a report to high level construction ltd. a soil ... investigation report... · borehole logs ......
TRANSCRIPT
A REPORT TO HIGH LEVEL CONSTRUCTION LTD.
A SOIL INVESTIGATION FOR RESIDENTIAL DEVELOPMENT
3879 TOWN LINE
CITY OF ORILLIA
REFERENCE NO. 1606-S168
AUGUST 2016 DISTRIBUTION 3 Copies - High Level Construction Ltd. 1 Copy - Soil Engineers Ltd. (Toronto)
Reference No. 1606-S168 ii
TABLE OF CONTENTS
1.0 INTRODUCTION ................................................................................... 1
2.0 SITE AND PROJECT DESCRIPTION .................................................. 2
3.0 FIELD WORK ........................................................................................ 3
4.0 SUBSURFACE CONDITIONS .............................................................. 4
4.1 Topsoil ............................................................................................ 4 4.2 Sand ................................................................................................ 5 4.3 Silty Sand Till ................................................................................. 6 4.4 Sandy Silt Till ................................................................................. 7 4.5 Compaction Characteristics of the Revealed Soils ........................ 9
5.0 GROUNDWATER CONDITIONS ........................................................ 11
6.0 DISCUSSION AND RECOMMENDATIONS ...................................... 13
6.1 Foundations .................................................................................... 15 6.2 Engineered Fill ............................................................................... 16 6.3 Basement and Slab-On-Grade ........................................................ 19 6.4 Underground Services .................................................................... 20 6.5 Backfilling in Trenches and Excavated Areas ............................... 21 6.6 Garages, Driveways, Interlocking Stone Pavement and
Landscaping .................................................................................... 24 6.7 Pavement Design ............................................................................ 25 6.8 Stormwater Management Pond ...................................................... 26 6.9 Soil Parameters ............................................................................... 28 6.10 Excavation ..................................................................................... 28
7.0 LIMITATIONS OF REPORT ................................................................. 30
Reference No. 1606-S168 iii
TABLES
Table 1 - Estimated Water Content for Compaction ........................................ 9
Table 2 - Groundwater Levels ........................................................................... 11
Table 3 - Founding Levels ................................................................................ 15
Table 4 - Pavement Design ............................................................................... 25
Table 5 - Coefficients of Permeability and Infiltration Rates .......................... 27
Table 6 - Soil Parameters .................................................................................. 28
Table 7 - Classification of Soils for Excavation ............................................... 29
DIAGRAM Diagram 1 - Frost Protection Measures (Garage) ............................................. 24
ENCLOSURES Borehole Logs .......................................................................... Figures 1 to 4 Grain Size Distribution Graphs ............................................... Figure 5 Borehole Location Plan .......................................................... Drawing No. 1 Subsurface Profile .................................................................... Drawing No. 2
Reference No. 1606-S168 1
1.0 INTRODUCTION
In accordance with a written authorization dated March 22, 2016 from Mr. David
Meeks, President of High Level Construction Ltd., a soil investigation was carried
out at a property located on the east side of Town Line and south of Millwood Road,
in the City of Orillia, for a proposed residential development.
The purpose of the investigation was to reveal the subsurface conditions and
determine the engineering properties of the disclosed soils for the proposed
development.
The geotechnical findings and resulting recommendations are presented in this
Report.
Reference No. 1606-S168 2
2.0 SITE AND PROJECT DESCRIPTION
City of Orillia is located within the periphery of Lake Simcoe basin where the glacial
till has been partly eroded in places, by glacial Lake Algonquin and filled with
lacustrine silts and clay.
The subject site is almost rectangular in shape, encompasses an area of 27.4 ac
(11.1 ha), having a municipal address of 3879 Town Line, City of Orillia. It is a
wooded area with a dense growth of mature trees. The existing ground surface is
undulated, generally descends to the east, with a maximum grade difference of nearly
12 m between Boreholes 1 and 4.
It is understood that a residential development is planned for this site, with municipal
services, paved access roadways, and a stormwater management pond located at the
northeast corner of the site. Details of the development, however, were not available
at the time this report was prepared.
Reference No. 1606-S168 3
3.0 FIELD WORK
The field work, consisting of drilling 4 boreholes to depths of 6.3 m and 7.8 m, was
performed on July 19, 2016, at the locations shown on the Borehole Location Plan,
Drawing No. 1. Due to the heavy growth of trees, a temporary access was created
through the centre of the site for the drilling program.
The holes were advanced at intervals to the sampling depths by a track-mounted,
continuous-flight power-auger machine equipped for soil sampling. Standard
Penetration Tests, using the procedures described on the enclosed “List of
Abbreviations and Terms”, were performed at the sampling depths. The test results
are recorded as the Standard Penetration Resistance (or ‘N’ values) of the subsoil.
The relative density of the granular strata and the consistency of the cohesive strata
are inferred from the ‘N’ values. Split-spoon samples were recovered for soil
classification and laboratory testing.
Upon completion of drilling, monitoring wells, consisting of 50-mm diameter PVC
pipes were installed in the boreholes for future groundwater monitoring and
hydrogeological study purpose.
The field work was supervised and the findings were recorded by a Geotechnical
Technician.
The elevation at each of the borehole locations was surveyed using hand-held Global
Navigation Satellite System surveying equipment (Trimble Geoexplorer 6000 series)
with an accuracy of 0.1± m.
Reference No. 1606-S168 4
4.0 SUBSURFACE CONDITIONS
Detailed descriptions of the encountered subsurface conditions are presented on the
Borehole Logs, comprising Figures 1 to 4, inclusive. The revealed stratigraphy is
plotted on the Subsurface Profile, Drawing No. 2, and the engineering properties of
the disclosed soils are discussed herein.
This investigation has disclosed that beneath a veneer of topsoil, the site is generally
underlain by strata of silty sand till and sandy silt till, with embedded sand and silt
seams and layers at various depths and locations.
4.1 Topsoil (All Boreholes)
The revealed topsoil is 20 to 25 cm in thickness. It is dark brown in colour, showing
that it contains appreciable amounts of roots and humus. These materials are
unstable and compressible under loads; therefore, the topsoil is considered to be void
of engineering value but can be used for general landscaping purposes.
Due to its humus content, the topsoil will generate an offensive odour under
anaerobic conditions and may produce volatile gases; therefore, it must not be buried
within the building envelope, or deeper than 1.2 m below the finished grade, as it
may have an adverse impact on the environmental well-being of the development.
The topsoil can only be reused in landscaping purpose. A fertility analysis can be
carried out to further assess the suitability of topsoil for re-use as a planting soil or
sodding medium.
Reference No. 1606-S168 5
4.2 Sand (Boreholes 1, 3 and 4)
A layer of sand was encountered beneath the topsoil, extending to depths of 0.7 m
and 1.3 m below ground. Sample examination indicates that it is fine grained in
Boreholes 1 and 3, fine to coarse grained in Borehole 4. The sand is a non-cohesive
material and its sorted structure indicates that it is a glaciolacustrine deposit.
The natural water content of the samples was found to range from 4% to 12%, with a
median of 9%, showing that the sand is in a damp to very moist, generally moist
condition.
The obtained ‘N’ values range from 3 to 6, with a median of 3 blows per 30 cm of
penetration, indicating that the relative density of the sand is very loose, probably
loosened by the weathering process.
Based on the above findings, the following engineering properties of the sand is
deduced:
• Medium frost susceptibility and low soil adfreezing potential.
• High water erodibility under seepage pressure.
• Relatively pervious, with an estimated coefficient of permeability of 10-3 cm/sec,
an average infiltration rate of 50 mm/hr, and runoff coefficients of:
Slope
0% - 2% 0.04
2% - 6% 0.09
6% + 0.13
• A frictional soil, its shear strength is derived from its internal friction angle and
is soil density dependent.
Reference No. 1606-S168 6 • In steep cuts, the sand will slough to its angle of repose, run under seepage
pressure and boil with a piezometric head of 0.4 m.
• A fair pavement-supportive material, with an estimated California Bearing Ratio
(CBR) value of 15%.
• Moderately low corrosivity to buried metal, with an estimated electrical
resistivity of 6000 ohm·cm.
4.3 Silty Sand Till (All Boreholes)
The silty sand till was encountered below the topsoil or sand deposit in the upper to
mid section of the revealed stratigraphy. It consists of a random mixture of soils; the
particle sizes range from clay to gravel, with sand being the dominant fraction. It is
heterogeneous in structure, indicating that it is a glacial deposit. The silty sand till
contains occasional sand and silt seams and layers, cobbles and boulders.
The obtained ‘N’ values range from 3 to 100, with a median of 14 blows per 30 cm of
penetration, showing the sand till is very loose to very dense, being generally
compact. The loose till is restricted to the weathered zone up to a depth of 2.0 m.
The natural water content of the soil samples was determined and the results are
plotted on the Borehole Logs; the values range from 8% to 30%, with a median of
11%, indicating that the till is in a damp to wet, generally moist condition.
Grain size analyses were performed on 2 representative samples of the silty sand till;
the result is plotted on Figure 5.
Based on the above findings, the following engineering properties are deduced:
• Highly frost susceptible and moderately water erodible.
Reference No. 1606-S168 7 • The laminated sand and silt layers are water erodible.
• Relatively low permeability, with an estimated coefficient of permeability of
10-5 cm/sec, an average infiltration rate of 15 mm/hr, and runoff coefficients
of:
Slope
0% - 2% 0.11
2% - 6% 0.16
6% + 0.23
• Frictional soil, its shear strength is primarily derived from internal friction, and
is augmented by cementation. Therefore, its strength is density dependent.
• It will generally be stable in a relatively steep cut; however, prolonged
exposure will allow the sand and silt layers to become saturated, which may
lead to localized sloughing.
• Fair pavement-supportive material, with an estimated CBR value of 10%.
• Moderately low corrosivity to buried metal, with an estimated electrical
resistivity of 5000 ohm·cm.
4.4 Sandy Silt Till (All Boreholes)
The sandy silt till was encountered in the lower zone of the revealed stratigraphy,
extending to the maximum investigated depth of the boreholes. It consists of a
random mixture of particle sizes ranging from clay to gravel, with silt being the
dominant fraction. The soil is heterogeneous in structure, showing it is a glacial
deposit.
Sample examinations disclosed that the till is slightly cemented and display slight to
some cohesion when remoulded, indicating that the clay content varies. The samples
slaked readily when placed in water and, when shaken, the samples displayed a low
Reference No. 1606-S168 8 dilatancy. Occasional sand and silt seams and layers were found in the soil samples,
and some of them were wet.
Hard resistance to augering was encountered, showing that occasional cobbles and
boulders are embedded in the till mantle. The obtained ‘N’ values range from 27 to
100, with a median of 100 blows per 30 cm of penetration, indicating the relative
density of the till deposits is compact to very dense, being generally very dense.
The natural water content of the soil samples was determined and the results are
plotted on the Borehole Logs. The values range from 5% to 14%, with a median of
8%, indicating that the tills are in a damp to moist, generally in a damp condition.
Accordingly, the engineering properties relating to the project are given below:
• Moderately high frost susceptible and moderately water erodible.
• Low permeability, with an estimated coefficient of permeability of
10-6 cm/sec, and runoff coefficients of:
Slope
0% - 2% 0.15
2% - 6% 0.20
6% + 0.28
• Frictional soil, the shear strength is primarily derived from internal friction,
and is augmented by cementation. Therefore, its strength is density dependent.
• It will be stable in relatively steep cuts; however, under prolonged exposure,
localized sheet collapse will likely occur.
• A fair pavement-supportive material, with an estimated CBR value of 8%.
• Moderate low corrosivity to buried metal, with an estimated electrical
resistivity of 5000 ohm·cm.
Reference No. 1606-S168 9
4.5 Compaction Characteristics of the Revealed Soils
The obtainable degree of compaction is primarily dependent on the soil moisture and,
to a lesser extent, on the type of compactor used and the effort applied.
As a general guide, the typical water content values of the revealed soils for Standard
Proctor compaction are presented in Table 1.
Table 1 - Estimated Water Content for Compaction
Soil Type
Determined Natural Water Content (%)
Water Content (%) for Standard Proctor Compaction
100% (optimum) Range for 95% or +
Sand 4 to 12 (median 9) 11 5 to 14
Silty Sand Till 8 to 30 (median 11) 12 6 to 15
Sandy Silt Till 5 to 14 (median 8) 13 8 to 17
Based on the above findings, the in situ soils are generally suitable for a 95% or +
Standard Proctor compaction. A portion of the silty sand till is too wet and will
require aeration prior to structural compaction. The aeration can be effectively
carried out by spreading the wet soil thinly on the ground in the dry, warm weather.
A portion of the sandy silt till is too dry and will require the addition of water for
structural compaction.
The weathered soil must be sorted free of topsoil and rootlets inclusions prior to its
use a structural backfill. The native soils should be compacted using a heavy-weight,
knead-type roller. The thickness of each lift should be limited to 20 cm before
Reference No. 1606-S168 10 compaction or to a suitable thickness assessed by test strips performed by the
equipment which will be used at the time of construction.
When compacting chunks of till, the compactive energy will frequently bridge over
the chunks in the soil and be transmitted laterally into the soil mantle. Therefore, the
lifts of this soil must be limited to 20 cm or less (before compaction). It is difficult to
monitor the lifts of backfill placed in deep trenches; therefore, it is preferable that the
compaction of backfill at depths over 1.0 m below the road subgrade be carried out
on the wet side of the optimum. This would allow a wider latitude of lift thickness.
If the compaction of the soils is carried out with the water content within the range
for 95% Standard Proctor dry density but on the wet side of the optimum, the surface
of the compacted soil mantle will roll under the dynamic compactive load. This is
unsuitable for road construction since each component of the pavement structure is to
be placed under dynamic conditions which will induce the rolling action of the
subgrade surface and cause structural failure of the new pavement. The foundations
or bedding of the sewer and slab-on-grade will be placed on a subgrade which will
not be subjected to impact loads. Therefore, the structurally compacted soil mantle
with the water content on the wet side or dry side of the optimum will provide an
adequate subgrade for the construction.
The presence of boulders will prevent transmission of the compactive energy into the
underlying material to be compacted. If an appreciable amount of boulders over
15 cm in size is mixed with the material, it must either be sorted or must not be used
for structural backfill and/or construction of engineered fill.
Reference No. 1606-S168 11
5.0 GROUNDWATER CONDITIONS
Groundwater seepage encountered in the boreholes during augering was recorded on
the borehole logs. The monitoring wells installed in the boreholes were also checked
for the presence of groundwater on August 5, 2016. The recorded levels are
summarized in Table 2.
Table 2 - Groundwater Levels
BH No. Borehole
Depth (m)
Soil Colour Changes Brown to
Grey
Groundwater Level Upon Completion of
Drilling Measured
Groundwater Level
Depth (m) Depth (m) El. (m) Depth (m) El. (m)
1 6.3 6.3+ 5.9 268.9 1.3 273.5
2 7.8 5.6± Dry Dry 3.1 267.5
3 6.3 4.3± 1.7 265.0 2.6 264.1
4 6.3 4.3± 2.0 260.7 2.3 260.4
As shown above, the stabilized groundwater levels in the monitoring wells were
recorded at depths ranging from 1.3 to 3.1 m below the ground surface, or at
El. 260.4 to 273.5 m. The groundwater level represents wet sand layers within the till
deposit and it will fluctuate with the seasons.
The soil colour changes from brown to grey at depths ranging from 4.3 to 5.6± m
below the prevailing ground surface in Boreholes 2, 3 and 4. The revealed soil in
Borehole 1 remains brown within the investigated depth. The brown colour indicates
that the soils have oxidized.
Reference No. 1606-S168 12 In excavation, the yield of groundwater seepage may be some to moderate and can be
removed by conventional pumping from sumps. Further assessment through
hydrogeological study can confirm the groundwater condition and the appropriate
dewatering method when the excavation depth is determined.
Reference No. 1606-S168 13
6.0 DISCUSSION AND RECOMMENDATIONS
The investigation has disclosed that beneath a veneer of topsoil, the site is underlain
by strata of very loose to very dense, generally compact silty sand till, and compact to
very dense, generally very dense sandy silt till, with embedded very loose sand layers
at various depths and locations.
Groundwater was recorded in three of the boreholes upon completion of drilling. On
August 5, 2016, the groundwater level in the monitoring wells was recorded at depths
ranging from 1.3 to 3.1 m below the ground surface, or at El. 260.4 to 273.5 m.
Percolated water from precipitation trapped in the sand and silt layers may also be
encountered at shallower depths during excavation. The yield of groundwater during
excavation may be some to moderate, which can be removed by conventional
pumping from sumps.
The geotechnical findings which warrant special consideration are presented below:
1. The topsoil, 20 to 25 cm in thickness, must be stripped and removed as it is
unsuitable for engineering applications. Due to its high humus content, it will
generate volatile gases under anaerobic conditions. For the environmental as
well as the geotechnical well-being of the future development, the topsoil
should not be buried under any structure, or deeper than 1.2 m below the
exterior finish grade.
2. The in situ native soils are weathered to depths ranging from 0.7± to 2.0± m
below the prevailing ground surface. The weathered soil is generally loose and
is not suitable for foundation support. The weathered soils can be
subexcavated, assessed and properly recompacted in layers to engineered fill
specifications for footing construction.
Reference No. 1606-S168 14 3. The sound natural soils below the weathered zone are suitable for normal
spread and strip footing for house construction. The footing subgrade must be
inspected by a geotechnical engineer, or a geotechnical technician under the
supervision of a geotechnical engineer, to ensure that its condition is
compatible with the design of the foundation.
4. Where cut and fill is required for site grading, it is generally more economical
to place an engineered fill for normal footing, sewer and road construction.
The placement of engineered fill will include the removal of the weathered
soils before compacting the fill in layers.
5. For slab-on-grade construction, any weathered or loose soils should be
subexcavated, aerated and properly compacted prior to the placement of the
slab. The slab should be constructed on a granular base, 20 cm thick,
consisting of 20-mm Crusher-Run Limestone, or equivalent, compacted to its
maximum Standard Proctor dry density.
6. Perimeter subdrains and dampproofing of the foundation walls will be required
for basement construction. The subdrains should be shielded by a fabric filter
to prevent blockage by silting. Depending on the design elevation of the
basement structure, underfloor subdrains may also be required below the
basement floor; this can be further assessed after the design is finalized or at
the time of basement excavation.
7. A Class ‘B’ bedding is recommended for the design of the underground
services. The bedding material should consist of compacted 20-mm Crusher-
Run Limestone, or equivalent. Where extensive dewatering is required in a
saturated soil subgrade a Class ‘A’ bedding should be considered.
8. Excavation into the tills containing cobbles and boulders may require extra
effort and the use of a heavy-duty backhoe equipped with a rock ripper.
Boulders larger than 15 cm in size are not suitable for structural backfill and/or
the construction of engineering fill.
Reference No. 1606-S168 15 The recommendations appropriate for the project described in Section 2.0 are
presented herein. One must be aware that the subsurface conditions may vary
between boreholes. Should this become apparent during construction, a geotechnical
engineer must be consulted to determine whether the following recommendations
require revision.
6.1 Foundations
Based on the borehole findings, the footings for the proposed structures should be
placed below the weathered soils and onto the sound natural soils. As a general guide
for the design of foundations, the recommended soil bearing pressures and
corresponding suitable founding levels are presented in Table 3.
Table 3 - Founding Levels
BH No.
Recommended Maximum Allowable Soil Pressure (SLS)/ Factored Ultimate Soil Bearing Pressure (ULS) and
Suitable Founding Level
100 kPa (SLS) 160 kPa (ULS)
200 kPa (SLS) 320 kPa (ULS)
400 kPa (SLS) 600 kPa (ULS)
Depth (m) El. (m) Depth (m) El. (m) Depth (m) El. (m)
1 1.0 or + 273.8 or - 2.4 or + 272.4 or - 4.6 or + 270.2
2 1.0 or + 269.6 or - 2.4 or + 268.2 or - 3.2 or + 267.4
3 1.0 or + 265.7 or - - - 2.4 or + 264.3
4 - - 2.0 or + 260.7 or - 2.4 or + 260.3
The recommended soil-bearing pressures incorporate a safety factor of three against
shear failure of the underlying soils. The total and differential settlements of the
footings founded on the sound natural soils are estimated to be 25 mm and 15 mm,
respectively.
Reference No. 1606-S168 16 The footing subgrade must be inspected by a geotechnical engineer, or a geotechnical
technician under the supervision of a geotechnical engineer, to ensure that its
condition is compatible with the design of the foundation.
If groundwater seepage is encountered in the footing excavation, or where the
subgrade of the normal foundations is found to be wet, the subgrade should be
protected by a concrete mud-slab immediately after exposure. This will prevent
construction disturbance and costly rectification.
The foundations exposed to weathering, or in unheated areas, should have at least
1.6 m of earth cover for protection against frost action, or must be properly insulated.
Where earth fill is required for site grading, it is generally more practical and
economical to place engineered fill suitable for a Maximum Soil Pressure of 100 kPa
for normal footing construction. The requirements and procedures for engineered fill
construction are discussed in Section 6.2.
The footings must meet the requirements specified in the latest Ontario Building
Code. As a guide, the structure should be designed to resist an earthquake force
using Site Classification ‘D’ (stiff soils).
6.2 Engineered Fill
Where earth fill is required for site grading, it is generally more economical to place
engineered fill for normal footing, underground services and pavement construction.
The engineering requirements for a certifiable fill for pavement construction,
municipal services, slab-on-grade, and footings designed with a Maximum Allowable
Soil Pressure (SLS) of 100 kPa and a Factored Ultimate Soil Bearing Pressure (ULS)
of 160 kPa are presented below:
Reference No. 1606-S168 17 1. All of the topsoil and organics must be removed, and the subgrade must be
inspected and proof-rolled prior to any fill placement. The weathered soil
must be subexcavated, sorted free of topsoil inclusions and deleterious
materials, if any, aerated and properly compacted in layers.
2. Inorganic soils must be used for backfilling, and they must be uniformly
compacted in lifts 20 cm thick to 98% or + of their maximum Standard Proctor
dry density up to the proposed finished grade and/or slab-on-grade subgrade.
The soil moisture must be properly controlled on the wet side of the optimum.
If the house foundations are to be built soon after the fill placement, the
densification process for the engineered fill must be increased to 100% of the
maximum Standard Proctor compaction.
3. If imported fill is to be used, the hauler is responsible for its environmental
quality and must provide a document to certify that the material is free of
hazardous contaminants.
4. If the engineered fill is to be left over the winter months, adequate earth cover,
or equivalent, must be provided for protection against frost action.
5. The engineered fill must extend over the entire graded area; the engineered fill
envelope and the finished elevations must be clearly and accurately defined in
the field, and they must be precisely documented by qualified surveyors.
Foundations partially on engineered fill must be reinforced by two
15-mm steel reinforcing bars in the footings and upper section of the
foundation walls, or be designed by a structural engineer, to properly distribute
the stress induced by the abrupt differential settlement (estimated to be
15± mm) between the natural soils and engineered fill.
6. The engineered fill must not be placed during the period from late November
to early April, when freezing ambient temperatures occur either persistently or
intermittently. This is to ensure that the fill is free of frozen soils, ice or snow.
Reference No. 1606-S168 18 7. Where the ground is wet due to subsurface water seepage, an appropriate
subdrain scheme must be implemented prior to the fill placement.
8. Where the fill is to be placed on sloping ground steeper than 1 vertical:
3 horizontal, the face of the sloping ground must be flattened to 3 + so that it is
suitable for safe operation of the compactor and the required compaction can
be obtained.
9. The fill operation must be inspected on a full-time basis by a technician under
the direction of a geotechnical engineer.
10. The footing and underground services subgrade must be inspected by the
geotechnical consulting firm that inspected the engineered fill placement. This
is to ensure that the foundations are placed within the engineered fill envelope,
and the integrity of the fill has not been compromised by interim construction,
environmental degradation and/or disturbance by the footing excavation.
11. Any excavation carried out in certified engineered fill must be reported to the
geotechnical consultant who supervised the fill placement in order to
document the locations of the excavation and/or to supervise reinstatement of
the excavated areas to engineered fill status. If construction on the engineered
fill does not commence within a period of 2 years from the date of
certification, the condition of the engineered fill must be assessed for
re-certification.
12. Despite stringent control in the placement of the engineered fill, variations in
soil type and density may occur in the engineered fill. Therefore, the strip
footings and the upper section of the foundation walls constructed on the
engineered fill will require continuous reinforcement with steel bars,
depending on the uniformity of the soils in the engineered fill and the
thickness of the engineered fill underlying the foundations. Should the
footings and/or walls require reinforcement, the required number and size of
reinforcing bars must be assessed by considering the uniformity as well as the
Reference No. 1606-S168 19
thickness of the engineered fill beneath the foundations. In sewer
construction, the engineered fill is considered to have the same structural
proficiency as a natural inorganic soil.
6.3 Basement and Slab-On-Grade
The basement structures should be designed to sustain the lateral earth pressure and
applicable surcharge loads which can be calculated using the soil parameters listed in
Section 6.9.
The subgrade for the slab-on-grade construction must consist of sound natural soils or
properly compacted inorganic earth fill. In preparation of the subgrade, the subgrade
must be inspected and assessed by proof-rolling. The badly weathered soils or any
soft or loose soils should be subexcavated, sorted free of any deleterious material,
aerated and uniformly compacted to 98% or + of its maximum Standard Proctor dry
density. If the deleterious materials cannot be sorted, the soils should be replaced by
properly compacted, organic-free earth fill.
Any new material for raising the grade should consist of organic-free soil compacted
to at least 98% of its maximum Standard Proctor dry density.
If the subgrade has been loosened due to construction traffic, it must be proof-rolled
before placement of the granular base.
The slab should be constructed on a granular base, 20 cm thick, consisting of
20-mm Crusher-Run Limestone, or equivalent, compacted to its maximum Standard
Proctor dry density.
Reference No. 1606-S168 20 A Modulus of Subgrade Reaction of 25 MPa/m can be used for the design of the floor
slab.
Where the subgrade is found to be wet, floor subdrains should be provided and
connected to a positive outlet. A vapour barrier should be placed at the crown level
of the floor subdrains to prevent upfiltration of moisture that may wet the floor. The
necessity to implement these measures can be assessed during construction.
The slab-on-grade in open areas should be designed to tolerate frost heave, and the
grading around the slab-on-grade and building structure must be such that it directs
runoff away from the structures.
6.4 Underground Services
The subgrade for the underground services should consist of sound natural soil or
properly compacted, organic-free earth fill. Where badly weathered or loose soil is
encountered, it should be subexcavated and replaced with bedding material
compacted to at least 95% or + of its Standard Proctor compaction.
A Class ‘B’ bedding is recommended for the underground services construction. The
bedding material should consist of compacted 20-mm Crusher-Run Limestone, or
equivalent, as approved by a geotechnical engineer. Where extensive dewatering is
required in saturated soil subgrade during sewer construction, a Class ‘A’ bedding
should be considered.
In order to prevent pipe floatation when the sewer trench is deluged with water, a soil
cover at least equal in thickness to the diameter of the pipe should be in place at all
times after completion of the pipe installation.
Reference No. 1606-S168 21 Where the sand and/or silt subgrade is encountered, the sewer joints should be leak-
proof, or wrapped with a waterproof membrane. This is to prevent the infiltration of
fines from the subgrade through inadvertent faulty joints. The necessity to implement
these measures can best be determined during sewer construction.
Openings to subdrains and catch basins should be shielded with a fabric filter to
prevent blockage by silting.
Sewer excavation must be sloped at 1 vertical:1 or + horizontal for stability.
Alternatively, a trench box can be used for the construction of the sewer.
For estimation purposes for the anode weight requirements, the electrical resistivity
which has been determined for the disclosed soils can be used. This, however, can be
confirmed by testing the soil along the water main alignment at the time of sewer
construction. Moreover, the anode weight must meet the minimum requirements
specified by York Region and City of Orillia.
6.5 Backfilling in Trenches and Excavated Areas
The on-site inorganic soils are generally suitable to use for trench backfill. The
backfill in the trenches should be compacted to at least 95% of its maximum Standard
Proctor dry density. Aeration of the wet in situ soils may be required for proper
compaction.
The backfill in service trenches should be compacted to at least 95% of its maximum
Standard Proctor dry density. In the zone within 1.0 m below the road subgrade, the
materials should be compacted with the water content 2% to 3% drier than the
optimum, and the compaction should be increased to at least 98% of the respective
maximum Standard Proctor dry density. This is to provide the required stiffness for
Reference No. 1606-S168 22 pavement construction. In the lower zone, the compaction should be carried out on
the wet side of the optimum; this allows a wider latitude of lift thickness. Backfill
below any slab-on-grade that is sensitive to settlement must be compacted to at least
98% of its maximum Standard Proctor dry density.
In normal construction practice, the problem areas of settlement largely occur
adjacent to manholes, catch basins, services crossings, foundation walls and columns.
In areas which are inaccessible to a heavy compactor, imported sand backfill should
be used. Unless compaction of the backfill is carefully performed, the interface of
the native soils and the sand backfill will have to be flooded for a period of several
days.
The narrow trenches for services crossings should be cut at 1 vertical:
2 or + horizontal so that the backfill can be effectively compacted. Otherwise, soil
arching will prevent the achievement of proper compaction. The lift of each backfill
layer should either be limited to a thickness of 20 cm, or the thickness should be
determined by test strips.
One must be aware of the possible consequences during trench backfilling and
exercise caution as described below:
• When construction is carried out in freezing winter weather, allowance should
be made for these following conditions. Despite stringent backfill monitoring,
frozen soil layers may inadvertently be mixed with the structural trench
backfill. Should the in situ soil have a water content on the dry side of the
optimum, it would be impossible to wet the soil due to the freezing condition,
rendering difficulties in obtaining uniform and proper compaction.
Furthermore, the freezing condition will prevent flooding of the backfill when
it is required, such as in a narrow vertical trench section, or when the trench
Reference No. 1606-S168 23
box is removed. The above will invariably cause backfill settlement that may
become evident within 1 to several years, depending on the depth of the trench
which has been backfilled.
• In areas where the underground services construction is carried out during the
winter months, prolonged exposure of the trench walls will result in frost
heave within the soil mantle of the walls. This may result in some settlement
as the frost recedes, and repair costs will be incurred prior to final surfacing of
the new pavement and the slab-on-grade.
• To backfill a deep trench, one must be aware that future settlement is to be
expected, unless the side of the cut is flattened to at least 1 vertical:
1.5+ horizontal, and the lifts of the fill and its moisture content are stringently
controlled; i.e., lifts should be no more than 20 cm (or less if the backfilling
conditions dictate) and uniformly compacted to achieve at least 95% of the
maximum Standard Proctor dry density, with the moisture content on the wet
side of the optimum.
• It is often difficult to achieve uniform compaction of the backfill in the lower
vertical section of a trench which is an open cut or is stabilized by a trench
box, particularly in the sector close to the trench walls or the sides of the box.
These sectors must be backfilled with sand. In a trench stabilized by a trench
box, the void left after the removal of the box will be filled by the backfill. It
is necessary to backfill this sector with sand, and the compacted backfill must
be flooded for 1 day, prior to the placement of the backfill above this sector,
i.e., in the upper sloped trench section. This measure is necessary in order to
prevent consolidation of inadvertent voids and loose backfill which will
compromise the compaction of the backfill in the upper section. In areas
where groundwater movement is expected in the sand fill mantle, anti-seepage
collars should be provided.
Reference No. 1606-S168 24
6.6 Garages, Driveways, Interlocking Stone Pavement and Landscaping
The driveways at the entrances to the garages can be backfilled with non-frost-
susceptible granular material, with a frost taper at a slope of 1 vertical:1 horizontal.
The recommended scheme is illustrated in Diagram 1.
Diagram 1 - Frost Protection Measures (Garage)
Interlocking stone pavement, slab-on-grade and landscaping structures in areas which
are sensitive to frost-induced ground movement, such as in front of building
entrances, must be constructed on a free-draining, non-frost-susceptible granular
material such as Granular ‘B’. This material must extend to at least 0.3 to 1.2 m
below the slab or pavement surface, depending on the degree of tolerance of ground
movement, and be provided with positive drainage, such as weeper subdrains
connected to manholes or catch basins. Alternatively, the landscaping structures,
slab-on-grade and interlocking stone pavement should be properly insulated with
50-mm Styrofoam, or equivalent.
The grading around structures must be such that it directs runoff away from the
structures.
Reference No. 1606-S168 25
6.7 Pavement Design
The recommended pavement design for the access roads and driveways is presented
in Table 4.
Table 4 - Pavement Design
Course Thickness (mm) OPS Specifications
Asphalt Surface 40 HL-3
Asphalt Binder 60 HL-8
Granular Base 150 OPSS Granular ‘A’ or equivalent
Granular Sub-base Local Collector
350 450
OPSS Granular ‘B’ or equivalent
In preparation of the pavement subgrade, topsoil must be removed and final subgrade
must be proof-rolled. Any soft spots, as identified, should be subexcavated, sorted
free of any concentrated topsoil, if encountered, aerated and properly compacted or
replaced with uniformly compacted inorganic earth fill.
The granular bases should be compacted to their maximum Standard Proctor dry
density.
In the zone within 1.0 m below the pavement subgrade, the backfill should be
compacted to at least 98% of its maximum Standard Proctor dry density, with the
water content at 2% to 3% drier than the optimum. In the lower zone, a 95% or +
Standard Proctor compaction is considered adequate.
Reference No. 1606-S168 26 The subgrade will suffer a strength regression if water is allowed to saturate the
mantle. The following measures should, therefore, be incorporated in the
construction procedures and road design:
• If the road construction does not immediately follow the trench backfilling, the
subgrade should be properly crowned and smooth-rolled to allow interim
precipitation to be properly drained.
• Lot areas adjacent to the roads should be properly graded to prevent ponding of
large amounts of water. Otherwise, the water will seep into the subgrade mantle
and induce a regression of the subgrade strength with costly consequences for
the pavement construction.
• Curb subdrains will be required on both sides of the roadway. The subdrains
should consist of filter-sleeved weepers to prevent blockage by silting.
• If the pavement is to be constructed during wet seasons and extensively soft
subgrade occurs, the granular sub-base should be thickened in order to
compensate for the inadequate strength of the subgrade. This can be assessed
during construction.
6.8 Stormwater Management Pond
A detailed design of the Stormwater Management Pond (SWM) pond, was not
available at the time of report preparation. Based on the Conceptual Development
Plan prepared by MHBC Planning Urban Design & Landscape Architecture, it is
understood that a SWM pond is proposed at the northeast corner of the property at the
vicinity of Borehole 4, where the soil stratigraphy consists of silty sand till and sandy
silt till material with a trace to some clay and a trace of gravel. Groundwater was
recorded at a depth of 2.3 m below the prevailing ground surface in this borehole, on
August 5, 2016.
Reference No. 1606-S168 27 Depending on the design grades, the pond will likely be constructed by excavating
into the till strata. Where the sides or bottom of the pond consist of significant strata
of sand and silt, an impermeable geosynthetic membrane or a clay liner should be
provided as a water barrier. The thickness of the clay liner or surchange above the
geosysthetic membrane should also be capable to overcome the hydrostatic pressure
at the bottom of the liner as recorded in the monitoring wells. The clay liner should
be compacted to 98% of its maximum Standard Proctor dry density.
The coefficients of permeability and the recommended infiltration rates for the design
of the pond are presented in Table 5.
Table 5 - Coefficients of Permeability and Infiltration Rates
Soil Coefficient of Permeability (cm/sec) Percolation Time (min/cm)
Silty Sand Till 10-5 15±
Sandy Silt Till 10-6 10±
The estimated infiltration rates are based on the grain size distribution of soil samples
and are provided for reference only. In situ infiltration tests can be carried out to
verify the above estimation.
The sides of the pond should be sloped at 1 vertical:4 or + horizontal below the wet
perimeter and should be 1 vertical:3 or + horizontal in dry areas. All slopes must be
vegetated and/or sodded to prevent runoff erosion.
For berm construction, the topsoil must be removed and the subgrade must be proof-
rolled. Inorganic soil material consisting of silty clay must be used and compacted to
at least 95% of its maximum Standard Proctor dry density. Berm shall be designed
with a minimum top width of 2.0 m with a 3:1 maximum side slope on the outside.
Reference No. 1606-S168 28 The core of the berm shall be constructed with engineered fill on the basis of the
recommendation in Section of 6.2 of this report.
The soil bearing capacity given in Section 6.1 can be used for the design of
foundations for the control structures. The footings must be placed below the
scouring depths and be provided with a minimum earth cover of 1.6 m for protection
against frost damage. The inlet and outlet of the pond must be lined with gabion
mats for protection against scouring.
6.9 Soil Parameters
The recommended soil parameters for the project design are given in Table 6.
Table 6 - Soil Parameters
Unit Weight and Bulk Factor Unit Weight
(kN/m3)
Estimated
Bulk Factor
Bulk Submerged Loose Compacted
Sand 20.5 10.5 1.20 1.00
Silty Sand Till/ Sandy Silt Till 22.5 12.5 1.33 1.05
Lateral Earth Pressure Coefficients
Active Ka
At Rest K0
Passive Kp
Compacted Earth Fill/Sand 0.40 0.52 2.00
Silty Sand Till/Sandy Silt Till 0.33 0.48 3.00
6.10 Excavation
Excavation should be carried out in accordance with Ontario Regulation 213/91.
Reference No. 1606-S168 29 Excavations in excess of 1.2 m should be sloped at 1 vertical:1 or + horizontal for
stability. For excavation purposes, the types of soils are classified in Table 7.
Table 7 - Classification of Soils for Excavation
Material Type
Sound natural Tills 2
Weathered Soils, Earth Fill and drained Sand 3
In excavations, the groundwater yield from the native till deposits will be some to
moderate, which can be collected to a sump pump and removed by conventional
pumping.
The appropriate method of dewatering should be determined by further assessment of
hydrogeological study.
The tills contain occasional cobbles and boulders. Extra effort and a properly
equipped backhoe will be required for excavation. Boulders larger than 15 cm in size
are not suitable for structural backfill and/or construction of engineered fill.
Prospective contractors must assess the in situ subsurface conditions prior to
excavation by digging test pits to at least 0.5 m below the invert elevation. These test
pits should be allowed to remain open for a period of at least 4 hours to assess the
trenching conditions.
LIST OF ABBREVIATIONS AND DESCRIPTION OF TERMS The abbreviations and terms commonly employed on the borehole logs and figures, and in the text of the report, are as follows: SAMPLE TYPES
AS Auger sample CS Chunk sample DO Drive open (split spoon) DS Denison type sample FS Foil sample RC Rock core (with size and percentage
recovery) ST Slotted tube TO Thin-walled, open TP Thin-walled, piston WS Wash sample PENETRATION RESISTANCE
Dynamic Cone Penetration Resistance:
A continuous profile showing the number of blows for each foot of penetration of a 2-inch diameter, 90° point cone driven by a 140-pound hammer falling 30 inches. Plotted as ‘ • ’
Standard Penetration Resistance or ‘N’ Value:
The number of blows of a 140-pound hammer falling 30 inches required to advance a 2-inch O.D. drive open sampler one foot into undisturbed soil. Plotted as ‘’
WH Sampler advanced by static weight PH Sampler advanced by hydraulic pressure PM Sampler advanced by manual pressure NP No penetration
SOIL DESCRIPTION
Cohesionless Soils:
‘N’ (blows/ft) Relative Density
0 to 4 very loose 4 to 10 loose
10 to 30 compact 30 to 50 dense
over 50 very dense
Cohesive Soils:
Undrained Shear Strength (ksf) ‘N’ (blows/ft) Consistency
less than 0.25 0 to 2 very soft 0.25 to 0.50 2 to 4 soft 0.50 to 1.0 4 to 8 firm 1.0 to 2.0 8 to 16 stiff 2.0 to 4.0 16 to 32 very stiff
over 4.0 over 32 hard
Method of Determination of Undrained Shear Strength of Cohesive Soils:
x 0.0 Field vane test in borehole; the number denotes the sensitivity to remoulding
Laboratory vane test
Compression test in laboratory
For a saturated cohesive soil, the undrained shear strength is taken as one half of the undrained compressive strength
METRIC CONVERSION FACTORS 1 ft = 0.3048 metres 1 inch = 25.4 mm 1lb = 0.454 kg 1ksf = 47.88 kPa
W.L
. @
El.2
73
.5 m
on
Au
gu
st 5
, 2
01
6
W.L
. @
El. 2
68
.9 m
up
on
co
mp
letio
n o
f d
rilli
ng
Job Number: 1606-S168
Ground Surface
SAMPLES Atterberg Limits
PL LL
Figure No.:
Method of Boring: Flight-Auger
Drilling Date: July 19, 2016
LOG OF BOREHOLE NO.: 1
Job Location: 3879 Town Line, City of Orillia
Project Description: Proposed Residential Development
SOIL ENGINEERS LTD.1 of 1Page:
W.L
. @
El. 2
67
.5 m
on
Au
gu
st 5
, 2
01
6
Dry
up
on
co
mp
letio
n o
f d
rilli
ng
Job Number: 1606-S168
Ground Surface
SAMPLES Atterberg Limits
PL LL
Figure No.:
Method of Boring: Flight-Auger
Drilling Date: July 19, 2016
LOG OF BOREHOLE NO.: 2
Job Location: 3879 Town Line, City of Orillia
Project Description: Proposed Residential Development
SOIL ENGINEERS LTD.1 of 1Page:
W.L
. @
El. 2
64
.1 m
on
Au
gu
st 5
, 2
01
6
W.L
. @
El. 2
65
.0 m
up
on
co
mp
letio
n o
f d
rilli
ng
Job Number: 1606-S168
Ground Surface
SAMPLES Atterberg Limits
PL LL
Figure No.:
Method of Boring: Flight-Auger
Drilling Date: July 19, 2016
LOG OF BOREHOLE NO.: 3
Job Location: 3879 Town Line, City of Orillia
Project Description: Proposed Residential Development
SOIL ENGINEERS LTD.1 of 1Page:
W.L
. @
El. 2
60
.4 m
on
Au
gu
st 5
, 2
01
6
W.L
. @
El. 2
60
.7 m
up
on
co
mp
letio
n o
f d
rilli
ng
Job Number: 1606-S168
Ground Surface
SAMPLES Atterberg Limits
PL LL
Figure No.:
Method of Boring: Flight-Auger
Drilling Date: July 19, 2016
LOG OF BOREHOLE NO.: 4
Job Location: 3879 Town Line, City of Orillia
Project Description: Proposed Residential Development
SOIL ENGINEERS LTD.1 of 1Page:
Reference No: 1606-S168
U.S. BUREAU OF SOILS CLASSIFICATION
COARSE
UNIFIED SOIL CLASSIFICATION
COARSE
Project: Residential Development BH./Sa. 2/4 4/5Location: 38796 Town Line, City of Orillia Liquid Limit (%) = - -
Plastic Limit (%) = - -Borehole No: 2 4 Plasticity Index (%) = - -Sample No: 4 5 Moisture Content (%) = 10 8Depth (m): 2.5 3.2 Estimated Permeability Elevation (m): 268.1 259.5 (cm./sec.) = 10-5 10-5
Classification of Sample [& Group Symbol]: SAND, Tilltrs. of clay and gravel
SILT & CLAY
Figure: 5
COARSE
MEDIUM
FINE
CLAY
SAND
MEDIUMFINE
GRAVEL
GRAIN SIZE DISTRIBUTION
SAND
V. FINE
GRAVELSILT
COARSE FINEFINE
3" 2-1/2" 2" 1-1/2" 1" 3/4" 1/2" 3/8" 4 8 10 16 20 30 40 50 60 100 140 200 270 325
0
10
20
30
40
50
60
70
80
90
100
0.0010.010.1110100
Perc
ent P
assi
ng
Grain Size in millimeters
BH.4/Sa.5
BH.2/Sa.4
255
273
271
269
267
265
263
261
259
257
255
4
13
14
24
27
100
100
3
14
14
32
100
100
100
100
3
11
14
100
100
100
100
3
6
5
54
100
100
100
1274.8
2270.6
3266.7
4262.7
Soil Engineers Ltd.CONSULTING ENGINEERSGEOTECHNICAL | ENVIRONMENTAL | HYDROGEOLOGICAL | BUILDING SCIENCE
BH No.El.
WL (STABILIZED)
Legend
TOPSOIL SAND SILTY SAND TILL SANDY SILT TILL
Job Number:
Job Location:
Project Description:
1606-S168
3879 Town Line, City of Orillia
Proposed Residential Development
Report Date: August 2016