82, bank road, 3rd floor, coimbatore 641 018 ph:0422 ......furnishing, electrical & air-conditioning...

34
BANK OF BARODA REGIONAL OFFICE - COIMBATORE 82, Bank Road, 3rd Floor, COIMBATORE 641 018 Ph:0422-2301264 Bank’s website http://www.bankofbaroda.com Furnishing, Electrical & Air conditioning Works for New premises of Bank of Baroda, SSI Branch, Tirupur . NP Complex, No:323, Avinashi Road, Tirupur 641602 TENDER DOCUMENTS for Partition, Furniture, Painting, Electrical & Air conditioning Works.

Upload: others

Post on 29-Jan-2021

0 views

Category:

Documents


0 download

TRANSCRIPT

  • BANK OF BARODA

    REGIONAL OFFICE - COIMBATORE

    82, Bank Road, 3rd Floor,

    COIMBATORE 641 018

    Ph:0422-2301264

    Bank’s website http://www.bankofbaroda.com

    Furnishing, Electrical & Air conditioning Works for

    New premises of Bank of Baroda, SSI Branch, Tirupur .

    NP Complex, No:323, Avinashi Road, Tirupur – 641602

    TENDER DOCUMENTS

    for

    Partition, Furniture, Painting, Electrical & Air conditioning Works.

    http://www.bankofbaroda.com/

  • INDEX

    S.N o CONTENTS PAGE NO:

    1 NOTICE INVITING TENDER

    2 FORM OF TENDER

    3 CONDITIONS OF CONTRACT

    4 APPENDIX 'A'

    5 GENERAL SPECIFICATIONS AND MODE OF MEASUREMENT

    6 PREAMBLE TO SCHEDULE OF QUANTITIES

    7 SCHEDULE OF QUANTITIES FOR FURNISHING WORKS OF BRANCH

    8 DRAWINGS FOR FURNISHING WORKS OF BRANCH

    9 SCHEDULE OF QUANTITIES FOR ELECTRICAL WORKS OF BRANCH

    10 DRAWINGS FOR ELECTRICAL WORKS OF BRANCH

  • Architect - Mr.S.Karthikeyan, M/s.Karthigeeta and Associates, Architects & Interior Designers, No: 100,

    Jagam Apartments, Jawahar Nagar, Bharathi Park No: 2, Coimbatore- 43.

    2 The work to be completed within 2 weeks from the date of issue of work order.

    3 The tender documents can be downloaded from Bank’s website http://www.bankofbaroda.com

    4 The tender documents shall be available on 27.11.2018 onwards to 17.12.2018 and the last date for

    receipt of tender is 17.12.2018 upto 3.00 P.M and Tender opening date is 17.12.2018 at 3.10 P.M.

    at Regional Office. Offerers / their authorized representatives may be present at the time of opening of the

    tenders.

    1. NOTICE INVITING TENDER

    1 Sealed tenders in two bid system are hereby invited for the proposed Interior Furnishing, Electrical & Air

    conditioning works to be carried out at the New premises of Bank of Baroda, SSI Branch, Tirupur.

    The Tenders may be submitted in the following manner:

    Envelope No. 1 (EMD & Technical Bid) :

    Earnest Money Deposit ( EMD ) : : Rs.22,500.00

    (Rupees Twenty Two Thousand and Five Hundred only) payable to Bank of Baroda by Demand Draft or

    Banker’s cheque payable at Coimbatore. The Tenderer must also submit the Mandatory information strictly in

    Bank’s prescribed proforma. Technical pre-qualification of the tendered will be based on the Mandatory

    information and supporting documents submitted along with the tender documents as well as Architect/

    Consultant/ Bank’s Scrutiny of the same and / or inspection of works carried out by the Tenderer. Bank

    reserves the right to accept or reject any tender without assigning any reason whatsoever. Tenderers who have

    executed works for Bank of Baroda, Tamil Nadu Region in the current / previous financial year need to submit

    only the Mandatory Information and need not submit the supporting documents.

    Important - Pre Qualification Condition: Tenderer must have satisfactorily execution of atleast one similar job

    of Rs.24 Lakhs value or 2 similar jobs of Rs.12 Lakhs each or 3 similar jobs of Rs.8 Lakhs each for a PSU in

    the last 5 years. Similar job means Furnishing, Electrical & Air conditioning Works.

    Envelope No. 2 (Commercial Bid) :

    • Commercial Bid Tenderer Bids received in any form other than mentioned above will be disqualified. Sealed

    tenders, in duplicate in the prescribed tender form, with the tender fees & EMD, along with the Mandatory

    information etc. & commercial bid (Envelope 1 & 2), should be addressed to “The Dy. General Manager, Bank

    of Baroda, Regional Office, 82, Bank Road, Coimbatore - 641 018 & superscribed “Tender for Interior

    Furnishing, Electrical & Air-Conditioning works for New premises of SSI Branch, Tirupur.

    Tenders should be submitted to the office not later than 3.00 P.M. on - 17.12.2018.

    Defect liability and free maintenance period shall be twelve months from the date of virtual completion of the

    works. Validity of offer shall be 120 days from the date of opening of the tender. The Bank does not bind itself

    to accept the lowest or any tender and reserves to itself the right to accept or reject any or all tenders, either in

    whole or in part, without assigning any reason for doing so.

    All the rates mentioned in the tender are inclusive of all taxes / levies / transport charges etc., and

    shall remain firm till completion of work. No escalation in price will be payable for whatsoever reason.

    The tender shall form part of the contract.

    (Dy.General Manager)

    Tamilnadu Region, Coimbatore.

    27.11.2018

    http://www.bankofbaroda.com/

  • Name of Tendering Company:

    Address:

    Mandatory information required for Prequalification of the bidder for Furnishing, Electrical &

    Air-Conditioning works for New premises of Bank of Baroda, SSI Branch, Tirupur .

    Important:

    1 Please type or handwrite in capital letters.

    2 Attach copies of the supporting documents.

    3 Please use additional sheets if required.

    Name of the Bidder

    email address

    Telephone number office

    Telephone number office

    Fax no

    Address 1

    Address 2

    City

    Pin code

    Year of Establishment

    Status of the Firm

    Names of the directors/Partners/proprietor :

    Name and address of the Bankers – 1 :

    Name and address of the Bankers – 2 :

    Name and address of the Bankers – 3 :

    Registration number and date with Registrar of

    Companies/Firms :

    PAN Card Number :

    GST Number :

    Turnover for the last 3 years. The average turn over per year should be minimum of Rs.4.5 Lakhs.

    FY 2017-18 :

    FY 2016-17 :

    FY 2015-16 :

    Empanelment with the other Companies/PSUs

  • List number of other staff working in the

    organization :

    Have you in past carried out any works for

    Bank of Baroda or its subsidiaries ? :

    Have you been ever disqualified or levied

    penalty by the Bank in past for non fulfillment of

    the contractual obligations. If yes, please

    provide details in brief.

    Have you been ever been put on a holiday list

    or banded by any public sector units ? if yes

    please provide details in brief.

    Field of activities :

    Main Activity :

    List particulars of minimum 10 successfully

    completed works during last Seven years:

    List Number of Technical staff working in the

    organization :

    I/ We confirm that to the best of our knowledge this information is authentic and accept that any

    deliberate concealment will amount to disqualification at any stage.

    Date Seal and Signature of the Bidder/s.

    Place

  • FORM OF TENDER

    The Deputy General Manager,

    Bank of Baroda,

    Regional Office,

    Coimbatore

    Dear Sir,

    With reference to the tenders invited by you on behalf of The Deputy General Manager,

    Bank of Baroda, Regional Office, Coimbatore for the proposed furnishing of New premises

    of Bank of Baroda, SSI Branch, Tirupur

    I / We the under signed hereby tender and under take to execute the works under the contract as the

    rates quoted by me/us in the schedules of quantities and on the terms and conditions with this

    I / We have carefully studied and understood the plan, drawing, terms and conditions, schedule of

    works and have acquainted myself / ourselves with the site conditions.

    I / We agree to completed the works within 2 weeks including the mobilization period from the

    date of issue of the work order.

    I / We do agree for the amount of 5 ( five) percent of the total amount of work done

    deducted proportionately from the interim bills shall remain with the Bank as retention

    money till the Defects Liability Period is over and the amount shall bear no interest.

    It is understood by me / us that the lowest or any tender will not necessarily be accepted.

    Yours faithfully,

    Signature of Contractor (s)

    Date:

    Place:

    Address:

  • 3. CONDITIONS OF CONTRACT

    1 Tenderers shall sign wherever provided for Tenders not so signed shall be rejected. The

    tenders shall be submitted in sealed covers to the office of The Deputy General Manager,

    Bank of Baroda, Regional Office, 82, Bank Road, 3rd Floor, Coimbatore 641 018 or before

    17.12.2018 upto 3.00 P.M

    2 Tenderers that do not fulfill any of the conditions mentioned herein shall be rejected.

    3 Fluctuations in the prices of any materials or equipment or labour etc., shall not be taken into account

    either for compensation for damage or for extra. The validity of the tender for acceptance shall be 60

    days.

    4 Watch and ward in respect of all plants and machinery at site for use in work shall be the contractor's

    sole responsibility.

    5 The contractor shall have to make his own arrangements to house his labour and staff and for their

    services.

    6 All instructions regarding the execution of work shall be received from the Architects :-

    Ar.S.Karthikeyan, M/s.Karthigeeta and Associates, Coimbatore- 43 / .Owner only. Any other

    instructions issued directly to the contactor by any one else shall not be binding on the owner.

    7 During execution of works the contactor must check his work with the drawings. In case of any

    discrepancy between the actual site conditions and that detailed in the drawings, the matter should

    be brought to the notice of the Architects - Mr.S.Karthikeyan, M/s.Karthigeeta and Associates,

    Coimbatore- 43. his representative before executing the work. The contractor shall be responsible for

    all the errors in this connection and will have to rectify all defects at his own cost, failing which the

    owner reserves all rights to get the same rectified at the risk and cost of the contractor.

    8 The contractor entrusted with the work shall indemnify the owner and the Architects against theft,

    mishaps in construction and injury to workmen, damage to persons, property etc. He shall make

    good the damage at his own expense.

    9 The Owners shall have the power to omit or cancel, add / or alter any item of the work without

    assigning any reason whatsoever and so claim for compensation for damage will be entertained

    for such omissions, alterations and cancellations other than taking into account the cost

    involved for such changes to be plus or minus, and the cost shall be arrived at by the Architects

    taking into consideration the market rate, site condition etc.

    10 Time is the essence of the work. All the works shall have to be completed within the stipulated time

    from the date of issue of work order. If the work is not completed within the aforesaid period, the

    contactor shall pay the owners and the owners shall be entitled to deduct from the money due to

    the said contactors the sum of 1% of contract value per week of delay or part thereof, subject to a

    maximum limit of 10% of the contract amount.

    11 The contractor shall maintain satisfactory progress of work as well as maintain the desired standard

    of workmanship. He shall submit fortnightly progress reports to the Architect & Owner in the format

    approved by the Owner/Architect. If in the opinion of the Architect / Mr.S.Karthikeyan,

    M/s.Karthigeeta and Associates, Architects & Interior Designers, No:100, Jagam Apartments,

    Jawahar Nagar, Bharathi Park No:2, Coimbatore- 43 / Owner the progress is unsatisfactory, the

    Architects shall advise the employer to take possession of the work in as and where condition with 7

    days notice to that effect. The employer shall then complete the entire work and rectify all the defects

    at the contractors cost and consequence.

    12 In case the Owner / Architects are not satisfied with the quality of materials used by the contractors,

    they reserve the right to reject such materials / work and direct the contractors, to procure such

    supplies from agencies they deem fit.

  • 13 It is agreed that if the works are delayed (1) by force majeure or (2) by reasons of any exceptionally

    inclement weather or (3) by reasons of loss or any damage by extensive fire not caused by an act or

    a default on the part of the contractor, by earthquake or civil commotion, strikes or lockouts affecting

    any of the trade employed upon the works then the owner shall make fair and reasonable extension

    of time for completion of works. Upon the happening of any such event, causing delay, the contractor

    shall immediately give notice there of in writing to the owner and the owner in all such eventualities

    agrees, without accepting any contractual obligations in this behalf, to assist the contractor to the

    utmost extent possible to meet the situation. If no such notice as mentioned above is given within 7

    days of happening of such event, no consideration for extra time on this account will be given. No

    claim for damage or compensation will be entertained on this account and the decision of

    Owner/Architect will be final and binding on the parties.

    14 The contractor shall submit the bills for payments along with detailed statement showing the actual

    works carried out under different heads of items. Maximum value of the work for interim payment

    shall be Rs.5 Lakhs. ( Five Lakhs only). The bills for non perishable materials on site may also

    be submitted and the payment by the owners against the same shall be to the maximum extent of

    75% of the value of these materials, solely at the discretion of the owners.

    15 The contractor shall clear the site of works as per the instruction of the Owner/Architects. The site of

    works shall be cleared of all men, materials etc. belonging to the contractor. The site shall be

    delivered in broom clean and neat condition immediately the job is completed. In case of failure by

    the contractor the employer shall have the right to get the site cleared at the risk and cost of the

    contractor.

    16 The contractor shall not without the written consent of the Owner / Architects assign the agreement

    or sublet any portion of work.

    17 The quoted rates shall be all inclusive and cover the cost of all materials, freight, all types of taxes,

    duties, royalties, erection, construction, testing of materials samples brought for approval, settings up

    mock up samples for approval, tools and tackles, plant and equipment, supervision, overheads, profit

    and any other expenditure incurred for completion of work as per drawings and specification.

    18 The final bill from the contactor shall not be entertained under any circumstances without full

    completion of all the items of work. Any work found defective or wrongly carried out, are to be

    rectified or replaced prior to submission of the final bill. It is to be expressly noted that no final bill will

    be held valid in the event of no rectification of defective or wrongly carried out items and the

    completion date shall not on this account be extended. Defects liability period will be effective from

    the day of satisfactory completion of all items of work, as may be certified by the Architects.

    19 In the event of work being executed on holidays and during or beyond the normal office working

    hours which might be required for the completion of the work, within the stipulated time, utmost care

    to be taken not to disturb the normal working of the office, neighbouring offices of such a situation

    exists.

    20 While executing the work, considerable amount of shifting and reshifting of several furniture items are

    likely to be involved. It is also likely that some of the items might be required to be temporarily shifted

    elsewhere in the premises on any other floors. These shall be done by the contractor, and no

    payment against these works shall be separately paid by the Owners.

    21 The Contractor shall acquaint himself with the site conditions, local traffic regulations local authority

    regulations, availability of materials, labor tax structure, etc and quote rate accordingly. No extra

    charge/ increase in rates shall be allowed in any of these or any other account.

    22 The Contractor shall have a competent supervisor on the Site at all the times.

    23 The Contractor and / or his authorized representative will attend all the meetings wherever called

    for and the decision taken in meeting will be binding on the contractor.

  • 24 The Contactor shall extend all necessary help to the agencies of associated works like A/C. works,

    fire detection works and works to be carried out by the landlord's agencies in such a manner that

    they can carry out their works smoothly and the whole finished work must appear absolutely

    integrated. Nothing extra shall be paid on the account whatsoever.

    25 Figured dimensions in all cases to be followed and in no case should they be scaled. Large scale

    details take precedence over small scale drawings. In case of any ambiguity, conflict of

    interpretation, generally the provisions giving more rigorous interpretation shall prevail, and the

    Architect's decisions in this regard shall be final and binding.

    26 In case any Municipal / Local Authorities approval is necessary then it shall be the contractors

    responsibility to get it approved and all expenses incurred thereof shall be borne by them.

    27

    28a

    28b

    In case the local authorities such as Ward Office raise objections in matters of water/electricity

    consumption, debris disposal etc the contractors shall solve the matter at their end without involving

    or putting financial liability on the Owners.

    The contractor shall be bound to carry out any extra items of work, and wherever possible, the rate

    for extra item shall be derived from the rate already quoted, otherwise the rate shall be worked out at

    cost of material + labour + 15% towards overheads, wastage, transportation and profit.

    Rate for extra items (readymade) directly bought by the contractor shall be allowed based on cost of

    material + profit @ of 10% of cost material.

    28c Variation and extra items if any, upto a value of Rs. 5000/- shall be carried out under specific written

    instructions by the Architects. However, such items of value in excess of Rs. 5000/- shall be carried

    out under prior sanction by the Owners. Sanction for all items shall be sought by the contractor

    within seven days from the occurrence of such necessity.

    29 The rates shall be entered in figures as well as in words.

    30 Water for consumption by the contractor is to be arranged by the contractor at his own

    cost.

    31 The contractor shall be given a single electrical connection at the work site. Electrical charges for

    consumption will be charged separately by Bank of Baroda at the applicable rate.

    32 When the works are complete in all respects, the contractor shall intimate in writing to the Architect

    and the Owner to enable the Owners to take the possession of the same. The works shall not be

    considered virtually complete until the Owners and the Architects have jointly inspected the works

    and certified in writing that this has been completed.

    33 Unless otherwise instructed, the contractor shall insure the work and keep them insured

    comprehensively, against loss or damage by fire and / or earthquake and flood, until the virtual

    completion certificate is used. The insurance must be placed with a company approved by the

    Owners in the joint names of the Owners and the contractor for such amounts and for any further

    sum if called to do by the Owners. The premium for such further sum shall be allowed to the

    contractor as an authorised extra. All the Owners supplied items forming a part of erection contract

    shall basically constitute these further sum once they are handed over to the contactor from the

    Owners stores. The contractor shall deposit the policy along with all amendments and the receipts for

    premium paid with all amendments and the receipts for premium paid with the Owners within 10 days

    from the date of issue of work order unless otherwise instructed.

    34 All quantities mentioned in the BOQ are approximate and contractor will not claim any damages for

    increase / decrease in profit.

  • 4. APPENDIX 'A'

    1 Estimated cost of Work :

    2 Date of Commencement : Immediately with issue of work order.

    3 Date of Completion : 2 weeks ( from the date of issue of work order.

    4 Liquidated Damages : 1%of the accepted contracted value per week of

    delay or part thereof subject to maximum of 10%

    : of the accepted contract value.

    5 Defects Liability period : 12 months

    6 Value of work for interim payment : Rs.500,000/-

    7 Retention Money :

    8 Retention after virtual completion against d :

    5% of value of work (in addition to Earnest money

    and Security deposit) to be deducted from the

    running bills

    5% of the total billed (certified) amount to be

    refunded on successful completion of defect

    liabilities period of 12 months.

    9 Period for honouring certificates the for : payment by the employer.

    10 Period for honouring final bill. :

    15 days (after receipt of certificates from Architects

    by the Owner.)

    20 days after receipt of certificate from the Architect.

    11 We agree to the terms incorporated in the above 'Appendix' - 'A'

    Date: Signature of Contractor (s).

  • 5. GENERAL SPECIFICATIONS for Furnishing Works

    These specifications are for work to be done, items to be supplied and materials to be used in the

    works as shown and defined on the drawings and described herein, to the satisfaction of the Owner /

    Architect

    1 GENERAL:

    1.1 The workmanship is to be the best possible and of a high standard. The contactor shall take all steps

    immediately to make up deficiency if any noticed by the Owner / Architect. Use must be made of

    special tradesmen in all aspects of the work and allowance must be made in the rates for the same.

    1.2 The materials to be provided by the contractor shall be in accordance with the samples already got

    approved from the Owner / Architect by the Contractor and in conformity with specification and

    approved list of manufactures and brand. The contractor shall produce all invoices, vouchers or

    receipts for any materials if called upon to do so by the Owner / Architect.

    1.3 Samples of materials are to be submitted to the Owner / Architect for their approval before

    the contractor orders or delivers the materials to the site. Samples together with their

    packing are to be provided free of charge by the Contractor and should any materials be

    rejected they will be removed from the site at the contractors expense.

    All samples will be retained by the Owners / Architects for comparison with materials which will be

    delivered at site. Also the contractor will be required to submit specimen finishes of colours, fabrics

    etc. for the approval of the Owners / Architects before proceeding with the works.

    1.4 The contractor shall be responsible for providing and maintaining temporary covering required for the

    protection of finished work. He is also to clean out all wood shavings, cut ends and other waste from

    all parts of the works before covering or infillings are constructed.

    1.5 All guarantees & warranties provided by manufacturer of all products used are to be handed over in

    original to the owner on completion of work.

    2 Joinery in wood work:

    2.1 The contact surface between internal frame and skinning shall be glued with approved adhesive in

    addition to fixing with necessary screws etc.,

    2.2 After preparing proper surface of skinning by sand-papering etc., the laminates or veneers shall be

    fixed on it with the help of approved adhesives.

    2.3 Framework for full height partitions shall be rigidly fixed to the floor, walls, and ceiling soffit. The

    partition height shall be measured upto bottom of false ceiling and framing members /ply going

    above the ceiling shall not be measured.

    2.4 Any portions that are warped or found with other defects are to be replaced. The whole of the work is

    to be finished in accordance with the detailed drawings and the direction of Owner / Architect.

    2.5 All joints shall be standard mortise and tenon, dowel, or cross halved. Screws, nails etc. will be of

    standard iron or wire. Tenons should fit the mortise exactly.

    2.6 Nailed or glued butt joints will not be permitted.

    2.7 Wherever screw heads are on a finished surface, those will be sunk and the hole plugged with a

    wood plug of the same wood and grain to match the colour.

  • 3 Timber:

    3.1 All the wood to be used shall be properly seasoned, of natural growth and shall be free from worm

    holes, loose or dead knots or other defects. Wood will be sawn square and shall not suffer warping

    splitting or other defects. Teakwood & Malaysian Sal should be of Ist quality.

    3.2 The moisture content shall not exceed 12%

    3.3 All internal frame work shall be treated with approved wood preservative and with fire retardant

    treatment / paint.

    3.4 All wood brought to site should be clean & not have any preservative or coating.

    3.5 All rejected or decayed wood shall be immediately removed from site

    3.6 All the dimensions mentioned for T.W. members are finished sizes.

    3.7 All T.W lipping & beading samples are to be approved by architects before usage.

    4 Plywood:

    4.1 Waterproof Plywood shall generally conform to BIS 303-1989, bonded with phenol formaldehyde.

    Commercial plywood shall generally confirm to BIS 303-1989,

    formaldehyde.

    bonded with melamine urea -

    5 Block board:

    5.1 All block board specified will be phenol formaldehyde bonded, confirming to BIS 1659-1990.

    6 Hardware and Metals:

    6.1 All the screws / bolts with nuts to be used shall have oxidized finish (unless required otherwise) of

    approved shape, size, and quality.

    6.2 Samples of all hardware are required to be approved by in advance.

    6.3 The agency should protect all hardware with suitable material as necessary and subsequently clean

    it at the time of handing over.

    6.4 All hardware shall be fitted with good workmanship without the surroundings edges being damaged.

    6.5 All castors shall be approved make, quality and type. They shall be glass reinforced nylon castors.

    7 Laminate:

    7.1 All laminates shall be 1.5mm thick of approved make.

    7.2 The contractors shall get the sample showing the surface texture, pattern and colour

    approved, by Owners / Architect.

    7.3 All laminate edges should be exposed. All laminate, plywood and block board edges will be covered

    with TW lipping / beading as specified.

    8 Glazier:

    8.1 All glass is to be approved manufacture, complying with BIS 2835 - 1977, or as per approved quality

    and sample. Glass to be of the qualities specified and free from bubbles, air holes, waviness and

    other defects.

    8.2 In cutting the glass, proper allowance shall be made for expansion.

    8.3 Glass for mirror shall be silvering quality (SQ) conforming to BIS 3438 - 1977 or as approved

    samples and quality.

  • 8.4 On completion, glass surfaces shall be cleaned inside and out, all cracked, scratched Glass /

    mirror shall be replaced.

    9 Paints and Polishes:

    9.1 All materials required for the works shall be specified and approved manufacture, delivered to the

    site in the manufacturer's containers with the seals, etc., unbroken and after use empty containers

    shall be stored till finally cleared by the Owners.

    9.2 All iron or steel / metal surfaces shall be thoroughly scraped and rubbed down with wire brushes and

    shall be entirely free from rust mill scale, etc. before applying the primary coat.

    9.3 Enamel paint to plywood & melamine polish to wood surfaces to be done using approved putty

    and techniques and paint from approved manufacture.

    9.4 Painting works shall be of high standard without any brush marks on the finished surfaces

    and nose parts on adjacent furniture, glass etc.,.

  • 5. GENERAL SPECIFICATIONS for Electrical Works

    I GENERAL

    a. This specification applies to all medium voltage power distribution control panels / meter boards /

    equipments / materials covered in the quantities / schedule of items.

    b. All the panels, distribution / control boards, meter boards and equipments / materials covered in the

    'Schedule' include design, manufacture, supply, installation, erection, testing and commissioning.

    These items also include making trenches / ducts, foundation, making recess in walls wherever

    necessary, fixing the distribution boards flush with the finished wall surface to plumb and proper

    levels, finishing masonry work that has been disturbed for electrical works making all the cable

    connections both incoming and outgoing earthing connections, providing cable supports, suitable

    covers for trenches / ducts inside the buildings, necessary fasteners, painting, writing the names of

    feeders etc. with paint and any other minor work incidental to the main work of installation and

    commissioning as directed by the Engineer in charge.

    c. The requirements of the power panels and distribution boards are clearly indicated in the 'Schedule'.

    The contractor shall prepare and submit to the 'Employer' for their approval the drawings for all the

    panels, distribution / control boards before fabricating them. The supplies should be as per approved

    drawings.

    d. All the equipments, power panels, distribution / control boards and meter boards shall be

    manufactured fully complying with the requirements of the relevant Indian Standard Specifications of

    latest issue.

    II SWITCH GEAR

    a. All the switchgear items such as MCCBs, SFUs, change over switches, MCBs, CTs, Meters, SFUs,

    Neutral links, indication lamps, Relays, Capacitors, Bus bars, internal connections, terminals for

    external cable connections etc., shall be housed in suitable cubicles as required. Design,

    construction, enclosures, doors' interlocking, earthing, marking and testing shall be in accordance

    with IS:3427 and the degree of protection shall be IP 54 of IS:2147. Clearance between phases and

    between phases and neutral and earth shall not be less than 25mm.

    b. There shall be a separate cubicle / compartment for each incoming side. The outgoing feeders and

    controls may be arranged in a multi-tier form of cubicles with provision for 1 or 2 more future

    additions. The height of cubicles shall not be more than 2mt. All or some of the incoming and

    outgoing cables shall be either at the bottom or top of the cubicles necessitated by site conditions

    and this shall be studied and determined before fabrication and assembly of the cubicles.

    c. All doors shall be hinged type except bus bar chamber covers which shall be bolted type. Suitable

    inter-locking arrangements shall be provided between the front cover / door of MCCB/SFUs so that

    the front cover is openable only when the main switch gears are in 'OFF' position.

    d. Wiring for metering, indicator lamps and control circuits shall be done with 1100V grade,

    stranded, tinned annealed copper conductors and PVC insulated. For measuring circuits, 2.5

    sq.mm size and for other circuits 1.5 sq.mm size wires shall be used. Coloured cables shall be

    employed for identification of phases and neutral. Wiring shall be neat and properly clamped.

  • III

    a

    b.

    SUB SWITCH BOARDS (SSB/PDBs) AND LIGHTING DISTRIBUTION BOARDS

    (LDBs), SERVICE / METER BOARDS

    All the SSBs, PDBs, LDBs, Service/Meter Boards shall be of robust construction and suitable for

    flush mounting on walls / floor. Compartmentalised and fabricated out of 16 swg sheet steel with M.S

    angles and channels of suitable sizes wherever necessary, totally enclosed, fully gasketted, dust and

    vermin proof, removable top and bottom plates with suitable knock-outs at appropriate locations for

    entry of 20, 25 and 40 mm dia, PVC/MS conduits, hinged front doors (single or two half doors

    depending upon the size of the board) with locking arrangement, two earthing terminals etc.

    Service / Meter boards housing front operated SFUs, terminal blocks, sealable fuse cut outs, KWH

    meters etc., shall be provided with suitable arrangements for locking and sealing front door. Suitable

    cut outs and glass windows in front of KWH meters shall be provided for taking readings and

    watching meter's working. this should be strictly as per TNEB Requirements.

    IV MINIATURE CIRCUIT BREAKER (MCB) AND ISOLATORS MCBs are required for both 3 phase and single phase in TPN and SPN grouping for "ON LOAD"

    switching operation and also protection of distribution circuits of 440 V against over load and short

    circuit faults. Actual requirements viz combination, current rating, number of sets etc. are given in the

    "Schedule". The MCBs shall conform in all respects to IS:8828 and have short circuit rating of 9 KA,

    as specified.

    V WIRING All the interconnections between the incoming, bus and outgoing of 100A and above rating shall be

    done by insulated copper strips of suitable sizes. Switch fuses and equipments below 100 A rating

    shall be wired with insulated copper conductors. The wiring for instruments, protection and control

    equipment shall be carried out by means of pressure clamps, special washers, etc. The wiring shall

    be terminated by using crimping sockets. Wiring shall be laid out neatly in bunches which are firmly

    fastened to the steel members of the panels. All the potential circuit shall be protected by fuses

    mounted near the top off point form the main connections.

    VI EARTHING The panels shall be provided with Tinned copper earth bus running through the length of the switch

    board. The earth bus shall be projected on either side of the panel with suitable size bolts at the end

    shall be provided to connect the same to the earth grid at the site.

    VII INSPECTION At all reasonable times during manufacturing and prior to despatch the supplier shall provide and

    secure for purchasers representative every reasonable access and facility at their place for

    inspection approval.

    VIII DEVIATION Any deviation in Technical / commercial can be communicated along with the bid. However, the bank

    reserves right to accept (or) reject.

  • MODE OF MEASUREMENT for Furnishing Works 1 Doors & windows:

    Clear areas over one face inclusive of frame shall be measured. Hold fasts and portions embedded

    in masonry or flooring shall not be measured.

    2 Grills: Clear area of grill shall be measured.

    3 Partitions in Woodwork The partition height shall be measured upto bottom of false ceiling and framing members / ply going

    above shall not be measured.

    4 Decorative panelling over wall: The area of cladding shall be measured in square metres. The gross area covered will be measured.

    5 False Ceiling: For false ceiling work, the measurement shall be for the actual area covered. No deductions shall be

    made for cut-outs for light fittings, speakers etc.

    6 Wood work: For conversion of inches to feet & cm to metre, the resultant figure shall be taken upto two digits after

    decimal point. Third digit shall not be taken into account.

    7 Boxing of Windows: Actual area of boxing will be measured. Size of wooden frame will not be included in the

    measurement.

    8 Storage Units:

    Area will be calculated as length, measured on front face multiplied by height of unit.

    9 Paintings:

    Windows & grills: Clear area of front face shall be measured. It will include painting rebates in frame,

    shutters, beadings & both sides of grill.

    Walls: Area of wall upto bottom of false ceiling will be measured. No separate quantity for cornice will

    be measured.

  • LIST OF APPROVED NOMINATION MANUFACTURERS / BRANDS

    NOTE:

    1 All materials shall be of the 1st quality and wherever possible ISI marked. If ISI mark is not available,

    it should conform to BIS specification

    2 Wherever contractor proposes to use equivalent makes (i.e. other than specified), the same shall be

    done after prior approval of the Owner / Architect. Any additional expenditure and time due to this

    shall be solely on contractor's account and no claims whatsoever shall be entertained, in this regard.

    3 Read, " or equivalent approved " at the end of the list of approved manufacturers / brand for every

    material.

    S.N o MATERIAL APPROVED MANUFACTURER / BRAND

    1 Gypsum board & accessories India Gypsum Ltd.

    2 Plywood Uniply, Sharon, Greenply

    3 Block board Sharon, Century

    4 Laminate Sundek, Formica

    5 Screws GKW

    6 Paints Asian Paints, ICI, Berger

    7 Wall putty NCL Altek

    8 Wood Preservatives Wood guard / Termisil

    9 Adhesive Fevicol, Vamicol, Araldaite

    10 Aluminium hinges & tower bolts Jyoti

    11 Brass hinges & latch Vardhaman

    12 Door handles, knobs Kich

    13 Locks Ebco, Ekri, Godrej

    14 Drawer Slides, sliding hardware,

    Telescopic slides & spring clips

    Ebco, Blum

    15 Door Closers Everite

    16 Castors Zipco

    17 Glass Asahi, Modiguard

    18 Toughened Glass Impact Safety Glass, Bangalore.

    'Shejal Glass, Mumbai.

  • 6. MAKE OF COMPONENTS APPROVED: for Electrical Works

    MODULAR SWITCHES - ANCHOR (ROMA) / MDS / TOYAMA

    MCBs & ELCBs - HAVELLS /L&T (HAGER) / SIEMENS / STANDARD

    PVC WIRES (FRLS ONLY) - FINOLEX / HAVELLS / RR KABEL

    PVC CONDUIT PIPE - VASAVI / AVONPLAST

    RJ11 & RJ 45 - HCL / D - LINK / KRONE / TOYAMA

    TELEPHONE CABLE - RR KABEL / HAVELLS / FINOLEX

    EXHAUST FAN - CROMPTON / GEC / ALMONARD

    LT UG CABLE - PARAGON / FORT GLOUSTER /HAVELLS

    Notes:

    1 The bidders are instructed to visit proposed premises of the above said branch before submitting the

    offers.

    2 Care must be taken during execution that the total load should be equally distributed in all the 3

    phases.

    3 All earth joints must be properly tinned and connected with suitable GI bolt, nut, etc., as per

    standards.

    4 Suitable tinned earth bus should be provided where ever necessary for connecting the different earth

    leads.

    5 For connecting the earth leads to the earth bus suitable sockets should be used.

    6 Using of PVC / MS flexible hoses should be avoided.

  • 6. PREAMBLE TO SCHEDULE OF QUANTITIES

    IMPORTANT NOTE:

    IT IS TO BE EXPRESSLY NOTED THAT SPECIFICATIONS WILL PREVAIL AND SUPERSEDE

    THE DRAWING IN CASE OF ANY INCONSISTENCY / DIFFERENCE IN BETWEEN THE

    SPECIFICATION AND THE DRAWINGS.

    THE TENDERER IS REQUIRED TO PERUSE CAREFULLY ALL PARTS OF TENDER DOCUMENTS

    AND DRAWINGS. IF ANY DIFFERENCES / INCONSISTENCY IS NOTICED, HE SHALL BRING IT TO

    ATTENTION OF BANK OF BARODA / ARCHITECT & GET THE REQUIRED CLARIFICATIONS

    BEFORE SUBMISSION OF TENDER. FAILURE TO DO SO WILL NOT ENTITLE THE SUCCESSFUL

    TENDERER TO PREFER ANY CLAIMS FOR EXTRA PAYMENTS LATER.

    1 The tenderer is required to inspect the site of the work and ascertain for himself site conditions,

    facilities available and other aspects before quoting for the work. The tenderer is also required,

    before quoting, to carefully peruse the tender documents, the tender drawings and connected details

    so as to understand clearly the scope and intent of the tender. Any claims by the successful tenderer

    at a later date on account of the failure to comply with the above instructions will not be entertained.

    2 The tenderer should note that the furniture and connected works are to be carried out and installed in

    the existing building. The tenderer should note that he should execute his part of the work with out

    causing any damage to any component of the building or services. Any damage so caused shall be

    made good at the cost and risk of the successful tenderer /contactor. The successful tenderer should

    protect all other items of work of other agencies, such as flooring, electrical work etc., from any

    damage shall be responsible for final clearing of the floor, walls etc., before handing over. No extra

    is payable toward this. The successful tenderer shall include this rate all minor civil works such as casing wall,

    drilling hooks etc., and making good and no extra is payable toward this. Neat house

    keeping at all shapes of work is the responsibility of the successful tenderer, who shall also

    ensure that removal of debris, wood shaving, waste materials etc., from the site at his own

    cost is organised at regular basis. The successful tenderer shall also responsible for safety and

    security of all this materials and also for ensuring fire prevention steps are taken at all

    times.

    3 The tenderer should note that the tender drawings and other documents describing each item of the

    schedule are only indicative in nature and cannot be taken as complete in detail. The tender being

    for furniture works, calls for good workmanship and finish including use of good quality materials of

    high standard.

    The tenderer should understand the intent of the tender drawings and specifications and provided for

    materials, workmanship finishes and accessories appropriately, so as to deliver the product of high

    standards in keeping with the function for which the furniture is designed. No claim from the contactor

    at a later date will be entertained for his failure to understand this requirement. The decision of Bank

    of Baroda / Architect in respect of the quality of materials, type of fabrication / assembling,

    workmanship, finish, etc., shall be final and binding on the contractor. No claim for such materials,

    construction, workmanship and finish can be entertained.

    4 Bank of Baroda /Architect reserve the right to insist on selection of material, workmanship detailing

    and finishes which they consider are appropriate, and suitable for the intended use for which the

    contactor is not eligible for any extra claim on this account.

    5 Bank of Baroda /Architect reserve the right to insist on proto-type to be made for approval before

    starting the full fledge manufacture of each type of the furniture.

    6 Bank of Baroda / Architect reserve the right to suggest or make modification at the prototype stage,

    which shall be complied with any extra cost.

  • 7 Bank of Baroda / Architect will required the contactor to produce samples of all materials accessories

    / finishes prior to procurement / manufacture. Failure to comply with these instructions can result in

    rejection of the work.

    8 Furniture item shall be guaranteed for a period of one year from Bank of Baroda's acceptance for

    covering materials, workmanship and finish. Any defects or shrinkage, warping or other forms of

    deterioration shall be made good by the contactor at his own cost within the guarantee period,

    immediately on being informed of such defects failure to comply will entail Bank of Baroda to

    unilaterally decide on getting the repair done through other agency at the cost and risk of the

    contractor.

    9 The contactor should use only the best material. Teak wood or other timber specified shall be of the

    best quality, free of defects of any kind. All plywood, block board, laminate etc., shall comply with

    respective I.S standard. If required by Bank of Baroda / Architect, the contactor shall arrange for

    testing the products or produce test certificate from recognised testing houses to establish the quality

    of materials at his own cost. Any defective material not meeting with the standard shall be replaced

    at the contractor's own cost.

    10 Tenderers Shall indicate the makes of the finishing materials such as: a) Plywood / Block board

    b) Laminate.

    c) Hardware fittings

    d) Screws.

    e) Wall putty & paints.

    along with the tender preferably with samples of catalogues, based on which rates have been

    quoted. The tenderer should be prepared to produce samples for not furnished with the tender when

    called for before consideration of the tender further on his own cost and responsibility and without

    any liability on Bank of Baroda.

    11 The dimension of furniture provided in the schedule as well as in the drawing are likely to vary slightly

    according to the site of space available in the respective rooms where they are to be provided or

    placed. Bank of Baroda / Architect have the right to slightly modify the dimension of furniture items

    for which no extra claim shall be entertained.

    12 The quoted rates shall include all materials, labour, furniture fittings, accessories of matching

    type with the main furniture, transport to site, all taxes (central, State and Local Taxes) and

    fixing at the specific places in the building complete. Rate should include cost of keeping the

    works insured as well as other Insurance requirements.

    13 Non-compliance of any of the above requirement will entail summary rejection /dispensing with the

    contract at any stage of progress of work.

    14 Enamel paint will be approved brand and will be applied as per manufacturer's specifications.

    If at the time of handling over, any scratches or deterioration of the finish is observed, Bank of

    Baroda / Architect shall have the right to insist on application of another coat without extra cost.

    Samples of all hardware fittings shall be shown to Bank of Baroda / Architect in advance and

    approval obtained before procurement. Rates such include fixing of mortise locks and door

    closers of best quality make to doors of cabins, etc., besides all hardware fittings. All

    exposed Teakwood members shall be given approved coat of automotive paint. All wood

    work concealed or covered by other materials shall be given approved enamel paint coating.

    15 In all case measurement will be made on net items in complete shape as manufactured,

    supplied and installed. Measurement to items such as false ceiling shall be taken for actual

    area laid to suit the shape and size of the room. The tenderers should note that they shall absorb

    all cutting wastage, etc., within the quoted rates and no separate payment will be made for

    the same. The tenderer shall have to make sure that they protect their materials and hand

    them over in good shape satisfactory to Bank of Baroda / Architect.

  • At the time of handling over any damages, scratches, dents or other such defects shall be

    rectified as directed without any extra charge by the tenderer / Contractor to the satisfaction of

    Bank of Baroda bank of India / Architect.

    16 Bank of Baroda / Architect reserves the right to reject any tender without assigning any reason. Bank

    of Baroda / Architect reserves the right to split the scope of the work for award to more than one

    tenderer at their discretion. Bank of Baroda / Architect reserves the right to modify thereafter the

    scope of the work. Tenderer / contractor shall not have not any claim on account of the above.

    17 The time of the completion of the entire work shall be 2_ weeks from the 7th day of the date of work

    order. Incase of splitting of work to more than one agency, the time of completion shall be suitably

    reduced. Bank of Baroda shall levy penalty / liquidated damages as per the conditions of the contract

    for delayed progress or work at different stages, final completion of work as the case may be

    18 All rates quoted shall include high quality hardware fittings and specials such as hinges, tower bolts,

    mortise lock, door closers, door handles, drawer pulls, drawer sliding accessories, sliding door gears

    and specials etc., and no extra cost is payable for these hardware fittings. Samples of the

    hardware fittings shall be approved by Bank of Baroda / Architect well in time, before procurement.

    19 Tenderer should note that for the sake of convenience, only entire description has been furnished of

    Quantities. For detailed description of each item a separate list of detailed description has been

    furnished. Both are complementary in nature and shall be read together for each item with

    corresponding cross-reference.

    Place:

    Date: Signature of Tenderer / Contractor.

  • TENDER AMOUNT

    Furnishing Works for Bank of Baroda, SSI Branch, Tirupur .

    Electrical Works for Bank of Baroda, SSI Branch, Tirupur .

    AC Works for Bank of Baroda, SSI Branch, Tirupur

    Add GST

    Grand Total Amount for all Works for the Branch

  • SCHEDULE OF QUANTITIES

    Name of the work :- The proposed Furnishing Works for the New Premises of Bank of Baroda, SSI Branch,

    Tirupur .

    No. Description of work Size /Qty

    Unit Rate Amount

    PARTITION:-

    1 Entrance Door/ Partition (Fully Glazed): Fully Glazed Entrance door with toughened 12mm thick glass fixed using

    30

    1 sq. ft.

    patch fittings, required hardware etc. complete.

    Size of opening: (4' 0"x 7' 0")

    2 Fully Glazed Partition (Manager Cabin):

    Full height glazed partition for Manager cabin as per plan to be done 340 1 sq. ft.

    using 4"x3" wooden frames for alround fixed with 12mm glass upto 7'0"

    ht.. Door to be done in the same specification with full glass including

    frosted design and provided with door closures, locks, handles and other

    accessories.

    3 Wicket Gate Size - 3' 6"x 2' 6"

    Wicket door and partition made 2" x 2" wooden frame covered with 6mm 1 no

    plywood on both sides finished with same lamination, edges are finished

    with teak wood beadings neatly painted.

    4 Non Glazed Partition:

    Non glazed partition for dining and record rooms, UPS, Backside 360 1 sq. ft.

    partition & Strong room partitions to be done using 21/2" x 21/2" Salwood

    frames good quality, fixed with 8mm plywood and both side 1mm

    laminated sheet (approved colour). Door to be done in the same

    specification including locks, handles and other accessories.

    b) Credit Section Partition 540 1 sq. ft.

    FURNITURE & WOOD WORKS:-

    5 Writing ledge:

    Writing desk to be done as per plan with 12mm glass topped with pigeon 1 no

    holes made with 18mm plywood structure with additional boxing as per

    design, finished with 1mm laminate outside and painted inside.

    Suggestion / complaint box with view glass and locking provision and

    cheque drop box in same manner to be provided along with the writing

    desk. Size: 8' 0" x 1' 6" x 3' 6" ht

    6 Notice Board:

    Made of 12 mm marine plywood with hardwood frame work of Size: 4 x 1 no

    2.5 cm thick. (Enamel paint finish of approved colour) including soft

    board finished with fabric upholstery of approved colour and make as per

    design. Size: 5' 0" x 3' 0".

  • 7 File cabinet : Providing and fixing 1'6" wide storage unit made of 19 mm marine

    plywood finished with1 mm lamination of approved colour & pattern on

    top and all visible sides with shelves inside. All exposed edges are

    finished with hardwood lipping (Enamel paint finish of approved

    colour).Provided openable shutters with SS handles, lock and auto

    closing hinges as per design. All inside portions finished with enamel

    paint of approved colour.

    a Br. manager rear storage of Size 11' 0" x 1' 6" x 2' 6" 28 1 sq. ft.

    b Banking hall - storage of Size: 27' 0" x 1' 6" x 2' 6" - 1 nos 68 1 sq. ft.

    c Credit Section - storage of Size: 14' 0" x 1' 6" x 2'6" - 1 nos 40 1 sq. ft.

    8 Vertical Blinds: 100 mm wide Vertical Blinds of vista leveler/Mac having top rail 39 mm x

    34 mm (1.2 mm thick ). The lower fabric shall be of polyester viscose/

    polyester/ yarn as per approval. (colour - need prior approval from

    Architect)

    320 1 sq. ft.

    b)Credit Section 35 1 sq. ft.

    9 Painting of walls in banking area with 2 coats of plastic emulsion over

    sufficient coat of putty in approved colour and brand. (Only Banking hall)

    2520 1 sq. ft.

    10 FALSE CEILING :-

    a Gypboard false ceiling

    Providing and fixing suspended false ceiling consisting of 12.5mm thick-

    gypsum plaster board suspended on GI frame work to consist of GI

    frame work. GI frame work to consist of GI perimeter channels 0.55mm

    thick 20mmx30mm along perimeter of false ceiling, screw fixed to wall/

    partition with nylon sleeves and screws @ 600mm c/c. Suspending GI

    intermediate channels of size.9mm thick 45mmx 15mm from the soffit at

    max dist 1220mm c/c ceiling angle. 55mm thick 25mmx10mm fixed to

    soffit using proprietary supplied GI cleats and steel expansion fasteners.

    Rate is included for cutouts for lights, smoke detectors and AC grills. The

    ceiling is putty finished and sanded to form clean and homogeneous

    surface. Rate shall include providing and applying of one coat of primer

    and two coats of acrylic emulsion painting.(Banking Hall)

    b)for Credit Section

    b Grid False Ceiling : Providing, fabricating, erecting lay-in type regular/

    drop type Metal false Ceiling of 600mm x 600mm grid with approved

    brands of ARMSTRONG/ ITTOBO. The item shall include the cost of

    additional Tee or L supports & other accessories near the ends/odd size

    edges / corners, Providing additional length support from ceiling to the

    false ceiling grid wherever necessary, making necessary openings for

    electrical light fittings, firm alarm detectors and any other fixtures. No

    extra payment shall be made for making openings in the panels/grid for

    the purpose of light fittings. Item rate shall include all the taxes,

    transportation, erection, loading & unloading and any other incidental

    expenditure that may be required to be spent in completing the work in

    totality as per above specifications.

    975 1 sq. ft.

    150 1 sq. ft.

    750 sq.ft

  • b)for Credit Section 150 1 sq. ft.

    11 Column Paneling:-

    Column Paneling upto 8' 6" height with 11/2"x1" hard wood fixed to the

    250

    1 sq. ft.

    columns/walls and then covered with 6mm plywood and to be laminated

    with 1.5mm thk.laminate of approved make and colour wooden cornice

    of size 3" x 2" has to be fixed on the top edge of wall paneling and

    around the column as per design duly melamine polished of approved

    colour etc.complete

    Grand Total:

  • SCHEDULE OF QUANTITIES

    Electrical Works for Bank of Baroda, SSI Branch, Tirupur .

    AC Works for Bank of Baroda, SSI Branch, Tirupur .

    Total Amount for Electrical & AC Works for the Branch

    Name of the work :- The proposed Electrical Works for the New Premises of Bank of Baroda, SSI

    Branch, Tirupur.

    No.

    Description of work

    Size

    /Qty

    Unit Rate Amount

    A EARTHING

    1 Providing earth electrode all as per IS 3043 with 600 X 600 X

    3.15mm thick copper plate fitted with 2 nos.2.5 mts. long 25 X 3

    3 1 No.

    mm tined copper flat riveted to the plate using copper rivets with

    alink on top with holes drilled for tapping connections with brass

    boly/nut washer etc. including 10 SWG copper wire. A brick

    masonry trough of size 450x450x450mm depth & wall thickness not

    less than 150mm shall be provided with RCC cover. (EB- ! nos,

    Genshed -02 nos)

    2 Supply and laying of 1R 6 Sqmm PVC insulated copper conductor

    wire drawn in 20mm dia PVC pipe from above earth electrodes to

    2 1 No.

    UPS Earth points and terminating both the ends with proper

    crimping type copper sockets. The conduit will be partly in

    underground and partly on wall with necessary clamping.

    3 Supply and run of 10 SWG copper wire for earth (25m for Genshed) 100 mtrs

    B WIRING & CIRCUIT MAINS

    1 Wiring for light, exhaust fan, 6 A socket outlet points

    Wiring for light, exhaust fan, 6 A socket outlet points etc., partly in

    surface conduit with 3 runs (P + N + E) of 1.5 sq mm PVC insulated

    (FRLS) with copper conductor in 20/25mm dia PVC conduit pipes

    with Bend, Couplings, etc. and fixing with PVC clamps screws etc.

    and fixing with false ceiling/ partition/ concealed in the wall 6A

    Modular type etc. plate and metal Box Wiring to be connected with

    supply & fixing of switch MK /ROMA / CRABTREE) with suitable

    Modular switches. ( Wires - Finolex / Havells)

    a Light point wiring - 1 light controlled by 1 no. 6A switch 11 pt

    b Light point wiring - 2 lights controlled by 1 no. 6A switch 18 pt

  • c Call bell point including supplying and call bell buzzer 1 pt

    d Ceiling fan point with step type electronic regulator and anchor

    hook for mounting fan

    e Wall mounting fan point including supplying and fixing 6A socket

    outlet controlled by switch. Socket fixed near the fan

    f Exhaust fan point including supplying and fixing 6A socket outlet

    controlled by switch. Socket fixed near exhaust fan

    2 Wiring for Name Board lighting circuit using 3R 4.0 sqmm PVC

    insulated multi stranded single core copper conductor FRLS wire in

    20mm PVC conduit to be on wall complete with all accessories.

    5 pt

    11 pt

    4 pt

    30 mtrs

    3 Wiring for lighting circuit main partly in surface conduit, with 3 runs

    (P + N + E) 2.5 sqmm FRLS copper wire in 20mm dia. pvc conduit

    pipe. ( Wires - Finolex / Havells)

    270 mtrs

    4 Wiring in surface conduit for 6A socket outlets (Raw power in

    workstation, cabin etc) with 3 runs (P + N + E) 2.5 sqmm FRLS

    copper wire in 20mm dia. PVC conduit pipe. ( Wires - Finolex /

    Havells)

    350 mtrs

    C PANEL BOARD & DISTRIBUTION BOARDS

    1 8 Way SPN Distribution board with neutral bar, earth bar, cables

    ties, top and bottom removable gland plate and with necessary

    adopter boxes if any. The DB should be IP 42 metallic double door

    with provision of MCB & ELCB etc as required including cutting of

    wall and plastering the same with neat finish. It comprising as

    follows:-

    Incomer : 63A 4P MCB - 2 Nos

    40A 4P MCB - 2 Nos

    Outgoing: 6A SP MCB - 8No for Lighting Circuits,

    16A SPMCB - 2Nos for Raw Power

    Circuits,

    a UPS DB Input 40A 4 pole MCB -1 No 1 set

    20 A DB MCB 6Nos

    Enclosure: 4 Way TPN DB

    b

    UPS DB Output 40A 4 pole MCB -1No 1 set

    20 A 5pole MCB 6 Nos

    Enclosure: 4 Way TPN DB

    2 a Supplying and fixing 25 A 3 pin metal plug & socket in suitable Ms 2 1 No.

    enclosure with 1no 25 A SP MCB for A/C unit. ( Havells / MDS

    Brand )

    b Supply & Installation of 40A 4pole Metal Clad Socket with top in a 2 1 No.

    specified company manufactured box with suitable rating MCB for

    connecting A/C.

    3 a Wiring for AC circuit:- Supplying and laying 2 runs of 4 sq.mm + 1

    run 1.5 sq.mm FRLS copper wire in 20mm dia. pvc conduit pipe. (

    150 mtrs

    Wires - Finolex / Havells)

  • b Supply & laying of 4C X 4 Sqmm Cu Flexible Cable 0 mtr

    4 Supplying and fixing of 63A PHASE Rotary with box, 3 nos 1 1 No.

    indication lamps, fixing with proper termination.(in UPS INPUT) (

    Havells Brand )

    5 Supplying and fixing of 125A 4 Pole Phase Rotary with box, 3phase 1 1 No.

    output automatic phase change over switch fixing with proper

    termination.(in lighting main)(Havells).

    D POWER OUTLETS

    1 Supplying and fixing 6A socket outlet controlled switch on the 15 pt

    existing switch control box (board plug point)

    2 Supplying and fixing 3 nos.6A 2/3 pin socket controlled by 3 nos 6A 13 pt

    switch in suitable Box – Modular Type

    3 a Supplying and fixing 1+1 Anchor Roma switch and socket with box

    plate, fixing with proper termination (all counters Raw power plug

    15 1 No.

    points)

    b for printer 2 1 No.

    E CABLES & TERMINATION

    1 Supplying and laying 3 1/2 core 35sqmm Al X LPE cable 1.1 KV 55 mtrs

    grade with aluminium conductor proposed Panel in the Electrical

    room EB to change over, Genset to change over, change over to

    load. ( Finolex / Polycab)

    2 a Providing end termination for the above cable using brass double 6 1 No.

    compression gland and copper cable sockets. Rate should include

    for earthing the cable gland with copper clamp and copper earth

    wire.

    b 4C x 10 Sqmm Copper Armoured Cable (Panel Board to VTPN DB 16 Mtrs

    )

    F LIGHT FIXTURES & FANS

    1 Supplying and commissioning of 11 W LED spot light complete 7 1 No.

    with electronic ballast, matt finish reflector to be fixed in the false

    ceiling including giving connections complete as required. Rate

    should include for all necessary supports for mounting the light

    fittings. ( Havells)

    2 Supplying, erection, testing and commissioning of 2 X 23 W (2' X 25 1 No.

    2') light fitting complete with electronic ballast and 2 nos. 23W LED

    suitably suspended with anchor fastener hook and auto clutch wire

    end clamps. The fitting should be independently supported from

    the ceiling and should not rest on the false ceiling.(Havells )

    3 Supplying and fixing single box type light fitting on surface of wall 18 each

    complete 1 no. 23 W LED Tube light including giving connections

    complete as required. (Havells)

  • 4 Supplying and fixing of 48" ceiling fan with Electronic Regulator 4 1 No.

    (Crompton / Havells)

    5 Supply and fixing of wall mounting fan (Crompton / Havells) 11 1 No.

    6 Supply and fixing of 300 mm Exhaust fan( Crompton / Havells) 5 1 No.

    G Telephone cabling

    1 Supplying and laying 25 mm dia. 2 mm thick rigid PVC conduit pipe

    complete with all accessories with GI pull wire for data socket

    outlets. Conduit embedded in floor/wall using cutting machine as

    per site requirement. For TELEPHONE & DATA & generator's

    neutral earth

    2 Supplying and fixing 20pair krone connector housed in a heavy duty

    ABS plastic body with suitable locking arrangement.

    3 Supplying and laying 3 pair 0.5 sqmm telephone cable with tined

    copper conductor in the above conduit. Rate should include for

    providing necessary identification with cable marking ferrules.

    (Cables - Finolex )

    4 Supplying and fixing 1 no.RJ 11 telephone socket for other areas. (

    MK / Anchor Roma)

    450 mtrs

    1 1 No.

    100 mtrs

    13 1 No.

    5 Supply and laying of 0.5mm dia copper conductor, PVC insulated 5

    pair telephone cable through the PVC conduit.

    6 Supply, Installation, testing and commissioning of special quality

    ceiling ring speaker in plastic mould with line matching transformer.

    7 Supplying and laying 2 core 24/0.2 mm ATC twin twisted speaker

    35 Mtrs

    4 1 No.

    90 mtrs

    cable in the above conduit including giving connections

    H

    1

    DATA CABLING

    Supply & laying of E-Cat 6 RJ 45 UTP Cable

    300

    1 m

    2 Supply & providing of RJ 45 Patch Cords – 7 Feet 13 1 No.

    3 Removal and refixing, testing & commissioning of 6U rack. 1 1 No.

    4 Removal and refixing, testing & commissioning of 24 port switch 1 1 No.

    5 Supply & installation of RJ 45 Information Outlets 13 1 No.

    Total

  • SCHEDULE OF QUANTITIES

    Name of the work :- The proposed AC Works for the New Premises of Bank of Baroda, SSI Branch,

    Tirupur .

    No.

    1

    Description of work

    Supply, Installation & Commissioning of split Air conditioners

    with copper coils & 5 star rating including adequate range of

    stabilizers including drain pipe, Mounting rack for placing AC, etc.

    Size

    /Qty

    Unit Rate Amount

    GRAND TOTAL ELECTRICAL & AC

    complete. Brand - Voltas / Blue Star / Daiken Make

    a Banking Hall - in ceiling (Cassette type) 3 4 ton

    b drain pipes 60 1 m

    c copper coils 60 1 m

    2 Supply, Installation & Commissioning of Hi wall split Air

    conditioners with copper coils, stabilizers including drain pipe, rack

    for placing AC, etc. complete to new premises.

    a Manager cabin 1 No. 1 ton

    b Credit Section 1 No. 2 ton

    Total

  • Furnishing, Electrical & Air conditioning Works for New premises of Bank of Baroda, SSI Branch, Tirupur . NP Complex, No:323, Avinashi Road, Tirupur – 641602Mandatory information required for Prequalification of the bidder for Furnishing, Electrical &

    FORM OF TENDERSignature of Contractor (s)

    3. CONDITIONS OF CONTRACT4. APPENDIX 'A'5. GENERAL SPECIFICATIONS for Furnishing Works3.5 All rejected or decayed wood shall be immediately removed from site

    SUB SWITCH BOARDS (SSB/PDBs) AND LIGHTING DISTRIBUTION BOARDS (LDBs), SERVICE / METER BOARDSIV MINIATURE CIRCUIT BREAKER (MCB) AND ISOLATORSV WIRINGVI EARTHINGVII INSPECTIONVIII DEVIATIONMODE OF MEASUREMENT for Furnishing Works2 Grills:3 Partitions in Woodwork4 Decorative panelling over wall:5 False Ceiling:6 Wood work:7 Boxing of Windows:8 Storage Units:9 Paintings:LIST OF APPROVED NOMINATION MANUFACTURERS / BRANDSS.N o MATERIAL APPROVED MANUFACTURER / BRAND6. PREAMBLE TO SCHEDULE OF QUANTITIESPlace:

    SCHEDULE OF QUANTITIESSCHEDULE OF QUANTITIES (1)No.No. (1)Description of work