851, Ext. 6429. Upon reasonable notice, efforts will be made to accommodate the needs of individuals with disabilities requiring special
accommodations for attendance at the meeting. For additional information or to make a request, contact the Administrative
Coordinator at 715-273-3531, Ext. 6429.
A quorum of County Board supervisors may be present. (10/9/17)
Ad Hoc 3 Committee > 09/14/17 Page 1
UNAPPROVED MINUTES OF THE AD HOC JAIL PLANNING & SPECIFICATIONS DEVELOPMENT COMMITTEE MEETING HELD
September 14, 2017 – 4:00 p.m.
STATE OF WISCONSIN COUNTY OF PIERCE
} County Board Room; Courthouse 414 W. Main St., ELLSWORTH, WI 2017 - 11
1) Meeting Convened The Pierce County Ad Hoc Jail Planning & Specifications Development Committee met in the County Board
Room of the Pierce County Courthouse, Ellsworth, WI. Chairman J. Aubart called the meeting to order at
4:01 p.m.
1a) Those Present A quorum was established acknowledging 4 members present; 1 absent. Members present:
Jon Aubart District #3
Scott Bjork District #7
Neil Gulbranson District #11
Brian O’Connell Citizen Member
Absent/Excused:
Mike Kahlow District #6
Also Present: Jason Matthys-Chief Deputy Sheriff, Steve Albarado-Jail Administrator, Brad Lawrence-Corp
Counsel, & Jamie Feuerhelm-County Clerk.
1b) Agenda Approved
Motion by B. O’Connell/N. Gulbranson to move items #21 & #22 after item #3 & approve agenda as
amended; motion carried unanimously.
2) Minutes Approved Motion by N. Gulbranson/B. O’Connell to approve the minutes of Aug. 17, 2017 as presented; motion carried
unanimously.
3) Public Comment
None.
21) CLOSED SESSION Motion by S. Bjork/N. Gulbranson to convene in closed session at 4:03 p.m. pursuant to Sec. 19.85(1)(e)Wis.
Stats. for the purpose of deliberating or negotiating the purchasing of public properties, the investing of public
funds, or conducting other specified public business, whenever competitive or bargaining reasons require a
closed session, and pursuant to Sec. 19.85(1)(g) Wis. Stats. for the purpose of conferring with legal counsel
for the governmental body who is rendering oral or written advice concerning strategy to be adopted by the
body with respect to litigation in which it is or is likely to become involved: for the purpose of discussing
caulking contract / Waumandee Creek. Motion carried unanimously by roll call vote.
22) OPEN SESSION Committee returned to open session at 4:40 p.m. by motion of N. Gulbranson/S. Bjork; motion carried
unanimously by roll call vote. No action taken.
- B. Lawrence exited meeting.
4) Discuss/Take action to approve Change Order #15 regarding various changes including
Ad Hoc 3 Committee > 09/14/17 Page 2 of 3
additional electrical circuits and outlets, wiring adds, extra carpeting, add exit light, and door changes J. Aubart gave brief explanation regarding items previously approved by Committee incorporated in the
present CO #15. Motion by N. Gulbranson/B. O’Connell to approve Change Order #15 in the amount of
$7,500; motion carried unanimously.
5) Discuss/Take action on PR #99 regarding fireproofing contract out of project contingency Brief explanation given for additional fireproofing. Motion by N. Gulbranson/S. Bjork to approve PR#099 in
the amount of $25,097 from project contingency funds; motion carried unanimously.
6) Discuss/Take action on PR #112 regarding additional circuits to room 2201 Chief J. Matthys explained that once all electronic gear had arrived it was determined that additional electrical
circuits would be needed to operate the equipment efficiently & within manufacturers’ specifications. Motion
by B. O’Connell/S. Bjork to approve PR#112 in the amount of $4,336; motion carried unanimously.
7) Discuss/Take action on PR #113 regarding additional circuits in room 1316 Chief J. Matthys gave brief explanation for purpose of additional circuitry. Motion by N. Gulbranson/S.
Bjork to approve PR#113 in the amount of $608; motion carried unanimously.
8) Discuss/Take action on PR #114 regarding furnish and install additional panel and breaker Little information was available to the Committee to consider, in addition no one present to offer further
explanation. Committee did not take action on Item #8.
9) Discuss/Take action on PR #115 regarding drain tile along building Item previously discussed as something that needed to be done to ensure proper drainage. Lt. S. Albarado
offered summary detail. Motion by N. Gulbranson/B. O’Connell to approve PR#115 in the amount of $2,615;
motion carried unanimously.
10) Discuss/Take action on PR #116 regarding relocated conduit for Ham radio antenna J. Matthys offered brief explanation. Motion by N. Gulbranson/B. O’Connell to approve PR#116 in the
amount of $306; motion carried unanimously.
11) Discuss/Take action on PR #120 regarding change to door 1130E J. Matthys offered brief explanation. Motion by N. Gulbranson/B. O’Connell to approve PR#120 in the
amount of $1,011; motion carried unanimously.
12) Discuss/Take action on PR #122 regarding additional Motorola circuits J. Matthys offered brief explanation. Motion by B. O’Connell/S. Bjork to approve PR#122 in the amount of
$694 from Undesignated Reserve funds; motion carried unanimously.
13) Discuss/Take action on PR #117 regarding signage J. Matthys explained additional handicap signage was needed. Motion by N. Gulbranson/B. O’Connell to
approve PR#117 in the amount of $569; motion carried with 3 in favor & S. Bjork abstaining.
14) Discuss/Take action on PR #118 regarding door sweeps J. Matthys explained door sweeps were needed to help regulate air flow. Motion by N. Gulbranson/B.
O’Connell to approve PR#118 in the amount of $659; motion carried unanimously.
15) Discuss/Take action on PR #119 regarding chiller heat tape Little information was available to the Committee to consider, in addition no one present to offer further
Ad Hoc 3 Committee > 09/14/17 Page 3 of 3
explanation. Committee did not take action on Item #15.
16) Discuss/Take action on PR #123R regarding install arrow strip of mirror from below the existing mirror to the backsplash in the restrooms J. Matthys explained additional narrow strips of mirror needed to be added to backsplash in restrooms to
accommodate handicap compliance issues. Motion by N. Gulbranson/S. Bjork to approve PR#123R in the
amount of $204; motion carried unanimously.
17) Discuss/Take action regarding possible changes to monument sign Committee discussed changes previously suggested. Common census was to wait on this issue & pursue
other possible options as well. No action taken.
18) Review project budget AC JoAnn Miller not present to offer review, no updated submitted.
19) Update on Jail Project progress J. Matthys indicated that the facility is now being occupied by Sheriff’s Office staff. Also department is
working through punch lists with contractors on the finishing touches. Lt. S. Albarado working to gather all
necessary documents & certificates from contractors/manufacturers preparing for final inspections.
20) Transition team update Lt. S. Albarado stated that team is primarily involved in training staff on procedures & operations in the new
facility. Also installing required equipment & cleaning.
23) Future Agenda Items
Items 8, 15, & 17 above
Proposal Requests
Review project budget
Updates on project
24) Next Meeting Date Committee discussed when to schedule next meeting. Next meeting set for Oct. 12
th at 4:00 p.m., to be held
at the EOC Room in the new facility located at 555 W. Overlook Dr., Ellsworth.
25) Adjournment Meeting adjourned at 5:32 p.m. by motion of S. Bjork/N. Gulbranson; motion carried unanimously.
Respectfully submitted by: Jamie R. Feuerhelm, County Clerk
9/29/2017 Pierce County Mail - Pierce County - RFI 230 & 231
JoAnn Miller <[email protected]>
Pierce County - RFI 230 & 2312 messages
Jordan Lieffring <[email protected]> Wed, Sep 20, 2017 at 8:21 AM
To: JoAnn Miller <[email protected]>
Cc: Randy LaFaive <[email protected]>
JoAnn,
RFI 230 - Chiller Heat Tape
o The spec on 23 64 30 calls for heat tape on the chiller evaporator to be installed to prevent freezing. The
heat tape was provided with the chiller, but it requires 120V power to operate. The chiller is provided with a
single power point connection for operating components of the chiller, however, the heat trace tape is an
accessory and is not included with the single point power connection. Reasoning for this is so that if the
disconnect to the chiller was ever turned off the power to the heat trace tape would still be on. The 120V
power for the heat tape did not show up on the electrical plans for the electrician to provide. We were
directed by IMEG to connect the circuit for the heat tape to panel NLJA which was the closest one available
for 120V. This was an extra cost for B&B since it was not shown on their plans.
RFI 231 - UPS Sub Panel
o We needed to add two circuits to the UPS-0 panel for 13 power injectors for the exterior cameras. UPS-
O panel was completely full with the added circuits needed for the security and with moving circuits from
emergency OLHA to UPS. The most economical fix for this was to add a sub panel since there was room to
add with the original panel. This allowed for future space as well which was a concern with the IT
department.
IMartefeIJohnson
Adding ValutaBtryfftuy WtVe
Jordan Lieffring
Field Engineer
Mobile: 715-579-0176 • Main: 715-834-1213
www.market-johnson.com
ORS • CO "'■]'..• i !•';.;•:"" iO\! Ma\A(-M<S
JoAnn Miller <[email protected]> Wed, Sep 20, 2017 at 10:08 AM
To: Jordan Lieffring <[email protected]>
Cc: Randy LaFaive <[email protected]>
Thanks, Jordan
[Quoted text hidden]
https://mail.google.corn/mail/u/0/?ui=2&ik=6ac2ad5b5f&jsver^ 1/2
Market & Johnson, Inc. 2350 Galloway Street PO Box 630 Eau Claire WI 54702-0630 Ph. 715.834.1213 Fax. 715.834.2331
TO: DATE:
RE: Proposal Request (PR ) #114
ATTN:
REQUESTED BY WHOM:
COST OF WORK:
Changes to Market & Johnson's Scope of Work (see attached breakdown)4444... $45.00
Changes to Owner Direct Contracts (see attached breakdown)44444444. $2,260.00
Changes to Contingency that's in M&J's Contract4444444444 ($2,305.00)
TOTAL CHANGE TO PROJECT $0.00
The Contract Time will be unchanged by zero days for this change.
This proposal may be withdrawn by us if not accepted within 30 days.
Project Manager
Enclosures
cc:
PROPOSAL REQUEST (PR)
NOTES:
Randy LaFaive
Chad Oistad, Potter Lawson
Matt Koehler, Superintendent
DESCRIPTION
OF CHANGE:
RFI #231 - Furnish and install additional panel and breakers
Jo Ann Miller
August 21, 2017
TIME:
Pierce County Jail & Sheriff's Dept.
Ellsworth, WI 54011
Pierce County
414 W. Main Street
Ellsworth, WI 54011
Sincerely,
MARKET & JOHNSON, INC.
INSTRUCTIONS
RECEIVED:
If you would like us to proceed with this work prior to a formal change order being processed, please check the accepted box, sign and return. If accepted, this will be included on a future change order.
□ Accepted □ Not Accepted
_____________________________ ______________Signature Date
Breakdown for Proposal Request (PR ) #114 by Market & Johnson
Dated: 08/21/2017
M&J
Contract
Owner Direct
Contract
MARKET & JOHNSON QTY U/M UNIT COST
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
Subtotal for M&J's Labor, Material & Equipment (rounded) $0.00 $0.00 $0.00
SUBCONTRACTED WORK DESCRIPTION OF WORK
$2,260.00
Subtotal for Subcontracted Work (rounded) $0.00 $2,260.00 $0.00
Mark-up for M&J Labor, Material and Equipment 2.00% $0.00
Mark-up for Subcontracted Work 2.00% $45.00
Performance Bond $0.00
TOTAL FOR CHANGES TO SCOPE OF WORK $45.00 $2,260.00 $0.00
Change to Contingency that's in M&J's Contract ($2,305.00)
Total Change to M&J's Contract ($2,260.00)
TOTAL CHANGE TO PROJECT
RFI #23 Additional Panel & Breakers
Pierce County Jail & Sheriff's Dept.
Ellsworth, WI 54011
B&B Electric
$0.00
Market & Johnson, Inc. 2350 Galloway Street PO Box 630 Eau Claire WI 54702-0630 Ph. 715.834.1213 Fax. 715.834.2331
TO: DATE:
RE: Proposal Request (PR ) #119
ATTN:
REQUESTED BY WHOM:
COST OF WORK:
Changes to Market & Johnson's Scope of Work (see attached breakdown)5555... $48.00
Changes to Owner Direct Contracts (see attached breakdown)55555555. $2,399.00
Changes to Contingency that's in M&J's Contract5555555555 ($2,447.00)
TOTAL CHANGE TO PROJECT $0.00
The Contract Time will be unchanged by zero days for this change.
This proposal may be withdrawn by us if not accepted within 30 days.
Project Manager
Enclosures
cc:
PROPOSAL REQUEST (PR)
NOTES:
Randy LaFaive
Chad Oistad, Potter Lawson
Matt Koehler, Superintendent
DESCRIPTION
OF CHANGE:
RFI 230 Chiller Heat Tape
Jo Ann Miller
August 29, 2017
Owner
TIME:
Pierce County Jail & Sheriff's Dept.
Ellsworth, WI 54011
Pierce County
414 W. Main Street
Ellsworth, WI 54011
Sincerely,
MARKET & JOHNSON, INC.
INSTRUCTIONS
RECEIVED:
If you would like us to proceed with this work prior to a formal change order being processed, please check the accepted box, sign and return. If accepted, this will be included on a future change order.
□ Accepted □ Not Accepted
_____________________________ ______________Signature Date
Breakdown for Proposal Request (PR ) #119 by Market & Johnson
Dated: 08/29/2017
M&J
Contract
Owner Direct
Contract
MARKET & JOHNSON QTY U/M UNIT COST
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
Subtotal for M&J's Labor, Material & Equipment (rounded) $0.00 $0.00 $0.00
SUBCONTRACTED WORK DESCRIPTION OF WORK
$2,399.00
Subtotal for Subcontracted Work (rounded) $0.00 $2,399.00 $0.00
Mark-up for M&J Labor, Material and Equipment 2.00% $0.00
Mark-up for Subcontracted Work 2.00% $48.00
Performance Bond $0.00
TOTAL FOR CHANGES TO SCOPE OF WORK $48.00 $2,399.00 $0.00
Change to Contingency that's in M&J's Contract ($2,447.00)
Total Change to M&J's Contract ($2,399.00)
TOTAL CHANGE TO PROJECT
Pierce County Jail & Sheriff's Dept.
Ellsworth, WI 54011
B&B Electric
$0.00
Market & Johnson, Inc. 2350 Galloway Street PO Box 630 Eau Claire WI 54702-0630 Ph. 715.834.1213 Fax. 715.834.2331
TO: DATE:
RE: Proposal Request (PR ) #121
ATTN:
REQUESTED BY WHOM:
COST OF WORK:
Changes to Market & Johnson's Scope of Work (see attached breakdown)4444... $10.00
Changes to Owner Direct Contracts (see attached breakdown)44444444. $520.00
Changes to Contingency that's in M&J's Contract4444444444 ($530.00)
TOTAL CHANGE TO PROJECT $0.00
The Contract Time will be unchanged by zero days for this change.
This proposal may be withdrawn by us if not accepted within 30 days.
Project Manager
Enclosures
cc:
PROPOSAL REQUEST (PR)
NOTES:
Randy LaFaive
Chad Oistad, Potter Lawson
Matt Koehler, Superintendent
DESCRIPTION
OF CHANGE:
Baby Station Replacements
Jo Ann Miller
August 31, 2017
Owner
TIME:
Pierce County Jail & Sheriff's Dept.
Ellsworth, WI 54011
Pierce County
414 W. Main Street
Ellsworth, WI 54011
Sincerely,
MARKET & JOHNSON, INC.
INSTRUCTIONS
RECEIVED:
If you would like us to proceed with this work prior to a formal change order being processed, please check the accepted box, sign and return. If accepted, this will be included on a future change order.
□ Accepted □ Not Accepted
_____________________________ ______________Signature Date
Breakdown for Proposal Request (PR ) #121 by Market & Johnson
Dated: 08/31/2017
M&J
Contract
Owner Direct
Contract
MARKET & JOHNSON QTY U/M UNIT COST
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
Subtotal for M&J's Labor, Material & Equipment (rounded) $0.00 $0.00 $0.00
SUBCONTRACTED WORK DESCRIPTION OF WORK
$520.00
Subtotal for Subcontracted Work (rounded) $0.00 $520.00 $0.00
Mark-up for M&J Labor, Material and Equipment 2.00% $0.00
Mark-up for Subcontracted Work 2.00% $10.00
Performance Bond $0.00
TOTAL FOR CHANGES TO SCOPE OF WORK $10.00 $520.00 $0.00
Change to Contingency that's in M&J's Contract ($530.00)
Total Change to M&J's Contract ($520.00)
TOTAL CHANGE TO PROJECT
Pierce County Jail & Sheriff's Dept.
Ellsworth, WI 54011
$0.00
Bartley Sales
1
Julie Schmidt
Subject: FW: BARTLEY // PO 57-5226-RGA request for a KB110-SSRE / Case# 268667 0
From: Allen Bechstein [mailto:[email protected]]
Sent: Thursday, May 04, 2017 8:22 AM
To: 'Jordan Lieffring' <[email protected]>
Cc: 'Randy LaFaive' <[email protected]>
Subject: RE: BARTLEY // PO 57-5226-RGA request for a KB110-SSRE / Case# 268667 0
Jordan,
Do you have specific paper work that needs to be completed?
Otherwise our e-mail pricing is our typical request for CO.
Pricing again here.
Materials:
2 only – Koala Baby Changing Stations
(horizontal/Surface mount)
Model KB200-00
Color: cream
Your cost, delivered, $520.00 + tax if applicable
Please advise if/how you wish to proceed.
*should you elect to proceed:
• Provide CO# for billing purposes if available
• Provide complete shipping address for material delivery
• Provide contact information (name/Phone) for material delivery
• Provide date requested for materials to be on site
Thanks,
Allen Bechstein
Bartley Sales Company | Project Manager
6509 cambridge Street, St. Louis Park, MN 55426
phone: (952)-929-0001 | Fax: (952)-929-4733 | Web: www.bartleysales.com
nt-Subdomain:bobrick
Market & Johnson, Inc. 2350 Galloway Street PO Box 630 Eau Claire WI 54702-0630 Ph. 715.834.1213 Fax. 715.834.2331
TO: DATE:
RE: Proposal Request (PR ) #124
ATTN:
REQUESTED BY WHOM:
COST OF WORK:
Changes to Market & Johnson's Scope of Work (see attached breakdown)…………... $11.00
Changes to Owner Direct Contracts (see attached breakdown)……………………. $550.00
Changes to Contingency that's in M&J's Contract………………………… ($561.00)
TOTAL CHANGE TO PROJECT $0.00
The Contract Time will be unchanged by zero days for this change.
This proposal may be withdrawn by us if not accepted within 30 days.
Project Manager
Enclosures
cc:
Sincerely,
MARKET & JOHNSON, INC.
INSTRUCTIONS
RECEIVED:
Sand and repaint areas that required new signage - Backcharge to Designer Signs
Jo Ann Miller
September 21, 2017
Owner
TIME:
Pierce County Jail & Sheriff's Dept.
Ellsworth, WI 54011
Pierce County
414 W. Main Street
Ellsworth, WI 54011
PROPOSAL REQUEST (PR)
NOTES:
Randy LaFaive
Chad Oistad, Potter Lawson
Matt Koehler, Superintendent
DESCRIPTION
OF CHANGE:
If you would like us to proceed with this work prior to a formal change order being processed, please check the accepted box, sign and return. If accepted, this will be included on a future change order.
□ Accepted □ Not Accepted
_____________________________ ______________ Signature Date
Breakdown for Proposal Request (PR ) #124 by Market & Johnson
Dated: 09/21/2017
M&J
Contract
Owner Direct
Contract
MARKET & JOHNSON QTY U/M UNIT COST
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
Subtotal for M&J's Labor, Material & Equipment (rounded) $0.00 $0.00 $0.00
SUBCONTRACTED WORK DESCRIPTION OF WORK
$550.00
Subtotal for Subcontracted Work (rounded) $0.00 $550.00 $0.00
Mark-up for M&J Labor, Material and Equipment 2.00% $0.00
Mark-up for Subcontracted Work 2.00% $11.00
Performance Bond $0.00
TOTAL FOR CHANGES TO SCOPE OF WORK $11.00 $550.00 $0.00
Change to Contingency that's in M&J's Contract ($561.00)
Total Change to M&J's Contract ($550.00)
TOTAL CHANGE TO PROJECT $0.00
Allied Painting
Pierce County Jail & Sheriff's Dept.
Ellsworth, WI 54011
Market & Johnson, Inc. 2350 Galloway Street PO Box 630 Eau Claire WI 54702-0630 Ph. 715.834.1213 Fax. 715.834.2331
TO: DATE:
RE: Proposal Request (PR ) #126
ATTN:
REQUESTED BY WHOM:
COST OF WORK:
Changes to Market & Johnson's Scope of Work (see attached breakdown)4444... $41.00
Changes to Owner Direct Contracts (see attached breakdown)44444444. $2,070.00
Changes to Contingency that's in M&J's Contract4444444444 ($2,111.00)
TOTAL CHANGE TO PROJECT $0.00
The Contract Time will be unchanged by zero days for this change.
This proposal may be withdrawn by us if not accepted within 30 days.
Project Manager
Enclosures
cc:
Sincerely,
MARKET & JOHNSON, INC.
INSTRUCTIONS
RECEIVED:
Additional Electrical Items: Emergency Lighting & Power for Steam Table
Jo Ann Miller
September 22, 2017
Owner
TIME:
Pierce County Jail & Sheriff's Dept.
Ellsworth, WI 54011
Pierce County
414 W. Main Street
Ellsworth, WI 54011
PROPOSAL REQUEST (PR)
NOTES:
Randy LaFaive
Chad Oistad, Potter Lawson
Matt Koehler, Superintendent
DESCRIPTION
OF CHANGE:
If you would like us to proceed with this work prior to a formal change order being processed, please check the accepted box, sign and return. If accepted, this will be included on a future change order.
□ Accepted □ Not Accepted
_____________________________ ______________Signature Date
Breakdown for Proposal Request (PR ) #126 by Market & Johnson
Dated: 09/22/2017
M&J
Contract
Owner Direct
Contract
MARKET & JOHNSON QTY U/M UNIT COST
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
Subtotal for M&J's Labor, Material & Equipment (rounded) $0.00 $0.00 $0.00
SUBCONTRACTED WORK DESCRIPTION OF WORK
$1,527.00
$543.00
Subtotal for Subcontracted Work (rounded) $0.00 $2,070.00 $0.00
Mark-up for M&J Labor, Material and Equipment 2.00% $0.00
Mark-up for Subcontracted Work 2.00% $41.00
Performance Bond $0.00
TOTAL FOR CHANGES TO SCOPE OF WORK $41.00 $2,070.00 $0.00
Change to Contingency that's in M&J's Contract ($2,111.00)
Total Change to M&J's Contract ($2,070.00)
TOTAL CHANGE TO PROJECT $0.00
B&B
B&B
Power for Steam Table
Emergency Lighting in Pods A, B, H
Pierce County Jail & Sheriff's Dept.
Ellsworth, WI 54011
Market & Johnson, Inc. 2350 Galloway Street PO Box 630 Eau Claire WI 54702-0630 Ph. 715.834.1213 Fax. 715.834.2331
TO: DATE:
RE: Proposal Request (PR ) #094
ATTN:
REQUESTED BY WHOM:
COST OF WORK:
Changes to Market & Johnson's Scope of Work (see attached breakdown)5555... $6.00
Changes to Owner Direct Contracts (see attached breakdown)55555555. $302.00
Changes to Contingency that's in M&J's Contract5555555555 ($308.00)
TOTAL CHANGE TO PROJECT $0.00
The Contract Time will be unchanged by zero days for this change.
This proposal may be withdrawn by us if not accepted within 30 days.
Project Manager
Enclosures
cc:
PROPOSAL REQUEST (PR)
NOTES:
Randy LaFaive
Chad Oistad, Potter Lawson
Matt Koehler, Superintendent
DESCRIPTION
OF CHANGE:
Re-paint five pod doors due caulking being redone
Jo Ann Miller
July 14, 2017
Owner
TIME:
Pierce County Jail & Sheriff's Dept.
Ellsworth, WI 54011
Pierce County
414 W. Main Street
Ellsworth, WI 54011
Sincerely,
MARKET & JOHNSON, INC.
INSTRUCTIONS
RECEIVED:
If you would like us to proceed with this work prior to a formal change order being processed, please check the accepted box, sign and return. If accepted, this will be included on a future change order.
□ Accepted □ Not Accepted
_____________________________ ______________Signature Date
Breakdown for Proposal Request (PR ) #094 by Market & Johnson
Dated: 07/14/2017
M&J
Contract
Owner Direct
Contract
MARKET & JOHNSON QTY U/M UNIT COST
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
Subtotal for M&J's Labor, Material & Equipment (rounded) $0.00 $0.00 $0.00
SUBCONTRACTED WORK DESCRIPTION OF WORK
$302.00
Subtotal for Subcontracted Work (rounded) $0.00 $302.00 $0.00
Mark-up for M&J Labor, Material and Equipment 2.00% $0.00
Mark-up for Subcontracted Work 2.00% $6.00
Performance Bond $0.00
TOTAL FOR CHANGES TO SCOPE OF WORK $6.00 $302.00 $0.00
Change to Contingency that's in M&J's Contract ($308.00)
Total Change to M&J's Contract ($302.00)
TOTAL CHANGE TO PROJECT
Pierce County Jail & Sheriff's Dept.
Ellsworth, WI 54011
$0.00
Allied Painting