Accelerated Bridge

Construction in

Connecticut

Page 2: Accelerated Bridge Construction in Connecticut

State Project No. 131-194/195

Rehabilitation of Bridge Nos. 01235 and 01236

I-84 over Marion Ave

Southington, Connecticut

Page 3: Accelerated Bridge Construction in Connecticut

CTDOT TEAM

Design

Ajit Gokhale, P.E., Close, Jensen & Miller, P.C

Andrew Lessard, P.E., Stantec Consulting Services, Inc.

Louis Bacho, P.E., CTDOT

Mary Baker, P.E., CTDOT

Construction, CTDOT Mohammed Bishtawi, P.E.

Joe Calafiore

Shawn Mangan

Terri Thompson

Page 4: Accelerated Bridge Construction in Connecticut
Page 5: Accelerated Bridge Construction in Connecticut

Bridge 01235 EB

Bridge 01236 WB

Page 6: Accelerated Bridge Construction in Connecticut

Bridge 01235 (EB) East Elevation

Page 7: Accelerated Bridge Construction in Connecticut

Bridge 01236 (WB) West Elevation

Page 8: Accelerated Bridge Construction in Connecticut

Bridge 01235 cracking

Page 9: Accelerated Bridge Construction in Connecticut

Bridge 01236 G7 spall beam end

Page 10: Accelerated Bridge Construction in Connecticut

Design Options superstructure replacements

• 3 stages maintaining 2 lanes

$6.5 M, 18 months

• Widening maintaining 3 lanes

$8.0 M, 24 months

• Temporary bridge and crossover, 3 lanes

$7.3 M, 24 months

• Closure using SPMTs

$7.0 M, 230 days

Page 11: Accelerated Bridge Construction in Connecticut

Selected methodology

• Replace two deficient superstructures

• Utilize SPMTs

• 56 hour maximum closure of I-84

• Implement ABC to minimize impact to

residents and businesses

• Safe work zone

“Get In, Get Out, and Stay Out”

Page 12: Accelerated Bridge Construction in Connecticut

Existing and Proposed Bridge Sections

Page 13: Accelerated Bridge Construction in Connecticut

WB

EB

Page 14: Accelerated Bridge Construction in Connecticut

Aspire Magazine Summer 2015

Page 15: Accelerated Bridge Construction in Connecticut

Informational meetings

• Public info in Design, October 2011

• Pre-bid conference, March 2013

• Town staff meeting, January 2014

• Reporter at jobsite, March 2014

• Traffic Coordination, SPD, April 2014

• Town Council Meeting, May 2014

• Public info in Construction, May 2014

• Project site visits , May-June 2014

• Merchant meeting, June 2014

• DOT Manager meeting, June 2014

Page 16: Accelerated Bridge Construction in Connecticut

Public Outreach

• Neighboring states: NY, MA, RI

• Emergency Management Coordinators -

DESPP

• Federal Law Enforcement Agencies

• Chambers of Commerce - local businesses

• Trucking companies, hospitals, major

venues

• Local residents and EMS

Page 17: Accelerated Bridge Construction in Connecticut

Detour west of project

Page 18: Accelerated Bridge Construction in Connecticut

I-84 Detour Plan

Page 19: Accelerated Bridge Construction in Connecticut

Regional And Local Variable Message Board Activation

Page 20: Accelerated Bridge Construction in Connecticut

Newspaper Coverage

Page 21: Accelerated Bridge Construction in Connecticut

Commissioner James P. Redeker

Page 22: Accelerated Bridge Construction in Connecticut
Page 23: Accelerated Bridge Construction in Connecticut

CONTRACTOR

Northern Construction Service, LLC

Weymouth, MA

Project awarded on June 7, 2013

Contract Amount: $6,031,429.40

Est. Revised Contract Amount: $7,400,000

Sean Hoey, Project Superintendent

Shawn Clark, Project Manager

Page 24: Accelerated Bridge Construction in Connecticut

Contractual Items

• Liquidated Damages

– Exceeding Calendar Days

– Lane Closures (other than weekend closure)

– Weekend Closure

• Incentives

Page 25: Accelerated Bridge Construction in Connecticut

Contractual Items

Liquidated Damages – Weekend Closure

• $100,000 per hour for each direction of I-84,

for each hour, or any portion thereof

• The aggregate amount of LDs assessed during

the shutdown period shall not exceed

$1,000,000

Page 26: Accelerated Bridge Construction in Connecticut

Contractual Items

Incentives

Page 27: Accelerated Bridge Construction in Connecticut

Construction Staging

• Stage 1 – Median Wingwall Parapets

• Stage 2 – Outside Wingwall Parapets

• Stage 3 – Rapid Replacement of Superstructures

• Maintain 3 lanes of traffic in I-84 during Stages 1 & 2

• Construct New Superstructures off-line during Stages 1 & 2

Page 28: Accelerated Bridge Construction in Connecticut

Stage 1

Page 29: Accelerated Bridge Construction in Connecticut

Stage 2

Page 30: Accelerated Bridge Construction in Connecticut
Page 31: Accelerated Bridge Construction in Connecticut
Page 32: Accelerated Bridge Construction in Connecticut
Page 33: Accelerated Bridge Construction in Connecticut

WB

EB

WB

EB

•BSA2

•BSA1

Page 34: Accelerated Bridge Construction in Connecticut

WB

EB

EB

Page 35: Accelerated Bridge Construction in Connecticut

Closure Schedule Friday, 6/27/14

9 am – Southington Rest Area, I-84 East Closed

5 pm to 9 pm - I-84 Exit 30 Off and On Ramps Closed

Marion Avenue closed at ramps- no through traffic

6 pm - One lane taken on I-84 East at Exit 27 (I-691)

7 pm - One lane taken at Exit 31 (Rt 229)

8 pm - Two lanes taken at EB Exit 27 and WB Exit 31 with one travel lane open

9 pm - I-84 Closed, one lane of traffic off at Exit 30 and Exit 29 On and Off Ramps at Route 10 Closed

Monday, 6/30/14 5 am

I-84 OPEN ALL LANES IN BOTH DIRECTIONS and I-84 East Southington Rest Area reopens

Page 36: Accelerated Bridge Construction in Connecticut
Page 37: Accelerated Bridge Construction in Connecticut
Page 38: Accelerated Bridge Construction in Connecticut

Demo Plan W.B

Page 39: Accelerated Bridge Construction in Connecticut
Page 40: Accelerated Bridge Construction in Connecticut

Demo procedure W.B

Page 41: Accelerated Bridge Construction in Connecticut
Page 42: Accelerated Bridge Construction in Connecticut
Page 43: Accelerated Bridge Construction in Connecticut
Page 44: Accelerated Bridge Construction in Connecticut
Page 45: Accelerated Bridge Construction in Connecticut
Page 46: Accelerated Bridge Construction in Connecticut
Page 47: Accelerated Bridge Construction in Connecticut
Page 48: Accelerated Bridge Construction in Connecticut
Page 49: Accelerated Bridge Construction in Connecticut

Making It On Time

• Traffic Management Unified Command Center

• DOT CHAMP (CT Highway Assistant Motorist Patrol) vehicles

• Incident Management response

• Traffic Management Plan

• Contractor Contingency plan

Page 50: Accelerated Bridge Construction in Connecticut

Detour Notification Strategies

• Use Intelligent Transportation System (ITS)

technology

• Cameras, Message Boards, Advisory Radio

• Massachusetts, Rhode Island, New York,

and New Jersey travel alert systems

• Officers located at project site and along

detour routes

• Local Fire and Police paid through the DOT

project

• Project Website

Page 51: Accelerated Bridge Construction in Connecticut

CTDOT Website

www.ct.gov/dot ---> I-84 Southington ABC Project

Page 52: Accelerated Bridge Construction in Connecticut
Page 53: Accelerated Bridge Construction in Connecticut

Lessons Learned

• Lighter weight superstructure

• Max grade for SPMTs

• Adequate travel path width

• Incentive/disincentives

• Advance utility/IMS relocation

• Local review of traffic plan

• Consider use of alternate bids and alternate contracting method to allow innovation and minimize risk for stakeholders.

Page 54: Accelerated Bridge Construction in Connecticut

Lessons Learned

• Time for Working Drawing Review

• More detailed TMP

• Staging area – contract items

• Bearing plate shims

• Contractor Survey

• DOT Construction project conflicts

• Site Accessibility

Page 55: Accelerated Bridge Construction in Connecticut

Bridge Opening EB: Sunday 4:40 p.m.

WB: Sunday 8:15 p.m.

CTDOT Successful Completion

Page 56: Accelerated Bridge Construction in Connecticut

CTDOT ABC Look ahead

• PBUs – Route 4, Harwinton

• GRS-IBS abutments – I-84 off-ramp, Manchester

• Slide – I-95, Waterford

• SPMTs -Route 1 over I-95, Stamford

• SPMTs – Metro North RR over Atlantic St., Stamford

Page 57: Accelerated Bridge Construction in Connecticut

ABC Decision Matrix - Implementation

Page 58: Accelerated Bridge Construction in Connecticut

Contact Information

Mr. Timothy D. Fields, P.E.

Principal Engineer

(860) 594-3217 or [email protected]

Ms. Mary E. Baker, P.E.

Supervising Engineer

(860) 594-3402 or [email protected]

Mr. Mohammed Bishtawi, P.E.

Supervising Engineer

(860) 258-4617 or [email protected]