a gentle introduction to earned value management systems (neutral)
Post on 19-Oct-2014
10.530 views
DESCRIPTION
TRANSCRIPT
![Page 1: A gentle introduction to earned value management systems (neutral)](https://reader034.vdocuments.us/reader034/viewer/2022051411/54441cdaafaf9f550d8b47d7/html5/thumbnails/1.jpg)
A GENTLE INTRODUCTION TO
EARNED VALUE
MANAGEMENT SYSTEMS
“Good metrics let us see if we are doing the right things and doing them well."
1/31
Glen B. Alleman
![Page 2: A gentle introduction to earned value management systems (neutral)](https://reader034.vdocuments.us/reader034/viewer/2022051411/54441cdaafaf9f550d8b47d7/html5/thumbnails/2.jpg)
What Do Project Managers Need to Know to Be
Successful?
Is the project on schedule?
Is the project on budget?
How much will this project cost on the end date?
What is the end date for this project?
Simple project analysis tools can answer these questions using time and cost tracking
How much is it costing us to earn each unit of value
– $1.00 spent returns $X.00 of value?
– How much of the budget “should have been” spent at this point in the project?
– How much “value” has the work on the project “earned” so far?
2/31
![Page 3: A gentle introduction to earned value management systems (neutral)](https://reader034.vdocuments.us/reader034/viewer/2022051411/54441cdaafaf9f550d8b47d7/html5/thumbnails/3.jpg)
What Is Earned Value Analysis?
It is a way to measure the amount of work actually
performed on a project.
It is a way to forecast a project’s cost and
completion date using historical and statistical
projections.
It is a way to tell how well a project is
“performing” compared to its original plan.
Given this information it is a way to forecast how
well the project will perform in the future.
3/31
![Page 4: A gentle introduction to earned value management systems (neutral)](https://reader034.vdocuments.us/reader034/viewer/2022051411/54441cdaafaf9f550d8b47d7/html5/thumbnails/4.jpg)
Some Introductory Definitions
In (olde) and (current )notation4/31
Budgeted Cost of Work Scheduled (BCWS)(PC)
“The Planned Cost”
– This is the total budgeted cost. It answers the question “how much do we plan to spend?” A second question that is answered is “How much work should be been completed by this date?”
Budgeted Cost of Work Performed (BCWP)(PV)
“Earned Value”
– This is the cost originally budgeted to accomplish the work that has been completed. It answers the question “how much work has been actually completed?”
Actual Cost of Work Performed (ACWP)(AC)
“The Investment Cost”
– The actual cost to accomplish all the work that was performed by a specific date. It answers the question “how much did we actually spend to deliver the Earned Value?”
![Page 5: A gentle introduction to earned value management systems (neutral)](https://reader034.vdocuments.us/reader034/viewer/2022051411/54441cdaafaf9f550d8b47d7/html5/thumbnails/5.jpg)
Basic Formulas Of Earned Value Management
Simple EVMS Terms
BCWS The planned of the work to be performed
BCWP The “earned value” of the performed work
ACWP The actual costs – in dollars – to complete the planned work
BAC The budget to complete the project
Cost and Schedule Variance
SV Schedule Variance BCWP – BCWS
CV Cost Variance BCWP – ACWP
SPI Schedule Performance Index BCWP / BCWS
CPI Cost Performance Index BCWP / ACWP
EAC Estimate at Complete ACWP + (BAC – BCWP)
TCPI To Complete Performance Index (BAC – BCWP) / (EAC – ACWP)
ISAC Independent Schedule at Complete Schedule / SPI
VAC Variance at Complete BAC – EAC
Print this page and keep in your notebook. No one, not even the pros can remember these
acronyms without a cheat sheet 5
![Page 6: A gentle introduction to earned value management systems (neutral)](https://reader034.vdocuments.us/reader034/viewer/2022051411/54441cdaafaf9f550d8b47d7/html5/thumbnails/6.jpg)
It’s the holidays, it’s cookie baking time! Let’s use Earned Value to
manage our Christmas Cookie project.
A Simple Edible Example6/31
![Page 7: A gentle introduction to earned value management systems (neutral)](https://reader034.vdocuments.us/reader034/viewer/2022051411/54441cdaafaf9f550d8b47d7/html5/thumbnails/7.jpg)
EVMS Of Our Holiday Cookie Baking
Process
Our Christmas Cookie “Plan”
40 cookies per batch
5 batches per hour (200 cookies per hour)
Schedule: 5 hours to make 1,000 cookies (a big neighborhood)
Budgeted cost = $0.05 per cookie
Total Budget = $50.00 for the 1,000 cookies
Analysis after one (1) hour of baking we’ve made …
150 edible cookies
some were burnt,
some hit the floor,
the kids ate some of the dough,
fed some to the dog.
Actual cost of ingredients after one hour (ACWP) = $9.00
7/31
![Page 8: A gentle introduction to earned value management systems (neutral)](https://reader034.vdocuments.us/reader034/viewer/2022051411/54441cdaafaf9f550d8b47d7/html5/thumbnails/8.jpg)
After One Hour of Making Cookies
8/31
Simple EVMS
BCWS $10.00 Planned cost
BCWP 150 cookies X $0.05 per Cookie $7.50 Product cost
ACWP $9.00 Materials cost
Cost and Schedule Variance
SV BCWP – BCWS ($7.50 - $10.00) –$2.50 We’re behind schedule
CV BCWP – ACWP ($7.50 - $9.00) –$1.50 We’re over budget
SPI BCWP / BCWS 0.75 25% behind schedule
CPI BCWP / ACWP 0.833 17% over budget
![Page 9: A gentle introduction to earned value management systems (neutral)](https://reader034.vdocuments.us/reader034/viewer/2022051411/54441cdaafaf9f550d8b47d7/html5/thumbnails/9.jpg)
What’s Going To Happen At The End
Of The Project?
9/31
Forecasting our production
IEAC BAC / CPI ($50.00 / 0.833) $60.00 Our plan was $50.00, darn
VAC BAC – IEAC ($50.00 – $60.00) $10.00 We’ll be $10 over budget
ISAC 5 hours / SPI (5 / 0.75) 6.67 And we’re gonna be late
![Page 10: A gentle introduction to earned value management systems (neutral)](https://reader034.vdocuments.us/reader034/viewer/2022051411/54441cdaafaf9f550d8b47d7/html5/thumbnails/10.jpg)
Can We Catch Up In Time?
Forecasting the future
To Complete Performance Index
TCPI
(Budget – BCWP) / (EAC – ACWP)
(50.00 – 7.50) / (500.00 – 9.00)
42.50 / 41.00
1.036
10
![Page 11: A gentle introduction to earned value management systems (neutral)](https://reader034.vdocuments.us/reader034/viewer/2022051411/54441cdaafaf9f550d8b47d7/html5/thumbnails/11.jpg)
A Simple EVMS Chart(The linear form is never this way in practice, it is an S-Curve)
BCWS
ACWP
BCWP
Hour 1 Hour 2 Hour 3 Hour 4 Hour 5
$10.00
$50.00
$40.00
$30.00
$20.00
SV
in $ CV
SV in hours
11/31
![Page 12: A gentle introduction to earned value management systems (neutral)](https://reader034.vdocuments.us/reader034/viewer/2022051411/54441cdaafaf9f550d8b47d7/html5/thumbnails/12.jpg)
PUTTING THESE “SIMPLE”
CONCEPTS INTO PRACTICE
EVMS can be deployed in many ways. For us the straight forward way is to “micro–schedule” the work activities.
12/31
![Page 13: A gentle introduction to earned value management systems (neutral)](https://reader034.vdocuments.us/reader034/viewer/2022051411/54441cdaafaf9f550d8b47d7/html5/thumbnails/13.jpg)
A Micro–Schedule
13/31
Micro–scheduling does NOT mean micro–managing.
It means planning at a sufficient level of detail to identify useful tasks that can be measured in days (3 to 5) or at most a week.
Micro–schedules consists of:
Objective completion criteria – so we know when we are done.
“Budgets” and “Values” – usually representing person days and some “measurable” value to the customer in terms of dollars.
Planned Completion Dates – so we know when to expect these tasks to be done.
![Page 14: A gentle introduction to earned value management systems (neutral)](https://reader034.vdocuments.us/reader034/viewer/2022051411/54441cdaafaf9f550d8b47d7/html5/thumbnails/14.jpg)
Some Fundamental Concepts of EVMS
14/31
Never relate what was planned to be spent (BCWS) to
the actual amount spent (ACWP).
This tells us nothing of value
It can warp our thinking into attempting to under–spend our
allowed amount to report favorable numbers.
Only report what was actually spent (ACWP) against what
“value” was delivered for that planned investment (BCWP)
Cost Performance (CV) reports what has been
accomplished (BCWP) versus what was invested to
accomplish that work (ACWP).
![Page 15: A gentle introduction to earned value management systems (neutral)](https://reader034.vdocuments.us/reader034/viewer/2022051411/54441cdaafaf9f550d8b47d7/html5/thumbnails/15.jpg)
A FRAMEWORK FOR
DEPLOYING EVMS
Let’s do it the simple way with some common sense†
15/31
![Page 16: A gentle introduction to earned value management systems (neutral)](https://reader034.vdocuments.us/reader034/viewer/2022051411/54441cdaafaf9f550d8b47d7/html5/thumbnails/16.jpg)
First the Bad News16
![Page 17: A gentle introduction to earned value management systems (neutral)](https://reader034.vdocuments.us/reader034/viewer/2022051411/54441cdaafaf9f550d8b47d7/html5/thumbnails/17.jpg)
ANSI/EIA–748A–2002 And Success Criteria Of
Earned Value Management
The EIA 748 specification calls out 32 performance
criteria required for compliance.
These criteria are too complex for our “agile”
environment.
There are 10 key criteria that can be deployed
here.
17/31
![Page 18: A gentle introduction to earned value management systems (neutral)](https://reader034.vdocuments.us/reader034/viewer/2022051411/54441cdaafaf9f550d8b47d7/html5/thumbnails/18.jpg)
ANSI/EIA–748A–2002 And Success
Criteria Of Earned Value Management18
![Page 19: A gentle introduction to earned value management systems (neutral)](https://reader034.vdocuments.us/reader034/viewer/2022051411/54441cdaafaf9f550d8b47d7/html5/thumbnails/19.jpg)
10 Criteria For Successful EVMS
19/31
1. Define authorized work elements
2. Identify project organizational structure
5. Provide integrated planning, scheduling, budgeting, work authorization, and cost accumulation processes
6. Schedule the authorized work in a sequential manner that identifies the significant task dependencies
7. Identify physical products and organizations
8. Establish and maintain time–phased budget baseline
16. Record direct costs consistently in a formal manner
23. Periodically generate project metrics
25. Develop revised cost estimates–at–completion based on performance to date
28. Incorporate authorized changes in a timely manner
![Page 20: A gentle introduction to earned value management systems (neutral)](https://reader034.vdocuments.us/reader034/viewer/2022051411/54441cdaafaf9f550d8b47d7/html5/thumbnails/20.jpg)
10 Criteria For Successful EVMS
20
![Page 21: A gentle introduction to earned value management systems (neutral)](https://reader034.vdocuments.us/reader034/viewer/2022051411/54441cdaafaf9f550d8b47d7/html5/thumbnails/21.jpg)
Define Authorized Work Elements
21/31
Create a Work Breakdown Structure (WBS) for all activities at the micro–schedule level
The scope of the entire project must be defined in order to measure performance.
This is a problem for agile methods, since scope evolves as the project evolves
Schedule major iterations on 2 to 3 week boundaries
Generate “macro” estimates of future work and “micro” estimates of the current iteration's work
Defined project objectives, deliverables, and key milestones are based primarily on experience
![Page 22: A gentle introduction to earned value management systems (neutral)](https://reader034.vdocuments.us/reader034/viewer/2022051411/54441cdaafaf9f550d8b47d7/html5/thumbnails/22.jpg)
Identify Project Organizational
Structure
22/31
Identify the structure of the functional organizations performing the work
Define all organizational elements responsible for delivering value
Identify who is doing what and what value they are delivering
Assign all tasks to specific named resources
Identify the major milestones and those responsible for meeting the commitments represented by these milestones
![Page 23: A gentle introduction to earned value management systems (neutral)](https://reader034.vdocuments.us/reader034/viewer/2022051411/54441cdaafaf9f550d8b47d7/html5/thumbnails/23.jpg)
Provide Integrated Planning, Scheduling, Budgeting,
Work Authorization, And Cost Accumulation Processes
23/31
Provide integration of the firm’s:
Planning,
Scheduling,
Budgeting,
Work Authorization
Cost accumulation
Project management processes should be integrated
with the WBS and the functional organization.
![Page 24: A gentle introduction to earned value management systems (neutral)](https://reader034.vdocuments.us/reader034/viewer/2022051411/54441cdaafaf9f550d8b47d7/html5/thumbnails/24.jpg)
Schedule The Authorized Work In A Sequential Manner
That Identifies The Significant Task Dependencies
24/31
Describe the work sequence
Identify significant dependencies required to meet
the requirements
Identify which tasks are impeading the process of
other tasks
Create a “master schedule” for larger projects to
connect the subordinate projects
![Page 25: A gentle introduction to earned value management systems (neutral)](https://reader034.vdocuments.us/reader034/viewer/2022051411/54441cdaafaf9f550d8b47d7/html5/thumbnails/25.jpg)
Identify Physical Products And The
Organizations That Produce Them
25/31
All project must be able to identify and measure physical performance
Define metrics which convert to “planned values” into “earned values”
Project must specify:
Physical Products
Deliverables
Outputs
Metrics
Milestones
Technical performance indicators
![Page 26: A gentle introduction to earned value management systems (neutral)](https://reader034.vdocuments.us/reader034/viewer/2022051411/54441cdaafaf9f550d8b47d7/html5/thumbnails/26.jpg)
Establish And Maintain A Time–phased
Performance Measurement Baseline
26/31
Establish initial budgets on internal management
estimates and external negotiated targets
Budget for long–term efforts must be held at higher
levels of the organization
Time–phased budget is required to measure
performance
Staff
Other Direct Costs (ODC)
![Page 27: A gentle introduction to earned value management systems (neutral)](https://reader034.vdocuments.us/reader034/viewer/2022051411/54441cdaafaf9f550d8b47d7/html5/thumbnails/27.jpg)
Record Direct Cost Consistency In A
Formal System
27/31
“Applied Direct Costs” is the preferred method of
accounting for the accrual of “value”
Isolate Level of Effort costs in a separate WBS
element
![Page 28: A gentle introduction to earned value management systems (neutral)](https://reader034.vdocuments.us/reader034/viewer/2022051411/54441cdaafaf9f550d8b47d7/html5/thumbnails/28.jpg)
Periodically Generate Project Metrics
28/31
The amount of planned versus budget earned for the work accomplished
The amount of budget earned versus the actual direct costs for the same work
This is the “cost variance”
This differentiates EVMS from other “actual versus budget” cost analysis
Weekly measures are now the “norm”
Comparisons need to be detailed enough to provide intervention opportunities
![Page 29: A gentle introduction to earned value management systems (neutral)](https://reader034.vdocuments.us/reader034/viewer/2022051411/54441cdaafaf9f550d8b47d7/html5/thumbnails/29.jpg)
Develop Revised Cost Estimates–at–completion
(EAC) Based On Performance To Date
29/31
Compare this information with the performance
measure baseline to identify variances at
completion
![Page 30: A gentle introduction to earned value management systems (neutral)](https://reader034.vdocuments.us/reader034/viewer/2022051411/54441cdaafaf9f550d8b47d7/html5/thumbnails/30.jpg)
Incorporate Authorized Changes In A
Timely Manner
30/31
All changes must be addressed as they effect
budget and schedule
Base changes on the estimated amount and
assignment to functional organizations needs to be
recorded as well
All approved changes must be incorporated into the
project baseline
![Page 31: A gentle introduction to earned value management systems (neutral)](https://reader034.vdocuments.us/reader034/viewer/2022051411/54441cdaafaf9f550d8b47d7/html5/thumbnails/31.jpg)
Ten Benefits of EVMS
31/31
It is a single management control system to provide reliable and consistent data on project performance.
It integrates work, schedule, and cost using a work breakdown structure.
The associated database of completed projects is useful for comparative analysis.
The cumulative cost performance index (CPI) provides an early warning signal.
The schedule performance index provides an early warning signal.
The CPI is a predictor for the final cost of the project.
It uses an index–based method to forecast the final cost of the project.
The “to-complete” performance index allows evaluation of the forecasted final cost.
The periodic (e.g., weekly or monthly) CPI is a benchmark.
The management by exception principle can reduce information overload.