acceleration

17
Delay and Disruption - Acceleration © Daniel Atkinson 21 November 2002 KEYWORDS: Delay and Disruption - Acceleration, constructive acceleration, deciding when to accelerate, reducing delays, acceleration measures, effect of acceleration, Glenlion Construction Ltd - v - Guinness Trust (1987) 39 BLR 89, obligation to accelerate, John Barker Construction Ltd v London Portman Hotel Ltd (1996) 83BLR35, Ascon Contracting Limited -v- Alfred McAlpine Construction Isle of Man Limited (1999), Motherwell Bridge Construction Limited v Micafil Vakuumtecchnik (2002) TCC 81 CONLR44, acceleration agreements, Lester Williams v Roffey Brothers & Nicholls (Contractors) Ltd (1989) 48BLR69, Amec & Alfred McAlpine (Joint Venture) v Cheshire County Council (1999)BLR303, express terms of standard forms, FIDIC 1998, ICE 7th Edition, ECC 2nd Edition, IChemE Red Book, MF/1 (Rev 4) 2000, JCT 1998, JCT 1998 With Contractor's Design, JCT 1998 Prime Cost Contract, IFC 1998, JCT 1998 Minor Works, CECA Blue Form 1998, DOM/1, The Problem Measures Effects Obligation Agreements Claims See also Constructive Acceleration EXPRESS TERMS OF STANDARD FORMS FIDIC 1998 ICE 7 Ed ECC 2 Ed MF/1 Rev 4 IChemE Red Book JCT 1998 JCT 1998 WCD JCT 1998 PC IFC 1998 JCT Minor CECA Blue DOM/1 SUMMARY Acceleration frequently involves a change in the allocation of resources which may lead to loss of productivity. If the entitlement to extension of time is uncertain, the contractor is faced with a difficult choice. The obligation to accelerate is examined together with terms of standard forms.

Upload: gimasavi

Post on 18-Aug-2015

215 views

Category:

Documents


0 download

DESCRIPTION

construction

TRANSCRIPT

Delay and Disruption - Acceleration Daniel Atkinson 21 November 2002KEYW!D"# Delay and Disruption - Acceleration$ constructive acceleration$ decidin% &'en to accelerate$ reducin% delays$ acceleration measures$ e(ect o) acceleration$ *lenlion +onstruction ,td - v - *uinness -rust .1/012 3/ 4,! 0/$ obli%ation to accelerate$ 5o'n 4arker +onstruction ,td v ,ondon 6ortman 7otel ,td .1//82 034,!39$ Ascon +ontractin% ,imited -v- Al)red :cAlpine +onstruction ;sle o) :an ,imited .1///2$ :ot'er&ell 4rid%e +onstruction ,imited v :icaG bli%ation to AccelerateThe &mployers remedy !or the (ontractors breach o! contract in !ailing to complete by the (ompletion Date will be damages, whether general damages or li#uidated damages. *any standard !orms re#uire the (ontractor not only to complete by the (ompletion Date but also toproceed regularly and diligently. *any standard !orms provide a power !or acceleration to be ordered in the event o! the contractors de!ault in progressing with due diligence, without additional payment. *any standard !orms also provide a power !or ordering the (ontractor to adopt acceleration measures i! it is considered that progress is not in accordance with the programme, I! due to the (ontractors de!ault. ;uch powers do not normally e$tend to agreeingto accelerate in the absence o! the contractors de!ault, which re#uires a separate agreement. I! such an agreement is entered into it is important to ensure that the terms relating to li#uidated damages still operate.In 5o'n 4arker +onstruction ,td v ,ondon 6ortman 7otel ,td .1//82 034,!395arer were building contractors carrying out re!urbishment o! wors to the ? @orm with #uantities. The contract provided !or completion o! -oors A to 88 on 83th 2uly 8AAB, -oors C to > by 7Ath 2uly 8AAB and -oors 7 to B by 8BAugust 8AAB. (lause 7B provided that li#uidated damages would be paid at 4?,??? per wee !or each section o! the contract which was not completed by the speci"ed date. Delays occurred and it was apparent to all concerned that 2ohn 5arer was entitled to e$tensions o! time. A!ter negotiations it was agreed that the wor would be accelerated so that all the wor would be completed by 8Bth August 8AAB and 2ohn 5arer would receive additional payment.A!ter the acceleration agreement there were !urther delays and !urther instructions !rom the Architect. Dne o! the issues which arose was the e'ect o! the acceleration agreement on the sectional completion provisions o! the contract in relation to li#uidated damages.2ohn 5arer argued that the e'ect o! the acceleration agreement was to dispense with all the provisions o! the sectional agreement supplement, including the provisions !or li#uidated damages. It was argued that the substitution o! a single date was logically inconsistent with such provisions having continuing contractual !orce. This was not accepted. It was common ground that at the time o! the acceleration agreement no9one raised the #uestion o! abandoning the li#uidated damages provisions. It was held that it was neither intended by the parties nor logically necessary that the li#uidated damages would no longer apply. It was held that the provisions o! the ;ectional completion supplement regarding li#uidated damages were capable o! continuing to have contractual !orce by merely substituting the new date o! 73th August 8AAB !or completion o! each ;ection. The parties intention did not go beyond that.In Ascon +ontractin% ,imited -v- Al)red :cAlpine +onstruction ;sle o) :an ,imited .1///2 there had been delays due to a number o! causes and Ascon the concrete subcontractor claimed e$tension o! time. It was held that in considering the subcontractors entitlement to e$tension o! time, that it could not be re!used or reduced because o! the possibility o! !uture acceleration. That would impose an obligation on the subcontractor to incur e$pense in order to mitigate the conse#uences o! the contractors breaches o! contract.It would also deprive the subcontractors o! the opportunity, nowing how much o! the current delay had been allowed, o! assessing whether it was necessary to consider incurring additional e$pense in accelerative measures in order to reduce its potential liability in damages !or any disallowed balance, and i! so to decide !or itsel! how !ar it was in its own interests to incur that e$pense in the absence o! instructions to do so as a variation. Accordingly Ascon was awarded an e$tension o! time.It was not in dispute that Ascon was also entitled to damages to the e$tent o! any recoverable loss which could be established as caused by the period o! delay, and a sum was awarded.Ascon also claimed !or loss caused by acceleration measures it had undertaen. 0is 0onour 2udge 0ics E( stated that acceleration had no precise technical meaning. Acceleration which was not re#uired to meet a contractors e$isting obligations was liely to be the result o! an instruction !rom the &mployers !or which he must pay. Dn the other hand pressure !rom the &mployer to mae good delay caused by the contractors own de!ault was unliely to be so construed. There was no instruction in this case. Ascon was under pressure !rom *cAlpine to accelerate the wors to recover the time lost, but was insisting that it was not going to pay !oracceleration. Ascons claim on that basis did not there!ore succeed.Ascon claimed that it allocated additional resources, wored longer hours, wored seven days per wee and purchased and supplied duplicate plant and e#uipment. Ascon claimed that these acceleration measures were taen in order to mitigate the delays caused.It was held that there could not be both an e$tension to the !ull e$tent o! the &mployers culpable delay, with damages on that basis, and also damages in the !orm o! e$penses incurred by the way o! mitigation, unless it was alleged and established that the attempt at mitigation, although reasonable, was wholly ine'ective. Ascon had not put its case in that way.It contended that the wor was indeed completed sooner than it would have been in the absence o! the accelerative measures. The mitigation claim wholly !ailed at the outset and theacceleration claim also !ailed.In :ot'er&ell 4rid%e +onstruction ,imited v :icath Dctober 8AA> to *arch 8AAA. *ica"l raised the de!ence that a term o! the contract provided that i! une$pected delays and di,culties occurred, *otherwell was re#uired to provide additional personnel at no e$tra cost at the re#uest o! *ica"l in order to meet the re#uired completion date. It was held that the delays and di,culties came within the de"nition o! "une$pected". There was no dispute that *ica"l constantly urged *otherwell to increase its resources to meet the re#uested completion date. Accordingly 2udge ;eymour held that *otherwell could not succeed in recovering damages !or this item.The second acceleration claim is e$amined in the article (onstructive Acceleration9G Acceleration A%reements;ome standard @orms mae provision !or the parties to agree to accelerate the wors. &ven without such clauses, it is always possible !or the parties to agree to vary the contract to their mutual bene"t. I! the acceleration is necessary solely due to the contractors de!ault, it may beargued that the agreement to accelerate has no legal e'ect !or lac o! consideration, since the&mployer will simply obtain that which he is already contractually re#uired to receive.In ,ester Williams v !o(ey 4rot'ers ? Nic'olls .+ontractors2 ,td .1/0/2 >04,!8/)o'ey was the main contractor !or the re!urbishment o! a bloc o! -ats nown as Twynholm *ansions. Williams was a carpentry subcontractor providing labour !or the roo! and "rst and second "$ to the -ats with a total price o! 7?,???. The price was too low and a reasonable price should have been 74,G>4. This was !urther aggravated by Williams !ailing to supervise his men ade#uately, which reduced productivity. Williams there!ore were e$periencing "nancial di,culties.In April 8A>A )o'ey agreed to pay Williams an additional 8?,4?? at the rate o! CGC !or each completed -at in order to have Williams continue with the wors and complete on time. The carpentry wor was on the critical pathe o! )o'eys global operations so that !ailure by Williams to complete the wor in accordance with the ;ubcontract would lead to )o'ey being liable !or li#uidated damages !or delay under the main contract. The e$pected payments were not made by )o'ey so that in *ay 8A>A Williams ceased wor. )o'ey engaged other contractors to complete the wor.It was argued that the agreement to mae additional payments was not legally binding on )o'ey, since they had agreed to pay !or wor which Williams was already bound to carry out under the subcontract. There was no consideration.There was some di,culty in "nding consideration. It was held that in this case a bene"t was derived !rom the agreement by each party and that was su,cient consideration !or the promise to pay additional sums to be binding.Although not re!erred to as such, it is suggested that the agreement was in the !orm o! an acceleration agreement, the delay in this case having been caused by Williams own de!ault.There may be considerable di,culties in evaluating the additional costs o! acceleration and di'erentiating those costs !rom the costs o! carrying out the wors at the normal pace. 1ood records are vital, but it may be appropriate to simply tae a broad approach.In Amec ? Al)red :cAlpine .5oint =enture2 v +'es'ire +ounty +ouncil .1///24,!303(heshire appointed the 2oint Henture as contractor !or construction o! the Wilmslow and 0and!orth 5ypass at *anchester under the I(& Cth &dition. 5y the end o! 8AAB there had been various delays !or which the 2oint Henture was not responsible. An acceleration agreement wasentered into !or which the .oint Henture was paid various sums !or completing by 7C8AAC. &arly in 8AAC it became clear that there was liely to be another overrun and the 2oint Henture was entitled to !urther e$tensions o! time. An in!ormal agreement was entered into inwhich the 2oint Henture agreed to use its best endeavours to complete by 7Cth Dctober 8AAC and (heshire would pay !air and reasonable recompense !or the additional acceleration measures necessary. The date was achieved.:o speci"c method o! valuation had been agreed and disputes arose as to the method o! valuation, particularly because o! delays !or which (heshire was not responsible and because o! the di,culties o! separating out the cost o! wor which the 2oint Henture was already obliged to carry out under the original contract. A method o! valuation was decided as a preliminary issue which was endorsed by the (ourt.@irst the 2oint Hentures actual costs (I) were ascertained !or the period o! acceleration. The amount that the wor carried out in the period o! acceleration should have cost was evaluated(J). The evaluation too into account all the events that had taen place be!ore commencement o! the acceleration period. The basic calculation o! the acceleration costs wasthere!ore I9J. @urther subtractions were made !or !actors and events !or which the 2oint Henture was liable (A). A !urther subtraction was the cost o! variations ordered in the acceleration period (5) since these were included in I but not in J. The prima !acie entitlementwas there!ore I9J9(AK5) plus a reasonable amount !or overheads and pro"t. This approach wasadopted because o! the di,culties o! causation by analysis o! particular items o! wor and o! how time had been saved.Dne issue be!ore the (ourt was the ad.ustment to be made !or payments received by the 2oint Henture !rom their insurers !or events during the acceleration period. The essential #uestion was whether insurance payments should be taen into account in deciding a !air and reasonable remuneration. It was held that to allow a deduction would give (heshire the !ull bene"t o! the insurance cover whereas it was primarily !or the bene"t o! the 2oint Henture and only incidentally (heshire. @urther there would be no double recovery because the principles o! indemnity which lie at the bais o! insurance law would re#uire the .oint Henture to be accountable to the insurers !or the proceeds o! amounts received !rom (heshire o! the relevant amounts.8G +laims )or AccelerationI! the contract does not mae completion by a particular date or time an obligation under the contract then the contractor will not be able to mae a claim !or the cost o! acceleration measures. The only obligation will be to complete within a reasonable time which will involve optimi/ation o! the resources !or greatest e,ciency and productivity. In most standard !orms the contractor has an obligation to complete by a particular date or within a speci"ed period. &ven with such an obligation, the contractor will have some di,culty in pursuing the additional costs o! acceleration where the contract entitles him to an e$tension o! time !or the delays which have occurred. In the case where the e$tension o! time provisions are not properly operated, the contractor may consider a constructive acceleration claim, but this is not without its di,culties.I! the (ontractor is ordered to accelerate in the mistaen belie! that the delay is due to the (ontractors de!ault, whereas the delay was the responsibility o! the &mployer under the (ontract, then the (ontractor may be entitled to the acceleration costs.1G E@press -erms o) "tandard AormsThe standard !orms generally give the contract administrator power to re#uire the contractor to revise his programme to re9se#uence the wors to reduce the e'ects o! delays which are the contractors de!ault. ;ome !orms also give the contract administrator power to order acceleration to achieve the completion date i! the delay is due to the contractors de!ault. Dnly!ew !orms allow the (ontract Administrator to negotiate acceleration agreements. 1enerally the contractors obligations are to complete by the speci"ed date and also to proceed regularlyand diligently. 5reach o! this obligation normally allows the &mployer to terminate the contractors employment !ollowing notice and !ailure to remedy the de!ault.A;D;+ 1//0(lause 4.8 o! the )ed and Jellow @orms provides that the &ngineer has no authority to amend the (ontract. There is no power there!ore !or the &ngineer to negotiate an acceleration agreement !or the &mployer.As e$pected with a modern contract the (ontractors obligation under @IDI( @orms is tied into aprogramme. (lause >.8 o! the )ed, Jellow and ;ilver @orms re#uires the contractor to proceed with the Wors with due e$pedition and without delay. (lause >.B o! the )ed and (lause >.4 o! the Jellow and ;ilver @orms re#uires the (ontractor to proceed in accordance with the programme, sub.ect to his other obligations under the (ontract.(lause >.3 o! the )ed, Jellow and ;ilver @orms gives the &ngineer (&mployer under the ;ilver @orm) power to instruct the (ontractor to submit a revised programme with revised methods to e$pedite progress and complete within the Time !or (ompletion. The power arises i! the actual progress is too slow to complete within the Time !or (ompletion, or i! the progress has !allen or will !all behind the programme. There is no such power i! the cause is one o! the matters which entitles the contractor to an e$tension o! time. The (ontractor is re#uired to adopt the revised methods which are stated to include increases in the woring hours and%or increase in resources and%or goods. The revised methods are at the contractors cost and ris and he is liable !or the &mployers additional costs incurred in addition to any delay damages.(lause 8C.7(c)(i) o! the )ed and Jellow @orms and (lause 8C.7(c) o! the ;ilver @orm allows the &mployer to terminate the (ontract i! the (ontractor !ails to proceed with the Wors in accordance with (lause >, without reasonable e$cuse, and sub.ect to notice.;+E 1t' Edition(lause 7(8)(c) provides that the &ngineer has no authority to amend the (ontract or to relieve the (ontractor o! any o! his obligations under the (ontract, e$cept as e$pressly stated in the (ontract. (lause B3(4) re!ers to acceleration agreements. The &mployer or the &ngineer may re#uest the (ontractor to complete in less than the time or e$tended time !or completion. I! the (ontractor agrees, then special terms and conditions o! payment are to be agreed be!ore any acceleration measures are taen.(lause 8B(B) re#uires the (ontractor to submit a revised programme showing such modi"cations to the original programme as may be necessary to ensure completion o! the Wors within the time !or completion, i! it appears to the &ngineer at any time that actual progress did not con!orm with the accepted programme.(lause B3(8) gives the &ngineer power to noti!y the (ontractor that in his opinion the progresso! the Wors is too slow to ensure substantial completion by the time !or completion. Dn doingso the (ontractor is re#uired to tae such steps as are necessary, and to which the &ngineer consents, to e$pedite progress so as to substantially complete the Wors by the time !or completion. The power arises only i! the reason !or delay is not an event which entitles the (ontractor to an e$tension o! time. The (ontractor is not entitled to any additional payment !or taing the steps. Lnder (lause B3(7) the may not unreasonably withhold permission to wor on ;ite at night or on ;undays i! re#uested.(lause 3C(8) allows the &mployer to e$pel the (ontractor !rom site, i! the &ngineer has certi"ed in writing to the &mployer that despite previous warnings by the &ngineer in writing, in his opinion the (ontractor is !ailing to proceed with the wors with due diligence.E++ 2nd Edition(lause 4?.8 re#uires the (ontractor to do the wor so that (ompletion is on or be!ore the (ompletion date.(lause 47.8 re#uires the contractor to issue revised programmes regularly and these are re#uired to show actual progress achieved and the e'ect on the timing o! the remaining wor. The programme is also re#uired to show how the (ontractor plans to deal with any delays.(lause 43.8 gives the =ro.ect *anager power to instruct the (ontractor to submit a #uotation !or an acceleration to achieve completion be!ore the (ompletion date. The (ontractor may submit a #uotation which is re#uired to comprise changes to the =rices and the (ompletion date. Alternatively the (ontractor may give reasons !or not doing so. (lause 43.4 ((lause 43.B Dptions & and @) provides that when the =ro.ect *anager accepts a #uotation !or acceleration, he changes the (ompletion date (and =rices Dptions A to D) and he accepts the revised programme.Dne o! the secondary options is Dption E which provides !or the (ontractor to be paid a bonus!or early completion at a speci"ed rate !rom the date o! completion or tae9over and the (ompletion Date.(lause 3?.8(A) provides that withholding o! acceptance is a compensation event, but e$pressly states that withholding acceptance o! a #uotation !or acceleration is not a (ompensation &vent.(lause AC.7 provides that the &mployer may terminate i! the =ro.ect *anager has noti"ed thatthe (ontractor is in de!ault by substantially !ailing to comply with his obligations and has not put right the de!ault within !our wees o! noti"cation.;+'emE !ed 4ook(lause 88.8 provides that the =ro.ect *anager has !ull authority to act on behal! o! the =urchaser in connection with the (ontract. An e$ception is (lause 4G.AM the =ro.ect *anager does not have power to issue a notice stating the =urchasers election to tae9over the =lant, which the =urchaser may do at any time.(lause 84.8 re#uires the (ontractor to complete the construction o! the =lant within the periods stated in ;chedule C (Times and ;tages o! (ompletion). The (ontractor is also re#uired to use his reasonable endeavours to per!orm his obligations in accordance with the Approved =rogramme. (lause 84.B gives the =ro.ect *anager power to re#uire the (ontractor either to tae steps as may be practicable in order to achieve the Approved programme or to revise the Approved =rogramme. In addition, under (lause 84.C i! the =ro.ect *anager decidesthat the rate o! progress by the (ontractor will pre.udice his ability to complete in accordance with (luse 84.8, and this is due to a cause !or which the (ontractor is responsible, the =ro.ect *anager has power to give notice to that e'ect. The (ontractor must then use his best endeavours to remedy the potential delay at his own cost. ;uch action does not a'ect the (ontractors liability to pay damages !or delayed completion ((lause 84.G).(lause B8.7 gives the =ro.ect *anager power to issue a notice that the (ontractor is in de!ault by !ailing to proceed regularly and diligently with the Wors. I! the (ontractor !ails to commence and diligently pursue the recti"cation o! such de!ault within 8B days a!ter receipt o! the notice or at any time therea!ter repeats the de!ault, the =urchaser may !orthwith determine the employment o! the (ontractor under the (ontract.:AB1 .!ev >2 2000(lause 7.8 re#uires the &ngineer to carry out the duties speci"ed in the (ontract. I! he is re#uired to obtain prior speci"c approval o! the =urchaser be!ore e$ercising his duties, by reason o! the terms o! his appointment, then these are re#uired to be set out in the ;pecial (onditions. (lause 84.8 re#uires the (ontractor to e$ecute the Wors and carry out the Tests on (ompletion within the Time !or (ompletion. (lause 8B.8 re#uires the (ontractor to submit a programme !or approval.Lnder (lause 8B.C the &ngineer has the power to order the (ontractor to revise the =rogramme i! he decides that progress does not match the =rogramme. The (ontractor is thenre#uired to revise the =rogramme to show the modi"cations necessary to ensure completion o! the Wors within the Time !or (ompletion. I! the modi"cations are re#uired !or reasons !or which the (ontractor is not responsible, the (ost o! producing the revised =rogramme is addedto the (ontract =rice.Lnder (lause 8B.3 the &ngineer has power to noti!y the (ontractor i! the &ngineer decides that the rate o! progress o! the Wors is too slow to meet the Time !or (ompletion and that this is not due to a circumstance !or which the (ontractor is entitled to an e$tension o! time. The (ontractor is then re#uired to tae such steps as may be necessary and as the &ngineer might approve to remedy or mitigate the liely delay, including revision o! the =rogramme. The (ontractor is not entitled to additional payment !or taing such steps.(lause BA.8 allows the =urchaser to give the (ontractor 78 days notice o! his intention to terminate the (ontract enter the site and e$pel the (ontractor, i! despite previous warnings in writing !rom the &ngineer the (ontractor is !ailing to proceed with the Wors with due diligence.5+- 1//0The 2(T 8AA> @orms do not provide clear e$press provisions !or the Architect to re#uire the (ontractor to accelerate in order to achieve the (ompletion Date. The (ontractor is re#uired under (lause B.8.8 to comply !orthwith will all instructions issued by the Architect, but only in respect o! matters which the Architect is e$pressly empowered by the (onditions to issue instructions.Lnder (lause 74.8.8 the (ontractor is re#uired to regularly and diligently proceed with the Wors and complete on or be!ore the (ompletion Date. (lause 7C provides !or the (ontractor to be granted e$tension o! time !or )elevant &vents, but importantly (lause 7C.4.B.8 re#uires the (ontractor to use constantly his best endeavours to prevent delay in the progress o! the Wors, however caused, and to prevent the completion o! the Wors being delayed or !urther delayed beyond the (ompletion Date. @urther, (lause 7C.4.B.7 re#uires the (ontractor to do all that may be reasonably re#uired to the satis!action o! the Architect to proceed with the Wors.(lause 7G.7.8.7 allows the Architect to give notice o! de!ault i! be!ore the date o! =ractical (ompletion the (ontractor !ails to proceed regularly and diligently with the Wors. I! the (ontractor continues the de!ault !or 8B days !rom receipt o! the notice, the &mployer may within 8? days a!ter the e$piry o! 8B days give notice determining the employment o! the (ontractor. I! the &mployers notice is not issued, then i! the (ontractor repeats the de!ault then upon or within a reasonable time a!ter such repetition, the &mployer may give notice determining the (ontractors employment, taing e'ect on the date o! receipt o! the notice.5+- 1//0 Wit' +ontractorCs Desi%n2(T 8AA> With (ontractors Design is in similar terms to 2(T 8AA> and similar considerations apply, e$cept that the &mployer administers the contract instead o! the Architect under 2(T 8AA>.5+- 1//0 6rime +ost +ontractThe 2(T 8AA> =rime (ost (ontract is similar in structure to the 2(T 8AA> @orm and similar considerations apply. There is no clear e$press provision !or the Architect to re#uire the (ontractor to accelerate in order to achieve the (ompletion Date. The (ontractor is re#uired under (lause 4.4.7 to comply !orthwith will all instructions issued by the Architect, but sub.ect to reasonable ob.ection under (lause 4.4.4 and sub.ect to re#uest !or authority under (lause 4.4.C.Lnder (lause 7.8.8 the (ontractor is re#uired to regularly and diligently proceed with the Wors and complete on or be!ore the (ompletion Date. (lause 7.C provides !or the (ontractor to be granted e$tension o! time !or )elevant &vents, but importantly (lause 7.C.B re#uires the (ontractor to use constantly his best endeavours to prevent delay in the progress o! the Wors, however caused. @urther, (lause 7.C.B re#uires the (ontractor to do all that may be reasonably re#uired to the satis!action o! the Architect to proceed with the Wors.(lause G.7.8 allows the Architect to give notice o! de!ault i! be!ore the date o! =ractical (ompletion the (ontractor !ails to proceed regularly and diligently with the Wors. I! the (ontractor continues the de!ault !or 8B days !rom receipt o! the notice, the &mployer may within 8? days a!ter the e$piry o! 8B days give notice determining the employment o! the (ontractor. I! the &mployers notice is not issued, then i! the (ontractor repeats the de!ault then upon or within a reasonable time a!ter such repetition, the &mployer may give notice determining the (ontractors employment, taing e'ect on the date o! receipt o! the notice.;A+ 1//0The I@( 8AA> is similar in structure to the 2(T 8AA> @orm and similar considerations apply. There is no clear e$press provision !or the Architect to re#uire the (ontractor to accelerate in order to achieve the (ompletion Date. Lnder (lause 7.8. the (ontractor is re#uired to regularly and diligently proceed with the Wors and complete on or be!ore the (ompletion Date. (lause 7.4 provides !or the (ontractor to be granted e$tension o! time !or speci"ed events, but importantly the (ontractor is re#uired to use constantly his best endeavours to prevent delay and to do all that may be reasonably re#uired to the satis!action o! the Architectto proceed with the Wors.(lause G.7.8 allows the Architect to give notice o! de!ault i! be!ore the date o! =ractical (ompletion the (ontractor !ails to proceed regularly and diligently with the Wors. I! the (ontractor continues the de!ault !or 8B days !rom receipt o! the notice, the &mployer may within 8? days a!ter the e$piry o! 8B days give notice determining the employment o! the (ontractor. I! the &mployers notice is not issued, then i! the (ontractor repeats the de!ault then upon or within a reasonable time a!ter such repetition, the &mployer may give notice determining the (ontractors employment, taing e'ect on the date o! receipt o! the notice.5+- 1//0 :inor WorksThe (ontractor is re#uired to !orthwith carry out the instructions o! the Architect under (lause 4.C. There is no clear e$press provision !or the Architect to re#uire the (ontractor to accelerate in order to achieve the (ompletion Date. (lause 8.8 re#uires the (ontractor to carry out and complete the Wors with due diligence. (lause G.7.8 allows the Architect to give notice o! de!ault i! the (ontractor !ails to proceed diligently with the Wors. I! the (ontractor continues the de!ault !or G days !rom receipt o! the notice, the &mployer may give !urther notice determining the employment o! the (ontractor. +E+A 4lue Aorm 1//0(lause G(7) gives the (ontractor under the ;ubcontract the same powers as the &ngineer under the main contract, which under the I(& Gth edition will include the powers under (lause B3 !or acceleration. (lause G(8) re#uires the ;ubcontractor to comply with all instructions and decisions o! the &ngineer which are noti"ed and con"rmed in writing by the (ontractor.(lause 3(8) re#uires the ;ubcontractor to proceed with the ;ubcontract Wors with due diligence and without delay e$cept as e$pressly sanctioned or ordered by the (ontractor or as may be wholly beyond the control o! the ;ubcontractor. The ;ubcontractor is re#uired to complete within the =eriod !or (ompletion speci"ed in the Third ;chedule.(lause 8G(8)(b) allows the (ontractor by written notice to determine the ;ubcontractors employment i! the ;ubcontractor !ails to proceed with due diligence a!ter being re#uired in writing to do so by the (ontractor.D:B1(lause 88.8 re#uires the subcontractor to complete the ;ubcontract Wors and reasonable in accordance with the progress o! the Wors. The ;ubcontractors entitlement to e$tension o! time is sub.ect to the proviso in (lause 88.> which re#uires the ;ubcontractor to use his best endeavours to prevent delay in the progress o! the ;ubcontract Wors however caused and to prevent any such delay resulting in the completion o! the ;ubcontract Wors being delayed beyond the period !or completion. The ;ubcontractor is re#uired to do all that may be reasonably re#uired to the satis!action o! the Architect and the (ontractor to proceed with the ;ubcontract Wors.(lause 7A.7.8.7 allows the (ontractor to give notice o! de!ault i! be!ore the date o! =ractical (ompletion the ;ubcontractor !ails to proceed regularly and diligently with the ;ubcontract Wors. I! the (ontractor continues the de!ault !or 8? days !rom receipt o! the notice, the (ontractor may within 8? days a!ter the e$piry o! 8? days give notice determining the employment o! the ;ubcontractor. I! the (ontractors notice is not issued, then i! the ;ubcontractor repeats the de!ault then upon or within a reasonable time a!ter such repetition, the (ontractor may give notice determining the (ontractors employment, taing e'ect on the date o! receipt o! the notice.