CONSTRUCTION PROGRESS
AS ON 31st OCT’19
STATUS
• Structure completed• Internal Painting – All floor Internal
Painting work completed.• Floor marble laying work under
progress.• Toilet Tiling work under Progress.• All floor Water Proofing work completed• All floor Plumbing work completed.• All floor Fire Fighting work completed.• Bedroom & Kitchen Tiling work under
Progress.• Electrical work under progress.
A – BLOCK
STATUS
• Structure completed• Internal Painting – All floor internal
painting work completed.• Floor marble laying work under progress.• Bedroom & Kitchen Tiling work under
Progress.• Upto 10th floor Toilet Tiling work
completed.• All floor Fire Fighting work completed.• All floor Water Proofing work completed.• All floor Plumbing work completed.• Window fixing work under Progress.• CP & Sanitary Fittings under progress.• Upto 14th floor Electrical work completed.
B – BLOCK
HALL
DINING & BEDROOM
TOILET
TRANSFORMER LINE-A B C D
STATUS
• Structure completed• Internal Painting – Painting work completed• Floor marble laying work completed • Bedroom & Kitchen Tiling work completed• Toilet Tiling work completed• Fire Fighting work completed• Water Proofing work completed• Plumbing work completed• Window fixing work completed• Door frame fixing work completed• Electrical work completed• CP & Sanitary fittings completed.
C – BLOCK
STATUS
• Structure completed• Internal painting – Painting work completed• Floor marble laying work completed• Bedroom & Kitchen Tiling work completed• Toilet Tiling work completed• Fire fighting work completed• Water proofing work completed• Plumbing work completed• Window fixing work completed• Door frame fixing work completed.• Electrical work completed• CP & Sanitary fittings work completed.
D – BLOCK
N – BLOCK
STATUS
• Structure completed• Internal painting – All floor Internal
Painting work completed.• Floor marble laying work under Progress.• Upto 10th floor Toilet Tiling work
completed.• Fire fighting work completed.• Water proofing work completed.• Upto 18th floor Plumbing work
completed.• Window fixing work Nearing completion.• Electrical work under progress.
HALL & BEDROOM
DINING & POOJA AREA
TOILET
O – BLOCK
STATUS
• Structure Completed• Internal painting – All floor painting
completed.• Floor marble laying work under
progress.• Upto 9th floor Toilet Tiling work
completed.• Fire fighting work Completed.• Water proofing work completed.• Plumbing work completed.• Window fixing work nearing
completion.• Upto 15th Electrical work completed.
HALL
KITCHEN & BEDROOM
DINING & POOJA AREA
DB PANEL
TOILET
JEWEL (Q) - BLOCK
STATUS
• Upto 16th floor slab work Completed.• Terrace Activity under progress.
JEWEL (Q) – BLOCK – MODEL UNIT WORK IN PROGRESS
INFINITY (CLUB HOUSE) – EXTERNAL VIEW
INFINITY (CLUB HOUSE) – ENTRANCE VIEW
INFINITY (CLUB HOUSE) – INTERNAL VIEW
INFINITY (CLUB HOUSE) – BANQUET HALL-1
INFINITY (CLUB HOUSE) – BANQUET HALL - 2
INFINITY (CLUB HOUSE) – BANQUET HALL - 3
INFINITY (CLUB HOUSE)-MINI THEATRE
INFINITY (CLUBHOUSE) – GYM - MEN
INFINITY (CLUBHOUSE) – GYM - WOMEN
INFINITY (CLUBHOUSE) – GYM - WOMEN
INFINITY (CLUB HOUSE) - KIDS PLAY AREA
INFINITY (CLUB HOUSE) – TOP VIEW