Kathmandu Sustainable Urban Transport Project (KSUTP)
A Sustainable Transport Project
Status and Progress
September 2016
Present Road Network in Kathmandu Valley
Strategic Road Network including Strategic Urban Road Kathmandu 224 km Lalitpur 188 km Bhaktapur 118 km Total 530 km
Present Public Transport in Kathmandu
200 plus Public Transport routes Many overlaps in the routes 10,000 vehicles comprising of Tempo, micro, mini and buses were issued for route permits Almost all PT funding are from private sectors. including one Public Company (Sajha Yatayat) and one Private company (Mahanagar) Many operators are self employer cum driver types. 100 public transport unions / committees operate the business
Present Public Transport in Kathmandu
s
Present Public Transport in Kathmandu
Public Transports are some time over supply often under supply. 673,000 vkm/day in operation much more than required. The Public Transport System in Kathmandu are not reliable, not fully dependable.
KSUTP
Start date 2011 January Completion 2015 June (extended2017 June) Total cost 26.32 m USD ADB loan 6.9 m USD ADB Grant 9.0 m USD Global Env Fund 2.52 m USD Govt of Nepal 7.4 m USD Kathmandu Met. City 0.5 m USD
Project Components
Project Objectives
Public Transport
Traffic Management
Walkability
Air Quality Monitoring
Project Organisation
Ministry of Physical Infrastructure and Transport Project Management Coordination Office PMCB Consultant : SMEC International JV Project Implementation Units (Five):
• Department of Roads (DOR) • Department of Transport Management (DOTM) • Metropolitan Traffic Police Department (MTPD) • Kathmandu Metropolitan City (KMC) • Department of Environment (DOEnv)
Design Supervision Consultants:
• SIDEF – BEAM JV for KMC works • Soil Test for DOR works Consultant for Mass Transit Study Consultant KSUTP for DOTM works
Transport Enterprenuers / Committes Town Development Fund
Component 1 Public Transport Tasks
Develop Public Transport restructuring policy
GON Approval of policy
Test Policy on 2 Pilot Bus Routes
• Industry-Level agreement with FNNTE
• Establish Operator Negotiating Forum
• Operational & Business Planning
• Fleet Financing mechanism with TDF
• Formation of Bus Operating Companies
• Operating Contract development and negotiation
• Operations and monitoring
Develop DoTM institutional restructuring plan
GON Approval of plan
Establish Public Transport capability within DoTM
Mass Transit Options & prioritisation Study
Completed or no current bottlenecks
Incomplete or partially completed
Requires action
Key
Component 1: Public Transport
Outputs expected:
• Re-structuring of DOTM with creation of a new Public Transport Division
• Restructuring of Public Transport Routes in the Kathmandu Valley
• Selection and Implementation of 2 Pilot Bus Routes
• Transformation of current public transport operators into companies or cooperatives (franchising)
• Purchase of electric or low emission buses through the TDF on the 2 selected pilot routes
• Feasibility Study on the mass transport system in Kathmandu Valley
Fleet rationalisation
• 8 Primary Routes: Requires a fleet of 470 buses, (12-Metre Rigid)
• 16 Secondary Routes: Fleet of 250 buses, 9 to 10 m in length
• 40 Tertiary Routes: Predominately using existing vehicle fleet, with some routes operated by new Electric vehicles
• Vehicle-km reduced by 332,000 per day
• Vehicle Operating Costs reduced by US$ 34 Million per year
• 10% Reduction in road space used (PCU’s)
PRIMARY PUBLIC TRANSPORT ROUTES
Component 2: Traffic Management
Outputs expected:
• Construction of the 2 new bridges at Dallu & Teku. (ICB-02)
• Construction of crossing junction at Teku.
• Construction of the remaining road section of BLR on east bank. (ICB-02)
• Improvements at 35 Junctions. (ICB-03)
• Traffic Signals (37) and Installation of CCTV cameras, traffic lights, equipment and Traffic Management Centre. ITS installation. (ICB-04)
• Launch road users’ awareness programs
Component 3: Walkability Improvements
Outputs expected:
• Improvement of 8 km of preliminary heritage pedestrian routes and 15 Km of sidewalk in the city center. ICB-01
• Construction of 1 new pedestrian bridge and renovation of 2 existing footbridges along BLR. NCB-02
• PPP investigations for car parking and the redevelopment of the Old Bus Park under KMC
Component 4: Air Quality Monitoring
Outputs expected:
• Expedite programs to restore operations at the existing AQM stations with solar-powered backup systems: Completed
• Procurement of 4 new AQM mobile stations completed
• Procurement of 4 sets emissions testing equipment : Completed
Project Status
• Time lapsed 85% • Physical Progress to date: 44% • Financial Progress to date: 38% In general
Component 4 : Air Quality Monitoring satisfactorily completed. Component 3 : Walkway is proceeding satisfactorily Component 2 : Traffic Management some lagging specially in ITS (ICB-04) Some extension required. Component 1: Public Transport is very much lagging behind. S5 route association came to agreement.
Challenges
• Introducing 3 tier route hierarchy
• Reducing the 200 routes in to 66 Routes
• Transforming the Public Transport unions in to Companies
• Replacing the small vehicles by larger vehicles
• Social safeguard of existing operators
• No operational subsidy is planned.
• Many implementation units
• Many activities of low volumes. Many funding components.
• Disturbances due to SAARC occupancy, Melamchi Coordination, Earthquake, Fuel Crisis