action-ss june 9, 2020 attachments board of education of ... · dr. samuel mudd, eva turner and dr....
TRANSCRIPT
Action-SS June 9, 2020 Attachments
BOARD OF EDUCATION OF CHARLES COUNTY AGENDA ITEM
SUBJECT FY 2021 Educational Facilities Master Plan (EFMP)
OVERVIEW The EFMP is the first step in the state's school construction program process that leads to the development and approval of a state supported Capital Improvements Program (CIP). Revisions to the EFMP are submitted annually to the Maryland Department of Planning by July 1. This plan is an “identification of needs document.” The CIP is developed later in the fall of each year and addresses these needs with careful consideration to project costs and affordability discussions with county government.
BUDGET IMPLICATIONS The EFMP is used to develop and prioritize both the state and local CIP. Funding consideration by the Interagency Commission on School Construction will be given to a local board's CIP only if a current EFMP is on file.
STAKEHOLDERS INVOLVED To ensure our system's facilities needs are objectively identified for the Board of Education’s (BOE) programming consideration, central office and local government staffs assisted in the development and refinement of the EFMP documents.
DESCRIPTION A synopsis of the required elements of the EFMP is included with this plan (attachment). Careful consideration was given to the long standing dialogue between the County Commissioners and the BOE relating to the Adequate Public Facilities Ordinance, and the responsiveness of the CIP to the county’s growth within the state and local anticipated revenues. The focus of the EFMP is reflected in the proposed project schedule along with the systemic renovations plan.
This year’s update follows our normal review of maintenance records, systems normal life expectancy records, and growth in the county; but also includes consideration of the new System Wide Capital Improvements Program (educational survey and assessment by GWWO Architects).
RECOMMENDATION/FUTURE DIRECTION That the BOE accept and approve the EFMP for FY 2021, as a working document, which will be submitted to the state by July 1, 2020.
G:\Planning_&_Construction\EFMP\FY 2021\ ACTION ITEM.doc
FY 2020 EDUCATIONAL FACILITIES MASTER PLAN SYNOPSIS
The Educational Facilities Master Plan (EFMP) is the first of three phases in the state's public school construction program - the programming phase. With Interagency Commission on School Construction approval, the EFMP will serve as the basis for the state's capital improvements program. The preparation of this year's plan considers evolving planning data, identified through the ongoing collaboration by central office staff and county staff, ensuring careful consideration of the Board of Education (BOE) and the County Commissioners’ recommendations for future planning efforts. The plan excerpts listed below (elements of a more detailed document) outline the following changes as contrasted with last year's plan:
Goals, Standards and Guidelines Section - Updated to reflect changes that have occurred over the last year and updated with new information from the various departments.
New Enrollment Data - Includes new projected enrollment and redistricting data on
which all subsequent analysis has been based.
Facilities’ Needs Analysis - A major component focusing on future planning efforts in one composite document. This section includes: Project Schedule - Graphically displays the suggested planning and construction
programming for renovations and required new capacity. New capacity requirements are drawn from an analysis of area step charts by school level included with this report. The step charts on pages 16 – 18 depict projected enrollment as developed by our school system staff and approved by the Maryland Department of Planning in May 2020.
Systemic Renovations – The report includes a section that formalizes the tie with the
Comprehensive Maintenance Plan as it impacts systemic renovations, bringing planning and programming consideration before the BOE on a yearly basis.
Educational Facilities
Master Plan
FY 2021
Arthur Middleton Elementary School
Charles County Public Schools
La Plata, Maryland
June 2020
Prepared
For
THE BOARD OF EDUCATION
OF CHARLES COUNTY
Virginia R. McGraw, Chairman
Latina L. Wilson, Vice Chairman
Jennifer S. Abell
Tajala Battle-Lockhart
Elizabeth C. Brown
David Hancock
Michael Lukas
Ian Herd, Student Member
Kimberly A. Hill
Superintendent
Michael L. Heim
Assistant Superintendent
of Supporting Services
Steven M. Andritz
Director of
Planning & Construction
June 2020
The Charles County public school system does not discriminate on the basis of race, color, religion, national origin,
sex, sexual orientation, gender identity, age or disability in its programs, activities or employment practices. For
inquiries, please contact Kathy Kiessling, Title IX/ADA/Section 504 Coordinator (students) or Nikial M. Majors, Title
IX/ADA/Section 504 coordinator (employees/adults), at Charles County Public Schools, Jesse L. Starkey Administration
Building, P. O. Box 2770, La Plata, Maryland 20646. (301) 932-6610/870-3814. For special accommodations call (301)
934-7230 or TDD 1-800-735-2258 two weeks prior to the event.
1
GOALS, STANDARDS AND GUIDELINES
Each school district in the State of Maryland prepares an annual Educational Facilities Master
Plan (EFMP) in order to receive funds from the state’s public school construction program.
Funds for specific schools are approved annually through the Capital Improvements Program
(CIP). The EFMP presents school resources and identifies needs; the subsequent CIP responds
to the identified needs by funding specific capital projects.
The state requires that each EFMP include a section on goals, standards and guidelines and
identifies eight policy areas to be addressed. Information for Charles County Public Schools
follows below.
A. GRADE ORGANIZATION PATTERN
Public schools in Charles County are organized into three levels: elementary schools
are from pre-K through grade 5; middle schools are grades 6 through 8; and high schools
are grades 9 through 12. The Robert D. Stethem Educational Center houses alternative
programs for students at the middle/high school levels and the Fresh Start Program.
The F.B. Gwynn Center houses programs serving students from infants and toddlers
through middle school. Seven Title I schools offer a three-year old full day program.
In addition, at the seven Title I schools there are 2 to 3 pre-K classrooms in order to
accommodate all income eligible students in a full day program. At the non-Title I
schools, there is only one pre-K classroom which accommodates half-day programs.
Title I schools include C. Paul Barnhart, Mt. Hope/Nanjemoy, Indian Head, J. P. Ryon,
Dr. Samuel Mudd, Eva Turner and Dr. Gustavus Brown. Arthur Middleton became a
targeted assistance school beginning in school year 2019-2020. Two Title I schools,
(Dr. Samuel Mudd, and Eva Turner) are served by the Judy Center Grant, and provide
early childhood and family support within and beyond the school building. This
program is based at Dr. Mudd Elementary but each school has a dedicated Family
Service Coordinator on staff full time.
B. STUDENT STAFFING RATIOS
A low student-teacher ratio provides a more individualized instructional program.
Presently, Charles County Public Schools average 25 pupils or less for every one
teacher. In addition to classroom teachers, other professionals staff the system’s early
childhood, library, school counselors, reading, math, special education, and gifted
education programs. Itinerant staff is deployed on an as-needed basis including pupil
personnel workers, school psychologists, speech therapists, nursing personnel, and
2
special education specialists. Specific program needs may also impact student-teacher
ratios such as recent initiatives in reading and the three-year old program.
C. TRANSPORTATION POLICIES
The transportation department operates a safe, efficient and reliable bus service with a
policy to hold busing to a minimum in terms of time and distance. Every effort is made
to keep student travel times less than one hour, especially in the rural areas of the
county. As development occurs, bus routes may change in order to meet the growing
number of students in current subdivisions and from new developments.
D. ATTENDANCE ZONES AND REDISTRICTING POLICIES
Each school has a geographically-based attendance area or zone. Students living within
a zone attend the designated school with certain exceptions for children attending
special education programs or other designated exceptions. A transportation link on
the school system’s website (www.ccboe.com) identifies the appropriate attendance
zone upon entry of a street address.
Changing enrollment patterns and the opening of new schools cause redistricting.
School enrollment boundaries are adjusted in order to promote uniform and efficient
use of school facilities and resources. The redistricting policy and rules, adopted in
1997 and last amended in October of 2017, requires staff to annually review enrollment
data of individual schools. When a boundary line adjustment becomes necessary, the
Superintendent establishes an advisory committee on redistricting. The factors
reviewed during redistricting include:
school capacity
impact on educational program quality
student enrollment trends
age or condition of buildings
transportation
impact on the community
limiting movement in elementary/middle schools to once in three years
limiting movement after enrollment in ninth grade.
The redistricting committee develops two proposals and holds at least one public
hearing. From the committee’s report and initial public input, the Superintendent
presents a redistricting proposal to the Board of Education. The Board holds at least
one public hearing on the Superintendent's redistricting proposal. The final decision
is made by the Board with at least 90 days’ notice prior to implementation. A
comprehensive elementary school redistricting took effect for school year 2019-2020
3
that impacted 15 existing schools and created the boundary for Billingsley Elementary
School.
The Superintendent implemented a moratorium on new construction within four
attendance blocks at Milton Somers Middle School. The change sent any new homes
occupied after July 15, 2016, to neighboring Benjamin Stoddert Middle School.
E. GIFTED EDUCATION SERVICES
Gifted education provides advanced academic experiences for students who perform or
show the potential to perform at high levels of accomplishment. A learning resource
teacher who works directly with the gifted education program is part of the
instructional leadership team at each elementary and middle school. At the elementary
and middle school levels, the learning resource teacher also serves as the testing
coordinator, and therefore, requires a secure area for testing materials.
Students identified for gifted services in reading/language arts and mathematics work
with the learning resource teacher in the classroom and in small group settings. In
addition, the learning resource teacher collaborates with classroom teachers and
provides staff development for small and large groups.
F. SPECIAL EDUCATION
Special education services are customized for each student through the Individualized
Education Program (IEP) or the Individual Family Service Plan process. The main
focus of both of these processes is to keep students with IEPs in regular classroom
settings and students with IFSPs in the natural environment. Every school has a
designated room or office for testing, meetings, and services, where confidential
student files are centralized.
Early intervention special education services are available for children from birth – 3
through the F. B. Gwynn Center and/or the Health Department. Service providers go
to the homes of students and implement a wide range of instructional, behavioral,
physical, and communication strategies to improve outcomes for very young children.
They also provide support to families in working with their children and ensure that
they are aware of community-based resources that are available to assist them.
Children can also access services in daycare settings and at the F.B. Gwynn Center.
Special Education services for preschool age students are delivered in a variety of ways
and are determined by the needs of the students and their families. Many of our
students attend Preschool Special Education Programs that are located in most
4
elementary schools; these programs include a strong philosophy and a co-teaching
model. Special Education Preschool programs are available in 18 elementary schools.
The Emotional Adjustment Program (EAP) is a highly structured, self-contained
therapeutic program with mainstreaming opportunities for those students who have
difficulty accessing the academic curriculum in the general education setting due to
emotional/behavioral dysregulation. The program is regionalized with school sites at
the elementary, middle, and high school settings. The program provides students with
academic, behavior, and psychological services support for the acquisition of essential
self-regulatory, social, and academic skills. The program continues to support those
students who are able to maintain appropriate behavior as they return to the
mainstream setting. Ultimately, these therapeutic supports are intended to assist the
student in achieving emotional/behavioral stability and academic success without the
need for such extensive supports.
Students with Autism Spectrum Disorder are served through the Structured Teaching,
Opportunities for Social Inclusion, Active Learning and Rigor (SOAR) program. This
regionalized program is designed to address the academic, social, and behavioral needs
of students with severe communication and behavior disorders. The program serves
students from preschool through grade 12. The classrooms operate using the principles
of an applied behavior analysis model. Students learn skills necessary to function
independently across academic, social, and behavior domains. Students are provided
with inclusion opportunities as specified in their IEP. Student placement in the SOAR
program is determined by the IEP team. Instruction in this program focuses on
academics, personal management, community access; communication and
socialization. All classes are located in elementary, middle, and high schools within the
county, thus ensuring that students are educated within the least restricted
environment. Each student is regularly included with their same age peers in daily
activities and instruction, as appropriate. During the 2019-2020 school year, there were
22 SOAR classes at the elementary level, 6 at the middle school level and 4 at the high
school level.
The ACHIEVE (Academics, Communication and Heightened Independence for
Education Vocation and Engagement) Program provides an alternate curriculum at
each grade level for students with moderate, severe, or profound disabilities.
Functional academics, communications, decision-making skills, and behavior
modifications are addressed. Instruction is community-based in that students work
on their IEP goals in community settings. Within the school setting, students are
included with non-disabled peers in both instructional and social activities. During
the 2019 – 2020 school year, there were 9 ACHIEVE classes at the elementary level, 9
at the middle school level, and 17 at the high school level.
5
Adult Independence Program (AIP) services are available for students with moderate
intellectual disabilities from ages 18 – 21. This program assists students in obtaining
supportive employment opportunities that will often translate into full-time
employment once the students leave the program. Additionally, students are provided
instruction in accessing community-based supports and resources. The purpose of this
program is to enable students to seamlessly transition into adulthood.
G. CAREER AND TECHNICAL EDUCATION
Career and Technical Education (CTE) prepares students for a wide range of careers
through programs that promote both academic and technical achievement. Students
enrolled in CTE program courses can enter careers that require varying levels of
education: high school diplomas, post-secondary certificates, apprenticeships, military
service, or college degrees. Additionally, CTE Programs of Study provide opportunities
to earn industry-recognized credentials and college credit while still in high school.
Students learn skills and develop attitudes that support career employment, college
readiness, and lifelong learning.
Family and Consumer Sciences (FACS) courses offered at the high school level prepare
students to become capable individuals, family members, and citizens managing the
challenges of living and working in a diverse global society. FACS programs include
Architecture and Interior Design, Fashion Design, Fashion Merchandising and
Marketing, Food and Nutrition Science and Intercultural Foods, Retail Merchandising,
and Textiles and Apparels.
Financial Literacy courses prepare students with the knowledge and skills necessary to
meaningfully plan for their financial future, manage their money, and evaluate choices
to make informed decisions. The courses cover a wide variety of financial literacy
topics such as credit card usage, credit scores and reports, buying a car, preparing a
budget, checking and savings accounts, investing, and income considerations. All
students must earn one credit in financial literacy.
Junior Reserve Officers Training Corps (JROTC) is a service specific student leadership
program that instills the values of citizenship, community service, personal
responsibility, character, and self-discipline. Air Force, Army or Navy (Sea Service-
Navy, Marine, and Coast Guard) programs are offered at each high school. The
programs are staffed with a minimum of one retired officer and one retired
noncommissioned officer.
Technology Education is a comprehensive experienced-based curriculum based on the
Maryland State Technology Education Standards. The Foundations of Technology
6
course, offered at all high schools is a graduation requirement. Advanced technology
education courses are also available for students interested in this subject matter.
Students are taught technological literacy by exploring the ways in which ingenuity,
processes, materials, devices, science, and mathematics are applied to solving practical
and perennial problems of a designed world. Laboratory activities include the safe use
of tools, machines, and materials.
Career and Technical Education Completer Programs by Career Clusters
Career and Technical Education Completer Programs provide high school students
with an opportunity to pursue sequential technical and academic programs of study
leading to a career. CTE Programs of Study prepare students for college and careers.
The Career Research and Development (CRD) Program of Study prepares students with
academic, technical, and workplace skills necessary to seek further education and
employment in a career field of their interest. The program consists of a classroom
instructional component and a paid or unpaid workplace component. This program
prepares students with the academic, technical, and workplace skills necessary to seek
further education and employment in a career field of their interest upon graduating
from high school.
Arts, Media and Communication Cluster
The Graphic Communication program gives students an overall understanding of the
graphing and printing industries and their major operations while teaching academic
and technical competencies that lead to nationally recognized certifications. Students
may gain certification in Introduction to Graphic Communication, Digital File
Preparation, Screen Printing, and Advertising/ Design from the Graphic Arts Education
Research Foundation (GAERF). Students may also earn college credits through an
articulation agreement with the College of Southern Maryland (CSM) and Bridgemont
Community & Technical College.
The Interactive Media Production Program of Study includes a strong foundation in
arts and communication with particular emphasis on graphic and media
communications, interactive technologies, and project development. Students in this
program have the opportunity to earn Dual Enrollment at the College of Southern
Maryland. Students complete courses in Arts, Media and Communication and
Interactive Media Production and Advanced Media Production.
7
Business Management and Finance Cluster
Business Education courses focus on pathway programs based on the Maryland State
Department of Education framework document for Business Management and Finance.
The program includes rigorous academics, broad cluster knowledge and skills as well
as more advanced technical skills related to the specific pathway: Business Management
and Finance. The pathway consists of four courses developed by business educators,
postsecondary instructors, and business partners to help prepare students for success in
their chosen business pathway. Skills for success, workplace readiness, computer
applications, written and oral communication skills, and math skills are all integrated
throughout the coursework. Industry certifications are incorporated where
appropriate and opportunities are made available for students to earn college credit
through articulation agreements with local colleges. Career planning and expectations
are incorporated throughout. This program allows students to graduate with the skills
and knowledge necessary to pursue a variety of careers in industry and continue their
education at postsecondary institutions.
Construction Development Cluster
The Construction Design and Management program is a four course CTE Program of
Study. Students will develop an understanding of the built world through the design
and construction process. Each course uses a project based learning approach to
advance students’ understanding of the design-build-maintain process. Advanced
architectural drafting and design skills are developed through lab-based instruction
using Autodesk software tools (AutoCAD and Revit Architecture). Throughout the
program, students will develop a portfolio to demonstrate knowledge of each phase of
the design and construction management process. Students will also have the
opportunity to earn industry certification in AutoCAD.
Electrical Construction is based on modules from the NCCER national standards, and
provides students with instruction and hands-on experiences. Students master a variety
of electrical skills in both residential and commercial wiring.
Heating, Air Conditioning and Refrigeration Mechanic (HVAC) is based on modules
from the NCCER national standards and provides students with instruction and hands-
on experiences learning about the industry as it relates to residential and commercial
building applications.
Welding provides students a variety of welding skills, such as oxyfuel cutting and
welding including Shielded Metal Arc Welding (SMAW). This course of study
correlates to modules from the NCCER national standards. NCCER meets the
8
American Welding Society (AWS) Entry Level Welder-Phase One and Phase Two
requirements of the AWS guidelines.
Consumer Services, Hospitality & Tourism Cluster
The ProStart-Food and Beverage Management program introduces high school
students to a wide variety of careers within the restaurant, food service, and hospitality
industry. Students study and practice professional food preparation, preparation of
international cuisines, food safety and sanitation, customer service relations,
accounting, cost control, marketing and an introduction to all aspects of lodging
management. Students will build strong culinary, business, management and
workplace skills as a result of their participation in this program. The National
Restaurant Association Education Foundation (NRAEF) designed the program’s
industry driven curriculum.
Careers in the Cosmetology program prepare individuals to care for and beautify hair,
skin and nails. Students are instructed in the art and science of cosmetology, as well as
all aspects of the industry. Emphasis is placed on hygiene, safety, and sanitation as well
as State Board of Cosmetologists’ rules and regulations. Related areas of instruction
include human anatomy and physiology, mathematics and measurement, analysis,
diagnosis and histology of hair, skin and nails, chemistry, fundamentals of electricity,
product knowledge; customer relations; and employability skills. Salon management is
an integral part of the classroom and clinical experience. The 1,600-hour program
includes classroom instruction, clinical experience, related mentored work-based
learning experience, and a senior capstone project. Upon successful completion and
the instructor’s recommendation, the student will be required to take the Maryland
State Board of Cosmetologists Examination.
The Culinary Arts (ACF) program prepares students for successful careers in the food
and beverage industry with a focus on Culinary Arts or Professional Baking. The
program includes education in food production, professional cooking, baking, cost
control, nutrition, sanitation, and food marketing. When combined with science
classes, this program will provide the necessary skills for further education and career
success. American Culinary Federation (ACF) is the culinary leader in offering
educational resources, training, apprenticeships, and programmatic accreditation.
Health & Biosciences Cluster
The Academy of Health Professions prepares college-bound students for medical
careers. Students will learn to use technology to provide all aspects of health services.
The program includes classroom instruction as well as hands-on laboratory and clinical
9
experiences at local health care facilities. Students will also take courses such as
anatomy/physiology, nutrition, and speech. Students are expected to take multiple
science classes, including Advanced Placement Biology and Chemistry. Students at
North Point High School earn a Certified Nursing Assistant certification. Students
attending the program at Robert D. Stethem Educational Center are prepared to take
the Pharmacy Technician Certification Board (PTCB) exam in the pharmacy technician
specialty course. They can also specialize in the Physical Rehabilitation specialty
course.
Biomedical Sciences, Project Lead the Way (PLTW) is based on the national standards
for science, mathematics, and English language arts, and the Accountability Criteria for
National Health Care Cluster Foundation Standards. The program consists of a
sequence of four courses: Principals of Biomedical Sciences; Human Body Systems;
Medical Interventions; and Medical Innovations (science research). Students who
complete the program are prepared for employment and further education at two and
four-year college levels.
Human Resource Services Cluster:
Education Careers in Early Childhood programs provide students with instruction that
supports careers such as daycare providers, school teachers, instructional assistants, and
school counselors as well as opportunities to earn college credits. Supplemental courses
include art, music, nutrition, and world language.
Criminal Justice prepares students for law enforcement careers. Students complete a
foundation level course with a focus on addressing threats to public safety through
effective communication, preparedness, detection, prevention, response, and recovery.
Students practice critical thinking in “mock crime scene” activities. Courses in Spanish,
computers, art, speech, and photography are recommended to supplement the
curriculum.
Fire Science/Fire Fighting is offered through collaboration with the Maryland Fire and
Rescue Institute (MFRI) of the University of Maryland, local fire and rescue companies,
and Charles County Public Schools. The program includes classroom instruction as
well as at selected local fire companies. Students must be members in good standing at
their local fire company, complete a minimum of 138 hours of work-based learning,
and take the seven certification exams. Successful completion of this program can lead
to MFRI certifications as well as college credits.
The Teacher Academy of Maryland (TAM) aligns with the Interstate New Teacher
Assessment and Support Consortium (INTASC) and the Maryland Essential Dimensions
10
of Teaching (EDoTs). The program focuses on teaching as a profession, human growth
and development, learning theory, and curriculum and instruction. Upon completion
of the program and passing the ParaPro assessment, high school graduates are ready for
entry level employment as an instructional aide in the teaching profession or can
continue their education at a four-year college.
Information Technology Cluster
The CISCO Networking Academy prepares students for industry certification (CCNA)
and advanced study in information technology. Emphasis is placed on solving
networking problems through decision making and problem-solving techniques,
involving applications of science, mathematics, and communication skills. Students
can enroll in the Cybersecurity specialty course resulting in additional industry
certifications.
Computer Science courses prepare students for success in computer science and related
informational technology degrees, as well as related fields such as engineering. Courses
cover topics such as computer programming and computational thinking, web
development, network technologies, and PC troubleshooting and repair. Students use
a variety of programming languages, including Java, virtual robots, animation software,
and professional web development applications. Middle School Computer Science
courses are available to students in grades 6-8 and in elementary school through PLTW
Launch in grades K-2.
Manufacturing, Engineering & Technology Cluster:
Architectural Drafting and Design students learn the basics of mechanical drawing and
then progress to orthographic projections, sectional views, and pictorial plans for use
in engineering. Supplemental courses are drawing, drafting and design, physics,
architecture, and interior design.
The Manufacturing Technologies Program of Study provides students with the
knowledge and skills needed to program and operate Computerized Numerical Control
(CNC) machines in order to create designed products from raw materials.
Manufacturing includes a study of computer assisted drafting and design, engineering
concepts, and computer programming.
Project Lead the Way (PLTW) Pathway to Engineer Pre-Engineering program prepares
students for further education and careers in engineering and engineering technology.
Students complete foundation level courses in Engineering, including Principles of
Engineering, Introduction to Engineering Design, and Digital Electronics. Students
then select an area of specialization, including Computer Integrated Manufacturing,
11
Civil Engineering and Architecture, Aerospace Engineering, or Biotechnical
Engineering. In the final course, students also complete an industry-mentored
capstone project in Engineering Design and Development.
Gateway to Technology (GTT) is the middle school pre-engineering program for
students exploring an engineering pathway as a possible career choice. The project-
based format is designed to appeal to learners who may not have considered careers in
science, mathematics, or engineering. This course is not a CTE Completer Program;
however, it is designed by PLTW as a precursor to their pre-engineering program.
Transportation Technologies Cluster
Collision Repair Technician combines technical, academic and workplace skills
through curriculum that is aligned with the Inter-Industry Conference on Auto
Collision Repair (I-CAR), National Automotive Technicians Education Foundation
(NATEF), including Automotive Service Excellence (ASE). Instruction prepares
students for careers and/or further education in collision repair and refinishing within
the Transportation Technology Cluster through the following courses: Non-Structural
Analysis and Damage Repair/ Plastics and Adhesives, Paint and Refinishing, and an
optional course Structural Analysis & Damage Repair.
The Automotive Technician program incorporates the Automotive Service Excellence
(ASE) program certification standards and the National Automotive Technicians
Education Foundation (NATEF) task lists. The program prepares students for further
education and careers in the Transportation Equipment Pathway and automotive
technology. The program consists of eight courses: Suspension and Steering, Brakes,
Electrical/Electronic Systems, Engine Performance, Engine Repair, Heating and Air
Conditioning, Automatic Transmission and Transaxle, and Manual Drive Train.
Environmental, Agriculture and Natural Resources Cluster
The Curriculum for Agriculture and Science Education (CASE) Natural Resources
Pathway begins with the Introduction to Agriculture, Food, and Natural
Resources course. Students then progress to the foundation level course, Natural
Resources and Ecology followed by the specialization course, Environmental Science
Issues. The CASE: Natural Resources Pathway culminates with the capstone
course, Agricultural Research and Development. Students will experience hands-on
activities, projects, and problems. Student experiences will involve the study of
communication, the science of agriculture, plants, animals, natural resources, and
agricultural mechanics. While surveying the opportunities available in agriculture
and natural resources, students will learn to solve problems, conduct research,
12
analyze data, work in teams, and take responsibility for their work, actions, and
learning.
H. EDUCATIONAL SUPPORT POLICIES
School counseling services are available at each school. Certified counselors can help
parents and students in areas of academic planning, personal decision making and
career development. Each high school also has a college and career advisor who assists
with these efforts. Counselors work with parents, administrators, teachers and
community resources to provide the best educational experiences for students.
School health service nurses update, maintain and implement medical plans for
medically fragile students, administer medications, review immunization records and
provide medical response for illness and injuries as needs arise for students and staff.
Vision and hearing technicians regularly screen students and re-screen upon requests
from parents or teachers.
Certified school psychologists provide crisis intervention, counseling for students and
groups of students, individual risk assessments, psychological assessments and
consultations with teachers, parents and administrators. This includes referrals to, and
consultations with, appropriate community agencies and professionals.
Pupil personnel workers act as liaisons between home, school and the community.
They investigate residence concerns and assist with attendance, behavior, enrollment,
and homeless issues.
Court liaisons work with the courts, Juvenile Services Department and the school
system to appropriately and effectively meet students' needs.
School Probation Officers (SPO’s) are employed by Department of Juvenile Services to
serve as mentors. They primarily work with students placed on probation by the court.
They devote time and attention to these and other students serving as positive role
models in prevention and early intervention programs.
School Resource Officers (SRO) are sworn police officers from the Sheriff’s Office. An
officer is assigned to each high school and middle schools. Service is provided to
elementary schools as needed. When requested by the school, the SRO’s serve as
mentors to the students and as consultants to the school administration and staff. They
provide school and personnel safety programs, teach DARE classes, counsel individual
students, work with parents, and carry out normal police duties when called upon to
do so.
13
I. SCHOOL CLOSING PROCEDURES
Charles County Public Schools provides high quality education at an efficient and cost
effective level through an optimum use of facilities. The local growth rate is an added
challenge to this policy; whereas the closing of schools is a lesser demand. School
closings comply with state regulations (COMAR 13A.02.09). The Superintendent
appoints a standing committee to review population patterns and other factors bearing
on school operations. The analysis includes:
educational program quality
student enrollment trends
student body racial composition
age or condition of schools
means of transportation
student relocations
financial projections and economic costs
community impact of school closings
impacts to schools at other levels
Based on each school’s assessment, the committee submits recommendations to the
Superintendent, which could include school closures. From the committee’s
recommendations, the Superintendent develops alternatives for review by the Board of
Education. If a school closure is included, the Board holds a public hearing on both the
proposed closure and alternatives. The decision to close a school rests with the Board.
As with redistricting actions, a minimum of 90-days public notice is provided prior to
implementation to ensure orderly transitions.
J. CONCLUSION
The goals, standards and guidelines established for the Charles County Public Schools
system fulfill the stated mission of the Board of Education, which is to provide an
opportunity for all school-aged children to receive an academically challenging, quality
education that builds character, equips for leadership and prepares for life, in an
environment that is safe and conducive to learning.
g:\planning_&_construction\efmp\fy 2019\efmp2019 goals, standards, guidelines.docm
14
SC
HO
OLS
RA
TE
DP
RO
JE
XC
ES
SR
AT
ED
PR
OJ
EX
CE
SS
RA
TE
DP
RO
JE
XC
ES
SR
AT
ED
PR
OJ
EX
CE
SS
RA
TE
DP
RO
JE
XC
ES
SC
AP
.E
NR
OLL
(SH
OR
T)
CA
P.
EN
RO
LL(S
HO
RT
)C
AP
.E
NR
OLL
(SH
OR
T)
CA
P.
EN
RO
LL(S
HO
RT
)C
AP
.E
NR
OLL
(SH
OR
T)
ELE
ME
NT
AR
YC
. Pau
l Bar
nhar
t60
866
9.0
(61.
0)60
867
3.0
(65.
0)60
867
5.0
(67.
0)60
8.0
666.
0(5
8.0)
608
669.
0(6
1.0)
Ber
ry65
669
2.0
(36.
0)65
670
1.0
(45.
0)65
670
8.0
(52)
656
689.
0(3
3)65
670
2.0
(46.
0)B
illin
gsle
y75
870
7.0
51.0
758
713.
045
.075
872
0.0
3875
869
8.0
6075
871
3.0
45.0
Dr.
Gus
tavu
s B
row
n38
142
7.0
(46.
0)38
142
7.0
(46.
0)38
142
4.0
(43.
0)38
1.0
401.
0(2
0.0)
381
404.
0(2
3.0)
Dr.
Jam
es C
raik
406
505.
0(9
9.0)
406
511.
0(1
05.0
)40
651
4.0
(108
)40
650
2.0
(96)
406
504.
0(9
8.0)
Will
iam
A. D
iggs
816
747.
069
.081
675
8.0
58.0
816
758.
058
.081
6.0
750.
066
.081
675
5.0
61.0
Gal
e-B
aile
y43
837
4.0
64.0
438
374.
064
.043
837
3.0
6543
834
6.0
9243
834
8.0
90.0
Dr.
Tho
mas
L. H
igdo
n44
740
2.0
45.0
447
400.
047
.044
740
3.0
44.0
447.
039
0.0
57.0
447
390.
057
.0In
dian
Hea
d40
446
1.0
(57.
0)40
446
1.0
(57.
0)40
446
2.0
(58)
404
445.
0(4
1)40
445
1.0
(47.
0)D
anie
l of S
t. T
hom
as J
enife
r49
562
5.0
(130
.0)
495
630.
0(1
35.0
)49
563
7.0
(142
.0)
495.
062
7.0
(132
.0)
495
634.
0(1
39.0
)M
alco
lm41
745
7.0
(40.
0)41
746
1.0
(44.
0)41
746
3.0
(46)
417
460.
0(4
3)41
748
0.0
(63.
0)T
. C. M
artin
486
526.
0(4
0.0)
486
533.
0(4
7.0)
486
539.
0(5
3.0)
486.
052
7.0
(41.
0)48
653
0.0
(44.
0)M
ary
H. M
atul
a55
457
2.0
(18.
0)55
458
1.0
(27.
0)55
459
0.0
(36)
554
576.
0(2
2)55
457
6.0
(22.
0)A
rthu
r M
iddl
eton
439
555.
0(1
16.0
)43
956
5.0
(126
.0)
439
574.
0(1
35.0
)43
9.0
557.
0(1
18.0
)43
957
5.0
(136
.0)
Wal
ter
J. M
itche
ll60
662
3.0
(17.
0)60
663
2.0
(26.
0)60
664
1.0
(35)
606
610.
0(4
)60
663
4.0
(28.
0)M
t. H
ope/
Nan
jem
oy37
325
5.0
118.
037
326
0.0
113.
037
325
8.0
115.
037
3.0
240.
013
3.0
373
243.
013
0.0
Dr.
Sam
uel A
. Mud
d53
261
4.0
(82.
0)53
261
4.0
(82.
0)53
261
5.0
(83)
532
581.
0(4
9)53
258
5.0
(53.
0)M
ary
Bur
gess
Nea
l79
169
1.0
100.
079
168
5.0
106.
079
169
5.0
96.0
791.
066
8.0
123.
079
167
4.0
117.
0J.
C. P
arks
656
615.
041
.065
662
8.0
28.0
656
624.
032
656
597.
059
656
619.
037
.0J.
P. R
yon
656
714.
0(5
8.0)
656
705.
0(4
9.0)
656
714.
0(5
8.0)
656.
070
7.0
(51.
0)65
672
1.0
(65.
0)E
va T
urne
r39
145
0.0
(59.
0)39
145
5.0
(64.
0)39
144
4.0
(53)
391
429.
0(3
8)39
143
2.0
(41.
0)W
illia
m B
. Wad
e67
269
4.0
(22.
0)67
269
8.0
(26.
0)67
270
4.0
(32.
0)67
2.0
679.
0(7
.0)
672
692.
0(2
0.0)
New
Ele
men
tary
#23
N/A
N/A
---
N/A
N/A
---
N/A
N/A
---
N/A
N/A
---
N/A
N/A
---
TO
TA
L E
LEM
EN
TA
RY
11,9
8212
,375
.0(3
93.0
)11
,982
12,4
65.0
(483
.0)
11,9
8212
,535
.0(5
53.0
)11
,982
.012
,145
.0(1
63.0
)11
,982
12,3
31.0
(349
.0)
MID
DLE
The
odor
e G
. Dav
is1,
112
874.
023
8.0
1,11
285
3.0
259.
01,
112
828.
028
4.0
1,11
2.0
884.
022
8.0
1,11
288
5.0
227.
0Jo
hn H
anso
n84
393
3.0
(90.
0)84
393
3.0
(90.
0)84
392
8.0
(85)
843
984.
0(1
41)
843
984.
0(1
41.0
)M
atth
ew H
enso
n65
981
5.0
(156
.0)
659
810.
0(1
51.0
)65
979
9.0
(140
.0)
659.
085
2.0
(193
.0)
659
852.
0(1
93.0
)M
atta
wom
an89
01,
058.
0(1
68.0
)89
01,
063.
0(1
73.0
)89
010
51.0
(161
)89
01,
154.
0(2
64)
890
1,14
1.0
(251
.0)
Pic
cow
axen
544
458.
086
.054
445
3.0
91.0
544
445.
099
.054
4.0
466.
078
.054
446
1.0
83.0
Gen
eral
Sm
allw
ood
659
513.
014
6.0
659
502.
015
7.0
659
494.
016
565
951
8.0
141
659
514.
014
5.0
Milt
on M
. Som
ers
802
1,09
4.0
(292
.0)
802
1,08
5.0
(283
.0)
802
1073
.0(2
71.0
)80
2.0
1,17
4.0
(372
.0)
802
1,15
7.0
(355
.0)
Ben
jam
in S
todd
ert
711
856.
0(1
45.0
)71
183
2.0
(121
.0)
711
803.
0(9
2)97
589
9.0
7697
590
7.0
68.0
New
Mid
dle
#9N
/AN
/A--
-N
/AN
/A--
-N
/AN
/A--
-N
/AN
/A--
-N
/AN
/A--
-T
OT
AL
MID
DLE
6,22
06,
601.
0(3
81.0
)6,
220
6,53
1.0
(311
.0)
6,22
0.0
6,42
1.0
(201
.0)
6,48
4.0
6,93
1.0
(447
.0)
6,48
46,
901.
0(4
17.0
)
HIG
HH
enry
E. L
acke
y1,
539
1,04
0.0
499.
01,
539
1,05
6.0
483.
015
3910
93.0
446.
01,
539.
01,
083.
045
6.0
1,53
91,
079.
046
0.0
La P
lata
1,16
21,
260.
0(9
8.0)
1,16
21,
301.
0(1
39.0
)11
6213
69.0
(207
)11
621,
354.
0(1
92)
1,16
21,
351.
0(1
89.0
)M
auric
e J.
McD
onou
gh1,
200
954.
024
6.0
1,20
097
3.0
227.
012
0010
20.0
180.
01,
200.
01,
014.
018
6.0
1,20
01,
010.
019
0.0
Nor
th P
oint
1,
600
1,86
4.0
(264
.0)
1,60
01,
883.
0(2
83.0
)16
0019
15.0
(315
)16
001,
905.
0(3
05)
1,60
01,
902.
0(3
02.0
)S
t.Cha
rles
1,51
11,
512.
0(1
.0)
1,51
11,
553.
0(4
2.0)
1,51
116
23.0
(112
.0)
1,51
1.0
1,60
7.0
(96.
0)1,
511
1,60
5.0
(94.
0)T
hom
as S
tone
1,51
31,
228.
028
5.0
1,51
31,
265.
024
8.0
1513
1333
.018
015
131,
317.
019
61,
513
1,31
2.0
201.
0W
estla
ke1,
203
1,24
0.0
(37.
0)1,
203
1,27
7.0
(74.
0)12
0313
45.0
(142
.0)
1,20
3.0
1,32
8.0
(125
.0)
1,20
31,
323.
0(1
20.0
)
TO
TA
L H
IGH
9,72
89,
098.
063
0.0
9,72
89,
308.
042
0.0
9,72
8.0
9,69
8.0
30.0
9,72
8.0
9,60
8.0
120.
09,
728
9,58
2.0
146.
0
OT
HE
RS
teth
em E
duca
tiona
l Cen
ter
396
81.0
315.
039
681
.031
5.0
396
81.0
326
396
81.0
315.
039
681
.031
5.0
TO
TA
L O
TH
ER
81.0
81.0
81.0
81.0
81.0
GR
AN
D T
OT
AL
*
27,9
3028
,155
.0(2
25.0
)27
,930
28,3
85.0
(455
.0)
27,9
3028
,735
.0(2
31)
28,1
9428
,765
.0(5
71.0
)28
,194
28,8
95.0
(701
.0)
* E
qu
ival
ent
Co
un
t (I
ncl
ud
ing
Pre
-K E
qu
iv.)
G:\P
lann
ing_
&_C
onst
ruct
ion\
EF
MP
\FY
202
1\S
prea
dshe
ets\
[Cap
acity
Pro
ject
ed E
nrol
lmen
t Com
paris
on _
May
20
02-J
un-2
020
CA
PA
CIT
Y &
PR
OJE
CT
ED
EN
RO
LL
ME
NT
* C
OM
PA
RIS
ON
SY
20
- 21
SY
21
- 22
SY
22
- 23
SY
23
- 24
SY
24
- 25
15
SC
HO
OLS
RA
TE
DP
RO
JE
XC
ES
SR
AT
ED
PR
OJ
EX
CE
SS
RA
TE
DP
RO
JE
XC
ES
SR
AT
ED
PR
OJ
EX
CE
SS
RA
TE
DP
RO
JE
XC
ES
SC
AP
.E
NR
OLL
(SH
OR
T)
CA
P.
EN
RO
LL(S
HO
RT
)C
AP
.E
NR
OLL
(SH
OR
T)
CA
P.
EN
RO
LL(S
HO
RT
)C
AP
.E
NR
OLL
(SH
OR
T)
ELE
ME
NT
AR
YC
. Pau
l Bar
nhar
t60
868
2.0
(74.
0)60
868
7.0
(79.
0)60
868
9.0
(81.
0)60
870
0.0
(92.
0)60
871
1.0
(103
.0)
Ber
ry65
671
5.0
(59.
0)65
671
9.0
(63.
0)65
672
0.0
(64.
0)65
673
3.0
(77.
0)65
674
5.0
(89.
0)B
illin
gsle
y75
872
6.0
32.0
758
732.
026
.075
874
2.0
16.0
758
761.
0(3
.0)
758
778.
0(2
0.0)
Dr.
Gus
tavu
s B
row
n38
140
8.0
(27.
0)38
140
3.0
(22.
0)38
139
9.0
(18.
0)38
140
2.0
(21.
0)38
140
5.0
(24.
0)D
r. J
ames
Cra
ik40
651
2.0
(106
.0)
406
508.
0(1
02.0
)40
650
8.0
(102
.0)
406
515.
0(1
09.0
)40
652
0.0
(114
.0)
Will
iam
A. D
iggs
816
775.
041
.081
678
3.0
33.0
816
789.
027
.081
681
5.0
1.0
816
834.
0(1
8.0)
Gal
e-B
aile
y43
835
3.0
85.0
438
352.
086
.043
835
2.0
86.0
438
356.
082
.043
835
9.0
79.0
Dr.
Tho
mas
L. H
igdo
n44
739
4.0
53.0
447
397.
050
.044
739
9.0
48.0
447
409.
038
.044
741
4.0
33.0
Indi
an H
ead
404
455.
0(5
1.0)
404
460.
0(5
6.0)
404
463.
0(5
9.0)
404
465.
0(6
1.0)
404
468.
0(6
4.0)
Jeni
fer
495
647.
0(1
52.0
)49
564
9.0
(154
.0)
495
654.
0(1
59.0
)49
565
9.0
(164
.0)
495
670.
0(1
75.0
)M
alco
lm41
749
1.0
(74.
0)41
749
7.0
(80.
0)41
750
0.0
(83.
0)41
750
9.0
(92.
0)41
751
3.0
(96.
0)T
. C. M
artin
486
538.
0(5
2.0)
486
533.
0(4
7.0)
486
531.
0(4
5.0)
486
535.
0(4
9.0)
486
540.
0(5
4.0)
Mar
y H
. Mat
ula
554
596.
0(4
2.0)
554
593.
0(3
9.0)
554
599.
0(4
5.0)
554
610.
0(5
6.0)
554
629.
0(7
5.0)
Art
hur
Mid
dlet
on43
959
5.0
(156
.0)
439
599.
0(1
60.0
)43
961
2.0
(173
.0)
439
624.
0(1
85.0
)43
964
3.0
(204
.0)
Wal
ter
J. M
itche
ll60
665
4.0
(48.
0)60
666
3.0
(57.
0)60
667
7.0
(71.
0)60
669
6.0
(90.
0)60
671
5.0
(109
.0)
Mt.
Hop
e/N
anje
moy
373
247.
012
6.0
373
244.
012
9.0
373
244.
012
9.0
373
247.
012
6.0
373
250.
012
3.0
Dr.
Sam
uel A
. Mud
d53
259
2.0
(60.
0)53
258
9.0
(57.
0)53
258
7.0
(55.
0)53
259
0.0
(58.
0)53
259
5.0
(63.
0)M
ary
Bur
gess
Nea
l79
169
4.0
97.0
791
696.
095
.079
171
4.0
77.0
791
721.
070
.079
174
0.0
51.0
J. C
. Par
ks65
664
2.0
14.0
656
656.
00.
065
667
2.0
(16.
0)65
669
3.0
(37.
0)65
671
2.0
(56.
0)J.
P. R
yon
656
741.
0(8
5.0)
656
744.
0(8
8.0)
656
759.
0(1
03.0
)65
677
6.0
(120
.0)
656
795.
0(1
39.0
)E
va T
urne
r39
143
9.0
(48.
0)39
143
3.0
(42.
0)39
143
2.0
(41.
0)39
143
4.0
(43.
0)39
143
9.0
(48.
0)W
illia
m B
. Wad
e67
269
9.0
(27.
0)67
269
8.0
(26.
0)67
270
3.0
(31.
0)67
270
5.0
(33.
0)67
271
0.0
(38.
0)N
ew E
lem
enta
ry #
2376
6N
/A76
6.0
766
N/A
766.
076
6N
/A76
6.0
766
N/A
766.
076
6N
/A76
6.0
TO
TA
L E
LEM
EN
TA
RY
12,7
4812
,595
.015
3.0
12,7
4812
,635
.011
3.0
12,7
4812
,745
.03.
012
,748
12,9
55.0
(207
.0)
12,7
4813
,185
.0(4
37.0
)
MID
DLE
The
odor
e G
. Dav
is1,
112
867.
024
5.0
1,11
285
3.0
259.
01,
112
864.
024
8.0
1,11
287
2.0
240.
01,
112
862.
025
0.0
John
Han
son
843
986.
0(1
43.0
)84
395
2.0
(109
.0)
843
952.
0(1
16.0
)84
396
0.0
(116
.0)
843
948.
0(1
16.0
)M
atth
ew H
enso
n65
985
4.0
(195
.0)
659
819.
0(1
60.0
)65
982
5.0
20.0
659
833.
020
.065
982
4.0
20.0
Mat
taw
oman
890
1,14
8.0
(258
.0)
890
1,09
4.0
(204
.0)
890
1,11
0.0
(253
.0)
890
1,12
9.0
(253
.0)
890
1,11
9.0
(253
.0)
Pic
cow
axen
544
461.
083
.054
444
2.0
102.
054
444
7.0
67.0
544
451.
067
.054
444
2.0
67.0
Gen
eral
Sm
allw
ood
659
514.
014
5.0
659
492.
016
7.0
659
499.
059
.065
950
3.0
59.0
659
495.
059
.0M
ilton
M. S
omer
s80
21,
165.
0(3
63.0
)80
21,
120.
0(3
18.0
)80
21,
138.
0(2
16.0
)80
21,
157.
0(2
16.0
)80
21,
144.
0(2
16.0
)B
enja
min
Sto
dder
t97
591
6.0
59.0
975
869.
010
6.0
975
886.
0(1
23.0
)97
590
6.0
(123
.0)
975
897.
0(1
23.0
)N
ew M
iddl
e #9
N/A
N/A
---
940
N/A
940.
094
0N
/A94
0.0
940
N/A
940.
094
0N
/A94
0.0
TO
TA
L M
IDD
LE6,
484
6,91
1.0
(427
.0)
7,42
46,
641.
078
3.0
7,42
46,
721.
019
8.0
7,42
46,
811.
019
8.0
7,42
46,
731.
019
8.0
HIG
HH
enry
E. L
acke
y1,
539
1,06
5.0
474.
01,
539
1,09
8.0
441.
01,
539
1,10
0.0
85.0
1,53
91,
089.
085
.01,
539
1,09
8.0
85.0
La P
lata
1,16
21,
328.
0(1
66.0
)1,
162
1,40
1.0
(239
.0)
1,16
21,
410.
0(4
88.0
)1,
162
1,40
0.0
(488
.0)
1,16
21,
424.
0(4
88.0
)M
auric
e J.
McD
onou
gh1,
200
999.
020
1.0
1,20
01,
033.
016
7.0
1,20
01,
034.
048
.01,
200
1,02
5.0
48.0
1,20
01,
036.
048
.0N
orth
Poi
nt1,
600
1,88
8.0
(288
.0)
1,60
01,
923.
0(3
23.0
)1,
600
1,92
7.0
(792
.0)
1,60
01,
917.
0(7
92.0
)1,
600
1,92
8.0
(792
.0)
St.C
harle
s 1,
511
1,58
2.0
(71.
0)1,
511
1,65
5.0
(144
.0)
1,51
11,
665.
0(1
54.0
)1,
511
1,65
6.0
(145
.0)
1,51
11,
680.
0(1
69.0
)T
hom
as S
tone
1,51
31,
288.
022
5.0
1,51
31,
359.
015
4.0
1,51
31,
366.
0(1
24.0
)1,
513
1,35
6.0
(124
.0)
1,51
31,
377.
0(1
24.0
)W
estla
ke1,
203
1,29
8.0
(95.
0)1,
203
1,36
9.0
(166
.0)
1,20
31,
376.
0(5
79.0
)1,
203
1,36
5.0
(579
.0)
1,20
31,
385.
0(5
79.0
)
TO
TA
L H
IGH
9,72
89,
448.
028
0.0
9,72
89,
838.
0(1
10.0
)9,
728
9,87
8.0
(250
.0)
9,72
89,
808.
0(2
50.0
)9,
728
9,92
8.0
(250
.0)
Ste
them
Edu
catio
nal C
ente
r39
681
.031
5.0
396
81.0
315.
039
681
.032
639
681
.032
639
681
.032
681
.081
.081
.081
.081
.0
GR
AN
D T
OT
AL
*
28,9
6029
,035
.0(7
5.0)
29,9
0029
,195
.070
5.0
29,9
0029
,425
.047
5.0
29,9
0029
,655
.024
5.0
29,9
0029
,925
.0(2
5.0)
* E
qu
ival
ent
Co
un
t (I
ncl
ud
ing
Pre
-K E
qu
iv.)
G:\P
lann
ing_
&_C
onst
ruct
ion\
EF
MP
\FY
202
1\S
prea
dshe
ets\
[Cap
acity
Pro
ject
ed E
nrol
lmen
t Com
paris
on _
May
20
02-J
un-2
020
SY
25
- 26
SY
26
- 27
SY
27
- 28
SY
28
- 29
SY
29
- 30
CA
PA
CIT
Y &
PR
OJE
CT
ED
EN
RO
LL
ME
NT
* C
OM
PA
RIS
ON
16
Ele
men
tary
Sch
ools
* P
roje
cted
Enr
ollm
ent &
Cap
acit
y
1318
5
12,9
55
12,7
4512
,635
12,3
31
12,5
9512
,145
12,5
35
12,1
02
12,3
7512
,465
11,0
00
11,5
00
12,0
00
12,5
00
13,0
00
13,5
00
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
Scho
ol Y
ear
2019
Enr
ollm
ent
Tren
d (2
012
Enro
llmen
t)
`
* C
ount
y W
ide
+ I
dent
ifie
d F
utur
e N
eed
5/26
/202
0
Cap
acit
y
12,7
56
New
Ele
m.
Sch
ool #
23
+76
6B
illin
gsle
y E
lem
. S
choo
l +
758
11,9
90
Dr.
Mu
dd
E.S
. A
dd
itio
n +
197
Ful
l Tim
e E
quiv
alen
t (F
TE
)
17
Mid
dle
Sch
ools
* P
roje
cted
Enr
ollm
ent &
Cap
acit
y
6,60
5
6,93
16,
901
6,91
1
6,72
16,
811
6731
6,64
16,
504
6,60
16,
637
5,50
0
6,00
0
6,50
0
7,00
0
7,50
0
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
Sch
ool Y
ear
2019
Enr
ollm
ent
Tre
nd (
2012
Enr
ollm
ent)
* C
ount
y W
ide
6,48
4
+ I
dent
ifie
d F
utur
e N
eed
5/26
/202
0
Cap
acit
y
7,42
4
New
Mid
dle
Sch
ool #
9
+94
0
6,22
0S
tod
der
t M
S
Exp
ansi
on
+26
4
Ful
l Tim
e E
quiv
alen
t (F
TE
)
18
Hig
h S
choo
ls*
Pro
ject
ed E
nrol
lmen
t & C
apac
ity
9,09
8
9,30
899
289,
808
8,61
9
9,69
89,
878
9,60
8
9,83
8
9,44
8
9,58
2
8,00
0
8,50
0
9,00
0
9,50
0
10,0
00
10,5
00
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
Sch
ool Y
ear
2019
Enr
ollm
ent
Tre
nd (
2012
Enr
ollm
ent)
* C
ount
y-W
ide
9,72
8
+ I
dent
ifie
d F
utur
e N
eed
5/26
/202
0
Cap
acit
y
Ful
l Tim
e E
quiv
alen
t (F
TE
)
19
FY
2020
FY
2021
FY
2022
FY
2023
FY
2024
FY
2025
FY
2026
FY
2027
FY
2028
FY
2029
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
Pla
nnin
g/D
esig
nC
onst
ruct
ion
Sch
ool O
pens
Fun
ding
App
rove
dP
lann
ing
App
rove
d
FY
2021
Edu
catio
nal F
acili
ties
Mas
ter
Pla
nC
harle
s C
ount
y P
ublic
Sch
ools
Pro
ject
Sch
edul
e
PR
OJE
CT
Ben
jam
in S
todd
ert M
S -
Ren
ovat
ion
Eva
Tur
ner
ES
- R
enov
atio
n
Dr.
Gus
tavu
s B
row
n E
S -
Ope
n S
pace
John
Han
son
MS
Roo
f SR
McD
onou
gh H
S -
Ren
ovat
ion,
Pha
se 1
Wes
tlake
HS
Roo
f SR
Indi
an H
ead
ES
Boi
ler
SR
J.P.
Ryo
n E
S F
DK
Add
n.
Mal
colm
ES
FD
K A
ddn.
T.C
. Mar
tin E
S -
Ren
ovat
ion
LaP
lata
HS
- R
enov
atio
n, P
hase
1
New
Ele
men
tary
#23
Wal
ter
J. M
itche
ll E
S F
DK
Add
n.
J.C
. Par
ks E
S F
DK
Add
n.
Pic
cow
axen
MS
Boi
ler
SR
Sm
allw
ood
MS
Chi
ll/H
&V
/UV
/Roo
f SR
Mat
ula
ES
Roo
f SR
Mat
taw
oman
MS
Roo
f SR
Ste
them
Ed.
Cen
ter
HV
AC
/Roo
f SR
Bar
nhar
t ES
Roo
f SR
New
Mid
dle
#9
Dr.
Tho
mas
Hig
don
ES
FD
K A
ddn.
20
FY
2020
FY
2021
FY
2022
FY
2023
FY
2024
FY
2025
FY
2026
FY
2027
FY
2028
FY
2029
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
Pla
nnin
g/D
esig
nC
onst
ruct
ion
Sch
ool O
pens
Fun
ding
App
rove
dP
lann
ing
App
rove
d
FY
2021
Edu
catio
nal F
acili
ties
Mas
ter
Pla
nC
harle
s C
ount
y P
ublic
Sch
ools
Pro
ject
Sch
edul
e
PR
OJE
CT
Wad
e E
S F
DK
Add
n.
Hen
son
MS
Mul
ti-zo
ne U
nit/H
eat P
ump
Wad
e E
S B
oile
r/C
hille
r S
R
Dr.
Hig
don
ES
Roo
f SR
Ber
ry E
S R
oof S
R
Dr.
Hig
don
ES
RT
U/B
oile
r S
R
Mid
dlet
on R
oof S
R
Wad
e E
S R
TU
/Roo
f SR
Mat
ula
ES
Boi
ler
SR
JC P
arks
ES
Roo
f SR
Wes
tlake
HS
Boi
ler
SR
Hen
son
MS
Roo
f SR
Mat
ula
ES
RT
U S
R
Mitc
hell
ES
Roo
f SR
Tho
mas
Sto
ne H
S R
oof S
R
Bar
nhar
t ES
Boi
ler
SR
Mat
thew
Hen
son
MS
Boi
ler
SR
Indi
an H
ead
ES
Roo
f SR
Wes
tlake
HS
RT
U/C
hille
r S
R
Hen
ry E
. Lac
key
HS
Roo
f SR
J.P.
Ryo
n E
S R
oof S
R
C. P
aul B
arnh
art E
S R
TU
/Chi
ller
SR
21
FY
2020
FY
2021
FY
2022
FY
2023
FY
2024
FY
2025
FY
2026
FY
2027
FY
2028
FY
2029
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
Pla
nnin
g/D
esig
nC
onst
ruct
ion
Sch
ool O
pens
Fun
ding
App
rove
dP
lann
ing
App
rove
d
FY
2021
Edu
catio
nal F
acili
ties
Mas
ter
Pla
nC
harle
s C
ount
y P
ublic
Sch
ools
Pro
ject
Sch
edul
e
PR
OJE
CT
La P
lata
HS
Roo
f SR
Pic
cow
axen
MS
Roo
f SR
McD
onou
gh H
S R
oof S
R
22
NEW CAPACITY AND RENOVATION/ADDITION
PROJECT DESCRIPTIONS FULL-DAY KINDERGARTEN ADDITIONS/RENOVATIONS – VARIOUS SCHOOLS: There is a need for
permanent space to support full-day kindergarten in the elementary schools. A study to
evaluate the existing conditions and recommend the most effective means of providing the
additional classrooms required to house a full-day kindergarten program is complete.
Planning approvals for 14 projects and construction funding for 12 projects were approved in
fiscal years 2007 through 2021. Planning approval and construction funds for additional
projects will be requested in FY 2022 and future years.
Planning and/or construction approvals:
C. Paul Barnhart Elementary School Gale-Bailey Elementary School
T. C. Martin Elementary School Mt. Hope/Nanjemoy Elementary School
Dr. Gustavus Brown Elementary School Eva Turner Elementary School
Indian Head Elementary School Arthur Middleton Elementary School
Mary H. Matula Elementary School Daniel of St. Thomas Jenifer Elementary
Berry Elementary School Dr. James Craik Elementary
Malcolm Elementary - Planning J.P. Ryon Elementary - Planning
Planning and/or construction requests:
J. P. Ryon Elementary School – FY 2022 Construction
Malcolm Elementary School - FY 2022 Construction
J. C. Parks Elementary School - FY 2022 Planning/ FY 2023 Construction
Walter J. Mitchell Elementary School - FY 2022 Planning/ FY 2023 Construction
Dr. Thomas Higdon Elementary School - FY 2022 Planning/ FY 2023 Construction
William Wade Elementary School - FY 2022 Planning/ FY 2023 Construction
EVA TURNER ELEMENTARY SCHOOL MODERNIZATION/ADDITION: The need is for modernization
and addition to Eva Turner Elementary School. The school was opened in 1979 and major
building systems have reached the end of their useful life. The school received a pre-
kindergarten addition in 1995 and an all-day kindergarten addition in 2011. The
modernization will upgrade the mechanical and electrical systems to meet current standards
and codes. The building will be modernized and expanded for increased enrollment and to
meet current educational program requirements. New individual classroom spaces will be
provided to replace existing open-space classrooms. The school is located in the Bannister
neighborhood of Smallwood Village in St. Charles and serves the development district. The
school serves a population that includes students with special needs, students with low
English proficiency, and children eligible to participate in the free and reduced meal
program. The State approved Planning for the school in FY 2018 and local design funds were
23
approved in FY 2018. State and local construction funds are requested in FY 2020, FY 2021
and FY 2022.
BENJAMIN STODDERT MIDDLE SCHOOL MODERNIZATION/ADDITION: The need is for
modernization and addition to Benjamin Stoddert Middle School. The school opened in
1976 and the major building systems have reached the end of their useful life. The school
has not had any previous renovations or additions. The modernization will upgrade the
mechanical and electrical systems to meet current standards and codes. The entire building
will be modernized and expanded for increased enrollment and to meet current educational
program requirements. New individual classroom spaces will be provided to replace existing
open-space classrooms. The school is located in the Bannister neighborhood of Smallwood
Village in St. Charles and serves the development district. The school serves a population
that includes students with special needs, students with low English proficiency, and
children eligible to participate in the free and reduced meal program. The State approved
Planning for the school in FY 2018 and local design funds were approved in FY 2018. State
and Local construction funds are requested in FY 2020, FY 2021 and FY 2022.
MAURICE J. MCDONOUGH HIGH SCHOOL, PHASE I RENOVATION: The need is for modernization
at McDonough High School, which was built in 1977 and serves a portion of the
development district. The proposed Phase I may include; an elevator, stair modifications,
improved accessibility, new secure building entrance and administrative office, renovations
to convert the existing administrative spaces to program spaces, and enhancements to the
performing arts area. The school serves a population that includes students with special
needs, students with low English proficiency, and children eligible to participate in the free
and reduced meal program. Local funding to initiate planning was approved in FY 2018.
Planning was approved in FY 2019. Local construction funds are requested in FY 2021 and
FY 2022. State construction funding will be requested in FY 2021 and FY 2022.
T.C. MARTIN ELEMENTARY SCHOOL MODERNIZATION/ADDITION: The need is for modernization
and addition to T. C. Martin Elementary School. The school was opened in 1967 and major
building systems have reached the end of their useful life. The boilers were replaced in 2006
and the school received an all-day kindergarten addition in 2009. The modernization will
upgrade the mechanical and electrical systems to meet current standards and codes. The
building will be modernized and expanded for increased enrollment and to meet current
educational program requirements. The school serves a population that includes students
with special needs, students with low English proficiency, and children eligible to participate
in the free and reduced meal program. Local planning funds were requested in FY 2021.
State and local construction funds are requested in FY 2022 and FY 2023.
24
LA PLATA HIGH SCHOOL, PHASE I RENOVATION: The need is for modernization at La Plata
High School, which was built in 1979 and serves a portion of the development district. The
proposed Phase I may include; envelope stabilization, open space enclosure, new secure
building entrance and administrative office, and enhancements to special programs. The
school serves a population that includes students with special needs, students with low
English proficiency, and children eligible to participate in the free and reduced meal
program. Local funding to initiate planning will be requested in FY 2022. State and local
construction funding will be requested in FY 202 and FY 2024.
NEW ELEMENTARY SCHOOL #23: The need is for additional school capacity in the La Plata
area. Continued development in the incorporated town, both east and west of route 301,
will cause enrollment at the elementary level to exceed the capacity of the existing schools
serving that area. The school will serve a population that includes students with special
needs, students with low English proficiency, and children eligible to participate in the free
and reduced meal program. Planning approval was requested in FY 2021. State and local
construction funding will be requested in FY 2023 and FY 2024.
NEW MIDDLE SCHOOL #9: The need is for additional capacity at the middle school level in the
rapidly growing county development district. The county’s Comprehensive Plan calls for the
majority of growth in the county to be concentrated in the development district, including
those areas west of Route 301. Enrollment projections indicate the schools serving this area
will continue to experience increasing enrollment and overcrowded conditions. The
proposed school site location is not determined. A school with a rated capacity of 940 is
planned. The school will serve a population that includes students with special needs,
students with low English proficiency, and children eligible to participate in the free and
reduced meal program. Planning approval will be requested in FY 2022. State and local
construction funding will be requested in FY 2023 and FY 2024.
25
SYSTEMIC RENOVATIONS
PROJECT DESCRIPTIONS
OPEN SPACE ENCLOSURE AT DR. GUSTAVUS BROWN ELEMENTARY SCHOOL: The need is for an
open space enclosure at Dr. Gustavus Brown Elementary School, located in the Smallwood
Village in St. Charles, within the development district. The original building opened in 1974
and designed with an open space floor plan and the need is for permanent enclosed
classrooms. This project will consist of constructing permanent classroom walls,
reconfiguring ductwork and lighting, electrical work, providing new drop ceiling, and new
floor finishes. Local design funds will be requested in FY 2021. State and Local construction
funding will be requested in FY 2022.
ROOF REPLACEMENT AT JOHN HANSON MIDDLE SCHOOL: The need is for a systemic renovation
at Hanson Middle School. Located in the Waldorf development district, this school opened
in 1972 and is the oldest operating middle school in Charles County. The building was re-
roofed in 1995 and will reach its expected 20-year life by FY 2017. The installation of a
four-ply, built-up roof with positive drainage is proposed. A full roof investigation will be
performed by our consultant prior to design to address any unforeseen problems. Local
planning approval and design funds were approved in FY 2018. Construction funding was
not approved in FY 2019, FY 2020 or FY 2021. Construction funding will be requested in FY
2022.
ROOF REPLACEMENT AT WESTLAKE HIGH SCHOOL: The need is for a systemic renovation at
Westlake High School, which opened in 1992 and located in Westlake Village in St. Charles.
The original roof will reach its life expectancy in FY 2017. The installation of a four-ply,
built-up roof with positive drainage is proposed. A full roof investigation will be performed
by our consultant prior to design to address any unforeseen problems. Local planning and
design funding has been approved for FY 2019. Local construction funding has been
approved for FY 2021 and FY 2022. State construction funding will be requested in FY 2022.
BOILER REPLACEMENT AT INDIAN HEAD ELEMENTARY SCHOOL: The need is for a systemic
renovation at Indian Head Elementary School, which opened in 1976 and is located in the
Town of Indian Head. The boiler and pump systems are over 30 years old and outlived their
expected usefulness. The installation of new efficient units is proposed to increase overall
efficiency of the heating system and reduce operating costs. Local planning and design
funding has been approved for FY 2019. Construction funding will be requested in FY 2022.
ROOF/CHILLER/H&V/UV REPLACEMENTS AT GENERAL SMALLWOOD MIDDLE SCHOOL: The need
is for a systemic renovation at Smallwood Middle School, which was renovated in 1979 and
serves a portion of the development district. The roof, heating and ventilation units, chiller
26
and all classroom unit ventilators were installed when the building was renovated in the
1970s and are approaching the end of their useful life. Approximately 40 H&V’s and UV’s
were replaced using the Aging Schools Program (ASP). The installation of a four-ply, built-
up roof with positive drainage is proposed. A full roof investigation will be performed by our
consultant prior to design to address any unseen problems. The installation of new efficient
units is proposed, which are environmentally friendly, and will increase the overall
efficiency of the heating cooling systems and reduce the operating costs. Planning approval
will be requested in FY 2021. Construction funding will be requested in FY 2022.
BOILER REPLACEMENT AT PICCOWAXEN MIDDLE SCHOOL: The need is for a systemic renovation
at Piccowaxen Middle School, which opened in 1977. The boiler and pump systems are over
30 years old and outlived their expected usefulness. The installation of new efficient units is
proposed to increase the overall efficiency of the heating system and reduce operating cost.
Planning approval will be requested in FY 2022. Construction funding will be requested in
FY 2023.
ROOF REPLACEMENT AT MARY H. MATULA ELEMENTARY SCHOOL: The need is for a systemic
renovation at Matula Elementary School, located in the Town of La Plata and opened in
1992. The original roof will reach the end of its expected life in FY 2021. The installation of
a four-ply, built-up roof with positive drainage is proposed. A full roof investigation will be
performed by our consultant prior to design to address any unseen problems. Planning
approval will be requested in FY 2021. Construction funding will be requested in FY 2022.
ROOF REPLACEMENT AT MATTAWOMAN MIDDLE SCHOOL: The need is for a systemic
renovation at Mattawoman Middle School, which opened in 1992 and located in the rapidly
growing route 228 corridor in Waldorf. The original roof will reach its life expectancy in FY
2017. The installation of a four-ply, built-up roof with positive drainage is proposed. A full
roof investigation will be performed by our consultant prior to design to address any
unforeseen problems. Planning approval will be requested in FY 2021. Construction
funding will be requested in FY 2022.
ROOF/BOILER/AHU/RTU REPLACEMENT AT ROBERT D. STETHEM EDUCATIONAL CENTER: The
need is for a systemic renovation at the Stethem Center. This school originally opened in
1977 as the Charles County Career & Technology Center. The air handler unit and rooftop
units are over 30 years old. These units have outlived their expected usefulness and no
longer maintain a suitable environment within the school. These roof top units are original
equipment when the building was constructed in the early 1970s and have approached the
end of their useful life expectancy. The installations of new units are proposed, which are
more efficient and would increase overall efficiency of the heating and cooling systems and
reduce operating costs. The multi-roof complex was re-roofed in 1995 and will reach its 20-
27
year life expectancy by FY 2017. Planning approval will be requested in FY 2022.
Construction funding will be requested in FY 2023.
ROOF REPLACEMENT AT C. PAUL BARNHART ELEMENTARY SCHOOL: The need is for a systemic
renovation at Barnhart Elementary School, which opened in 1993 and is located in Westlake
Village in St. Charles. The original roof will reach its life expectancy in FY 2017. The
installation of a four-ply, built-up roof with positive drainage is proposed. A full roof
investigation will be performed by our consultant prior to design to address any unforeseen
problems. Planning approval will be requested in FY 2021. Construction funding will be
requested in FY 2022.
MULTI-ZONE UNIT/HEATPUMP REPLACEMENT AT MATTHEW HENSON MIDDLE SCHOOL: The need
is for a systemic renovation at Henson Middle School. The school was renovated in 1982 and
the multi-zone unit with Dx cooling and the water-cooled, heat pumps in the classrooms will
be over 30 years old and will have outlived their expected usefulness. The installation of
new units will increase overall efficiency of the heating system and reduce operating costs.
Planning approval will be requested in FY 2022. Construction funding will be requested in
FY 2023.
BOILER/CHILLER REPLACEMENT AT WILLIAM B. WADE ELEMENTARY SCHOOL: The need is for a
systemic renovation at Wade Elementary School, which opened in 1989 and is located in
Westlake Village in St. Charles. The boiler and pump systems and chiller are over 25 years
old and outlived their expected usefulness. The installation of new efficient units is proposed
to increase the overall efficiency of the heating and cooling systems and reduce operating
cost. Planning approval will be requested in FY 2022. Construction funding will be
requested in FY 2023.
ROOF REPLACEMENT AT DR. THOMAS L. HIGDON ELEMENTARY SCHOOL: The need is for a
systemic renovation at Higdon Elementary school, which was renovated in 1988. The school
was re-roofed as part of the renovation and the roof is past the 20-year life expectancy. The
installation of a four-ply, built-up roof with positive drainage is proposed. A full roof
investigation will be performed by our roof consultant prior to design to address any unseen
problems. Planning approval will be requested in FY 2022. Construction funding will be
requested in FY 2023.
ROOF REPLACEMENT AT BERRY ELEMENTARY SCHOOL: The need is for a systemic renovation at
Berry Elementary School, which opened in 1996 and located in the rapidly growing route
228 corridor in Waldorf. The original roof will reach its 20-year life expectancy in FY 2017.
The installation of a four-ply, built-up roof with positive drainage is proposed. A full roof
investigation will be performed by our consultant prior to design to address any unforeseen
28
problems. Planning approval will be requested in FY 2022. Construction funding will be
requested in FY 2023.
RTU/BOILER REPLACEMENT DR. THOMAS L. HIGDON ELEMENTARY SCHOOL: The need is for a
systemic renovation at Higdon Elementary School. This school, located in Newburg and
services the southern part of the county, opened in 1988. The rooftop units and boilers are
original equipment when the building was renovated in the 1980s and no longer maintains a
suitable environment within the school. Installation of new units are proposed, which are
more efficient and would increase overall efficiency of the heating and cooling systems, to
reduce operating costs. Planning approval will be requested in FY 2023. Construction
funding will be requested in FY 2024.
ROOF/RTU REPLACEMENT AT WILLIAM B. WADE ELEMENTARY SCHOOL: The need is for a
systemic renovation at Wade Elementary School, which was renovated in 1989 and is located
in Westlake Village in St. Charles. The original roof will have reached its 20-year life
expectancy. The installation of a four-ply, built-up roof with positive drainage is proposed.
A full roof investigation will be performed by our consultant prior to design to address any
unforeseen problems. The rooftop units are original equipment when the building was built
and have reached the end of their useful life. The installation of new efficient units is
proposed, which are environmentally friendly, and will increase the overall efficiency of the
heating cooling systems and reduce the operating costs. Planning approval will be requested
in FY 2023. Construction funding will be requested in FY 2024.
BOILER REPLACEMENT AT MARY H. MATULA ELEMENTARY SCHOOL: The need is for a systemic
renovation at Matula Elementary School, which opened in 1992 and is located in the Town
of La Plata. The boiler and pump systems are over 30 years old and outlived their expected
usefulness. Installations of new efficient units are proposed to increase overall efficiency of
the heating system and reduce operating costs. Planning approval will be requested in FY
2023. Construction funding will be requested in FY 2024.
ROOF REPLACEMENT AT J. C. PARKS ELEMENTARY SCHOOL: The need is for a systemic
renovation at Parks Elementary School, which opened in 1967 and located in the Bryans
Road Town Center Revitalization Area. The building was re-roofed in 1997 will have
exceeded its 20-year life expectancy in FY 2025. The installation of a four-ply, built-up roof
with positive drainage is proposed. A full roof investigation will be performed by our
consultant prior to design to address any unforeseen problems. Planning approval will be
requested in FY 2024. Construction funding will be requested in FY 2025.
BOILER REPLACEMENT AT WESTLAKE HIGH SCHOOL: The need is for a systemic renovation at
Westlake High School, which opened in 1992 and is located in Westlake Village in St.
29
Charles. The boiler and pump systems are over 25 years old and will have outlived their
expected usefulness. Installations of new efficient units are proposed to increase overall
efficiency of the heating system and reduce operating costs. Planning approval will be
requested in FY 2024. Construction funding will be requested in FY 2025.
ROOF REPLACEMENT AT MATTHEW HENSON MIDDLE SCHOOL: The need is for a systemic
renovation at Henson Middle School. This school was renovated in 1982 and serves a
portion of the development district. The school was re-roofed as part of the 1982 renovation
and again in 1998 after a catastrophic failure of its single-ply membrane roof. The roof will
have exceeded its 20-year life expectancy by FY 2025. The installation of a four-ply, built-up
roof with positive drainage is proposed. A full roof investigation will be performed by our
consultant prior to design to address any unforeseen problems. Planning approval will be
requested in FY 2024. Construction funding will be requested in FY 2025.
RTU REPLACEMENT AT MARY H. MATULA ELEMENTARY SCHOOL: The need is for a systemic
renovation at Matula Elementary School, which opened in 1992 and located in the Town of
La Plata. The rooftop units are original equipment when the school was constructed and
have approached the end of their useful life. The installation of new efficient units is
proposed, which are environmentally friendly, and will increase the overall efficiency of the
heating cooling systems and reduce the operating costs. Planning approval will be requested
in FY 2025. Construction funding will be requested in FY 2026.
ROOF REPLACEMENT AT WALTER J. MITCHELL ELEMENTARY SCHOOL: The need is for a systemic
renovation at Mitchell Elementary School, which opened in 1965 and located in the Town of
La Plata. The roof is a combination of shingles and is a built-up roofing area. The
installation of a four-ply, built-up roof with positive drainage is proposed. A full roof
investigation will be performed by our consultant prior to design to address any unforeseen
problems. Planning approval will be requested in FY 2025. Construction funding will be
requested in FY 2026. ROOF REPLACEMENT AT THOMAS STONE HIGH SCHOOL: The need is for a systemic renovation
at Stone High School. This school was renovated in 1997 and serves several designated
revitalization areas. The school was re-roofed as part of the renovation and will exceed its
20-year life expectancy by FY 2025. The installation of a four-ply, built-up roof with
positive drainage is proposed. A full roof investigation will be performed by our consultant
prior to design to address any unforeseen problems. Planning approval will be requested in
FY 2025. Construction funding will be requested in FY 2026.
BOILER REPLACEMENT AT C. PAUL BARNHART ELEMENTARY SCHOOL: The need is for a systemic
renovation at Barnhart Elementary School. This school opened in 1993, and is located in
Westlake Village in St. Charles. The boilers and pumps are original equipment when the
30
building was constructed and outlived their usefulness. The installation of a new efficient
heating system that will reduce operating costs is proposed. Planning approval will be
requested in FY 2025. Construction funding will be requested in FY 2026.
BOILER REPLACEMENT AT MATTHEW HENSON MIDDLE SCHOOL: The need is for a systemic
renovation at Henson Middle. This school was renovated in 1982, and the boiler and pump
systems are over 30 years old and will have outlived their expected usefulness. The
installation of new efficient units to reduce the operating costs is proposed. Local planning
approval will be requested in FY 2026. Construction funding will be requested in FY 2027.
ROOF REPLACEMENT AT INDIAN HEAD ELEMENTARY SCHOOL: The need is for a systemic
renovation at Indian Head Elementary School, which is located in the Town of Indian Head.
The building was re-roofed in 1997 and will have reached the end of its expected 20-year life
by FY2026. The installation of a four-ply, built-up roof with positive drainage is proposed.
A full roof investigation will be performed by our consultant prior to design to address any
unforeseen problems. Local planning approval will be requested in FY 2026. Construction
funding will be requested in FY 2027.
RTU/CHILLER REPLACEMENTS AT WESTLAKE HIGH SCHOOL: The need is for a systemic
renovation at Westlake High School, which opened in 1992 and is located in Westlake
Village in St. Charles. The rooftop units and chiller systems are over 25 years old and will
have outlived their expected usefulness. Installations of new efficient units are proposed to
increase overall efficiency and reduce operating costs. Local planning approval will be
requested in FY 2026. Construction funding will be requested in FY 2027.
ROOF REPLACEMENT AT HENRY E. LACKEY HIGH SCHOOL: The need is for a systemic renovation
at Lackey High School, which opened in 1969 and was renovated in 2001. The installation of
a four-ply, built-up roof with positive drainage is proposed. A full roof investigation will be
performed by our consultant prior to design to address any unforeseen problems. Local
planning approval will be requested in FY 2027. Construction funding will be requested in
FY 2028.
ROOF REPLACEMENT AT J.P. RYON ELEMENTARY SCHOOL: The need is for a systemic renovation
at JP Ryon Elementary School, which opened in 1969 and was renovated in 2001 and is
located in Waldorf. The installation of a four-ply, built-up roof with positive drainage is
proposed. A full roof investigation will be performed by our consultant prior to design to
address any unforeseen problems. Local planning approval will be requested in FY 2027.
Construction funding will be requested in FY 2028.
RTU/CHILLER REPLACEMENTS AT C. PAUL BARNHART ELEMENTARY SCHOOL: The need is for a
systemic renovation at Barnhart Elementary School, which opened in 1994 and is located in
31
Westlake Village in St. Charles. The rooftop units and chiller systems are over 25 years old
and will have outlived their expected usefulness. Installations of new efficient units are
proposed to increase overall efficiency and reduce operating costs. Local planning approval
will be requested in FY 2027. Construction funding will be requested in FY 2028.
ROOF REPLACEMENT AT LA PLATA HIGH SCHOOL: The need is for a systemic renovation at La
Plata High School, which opened in 1979 and was re-roofed in 2002. The installation of a
four-ply, built-up roof with positive drainage is proposed. A full roof investigation will be
performed by our consultant prior to design to address any unforeseen problems. Local
planning approval will be requested in FY 2028. Construction funding will be requested in
FY 2029.
ROOF REPLACEMENT AT PICCOWAXEN MIDDLE SCHOOL: The need is for a systemic renovation
at Piccowaxen Middle School, which opened in 1977 and was re-roofed in 2000. The
installation of a four-ply, built-up roof with positive drainage is proposed. A full roof
investigation will be performed by our consultant prior to design to address any unforeseen
problems. Local planning approval will be requested in FY 2028. Construction funding will
be requested in FY 2029.
ROOF REPLACEMENT AT MAURICE J. MCDONOUGH HIGH SCHOOL: The need is for a systemic
renovation at McDonough High School, which opened in 1977 and was re-roofed in 2002.
The installation of a four-ply, built-up roof with positive drainage is proposed. A full roof
investigation will be performed by our consultant prior to design to address any unforeseen
problems. Local planning approval will be requested in FY 2028. Construction funding will
be requested in FY 2029.
g:\planning_&_construction\efmp\fy2021\projectdescriptions.doc
32