accepted value engineering proposal - you design it. predl

16
Accepted Value Engineering Proposal Recognized Advantages of PREDL Concrete Protective Liner Systems [ Rohnert Park, CA ] PREDLsystems.com Owner: City of Rohnert Park [ Rohnert Park, CA ] Engineer: GHD Engineering [ Santa Rosa, CA ] Contractor: Ghilotti Construction Company [ Santa Rosa, CA ] Precaster: Jensen Precast [ Sacramento, CA ] ISO 9001:2015

Upload: others

Post on 14-Apr-2022

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Accepted Value Engineering Proposal - You design it. PREDL

Accepted Value Engineering ProposalRecognized Advantages of PREDL Concrete Protective Liner Systems

[ Rohnert Park, CA ]

PREDLsystems.com

Owner: City of Rohnert Park [ Rohnert Park, CA ]

Engineer: GHD Engineering [ Santa Rosa, CA ]

Contractor: Ghilotti Construction Company [ Santa Rosa, CA ]

Precaster: Jensen Precast [ Sacramento, CA ]

ISO 9001:2015

Page 2: Accepted Value Engineering Proposal - You design it. PREDL

Project Plans

Page 2 of 16

Page 3: Accepted Value Engineering Proposal - You design it. PREDL

Custom Connection Detail for PREDL Bell & Compression Gasket

Page 3 of 16

Page 4: Accepted Value Engineering Proposal - You design it. PREDL

Original Proposal vs. PREDL Systems Accepted Value Engineering Proposal

Competitor’s Design [ Min 60” Dia Requiered ] PREDL Design [ 48” Dia Requiered ]

Page 4 of 16

PREDL HDPE CORPROTECT

PREDL FRP BASELINER

RIGID PIPE CONNECTION ACCURATE, FLEXIBLE, WATER TIGHTPREDL PIPE CONNECTION

Page 5: Accepted Value Engineering Proposal - You design it. PREDL

Original Proposal vs. PREDL Systems Accepted Value Engineering Proposal

Page 5 of 16

All tasks with strike through indicate ways in which PREDLsystems Accepted Value Engineering Proposal Reduced Time and Cost from Standard Specification.

Page 6: Accepted Value Engineering Proposal - You design it. PREDL

Page 6 of 16

Integral HDPE Transition Strip Allows Extrusion Weld Joint Connection to HDPE Lined Precast Risers

Page 7: Accepted Value Engineering Proposal - You design it. PREDL

PREDL FRP Baseliners Accomadate Tight Angle Flow Channel Designs

Page 7 of 16

48” Dia MH

24” C905

DR25 PVC

PIPE

Page 8: Accepted Value Engineering Proposal - You design it. PREDL

PREDL Precast Concrete Partner [ Jensen Precast - Sacramento, CA ]

Page 8 of 16

Page 9: Accepted Value Engineering Proposal - You design it. PREDL

Post Pour - No Additional Finishing Steps Requiered... Pour, Strip and Ship

Page 9 of 16

Page 10: Accepted Value Engineering Proposal - You design it. PREDL

Delivered Onsite to Contractor Partner [ Ghilotti Construction Company - Santa Rosa, CA ]

Page 10 of 16

Page 11: Accepted Value Engineering Proposal - You design it. PREDL

1ST PREDL Installation in California [ December 16th, 2013 ]

Page 11 of 16

Page 12: Accepted Value Engineering Proposal - You design it. PREDL

Field Installation Method for Downstream Pipe - PREDL Bell & Compression Gasket

Page 12 of 16

Pipe Cut to Length

then Chamferd

Excavator Drives

MH onto Pipe

Lubricant Applied to Gasket Lip

Field Chamfered Spigot

w/ Applied Lubricant

Page 13: Accepted Value Engineering Proposal - You design it. PREDL

Successful Execution of Pipe to MH Connection

Page 13 of 16

Page 14: Accepted Value Engineering Proposal - You design it. PREDL

Page 14 of 16

Project Details Presented @ WEFTEC 2015 [ Chicago, IL ]

Matt Winkelman, PE GHD [ Sata Rosa, CA ]

Page 15: Accepted Value Engineering Proposal - You design it. PREDL

METHODOLOGY AND FINDINGS

The 3.5 mile (5.6 km), 12- to 42-inch (300 to 1,060 mm) diameter ESTS conveys a flow rate of up to 14 mgd (53 ML/d) from various contributing sewers. Due to the size of the project, the planning, design, and construction was split into three phases to meet intermediate flow conditions and City budget needs. As the project was implemented over time, the City and design team embraced and applied wastewater industry and job-specific lessons learned, emerging construction materials, and revised planning numbers for collection system flows. A summary of project hydraulics and construction materials and techniques is provided below, which are based on lessons learned from the local project experience and conditions, as well as current trends in the wastewater industry.

Hydraulic ConsiderationsJob planning involved hydraulic evaluation and modeling of the City’s collection system. Emphasis was set on updating previous models with current planning numbers that accounted for water conservation measures, flows for various planned developments, and measured infiltration and inflow (I/I) rates. Areduction in base flows from planned developments resulted in a reduction in the ESTS pipeline diameter for Phases II and III. A summary of the planning numbers is provided below:

Water conservation and flows for planned developments: Base flows were adjusted in the City’s model to account for a new state law generally requiring a 20 percent reduction in water use for urban water suppliers.I/I flow rates: Results of flow monitoring study showed that performance of the City’s collection system more closely matched a reference standard. The model was calibrated to simulate observed conditions.

Through this analysis, the alignment and hydraulic performance needed for the ESTS was determined, which confirmed that conveyance of flows from the collection system by gravity was feasible, albeit challenging.

Emerging Construction Materials and TechniquesDue to aging collection system infrastructure, high groundwater table, and the use of pea gravel backfill for a majority of the City’s utilities, management of I/I has become a system-wide necessity. City collection system planning includes the use of modern construction materials and techniques to minimize I/I and promote high quality construction. Tables 1 and 2 provide a summary of construction materials and techniques used for the ESTS project.

The Challenge with Gravity – How to Build a Better Trunk Sewer

Matt Winkelman, PE, GHD Inc. ([email protected])Iver Skavdal, PE, GHD Inc.Darrin Jenkins, PE, City of Rohnert ParkPatrick Barnes, PE, City of Rohnert Park

GHD Inc.2235 Mercury Way, Suite 150Santa Rosa, CA 95407(707) 523-1010

ABSTRACT

The Eastside Trunk Sewer (ESTS) conveys a majority of the wastewater from the City of Rohnert Park(population ~45,000) to the City’s effluent pump station. This 3.5 mile (5.6 km), 18- to 42-inch (460 to 1,060 mm) pipeline conveys up to 14 mgd (53 ML/d) from various contributing sewers and traverses City commercial and residential corridors.

Planning and design for the ESTS involved a gravity pipeline that would manage various challenges such as high groundwater and poor soils during construction and minimize infiltration and inflow (I/I) over the service life of the construction materials. As the ESTS progressed through three phases of design and construction from 2005 to 2015, new and improved construction materials and techniques were incorporated into the project. Materials focused on two primary goals: 1) keeping manholes and pipelines water tight; and, 2) extending the useful life of the project to reduce future rehabilitation needs.Construction techniques focused on coordinating construction activities and quality assurance for excavation in difficult ground conditions and quality control for completed work.

Challenges and findings from the implementation of the materials and techniques are presented herein.

KEYWORDS

Collection systems, infiltration/inflow, innovative technology

INTRODUCTION

In contrast to many collection systems, the City of Rohnert Park system conveys all wastewater (with the exception of one small lift station) from the City’s service area (population ~45,000) by gravity through various collector, trunk, inverted siphon, and lateral sewers to the City’s effluent pump station. Planning for the Eastside Trunk Sewer (ESTS), which serves a majority of the east side of the City, followed the same planning scheme: to achieve gravity flow. This presented various challenges for design and construction, including: deep utility trenching in unconsolidated native soils within a high groundwater table and a seismically-active region; tunneling; resource agency permitting; and community impacts.

The ESTS alleviated hydraulic deficiencies within a large portion of the existing collection system by intercepting flows at key locations to relieve hydraulic impacts to undersized sewers. Completion of the project also allows for new development with the City’s service area. Figure 1 provides an overview of the project limits and phases, including the completion date for each phase.

The Challenge with Gravity – How to Build a Better Trunk Sewer

Page 15 of 16

Page 16: Accepted Value Engineering Proposal - You design it. PREDL

Table 2. ESTS Construction TechniquesConstruction Technique Benefits

Potholing all crossing existing utilities

Verify design conditions and coordinate with utility providers ahead of utility construction.

Stabilized unconsolidated soils in critical utility zones using an injected cement mixture

Increased the stiffness of native soils to reduce caving and associated impacts to surrounding infrastructure.

Installation of dewatering wells at 50- to 100-foot on center in combination with conventional shoring

Lowered groundwater levels ahead of utility trenching.Promoted efficient production rates for utility installation by enabling the use of conventional shoring techniques.Dewatered water reused for agricultural benefit during drought conditions.

Backfilled trenches using controlled low strength material (CLSM)

Promoted efficient production rates for utility installation by eliminating need for compaction efforts and testing of soil backfill.Improved backfill quality that reduces the potential for settlement-induced damages to surrounding hardscape.

Testing and CCTV inspection for pipelines, with low tolerance for pipe “bellies”

Verify quality of construction for flat sewer design.

Spark and vacuum testing for manholes

Verify quality of construction for water-tight installation of HDPE manhole liner.

SIGNIFICANCE

The ESTS project critically reviewed existing design standards of practice against emerging industry trends for construction materials and techniques. This effort began at job planning, with an assessment of hydraulic design criteria to fit with modern conditions for drought and water conservation, as well as the use of recorded flow data in lieu of empirical data for sizing of infrastructure. A review of industry trends continued during the design phase to incorporate modern construction materials that target reduced I/I and enhanced corrosion resistance, as well as construction techniques that promoted efficiencies and quality. During the construction phase, the project team worked with the contractor to promote a beneficial balance between quality and efficiency for production rates, requiring quality checks at regular intervals and for all installed system components.

The City invested capital funds for the long term betterment of its collection system. Future I/I contribution from the ESTS pipeline is anticipated to be very low, and with retrofits planned for other City infrastructure (i.e., replacement of manhole “chimneys”, rehabilitation of aging pipelines and manhole structures using trenchless technologies), operation and maintenance costs are anticipated to decrease.

Table 1. ESTS Construction MaterialsMaterial Benefits

Fiberglass manhole base insert

Increased water-tight design at pipe penetrations using integral pipe bells with compression gasket fittingsImproved quality control with factory fabrication of fiberglass insert in combination with precast concrete manhole baseIncreased efficiency for construction with the complete manhole base delivered to the site ready for installationReduced manhole diameters, typically from 60 inches to 48 inches,which reduced the excavation footprint and impacts to adjacent utilities.

High density polyethylene manhole liner

Increased water-tight design and resistance to hydrostatic pressure for manhole barrels and barrel joints using embedded HDPE anchors (a.k.a. “studs”) and welded seams.Improved corrosion resistance.

High density polyethylene manhole grade rings with external joint seal and tape wrap

Improved water-tight design near ground surface.

Composite manhole frame and cover

Reduced cover weight while maintaining structural integrity for use in roadways.Standardization of locking and opening mechanisms.

Water main piping (AWWA C905)

Increased hoop strength to account for pipe loading.Improved water-tight design at pipe joints using water main gasket connections.

The Challenge with Gravity – How to Build a Better Trunk Sewer

Page 16 of 16