A Presentation by ECL

Issues related to Technology & Spares Management

20th January, 2015

Page 2: A Presentation by ECL Issues related to Technology & Spares Management 20 th January, 2015

Production built-up Program of ECL

ECL’s share in 1 billion te coal by CIL in 2019-20 is 62 million te.

YearCoal Prod

(MT)Abs. Grwth.

(MT)% Grwth

2013-14 36.05

2014-15 (Plan) 38.00

2015-16 (Proj) 42.03 4.03 10.60%

2016-17 (Proj) 46.94 4.91 11.68%

2017-18 (Proj) 51.68 4.74 10.10%

2018-19 (Proj) 56.56 4.88 9.44%

2019-20 (Proj) 62.00 5.44 9.62%

Page 3: A Presentation by ECL Issues related to Technology & Spares Management 20 th January, 2015

Technology Requirement for UG Production

Intermediate Technology Existing 2015-16 2016-17 2017-18 2018-19 2019-20

Low Height 17 3 2 - 8 2

Standard Height 202 22 91 21 - 26

Standard Height (1.5 cum) 17 - 15 - - -

Standard Height (3.0 cum) 7 2 - 2 1 2

Low Height 1 - - - - -

SDL

LHD

Page 4: A Presentation by ECL Issues related to Technology & Spares Management 20 th January, 2015

Technology Requirement for UG Production

Mass Production Technology Existing 2015-16 2016-17 2017-18 2018-19 2019-20

Requirement of Std. Ht. CM 3 - - - 1 2

Requirement of Low Ht. CM - - 2 1 - -

Requirement of PSLW - 1 - - - 1

(b) Powered Support LW

(a) Cotinuous Miner Package (1 CM + 2 Shuttle Car + 1 LHD + Roof Bolter etc)

Page 5: A Presentation by ECL Issues related to Technology & Spares Management 20 th January, 2015

Technological Issues for increasing UG Production

Sl. No Issues Description Benefits

1

Increasing working height of CM

At present, CM is permitted to extract seams up to 4.5 Mts. It should be increased to extract coal seams of more than 4.5 Mts - preferably up to 6.0 Mts; maximum upto 8m, in single lift

Increase in % extraction of coal for higher production & productivity

Single stage extraction by CM (i.e., only development by Room & Pillar method)

Practised in other countries like South Africa & USA

Low gestation period, Better % recovery

2Use of diesel operated machine in gassy mines of higher degree

Restriction in use of Diesel operated RAM -CAR/ SHUTTLE CAR in gassy mines of Degree -II & Degree -III for coal transport

Higher Productivity and scale of Production

Restriction in use of Diesel Operated Multi purpose Free Steered vehicle for man & material transport in gassy mines of Degree-II & Degree-III

Reduced travel time will improve effective working hour and hence, productivity

Page 6: A Presentation by ECL Issues related to Technology & Spares Management 20 th January, 2015

Technological Issues for increasing UG Production

Sl. No Issues Description Benefits

3 Thick seam mining by Longwall method

Non availability of Top Coal Caving Equipment for thick seam Long wall Mining

Increase in % extraction of coal for very high scale of production

4 High speed stowing/ void filling technology

Coal extraction rate in depillaring panels is restricted due to unavailability of high speed Stowing Technique

Extraction of seams below water-logged and heavily built-up areas at increased rate

5 High speed drivage of incline i.e., Speed > 80 m per month

Gestation period will reduce; early start of coal production; continuous coal evacuation through belt.

6 High speed Shaft Sinking & Deepening

High speed Shaft Sinking & Deepening

Fast access to deeper/ lower virgin seams

Page 7: A Presentation by ECL Issues related to Technology & Spares Management 20 th January, 2015

Technology/HEMM requirement for OC Production

Sl.No

Equipment Description

2015-16 2016-17 2017-18 2018-19 2019-20

(No) (No) (No) (No) (No)

I ER SHOVEL 1 20 m3 - - 2 3 -2 10 m3 1 4 1 0 -3 4.6/5 m3 1 - - - 1

II HYD SHOVEL 1 10 m3 & above - 3 - - -2 4.5-5.5 m3 - - - 2 -3 2.7-4.2 m3 4 2 3 3 24 1-2 m3 4 1 - - -

III DUMPERS 1 170T/190T - 18 - - -2 100T 4 3 8 3 53 50T/60T 7 - 4 5 -4 35T/40T 14 13 21 3 37

IV CR DOZER 1 410HP 4 0 4 1 62 320HP 4 0 8 5 3

Page 8: A Presentation by ECL Issues related to Technology & Spares Management 20 th January, 2015

Technology/HEMM requirement for OC Production

Sl.No

 Equipment Description

2015-16 2016-17 2017-18 2018-19 2019-20

(No) (No) (No) (No) (No)

V W DOZER 

1 410HP 1- - - -

VI RBH DRILL 

1 250mm 1 - 0 -  2

2 160 mm 10 3 3 1 4

VII GRADER

1 280 HP 1 - 2 2 2

VIII CRANES

1 More than 40T- - -

3 -

IX WATER SPRINKLER

1 28Kl 2- -

2 -

Page 9: A Presentation by ECL Issues related to Technology & Spares Management 20 th January, 2015

Issues with Equipment manufacturing Cos.

BEML Performance of dozers and 35T dumpers requires improvement Frequent problem being faced with newly supplied D155 &

D355 Dozers with Joy stick arrangement.

Failure to supply spare parts within delivery time stipulated in Depot Agreement.  

Issue: To improve the quality of newly supplied equipment and ensure supply of spare parts within delivery time. 

L&T Performance of recently supplied hydraulic shovel It has gone down because of failures of major assemblies like

cracking of boom, final drive failures, fast wearing of bucket assy., hoses etc. 

HEC Performance of recently supplied 5 cum electric rope shovel, model EKG 5A

It is not upto the mark. There are number of failures of major sub-assemblies.

HEC is also not supplying spares against Guaranteed Availability Contract in time.

Page 10: A Presentation by ECL Issues related to Technology & Spares Management 20 th January, 2015

Issues with Equipment manufacturing Cos.

Caterpillar Since it has taken over BE, they have to take care of supply of spare parts of Dragline and Electric rope shovel of Marion and BE making respectively.

Joy Global Presently the Company takes 6 months to 9 year to supply spare parts after LCLong supply time : This hampers the availability of high capacity equipment like 10 Cum & 20 Cum electric rope shovel. Should make arrangement to supply spares within 3 to 4 months time.  

Not supplying PLC & SLC system components and spares for 20 cum rope shovel deployed in Rajmahal whereas they are supposed to support ECL for supplying these spares for whole life of the equipment. This is going to affect availability of 20 cum shovel, the main digging equipment at Rajmahal OCP.  

To rationalize price of Spares: The Company increases the price of spares at their will. This should be rationalized as per market trends.

Page 11: A Presentation by ECL Issues related to Technology & Spares Management 20 th January, 2015

Issues of Technology upgradation

Technology upgradation: Present Status Issues to be addressed  

(a) Higher capacity and technologically advanced equipment: being procured. (100 T dumpers have replaced 85T Dumpers & 190T dumpers have been proposed as replacement of 170T Dumpers)

(b) Equipment with self-diagnostic tools: being procured.(e.g., Vehicle Health Monitoring System, Payload Monitoring System, etc. which provide data to analyze and improve mine efficiency, reduce failure and improve maintenance practices.)

(c) HEMM with more safety and comfort features: being procured.(e.g., AC cabin, proximity warning device, rear vision camera etc. for safety & productivity of the operator and the equipment.) 

Proximity Warning Device in dumpers presently provides an audio- visual warning to the operator when it detects objects in front or rear of the dumper up to 8 meters from the sensor mounting. This should be enhanced to at least 25 to 30 meters.

Tail Gate Protection system in dumpers is not full proof. It has to be redesigned by the OEMs in consultation with DGMS.

Page 12: A Presentation by ECL Issues related to Technology & Spares Management 20 th January, 2015

Issues related to Maintenance & Spares Management

Maintenance and Spare Parts Management: Present Status

 

Issue to be addressed

(a) Equipment Procurement in ECL is with one year warranty followed by two years guaranteed availability. to ensure that the bidder (both global & domestic) has sufficient service support & spares backup to ensure high availability of newly procured equipment to ensure smooth availability of spares to have sufficient time for finalizing spares procurement process (RC or Depot Agreement ) in case of new equipment model. (b) Depot Agreement: ECL is having depot agreement with all major OEMs to ensure smooth supply of spares.

Consignment Store concept for prompt supply of quality spares with zero inventory (like BEML consignment store at Rajmahal Area) - May be considered for other High Producing Areas or at some central location for a group of smaller Areas, by BEML and other major suppliers.  

Page 13: A Presentation by ECL Issues related to Technology & Spares Management 20 th January, 2015

Issues of Technology upgradation

1.Extensive use of Surface Miner & Ripper especially near habitation & near to sensitive structures.

2. OB disposal through belt after sizing.

3. Transport of coal through tube conveyors.

4. Use of highwall technology wherever possible/feasible.