A Streamlined Approach to Multi Facility Master Planning with Triple Bottom Line Optimization Vera Gouchev, P.E. January 22, 2018 NEWEA 2018 Annual Conference and Exhibit
Outline
1. Study Goals 2. Current Operations
3. State-of-Good-Repair 4. 5-Year Plan Approach
5. Multi-Facility Planning Tool 6. 25-Year Plan Approach
7. Conclusions and Next Steps 8. Q+A
Westchester County, NY Water Resource Recovery Facilities (WRRFs)
§ 7 WRRFs, 5 to 120 MGD § Discharge effluent to
Hudson River and Long Island Sound
§ Produce 19,700 Dry Tons sludge annually
Study Goals • Perform detailed assessment of current
operations, practices, and equipment • Develop 5-Year and 25-Year plans to mitigate
future risks while balancing County priorities
Westchester County WRRFs: Residual Process Matrix
Facility Thickening Dewatering Digestion
New Rochelle (NR) 21 MGD + Mamaroneck (MM) 23 MGD
Port Chester (PC) 6 MGD + Blind Brook (BB) 5 MGD
Ossining (OS) 7 MGD
Peekskill (PK) 10 MGD
Yonkers Joint (YJ) 120 MGD
Residuals Asset Evaluation
• Developed Capital Plan based on maintaining State of Good Repair (SOGR)
• Evaluated 1,607 residuals assets • SOGR 5-Year Plan = $3.2 million • SOGR 25-Year Plan = $120-150 million
• Of this total, $80-120 million related to digester tank refurbishments at YJ WRRF (may be partially offset by final 25-Year recommendation – will be discussed in upcoming slides)
Evaluation of Current Operations Energy Usage Profile • Hazen’s Energy Efficiency Tool (HEET) used to determine
fraction of power used for solids handling operations across the seven facilities
Evaluation of Current Operations Operating Cost Analysis
Digests + Dewaters
Digests Dewaters
Thickens Thickens
• Range - $191/DT to $650/DT • Average - $241/DT
5-Year Improvement Planning
• Find opportunities for low capital cost improvements
• Reduce liquid sludge volume • Provide foundation for future, larger-
scale improvement projects proposed in the 25-Year plan
Goals
5-Year Improvement Strategy Opportunity for Centralization
• Combine treatment of sludge from four facilities (PK, OS, BB, and PC) at one facility (PK)
• PK selected based on digester capacity and space availability
OS WRRF
PK WRRF Centralized Dewatering
PC WRRF
BB WRRF
WAS Thickened Sludge
Capital Improvements at PK • Build Storage • Enhance Digestion with
Combined Heat and Power and FOG
• Rehab of Decommissioned Dewatering Facility
25-Year Improvement Planning
• Reduce wet mass • Reduce dry mass • Lower unit disposal Costs by achieving
Class A biosolids • Increase biogas production for CHP
Goals
25 Year Plan –Technology Options
Thermal hydrolysis Thermo-chemical pretreatment Utrasonication Oxidation (chemical) Biological pretreatment
Pretreatment Technologies Dewatering Technologies
Post-dewatering Technologies
Energy Recovery
Stabilization Technologies Anaerobic Digestion (AD) HSOW Co-Digestion Acid-Gas Phased AD High Solids AD Temperature Phased AD (TPAD) Pasteurization Neutralizer Process
Belt Filter Press (BFP) Centrifuge Screw Press Rotary Fan Press Electro-Dewatering Geotextile Tube Dewatering
Thermal Drying Gasification (Thermochemical) Pyrolysis (Thermochemical) Plasma-Assisted Thermal Oxidation (Thermochemical) Chemical Drying (for High Quality Fertilizer Production) Composting
Combined Heat and Power Biogas for thermal energy Biogas for biofuels Biogas for pipeline injection
Nutrient Recovery Ammonia Recovery Struvite Crystallization
25 Year Plan – Shortlist Technology Options
Thermal hydrolysis Thermo-chemical pretreatment Utrasonication Oxidation (chemical) Biological pretreatment
Pretreatment Technologies Dewatering Technologies
Post-dewatering Technologies
Energy Recovery
Stabilization Technologies Anaerobic Digestion (AD) HSOW Co-Digestion Acid-Gas Phased AD High Solids AD Temperature Phased AD (TPAD) Pasteurization Neutralizer Process
Belt Filter Press (BFP) Centrifuge Screw Press Rotary Fan Press Electro-Dewatering Geotextile Tube Dewatering
Thermal Drying Gasification (Thermochemical) Pyrolysis (Thermochemical) Plasma-Assisted Thermal Oxidation (Thermochemical) Chemical Drying (for High Quality Fertilizer Production) Composting
Combined Heat and Power Biogas for thermal energy Biogas for biofuels Biogas for pipeline injection
Nutrient Recovery Ammonia Recovery Struvite Crystallization
Triple Bottom Line Results Output
Parameter Dry Tons per Year Processed Total Annual O+M Costs Range Estimated Capital Cost Annual O+M Cost Savings Range Estimated Payback Time Unit Processing Cost $/DT Total Wet Tons per Year Disposed Total Dry Tons per Year Disposed Estimated YJ Ammonia Load from Dewatering Estimated PK Ammonia Load from Dewatering Carbon Footprint Additional FTEs Required Trucks per Day at YJ
Future Risk Mitigation Future Risk
Strategy and Rank
Stabilization Requirements
Loss of Class B Biosolids
Disposal Options
Sustainability Mandates
Nutrients in Dewatering
Recycle
YJ TPAD 1st
++ ++ ++ -
YJ Co-Digestion + PK Central Drying
2nd
++ ++ + 0
YJ Central Hydrolysis
3rd ++ ++ + - -
SustainabilityMandates,(2)LossofClassBBiosolidsDisposalOp;ons,(3)Stabiliza;onRequirements,and(4)FutureNutrientLimits
Sensitivity Analysis – Total Unit Costs
Baseline Class B Disposal Cost
$75/WT
Existing
5-Year Plan (Centralized Dewatering)
25-Year Plan (Centralized Class A Biosolids)
[VALUE]/DT
[VALUE]/DT
$0
$200
$400
[VALUE]/DT
[VALUE]/DT
$0
$200
$400
[VALUE]/DT
[VALUE]/DT
$0 $100 $200 $300 $400
Future Class B Disposal Cost
$150/WT
25 Year Plan Strategy Reduces Wet Mass
Reduces Dry Mass
Lower Unit
Disposal Cost
(Class A)
IncreasesBiogas $
Five Year Plan - PK Central Dewatering + Co-Digestion PK Central Drying YJ Central Hydrolysis YJ Temperature Phased Anaerobic Digestion YJ Co-Digestion YJ + PK Hydrolysis PK Central Drying + YJ Co-Digestion YJ Struvite Recovery *
Reduces Wet Mass
Reduces Dry Mass
Lower Unit Disposal
Cost (Class A)
IncreasesBiogas $
• Transform YJ into a Centralized Class A biosolids facility by converting existing digesters to Temperature Phased Anaerobic Digestion
• Process cake from PK and NR to Class A at YJ
• Covers all seven WRRFs • $30-$45 million
Conclusions
• 5-Year Plan sets up 25-Year Plan
• 25-Year Plan has multiple options with potential to save $100/DT depending on truck traffic/capital/ammonia loading. Class A is KEY. TPAD economics based on reusing YJ digesters.
• Total $45-$67 million
Wet tons