access to esf by sub-contracting to dwp prime contractors

Upload: ncvo

Post on 03-Apr-2018

227 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/28/2019 Access to ESF by sub-contracting to DWP prime contractors

    1/16

    ACCESS TO ESF BY SUB-CONTRACTING TO DWP PRIME CONTRACTORS

    Summary

    Prime contractors compliance with DWP Code of Conduct obligations in their dealings with sub

    contractors was generally good, with third sector sub contractors responding that compliance was

    generally adequate or better. Compliance was rated better, on average, with regard to pre-award of

    contract obligations (89%) than compliance with post award of contract obligations (79%).Compliance was rated particularly good in areas of Competition and Advertising at the pre award of

    contract phase and particularly good in areas of communication (...very open to sharing best practice

    and documentation) and support in the post award of contract phase.

    Examples of poor compliance were, however, cited with regard to most Code of Conduct obligations.

    Areas in particular need of improvement were those in the post award of contract phase. With regard

    to monitoring, one respondent remarked that monitoring changed on a weekly basis over 6 months. A

    further area of particular concern for third sector organisations is poor compliance of the Prime in the

    provision of funding that reflects the relative ability to bear risks. One organisation remarked that the

    prime had little understanding of specific client groups needs and the costs required in helping clientsovercome barriers to employment. Another referred to the prime requiring changes to the process of

    delivery in order to receive a payment.

    These areas of poor compliance are a concern for small third sector organisations given the

    difference in bargaining power between the Prime and small third sector organisations. We therefore

    welcome the introduction of the Merlin Standards1 which aim to foster professional sub contractor

    commissioning and management of sub contracts, mirroring public sector standards. It is hoped that

    the standards will scrutinise the Prime provider and reduce examples of poor compliance with Code

    of Conduct obligations. The introduction of an ombudsman to act as a mediation and arbitration

    service is particularly welcome, providing small third sector organisations an alternative route forresolution in areas of poor compliance with Code of Conduct obligations.

    Introduction

    Prior to policy changes during the latter stages of the 2000-2006 European Social Fund (ESF)

    programme, third sector organisations accessed ESF through direct bidding. Under this process,

    organisations would submit project applications to the Government Office2 and would be responsible

    for finding their own match. Following the introduction of Co-financing ESF was channelled through

    Co-financing Organisations (CFOs) such as the Learning and Skills Council and the Department for

    Work and Pensions. In the current (2007-2013) programme ESF is mainly channelled through CFOs

    and is subject to competitive tendering. Fewer contracts of a larger scale are awarded compared to

    previous programme. DWP has the largest allocation of ESF for Priority 1 Extending Employment

    Opportunities (around 300 million). The main objective of this Priority is to increase employment,

    reduce unemployment and inactivity whilst tackling barriers to work faced by disadvantaged groups3.

    1For further information seehttp://www.dwp.gov.uk/supplying-dwp/what-we-buy/welfare-to-work-services/subcontractingwithdwp.shtml2

    See section 4 of the TSEN commissioned report (2009)Evidence Review of the Impact of the ESF on Those Furthest From the Labour Marketfor

    allocation of funding for 2007-2010.

    1

    http://www.dwp.gov.uk/supplying-dwp/what-we-buy/welfare-to-work-services/subcontractingwithdwp.shtmlhttp://www.dwp.gov.uk/supplying-dwp/what-we-buy/welfare-to-work-services/subcontractingwithdwp.shtmlhttp://www.tsen.org.uk/TSEN%20Evidence%20review.pdfhttp://www.dwp.gov.uk/supplying-dwp/what-we-buy/welfare-to-work-services/subcontractingwithdwp.shtmlhttp://www.tsen.org.uk/TSEN%20Evidence%20review.pdf
  • 7/28/2019 Access to ESF by sub-contracting to DWP prime contractors

    2/16

    DWP Procurement and the Third Sector

    The providers awarded large regional or sub regional contracts (contracting directly with DWP) are

    known as Prime providers. Smaller third sector organisations do not have the capacity to access ESF

    through large regional or sub regional contracts. Instead, small third sector organisations can access

    ESF through securing smaller contracts (otherwise known as sub contracts) with Prime providers to

    deliver a portion of the larger regional or sub regional contract.

    This method of administering ESF (through prime providers and sub contractors) is set out in the

    DWPs Commissioning Strategy. The strategy sets out a Code of Conduct 4 which stipulates the

    values and principles DWP expect prime providers to comply with in their relationship with sub

    contractors. In November 2009, the DWP launched a two year pilot of the Merlin Standard 5. The pilot

    involves the publication of the Merlin standard itself (used as a measure of Prime Provider

    compliance with Code of Conduct obligations), Mediation and Arbitration Service, and a web portal to

    share information. It is envisaged that these three strands will lead to subcontracting opportunities

    commissioned through a common industry process.

    Survey Aims

    The broad aim of this survey is to learn about the experience of third sector providers seeking access

    to ESF through DWP prime providers by asking respondents to rate the degree to which the prime in

    question had complied with the Code of Conduct obligations set out in the DWP commissioning

    strategy. The Code of Conduct obligations are divided into pre award of contract and post award of

    contract phases.

    The survey6reflects this division in the analysis of the results. Responses were restricted to the

    following: Exemplary compliance, very good compliance, adequate compliance, poor compliance,

    several problems complying, failed to comply.

    If the respondent rated compliance as particularly good or particularly bad they were asked to cite

    examples of according prime provider behaviour. Examples cited by respondents are reproduced

    below if appropriate. In the following, each Code of Conduct obligation is set out, with the distribution

    of respondent ratings and according examples of particularly poor or particularly good compliance.

    Not all examples are reproduced. Only those which are representative of examples most commonly

    made.

    Respondents also considered their overall experience of being a sub contractor with DWP, and some

    indicated the value of the sub contracts they were seeking to achieve.

    Respondents

    3Seehttp://www.tsen.org.uk/legregional.aspfor further detail on the Priorities of the English European Social Fund programme as set out by theOperational programme.4See Annex 1 of the DWP Commissioning Strategy, Feb 2008www.tsen.org.uk/documents/DWP_Commstrategy.pdf5

    For further information see http://www.dwp.gov.uk/supplying-dwp/what-we-buy/welfare-to-work-services/subcontractingwithdwp.shtml6Seewww.tsen.org.uk/documents/DWP_survey.pdffor the survey

    2

    http://www.tsen.org.uk/legregional.asphttp://www.tsen.org.uk/legregional.asphttp://www.tsen.org.uk/documents/DWP_Commstrategy.pdfhttp://www.tsen.org.uk/documents/DWP_Commstrategy.pdfhttp://www.tsen.org.uk/documents/DWP_Commstrategy.pdfhttp://www.dwp.gov.uk/supplying-dwp/what-we-buy/welfare-to-work-services/subcontractingwithdwp.shtmlhttp://www.dwp.gov.uk/supplying-dwp/what-we-buy/welfare-to-work-services/subcontractingwithdwp.shtmlhttp://www.tsen.org.uk/documents/DWP_survey.pdfhttp://www.tsen.org.uk/documents/DWP_survey.pdfhttp://www.tsen.org.uk/documents/DWP_survey.pdfhttp://www.tsen.org.uk/legregional.asphttp://www.tsen.org.uk/documents/DWP_Commstrategy.pdfhttp://www.dwp.gov.uk/supplying-dwp/what-we-buy/welfare-to-work-services/subcontractingwithdwp.shtmlhttp://www.tsen.org.uk/documents/DWP_survey.pdf
  • 7/28/2019 Access to ESF by sub-contracting to DWP prime contractors

    3/16

    There were 53 responses in total. 34 of these respondents held sub contracts with the DWP. There

    are 102 DWP third sector sub contractors (using the LSC definition of third sector).

    Table 1: Provider applications by region

    Responses Percent

    South East 13 24.5

    Cornwall 9 17.0London 6 11.3

    Merseyside 4 7.5

    South West 4 7.5

    Yorkshire and

    Humberside

    4 7.5

    East Midlands 3 5.7

    East 3 5.7

    North East 3 5.7

    West Midlands 3 5.7

    The rest of the North West 1 1.9

    Success in the 2000-2006 ESF programme

    Some of the respondents successfully accessed ESF through more than one route in the previous

    programme. Therefore the number of responses exceeds the number of respondents 53. 49

    attempted to become a sub contractor in the current ESF programme. Analysis focuses on these 49,

    excluding the four that did not attempt to become a sub-contractor.

    Table 2: Success in application for ESF in last (2000-2006) programme

    Response No of Responses

    Have never applied before 15

    Yes, successful through LSC co-financed tendering 14

    Yes, successful through direct bidding 13

    Yes, successful through other co-financed tendering 10

    Not successful in our own right, but delivered ESF activities as partner or sub-contractor. 7

    Have applied but never succeeded 0

    3

  • 7/28/2019 Access to ESF by sub-contracting to DWP prime contractors

    4/16

    Pre -awarding of contract stage

    Respondent ratings of Prime contractor compliance with pre awarding of

    contract Code of Conduct obligationsand examples of particularly good or

    particularly bad compliance cited by respondents

    Figures 1 to 6 show the respondents ratings of the pre awarding of contract Code of Conduct

    obligations. Respondents examples of particularly bad or good compliance are reproduced next to

    the overall respondent ratings. Note that in some cases no examples of particularly bad or good

    compliance were cited. Table 3 shows the proportion of respondents that rated compliance with the

    Code of Conduct obligations as adequate or better.

    Figure 1: How far do you think the Prime Contractor complied with the Code of Conduct obligation to:

    ADVERTISE SUB-CONTRACTING OPPORTUNITIES AS OPENLY AND AS WIDELY AS POSSIBLE?

    4

    Particularly good

    They advertised on website. Follow up was very good

    Advertised to a number of organisations, received e-mail

    advertisements

    Particularly bad

    Didnt advertise at all spoke to the organisations they

    knew

  • 7/28/2019 Access to ESF by sub-contracting to DWP prime contractors

    5/16

    Figure 2: How far do you think the Prime Contractor complied with the Code of Conduct obligation to:

    CONDUCT A SUB-CONTRACTING APPLICATION PROCESS THAT WAS OPEN AND FAIR, AS SIMPLE AS POSSIBLE,

    CONSISTENT, AND IN PROPORTION TO THE SIZE OF THE CONTRACT?

    Particularly good

    very well organised in terms of information available and

    method for expressing interest

    Open to negotiation every stage of the process

    Particularly bad

    did not conduct a process

    Figure 3: How far do you think the Prime Contractor complied with the Code of Conduct obligation to:

    ALLOW POTENTIAL SUB-CONTRACTORS TO NEGOTIATE WITH THEIR (THE PRIME'S) COMPETITORS? (AND)

    OFFER CONTRACTS OF SUFFICIENT LENGTH TO ENABLE LONG-TERM PLANNING AND INVESTMENT?

    Figure 4: How far do you think the Prime Contractor complied with the Code of Conduct obligation to:

    5

  • 7/28/2019 Access to ESF by sub-contracting to DWP prime contractors

    6/16

    AGREE TERMS OF DELIVERY AT THE OUTSET, AND AGREE HOW RISK IS ALLOCATED?

    Figure 5: How far do you think the Prime Contractor complied with the Code of Conduct obligation to:

    PROVIDE FUNDING THAT IS FAIR AND REFLECTS THE RELATIVE ABILITY TO BEAR RISKS

    Figure 6: How far do you think the Prime Contractor complied with the Code of Conduct obligation to:

    PROVIDE TIMELY, TRANSPARENT, FEEDBACK IF YOU WERE UNSUCCESSFUL IN BECOMING A SUBCONTRACTOR?

    6

    Particularly good

    Pre contract negotiations set up to discuss programme

    criteria and the setting of achievable targets

    Partnership approach

    Particularly bad

    Several cost reductions & non-negotiable outcome

    changes; reportedly required by DWP during post tender

    discussions but later due to errors in Prime's finance

    calculations.

    Particularly bad

    Little understanding of specific client group's needs orcosts associated in helping clients overcome barriers to

    employment; again told funding non-negotiable &

    governed by DWP expectations.

    ..(the prime) had agreed price which they then decided

    was 'too much'....(the prime then) decided that (the lead

    partner) had been overpaid, some way into the delivery

    of the programme, and requested money back. This had

    a knock on effect to us

  • 7/28/2019 Access to ESF by sub-contracting to DWP prime contractors

    7/16

    Table 3: Proportion of respondents rating the prime contractors compliance with the respective pre-award Code

    of Conduct obligation as adequate or better

    Item %

    Contract Length 100.0Competition 96.8

    Advertising 94.3

    Application 91.9

    Provide funding that is fair and reflects the relative ability to bear risks? 84.6

    Terms & Risk 81.6

    Provide timely, transparent, feedback if you were unsuccessful in becoming a subcontractor? 75.0

    Mean 89.1

    Compliance with the Code of Conduct obligations was generally adequate or better. On average

    almost 90% (89.2%) of respondents rated compliance as adequate or better. Compliance was over

    90% in contract length, advertising, competition, advertising and application.

    Some respondents were very positive about their dealings with the prime, describing them as very

    honest, reliable, and organised. For providing funding that is fair and reflects the relative ability to

    bear risks, agreeing terms at the outset and providing feedback , 75% or more rated compliance as

    adequate to good. However, with regard to relative ability to bear risks two examples of particularly

    poor compliance were cited. One reported that the prime had initially agreed a price with the lead

    partner of the consortium and then, under the belief that this was too much, sought to recover the

    excess from the partner in question. Another reported that funding did not reflect client group needs,apparently on the basis of DWP expectations.

    It is important to note, however, that while there were instances of failure to comply the overall

    compliance at the pre award of contract stage was adequate or better.

    7

  • 7/28/2019 Access to ESF by sub-contracting to DWP prime contractors

    8/16

    Post-award of contract phase

    Respondent ratings of Prime contractor compliance with post awarding of

    contract Code of Conduct obligations and examples of particularly good

    or particularly bad compliance cited by respondents

    Figures 7 to 15 show the respondents ratings of compliance for the post awarding of contract Code ofConduct obligations. Table 4 shows the proportion of respondents that rated compliance with the

    Code of Conduct obligations as adequate or better

    Figure 7: How far do you think the Prime Contractor complied with the Code of Conduct obligation to:

    LIVE UP TO COMMITMENTS THEY MADE AT THE TIME OF CONTRACTING?

    8

    Particularly good

    Open honest, provided training, database

    and very open for suggestions for

    paperwork and weve been quite

    instrumental on paperwork available and

    statistically open at meeting

    Particularly bad

    twice tried to reduce the agreed price

    and cancelled contract. ..requirements

    for process of delivery in order to receive

    payment changed several times.

    . Not honoured the contract - ran

    courses for the first month then not paid

    for this. Therefore service stopped

  • 7/28/2019 Access to ESF by sub-contracting to DWP prime contractors

    9/16

    Figure 8: How far do you think the Prime Contractor complied with the Code of Conduct obligation to:

    EMPLOY MONITORING & MANAGEMENT THAT IS NOT OVERLY BUREAUCRATIC AND THAT IS CONSISTENT,

    PROPORTIONATE, CLEARLY SPECIFIED AND AGREED AT THE TIME OF CONTRACT?

    Particularly good..formal structured fair two way meetings.

    Partnership management is very good

    Particularly bad

    ...changed on weekly basis over 6 months

    and was recognised by other government

    bodies as overly bureaucratic.

    ..little or none to a lot.

    Figure 9: How far do you think the Prime Contractor complied with the Code of Conduct obligation to:

    PROVIDE REASONABLE EXTRA SUPPORT TO NEW ENTRANTS TO THE MARKET?

    PROVIDE ADVANCE PAYMENTS WHERE NECESSARY TO ACHIEVE VALUE FOR MONEY?

    9

  • 7/28/2019 Access to ESF by sub-contracting to DWP prime contractors

    10/16

    Figure 10: How far do you think the Prime Contractor complied with the Code of Conduct obligation to:

    ENSURE TRANSPARENCY ABOUT DECISIONS OR REFERRALS?

    Particularly good

    If we have outcome rejected, full explanation is provided

    and help to go forward

    Particularly bad

    poor referral system was to detriment of customers and

    posed significant risk to our reputation.

    Figure 11: How far do you think the Prime Contractor complied with the Code of Conduct obligation to:

    AGREE PAYMENT TIMINGS THAT ARE CONSISTENT AND MINIMISES RISK TO THE DELIVERY BODY

    10

  • 7/28/2019 Access to ESF by sub-contracting to DWP prime contractors

    11/16

    Particularly good

    Clear payment profile with reasonable proportion payment

    based on starts

    We have agreed a system of monthly invoicing, which

    assists our cashflow

    Particularly badInconsistency around processing of invoicing and delays in

    payment

    Initial set-up poor; prime contractors mangers unsure of

    own financial accountability limits so agreements delayed;

    some payments not made

    Figure 12: How far do you think the Prime Contractor complied with the Code of Conduct obligation to:

    MAINTAIN OPEN LINES OF COMMUNICATION?

    Particularly good

    New contract manager and admin assistant are

    always available and we have regular meetings

    ..district manager very open, sharing best

    practice and documentation

    Where there been quality / performance issues

    there have been extra staff to support, contact

    responsive

    Particularly bad

    ..internal confusion within prime contractorsmeant discussions did not always result in

    agreed actions or changes

    11

  • 7/28/2019 Access to ESF by sub-contracting to DWP prime contractors

    12/16

    Figure 13: How far do you think the Prime Contractor complied with the Code of Conduct obligation to:

    NOT TO OBSTRUCT PRESENTATION OF REASONABLE STRATEGIC OR OPERATIONAL GRIEVANCES TO DWP?

    Particularly good

    Along with (name of Prime), we and the other two sub-

    contractors have all met together DWP and been

    provided with the opportunity to have direct

    communication with DWP staff in order to maximisedelivery

    Always had opportunity to have meetings with DWP

    represented

    Particularly bad

    Prevented involvement in dialogue / representation to

    DWP

    Figure 15: How far do you think the Prime Contractor complied with the Code of Conduct obligation to:

    AGREE AT THE OUTSET TO - AND IF NECESSARY COMPLY WITH - A SUFFICIENT TERMINATION PERIOD?

    Particularly goodVery clear within contract discussed issues involved from

    outset

    Agreed at point of setting up

    Particularly bad

    Not discussed

    Table 4: Percentage adequate or better for compliance with Code of Conduct obligation

    Item %

    Support 91.3

    12

  • 7/28/2019 Access to ESF by sub-contracting to DWP prime contractors

    13/16

    Communication 90.6

    Transparency 88.9

    Grievances 83.3

    Commitments 78.8

    Termination 76.9

    Timings 75.0

    Advances 70.6

    Monitoring 59.4

    Mean 79.4

    Compliance with the Code of Conduct obligations at the post award of contract phase was generally

    adequate or better. On average almost 80% (79.4%) of respondents rated compliance as adequate or

    better. Compliance was over or near 90% in support for new entrants to the market, Communication,

    and transparency on decisions or referrals. With regard to Communication, one respondent reported

    that the prime providers district manager was very open to sharing best practice and documentation.

    Importantly, almost 80% of respondents felt that the prime had lived up to commitments made at the

    time of contracting.

    Two exceptions were made to the generally positive ratings of compliance with living up to

    commitments made at the time of sub contracting. One respondent reported that the prime had not

    honoured the contract by failing to pay the sub contractor for the training courses provided. Another

    reported that the prime had twice tried to reduce the agreed price and then cancelled the contract.

    Compliance with regard to payment timings and advances was rated between 70 to 75% adequate or

    better. Some respondents reported experience of clear payment profiles with reasonable proportion

    payment based on starts. Others reported that there were inconsistencies around payment timings.

    Compliance was worst in monitoring, almost 60% adequate or better. One respondent reported that

    monitoring changed on a weekly basis over 6 months and was recognised by other government

    bodies as overly bureaucratic.

    Overall experience of being a sub contractor

    Table 5 shows the overall experience of being a sub-contractor. Respondents could choose more

    than one response therefore total responses exceed the number of respondents. Most respondents

    (54%) had full and open advance discussions resulting in the shared ownership of the tender with few

    (11%) responding that they had been included in the tender with little or no involvement. 43% felt that

    involvement at the time of responding had been specified in an equitable and timely way. Many (43%)

    respondents had little involvement until delivery and a similar number stated involvement was exactly

    as planned.

    Table 5: Overall experience as a sub-contractor

    Item Number

    13

  • 7/28/2019 Access to ESF by sub-contracting to DWP prime contractors

    14/16

    Advance discussions were conducted in an proper

    partnership fashion with open and full discussion,

    resulting in shared ownership of the tender

    19 (54%)

    We had little or no further involvement until the time

    to begin delivery arrived.

    15 (43%)

    Our involvement with the lead/prime has been exactly

    as planned.

    15 (43%)

    We have been kept fully informed with the progress of

    the tender and subsequent contracting negotiations.

    14 (40%)

    We were canvassed for our involvement but had little

    input into the tender.

    10 (29%)

    Our involvement has now been specified in an

    equitable and timely way.

    10 (29%)

    Our lead/prime has begun discussions again on the

    terms of our involvement.

    7 (20%)

    Our involvement has been, to a significant extent,

    "dictated" to us without proper involvement

    6 (17%)

    We were included in the tender with little or no

    involvement.

    4 (11%)

    Table 6: Time period after the in-principle decision to award a sub-contract

    Time Period No of

    Resp.

    Percent

    No delay 3 10.0

    < 2 months 9 30.0

    2-3 months 14 46.7

    4-5 months 4 13.3

    Total7 30 100.0

    Value of contract sought and awarded

    Respondents were asked about the value of the contract which they sought to and the contract value

    they were actually awarded by the prime contractor. It is important to note that 18 (51%) of the 35

    respondents who obtained a contract with the prime responded to this question. The majority of those

    7 Should be 35, presumably 5 respondents did not answer

    14

  • 7/28/2019 Access to ESF by sub-contracting to DWP prime contractors

    15/16

    responding to this question (55.6%) achieved 100% of the contract value which they were seeking.

    Almost three quarters of those responding to this question achieved 75% or above of the contract

    value they were seeking. It is important to note however that 27% achieved less than 50% of the

    contract value they were seeking, with 22% of those responding to this question achieving less than

    25% of the contract value they were seeking.

    Table 7: Value of contract sought and value of contract actually awarded to third sector organisation

    Attempt Actual % actual of attempt

    1,200,000 1,200,000 100.00

    750,000 75,000 10.00

    600,000 450,000 75.00

    221,000 221,000 100.00

    130,000 130,000 100.00

    120,000 100,000 83.33

    62,000 62,000 100.00

    60,000 3,000 5.00

    51,000 51,000 100.00

    50,000 15,000 30.00

    38,280 38,280 100.00

    35,000 35,000 100.00

    33,000 33,000 100.00

    30,000 22,500 75.00

    30,000 5,000 16.67

    11,200 11,200 100.00

    4,200 4,200 100.00

    4,200 300 7.14

    Table 8: Frequency bands and cumulative %

    % funded of that applied for Frequency % Cumulative %

    =100% 10 55.6 55.6

    >=75 and =50 and =25 and

  • 7/28/2019 Access to ESF by sub-contracting to DWP prime contractors

    16/16

    % funded of that applied for Frequency % Cumulative %