To: Engr. Turki A. Al Ahmari Date:10.01.2015 Project Manager, SEC-EHVPD Subject: Reinforcement of Khulais 380/110/13.8 kV BSP Civil works Activities done during the week (from 4 th to 10 th of Jan. 2015) ___________________________________________________________________ A. 380 KV Area : a-Concreting and adjusting the cover seat offset on the walls and finishing of cable trench: 60% completed. b- Fixing of cover seating channel on top of cable trench: 60% completed. c- Final Finishing painting of pedestals: 80% completed B. 110 KV Area: C.110KV duct bank and manholes : a- Excavation has completed but further work has been stooped due to some design problem of cable bending curvature and radius. (Waiting for the revised approved drawings.)

Upload: mahnooranjum

Post on 23-Dec-2015

1 views

Category:

Documents


0 download

DESCRIPTION

construction activities

TRANSCRIPT

Page 1: Activities Done During a Week From 4th to 10th of Jan 2015

To: Engr. Turki A. Al Ahmari Date:10.01.2015

Project Manager, SEC-EHVPD

Subject: Reinforcement of Khulais 380/110/13.8 kV BSP

Civil works Activities done during the week (from 4th to 10th of Jan. 2015)

___________________________________________________________________

A. 380 KV Area : a-Concreting and adjusting the cover seat offset on the walls and finishing of cable trench: 60% completed.b- Fixing of cover seating channel on top of cable trench: 60% completed. c- Final Finishing painting of pedestals: 80% completed

B. 110 KV Area:

C.110KV duct bank and manholes: a- Excavation has completed but further work has been stooped due to some design problem of cable

bending curvature and radius. (Waiting for the revised approved drawings.)