accurate capex for industrial projects
TRANSCRIPT
BILFINGER TEBODIN
ACCURATE CAPEX FORINDUSTRIAL PROJECTSSmart decisions and effective cost tracking
––––––
Introduction
Smart investment is a way to embracecurrent global economic challenges and turnthem into opportunities. Bilfinger Tebodinhelps clients predict project costs and futureoperational expenses. Our experts useindustry-leading data and insights from over10 years of constant analysis.
In the end, the investor should focus on afew cost factors that have a significantimpact on the overall project budget. Usingthat data, asset investors and owners get achance to focus on their capital growth,rather than hesitating to invest due topotential risks.
To help you make smart decisions, BilfingerTebodin annually summarizes its knowledgeof costs on the market across a variety ofsectors, focusing on industrial projects thatthe company executes worldwide. Thisunique analysis is based on an internationalcost database created from 2008-2020while working on hundreds of projects fromstart to finish and based on the actual pricesfrom various national markets.
To help you make smart decisions, Bilfinger Tebodin annually summarizes its knowledge of costs on theCentral & Eastern European market across a variety of sectors, focusing on industrial projects.
Bilfinger Tebodin
Note: Information provided in this brochure is not intended toserve a basis for the investment decision, as each case shouldbe approached individually. However, it describes factors, thatshape total CAPEX and their volume in the overall project cost.All data and information is provided by Bilfinger Tebodin costmanagers in CEE countries.
Project stages
Each project is unique,so there is no commonformula for executionsuccess that appliesacross the board.Nevertheless, projectstages are similar.
PROJECT STARTMarket researchBusiness planFinancing PROJECT STRATEGY
ManagementCooperation with licensors
LAND PLOTLand plot selectionAuditRegistration
COMMISSIONINGAND OPERATION START
Start upHiring of staffRegistration
OBTAINING INITIAL PERMITSENGINEERING SURVEY
EXPERT ASSESSMENT OF DESIGNDOCUMENTATION & CONSTRUCTION PERMIT
OBTAININGCONSTRUCTION PERMIT
DESIGN
CONSTRUCTION CAPEX varies depending on the project type. For theindustrial projects with main buildings area of more than10,000 m², cost breakdown would look like this:
Land plot – 0.01-10 %
Design – up to 6 %
Project management,including procurement – up to 10 %
Construction – up to 70-80 %
Other costs – < 5 %
Bilfinger TebodinBilfinger Tebodin
Project Management:choosing the rightapproach
With the EPC approach, one contractor isselected with consolidated responsibility tothe investor. The scope includes design,procurement and construction.
With the EPCM approach, the investorchooses a partner for design, procurementand construction management, while theconstruction and installation works arecarried out directly by a third partyor a number of companies selectedfor the project.
Bilfinger TebodinBilfinger Tebodin
When implementing industrialprojects, two types of strategiesare most often used: EPC andEPCM.
EPCM EPCOWNER CONTRACT OWNER CONTRACT
EPCM COMPANY- Engineering- Procurement- Construction
Management
PROJECTMANAGEMENTFOR THE OWNER
- EPC contractor- Engineering- Procurement- Construction
GENERALCONTRACTORorMULTIPLECONTRACTORS
How a specific type oftechnology dictatesthe project approach
Bilfinger TebodinBilfinger Tebodin
Is process technology wellknown and proven on anindustrial scale?
Are suppliers of keyequipment known to theinvestor?
Are the technologieslicensed?
Is the investor familiar withthe selected processtechnology and itsoperational aspects?
Are there EPC companies onthe market with referencesto build such technology in asimilar size?
Is the project a ‘very brownfield’, with a lot ofinteraction with already builttechnology / objects?
YES YES
YES YES
YES YES
NO NO
NO NO
NO NO
1 2
3 4
5 6
EPCMEPCTEPC
EPCMEPCTEPC
EPCMEPCTEPC
EPCMEPCTEPC
EPCMEPCTEPC
EPCMEPCTEPC
EPCMEPCTEPC
EPCMEPCTEPC
EPCMEPCTEPC
EPCMEPCTEPC
EPCMEPCTEPC
EPCMEPCTEPC
Based on our available experience,when choosing a strategy for theimplementation of an industrialproject, one should make thechoice based on the answersto the following questions:
*TEPC – EPC contractor as technology owner
Land plot
Bilfinger TebodinBilfinger Tebodin
More alternatives forsite selection
A land plot of required sizeand shape can be found
Maximum design flexibility(design to fit the budget)
Easier to achieve high QHSEstandards
Potential for extensions
Adjustable maintenance costs
Greenfield
Adva
ntag
esDi
sadv
anta
ges
Brownfield Industrial parks /Special economic zones
Time and costly permittingand extra approval procedures
Land and town planninglimitations for construction
High costs for infrastructureand utilities connection
A long-term project
Infrastructure and utilitiesalready in place
Total project cost may be lower
Permitting process may be easier
Quick modification to a newproduction
Site selection possibilitiesare limited
Design adjustment couldbe required
High risk of hidden pitfalls
Background pollution of the area
In most cases, poor constructionquality
Limitations for extension
Higher maintenance costs
A land plot of required sizeand shape can be found
Design flexibility
Utilities and transport networksare available
Administration support froma professional company
Built-to-suit and built-to-rent options
Tax advantages for investors
Dependency on commonengineering infrastructure(limited utility capacities)
Environmental limitations (e.g.permitted sanitary class ofa facility, limitations dueto neighboring facilities)
Specific requirements to aninvestment project due toIndustrial Parks / Special EconomicZones memoranda
Design andengineering
Bilfinger TebodinBilfinger Tebodin
Considering that a substantial portion of thecosts comes from design solutions, it makessense to be particularly careful whenselecting a design partner.
Experience
Check the track record, permanently updatedand large database built duringimplementation of investment projects.
Digital tools
Engineer’s advanced tools allow fasterexecution, increased quality, and minimizedconflicts in the design stage, while alsomitigating delays and cost overruns in theconstruction stage.
Quality control
Ensure implemented and live qualitymanagement system with audits and gatereviews, certified with ISO.
Staff
Ensure all required experienced and qualifiedspecialists are available to execute projectsin-house.
Professional project managers
The importance of PMI certified projectmanagers with strong management andcommunication skills, should not beunderestimated. These professionals takecontrol over the project strategy andcoordination of stakeholders (investor,designer, licensor/s, other parties).
Presence in the region whereyour project is located
Ideally, there should be a combination ofinternational experience and knowledge oflocal requirements and norms,communication and deliverables in boththe local language and English.
Legally and financially stable
Make sure the partner’s required guaranteesand insurance are in place.
Take note of the followingcapabilities:
Bilfinger TebodinBilfinger Tebodin
Construction
Bilfinger TebodinBilfinger Tebodin
During project execution, the investor is ableto get cost estimations with a necessarylevel of accuracy.
Advice: fix major cost segments, work themout in detail during project execution. Thiswill allow you to track the budget throughout
different project stages, and will provide anopportunity to influence the decisions andensure proper project control. Moreover,using a similar cost structure on differentprojects, is a good way to create a reliableinternal cost database.
One of the success factors for projectrealization is preparation of cost estimatesfor construction of the project. It’s extremelyimportant to foresee all required expenses,such as: main buildings and facilities, landplot networks, site improvement and off-sitenetworks.
Estimation accuracy
Project strategy,business plan,scouting phase
+/-50%
Conceptualdesign
+/-25-40%
Basicengineering+/-10-20%
Detailengineering
+/-5-10%
Construction+/-3-5%
Start-up/Commissioning
+/-3 - 0%
1) Projectmanagement
2) Land plot
3) Design
4) Construction
5) Other costs
Total - ___
1) Projectmanagement
2) Land plot
3) Design
4) Construction
- Buildings
- Facilities
- Infrastructure
- On site networks
- Outside networks
5) Other costs
Total - ___
1) Project management
2) Land plot
3) Design
4) Construction
5) Other costs
Total - ___
Unit prices are mainly based onprototype projects Unit prices are based on the quantities and vendors verification
Bill of Quantities (BoQ) form example:
Constructioncost ratio
Bilfinger TebodinBilfinger Tebodin
The cost ratio shows the typical project costallocation in detail. Nevertheless, for eachsector a partially different cost ratio isapplicable, as well as for each type ofproduction.
Description CEE RUmin max min max
Productionbuilding costAutomotive 710 860 775 840Food & Beverage 1,160 1,680 787 1,428Pharma 1,160 1,680 1,258 1,798Chemical 940 1,310 674 1,179Agro 680 1,050 506 945Warehouse 450 820 438 506Offices (shell& core) 950 1,500 1,100 1,300Hotels 3* 1000 1500 700 1300Hotels 5* 1,400 2,200 1,600 2,100Retail 800 1,200 800 1,100
Office
Production
Warehouse
Projectcost ratio
Productionconstruction materials, mechanicalengineering, chemistry, agriculture
food and pharmaceutical industry
Architecture (basement, walls, partitions, doors, windows, gate, skylights, roofing system, finishing)
Structure (piles, fundations, floors, pits, reinforced-concrete and steel structures)
HVAC, water supply, water discharge, mechanical systems (equipment, piping, air ducts, connections)
Power supply and low voltage systems (equipment, boards, cables, connections, lamps)
Fire safety systems (equipment, cables, connections)
Main buildings
Architecture
StructureStructure
Structure
HVAC
HVAC
HVAC HVAC
Power Power
PowerPower
Fire
Fire Fire
Fire
Structure
Architecture
ArchitectureArchitecture
Facilities
Infrastructure
Land plot networks
70 %
10 %
39 %
25 %
18 %
47 % 35 %
23 %
21 %
18 %3 %
15 %
11 %
9 %
21 %
12 %3 % 3 %
14 %
14 %
52 %
17 %
15 %
5 %
Note: cost per square meter is based on GBA
Trends
Bilfinger TebodinBilfinger Tebodin
Bilfinger Tebodin notes a slightdifference in the level of prices onthe construction market in Central& Eastern Europe.
Production building cost per sq.m(without building networks)
Country priceindices
In comparison with North-West Europe, the prices inCentral and Eastern Europe are still 20-50% lower.
Russia90 - 105 %
Poland100 - 105 %
Ukraine80 - 90 %
Hungary105 - 110 %
CzechRepublic
100 %
SlovakRepublic
100 %
Serbia85 - 90 %
Romania90 - 95 %
It is worth mentioning that a range ofparameters from the previous marketchanges of 2008 and 2014-2015, is alsoapplicable for the 2020 crisis, triggered by
the pandemic. So this experience will betaken into account when forecasting futureinvestments.
30.000
25.000
20.000
15.000
10.000
5.000
2007 2008 2009
Czech Republic, KC Czech Republic, USD Russia, USDRussia, RUB
2011 2012 2013 2014 2015 2016 2017 2018 2019 2020
0
Trends
Bilfinger TebodinBilfinger Tebodin
Analyzing the construction marketof 2020, Bilfinger Tebodin hasidentified several key specifics,that are likely to remain in 2021.
Timing
Projects that entered the constructionphase before April 2020 have continuedas planned.
Many investors with projects in the phaseof choosing contractors at the beginningof 2020, have postponed their decision tocontinue the project until the end of 2020,or the first quarter of 2021.
In January 2020 there was increasedactivity regarding both postponed andnew projects.
Extension of terms of delivery forimported materials and equipment.
Prices
Over 10% price increase for a range ofservices and materials during 2020.
A sharp increase in the price of metal ofover 20% worldwide in December 2020.
Materials and equipment delivery gapsduring March through May 2020 causedby lockdown and production delays.Dealers and suppliers were sellingavailable products from warehouses atMarch April prices. During the summerperiod, the delivery schedule wasstabilized, construction companies beganto closely monitor the supply of goodsfrom outside the country of where theproject was located. Later on, newsupplies appeared on the market withupdated price proposition, oftensignificantly higher.
The increase in the selling price wassignificant for those countries, wherenational currency depreciated.
Anti-pandemic measures are beingincluded in the project cost, creatingadditional costs.
Resources
Lack of local construction staff, especiallygeneral workers, due to inability toinvolve migrants in the face of closedborders.
Continuous decrease of skilled staff(welders, fitters, etc.) due to free flow toWestern European countries. Pandemicmay have stopped this trend for a whiledue to travel restrictions.
Design solutions turnaround towardslimiting imported materials andequipment.
Focus on digitalization: remote workopportunities, shared work and dataprocessing, BIM modeling, video calls,web-cams, 3D scans, drones.
Construction companies
The tendency for companies’consolidation continues, smaller playersare leaving the market.
Low workloads lead to personnelreductions and work suspension.
Investors tend to focus on companieswith a bigger staff, which are present inthe construction location or able toquickly move there if needed.
Bilfinger Tebodin
Link to construction management service page:
Your project is unique and can't be calculatedbased on average numbers. Contact ourexperienced and enthusiastic team for supportwith expert cost estimation or advice:
Maja CesljevicBusiness Development Director in CEEMobile: +381 63 281 [email protected]