To: Engr. Turki A. Al Ahmari Date:10.01.2015
Project Manager, SEC-EHVPD
Subject: Reinforcement of Khulais 380/110/13.8 kV BSP
Civil works Activities done during the week (from 4th to 10th of Jan. 2015)
___________________________________________________________________
A. 380 KV Area : a-Concreting and adjusting the cover seat offset on the walls and finishing of cable trench: 60% completed.b- Fixing of cover seating channel on top of cable trench: 60% completed. c- Final Finishing painting of pedestals: 80% completed
B. 110 KV Area:
C.110KV duct bank and manholes: a- Excavation has completed but further work has been stooped due to some design problem of cable
bending curvature and radius. (Waiting for the revised approved drawings.)