abc final asb 110211
TRANSCRIPT
-
8/2/2019 ABC Final Asb 110211
1/88
Activity-Based Cost
Management Systems
Rishiraj
-
8/2/2019 ABC Final Asb 110211
2/88
Problems With Simple CostAccounting Systems: The Cooper
Pen Company Example
Cooper Pen had been the low-cost
producer of blue pens and black pens,with profit margins exceeding 20% of sales
Several years ago Cooper Pen expanded
their business by extending their productline into products with premium sellingprices
-
8/2/2019 ABC Final Asb 110211
3/88
The Cooper Pen Company Example
Five years ago red pens were introduced
The same basic production technology
Could be sold at a price that was 3% higher than forblue and black pens
Last year purple pens were added Could be sold at a 10% price premium
The controller of Cooper Pen was disappointedwith the most recent quarters financial results
Overall profitability for all four together had decreased
The red and purple pens, however, were more profitablethan the blue and black pens
-
8/2/2019 ABC Final Asb 110211
4/88
Total Profitability by Product
Blue Black Red Purple Total
Units 50,000 40,000 9,000 1,000 100,000
Price 4.50 4.50 4.65 4.95
Sales 225,000 180,000 41,850 4,950 451,800
Material 75,000 60,000 14,040 1,650 150,690Labor 30,000 24,000 5,400 600 60,000
Overhead 90,000 72,000 16,200 1,800 180,000
Total Mfg.
Expenses
195,000 156,000 35,640 4,050 390,690
GrossMargin
30,000 24,000 6,210 900 61,110
G.M. % 13.3% 13.3% 14.8% 18.2% 13.5%
-
8/2/2019 ABC Final Asb 110211
5/88
Concern at Cooper Pen
The controller of Cooper Pen wondered whetherthe company should continue to deemphasize theblue and black commodity products and keepintroducing new specialty colored pens
Coopers manufacturing manager commented onhow the introduction of colored pens hadchanged the production environment:
Everything ran smoothly when producing just
blue and black pens in long production runs
Difficulties started when the red pens wereintroduced and required more changeovers
-
8/2/2019 ABC Final Asb 110211
6/88
Changes Caused by New Pens (1 of 2)
Making black ink was simple; there was not evena need to clean out the residual blue ink fromthe previous run if enough black ink wasdumped in to cover it up
Red required Cooper to stop production, emptythe vats, clean out all remnants of the previouscolor, and then start the production of the red ink
Even small traces of the blue or black inkcreated quality problems
The ink for the purple pens also had demandingspecifications, though not quite as demandingas the red ink
-
8/2/2019 ABC Final Asb 110211
7/88
Changes Caused by New Pens(2 of 2)
Cooper Pens was also spending more time onpurchasing and scheduling activities andkeeping track of existing, backlogged, and futureorders
Coopers manufacturing manager wasconcerned about rumors that new colors may beintroduced in the near future He did not think they had any more capability to
handle additional confusion and complexity in the
operations Last years new computer system helped to
reduce some of the confusion
-
8/2/2019 ABC Final Asb 110211
8/88
Pen Production At Coopers
Pen production at the factory involved:
Preparing and mixing the ink for the different color pens Inserting the ink into the pens in a semiautomated
process Packing and shipping the pens in a manual stage
Each product had a: Bill of materials that identified the quantity and cost of
direct materials required for the product Routing sheet that identified the sequence of
operations required for each operating step
This information was used to calculate the laborexpenses for each of the four products From this information, it was easy to calculate the direct
materials costs and direct labor costs for each colorpen
-
8/2/2019 ABC Final Asb 110211
9/88
Coopers Indirect Cost Allocation
Because it was a small company and historicallyhad produced only a narrow range of products,Cooper used a simple costing system
All the plants indirect expenses were aggregated at
the plant level and allocated to products based oneach products direct labor cost
Currently the cost systems overhead burden rate was
300% of direct labor cost
Before the new specialty products were introduced,the overhead rate was only 200% of direct labor cost
-
8/2/2019 ABC Final Asb 110211
10/88
Cooper Pens Cost System
Coopers management accountants designed
the system years ago when:
Production operations were mostly manual
Total indirect costs were less than direct labor costs
Coopers two products had similar productionvolumes and batch sizes
Given the high cost of measuring and recordinginformation, the accountants at the time judged
correctly that a complex costing system wouldcost more to operate than the benefits it wouldprovide
-
8/2/2019 ABC Final Asb 110211
11/88
A Changed Production Environment
Direct labor costs have decreased and indirectexpenses have increased as a result ofautomation
As custom low-volume products, such as red
and purple pens were added, Cooper needed: More scheduling
More setups
More quality control personnel
A computer to track orders and product specifications
-
8/2/2019 ABC Final Asb 110211
12/88
An Outdated Cost System
Cooper operates with only a single cost center,the plant Most complex companies use many cost centers for
cost accumulation
Even if Cooper Pen used multiple productionand service department cost centers, it could stillencounter severe distortions in its reportedproduct costs: In an environment of high product variety, using only
unit-level drivers (such as direct labor costs) toallocate overhead costs to products could lead toproduct cost distortion
-
8/2/2019 ABC Final Asb 110211
13/88
Reason for Cost Distortions (1 of 3)
schedule machine andproduction runs
perform setups
inspect produced items aftersetup
move materials
ship orders
expedite orders
rework defective items
design new products
improve existing products
negotiate with vendors
schedule materials receipts order, receive, and inspect
incoming materials and parts
update and maintain the muchlarger computer-based
information system
A complex factory has a much larger production support
staff because it requires more people to:
A complex factory generally also operates with higherlevels of idle time, setup time, overtime, inventory, rework,and scrap
-
8/2/2019 ABC Final Asb 110211
14/88
Reason for Cost Distortions (2 of 3) Because the factory has the same physical
output, it has roughly the same cost of materials(ignoring the slightly higher acquisition costs forsmaller orders of specialty colors and othermaterials)
Because all pens are about the same complexity,each pen would require the same number ofdirect labor hours and machine hours to produce
The Cooper Pen Company factory has about the
same property taxes, security costs, and heatingbills as before, but it has much higher indirect andsupport costs because of its more varied productmix and complex production tasks
-
8/2/2019 ABC Final Asb 110211
15/88
Reason for Cost Distortions(3 of 3) On a per unit basis, high-volume standard blue and black
pens require about the same amount of direct labor costs(the allocation basis) as the low volume color pens
Therefore, the traditional costing system would reportessentially identical product costs for all products,standard and specialty, irrespective of their relativeproduction volumes
This would hold true even if the cost system hadmultiple production and service cost centers
Clearly, however, considerably more indirect and supportresources are required on a per-unit basisfor the low-volume, newly designed products than for the high-volume, standard blue and black pens
-
8/2/2019 ABC Final Asb 110211
16/88
Activity-Based Cost Systems Activity-based cost systems have been
developed to eliminate this major source of costdistortion
Activity-based cost (ABC) management systemsuse a simple two-stage approach similar to butmore general than traditional cost systems
The next slide compares the essential elementsof the two systems
-
8/2/2019 ABC Final Asb 110211
17/88
Traditional v. ABC System
Traditional:
Uses actual departments orcost centers for accumulatingand redistributing costs
Asks how much of anallocation basis (usually
based on volume) is used bythe production department
Service departmentexpenses are allocated to aproduction department based
on the ratio of the allocationbasis used by the productiondepartment
ABC:
Uses activities, foraccumulating costs andredistributing costs
Asks what activities arebeing performed by the
resources of the servicedepartment
Resource expenses areassigned to activities basedon how much of the
resource is required or usedto perform the activities
-
8/2/2019 ABC Final Asb 110211
18/88
Tracing Costs to Activities
Heres how an ABC system works, using
the Cooper Pen Company as an example:
The controller started an analysis of indirectexpenses, beginning with indirect labor
The controller interviewed department heads incharge of indirect labor and found that thepeople in these departments performed threemain activities
-
8/2/2019 ABC Final Asb 110211
19/88
Indirect Labor Activities (1 of 2)
50% of indirect labor was involved in what the
controller called handle production runs Scheduling production orders
Purchasing, preparing, and releasing materials
Inspecting the first few units produced each time the
process was changed to a new-colored pen 40% of indirect labor actually performed the
physical changeover from one color pen toanother, an activity that she labeled perform
setups Change to Black pens takes 2.4 hours
Change to Red or Purple pens takes 5.6 hours
-
8/2/2019 ABC Final Asb 110211
20/88
Indirect Labor Activities (2 of 2)
10% of the time was spent on activities the
controller called support products: maintainingrecords on the four products, such as:
Making up the bill of materials and routing information
Monitoring and maintaining a minimum supply of rawmaterials and finished goods inventory for eachproduct
Improving the production processes
Performing engineering changes for the products
-
8/2/2019 ABC Final Asb 110211
21/88
First Steps in Design of An ABC System
As she conducted the interviews, the controller
was performing the first two steps for designingan activity-based cost system:
1) Develop the activity dictionary: the list of major
activities performed by both the factoryshuman and physical resources
2) Obtain sufficient information to assign resourceexpenses to each activity in the activity
dictionary (50% of indirect labor to handleproduction runs, 40% to perform setups, and
10% to support products)
-
8/2/2019 ABC Final Asb 110211
22/88
Computer System Expenses (1 of 2) The controller next turned her attention to the
$30,000 of expenses needed to operate thecompanys computer system and interviewed the
manager of the data center and the manager ofthe management information system department
20% of computer expenses should be assignedto support products, an activity already
defined in her activity dictionary, because it was
used to keep records on the four products,including:
Production process
Associated engineering change notice information
-
8/2/2019 ABC Final Asb 110211
23/88
Computer System Expenses (2 of 2) About 80% of the computer resource was
involved in the production run activity andseemed to relate well to the handle productionruns activity already defined: Schedule production runs in the factory
Order and pay for the materials required in eachproduction run
Since each production run was made for a particularcustomer, also included in this activity was thecomputer time required to:
Prepare shipping documents Invoice a customer
Collect from a customer
-
8/2/2019 ABC Final Asb 110211
24/88
Other Overhead Expenses There were three remaining categories of
overhead expense: Machine depreciation
Machine maintenance
Energy to operate the machines
These expenses were incurred to supplymachine capacity to produce the pens: A practical capability of 10,000 hours of productive
time could be supplied to pen production
The controller labeled this production activityrun machines
-
8/2/2019 ABC Final Asb 110211
25/88
Identifying Cost Hierarchies The controller noted that even though she had defined
only four activities for Coopers indirect costs, theyrepresented the three different levels of themanufacturing cost hierarchy:
PRODUCT SUSTAININGSUPPORT PRODUCTS
BATCH LEVELSETUP MACHINES
BATCH LEVELHANDLE PRODUCTION RUNSUNIT LEVELRUN MACHINES
COST HIERARCHYACTIVITY
Finding at least one activity for each hierarchy level gaveher confidence that the complexity of the manufacturingprocess could be represented well enough by theactivity-based cost system
-
8/2/2019 ABC Final Asb 110211
26/88
Benefits from Half an ABC System
The ABC model was only half completed (costs
have not yet been driven down to products), yet ithad already provided some important insights:
Now the controller could see why Cooper Pens wasincurring expenditures for resources instead of seeingcategories of expenses
In particular she saw how expensive activities such ashandling production runs and setting up machines were
The ABC model shifted the focus from what themoney was being spent on (labor, equipment,supplies) to what the resources acquired byspending were actually doing
-
8/2/2019 ABC Final Asb 110211
27/88
From ABC to ABM (1 of 2)
In the past, industrial engineers at Cooper Penhad studied labor and materials usage closely:
These had been the high cost resources
They were also the primary cost categories featured by
Coopers traditional cost system The high overhead rate on direct labor seemed to
amplify any benefits from direct labor cost savings thatthe industrial engineers could achieve
-
8/2/2019 ABC Final Asb 110211
28/88
From ABC to ABM (2 of 2)
It would be worthwhile to have industrialengineers study the way Cooper handled andscheduled production runs and how theemployees set up machines to uncover new
opportunities for cost reduction and processimprovement projects
This is an example of operational activity-basedmanagement(ABM), where managers use
information collected by the ABC system at theactivity level to identify opportunities for reducingcosts in indirect and support activities
-
8/2/2019 ABC Final Asb 110211
29/88
Tracing Costs From Activities To Products
The controller next turned her attention tounderstanding the demands for theseactivities by the four different products
By understanding how products useactivities, she would be able to relate thecost of performing activities to individualproducts
-
8/2/2019 ABC Final Asb 110211
30/88
Activity Cost Drivers Activity cost drivers represent the quantity of activities
used to produce individual products The controller identified the following activity cost drivers
for the activities in her activity dictionary:
ACTIVITY ACTIVITY COST DRIVER
HANDLE PRODUCTION RUNS PRODUCTION RUNS
SET UP MACHINES SETUP HOURS
SUPPORT PRODUCTS NUMBER OF PRODUCTS
RUN MACHINES MACHINE HOURS
PROVIDE FRINGE BENEFITS LABOR DOLLARS
-
8/2/2019 ABC Final Asb 110211
31/88
Completing the ABC Model (1 of 2)
Once the activity cost drivers had been
determined, the controller obtainedquantitative information on:
The total quantity of each activity cost driver
The quantity of cost driver used by eachproduct
-
8/2/2019 ABC Final Asb 110211
32/88
Completing the ABC Model (2 of 2)
The controller now had sufficientinformation to estimate a complete activity-based cost model for Cooper Pens factory
She calculated the activity cost driver rate
(ACDR) by dividing the activity expense bythe total quantity of the activity cost driver
She then multiplied the activity cost driver rate
by the quantity of each activity cost driverused by each of the four products
-
8/2/2019 ABC Final Asb 110211
33/88
Activity Cost Drivers
Activity Cost
Driver Blue Black Red Purple Total**
DL hr/unit 0.02 0.02 0.02 0.02 2,000
Mch. hr/unit 0.1 0.1 0.1 0.1 10,000
Prod. runs 70 65 50 15 200
Setup time/run 4 2.4 5.6 5.6 --
Total setup hr 280 156 280 84 800
# of products 1 1 1 1 4
**Total = per unitX quantity 50,000 40,000 9,000 1,000
-
8/2/2019 ABC Final Asb 110211
34/88
Activity Cost Driver Rates (ACDR)
Activity
Expense
Activity Cost
Driver
Driver
Quantity ACDR
HandleProduction Runs
66,000 Number ofproduction runs
200 330 perrun
Set up machines 33,600 Number ofsetup hours
800 42 persetup hr
SupportProducts
14,400 Number ofproducts
4 3,600 perproduct
Run Machines 42,000 Number of
machine hours
10,000 4.20 per
machine hr
156,000
-
8/2/2019 ABC Final Asb 110211
35/88
Activity Expenses Assigned
Blue Black Red Purple Total
HandleProductionRuns
23,100 21,450 16,500 4,950 66,000
Set upmachines
11,760 6,552 11,760 3,528 33,600
SupportProducts
3,600 3,600 3,600 3,600 14,400
Run
Machines
21,000 16,800 3,780 420 42,000
Total CostsAssigned 59,460 48,402 35,640 12,498 156,000
-
8/2/2019 ABC Final Asb 110211
36/88
ABC Profitability Report The controller combined the activity expense analysis for
each product with their direct materials and labor coststo obtain a new ABC profitability report
The results from the activity-based costing system werequite different from the results based on the traditional
cost system The controller now understood why the profitability of
Cooper Pen has deteriorated in recent years: The two specialty products, which the previous cost system had
reported as the most profitable, were in fact the most
unprofitable, and losing lots of money The company had added large quantities of overhead resources
to enable these products to be designed and produced, but theirincremental revenue did not cover those costs
-
8/2/2019 ABC Final Asb 110211
37/88
Total ABC Profitability by Product
Blue Black Red Purple Total
Sales 225,000 180,000 41,850 4,950 451,800Material 75,000 60,000 14,040 1,650 150,690
Labor 30,000 24,000 5,400 600 60,000
40%
fringe onDL
12,000 9,600 2,160 240 24,000
Support 59,460 48,402 35,640 12,498 156,000
Total Mfg.
Expenses
176,460 142,002 57,240 14,988 390,690
GrossMargin
48,540 37,998 (15,390) (10,038) 61,110
G.M. % 21.6% 21.1% -36.8% -202.8% 13.5%
-
8/2/2019 ABC Final Asb 110211
38/88
Using ABC to Improve Profitability (1 of 2)
The ABC information provides managers
with numerous insights about how toincrease the profitability of Cooper Pen:
Increase either their sales volume or prices to
compensate for the large batch and product-sustaining expenses of the red and purple pens
Impose minimum order sizes to eliminate short,unprofitable production runs
Try to increase demand for the highly profitableblack and blue pens, which could generate newrevenues that exceed their incremental costs
-
8/2/2019 ABC Final Asb 110211
39/88
Using ABC to Improve Profitability (2 of 2) Improve processes, particularly the processes
performing batch and product-sustaining activities Manufacturing personnel can redirect their attention: From trying to run their production equipment faster, in
order to improve the performance of unit-level activities
To learning how to reduce setup times, in order toimprove the performance of batch-level activities so thatsmall batches of the specialty products would requirefewer resources to produce and be less expensive
The goal of these ABM actions is to enable the companyto produce the same volume and mix of products withfewer resources This leads to lower costs for producing low-volume, specialty
products, and reduces the pressure to raise prices or imposeminimum order sizes on customers in order to make suchproducts profitable
-
8/2/2019 ABC Final Asb 110211
40/88
Selecting Activity Cost Drivers (1 of 2) Activity cost drivers are the central innovation of activity-
based cost systems They are also the most costly to measure
Particularly the quantity of each activity cost driverused by each product
Accordingly, it is important to understand the issuesinvolved in selecting activity cost drivers
The selection of an activity cost driver reflects asubjective trade-off between accuracy and the cost of
measurement An ABC system with 50 activity cost drivers and 2,000
products would require that 100,000 data elements beestimated
-
8/2/2019 ABC Final Asb 110211
41/88
Selecting Activity Cost Drivers(2 of 2) Because of the large number of potential activity-to-product
linkages, management accountants attempt to economizeon the number of different activity cost drivers
Activities triggered by the same event may all use thesame activity cost driver For example, preparing production orders, scheduling production
runs, performing first part inspections, and moving materials may alluse the number of production runs
ABC system designers choose from three different types ofactivity cost drivers: Transaction
Duration Intensity (direct charging)
The choice of a transaction, duration, or intensity costdriver can occur for almost any activity
-
8/2/2019 ABC Final Asb 110211
42/88
Transaction Drivers Least expensive type of cost driver
Also the least accurate They assume that the same quantity of resources is
required every time an activity is performed For example, a transaction driver such as the number of setups
assumes that all setups take about the same time to perform
For many activities, the variation in the quantity ofresources used by each is small enough that a transactiondriver will be fine for assigning activity expenses to the costobject E.g., all setup times are between 30 and 35 minutes
If the amount of resources required to perform the activityvaries considerably from product to product then moreaccurate and more expensive types of cost drivers shouldbe used E.g., Setup times range from 30 minutes to 6 hours
-
8/2/2019 ABC Final Asb 110211
43/88
Duration Drivers Represent the amount of time required to perform an activity
Should be used when significant variations exist in theamount of activity required for different outputs A transaction driver such as number of setups will overcost the
resources required to set up simple products and undercost theresources required for complex products
More expensive to implement because they require anestimate of time needed each time an activity is performed
The choice between a duration driver and a transactionaldriver is, as always, one of economics: Balancing the benefits of increased accuracy against the costs of
increased measurement
-
8/2/2019 ABC Final Asb 110211
44/88
Intensity Drivers Directly charge for the resources used each time an activity
is performed
A duration driver, such as setup cost per hour, assumesthat all hours are equally costly but does not reflect thehigher costs that may be required on some setups: E.g., extra personnel, more skilled personnel, more expensive
machinery
Activity costs may have to be charged directly to theoutput, based on work orders or other records thataccumulate the activity expenses incurred for that output
Intensity drivers are the most accurate activity cost driversbut the most expensive to implement
Intensity drivers should be used only when the resourcesassociated with performing an activity are both expensiveand variable each time an activity is performed unless themeasurements are inexpensive
-
8/2/2019 ABC Final Asb 110211
45/88
Designing an ABC System (1 of 2)
Sometimes ABC system designers getcarried away with the potential capabilitiesof an activity-based cost system
For product costing and customer costing
purposes, most companies: Limit their activity dictionary to 30 to 50
different activities
Choose activity cost drivers that can beobtained simply and are available within theirorganizations existing information system
-
8/2/2019 ABC Final Asb 110211
46/88
Designing an ABC System (2 of 2)
The goal of an ABC system should be to have
the best cost system -- not the most accurateone
The ABC system designer should balance the
cost of errors resulting from inaccurate estimateswith the cost of measurement
Most of the benefits from a more accurate costsystem can be obtained with simple ABC
systems
M i Th C
-
8/2/2019 ABC Final Asb 110211
47/88
Measuring The CostOf Resource Capacity (1 of 2)
The calculation of activity cost driver rates aresometime based on the capacity actually used
Analysts can obtain a better estimate for the costof resources required to handle each production
run by dividing activity expenses by the practicalcapacity of work the resources could perform
Otherwise, the activity cost driver ratesoverestimate the cost of the activity provided
The cost of unused capacity should not beassigned to products produced or customersserved during a period
M i Th C t
-
8/2/2019 ABC Final Asb 110211
48/88
Measuring The CostOf Resource Capacity (2 of 2)
The activity cost driver rate should reflect theunderlying efficiency of the process: the cost ofresources to handle each production order
This efficiency is measured better by using the
capacity of the resources supplied as thedenominator when calculating activity cost driverrates
Still, the cost of unused capacity should not be
ignored
-
8/2/2019 ABC Final Asb 110211
49/88
Cost of Unused Capacity (1 of 2) The cost of unused capacity remains someones or
some departments responsibility Usually you can assign unused capacity after analyzing
the decision that authorized the level of capacitysupplied
For example, if the capacity was acquired to meet anticipateddemands from a particular customer or a particular marketsegment, then the costs of unused capacity due to lower thanexpected demands can be assigned to the person ororganizational unit responsible for that customer or segment
Such an assignment is done on a lump-sum basis; it willbe treated as a sustaining, not a unit-level, expense.
-
8/2/2019 ABC Final Asb 110211
50/88
Cost of Unused Capacity (2 of 2)
If the unused capacity relates to a particular product line
then the cost of unused capacity is assigned to thatproduct line, where the demand failed to materialize
Unused capacity should not be treated as a general cost,to be shared across all product lines
In making assignment of unused capacity costs, wetrace the costs at the level in the organization wheredecisions are made that affect the supply of capacityresources and the demand for those resources
The lump-sum assignment of unused capacity costsprovides feedback to managers on their supply anddemand decisions
Fi d d V i bl E
-
8/2/2019 ABC Final Asb 110211
51/88
Fixed and Variable Expenses
Most indirect expenses assigned by an ABC
system are committed costs Committed costs become variable via a two-step
procedure:
First, demands for resources change either because ofchanges in the quantity of activities performed orbecause of changes in the efficiency of performingactivities
Second, managers must make decisions to change thesupply of committed resources, either up or down, tomeet the new level of demand for the activitiesperformed by these resources
A ti it i E f C it
-
8/2/2019 ABC Final Asb 110211
52/88
Activity in Excess of Capacity
If activity volumes exceed the capacity of existingresources, the result is Bottlenecks
Shortages
Increased pace of activity
Delays
Poor-quality work Such shortages occur often on machines, but can also
occur in human resources who perform support activities
Facing such shortages, companies typically makecommitted costs variable They relieve the bottleneck by spending more to increase the
supply of resources to perform work
This is why many indirect costs increase over time
Decreased Demand for Resources
-
8/2/2019 ABC Final Asb 110211
53/88
Decreased Demand for Resources Demands for indirect and support resources also can
decline
Consciously through activity-based management Inadvertently through competitive or economy-wide forces that lead
to declines in sales
Should the demands for batch and product-sustaining
resources decrease, few immediate spending reductionswill be noticed
Even for many unit-level resources, such as machines anddirect labor, reduced demands for work does notimmediately lead to spending decreases
The reduced demand for organizational resources lowersthe cost of resources used, but this decrease is offset byan equivalent increase in the cost of unused capacity
M ki C itt d C t
-
8/2/2019 ABC Final Asb 110211
54/88
Making Committed CostsVariable Downward
After unused capacity has been created,committed costs will vary downward if, and onlyif, managers actively reduce the supply ofunused resources
What makes a resource cost variable
downward is not inherent in the nature of theresource
It is a function of management decisions To reduce the demands for the resource
To lower the spending on it
Managers Make Costs Fixed
-
8/2/2019 ABC Final Asb 110211
55/88
Managers Make Costs Fixed (1 of 2)
Organizations often create unused capacity
through activity-based management actions Process improvement
Repricing to modify the product mix
Imposing minimum order sizes on customers
They keep existing resources in place, whendemands for the activities performed by theresources have diminished
They also fail to find new activities that could bedone by the unused resources already in place
Managers Make Costs Fixed
-
8/2/2019 ABC Final Asb 110211
56/88
Managers Make Costs Fixed (2 of 2)
The organization receives no benefits from its activity-based management decisions that reduced the demands
on their resources if capacity is not reduced or redeployed The failure to capture benefits from activity-based
management is not because their costs are fixed The failure occurs because managers are unwilling or unable to
take advantage of the unused capacity they have created by
Spending less on capacity resources Increasing the volume of work processed by the capacity
resources
The cost of these resources is only fixed if managers donot exploit the opportunities from the unused capacity theyhelped to create
Making decisions based solely upon resource usage (theABC system) may not increase profits if managers are notprepared to reduce spending to align resource supply withfuture lower levels of demand
-
8/2/2019 ABC Final Asb 110211
57/88
Problems Implementing ABC (1 of 3)
Several problems arise in practice from thecommon approach to activity-based costing thatassigns many resource expenses to activitiesbased on interviews, surveys, and direct
observation of production and support processes The interview and survey processes are time
consuming and costly
This front-end cost to an ABC analysis is often a
barrier to widespread ABC adoption
P bl I l i ABC
-
8/2/2019 ABC Final Asb 110211
58/88
Problems Implementing ABC (2 of 3)
Inaccuracies and bias may affect the accuracy of cost
driver rates derived from individuals subjectiveestimates of their past or future behavior
Companies must periodically repeat the interviewingand surveying processes if they want to keep their
activity-based cost systems updated High updating cost leads to infrequent updates of
many ABC systems and, eventually, to obsolete costdriver estimates
Adding new activities to the system is also difficult,requiring re-estimates of the relative amount of resourcetime and effort required by the new activity
-
8/2/2019 ABC Final Asb 110211
59/88
Problems Implementing ABC(3 of 3) A more subtle and serious problem arises from the
interview or survey process People estimating how much time they spend on a
list of activities handed to them invariably reportpercentages that add up to 100%
Few individuals report that a significant percentageof their time is idle or unused
Accordingly, the cost driver rates calculatedfrom this process assume that resources are
working at full capacity But operations at capacity are more the
exception than the rule
Time-Driven ABC:
-
8/2/2019 ABC Final Asb 110211
60/88
Time-Driven ABC:An Alternative Approach
Several companies have overcome theseproblems by using a new approach forestimating their ABC models
The insight for the new approach issimple: Most ABC systems use a large number of
transactional cost drivers that assume each
occurrence of the event (a production run, acustomer order, a product to support)consumes the same quantity of resources
Ti D i ABC
-
8/2/2019 ABC Final Asb 110211
61/88
Time-Driven ABC:
This homogeneity assumption provides
the foundation for an alternative approachto estimating cost driver rates. The newapproach requires two new estimates:
The unit cost of supplying capacity, and The consumption of capacity (unit times) by
each activity
Unit Cost Estimate
-
8/2/2019 ABC Final Asb 110211
62/88
Unit Cost Estimate (1 of 3)
The new procedure starts with the same
information used by a traditional ABC approach: The cost of resources that supply capacity and
The practical capacity of the resources supplied
Practical capacity is often estimated as apercentage (e.g., 80% or 85%) of theoreticalcapacity
This estimate allows time (e.g., 15 20%) fornonproductive time:
For personnel, time for breaks, arrival anddeparture, and communication and readingunrelated to actual work performance
U it C t E ti t
-
8/2/2019 ABC Final Asb 110211
63/88
Unit Cost Estimate(2 of 3)
For machines, an allowance for downtime due to
maintenance, repair, and scheduling fluctuations
With estimates of the cost of supplying capacityand practical capacity, the analyst can calculate
the unit cost of supplying capacity:
Unit cost =
Cost of capacity supplied
Practical capacity of resources supplied
U it C t E ti t
-
8/2/2019 ABC Final Asb 110211
64/88
Unit Cost Estimate (3 of 3)
For example, assume that indirect laboremployees supply about 2,500 hours of labor intotal each quarter at a cost of 84,000. Thepractical capacity (at 80% of theoretical) is about
2,000 hours per quarter, leading to a unit cost(per hour) of supplying indirect labor capacity of:
Indirect labor cost per hour =84,000
2000 hours= 42 per hour
Unit Time Estimate
-
8/2/2019 ABC Final Asb 110211
65/88
Unit Time Estimate
The second piece of new information is an estimate of
time used each time a committed resource performs atransactional activity
Precision is not critical
Rough accuracy is sufficient
Estimates for the indirect labor from the Cooper Penexample are:
Resource Activity Unit Time
Indirect Labor Production Run 5 hours
Support Products 50 hours
Cost Driver Rate
-
8/2/2019 ABC Final Asb 110211
66/88
Cost Driver Rate
Assume similar calculations regarding computer
resources produced estimates of 60 per hour and 2hours per production run
The cost driver rate for the activity, handle productionruns, can now be calculated as the costs of usingindirect labor and the computer for each production run:
Unit Cost Unit Time Cost Driver
Indirect Labor Resource 42 per hour 5 hours/run 210 per run
+ Computer Resource 60 per hour 2 hours/run 120 per run
= Activity Cost Driver Rate 330 per run
Advantages of Time Driven ABC
-
8/2/2019 ABC Final Asb 110211
67/88
Advantages of Time-Driven ABC
Managers may easily update their time-driven
ABC model to reflect changes in their operatingconditions
They can incorporate the new knowledge by providingreasonable estimates about the unit times required for
different activities for each type of product Managers may also easily update the activity
cost driver rates
Changes in the prices of resources supplied affect the
hourly cost rate
Activity cost driver rates change when there has beena shift in the efficiency of the activity
Tracing Marketing-Related
-
8/2/2019 ABC Final Asb 110211
68/88
Tracing Marketing RelatedCosts to Customers
The costs of marketing, selling, and distribution expenseshave been increasing rapidly in recent years
Result of increased importance of customer satisfactionand market-oriented strategies
Many of these expenses do not relate to individualproducts or product lines but are associated with:
Individual customers
Market segments
Distribution channels Companies need to understand the cost of selling to and
serving their diverse customer base
Alpha Beta Example (1 of 7)
-
8/2/2019 ABC Final Asb 110211
69/88
Alpha Beta Example (1 of 7) Assume Alpha and Beta are customers generating about
equal revenue and seen as equally valuable customers
Using a conventional cost accounting system, marketing,selling, distribution, and administrative (MSDA) expenseswere allocated to customers at a rate of 35% of Sales
ALPHA BETA
Sales 320,000 315,000CGS 154,000 156,000
Gross Margin 166,000 159,000
MSDA expenses (@35% of Sales) 112,000 110,250
Operating profit 54,000 48,750Profit percentage 16.9% 15.5%
In many respects, however, the customers were not similar
Alpha Beta Example (2 of 7)
-
8/2/2019 ABC Final Asb 110211
70/88
Alpha Beta Example (2 of 7)
Betas account manager spent a huge amount of time
on that account Beta required a great deal of hand-holding and was
continually inquiring whether the company could modifyproducts to meet its specific needs
Betas account required many technical resources, inaddition to marketing resources
Beta also: Tended to place many small orders for special products
Required expedited delivery
Tended to pay slowly
All of which increased the demands on the order processing,invoicing, and accounts receivable process
Alpha Beta Example (3 of 7)
-
8/2/2019 ABC Final Asb 110211
71/88
Alpha Beta Example (3 of 7)
Alpha, on the other hand:
Ordered only a few products and in large quantities Placed its orders predictably and with long lead times
Required little sales and technical support
The Accounting Manager in Marketing knew thatAlpha was a much more profitable customer thanthe financial statements were currently reporting
He launched an activity-based cost study of the
companys marketing, selling, distribution, andadministrative costs
Alpha Beta Example (4 of 7)
-
8/2/2019 ABC Final Asb 110211
72/88
Alpha Beta Example (4 of 7)
The multifunctional project team:
Studied the resource spending of the various accounts Identified the activities performed by the resources
Selected activity cost drivers that could link eachactivity to individual customers
The Accounting Manager used: Transactional activity cost drivers
Number of orders, number of mailings
Duration drivers Estimated time and effort
Intensity drivers when he had readily-available data Actual freight and travel expenses
Alpha Beta Example (5 of 7)
-
8/2/2019 ABC Final Asb 110211
73/88
Alpha Beta Example (5 of 7)
The manager also used a customer cost
hierarchy that was similar to the manufacturingcost hierarchy
Some activities were order-related
Handle customer orders
Ship to customers
Others were customer-sustaining
Service customers
Travel to customers
Provide marketing and technical support
Alpha Beta Example (6 of 7)
-
8/2/2019 ABC Final Asb 110211
74/88
Alpha Beta Example (6 of 7)
The picture of relative profitability of Alpha and Beta
shifted dramatically Alpha BetaGross Margin (as previously) 166,000 159,000
Marketing & tech. support 7,000 54,000
Travel to customer 1,200 7,200
Distribute sales catalog 100 100Service customers 4,000 42,000
Handle customer orders 500 18,000
Warehouse inventory 800 8,800
Ship to customers 12,600 42,000
Total activity expenses 26,200 172,100
Operating profit 139,800 (13,100)
Profit percentage 43.7% (4.2%)
Alpha Beta Example (7 of 7)
-
8/2/2019 ABC Final Asb 110211
75/88
Alpha Beta Example (7 of 7)
As the manager suspected, Alpha Company was
a highly profitable customer Its ordering and support activities placed fewdemands on the companys marketing, selling,distribution, and administrative resources
Almost all the gross margin earned by selling to Alpha
dropped to the operating margin bottom line
Beta Company was now seen to be the mostunprofitable customer that the company had
While the manager intuitively sensed that Alphawas a more profitable customer than Beta, hehad no idea of the magnitude of the difference
ABC Customer Analysis
-
8/2/2019 ABC Final Asb 110211
76/88
ABC Customer Analysis The output from an ABC customer analysis is often
portrayed as a whale curve
A plot of cumulative profitability versus the number ofcustomers
Customers are ranked, on the horizontal axis frommost profitable to least profitable (or most unprofitable)
Customer Profitability
-
8/2/2019 ABC Final Asb 110211
77/88
Customer Profitability Cumulative sales follow the usual 20-80 rule
20% of the customers provide 80% of the sales
A whale curve for cumulative profitability typically reveals: The most profitable 20% of customers generate
between 150% and 300% of total profits
The middle 70% of customers break even
The least profitable 10% of customers lose 50% - 200%of total profits, leaving the company with its 100% oftotal profits
It is not unusual for some of the largest customers to turnout being the most unprofitable
The largest customers are either the companys mostprofitable or its most unprofitable
They are rarely in the middle
Managing Customer Profitability (1 of 3)
-
8/2/2019 ABC Final Asb 110211
78/88
Managing Customer Profitability (1 of 3)
High-profit customers, such as Alpha, appear in
the left section of the profitability whale curve These customers should be cherished and
protected
They could be vulnerable to competitiveinroads
The managers of a company serving themshould be prepared to offer discounts,
incentives, and special services to retain theloyalty of these valuable customers if acompetitor threatens
Managing Customer Profitability (2 of 3)
-
8/2/2019 ABC Final Asb 110211
79/88
Managing Customer Profitability (2 of 3)
The challenging customers, like Beta, appear onthe right tail of the whale curve, dragging thecompanys profitability down with their lowmargins and high cost-to-serve
The high cost of serving such customers can becaused by their:
Unpredictable order pattern Small order quantities for customized
products Nonstandard logistics and delivery
requirements Large demands on technical and sales
personnel
Managing Customer Profitability (3 of 3)
-
8/2/2019 ABC Final Asb 110211
80/88
Managing Customer Profitability (3 of 3)
The opportunities for a company to transform its
unprofitable customers into profitable ones isperhaps the most powerful benefit thecompanys managers can receive from an
activity-based costing system
Managers have a full range of actions fortransforming unprofitable customers intoprofitable ones
Process improvements
Activity-based pricing
Managing customer relationships
Process Improvements
-
8/2/2019 ABC Final Asb 110211
81/88
Process Improvements
Managers should first examine their internal operations
to see where they can improve their own processes tolower the costs of serving customers
If customers are migrating to smaller order sizes:
Strive to reduce batch-related costs, such as setup
and order handling Electronic systems greatly lower the cost of
processing large quantities of small orders
If customers prefer suppliers offering high variety
Try to customize products at the latest possible stage Use information technology to enhance the linkages
from design to manufacturing
Activity-Based Pricing
-
8/2/2019 ABC Final Asb 110211
82/88
ct ty ased c g
Pricing is the most powerful tool a company can
use to transform unprofitable customers intoprofitable ones
Activity-based pricing establishes a base pricefor producing and delivering a standard quantity
for each standard product To this base price, the company provides a menu ofoptions, with associated prices, for any specialservices requested by the customer
Special services may be priced just to covercosts or also to earn a margin
Activity-based pricing prices orders, not products
Managing Relationships
-
8/2/2019 ABC Final Asb 110211
83/88
g g p
Companies can transform unprofitable customers intoprofitable ones by persuading the customer to use agreater scope of the companys products and services
The margins from such increased businesspurchases contribute to covering customer-sustainingcosts
If these efforts fail, the company may then contemplatefiring the customer
Some customers may be unprofitable only because it isthe start of the relationship with the company Companies can afford to be more tolerant of newly-acquired
unprofitable customers than they can of unprofitable customersthey have served for 10 or more years
ABC at Service Companies (1 of 2)
-
8/2/2019 ABC Final Asb 110211
84/88
ABC at Service Companies (1 of 2)
Although ABC had its origins in manufacturing
companies, many service organizations today areobtaining great benefits from this approach
In practice, the actual construction of an ABC model isnearly identical for both types of companies
This should not be surprising since, in manufacturingcompanies, the ABC system focuses on the service
component of the company
ABC at Service Companies (2 of 2)
-
8/2/2019 ABC Final Asb 110211
85/88
ABC at Service Companies (2 of 2)
Service companies in general are ideal
candidates for activity-based costing Virtually all costs are indirect and appear fixed
They often do not have direct, traceable costs toserve as convenient allocation bases
They must supply virtually all their resources inadvance to provide the capacity to perform work forcustomers during each period
Implementation Issues (1 of 2)
-
8/2/2019 ABC Final Asb 110211
86/88
p ( )
Not all ABC systems have been sustained or contributedto higher profitability for the company Some companies have experienced difficulties and frustrations
in building and using activity-based cost and profitability modelsfor some of the following reasons
Lack of clear business purpose
The project may start in Accounting/Finance, and nobodyoutside the department understands what changes need to bemade and why
Lack of senior management commitment The group (usually Accounting/Finance) that initiates the project
probably does not have the authority to make decisions aboutprocesses, product designs, etc., without full senior managementsupport
Implementation Issues (2 of 2)
-
8/2/2019 ABC Final Asb 110211
87/88
p ( ) Delegating the project to consultants
Consultants are usually not familiar enough with the businesss
organization and problems and may not be able to buildmanagement consensus
Poor ABC model design The model may be too complicated to build and maintain and too
complex for managers to understand and act upon
Or the model may use arbitrary allocations that merely createdifferent distortions than the old system
The new data requirements may increase the workload of otherfunctions without increasing the benefits to them
Individual and organizational resistance to change
People may feel threatened by the suggestion that their workmight be improved
Resistance may be overt, but it may be more subtle and passive
-
8/2/2019 ABC Final Asb 110211
88/88
If you have any comments or suggestions concerningthis PowerPoint presentation, please contact:
Rishiraj Dasgupta([email protected])