accredited service provider rate 2 public lighting process
TRANSCRIPT
-
w ~ 0
z 0 f'= a. ii': u en w 0
DEVELOPER DETAILS
THE DEVELOPER MAY BE A LAND DEVELOPER/ PROPERTY DE.VELOPE.R / PRIVATE COMPANY/ PUBLIC COMPANY ENGAGING THE SERVICES OF THE EN ERG EX ACCREDITTED DESIGN CONSUL TANT FOR A CONTE.STIBLE. WORKS RATE. 2 PUBLIC LIGHTING PROJECT
THE DEVELOPER MAY ALSO BE A PUBLIC BODY (LOCAL COUNCIL OR DEP'T OF TRANSPORT AND MAIN ROADS) ENGAGING THE SERVICES OF TI-lE ENERGEX ACCREDITTED DESIGN CONSUL TANT FOR A CONTESTIBLE WORKS RATE 2 PUBLIC LIGHTING PROJECT.
PUBLIC LIGHTING SUPPLY AGREEMENT
THE PUBLIC LIGHTING SUPPLY AGREEMENT IS THE "CONTRACT" BETWEEN THE DEVELOPER AND ENERGEXTHAT PERMITS THE DEVELOPER TO UNDERTAKE CONTESTIBLE WORKS ON THE ENERGEX PUBLIC LIGHTING NETWORK
NO WORKS OF ANY TYPE CAN BE UNDERTAKEN ON THE ENERGEX PUBLIC LIGHTING NETWORK WITHOUT A PUBLIC LIGHTING SUPPLY AGREEMENT.
<>: ~ a. 0 <("'
f-- >-z ..J Wz ~o 0 X Ow O(!)
l< 15 wz zw ~
0
( START )
THE DEVELOPER ENGAGES THE RATE 2
PUBLIC LIGHTING DESIGN CONSULTANT
THE CONSUL TANT SUBMITS ELECTRONIC CORRESPONDENCE TO ENERGEX WITH A REQUEST FOR A MAPS PACKAGE.
THE CORRESPONDENCE SHALL INCLUDE INFORMATION ON THE LOCATION AND SCOPE OF THE PROJECT.
THE CONSUL TANT SUBMITS CORRESPONDENCE TO THE LOCAL COUNCIL AND/ OR THE DEPARTMENT OF MAIN ROADS REQUESTING PUBLIC BODY REQUIREMENTS FOR THE
CATEGORY OF LIGHTING TO BE DESIGNED FOR THE PROJECT
ENERGEX PROVIDES NETWORK MAPPING
INFORMATION TO THE DESIGN CONSULTANT
PROJECT SCOPE AND PLANNING
LOCAL COUNCIL I DTMR PROVIDES LIGHTING
INFORMATION TO THE DESIGN CONSULTANT
THE DESIGN CONSUL TANT SCOPES AND PLANS All. PROPOSED WORKS, INCLUDING ANY REQUIRED AL TE RATIONS TO THE
EXISTING PUBLIC LIGHTING NETWORK
CONCEPT PLAN
THE CONSULTANT MAY NEED TO SUBMIT A CONCEPT PLAN TO ENERGEX TO DISCUSS AND RESOLVE ANY ISSUES SUCH AS:
(1) LIGHTING TARIFF. Eg: COMPLIANCE WITH RATE 2 POLICY (2) ADJACENT PUBLIC LIGHTING PROJECTS (3) ENSAR'e (NON STANDARD PROPOSALS) (4) NON CONTESTIBLE WORK I.e. A new Point of Supply is required to be established for the propse<:I Rate 2 Public Lighting
LOCAL COUNCIL APPROVAL AND f OR
DEP'T OF MAIN ROADS APPROVAL OF THE
PUBLIC LIGHTING DESIGN
DESIGN ACCEPTED
YES •
NO
.
NO
DETAILED DESIGN
THE CONSUL TANT DESIGNS THE RATE 2 PUBLIC LIGHTING PROJECT
INCLUDING ALL REQUIRED ALTERATIONS TO THE EXISTING
PUBLIC LIGHTING NETWORK
.
DESIGN COMPLIES WITH ENERGEX STANDARDS
AND POLICIES
DESIGN COMPLIES
YES
'
THE CONSUL TANT SUBMITS THE DESIGN PACKAGE AND
ALL SUPPORTING DOCUMENTATION TO
ENERGEX
ENERGEX ACCEPTS PACKAGE
YES
NO
EN ERG EX MAKE A "LETTER OF OFFER" AND A PUBLIC LIGHTING SUPPLY
AGREEMENT (PLSA) TO THE DEVELOPER VIA THE CONSULTANT'S OFFICE
OTHERAPPROVALSAS MAY BE REQUIRED: POWERLINK, □ERM, QUU, APA GAS, ETC
DESIGN ACCEPTED
YES
NO
ENERGEX ISSUES A LETTER OF OFFER ANDA
PUBLIC LIGHTING SUPPLY AGREEMENT
THE DEVELOPER SIGNS THE ENERGEX SUPPLY AGREEMENT AND PAYS ALL FEES
NO THE PROJECT DOES NOT PROCEED AND ENERGEX
►-I--< WILL CANCEL THE
YES .
THE DEVELOPER RETURNS THE SIGNED PUBLIC LIGHTING SUPPLY
AGREEMENT TO EN ERG EX, VIA CONSULTANT'S OFFICE.
PROJECT AND ARCHIVE THE MASTER FILE
•
SITE CONTACT DETAILS
NAME . COMPANY .
PHONE -MOBILE -FAX -E-MAIL -
I
PROJECT CONSTRUCTION
CONSTRUCTION OF THE PROJECT CAN ONLY COMMENCE WHEN THE ENERGEX ACCREDITED ELECTRICAL CONTRACTOR IS IN POSSES ION OF THE APPROVAL TO CONSTRUCT - ISSUED BY ENERGEX.
THE DEVELOPER, WITH THE ASSISTANCE OF THE DESIGN CONSUL TANT, TENDERS THE
PROPOSED WORKS TO ENERGEX ACCREDITED ELECTRICAL
CONTRACTORS
'
THE ENERGEX ACCREDITED ELECTRICAL CONTRACTORS SUBMIT
THEIR TENDER PRICES TO THE CONSUL TANT AND THE DEVELOPER
THE DEVELOPER APPOINTS THE SUCCESSFUL ENERGEX ACCREDITED
ELECTRICAL CONTRACTOR
'
THE CONSUL TANT PROVIDES THE DETAILS OF THE APPOINTED
ELECTRICAL CONTRACTOR TO ENERGEX
!!!lJ!.; THESE DETAfLS MAY HAVE ALREADY BE SUBMITTED WITH THE
DESIGN PACKl!GE
'
ENERGEX ISSUES THE APPROVAL TO CONSTRUCT
ENERGEX ISSUES THEAPPROVAL TO CONSTRUCT TO THE DESIGN
CONSUL TANT AND THE ACCREDITED ELECTRICAL CONTRACTOR
START OF CONSTRUCTION OF THE RATE 2 PUBLIC LIGHTING PROJECT
PROJECT CONSTRUCTION
ELECTRICAL CONTRACTOR THE ACCREDITED ELECTRICAL CONTRACTOR CONSTRUCTS TliE PUBLIC LIGHTING WORKS USING ENERGEX APPROVED MATERIALS AND IN ACCORDANCE WITH ENERGEX'S CONSTRUCTION STANDARDS
DESIGN CONSULTANT THE DESIGN CONSUL TANT PROVIDES ONGOING TECHNICAL SUPPORT TO THE ELECTRICAL CONTRACTOR DURING THE CONSTRUCTION PHASE OF THE PROJECT FOR ISSUES SUCH AS: (i) NON STANDARD CONSTRUCTION APPROVALS. (ii) OUT OF ALIGNMENT APPROVALS. (iii) SHALLOW CONDUIT APPROVALS. (iv) DESIGN AMENDMENTS. (v) REVISED WORKSPLANS, ETC.
. SWITCHING AND COMMISSIONING
THE ACCREDITED ELECTRICAL CONTRACTOR LIAISES DIRECT WITH THE ENERGEXASSESSMENT OFFICER IN THE LOCAL ENERGEX HUB DEPOT Willi REGARD TO SWITCHING AND COMMISSIONING OF THE NEWLY BUil T ASSETS. THE ELECTRICAL CONTRACTOR SWITCHES AND COMMISSIONS TliE RATE 2 PUBLIC LIGHTING ASSETS .
EN ERG EX UNDERTAKES NO SWITCHING AND NO COMMISSIONING OF RATE 2 PUBLIC LIGHTING ASSETS, THIS IS THE RESPONSIBLITY OF THE ACCREDITED ELECTRICAL CONTRACTOR.
COMPLETION PACKAGE
FOLLOWING COMMISSIONING OF THE ASSETS, THE ELECTRICAL CONTRACTOR SUBMITS THE"COMPLETION PACKAGE~ TO THE ENERGEX CONTESTABLE WORKS TEAM. SPECIFIC TIME LIMITS APPLY TO THIS PROCESS.
THE CONTESTABLE WORKS TEAM THEN SCHEDULES A FINAL PRODUCT AUDIT OF THE COMMISSIONED ASSETS.
ENERGEX UNDERTAKES A FINAL PRODUCT AUDIT OF THE
COMMISSIONED AS BUILT ASSETS
'
THE EN ERG EX ASSESSMENT OFFICER CONDUCTS A
COMPLIANCE AUDIT OF THE AS CONSTRUCTED WORKS
I CONSTRUCTION DEFECTS
THE CERTIFICATE OF COMPLETION FROM THE ELECTRICAL CONTRACTOR IS
INCLUDED IN THE "COMPLETION PACKAGE"
THE ELECTRICAL CONTRACTOR IS RESPONSIBLE FOR RECTIFYING ANY CONSTRUCTION NON-CONFORMANCES (DEFECTS) FOUND DURING TliE FINAL PRODUCT AUDIT
ENERGEX ISSUES THE CERTIFICATE OF ACCEPTANCE
THE WORKS
PASS AUDIT
YES
ENERGEX ACCEPTS OWNERSHIP OF THE
PUBLIC LIGHTING INSTALLATION AND
ISSUES A CERTIFICATE OF ACCEPTANCE TO
THE ELECTRICAL CONTRACTOR AND TliE DESIGN CONSUL TANT
'
NO
THE ACCREDITED ELECTRICAL CONTRACTOR FORWARDS A
COPY OF THE CERTIFICATE OF
(
ACCEPTANCE TO THE DEVELOPER
FINISH )
DESIGN DEFECTS THE DESIGN CONSULTANT IS RESPONSIBLE FOR RECTIFYING ANY DESIGN NON-CONFORMANCES (DEFECTS) FOUND DURING TliE FINAL PRODUCT AUDIT
I
NOMENCLATURE The design consultant and the electrical contractor are referred to as Accredited Service Providers or ASP's for the purpose of DD&C (Developer Design and Construct) Contestable Works Projects.
ALIGNMENTS WORKS COORDINATOR: . APPROVED: - ENERGEX WORKPLANS VERSION 5.0
ENERGEXOH - PARENT PROJECT No: . RPEQNo: - SCALE: NOT APPLICABLE
ENERGEXUG WORKS REQUEST No: . CHECKED: PROJECT/SUB PROJECT No. -TELSTRA - PHONE: (07) DEVELOPER DESIGN AND CONSTRUCT
CONTESTABLE WORKS GAS - PROPOSED LOTS: . DESIGNER : J. LAMBERT
HP GAS CANCELLING LOT PHONE: (07) 3664 7244 Sxxxxxxx - .
WATER PLANNER: J. LAMBERT -STORMWATER - LOCAL AUTHORITY: . PHONE: (07) 3664 7244 RATE 2 PUBLIC LIGHTING
SHEET 1 OF 1 A1 HIGH LEVEL PROCESS FLOWCHART SEWERAGE - UBD GRID REF: .
01 l 1 l 1 l ISSUE DATE : 22.04.2019 OTHER - MAINS POLES PEGGED: .
1 I