A Dilemma for New Producers of PGE Concentrates – Downstream Processing to Saleable Metals ROUNDUP 2001 John A. Chapman J.A. Chapman Mining Services

Upload: john-chapman

Post on 16-May-2015

976 views

Category:

Education


0 download

DESCRIPTION

New producers of base metal/PGE/precious metal concentrates are faced with very unique challenges regarding downstream processing to saleable metals. The normally complex sulfide concentrate produced consists principally of nickel, copper, cobalt, PGE’s, gold and silver. The alternatives available for downstream processing to saleable metals are very few, and at this time the only standard commercial route is by way of conventional smelting (pyrometallurgy), hydrometallurgical/electrochemical refining to recover base metals, and then a complex chemical (leach and precipitate) refining process to recover PGE’s and precious metals from the base metal leach residue.

TRANSCRIPT

Page 1: A Dilemma for New Producers of PGE/Base Metal Flotation and Gravity Concentrates – Downstream Processing to Saleable Metals

A Dilemma for New Producers of PGE

Concentrates – Downstream Processing to Saleable Metals

ROUNDUP 2001

John A. ChapmanJ.A. Chapman Mining Services

Page 2: A Dilemma for New Producers of PGE/Base Metal Flotation and Gravity Concentrates – Downstream Processing to Saleable Metals

Finished PGEProducts

Smelting & Refining Producing PGERich SulfideConcentrates

Page 3: A Dilemma for New Producers of PGE/Base Metal Flotation and Gravity Concentrates – Downstream Processing to Saleable Metals

Today’s Situation

Oligopoly of vertically integrated major mining, smelting & refining companiesRestricted access for new PGE rich sulfide concentrate producer(s) to smelting & refining facilities of majorsToll (custom) smelting and refining, if negotiated, is very expensiveWith very few facilities available concentrate transportation costs may be significant

Page 4: A Dilemma for New Producers of PGE/Base Metal Flotation and Gravity Concentrates – Downstream Processing to Saleable Metals

Principal Purpose PGE

Company Location of Smelter BMR RefineryOutokumpu Finland Nickel

Norilsk Russia Nickel Anglo Platinum South Africa PGE's

Implats South Africa PGE's Lonmin South Africa PGE's

Zimplats Zimbabwe PGE's Union Miniere Belgium Cu-Pb

Inco Sudbury Nickel Falconbridge Sudbury Nickel

Stillwater Montana, USA PGE's

Integrated PGE Smelters and Refineries

Page 5: A Dilemma for New Producers of PGE/Base Metal Flotation and Gravity Concentrates – Downstream Processing to Saleable Metals

Smelter TermsCharges & Penalties

Typical concentrate contains Ni, Cu, Co, PGE’s, Au, AgMoisture content 10% +/- 2%Approximate grade set on each payable metal in concentrateMay be rejected due to deleterious elements or off-specification moisture or metals grades Treatment charge on dmt basis of feed

Page 6: A Dilemma for New Producers of PGE/Base Metal Flotation and Gravity Concentrates – Downstream Processing to Saleable Metals

Smelter TermsCredits

Smelter sets “accountable” metal recoveries (%) or a minimum deductionCredits based upon refined “accountable” base, precious and PGE metals with a deduction for refining chargeSmelting and refining charges adjusted annually by various price indices

Page 7: A Dilemma for New Producers of PGE/Base Metal Flotation and Gravity Concentrates – Downstream Processing to Saleable Metals

Smelter TermsCredits (cont.)

Smelter price participation against base prices of metals (usually LME)Final payments may be spread over considerable time periods for different metals

Page 8: A Dilemma for New Producers of PGE/Base Metal Flotation and Gravity Concentrates – Downstream Processing to Saleable Metals

Independent Refiners

Johnson MattheyUnion Miniere Precious MetalsHeraeus Metal ProcessingSabin Metal CorpEngelhard CorporationDegussa CorporationHandy & Harman Refining Group, Inc.See www.ipmi.org for complete list of Refiners

Page 9: A Dilemma for New Producers of PGE/Base Metal Flotation and Gravity Concentrates – Downstream Processing to Saleable Metals

The Dilemma

You have a PGE property that appeared to be technically and

economically viable until the feasibility study showed the X-Mine costs were so high that the project

was rendered uneconomic (PROJECT NPV = NIL)

Page 10: A Dilemma for New Producers of PGE/Base Metal Flotation and Gravity Concentrates – Downstream Processing to Saleable Metals

Possible Solutions To The Dilemma for Large Deposits

The Stillwater Mining Company “model”• proven smelting & base metal refining

technology that is cost sensitive to concentrate grade and economy-of-scale

New technology, “PlatSol”• high risk but with potential high reward

Page 11: A Dilemma for New Producers of PGE/Base Metal Flotation and Gravity Concentrates – Downstream Processing to Saleable Metals

The “Stillwater”Model

Commenced production in 1987 at Nye, Montana and shipped concentrate to UM (~35K oz/yr PGE’s)Added a smelter in 1990 and shipped granulated matte to UM (~250K oz/yr PGE’s)

Page 12: A Dilemma for New Producers of PGE/Base Metal Flotation and Gravity Concentrates – Downstream Processing to Saleable Metals

The Stillwater Model (cont.)

Added a BMR in 1996 and shipped high grade PGE residue to JM and UM and copper and nickel solutions to Sherritt(~300K oz/yr PGE’s)Expanded smelter and BMR in 2000, ship PGE residues to JM et al, and now produce cathode copper and nickel-cobalt crystallization at site (~400K oz/yr PGE’sand increasing)

Page 13: A Dilemma for New Producers of PGE/Base Metal Flotation and Gravity Concentrates – Downstream Processing to Saleable Metals

Stillwater BMR & Smelter (1998 Photo)

PGE’s in Flotation Concentrate Upgraded From 50 opt to 60%Then Shipped to Off-Site PGE Refineries

Byproducts Include Cathode CopperAnd Nickel/Cobalt Xtals

Page 14: A Dilemma for New Producers of PGE/Base Metal Flotation and Gravity Concentrates – Downstream Processing to Saleable Metals

PGE SmelterProcess Description

Electric 5 mW Furnace (EF)• 100 tons concentrate per day

processing design capacity• Removes oxide materials (SiO2, FeO)

from concentrate• Upgrades PGE's from 50 opt to 200

opt• Smelter PGE recovery is plus 99%

Page 15: A Dilemma for New Producers of PGE/Base Metal Flotation and Gravity Concentrates – Downstream Processing to Saleable Metals

New Stillwater Electric Furnace

Page 16: A Dilemma for New Producers of PGE/Base Metal Flotation and Gravity Concentrates – Downstream Processing to Saleable Metals

PGE Smelter Process Description (cont.)

Top Blown Rotary Converter (TBRC)• Processing capacity equivalent to 50-

60 tons concentrate/day• Removes iron (FeO) and sulfur (SO2)

from EF matte• Upgrade PGE's from 200 opt to 600

opt

Page 17: A Dilemma for New Producers of PGE/Base Metal Flotation and Gravity Concentrates – Downstream Processing to Saleable Metals

New Stillwater TBRC

Page 18: A Dilemma for New Producers of PGE/Base Metal Flotation and Gravity Concentrates – Downstream Processing to Saleable Metals

PGE SmelterProcess Description (cont.)

Granulation/Regeneration• Water jets cool EF and TBRC matte• High efficiency scrubbing captures

plus 99.5% SO2• Regeneration product is gypsum,

used locally as a soil amendment• No discharge of process solutions

Page 19: A Dilemma for New Producers of PGE/Base Metal Flotation and Gravity Concentrates – Downstream Processing to Saleable Metals

Stillwater PGE Smelter

Page 20: A Dilemma for New Producers of PGE/Base Metal Flotation and Gravity Concentrates – Downstream Processing to Saleable Metals

BMRProcess Description

Grinding – Batch Process• Tower mill grinds smelter matte to 85%

passing 200 meshAtmospheric Leach• Leaches nickel, iron, cobalt and some

copper• Precipitates out any PGE's from solution• Upgrades PGE's from 2% to 4%

Page 21: A Dilemma for New Producers of PGE/Base Metal Flotation and Gravity Concentrates – Downstream Processing to Saleable Metals

Stillwater Mining CompanyBase Metals Refinery Atmospheric Leach

PGE’s = 4%

PGE’s = 600 opt

Page 22: A Dilemma for New Producers of PGE/Base Metal Flotation and Gravity Concentrates – Downstream Processing to Saleable Metals

BMRProcess Description (cont.)

Pressure Leach• Autoclaves operate on a batch basis• Leaches nickel, copper and iron from the

atmospheric leach residue• Upgrades the PGE’s from 4% to 60-65%

Iron Removal• Precipitates iron (Goethite) from solution

(recycled to smelter)

Page 23: A Dilemma for New Producers of PGE/Base Metal Flotation and Gravity Concentrates – Downstream Processing to Saleable Metals

BMRProcess Description (cont.)

The nickel/copper/cobalt sulfate solution• Nickel/cobalt crystallized and shipped

offsite• Copper electrowinning on site

PGE Residue Processing• Filtered and shipped offsite for refining

Page 24: A Dilemma for New Producers of PGE/Base Metal Flotation and Gravity Concentrates – Downstream Processing to Saleable Metals

Stillwater Mining Company Base Metals Refinery Pressure Leach

PGE’s = 4%

PGE’s = 60%

Page 25: A Dilemma for New Producers of PGE/Base Metal Flotation and Gravity Concentrates – Downstream Processing to Saleable Metals

The PlatSol Process

Patented process by International PGM Technologies Ltd.First pilot testing done in 2000 at Lakefield Research in Ontario for PolyMet Mining Corporation on a bulk sample from the NorthMet deposit

Page 26: A Dilemma for New Producers of PGE/Base Metal Flotation and Gravity Concentrates – Downstream Processing to Saleable Metals

The PlatSol Process (cont.)

Process uses an innovative combination of concentrate pressure leaching followed by precipitation (gold & PGE’s), SX-EW (copper) and crystallization (nickel & cobalt)

Page 27: A Dilemma for New Producers of PGE/Base Metal Flotation and Gravity Concentrates – Downstream Processing to Saleable Metals

Lakefield Research FacilitiesLakefield, Ontario

Page 28: A Dilemma for New Producers of PGE/Base Metal Flotation and Gravity Concentrates – Downstream Processing to Saleable Metals

Pilot Plant Crushing

Page 29: A Dilemma for New Producers of PGE/Base Metal Flotation and Gravity Concentrates – Downstream Processing to Saleable Metals

Pilot PlantConcentration

Page 30: A Dilemma for New Producers of PGE/Base Metal Flotation and Gravity Concentrates – Downstream Processing to Saleable Metals

Pilot Plant Pressure Leaching & Metals Recovery

Page 31: A Dilemma for New Producers of PGE/Base Metal Flotation and Gravity Concentrates – Downstream Processing to Saleable Metals

Conclusions

Very restricted access to PGE smeltersDeposits of +2.5 million ounces PGE’shave a chance of processing to finished metals at or near the mine-site, and could yield a viable NPV for developmentSmaller deposits will have great difficulty in achieving a viable NPV for project development because of the smelter situation

Page 32: A Dilemma for New Producers of PGE/Base Metal Flotation and Gravity Concentrates – Downstream Processing to Saleable Metals

The Goal!

A Technically Feasible &

Economically Viable PGE Operation