activity- jobs time (hours) preceding activities-jobs decorating & furnishing a spare bedroom 1...
TRANSCRIPT
Activity- JobsTime
(hours)Preceding
Activities-Jobs
Decorating & furnishing a spare bedroom
1Remove old furnitureRemove carpetTake down curtains & railRemove wallpaper
0.5
0.52
A
B C
A
B
CD
Prepare wallsPrepare woodworkPaint walls & ceiling 1st coat (& dry)Paint woodwork (& dry)
Lay new carpetPut up curtain rail & hang curtainsArrange new furniture
Paint walls & ceiling 2nd coat (& dry)
EF
GH
I
JKL
M
0.5
1.5
58
52
11
0.5Put up posters
DD
EF
GH I
H IJ
I
Latest finish time
Earliest start time
Activity
DurationHow long it takes
1
BLatest finish time
Earliest start time
Activity
Duration
0.51.5
Activity B
Remove carpet
Using Labels to Identify the Activity
K
1
End0
M
0.5
L
1
I5
G5
F
1.5
E
0.5
D
2
C0.5
B
0.51
A
Start
00
0 1
0
3.5
3.5
1.5
4 9
J2
14
14
16
17 17
Draw an activity networkShow the time needed for each activity
14
8
H
5
A starts at 0 and takes 1 hrSo B starts at 1C starts at 0 and takes 0.5 hrSo D could start at 0.5 hrsB starts at 1 and takes 0.5 hrSo D must start at 1.5 hrs as both B and C must be finished.D starts at 1.5 and takes 2 hrSo E and F must start at 3.5 hrsI starts at 9 and takes 5 hrSo J, K and M must start at 14 hrsH starts at 5 and takes 8 hr = 13hrs But J and K must start after both H and I so use 14 hrs
L starts at 16 and takes 1 hr = 17 hrs So End is at 17 hrsK starts at 14 and takes 1 hr = 15 hrsM starts at 14 and takes 0.5 hr = 14.5 hrs But End must occur after M,L and K are finished so use 17 hrs
Put up posters
1Remove old furnitureRemove carpetTake down curtains & railRemove wallpaper
0.50.52
A
B C
ABCD
Prepare wallsPrepare woodworkPaint walls & ceiling 1st coat (& dry)Paint woodwork (& dry)
Lay new carpetPut up curtain rail & hang curtainsArrange new furniture
Paint walls & ceiling 2nd coat (& dry)
EFGHIJKLM
0.51.5585211
0.5
DDEFG
H IH I
JI
Carry out a forward pass to show earliest possible start times
Latest finish time
Earliest start time
Activity
Duration
1.5
0.5
13
14
13
14 14.5
15
17
K
1
End0
M
0.5
L
1
I5
G5
F
1.5
E
0.5
D
2
C0.5
B
0.51
A
Start
00 0
0 1 1 1.5
0 1.5
3.5 4
3.5 6
1.5 3.5
4 9 9 14
J2 16
14 17
14 17
16 17
17 17
Draw an activity network
Carry out a reverse pass to show latest possible finish times
Show the time needed for each activity
14
8
H
5 14
M ends at 17 and takes 0.5 hr so I could end at 17 – 0.5 = 16.5 hrs
But J ends at 16 and takes 2 hrs so I ends at 16 – 2 = 14 hrs
K ends at 17 and takes 1 hr so I could end at 17 – 1 = 16 hrs
But I must end before M,J and K start so use 14 hrs – lowest value
J ends at 16 and takes 2 hr so H ends at 16 – 2 = 14 hrs
K ends at 17 and takes 1 hr so H could end at 17 – 1 = 16 hrs
But H must end before J and K start so use 14 hrs – lowest value
L ends at 17 and takes 1 hr so J ends at 17 – 1 = 16 hrsE ends at 4 and takes 0.5 hr so D ends at 4 – 0.5 = 3.5 hrs
F ends at 6 and takes 1.5 hr so D could end at 6 – 1.5 = 4.5 hrs
But D must end before E and F start so use 3.5 hrs – lowest value
16.5 14 16
1614
Critical activities must start on time if the project is not to be delayed.
K
1
End0
M
0.5
L
1
I5
G5
F
1.5
E
0.5
D
2
C0.5
B
0.51
A
Start
00 0
0 1 1 1.5
0 1.5
3.5 4
3.5 6
1.5 3.5
4 9 9 14
J2 16
14 17
14 17
16 17
17 17
Draw an activity networkShow the time needed for each activity
14
Find a critical path
Start A B D E G I J L End
8
H
5 14
Earliest start time + duration = Latest finish time
Critical path analysis
Step 1 List the activities with a time estimate for each.
Step 2 Note which activities must precede others.
Step 3 Draw an activity network, including the time for each activity.
Step 4 Carry out a forward pass to find the earliest possible start times.
Step 5 Carry out a reverse pass to find the latest possible finish times.
Step 6 Identify critical activities and find a critical path.
Critical activities must start on time if the project is not to be delayed.
A Furniture removal
B Carpet removal
D Wallpaper removal
E Wall preparation
G 1st coat on walls
I 2nd coat on walls
J Carpet laying
L Arranging new furniture
must start at 0 hours – lasts 1hr
must start at 1 hour – lasts 0.5hrs
must start at 1.5 hours – lasts 2hrs
must start at 3.5 hours – lasts 0.5hrs
must start at 4 hours – lasts 5hrs
must start at 9 hours – lasts 5hrs
must start at 14 hours – lasts 2hrs
must start at 16 hours
Earliest start time + duration = Latest finish time
They are those for which:
Start A B D E G I J L End
ActivityEarliest
startLatest finishDuration Float
The other activities have some flexibility in their start time.
C Remove curtain & rail
F Prepare woodwork
H Paint woodwork
K Put up curtain & rail
M Put up posters
0 1.5 1 h
3.5 6 1 h
5 14 1 h
14 17 2 h
14 17 2.5 h
Float = latest finish time – earliest start time – duration
0.5
1.5
8
1
0.5
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17A B D E G I J L
CF
H
K
Put the critical activities along the bottom
M
K
1
End0
M
0.5
L
1
I5
G5
F
1.5
E
0.5
D
2
C0.5
B
0.51
A
Start
00 0
0 1 1 1.5
0 1.5
3.5 4
3.5 6
1.5 3.5
4 9 9 14
J2 16
14 17
14 17
16 17
17 17
14
8
H
5 14
Gantt Chart
These activities must be started and completed on timeNow put in the non–critical activities at their earliest start timeFinally show the float time
How many people are needed to complete the job?
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17A B D E G I J L
C F H K M
K
1
End0
M
0.5
L
1
I5
G5
F
1.5
E
0.5
D
2
C0.5
B
0.51
A
Start
00 0
0 1 1 1.5
0 1.5
3.5 4
3.5 6
1.5 3.5
4 9 9 14
J2 16
14 17
14 17
16 17
17 17
14
8
H
5 14
Gantt Chart
One person can do the critical activities
If activity M is completed after K then the 2nd person can do the other jobs.
Alternative Gannt Chart – this is the version needed in the exam
Duration RedFloat BlueThe critical activities have no float