Page 1: 9-1 ELC 347 project management Week 10. 9-2 Agenda Integrative Project –2nd part Graded A few Minor problems –3nd part Due –Outline of deliverables (posted

9-1

ELC 347 project management

Week 10

Page 2: 9-1 ELC 347 project management Week 10. 9-2 Agenda Integrative Project –2nd part Graded A few Minor problems –3nd part Due –Outline of deliverables (posted

9-2

Agenda

• Integrative Project – 2nd part Graded

• A few Minor problems

– 3nd part Due – Outline of deliverables (posted in WebCT)

• Quiz 2 is postedand must be completed by Nov 9– Chapters 5-9, 20 short essays (4 from each chapter) – Take home exam with 48 hours time limit – Three will only be 3 Quizzes instead of the 4 mentioned in the

syllabus – Password is “CreepyScope”

• Today we will discuss Project Scheduling

Page 3: 9-1 ELC 347 project management Week 10. 9-2 Agenda Integrative Project –2nd part Graded A few Minor problems –3nd part Due –Outline of deliverables (posted

9-3

Project Scheduling: Networks, Duration Estimation,

and Critical PathChapter 9

© 2007 Pearson Education

Page 4: 9-1 ELC 347 project management Week 10. 9-2 Agenda Integrative Project –2nd part Graded A few Minor problems –3nd part Due –Outline of deliverables (posted

9-4

Page 5: 9-1 ELC 347 project management Week 10. 9-2 Agenda Integrative Project –2nd part Graded A few Minor problems –3nd part Due –Outline of deliverables (posted

9-5

Page 6: 9-1 ELC 347 project management Week 10. 9-2 Agenda Integrative Project –2nd part Graded A few Minor problems –3nd part Due –Outline of deliverables (posted

9-6

Project Scheduling Terms

• Successors

• Predecessors

• Network diagram

• Serial activities

• Concurrent activities

ED

C

B

A F

• Merge activities

• Burst activities

• Node

• Path

• Critical Path

Page 7: 9-1 ELC 347 project management Week 10. 9-2 Agenda Integrative Project –2nd part Graded A few Minor problems –3nd part Due –Outline of deliverables (posted

9-7

Network Diagrams

Show interdependence

Facilitate communication

Help schedule resources

Identify critical

activities

Determine project completion

Show start & finish dates

Page 8: 9-1 ELC 347 project management Week 10. 9-2 Agenda Integrative Project –2nd part Graded A few Minor problems –3nd part Due –Outline of deliverables (posted

9-8

AOA Vs. AON

The same mini-project is shown with activities on arc…

C

ED

B F

E

C

DB F

…and activities on node.

Page 9: 9-1 ELC 347 project management Week 10. 9-2 Agenda Integrative Project –2nd part Graded A few Minor problems –3nd part Due –Outline of deliverables (posted

9-9

Node LabelsEarly Start

Activity Float Activity Descriptor

Late Start

ID Number

Activity Duration

Late Finish

Early Finish

Basic mathES + DUR = EFLS + DUR = LF

ES+AF=LS

Page 10: 9-1 ELC 347 project management Week 10. 9-2 Agenda Integrative Project –2nd part Graded A few Minor problems –3nd part Due –Outline of deliverables (posted

9-10

CPM versus PERT

• PERT was developed by US Navy in the 1950s’• CPM was developed by Remington Rand and DuPont

around the same time.• Only difference is in durations estimating

– Pert uses 3 cases Most optimistic, most pessimistic and most likely and determines probability for each

• DoPo + DpOp +DePe = final duration

– CPM use only the most likely duration

Page 11: 9-1 ELC 347 project management Week 10. 9-2 Agenda Integrative Project –2nd part Graded A few Minor problems –3nd part Due –Outline of deliverables (posted

9-11

Duration Estimating

• Duration – the elapsed time from the start of an activity until it is finished

• Effort -- the actual time spent on the project• Example

– Tony work on a project task for 20 hours at 4 hours per day starting Monday mourning. The project task was completed Late Friday

• Effort – 20 hours

• Duration – 5 days

Page 12: 9-1 ELC 347 project management Week 10. 9-2 Agenda Integrative Project –2nd part Graded A few Minor problems –3nd part Due –Outline of deliverables (posted

9-12

Techniques for Estimating Duration

• Experience• Historical data• Research• Modeling• Experiments• Breakdown/roll-up

• Delphi Method– Panel of experts

• Consultants• Three outside Estimates• Ranging• Other techniques

Page 13: 9-1 ELC 347 project management Week 10. 9-2 Agenda Integrative Project –2nd part Graded A few Minor problems –3nd part Due –Outline of deliverables (posted

9-13

Page 14: 9-1 ELC 347 project management Week 10. 9-2 Agenda Integrative Project –2nd part Graded A few Minor problems –3nd part Due –Outline of deliverables (posted

9-14

Duration Estimation Methods

• Past experience• Expert opinion• Mathematical derivation – Beta distribution

– Most likely (m)– Most pessimistic (b)– Most optimistic (a)

22 =

6

b aActivity Variance

4 = TE

6

a m bActivity Duration

Page 15: 9-1 ELC 347 project management Week 10. 9-2 Agenda Integrative Project –2nd part Graded A few Minor problems –3nd part Due –Outline of deliverables (posted

9-15

Task Predecessor a m b

Z -- 7 8 15

Y Z 13 16 19

X Z 14 18 22

W Y, X 12 14 16

V W 1 4 13

T W 6 10 14

S T, V 11 14 19

1. Sketch the network described in the table.

2. Determine the expected duration and variance of each activity.

Duration estimate.xls

Page 16: 9-1 ELC 347 project management Week 10. 9-2 Agenda Integrative Project –2nd part Graded A few Minor problems –3nd part Due –Outline of deliverables (posted

9-16

Constructing the Critical Path

• Forward pass – an additive move through the network from start to finish– Determines ES and EF using ES+DUR = EF – If 2 (or more) EF from proceeding uses largest

• Backward pass – a subtractive move through the network from finish to start– Determines LS and LF using LF- DUR = LS– If 2 (or more) LS from succeeding use smallest – Determine AF using LS-ES = AF

• Critical path – the longest path from end to end which determines the shortest project length

Page 17: 9-1 ELC 347 project management Week 10. 9-2 Agenda Integrative Project –2nd part Graded A few Minor problems –3nd part Due –Outline of deliverables (posted

9-17

Rules for Forward/Backward Pass

Forward Pass Rules (ES & EF)– ES + Duration = EF– EF of predecessor = ES of successor– Largest preceding EF at a merge point becomes EF

for successor

Backward Pass Rules (LS & LF)– LF – Duration = LS– LS of successor = LF of predecessor– Smallest succeeding LS at a burst point becomes LF

for predecessor

Page 18: 9-1 ELC 347 project management Week 10. 9-2 Agenda Integrative Project –2nd part Graded A few Minor problems –3nd part Due –Outline of deliverables (posted

9-18

Calculating a Project Duration

• Determine each activity and its predecessors • Determine an estimated duration for each

activity• Find the “Critical Path”

– Add up the durations along the critical path

Page 19: 9-1 ELC 347 project management Week 10. 9-2 Agenda Integrative Project –2nd part Graded A few Minor problems –3nd part Due –Outline of deliverables (posted

9-19

Whats the “Critical Path”

• The longest path based on precedence of activities and durations through a PERT/CPM network

• It’s critical because – Its combined length determines the length of the project– It has NO slack– Delay of any activities on the critical path delays the entire

project

Page 20: 9-1 ELC 347 project management Week 10. 9-2 Agenda Integrative Project –2nd part Graded A few Minor problems –3nd part Due –Outline of deliverables (posted

9-20

Finding the critical path

• Use “forward pass” Calculations• Each activity should have

– ES earliest possible Start time– EF earliest possible finish time– DUR duration – EF = ES + DUR

ES DUR EF

Activity

Page 21: 9-1 ELC 347 project management Week 10. 9-2 Agenda Integrative Project –2nd part Graded A few Minor problems –3nd part Due –Outline of deliverables (posted

9-21

Example

3 4 7

A

7 5 12

B

Page 22: 9-1 ELC 347 project management Week 10. 9-2 Agenda Integrative Project –2nd part Graded A few Minor problems –3nd part Due –Outline of deliverables (posted

9-22

Special Case

• If an activity has more than one processor its EPS is set to the latest EPF of all its processors

3 4 7

A7 5 12

C0 5 5

B

Page 23: 9-1 ELC 347 project management Week 10. 9-2 Agenda Integrative Project –2nd part Graded A few Minor problems –3nd part Due –Outline of deliverables (posted

9-23

An example of forward pass

0 0 0

Start

8 4 12

F

0 4 4

D

4 8 12

C

25

4 29

Finish

0 5 5

A

16

5 21

I

21

4 25

J

4 4 8

E

16

7 23

H

12

4 16

G

5 4 9

B

Page 24: 9-1 ELC 347 project management Week 10. 9-2 Agenda Integrative Project –2nd part Graded A few Minor problems –3nd part Due –Outline of deliverables (posted

9-24

Backwards Pass

• Use to calculate Slack– LS -> Latest start time– LF -> Latest finish time– TS -> total slack

ES DUR EF

ActivityLS TS LF

Page 25: 9-1 ELC 347 project management Week 10. 9-2 Agenda Integrative Project –2nd part Graded A few Minor problems –3nd part Due –Outline of deliverables (posted

9-25

An example of backward pass

0 0 0

Start

0 0 0

8 4 12

F

12

4 16

0 4 4

D

0 0 4

4 8 12

C

4 0 12

25

4 29

Finish

25

0 29

0 5 5

A

3 3 8

16

5 21

I

16

0 21

21

4 25

J

21

0 25

4 4 8

E

8 4 12

16

7 23

H

18

2 25

12

4 16

G

12 0 16

5 4 9

B

8 3 12

Page 26: 9-1 ELC 347 project management Week 10. 9-2 Agenda Integrative Project –2nd part Graded A few Minor problems –3nd part Due –Outline of deliverables (posted

9-26

Task Predecessor Time

A -- 4

B A 9

C A 11

D B 5

E B 3

F C 7

G D, F 3

H E, G 2

K H 1

1. Sketch the network described in the table.

2. Determine the ES, LS, EF, LF, and slack of each activity

SLACK.xls

Page 27: 9-1 ELC 347 project management Week 10. 9-2 Agenda Integrative Project –2nd part Graded A few Minor problems –3nd part Due –Outline of deliverables (posted

9-27

Examine Critical Path for Reality Check

• Is the total duration typical?• Are the durations of the CP activities typical?• Reexamine all CP activity durations• Reexamine assumptions

Page 28: 9-1 ELC 347 project management Week 10. 9-2 Agenda Integrative Project –2nd part Graded A few Minor problems –3nd part Due –Outline of deliverables (posted

9-28

Laddering Activities

Project ABC can be completed more efficiently if subtasks are used

A(3) B(6) C(9) ABC=18 days

Laddered ABC=12 days

A1(1) A2(1) A3(1)

B1(2) B2(2) B3(2)

C1(3) C2(3) C3(3)

Page 29: 9-1 ELC 347 project management Week 10. 9-2 Agenda Integrative Project –2nd part Graded A few Minor problems –3nd part Due –Outline of deliverables (posted

9-29

Hammock Activities

Used as summaries for subsets of activities

0 A 5

0 5 5

5 B15

5 1015

15 C 18

15 3 18

0 Hammock 18

0 18 18

Useful with a complex project or one that has

a shared budget

Page 30: 9-1 ELC 347 project management Week 10. 9-2 Agenda Integrative Project –2nd part Graded A few Minor problems –3nd part Due –Outline of deliverables (posted

9-30

Reducing the Critical Path

• Eliminate tasks on the CP• Convert serial paths to parallel when possible• Overlap sequential tasks• Shorten the duration on critical path tasks• Shorten

– early tasks– longest tasks– easiest tasks– tasks that cost the least to speed up