abstract - brown and caldwell | home · pdf fileconference: design-build for water/wastewater...

Download Abstract - Brown and Caldwell | Home · PDF fileConference: Design-Build for Water/Wastewater Conference 2017 Paper/Presentation Title: Standard Form of Contract for Progressive Design-Build

If you can't read please download the document

Upload: hoangdien

Post on 06-Feb-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

  • Conference: Design-Build for Water/Wastewater Conference 2017 Paper/Presentation Title: Standard Form of Contract for Progressive Design-Build Authors: Stephen Gates, Brown and Caldwell/Water Design-Build Council, Board; Jason Sheck, Brown and Caldwell; Holly A. Streeter-Schaefer, Burns & McDonnell Engineering Co.; Mark Alpert, Integrated Delivery Solutions, Inc. Contact: Stephen Gates - [email protected]

    Abstract Standard Form of Contract for Progressive Design-Build As Progressive Design-Build (PDB) gains momentum; there is a greater need for standardized contract forms

    to help guide the design and construction industry through the procurement process. DBIA and the Water

    Design-Build Council (WDBC), through a collaborative partnership, have developed that much-needed form.

    This session provided an overview of the new standard form and highlighted key areas.

  • DBIA Progressive Design-Build ContractMark E Alpert, Water Design-Build Council, Executive Director

    Jason Scheck, Contracts Manager, Brown and Caldwell

    Holly Streeter-Schaefer, Attorney, Burns & McDonnell

    March 29 - 31, 2017

  • 1. Several year effort in conjunction with DBIA and WDBC Strategic Alliance

    2. Developed in cooperation with the Water Design-Build Council (WDBC)

    3. Addresses two phased design-build services

    4. Adopted by DBIA and WDBC Boards in November 2016

    5. Presented at DBIA National Convention

    DBIA Progressive Design-Build Agreement Form

  • Public and Private Sector Owners

    Template with many choices for customization to meet Owners requirements

    Drafted with intent to be used on Water and Wastewater projects, but applicable to all market sectors

    Use of the Agreement

  • Procurement flow of activities and relationship of the Owner and PDB firm/team

    DBIA Progressive Design-Build Primer

    WDBC Model Procurement Documents

    Progressive Design Build Resources

  • Progressive Design-Build (PDB)

  • PDB Procurement Considerations

    6

    1. Open book cost based on collaboratively developed scope and design2. Price agreement prior to construction3. May require separate approval, contract amendment, or second contract4. Owner has the off-ramp option

    1. One- or Two-Step Procurement (two-step shown)

    2. First Step is based on qualifications

    3. Short list of up to three qualified firms

    4. Second Step focuses on approach and fee

    1. Evaluation based on quals approach, and fee %2. Interviews of short-list are typical

  • http://www.dbia.org/resource-center/Pages/Contracts.aspx

  • Modifications to instructions to account for phased services

    Lump sum compensation added

    Phase 1 Preconstruction Services including Design, Constructability reviews and planning, and progressive estimates leading to price proposal for Phase 2 costs

    Phase 2 Cost of the Work and final design (GMP, Lump Sum, Cost Plus)

    Specific Provisions

  • Proposal submitted at end of Phase 1 for Phase 2 services

    If Phase 2 proceeds, Contract Price Amendment executed by parties

    Proposal should be part of Contract Price Amendment

    Agreement allows for parties to decide when design is sufficient for Phase 2 costs determination

    Specific Provisions

  • Phase 1 Services

    PHASE 1

  • PHASE 2

    Phase 2 Services

    The Off Ramp

    PHASE 1

  • If accepted, parties execute Contract Price Amendment

    Failure to accept proposal

    Modify proposal

    Owner authorizes DB to proceed on a reimbursable basis

    Terminate for convenience

    The Off Ramp

    Proposal Acceptance

  • What If No Option Is Exercised?

  • DB can continue as if Owner elected to proceed and paid accordingly

    DB can suspend performance

    DB may give written notice to Owner that it considers the Agreement completed

    If Owner fails to exercise option within ten days of DBs notice, Agreement deemed completed and

    DB has no further liability or obligations

    If No Option Is Exercised . . .

  • Phase 1 - Compensation

    Compensation

    $

  • Phase 2 Compensation

    Lump Sum

    GMP

    Fee plus Cost of the Work

    Compensation

  • Contingency terms:

    1. Contemplates contingency for GMP

    2. Exclusive use of Design-Builder

    3. Allows for Owner to have separate contingency

    As part of GMP or outside of the GMP

    Owners use of savings before project completion

    Contingency

  • Savings sharing is contemplated

    Costs for defective /non-conforming work as a Cost of the Work

    Savings and Costs for Defective Work

    SAVINGS

  • Options for liquidated damages for substantial and final completion

    Cap on liquidated damages

    Early completion bonus

    Liquidated damages

    1. in lieu of any and all costs

    2. for delay

    Liquidated Damages

  • Article 13 added

    New Provision in DBIA Document

    Limitation of Liability

    Limitation

    LiabilityLiability

    Liability

  • Thank you.

    Questions?