a community restaurant - ucbx4703+-+breathe... · a community restaurant a redesign 3 project...
TRANSCRIPT
PAGE - 1 -
A Community Restaurant
A Redesign 3 Project
Ronnie Blomberg Leila Carrillo
Tatjana Eggert-Reich John Ingham
Lisa Mekis Elizabeth Neil
Wei Ping Chang Sohaila Shooshtarian
PAGE - 2 -
Table of Contents
Scope Statement
Vision Statement 3 Business Need 3 Project Description 3 Project Deliverables 4 Objectives 5 Assumptions 6 Constraints 6 High - Level Risks 7
Stakeholder Analysis 8 Lifecycle Approach 9 Lifecycle 9 - 10 WBS 11 - 14 Project Schedule 15 - 16 Cost Baseline 17 - 20 Cost Baseline Graph 21 Communication Plan 22 - 23 Responsibility Assignment Matrix 24 - 26 Risk Matrix 27 Risk Response Plan 28
PAGE - 3 -
Scope Statement
Vision Statement Design and construct a full service, neighborhood restaurant in San Francisco serving California cuisine focusing on locally grown food, and locally produced art to benefit the overall neighborhood community and economy Business Needs Currently San Francisco does not have one full service restaurant that is solely focused on locally grown organic food, local entertainment, and local art. The Fillmore neighborhood community is eager to support the opening of a restaurant that features food from local farms, creates employment for neighborhood youth and adults, and is an evening venue for conviviality, art, and community building. Project Description Design and build a full service restaurant on Fillmore Street in San Francisco. Priority will be given to local and green purveyors, merchants and contractors for all construction and design needs. The restaurant construction will meet all current building codes and regulations, be on time, and within budget. The design and construction of the restaurant will include:
Seating for approximately 75 diners Sound system supporting acoustic performance Two wheel chair accessible bathrooms State of the art open kitchen Enclosed kitchen prep area Warm overall design that highlights the art, music, and food
PAGE - 4 -
Scope Statement (Continued) Project Deliverables
IS IS NOT
Planning Completed by 2/11/08 Promotional design (menus, logos, matchbooks, etc.)
Permits & Licenses by 3/7/08 Finding a location, handling tax & insurance matters
Design and Construction of Restaurant by 6/11/08 Marketing & organization of soft- open / grand opening
Walk Through and Sign off by Sponsor by 7/3/08 Hiring chef, kitchen/front of house staff
Providing tableware, linens, silverware, plates, platters, table, decorations, etc.
PAGE - 5 -
Scope Statement (Continued) Objectives
Objective Criteria for Evaluation
Complete Requirement for Plan Submission by 2/11/08 “J” Permit Obtained form City
Hire Designer and General Contractor (GC) by 2/12/08 Sponsor Approval and Signed Contracts
Complete Design Process 3/7/08 Sponsor Sign Off
Complete Construction Requirements by 6/11/08 General Contractor and Project Manager Sign Off
Final Inspection by 6/12/08 Final Inspection Document Received
Sponsor Acceptance of Completed Work by 7/03/08 Signed “Final Sign Off Document”
PAGE - 6 -
Scope Statement (Continued) Assumption and Constraints
Assumptions Constraints
GC Will Obtain Construction Permit Funding – 1.2 MIL
Owner/ Sponsor will hire a qualified General Contractor Timeline – Completion within 120 days of start
Owner/ Sponsor will hire a qualified Interior Designer
Cost of material will not increase more than 10%
No labor issues / strikes
Change order will not exceed more than 6%
PAGE - 7 -
Scope Statement (Continued) High Level Risks
Risk Description Trigger Impact on Cost, Scope or Time Funding Cut Bank Pulls Out Kills Project
Construction Costs Increase Costs Exceed 10% Cost
Schedule Delays Labor Dispute Vendor Delays Time
Inspections Failure Non Compliance with City Building Codes Cost and Time
PAGE - 8 -
Stakeholder Analysis
Stakeholder Needs Wants / Expectations
Bank Proper return on its investment Potential profit Breathe Local continues as a profitable business
Interior Designer
Clear understanding of design vision Clear understanding of code requirements
Sufficient funds to obtain materials/supplies
Weekly team meeting Prompt payment of invoices
Recommendations for future business Design to achieve local recognition
Local Residents To be considered in the design
Communication of vision Milestone updates
Notification of opening Neighborhood enhancement
Owner / Sponsor
Final design and construction/design to meet ‘local’ vision
Communication Plan
Project on schedule and within budget Weekly status report
Project Team
Owner/Sponsor approval Sufficient cash flow
Authority to control project Qualified labor
Communication Plan
Deliverables on schedule and within budget Success will solidify contract for sponsor’s next project
Weekly group status meeting
Contractors
/Vendors
Detailed plans/drawings Clear understanding of deliverables
Sufficient funds to obtain materials/supplies
Prompt payment of final invoices Recommendations for future business
PAGE - 9 -
Lifecycle Approach Linear, restaurants have previously been constructed and designed and models used in those instances can be applied here. The uniqueness of this project lies in the design implementation of a neighborhood atmosphere. To that end, we also utilize a progressive elaboration approach.
Lifecycle (1 of 2)
PROJECT MANAGEMENT DELIVERABLES
REQUIREMENTS PLANNING CONSTRUCTION / EXECUTION CLOSING
Project Charter
Preliminary Scope Statement
Project Mgmt. Plan:
Scope Statement WBS
Project schedule Cost Baseline Responsibility
Assignment Matrix Communication Plan Risk Response Plan
Milestone List Status Report
Change Control
Closing Documents
Sponsor Sign-off Lessons Learned
PAGE - 10 -
Lifecycle (2 of 2)
PRODUCT PROCESS DELIVERABLES
REQUIREMENTS PLANNING CONSTRUCTION / EXECUTION CLOSING
Licensing and Permitting
Construction Requirements GC/Designer Requirements
Civil Engineering Plan Architectural Plan
Plan Submitted to City
Designer Contracted Design Completion
GC Contracted “J” Permit (Demolition)
City Permit Building Permit
Schedule Approval
Construction of Restaurant
City Inspections
Final City Inspection
Operational Hand Off
PAGE - 11 -
WBS REQUIREMENTS 1. Project Charter 2. Preliminary Scope Statement 2.1. Preliminary WBS 2.2. Preliminary time line 2.3. Preliminary cost baseline 2.3.1. Obtain cost estimates from GC and Designer 2.3.2. Labor cost estimates 3. Licensing and Permitting 3.1. Determine building permit requirements 3.2. Determine local jurisdiction 3.3. Determine Gas/Water/Electricity requirements 3.4. Permits cost estimates 4. Construction Requirements: 4.1. Obtain Building plan from sponsor 4.2. Obtain sponsor’s requirements and specifications 4.3. Understand sponsor’s internal procedure (bidder qualification-bonding requirements etc.) 5. Designer and GC Requirements 5.1. Obtain designs 5.2. Understand responsibility of designer and construction manager 5.3. Establish construction responsibilities 5.4. Set up temporary Utilities 6. Civil Engineering Plan 7. Architectural Plan 8. Plan Submittal to City
PAGE - 12 -
WBS (Continued) PLANNING 1. Scope statement 2. WBS 3. Project Schedule 3.1. GC schedules (Construction) 3.2. Designer schedules (Furniture Procurement) 3.3. Bar-chart schedule 3.4. Inspections schedules 4. Cost Baseline 4.1. Reviewed GC & designer estimates 4.2. Permits & licenses payment 5. Responsibility Assignment Matrix (RAM) 6. Communication Plan 7. Risk Response Plan 8. Designer Contract 9. Design Completion and Approval 10. GC Contract 10.1. Have GC hire subcontractors for plumbing / Drainage / Power / Electricity / Telephone lines 10.2. Worker / Vendor Contracts 11. “J”-Permit (Demolition) 12. City Permit 13. Building Permit 14. Schedule Approval 14.1. Sponsor Schedule approval
PAGE - 13 -
WBS (Continued) CONSTRUCTION/ EXECUTION 1. Milestone List 2. Status Report 2.1. Constant monitoring of progress, budget and permit process 2.2. Weekly review meetings 3. Change Control 4. Construction of Restaurant 4.1. Aluminum flush tube frame (for 1/4" glass, 1-3/4"x4", 5'x6' opening, no intermediate horizontals)
4.2. Glazing panel, plate glass, 1/4" thick, tempered 4.3. Exterior Doors 4.4. Roof Construction 4.5. Partitions-rough framing 4.6. Interior Doors 4.7. Fittings-Pluming Fixture 4.8. Wall Finishes 4.9. Floor Finishes 4.10. Ceiling Finishes 4.11. Plumbing Fixtures 4.12. Terminal & Package Units, Multi zone-Air condition-Heating 4.13. Sprinklers 4.14. Electrical Service/Distribution 4.15. Communications and Security 4.16. Other Electrical Systems
4.17. Indoor Furniture and fixture procurement finished 5. City Inspections
PAGE - 14 -
WBS (Continued) CLOSING 1. Closing Documents 2. Sponsor Sign-Off 3. Lessons Learned 4. Final City Inspection 5. GC closing document 5.1. Final Bill payment
5.2. Punch List with all the sub-contractors 6. Operational Hand-Off 6.1. Sponsor acceptance and Sign-off 6.2. Obtain final payment 6.3. Recommendations for future projects
PAGE - 22 -
Communication Plan
X = Consulted/Reviewed O = Organizer * = Additional Updates As Needed
Sponsor PM Project Team
Members Designer Architect GC GM Freq. Dist. Method Doc
Type
Project Charter X O X Once Mtg / Email Word
Project Scope X O X Once* Mtg. / Email Word
WBS O X Once Mtg. / Email Word
Project Schedule O X X X X X Weekly Mtg. / Email Word
Cost Baseline O X X Once* Mtg. / Email Excel
PAGE - 23 -
Communication Plan (Continued)
Sponsor PM Project Team
Members Designer Architect GC GM Freq. Dist. Method Doc
Type
Risk Plan X O X X Once Mtg. / Email Word
Sponsor Report X O X Weekly WebEx Mtg. / Email Word
Reports & Minutes O X X X X Semi Monthly Mtg. / Email Word
Design Mtg Minutes X X X Weekly Email Word
RFP O X X X Once* Mtg. / Email Word
Sign-Off X O X X Once* Mtg. / Email Word
Final Report To
Stakeholders X O X X X X X Once* Mtg. / Email Word
PAGE - 24 -
Responsibility Assignment Matrix (RAM)
Execution = E Consultation = C Approval Authority = A Be Informed = I
RAM Deliverables
Project Sp
onso
r
Proj
ect
Man
agem
ent
Con
trac
tors
Ve
ndor
s
Ban
k
Inte
rior
Des
igne
r
Com
mun
ity
Project Charter A,C,I E C C,I C C Preliminary Scope Statement A,C,I E C C,I C C
WBS A,C,I E C,I C,I Scope Statement A,C,I E C,I C,I Project Schedule A,C,I E C,I C,I C
Cost Baseline A,C,I E C,I,E I,A C,I,E C Risk Response Plan A,C,I E C,I C,I
RAM A,C,I E C,I C,I Communication Plan A E C, I C,I
Milestone List A,C,I E C,I I C,I C Status Report A,C,I E C,I C,I C
Change Control A,C,I E C,I C,I C Closing Document A,C,I E C,I C,I Sponsor Approval A,C,I E C C Lesson Learned A,C,I E C,I C,I C
PAGE - 25 -
Responsibility Assignment Matrix (RAM) (Continued)
Execution = E Consultation = C Approval Authority = A Be Informed = I
RAM Deliverables
Product (1 of 2) Sp
onso
r
Proj
ect
Man
agem
ent
Con
trac
tors
Ve
ndor
s
Ban
k
Inte
rior
Des
igne
r
Com
mun
ity
Licensing and Permitting I E I Construction Requirements A,I E E GC/Designer Requirements A,I E E E C
Civil Engineering Plan I I C E Architectural Plan A,I E E
Submit Plan to City I E I Hire Designer A E E
Design Completion A I E C Hire GC A E E
“J” Permit (Demolition) E C C City Permit E C C
Building Permit E C I C Schedule Approval A E C C
PAGE - 26 -
Responsibility Assignment Matrix (RAM) (Continued)
Execution = E Consultation = C Approval Authority = A Be Informed = I
RAM
Deliverables
Product (2 of 2)
Spon
sor
Proj
ect
Man
agem
ent
Con
trac
tors
/ Ve
ndor
s
Ban
k
Inte
rior D
esig
ner
Loca
l Com
mun
ity
Construction of Restaurant A E City Inspections I E E
Final City Inspection I E GC closing document A E E
Operational Off A E
PAGE - 27 -
RISK MATRIX
• Scope Change
• Poor Workmanship
• Defective Product • Late Delivery
• Cost Overrun • Theft / Vandalism • Sickness / Accident
• Communication Block • External economy
• Natural Force delays • Inspection and Permit Issues
High
Medium
High
Low Medium
Low
IMPACT
PROBAB I L I TY
PAGE - 28 -
Risks Response Plan
Risk Affected Areas Probability Impact Priority Strategy /
Action Owner Status
Design Change Cost / Sched. / Scope Low Mid Low Accept PM / Sponsor / Vendor / GC O
Sched. Delays Sched. / Cost High High High Accept PM / Sponsor / Vendor / GC O
Scope Change Sched. / Cost Mid High Mid Accept PM / Sponsor O
Permits / Insp / Issues Sched. / Cost Low High High Avoid PM / GC C
Natural Force Delay Sched. / Cost Low High Low Accept PM / Sponsor / Vendor / GC C
Vendor Issues Sched. / Cost Med Low High Transfer PM / Sponsor / Vendor / GC C
Communication Block Sched. / Planning Med Mid Low Mitigate PM / Sponsor / Vendor / GC O
Legal Issues Sched. / Cost / Closure Med Mid High Accept PM / Team / Insurance O
Theft / Vandalism Cost / Sched. Med Mid Mid Avoid Insurance O
Cost Overrun Cost / Budget Med Mid Low Accept GC O