    ABC I-Net

    Sample Project Management Plan

    Upgrading the ABC Intranet and

    ABC Internet Infrastructures

    Note: This is a real document provided by a

    real project team. Names have been changed

    to sanitize the document.

    Last Updated: 10/09/2001

    Prepared By: ABC I-Net Project Team

    Version 1.9

  • 8/2/2019 ABC Inet Pm Plan

    2/44

    Sample Project Management Plan DRAFT

    Page: 2

    Table of Contents

    TABLE OF CONTENTS...................................................................................................................2

    I. EXECUTIVE SUMMARY (DEFINITION) .........................................................................4

    II. BENEFITS (BUSINESS REQUEST).................................................................................................5

    III. SCOPE (BUSINESS CASE)..................................................................................................................6

    A. In Scope .................................................................................................................................................6

    B. Out of Scope..........................................................................................................................................8

    C. Project Dependencies ...........................................................................................................................9

    D. Project Goal and Objectives................................................................................................................9

    E. Project Deliverables..............................................................................................................................9

    F. Acceptance Criteria............................................................................................................................11

    E. Assumptions........................................................................................................................................11

    F. Constraints..........................................................................................................................................12

    IV. CRITICAL SUCCESS FACTORS..........................................................................13

    V. COST ESTIMATES(FINANCIAL BUSINESS CASE)...............................................14

    A. Total Budgeted Costs for Hardware and Software:........................................................................14

    B. Phase-I Intranet Budgeted Costs for Hardware and Software: .....................................................15

    C. Phase-II Internet Budgeted Costs for Hardware and Software:....................................................15

    VI. APPROACH STRATEGY .............................................................................................16

    D. Technique/X Project Management ...................................................................................................17

    X. WORK BREAKDOWN STRUCTURE............................................................18

    IX. PROJECT PLAN..........................................................................................................................19

    X. PROJECT TEAM................................................................................................................... 20

    A. Organizational Breakdown Structure ..............................................................................................20

    B. Project Roles and Responsibilities ....................................................................................................21

    C. Project Roster .....................................................................................................................................25

    XI. RISK MANAGEMENT.....................................................................................................27

  • 8/2/2019 ABC Inet Pm Plan

    3/44

    Sample Project Management Plan DRAFT

    Page: 3

    XII. GOVERNANCE PLAN................................................................................................28

    XIII.

    PROJECT CONTROL STRATEGIES.........................................................29

    A. Quality Assurance ..............................................................................................................................29

    B. Change Control...................................................................................................................................29

    C. Communications.................................................................................................................................29

    D. Information Management..................................................................................................................30

    XIV. APPENDIX A - INITIAL PROJECT RISK ASSESSMENT...........................32

    XV. APPENDIX B COMMUNICATIONS MATRIX ...............................................42

    XVI. APPROVAL SIGNATURES....................................................................................44

  • 8/2/2019 ABC Inet Pm Plan

    4/44

    Sample Project Management Plan DRAFT

    Page: 4

    I. Executive Summary (DEFINITION)

    The ABC Intranet and the ABC Internet have gone through many changes over the

    course of the past year. The primary reason for making such changes is to align with I-

    Nets mission statement that states that we will provide our customers with reliable,

    integrated, secure and flexible I-Net solutions to meet their expanding business needs.

    As a next step in keeping with this mission statement, the I-Net group determined that

    there is a need to enhance the existing ABC Intranet and ABC Internet infrastructure,

    policies and procedures, and security to meet current and future business needs.

    More specifically, the ABC Intranet and ABC Intranet will be expanded and modified to

    provide like environments through common software configurations, like processes

    through standard policies and documentation (where appropriate), common security

    measures, and greater capacity with added hardware.

    The overall project approach will be to follow industry standard project management

    practices that will break the project down into two phases:

    Phase-I ABC Intranet

    Phase-II ABC Internet

    It should be noted that there is the potential for additional add-on phases to address theitems that have been categorized under Future Considerations (beyond phase-II). The

    Future Consideration items will be reviewed and categorized accordingly as part of the

    Sample Charter project. Any items that are deemed part of the Phase-I and/or Phase-II

    will be incorporated through the Sample Charter project Change Control processes.

  • 8/2/2019 ABC Inet Pm Plan

    5/44

    Sample Project Management Plan DRAFT

    Page: 5

    II. Benefits (BUSINESS REQUEST)

    Upon completion of the Sample Charter Project, ABC will realize the following benefits:

    An Intranet and Internet infrastructure that leverages standards for technical

    configuration, technical management, and procedures to provide optimum

    proficiency.

    Provide an infrastructure that allows ABC business units to properly house their

    Intranet and Internet applications.

    Alleviate current production capacity issues.

    Increased capacity (up to 100%) to accommodate ABC business units future

    business growth needs.

    A standardized infrastructure and procedures will allow for easier and more efficient

    Intranet and Internet support.

    Updated process definitions as a result of the new architecture will provide better

    ease of use for users.

  • 8/2/2019 ABC Inet Pm Plan

    6/44

    Sample Project Management Plan DRAFT

    Page: 6

    III. Scope (BUSINESS CASE)

    A.In Scope

    1. PHASE-I ABC Intranet

    a) Enable the I-Net tool set (Actuate, Harvest, iPlanet, SiteMinder, andWebsphere) to function on the new ABC Intranet.

    b) Architect, design and build the new ABC Intranet in such a way that theinfrastructure supports the following environments: DEV, INT, IMPL,

    TRAIN, and PROD.

    c) Migrate the following applications from the existing ABC Intranet and/orABC Internet to the new ABC Intranet:

    i. Conswakoii. Technique/Xiii.State Farmersiv. U.S. News and Daily Reportv. Migrate the Visual Age Generator (VAGEN) application from

    the existing ABC Intranet environment to the new ABC

    Intranet environment.

    d) Architect the new ABC Intranet in such a way that the ABC Internetdatabases (DB2, data warehouse, NEON, ORACLE, etc.) can be accessed

    from the new ABC Intranet

    e) Provide flexibility in the new ABC Intranet Production Control process toaccommodate different levels (static content and application code) of code

    migration.

    f) Enable domain-naming capabilities so that each Intranet application mayutilize a specific domain name (ex. usnews.ABC.com).

    g) Secure the HOST system log files for the new servers and the redeployedexisting servers.

    h) Implement a standard HOST configuration (see appendix A) for the newservers and the redeployed existing servers.

    i) Implement a standard APPLICATION configuration (see Appendix A) forthe new servers and the redeployed existing servers.

  • 8/2/2019 ABC Inet Pm Plan

    7/44

    Sample Project Management Plan DRAFT

    Page: 7

    j) Implement time-sync software for the new and redeployed I-Net servers.

    k) Re-rack the new servers and redeployed existing servers.

    l) Update appropriate ABC Intranet processes and procedures impacted byIntranet changes and necessary to support the new ABC Intranet

    infrastructure (ex. shared components).

    m) All exiting software applications and software tools will remain as is forthe existing ABC Intranet (servers u1ecm04 and u1ecm05) unless

    otherwise noted in the Project Charter.

    n) Required documentation to meet Technique/X minimum deliverablerequirements is completed.

    2. PHASE-II ABC Internet

    a) Scale the production Websphere Infrastructure to provide approximatelydouble the storage and processing capacity.

    b) Provide additional fault tolerance and redundancy to decrease businessinterruptions due to unplanned downtime.

    c) Provide migration processes (i.e. anytime migration not just scheduledSundays) for the new ABC Intranet and ABC Internet that will result in

    minimal downtime.

    d) Provide increased flexibility in the DEV, INT, IMPL, and TRAINenvironments to allow for a load testing environment and separate DEV

    environments for each business.

    e) Create a TECH environment to allow the I-Net Department to conduct anddirect research and analysis of Internet applications, fixes, tools, and

    upgrades.

    o) Secure the HOST system log files for the new servers and the redeployedexisting servers.

    p) Implement a standard HOST configuration (see appendix A) for the newservers and the redeployed existing servers.

    q) Implement a standard APPLICATION configuration (see Appendix A) forthe new servers and the redeployed existing servers.

    r) Implement time-sync software for the new and redeployed I-Net servers.

  • 8/2/2019 ABC Inet Pm Plan

    8/44

    Sample Project Management Plan DRAFT

    Page: 8

    s) Required documentation to meet Technique/X minimum deliverablerequirements is completed.

    3. Future Considerations (beyond Phase-II)

    a) Consolidate webservers where appropriate to maximize the new ABCIntranet and ABC Internet efficiencies while maintaining the high-level

    company domains.

    b) Research, analyze, and reconfigure the deployment of the u1ecm04 andu1ecm05 servers (existing ABC Intranet).

    c) Secure APPLICATION log files (Apache, Websphere, and iPlanet) andHOST log files for the remaining I-Net servers.

    d) Implement the Solaris v.2.8 operating system on the remaining I-Netservers.

    e) Implement a base server configuration on the remaining I-Net servers.

    f) Re-rack the remaining I-Net servers.

    g) Use of mainframe platform within the ABC Intranet and ABC Internetinfrastructure.

    B.Out of Scope

    1) The research and evaluation of alternative tools as possible replacements forFront Page, Harvest and Host Publisher.

    2) The infrastructure changes required eliminating single points of failure.

    3) The upgrade and fail-over of the Media Surface content management tool.4) The LDAP Directory Strategy Design and Implementation.

    5) Eliminate identified security weaknesses in the existing ABC Intranet and ABCInternet infrastructure.

  • 8/2/2019 ABC Inet Pm Plan

    9/44

    Sample Project Management Plan DRAFT

    Page: 9

    C.Project Dependencies

    1) The Sample Charter Project is dependent on the SiteMinder Upgrade project tomaintain compatibility and to complete final testing.

    2) The Sample Charter Project is dependent on the Harvest 5.0 Upgrade project forany Production Control Processes changes.

    D.Project Goal and Objectives

    1) Implement fault tolerance and redundancy (no downtime for most productionmoves)

    2) Implement full functions on the Intranet (security, application, multipledevelopment regions)

    3) Implement doubling of I-Net capacity

    4) Implement separate DEV environments for each company

    5) Implement scalable infrastructure for future growth

    6) Implement I-Net TECH environment for R&D

    7) Establish common technical and process standards

    E.Project Deliverables

    The following Project Delivery Table provides a project timeline with estimated project

    delivery dates for key project milestones.

    Project

    Deliverable 9/15 9/30 10/15 10/31 11/15 11/30 12/15 12/31 1/15 1/31 2/15 2/28 3/15 3/31 4/15 4/30

    1.1 PROJECT

    MANAGEMENT

    Project Charter Sign-

    off

    10/19

    Project RAF Sign-off 10/19

    Project Plan 10/12

  • 8/2/2019 ABC Inet Pm Plan

    10/44

    Sample Project Management Plan DRAFT

    Page: 10

    Project

    Deliverable 9/15 9/30 10/15 10/31 11/15 11/30 12/15 12/31 1/15 1/31 2/15 2/28 3/15 3/31 4/15 4/30

    Baselined

    Technical Kick-offMeeting

    9/18

    Business Kick-off

    Meeting

    9/27

    1.2 ANALYSIS

    Hardware/Software

    Negotiations

    Complete

    8/24

    Receive Hardware 9/10

    Project Phases

    Defined

    8/31

    Business

    Requirements Sign-

    off

    11/1

    TechnicalRequirements Sign-

    off

    8/31

    Procedure Updates

    Sign-off

    11/8

    1.3 DESIGN

    Hardware Design

    Sign-off

    10/2

    Software Design

    Sign-off

    10/2

    1.4 BUILD

    Facilities Prep

    Completed

    9/25

    Server Installation

    Prep Completed

    10/9

    TECH Test

    Environment Prep

    Completed

    11/19

    Phase-I Intranet

    Hardware Install

    Completed

    11/5

    Phase-I Intranet

    Software

    Configuration

    Completed

    1/4

    Phase-II Internet

    Hardware Install

    Completed

    12/5

    Phase-II InternetSoftware

    Configuration

    Completed

    2/5

    1.5

    INTEGRATION/

    TEST

    Business Test Plans

    Created

    11/15

    Technical Test Plans 10/26

  • 8/2/2019 ABC Inet Pm Plan

    11/44

    Sample Project Management Plan DRAFT

    Page: 11

    Project

    Deliverable 9/15 9/30 10/15 10/31 11/15 11/30 12/15 12/31 1/15 1/31 2/15 2/28 3/15 3/31 4/15 4/30

    Created

    User AcceptanceTesting Sign-off

    1/24

    Technical

    Acceptance Testing

    Sign-off

    12/4

    1.6 PRODUCTION

    CUT-OVER

    Phase-I Intranet

    Cutover

    2/14

    Phase-II Internet

    Cutover

    3/7

    Management

    Reserve

    4/16

    F.Acceptance Criteria

    The project plan takes into account a project task for sign-off on each milestone within

    the project. At the time of milestone sign-off, the appropriate business stakeholder

    and/or technical stakeholders will participate in the review/sign-off meeting(s).

    The primary reason for this is to demonstrate project progress as well as receive

    acceptance from the project stakeholders as we progress through the project timeline.

    E.Assumptions

    1) Users who have rights to Front Page in the existing ABC Inc. Intranetenvironment will maintain the same Front Page rights through the continued use

    of the existing ABC Intranet environment.

    2) Users who have access to the Host Publisher tools in the existing ABC Intranetenvironment will maintain same Host Publisher Tolls access capabilities through

    the continued use of the exiting ABC Intranet environment.

    3) All identified project risks are mitigated at the start of the project.

    4) All scope changes will follow the Change Control Process and be approvedthrough the Executive Steering Committee as needed.

  • 8/2/2019 ABC Inet Pm Plan

    12/44

    Sample Project Management Plan DRAFT

    Page: 12

    5) The assigned project resources are available to complete project tasks asscheduled within the project plan

    6) The existing ABC Intranet will exist in its current state until a decision is made tomigrate to the new ABC Intranet.

    F.Constraints

    1) Assigned resources may be redirected as a result of current production issues.

    2) Change Control decisions will be prioritized by impact on schedule, cost, andfeature/functionality.

  • 8/2/2019 ABC Inet Pm Plan

    13/44

    Sample Project Management Plan DRAFT

    Page: 13

    IV. Critical Success Factors

    The key elements that must be in place to ensure the success of this project are as

    follows:

    The facility preparation to accommodate the additional hardware and software

    required for the Sample Charter project is completed by 9/14/2001.

    The procurement of the necessary hardware and software components for the Sample

    Charter project is secured by 9/21/2001.

    The procured hardware and software required is delivered on time and as planned.

    Assigned resources work activities are prioritized in such a way that project work can

    be completed on time

    Participation, influence and leadership from project sponsor and business project

    leads including decision making, and issues resolution in a timely and effective

    manner

    Scope must be managed with the tightest controls. Escalated change requests must be

    approved by the Executive Steering Committee

    Timely and effective management of project risks

    Manage within the project budget funding

    Active Executive sponsorship

  • 8/2/2019 ABC Inet Pm Plan

    14/44

    Sample Project Management Plan DRAFT

    Page: 14

    V. Cost Estimates(FINANCIAL BUSINESS CASE)

    A.Total Budgeted Costs for Hardware and Software:

    ar ware ervers o tware cense

    Netra Netra AC200 250 280 450 420 WebSphere IPlanet Actuate Edge Server OracleTechnical Environement: 2 0 2 0 2 0 4 2 2 1

    Development 1 1 1 1 0 0 3 2 3 0

    Integration 0 1 2 0 0 0 4 2 0 0

    Implementation 2 2 1 3 0 1 6 2 0 2

    Training 0 2 1 0 0 2 2 4 0 0

    Development/Training Environment: 3 6 5 4 0 3 15 10 3 2

    Production Environment: 4 5 2 6 0 5 12 10 2 4

    Servers needed as a Result of Repurposing

    the 420s servers (used for Proxy Servers): 4 12 0 0 0 0

    Subtotal Unit Count of Hardware/Software: 13 23 9 10 2 8 31 22 7 7 0

    Total Count of Fortis Owned Equipment: 17 0 9 0 0 8 12 5 5 6

    Net Total Unit Count of Hardware/Software

    (subtotal - Fortis owned): 0 23 0 10 2 0 19 17 2 1 0

    Approximate Unit Costs: $11,000 $46,000 $42,000 $6,032 $1,400 $50,000 $8,000 $50,000

    Subtotal Costs: $253,000 $460,000 $84,000 $114,608 $23,800 $100,000 $8,000 $0

    Hardware/Software TotalsTotal Number of New Servers: 35

    Total Cost of New Servers: $797,000Total Cost of Additional Software Licenses: $346,4082 Additional CPUs for Database HA Server: $20,000

    Rack kit for 450s: $16,000

    Grand Total: $1,179,408

    0

    0

    0

    0

    0

    0

    0

    0

  • 8/2/2019 ABC Inet Pm Plan

    15/44

    Sample Project Management Plan DRAFT

    Page: 15

    B.Phase-I Intranet Budgeted Costs for Hardware and Software:

    C.Phase-II Internet Budgeted Costs for Hardware and Software:

  • 8/2/2019 ABC Inet Pm Plan

    16/44

    Sample Project Management Plan DRAFT

    Page: 16

    VI. Approach Strategy

    One of the primary principles behind the Approach Strategy for the Sample Charter

    project is to establish a project foundation that follows proven industry standards for the

    following Project Management Life Cycle Phases:

    Project Initiation

    Project Planning

    Project Execution

    Project Control

    Project Close-Out

    By following an industry standard Project Management Life Cycle the project team is

    effectively managing risk in the area of how the project will project managed.

    In addition, the project will follow the Technique/X (MAGNUS) Project Life Cycle as a

    way to effectively organize, manage, and track project work. As with the Project

    Management Life Cycle, by following an industry standard Project Life Cycle the project

    team is effectively managing risk in the area of project work.

    Also, the project team will fast track (run in parallel) project tasks at the start of the

    project as a way to move things along more quickly. Only project tasks that have

    minimum risk and provide optimum return will be fast tracked.

    Finally, the project team will start early to develop appropriate and adequate test plans to

    ensure that the appropriate unit testing, system integration testing, regression testing

    (where applicable) and User acceptance testing is conducted. User training through

    documentation and classroom training will be provided as determined by the project

    team. A detailed synchronized implementation plan will be developed that covers all

    dependencies and linkages in an effort to help coordinate the final production rollout.

  • 8/2/2019 ABC Inet Pm Plan

    17/44

    Sample Project Management Plan DRAFT

    Page: 17

    D.Technique/X Project Management

    The Project Management practices for the Sample Charter project will adhere to the ABC

    Technique/X (MAGNUS) Project Management Methodology. The primary reason for

    this is to ensure that the ABC Technique/X minimum project deliverables are achieved.

    By following an industry standard Project Management methodology the Sample Charter

    Project will be managed in such a way that consistent practices for both business and

    technology are followed. This will provide a common approach, verifiable project

    deliverables, and clearly defined project roles and responsibilities.

    These practices will achieve a balance between competing stakeholder needs and

    managing expectations related to scope, time, cost, and quality.

    Plan ProjectExecution

    Project Plan-Project Schedule-Project Risk Mgmt Rpt

    OrganizeProject

    Resources

    Define and Mana e Business CaseBusiness Case

    -Busines Case Economics

    ReportProjectStatus

    Project Status Rpt Pkg

    ControlProject Work

    Issue or Open Pt.Project Change Request

    Manage the Testing Effort

    Iterate as required

    PrepareProject

    CompleteProject

    Final Project Report

    Manage the Infrastructure

    Technique X

    Project Management

  • 8/2/2019 ABC Inet Pm Plan

    18/44

    Sample Project Management Plan DRAFT

    Page: 18

    X. Work Breakdown Structure

    ProjectWork Breakdown Structure

    As of: 9/21/2001

    1.2 Analysis 1.3 Design1.1 Project Management

    1.1.1 Project Charter

    1.1.1.1 Benefits

    1.1.1.2 Cost Estimate

    1.1.1.3 Scope

    1.1.1.4 Project Approach/Strategy

    1.1.1.5 Define ProjectTeam

    1.1.1.7 Governance Plan

    1.1.1.8 Project Plan

    1.1.1.9 Control Strategy

    1.1.1.10 Risk Assessment

    1.2.1 ProjectPhase Definition

    1.2.1.1 Phase-I ABCCo.Net

    1.2.1.2 Phase-II Internet

    1.2.2 BusinessRequirements

    1.2.2.2 ABC

    1.2.3 Technical

    Requirements

    1.2.5 ProcedureChanges

    1.3.1 HardwareDesign

    1.3.3 SoftwareDesign

    1.4.1 CreateBranch

    1.4.2 PrepareFacilities

    1.4.2.1 Data CenterSpace

    1.4.2.2 SANConnections

    1.4.2.3 NetworkConnections

    1.4.3 Prepare forServer Installs

    1.4.3.1 Rack/StackServers

    1.4 Build

    1.4.3.2 JumpstartServers

    1.5.1 Create TestPlans

    1.5 Integration/Test

    1.6.1 Phase-I ABCCo.Net

    1.6 Production COver

    1.6.3 Phase II -Internet

    1.2.3.1 Phase-I ABCCo.Net / Phase-II

    Internet

    1.4.5 Phase-I BuildABC Co.Net

    1.4.5.1 Build Servers

    1.4.5.2 Build Software

    1.5.1.1 BusinessTest Plans

    1.5.1.2 TechnicalTest Plan

    1.5.2 Phase-I ExecuteTest Scripts

    1.5.2.1 BusinessTest Scripts

    1.5.2.2 TechnicalTest Scripts

    1.1.1.6 OrganizationalBreakdown Structure

    1.1.2 Kick-OffMeetings

    1.1.4 Project RAF

    1.2.2.3 FBXC

    1.2.2.4 ABC Co. Family

    1.2.2.5 ABC Co. Health

    1.2.2.6 Hartland

    1.2.2.7 ABC Co. Inc.

    1.2.4 SoftwareRequirements

    1.2.4.1 Phase-I ABCCo.Net / Phase-II

    Internet

    1.2.6 OrderHardware/Software

    1.4.5.3 MigrateApplications

    1.4.6 Phase-IIInternet

    1.4.6.1 Build Servers

    1.4.6.2 Build Software

    1.5.3 Phase-IIExecute Test Scripts

    1.5.3.1 BusinessTest Scripts

    1.5.3.2 TechnicalTest Scripts

  • 8/2/2019 ABC Inet Pm Plan

    19/44

    Sample Project Management Plan DRAFT

    Page: 19

    IX. Project Plan

    The following project plan provides a timeline that assumes no new resources added to the project.

    D Task Name % Finish1 1 Project 0% Tue 04/16/022 1.1 Project Management 0% Tue 04/16/023 1.1.1 Project Charter 0% Tue 10/16/01

    48 1.1.2 Project Kick-Off Meetings 0% Thu 09/27/0154 1.1.3 Project Meetings 0% Fri 04/05/0258 1.1.4 Document the RAF 0% Mon 10/08/0159 1.1.5 Management Reserve Based on Initial Risk Assessment 0% Tue 04/16/02

    60 1.2 Analysis 0% Thu 11/08/0161 1.2.1 Define Project Phases 0% Tue 09/04/0169 1.2.2 Business Requirements 0% Fri 10/19/0101 1.2.3 Technical Requirements 0% Tue 10/09/0107 1.2.4 Software Requirements 0% Tue 10/23/0122 1.2.5 Document Procedure Changes 0% Thu 11/08/0145 1.2.6 Order Hardware/Software 0% Fri 09/28/0150 1.3 Design 0% Fri 10/19/0151 1.3.1 Hardware Design 0% Tue 09/11/0155 1.3.2 Software Design 0% Tue 10/02/0159 1.3.3 Prepare for Architectual Design Review 0% Fri 10/19/0160 1.3.4 Conduct Architectual Design Review 0% Fri 10/19/0162 1.4 Build 0% Tue 02/05/02

    63 1.4.1 Create Second Branch to Resolve PROD Load Issue 0% Fri 10/19/0178 1.4.2 Prepare Facilities for New Hardware/Software 0% Fri 09/28/0199 1.4.3 Prepare for Server Installations 0% Fri 10/12/0111 1.4.4 Validate software/system requirements 0% Mon 09/10/0112 1.4.5 Phase-I Build isNet 0% Tue 01/15/0278 1.4.6 Phase-II Build Internet 0% Tue 02/05/0272 1.5 Integration/Test 0% Thu 02/14/0273 1.5.1 Create Test Plans for ALL Phases 0% Thu 11/15/0105 1.5.2 Execute Test Scripts for Phase-I Net 0% Thu 01/24/0230 1.5.3 Execute Test Scripts for Phase-II Internet 0% Thu 02/14/0255 1.6 Production Cut-Over 0% Thu 03/07/0256 1.6.1 Cut-Over Phase-I sNet to Production 0% Thu 02/14/0260 1.6.2 Cut-Over Phase-II Internet to Production 0% Thu 03/07/02

    0%0%

    0%

    0%0%

    0%0%

    0%0%

    0%0%

    0%0%

    0%10/19

    0

    0%0%

    0%0%

    0%

    0

    0%0%

    Aug Sep Oct Nov Dec Jan Febuarter 4th Quarter 1st Quarter

  • 8/2/2019 ABC Inet Pm Plan

    20/44

    Sample Project Management Plan DRAFT

    Page: 20

    X. Project Team

    A.Organizational Breakdown Structure

    AProject Lead

    DProject Lead

    Team Member

    AProject Lead

    b

    BProject Lead

    Project Steering CommitteeJon Doe

    s

    I-Net Relationship Managers

    Project Manager

    Project Auditor

    Team MemberProject Sponsor

    I-NetManager

    Technical ArchitectTeam Lead

    I-Net Manager I-Net Manager

    I-Net OperationExpert

    Security Expert

    Production ControlExpert

    Open SYstemsSupport

    Team Lead

    Lead EngineerTBD

    Oracle DBA Expert

    Middleware Expert Network ExpertOpen SystemsSupport

    CProject Lead

    EProject Lead

    Team Member

    AProject Lead

    AProject Lead

    Team Member Team Member

    AProject Lead

    Project Organizational Breakdown Structure as of 10/05/2001

    Team MemberF

    Project LeadF

    Project Lead

    I-Net Tools Support

  • 8/2/2019 ABC Inet Pm Plan

    21/44

    Sample Project Management Plan DRAFT

    Page: 21

    B.Project Roles and Responsibilities

    Sample Charter ProjectRoles and Responsibilities Matrix

    Individual(s) Role Responsibilities

    Project Sponsor Project Champion

    Offer strategic business leadership and direction

    Provide Communication bridge to outside the

    project Senior Management

    Scope change approval

    Budget variance approval

    Removes project barriers

    I-Net

    Relationship

    Managers

    Executive SteeringCommittee

    Scope change approval Offer strategic business leadership and direction

    Remove project barriers

    Project Manager Manage daily project tasks

    Manage project deliverables, resources, andschedule

    Track project progress to plan and manage the

    project plan

    Facilitate project communication, project

    decision making, project issue resolution, and

    project risk management

    Facilitate Monthly Executive Steering

    Committee meetings

    Review project deliverables, facilitate

    adjustments as needed, and facilitate change

    approval

    Issue and Change management log owner

    Project Status Report author

    Testing site auditor/QA

    I-Net AccountManagers

    Ensure that the business needs are met Communicate project scope/objectives to

    business I-Net customers

    Obtain testing resources from the businesses

    FBIC

    Business Project

    Leads

    Act as project contact for the business

    Provide leadership in the coordination of

    assigned project tasks for business team

    members

  • 8/2/2019 ABC Inet Pm Plan

    22/44

    Sample Project Management Plan DRAFT

    Page: 22

    Individual(s) Role Responsibilities

    ABC Family

    ABC HealthHartford

    ABC Inc.

    ABC IT

    Provide business requirements input, test

    planning, test execution, and User Acceptancetesting sign-off

    Provide business sign-off for project milestones

    as needed

    Ensure that the appropriate business resources

    are available to meet project schedule and

    project deliverables

    Business Team

    Members

    Provide business content expertise

    Provide input to business requirements

    Provide input to business test planning

    Conduct test script execution

    Provide documentation as required for theproject

    Project Auditor Provide independent assessment of projectactivities and issues

    Provide audit standards guidelines and

    enforcement where needed and appropriate

    Provide documentation as required for the

    project

    Technical

    Architect,

    Technical Lead

    Provide leadership in the coordination of

    assigned project tasks for the technical team

    Provide technical architect and design expertise Ensure that the architected designs fit within

    ABC strategic infrastructure vision

    Provide technical sign-off for project milestones

    as needed

    Provide documentation as required for the

    project

    Open Systems

    Support, Technical

    Lead

    Act as the project contact for the Open Systems

    Support area

    Provide leadership in the coordination of

    assigned project tasks for the Open Systems

    Support area

    Provide Unix operating system expertiseImplement Unix hardware configuration and

    setup

    Implement system software configuration and

    setup

    Insure that all ABC standards are met (i.e. base

    configuration, security audits, etc.)

  • 8/2/2019 ABC Inet Pm Plan

    23/44

    Sample Project Management Plan DRAFT

    Page: 23

    Individual(s) Role Responsibilities

    Provide technical sign-off for project milestones

    as neededEnsure that the appropriate Open Systems

    Support resources are available to meet project

    schedule and project deliverables

    1st line of support for all project issues related

    above responsibilities

    Provide documentation as required for the

    project

    I-Net Operations

    Expert

    Provide technical expertise in the area of

    Websphere configuration and setup

    Provide technical expertise in the area of Apache

    server, Application server, NFS server, and Webserver configuration and setup

    Provide technical expertise for the configuration

    and setup of appropriate software for the various

    server types

    Provide technical expertise for SiteMinder agent

    Provide technical expertise for load balancing

    Provide input to technical test plan

    Conduct technical testing as required

    1st

    line of support for all project issues related

    above responsibilities

    Provide documentation as required for theproject

    Security Expert

    Provide technical expertise for the configuration

    and setup for SiteMinder

    Provide technical expertise for SiteMinder agent

    Provide technical expertise for the configuration

    and setup of iPlanet

    Provide input to technical test plan

    Conduct technical testing as required

    1st

    line of support for all project issues related

    above responsibilities

    Provide documentation as required for theproject

    Production Control

    Expert

    Provide technical expertise for the configuration

    and setup of Harvest

    Provide input to technical test plan

    Conduct technical testing as required

    1st line of support for all project issues related

    above responsibilities

  • 8/2/2019 ABC Inet Pm Plan

    24/44

    Sample Project Management Plan DRAFT

    Page: 24

    Individual(s) Role Responsibilities

    Provide documentation as required for the

    projectTBD Lead Engineer

    Provide technical expertise in the area of Load

    testing

    Provide input to the technical test plan for Load

    Testing

    Complete technical tasks as related to the setup,

    configuration, and testing of Load testing as

    related to the new ABC Intranet and ABC

    Internet

    Provide documentation as required for the

    project

    Oracle DBAExpert

    Provide technical expertise in the area of Oracledatabases as related to the new ABC Intranet and

    ABC Internet infrastructures

    Complete technical tasks as related to the setup,

    configuration, and testing of the Oracle

    databases as related to the new ABC Intranet and

    ABC Internet

    Provide documentation as required for the

    project

    Network Expert

    Act as the primary project contact for all

    network related issues/questions

    Provide technical expertise in the area ofnetwork administration, components, and

    implementation

    Complete technical tasks as related to the setup,

    configuration, and testing of the network as

    related to the new ABC Intranet and ABC

    Internet

    Provide documentation as required for the

    project

    Middleware

    Expert

    Act as the primary project contact for all

    Middleware issues/questions

    Provide technical expertise in the area ofMiddleware coding, components, and

    implementation

    Complete technical tasks as related to the setup,

    configuration, and testing of the Middleware as

    related to the new ABC Intranet and ABC

    Internet

    Provide documentation as required for the

  • 8/2/2019 ABC Inet Pm Plan

    25/44

    Sample Project Management Plan DRAFT

    Page: 25

    Individual(s) Role Responsibilities

    project

    I-Net ToolsSupport

    Act as the primary technical contact for thebusiness units during the life of the project

    Provide business application support during

    application migration and testing

    Complete support tasks as related to the setup,

    configuration, and testing of the business

    applications as related to the new ABC Intranet

    and ABC Internet

    Provide documentation as required for the

    project

    C.Project Roster

    All project resource phone numbers and email addresses are outlined in the table

    below. This information will be used as the best means of communication for the

    team and other key resources for the project.

    Name Department Project Role Work Phone Pager/CellPhone

    Home Phone

    Internet Address

    Assurant Business Project

    Lead

    N/A N/A

    I-Net Production

    Control Expert

    N/A

    I-Net Technical

    Architect

    N/A

    Open Systems

    Support

    Open Systems

    Support Expert

    N/A

    Corporate

    Security

    Executive

    Steering

    Committee

    N/A N/A

    Open Systems

    Support

    Executive

    SteeringCommittee

    N/A N/A

    Audit Services Project Auditor N/A N/A

    I-Net Project Sponsor N/A

    I-Net Tools I-Net Tools

    Support

    N/A

    Data Center

    Operations

    Executive

    Steering

    Committee

    N/A

    I-Net I-Net N/A

  • 8/2/2019 ABC Inet Pm Plan

    26/44

    Sample Project Management Plan DRAFT

    Page: 26

    Name Department Project Role Work Phone Pager/Cell

    Phone

    Home Phone

    Internet Address

    RelationshipManager

    I-Net Tools I-Net Tools

    Support

    N/A

    I-Net I-Net

    Relationship

    Manager

    N/A

    FBX Business Project

    Lead

    N/A

    ABC Health Business Team

    Member

    N/A

    I-Net I-Net

    Operations

    Expert

    N/A

    I-Net Services Stakeholder N/A

  • 8/2/2019 ABC Inet Pm Plan

    27/44

    Sample Project Management Plan DRAFT

    Page: 27

    XI. Risk Management

    The project risks will be identified at the start of the project and the impact of realizing the risks

    will be factored in as part of the project plan planning process (management reserve). Each risk

    will be assessed, prioritized, and rated. Such an approach provides a means to track risks, and

    more importantly a means to proactively work to prevent them from negatively impacting the

    project.

    In addition, risk trigger points will be identified and mitigation strategies documented. As risks

    are realized, the risk will be logged as an issue and then tracked through the change control

    process (if required) until the risk is mitigated.

    Also, new project risks will be identified and logged throughout the life of the project. As new

    risks are discovered, the risk is logged as an issue and follows the issue management processes.

    If deemed necessary, a risk assessment will be conducted for the issue and factored into the

    project plan. All risks will be managed at the project team level unless escalated to the

    Executive Steering Committee.

    Detailed information outlining the initial Risk Assessment for the Sample Charter Project is

    provided in Appendix A of the Sample Charter Project Charter document.

  • 8/2/2019 ABC Inet Pm Plan

    28/44

    Sample Project Management Plan DRAFT

    Page: 28

    XII. Governance Plan

    Issue Escalation

    Issues will surface weekly, if not daily throughout the course of the project.

    Effective issue tracking and resolution are critical to the success of the project.

    The following issue escalation process is recommended:

    Tier 1 Project Team to Project Manager

    Project Team members escalate issues to the Project Manager who in turn will

    document the issue(s) on the Issue Tracking Log. The log is reviewed weekly by

    the Project Manager to ensure issues are being appropriately addressed andclosed.

    Tier 2 Project Manager to Project Team

    The Project Manager escalates issues to the Project Team for further discussion in

    an effort to clarify and/or resolve issues. The Project Team will assist the Project

    Manager in resolving the issue, if possible. If resolved, the Project Manager will

    update the Issue Tracking Log and close the issue.

    Tier 3 Project Manager to Project Sponsor

    The Project Manager escalates issues to the Project Sponsor to ensure that ABC

    management members are fully aware of unresolved critical issues. The ProjectSponsor will assist the Project Manager in resolving the issue, if possible. If

    resolved, the Project Manager will update the Issue Tracking Log and close the

    issue.

    Tier 4 Project Manager to Executive Steering Committee

    The Project Manager escalates the most sensitive and urgent issues to the

    Executive Steering Committee to ensure that the appropriate ABC senior

    management members are fully aware of unresolved critical issues. The

    Executive Steering Committee will assist the Project Manager in resolving the

    issue, if possible. When resolved, the Project Manager will update the Issue

    Tracking Log and close the issue.

  • 8/2/2019 ABC Inet Pm Plan

    29/44

    Sample Project Management Plan DRAFT

    Page: 29

    XIII.Project Control Strategies

    A. Quality Assurance

    Milestone reviews by the business and technical teams will be presented during the weekly

    team meetings. Tight controls and metrics will be utilized to manage scope, budget and

    timeline through dedicated task management from the Project Manager, a detailed project

    measurement tool, and the change request approval process.

    B. Change Control

    All changes to the Sample Charter project will be reviewed and approved by the Executive

    Steering Committee. All approved changes will be added to the Project Charter document

    and be identified as an approved Change request.

    Detail Change control information will be documented in the Sample Charter Change

    Request MAGNUS and maintained within the Sample Charter Change Control Log. The

    Change Control process and definition is outlined and explained within the Sample Charter

    Change Control Plan.

    In addition, the following Change Control rules apply:

    At any time, any team member may submit a Project Change Request (PCR)

    to the Project Manager.

    The Project Manager is responsible to assess and present the PCR to the

    technical and core project teams for review.

    The Project Manager is responsible for maintaining the Sample Charter

    Change Control Log.

    C. Communications

    Status Reports

    Status reports will be submitted by the Project Manager to the Sample Charterproject team members on a weekly basis (bend of business every Tuesday).

    In addition, a copy of the weekly status report will be submitted to the appropriate

    ABC management team as indicated in the Sample Charter Communications

    Matrix (see appendix B).

  • 8/2/2019 ABC Inet Pm Plan

    30/44

    Sample Project Management Plan DRAFT

    Page: 30

    These reports provide a snapshot of weekly accomplishments, tasks to complete

    for the next reporting period, milestones reached, project issues, and PCRs in

    progress.Input by project team members will be provided as part of the weekly core team

    and technical team meetings. Project team members will provide the necessary

    information to complete the weekly snapshot for their area of responsibility.

    Meetings

    Meetings for the Sample Charter project will be conducted under the following

    format:

    Core Team Meetings

    Core team meetings will include technical team leads, business project teammembers, and will meet on a weekly basis. The core team meeting will be a

    primary vehicle for project communications and decision-making.

    Technical Team Meetings

    Technical team meetings will include technical team leads, technical team

    members, and will meet on a weekly basis. The technical team meeting will

    be a primary vehicle for project communications and decision-making.

    Executive Steering Committee Meetings

    Executive Steering Committee meetings will meet on a monthly basis as a

    way to communicate project progress to ABC senior management. Additional

    meetings may be scheduled as required based upon project issues resolutionand change control needs.

    Additional Meetings

    Additional meetings will be scheduled as required.

    E-Mail

    E-mail will be the primary mode of communication for project team members.

    D. Information Management

  • 8/2/2019 ABC Inet Pm Plan

    31/44

    Sample Project Management Plan DRAFT

    Page: 31

    Project Website

    In an effort to manage and maintain project documentation, the Project Manager will

    maintain a binder, file set and/or electronic repository of all required documentation to meetthe Technique/X minimum deliverables. This information will be published on the project

    website located at the following address: http://inc.us.ABC.com/xxx/

    The Project website may include the following documentation:

    Project Charter

    Project Plan

    Project Issue Log (includes resolution)

    Project Risk Watch (Risk Assessment)

    Project Change Requests and Change Log Meeting Notes

    Status Reports

    Communication plan

    Updated budget

    Test plan strategy

    Technical and Functional Specifications

    All signature signoffs will be captured and maintained by the Project Manager in thepaper based project handbook.

  • 8/2/2019 ABC Inet Pm Plan

    32/44

    Sample Project Management Plan DRAFT

    Page: 32

    XIV.APPENDIX A - Initial Project Risk AssessmentThe risks identified in the following table represent items that have been identified by the Sample Charter project t

    project.

    Risk

    Item/

    Priority

    Potential Risk

    Consequence

    Risk Resolution Progress Probability

    (%)

    Impact

    (Hours)

    P1.1-01 The impact of

    daily work for

    the technical

    team maycause delays in

    completing

    project work

    Resolution to this risk can be incrementally

    realized by implementing the following

    measures to mitigate the risk:

    Add additional technical resources. Shift production support from the project

    technical resources to non-project

    technical resources.

    Cut back on project scope. Extend the project time line to

    accommodate resource constraints.

    100% 440

    OPS=8hrs/wk*20

    wks=160hrs

    UNIX=

    8hrs/wk*20

    wks=160hrs

    PROD

    CNTRL=

    4hrs/wk*20

    wks=80hrs

    SEC=

    4hrs/wk*10

    wks=40hrs

  • 8/2/2019 ABC Inet Pm Plan

    33/44

    Sample Project Management Plan DRAFT

    Page: 33

    Risk

    Item/

    Priority

    Potential Risk

    Consequence

    Risk Resolution Progress Probability

    (%)

    Impact

    (Hours)

    P1.2-02 The impact of

    added other

    project work

    do to the I-Net

    Operations

    resource

    vacancy is

    causing delays

    in completing

    project work

    Resolution to this risk can be incrementally

    realized by implementing the following

    measures to mitigate the risk:

    Fill I-Net Operation Manager position Add additional technical resources. Shift I-Net Manager tasks from the

    project technical resources to non-project

    technical resources.

    Cut back on project scope. Extend the project time line to

    accommodate resource constraints.

    Prioritize I-Net projects so that SampleCharter is #1 priority

    100 80

    4hrs/wk *20

    weeks =

    80hrs

  • 8/2/2019 ABC Inet Pm Plan

    34/44

    Sample Project Management Plan DRAFT

    Page: 34

    Risk

    Item/

    Priority

    Potential Risk

    Consequence

    Risk Resolution Progress Probability

    (%)

    Impact

    (Hours)

    P1.3-03 The impact of

    daily work for

    the business

    team may cause

    delays in

    completing

    project work

    Resolution to this risk can be incrementally

    realized by implementing the following

    measures to mitigate the risk:

    Add additional business resources. Shift daily business tasks from the

    project technical resources to non-project

    technical resources.

    Designate a Business Project Lead foreach business unit to assist in the

    coordination and completion of projectwork.

    Assign a project Business Liaison toassist in working with the Business

    Project Leads to complete project work.

    Cut back on project scope. Extend the project time line to

    accommodate resource constraints.

    Provide a minimum of 30 day lead timeon project work requests to the business

    units for planning purposes Allow an appropriate amount of time for

    testing

    100% 48

    8hrs/month* 6 months

    = 48 hrs

  • 8/2/2019 ABC Inet Pm Plan

    35/44

    Sample Project Management Plan DRAFT

    Page: 35

    Risk

    Item/

    Priority

    Potential Risk

    Consequence

    Risk Resolution Progress Probability

    (%)

    Impact

    (Hours)

    P1.4-04 The installation

    of Netegrity

    software on the

    Apache servers

    with Solaris 2.8

    is being done

    for the first time

    Resolution to this risk can be incrementally

    realized by implementing the following

    measures to mitigate the risk:

    Conduct Netegrity research/analysistesting early in the project (complete by

    end of Sept. 2001) to allow for time to

    switch to alternative option (stay

    w/Solaris 2.7 on old Netras) if necessary

    without impacting project time line.

    Contract a Service Level Agreement withthe Netegrity vendor that provides

    immediate response with Senior Level

    Netegrity programming resources as a

    way to expedite issue resolution.

    Project Sponsor contacts Netegritymanagement to raise awareness of ABC

    I-Net support expectations and impact

    during the implementation of a ABC

    mission critical project.

    25% 260

    Hour

    estimates

    based on

    history of

    previous

    implementat

    ion of

    Netegrity

  • 8/2/2019 ABC Inet Pm Plan

    36/44

    Sample Project Management Plan DRAFT

    Page: 36

    Risk

    Item/

    Priority

    Potential Risk

    Consequence

    Risk Resolution Progress Probability

    (%)

    Impact

    (Hours)

    P1.5-05 The upgrade to

    Websphere 4.0

    may uncover

    compatibility

    issues

    Resolution to this risk can be incrementally

    realized by implementing the following

    measures to mitigate the risk:

    Contract with the IBM for a senior levelWebsphere expert (interviewed/ accepted

    by ABC) as a way to minimize the

    learning curve and expedite issue

    resolution.

    Install TECH environment during Phase-I (moved up from Phase-II) to conductWebsphere 4.0 testing.

    Project Sponsor contact IBMmanagement to raise awareness of ABC

    I-Net support expectations and impact

    during the implementation of an ABC

    mission critical project.

    50% 100

    Hour

    estimatesbased on

    history of

    previous

    implementat

    ion of

    Websphere

  • 8/2/2019 ABC Inet Pm Plan

    37/44

    Sample Project Management Plan DRAFT

    Page: 37

    Risk

    Item/

    Priority

    Potential Risk

    Consequence

    Risk Resolution Progress Probability

    (%)

    Impact

    (Hours)

    P1.6-06 The

    implementation

    of Model

    Cloning may

    uncover

    compatibility

    issues

    Resolution to this risk can be incrementally

    realized by implementing the following

    measures to mitigate the risk:

    Implement Websphere 4.0 to takeadvantage of added Websphere

    functionality.

    Contract with the IBM for a senior levelWebsphere Model Cloning expert

    (interviewed/ accepted by ABC) as a way

    to minimize the learning curve andexpedite issue resolution

    Project Sponsor contact IBMmanagement to raise awareness of ABC

    I-Net support expectations and impact

    during the implementation of an ABC

    mission critical project.

    50% 80

    Hour

    estimatebased on

    experience

    with Web

    sphere and

    Model

    Cloning

  • 8/2/2019 ABC Inet Pm Plan

    38/44

    Sample Project Management Plan DRAFT

    Page: 38

    Risk

    Item/

    Priority

    Potential Risk

    Consequence

    Risk Resolution Progress Probability

    (%)

    Impact

    (Hours)

    P1.7-07 Veritas

    Clustering is

    new and

    complex and

    may uncover

    compatibility

    issues

    Resolution to this risk can be incrementally

    realized by implementing the following

    measures to mitigate the risk:

    Implement Websphere 4.0 to takeadvantage of added Websphere

    functionality.

    Contract with the Veritas vendor for asenior level Veritas expert (interviewed/

    accepted by ABC) as a way to minimize

    the learning curve and expedite issueresolution

    Project Sponsor contacts Veritasmanagement to raise awareness of ABC

    I-Net support expectations and impact

    during the implementation of an ABC

    mission critical project.

    Conduct Veritas research/analysis testingearly in the project to allow for time to

    switch to alternative option if necessary

    without impacting project time line.

    Connect directly to the SAN.

  • 8/2/2019 ABC Inet Pm Plan

    39/44

    Sample Project Management Plan DRAFT

    Page: 39

    Risk

    Item/

    Priority

    Potential Risk

    Consequence

    Risk Resolution Progress Probability

    (%)

    Impact

    (Hours)

    P1.8-08 The use of NFS

    servers in the

    ABC

    infrastructure is

    new and

    potentially

    unstable

    Resolution to this risk can be incrementally

    realized by implementing the following

    measures to mitigate the risk:

    Conduct NFS research/analysis testingearly in the project to allow for time to

    switch to alternative option if necessary

    without impacting project time line.

    Connect directly to the SAN (note: needto pre-order cards for this option)

    Add disk space to servers and do not useNFS

    80

    8hrs/server*

    10 servers =80hrs

    P1.9-09 The use of NIS

    PLUS is new to

    the ABC

    infrastructure

    and complex

    Resolution to this risk can be incrementally

    realized by implementing the following

    measures to mitigate the risk:

    Conduct NIS PLUS research/analysistesting early in the project to allow for

    time to switch to alternative option if

    necessary without impacting project time

    line. Add additional technical resources. Dont install NIS PLUS as part of

    Sample Charter project

  • 8/2/2019 ABC Inet Pm Plan

    40/44

    Sample Project Management Plan DRAFT

    Page: 40

    Risk

    Item/

    Priority

    Potential Risk

    Consequence

    Risk Resolution Progress Probability

    (%)

    Impact

    (Hours)

    P1.10-10 The SAN Space

    and SAN

    connections are

    near full

    capacity

    Resolution to this risk can be incrementally

    realized by implementing the following

    measures to mitigate the risk:

    Communicate to the SAN group theSample Charter project time line and

    expectations

    25% 120

    Based on

    past history,

    SAN delays

    have been

    as great as 3

    weeks or

    120hrs

    Totals:

  • 8/2/2019 ABC Inet Pm Plan

    41/44

  • 8/2/2019 ABC Inet Pm Plan

    42/44

    DRAFT

    Page: 42

    XV. APPENDIX B Communications MatrixDAY OF

    MEETING

    TYPE OF MEETING/

    COMMUNICATION TIME of

    MEETING PURPOSE of MEETING

    MATERIALS

    SENT OUT BY: A

    WEEKLY Project Status Report N/A The Weekly Project Status Report will

    be e-mailed to project team members

    and published on the Sample Charter

    web site.

    Published every

    Tuesday

    WEEKLY Technical Team Meeting Wednesday at

    11:00am CST

    The technical team meeting is a forum

    for the technical team to discuss

    project work, project schedule, and

    project issues at a detailed level.

    Within 2 days

    after meeting

    WEEKLY Core Team Meeting Thursday at10:00am CST

    The business team meeting is a forumfor the business team to discuss

    project work, project schedule, and

    project issues at a detailed level.

    Within 2 daysafter meeting

    MONTHLY Executive Steering

    Committee Meeting

    9/18/01, 10/16/01,

    11/13/01,

    12/18/01, 1/15/02,

    2/19/02, 3/19/02

    The Project Steering Committee

    meeting is designed to inform

    executive management of project

    progress to date. This meeting will

    also be used to make decisions

    regarding project budget, issues,

    scope, and timeline.

    Within 2 days

    after meeting

    Sample Project Management Plan

  • 8/2/2019 ABC Inet Pm Plan

    43/44

  • 8/2/2019 ABC Inet Pm Plan

    44/44

    Sample Project Management Plan DRAFT

    XVI.Approval Signatures

    Jon Muggins / Project Manager Date

    / Executive Sponsor Date

    / Executive Steering Committee Date

    / Executive Steering Committee Date

    / Executive Steering Committee Date

    / Executive Steering Committee Date

    / Executive Steering Committee Date

    / Executive Steering Committee Date