Marked for review 1. ________ is typically not referred to as a buffer type in Critical Chain project management. Resource buffer Free buffer Feed buffer Strategic resource buffer 2. A company has to make a choice between two projects, because the available resources in money and kind are not sufficient to run both at the same time. Each project would take 9 months and would cost $250,000. 1. The first project is a process optimization which would result in a cost reduction of $120,000 per year. This benefit would be achieved immediately after the end of the project. 2. The second project would be the development of a new product which could produce the following net profits after the end of the project: 1. year: $ 15,000 2. year: $ 125,00 0 3. year: $ 220,00 0 Assumed is a discount rate of 5% per year. Looking at the present values of these projects' revenues in the first 3 years, what is true? Both projects are equally attractive. The first project is more attractive by app. 7%. The second project is more attractive by app. 5%. The first project is more attractive by app. 3%. 3. A production process has been defined as part of an industrial equipment manufacturing project. The process is intended to produce steel bolts with a length of 20 cm. The control limits are 19.955cm and 20.045cm.

Upload: mynafipmp5283

Post on 30-Dec-2015

37 views

Category:

Documents


0 download

DESCRIPTION

PMP 70 Free Questions & Websites

TRANSCRIPT

Page 1: 70 Free Questions & Websites

Marked for review

  1. ________ is typically not referred to as a buffer type in Critical Chain project management. 

Resource buffer

Free buffer

Feed buffer

Strategic resource buffer

  2. A company has to make a choice between two projects, because the available resources in money and kind are not sufficient to run both at the same time. Each project would take 9 months and would cost $250,000.

1. The first project is a process optimization which would result in a cost reduction of $120,000 per year. This benefit would be achieved immediately after the end of the project. 

2. The second project would be the development of a new product which could produce the following net profits after the end of the project:

1. year:       $ 15,0002. year: $ 125,0003. year: $ 220,000

Assumed is a discount rate of 5% per year. Looking at the present values of these projects' revenues in the first 3 years, what is true? 

Both projects are equally attractive.

The first project is more attractive by app. 7%.

The second project is more attractive by app. 5%.

The first project is more attractive by app. 3%.

  3. A production process has been defined as part of an industrial equipment manufacturing project. The process is intended to produce steel bolts with a length of 20 cm. The control limits are 19.955cm and 20.045cm.

The measurements made at the end of the process yielded the following results:

20.033cm, 19.982cm, 19,995cm, 20.006cm, 19.970cm, 19.968cm, 19.963cm, 19.958cm, 19.962cm, 19.979cm, 19.959cm.

What should be done? 

The process is under control. It should not be adjusted.

Page 2: 70 Free Questions & Websites

A special cause should be investigated, the process should be adjusted.

The control limits should be adjusted.

The measuring equipment should be recalibrated.

  4. Your project management team includes two external consultants each from a different company. You found that repeated conflicts between the two consultants already slow down project progress and jeopardize achievement of objectives.Which stage of team development can be difficult to overcome in such a situation? 

Storming from Forming, Storming, Norming, Performing

Panic from Enthusiasm, Panic, Hope, Solution

Kickoff from Assignment, Kickoff, Training, Communicating

Frustration from Direction, Frustration, Cooperation, Collaboration

Marked for review

  5. During a project Earned Value Analysis is performed and gives the following results:

Page 3: 70 Free Questions & Websites

EV: 523,000; PV: 623,000; AC: 643,000.

Which results are correct?

CV: +120,000; SV: +100,000

CV: +100,000; SV: +120,000

CV: -100,000; SV: -120,000

CV: -120,000; SV: -100,000

Marked for review

  6. A project manager spent some days to create a multi-page document which he called Project Charter. The document should have been issued by the project sponsor. The sponsor found the document outsized and asked for a condensed document. 

Which of the following is not normally an element of the Project Charter? 

The formal authorization to apply organizational resources to project activities

Detailed control account and work package descriptions

The business need that the project was undertaken to address

The product description or a reference to this document

Marked for review

  7. A document called ____________ is created by decomposing the project scope into smaller, more manageable elements. 

Page 4: 70 Free Questions & Websites

Scope Statement

Network Logic Diagram

Work Breakdown Structure

Requested Change

Marked for review

  8. Which of the following tools is used to create a Risk Management Plan?

Risk planning meetings

Documentation reviews

Data precision rankings

Diagramming techniques

Page 5: 70 Free Questions & Websites

Marked for review

  9. In order to speed up a project, you made a decision to fast-track a phase currently performed with five team members and another one which was planned to begin in four weeks time with another five team members.

Which of the following activities should you do first?  

Make sure that all exit criteria of the consecutive phase have been met to ensure the flow of communications in a team situation which is more complex by a factor of 2.

Make sure that all entry criteria of the previous phase have been met by planning and performing a phase gate meeting to assess technical aptness.

Make sure that all exit criteria of the previous phase have been met by planning and performing a phase gate meeting to assess technical performance.

Restructure your team and delegate tasks in order to ensure the flow of communications in a team situation which is more complex by a factor of 4.5.

Marked for review

  10. A project manager needs a certain number of identical valve housings for a power station project.

He starts with 100 raw items which are made as metal castings. Out of this batch, 15 are found leaking from micro-porosities in a subsequent pressure test. 6 of these housings can be recovered by a special sealing process for raw castings.

The 91 housings are then being machined. After this process step 10 machined castings are found leaking. 3 of these items can also be saved using another sealing process for machined castings.

The remaining 84 housings are getting mounted to the power plant pipework. During a pressure test after this process step it is found that 12 valves are leaking. Out of these a number of 6 valves can be saved by replacing the sealing rings used.

Page 6: 70 Free Questions & Websites

Finally the project manager has 78 valves which he can use. What is true? 

FTY = 0.91, RTY = 0.84

FTY = 0.65, RTY = 0.78

FTY = 0.84, RTY = 0.91

FTY = 0.78, RTY = 0.65

Marked for review

  11.  You found the following Earned Value Analysis information for a recently closed out project:SPI = 0.7, CPI = 1.0

The project has been cancelled while it was executed. At that time the project was behind schedule and on budget.

The project's deliverables have all been finished. The project came in behind schedule but on budget.

The project's deliverables have all been finished. The project came in ahead of schedule but on budget.

The project's deliverables have all been finished. The project came in on schedule but over budget.

Marked for review

 12. You are working as a project manager for a major US-based public company. This morning you received alarming news that the major strategic project you are responsible for will not be able to provide financial benefits to the organization as expected. This drawback

Page 7: 70 Free Questions & Websites

will significantly influence future profits of the entire corporation. What should you do right now?

You should not overact and check at least three options before making any decisions.

You must immediately inform the corporate management to ensure Real Time Issuers Disclosures.

You should investigate detailed information on the problem before escalating it to corporate management.

You should find a quick solution for the problem and implement this immediately.

Marked for review

 13. In a traditionally drawn decision tree, a circle represents ___________. 

a chance to which no Estimated Monetary Value can be assigned so that a likely pay-off can not be shown.

a decision to which no Estimated Monetary Value can be assigned so that a likely pay-off can not be shown.

a chance to which an Estimated Monetary Value may be assigned to calculate the most likely pay-off.

Page 8: 70 Free Questions & Websites

a decision to which an Estimated Monetary Value may be assigned to calculate the most likely pay-off.

Marked for review

 14. A project management team has subcontracted work to a service company. Which of the following tools is the best choice to assure that this company will be able to meet the quality requirements of the project?

Quality audit

Deliverable inspection

Fixed price contract

Service level agreement

Marked for review

 15. With your team you are using judgment from subject matter experts to identify and analyze project risks. There is a small number of experts available, but some of them have long been in a teacher-student or manager-assistant relationship.

Which of the following techniques can ensure best that there is no dominating opinion during an expert review? 

Peer review

Page 9: 70 Free Questions & Websites

SWOT analysis

Delphi technique

Monetary value calculation

Marked for review

 16. You are running a project for a customer based on a cost reimbursable contract with the following terms: 

Target costs:     $ 1,000,000

Fixed fee: $ 100,000

Benefit/cost sharing: 80% / 20%

Price ceiling: $ 1,200,000

Which is the PTA (= Point of total assumption, Break point) of the project? 

$1,300,000

$1,500,000

$80,000

$1,125,000

Marked for review

 17. During execution of a project which is performed for a customer on a T&M (Time and

Page 10: 70 Free Questions & Websites

Material) contract base, a new project manager is taking over the assignment. 

He discovers that two members assigned to the project have charged time without performing any work for the project customer. Upon further investigation, he determines that this occurred because there have been no other project assignments open for these employees. The customer is unaware of these facts. 

What should the project manager do?

Try to find some productive work for these staff members in the project and leave them on the team.

The best thing is to do nothing. The customer will not realize the problem anyway.

Try to find a responsible person for the over-assignment who can be made accountable.

Take the two people off the team immediately and arrange for the refund of the excess charges to the customer.

Marked for review

 18. In the following network logic diagram start dates are defined as early morning, finish dates are evening.

If tasks are scheduled to begin at early start date, what is true?

Activity B has a free float of 10 d.

Page 11: 70 Free Questions & Websites

Activity B has a total float of 10 d.

Activity A has a free float of 10 d.

Activity A has a total float of 10 d.

Marked for review

 19. Your project is executed with a globally spread virtual team. The project progress has been found to be too slow. Which measure is most likely to immediately speed up the project? 

Technical training for all team members

Daily phone conferences and detailed reporting

A team meeting at a location convenient to all team members

Collocation of team members at a suitable place

Page 12: 70 Free Questions & Websites

Marked for review

 20. A project management team wants to procure some customized products which are available in identical grade and quality from many vendors. What should be included in the procurement package to ensure that their offers will be comparable? 

A statement of work describing the needs of the project in sufficient detail to enable vendors to make suitable proposals

A statement of work specifying attributes and metrics of the requested deliverables in detail to allow vendors submission of bids

The approved project scope statement, the WBS which should be broken down to Work Package level and the WBS dictionary

The risk management plan and the reports from those risk management reviews which have been made so far

Marked for review

 21. What is sometimes referred to as Global literacies? 

The ability to read reports written in many different languages.

The ability to succeed in a cross cultural environment.

Page 13: 70 Free Questions & Websites

The ability to develop internationally accepted contracts.

The ability to communicate using drawings and pictograms which are understood all over the world.

Marked for review

 22. You are assigned as the project manager to a project which is executed for a customer under FP contract. Your customer informed you this morning that they insist on certain "refinements" of the project scope. You agree that the requested actions make really sense to the project, but believe that they constitute a major change increasing the project scope. What should you do next?

Accept the request of the customer. Diligently document the additional costs and working hours spent by yourself and the team on the implementation of the change and invoice these to the customer at appropriate rates.

Perform Earned Value Analysis to assess the current status of the project and get all the numbers you need to communicate the case to the Change Control Board which then will have to make the best decision regarding the customer request.

Check the contract, the project charter, the scope statement and other documents related to the project and the contract. Assess the impacts of the scope change. Then discuss the situation with the Project Sponsor and the Change Control Board.

Page 14: 70 Free Questions & Websites

Talk to the project sales department and find a joint solution with them how to best reject the request considering the commercial and strategic value of the customer to the organization you are working for.

Marked for review

 23. During a project the scope of a product purchased on a cost reimbursable contract has increased. In the contract the fee to cover the contractor‘s indirect costs and allow a profit is calculated as 20% of the direct costs. What is most likely to be true? 

The contractor‘s indirect costs will increase and the customer‘s payment for them will increase, too.

The contractor‘s indirect costs will increase but the customer‘s payment for them will not increase.

Neither the contractor's indirect costs nor the customer‘s payment for them will  increase.

The contractor‘s indirect costs will not increase but the customer‘s payment for them will.

Page 15: 70 Free Questions & Websites

Marked for review

 24. A project management team is evaluating the causes that might contribute to unsatisfactory performance and quality. Which of the following statements is not true? 

Normal process variation is attributable to random causes and sometimes also called "white noise".

Special causes are easier to predict and handle than random causes (also called common causes).

Special causes are unusual events which are difficult to foresee and mostly produce outliers.

A process can be optimized to limit the bandwidth of variations due to random causes.

Marked for review

Page 16: 70 Free Questions & Websites

 25. You are performing a project management audit in your company and find that most of the project plans are neither consistent nor up-to-date.

Which of the following statements is not true?

Projects should never be executed without a valid, updated and working project management plan.

The consistency of the project management plan is secondary because it is only the results that matter.

A great deal of effort is required to develop and update a project plan, but the benefits include less pressure on all stakeholders and a resulting product that will satisfy the requirements.

Poor planning and insufficient updating of project management plans are common reasons for cost and time overruns.

Marked for review

 26. You want to perform active risk acceptance. What should you do? 

Create contingency reserves in resources, money and time.

Develop a plan to minimize impact in case that an identified risk occurs.

Develop a plan to minimize the probability of occurrence for identified risks.

Page 17: 70 Free Questions & Websites

Make additional resources available to speed up the project.

Marked for review

 27. A project manager made 3-point estimates on a critical path and found the following results:

Assuming ±3 Sigma precision level for each estimate, what is the standard deviation of the allover path? 

App. 4.2 days

App. 5.2 days

App. 6.2 days

You can not derive the path standard deviation from the information given.

Marked for review

Page 18: 70 Free Questions & Websites

 28. A project team is suffering from misunderstandings between team members who have different cultural backgrounds. The project manager is evaluating how to improve communication and collaboration.

Which of the following statements is not true? 

Only those who realize that cultural differences are a resource to be fully utilized will survive in international project business.

There is a common ground for people from different cultures on which they can interact without unsolvable conflicts.

Cultural differences will always remain an obstacle to be overcome for cross-cultural projects.

Cross-cultural competence is a critical lever for competitive advantage in international project business.

Marked for review

 29. What is defined by control limits? 

A measuring instrument solely used to describe process capability. The process is found capable if the ±3 Sigma range is exceeded by not more than 0.3% of a tested sample lot.

The limits of the six sigma area on either side of a control chart to plot measured values; data found outside the area are out of specification and can lead to rejection

Page 19: 70 Free Questions & Websites

of an entire batch.

The area consisting of typically three standard deviations on either side of a mean value of a control chart to plot measured values found in statistical quality control

The area consisting of typically three standard deviations on either side of a mean value of a control chart to plot measured values found in quality assurance

Marked for review

 30. You are assigned as the project manager in a project with an aggressive schedule. During a recent meeting your team complained about the high pressure applied and the many hours of overwork time.  

What should you do first?

Try to obtain additional budget and time.

Improve team communication and availability of high quality data on risks. Use this information to enable you to make well-founded decisions earlier.

The problem might be the customer disturbing project rhythm. Keep him on distance from the team.

Apply fast tracking to shorten project duration without additional work.

Page 20: 70 Free Questions & Websites

Marked for review

 31. Activity 1 has a duration of 20 days, Activity 2 of 10 days, Activity 3 of 5 days and Activity 4 of 6 days.

What is the minimum total duration between the Milestones A and B?

36 days

37 days

39 days

42 days

Marked for review

 32.

The following ADM diagram assumes the activity durations:

A: 14 days      E: 22 days

B: 5 days   F: 8 days

Page 21: 70 Free Questions & Websites

C: 6 days   G: 7 days

D: 9 days   H: 12 days

Assuming that there are no other schedule constraints on the activities, what is the total minimum duration of the project? 

37 days

19 days

34 days

49 days

Marked for review

 33. Which of the following statements regarding whistleblowing are not true?

a. It is a term used to define an employee’s decision to disclose information on unethical, immoral or illegal actions at work to an authority figure.

b. An employee should always discuss the matter with people external to the company before following the "chain of command" and discuss it with the immediate superior.

c. The consequences of whistleblowing are often extreme and include possible being branded as having bad judgment, firing, civil action and imprisonment.

d. Carefully considered whistleblowing can lead to the end of unethical business practices.

a

Page 22: 70 Free Questions & Websites

b

b, c

c, d

Marked for review

 34. Which of the following statements is not true? 

Attribute sampling is the process of assessing whether results conform to specifications or not.

Prevention means keeping errors out of the process by applying actions before the process starts changing its input.

Variables sampling means that the result is classified into one of the 3 categories:"acceptable" - "acceptable after rework" - "rejected".

Inspection is often mainly done to keep errors out of the hands of the customer instead of as a means of process control.

Page 23: 70 Free Questions & Websites

Marked for review

 35. Which statement describes best why you should document assumptions? 

Assumptions might prove to be wrong.  Knowing which assumptions were incorrect  allows baseline adjustments in case of project crisis.

Assumption analysis is a valuable tool and technique of Risk Identification during documentation review in a risk identification workshop.

Assumptions limit the project management team's options for decision making because they can not be controlled by the team.

In case of schedule or budget overruns, the documentation of assumptions supports a clear assignment of responsibility.

Marked for review

 36. All the following statements are true except 

Page 24: 70 Free Questions & Websites

It is axiomatic of the quality management discipline that the benefits outweigh the costs.

Quality should mainly be achieved by testing and inspections of work results on a regular base.

The primary cost of meeting quality requirements is the expense associated with project quality management activities.

The primary benefit of meeting quality requirements is less rework, which means higher productivity, lower costs, and increased stakeholder satisfaction.

Marked for review

 37. You have recently been assigned as a project manager to a new B-O-T (Build, Operate, Transfer) capital project. Reviewing the initial documentation you found out that it has been calculated with a very small margin during operations of its product for the shareholders. What should you do? 

As you are not responsible for lifecycle costing, you don't have to worry about operation profits. Focus on project costs from initiation through handover.

Page 25: 70 Free Questions & Websites

Ensure maximum profits by buying the best and cheapest items, components and modules - potentially from a big number of different suppliers - and integrating them.

Create a realistic plan broken down to a sufficient level of detail. Perform all risk management processes. Ensure real-time communications with all stakeholders.

Try to get a second project manager assigned to share decision making and accountability to shareholders with the person.

Marked for review

 38. A project is handled by departments of an organization and expedited by a project coordinator. Which of the following statements is most likely to be true? 

The performing organization is a weak matrix.

The performing organization is doing "management by projects".

Page 26: 70 Free Questions & Websites

The performing organization is a strong matrix.

The performing organization is projectized.

Marked for review

 39. Which of the following statements concerning cross-cultural differences is true? 

Cultural and individual diversity may help project teams solving unforeseen problems during the course of the project.

Some cultures are developed, others are more primitive. Some have values, some not.

Cultural dilemmas should be smoothed or suppressed to not allow them to disrupt project work.

Communicating across cultures should only be done using language. The nonverbal dimension bears too many risks.

Page 27: 70 Free Questions & Websites

Marked for review

 40. What are dummy activities? 

Activities in PDM which are not necessary and can be dropped if time is running out.

Arrows in ADM which represent dependencies between nodes without real activities.

Activities, which can be passed to the team members with the lowest IQ.

Activities in PDM which are not performed by team members.

Marked for review

 41. A change request in a project has been rejected some weeks ago. Yesterday, the project

Page 28: 70 Free Questions & Websites

manager found out that it nevertheless has been implemented by the team members, who knew of the change request, but not of the rejection.

In order to avoid such a situation, Rejected change requests are input to which process? 

Schedule Development

Scope Verification

Monitor and Control Project Work

Information Distribution

Marked for review

 42. What is a trigger in project risk management?  

An expected situation causing an unidentified risk to occur

A warning sign that a previously identified risk might be occurring or has occurred

An unexpected situation causing an identified risk to occur

Page 29: 70 Free Questions & Websites

An unexpected situation causing an unidentified risk to occur

Marked for review

 43. According to the project plan, a contractor is scheduled to deliver some software components today afternoon. A regular payment is due to be made to this contractor tomorrow.

You and your project team received a note this morning informing you that the software delivery will be delayed by 2 weeks.

What should you do right now?

You should delay the payment also for 2 weeks.

You must immediately find a different contractor.

You should conduct a meeting with the contractor to resolve the delivery issues before making the payment.

You should make the payment and reschedule the project plan. 

Marked for review

 44. In a software company a large number of simultaneously performed projects utilize the same groups of human and other resources.

Page 30: 70 Free Questions & Websites

What is the term commonly used for this situation?

Concurrent engineering

Resource over-allocation

Resource pooling

Program management

Marked for review

 45. What does the acronym RACI commonly stand for in project management? 

Responsible, Accountable, to be Communicated, to be Informed.

Remote, Attached, Connected, Integrated

Page 31: 70 Free Questions & Websites

Risk Analysis and Caution Initiative

Randomly Accessible Cashflow Information

Marked for review

 46. You have used estimates made by your team members and applied Critical Path Method to compute a network logic diagram for your project. Then you found out that it can not sufficiently be optimized for scarce resources and fast progress against a deadline. What should you do next? 

Apply resource leveling heuristics to uncritical activities only.

Reduce estimates on duration and work efforts by an adequate percentage.

Apply 3-point estimation and Critical Chain Project Management.

Remove physical constraints and replace hard logic with soft logic.

Page 32: 70 Free Questions & Websites

Marked for review

 47. A ________ is a pre-contract agreement that formally establishes the intent of one party to buy products or services from another party and establishes some preliminary consideration in order to reserve resources for the anticipated contract. 

Seller initial response

Memorandum of understanding

Letter of intent

Letter contract

Marked for review

Page 33: 70 Free Questions & Websites

 48. What should not be part of a risk management plan? 

Roles and responsibilities for handling risks

Timing of risk management activities

The managerial approach towards risk

Individual risks

Marked for review

 49. Being assigned as the project manager to a project you perform Earned Value Analysis and find the following results:

EV: 250,000; PV: 200,000; AC 275,000

BAC is 500,000.

What is right?

EAC = 400,000

Page 34: 70 Free Questions & Websites

EAC = 550,000

BTC = 400,000

ETC = 75,000

Marked for review

 50. An estimation has been made that the construction of a residential home will cost a certain amount per square foot of living area. This is an example of what type of estimating? 

Analogous estimating

Bottom-up estimating

Top-down estimating

Parametric modeling

Page 35: 70 Free Questions & Websites

Marked for review

 51. Which of the following should not be reason for “rebaselining” in a project? 

Scope changes

Cost variances

Major schedule changes

New information indicating that the basis for the original project cost estimates was incorrect

Marked for review

 52. What is true when a change control system‘s provision for changes without formal review in case of emergency is being utilized? 

Page 36: 70 Free Questions & Websites

Changes can be simply applied without further managerial activities if they help solving the problem.

Changes must still be documented and captured so that they do not cause problems later in the project.

A new change control board (CCB) should be established.

The project baseline must be changed as well.

Marked for review

 53. Which of the following is generally not regarded to be a motivator according to Frederick Herzberg? 

Working conditions and interpersonal relations

Responsibility for enlarged task

Page 37: 70 Free Questions & Websites

Interest in the task

Recognition for achievement

Marked for review

 54. Companies and institutions most commonly hire project management leaders with   

A strict standing in negotiating

Experience in tricking business partners

Integrity and expertise

A strong link to local traditions

Page 38: 70 Free Questions & Websites

Marked for review

 55. You are the project manager and have recently signed a contract with a service provider for the development of a complicated software solution This software is necessary to control the machinery equipment which your project team will develop. It is a lump-sum contract with additional incentives for meeting predefined schedule targets. The payment schedule and incentives are as follows:

1. 10% with order 2. 20% after submission of prototype (+ 5% if delivered one week early) 3. 50% after product delivery (+ 5 % if delivered one week early) 4. 20% after final product acceptance (+ 5 % if delivered one week early)

Yesterday the company submitted the prototype to your project team. This was 2 weeks after the scheduled delivery date and 3 weeks after the date necessary to qualify for the incentive payment.

This morning, the manager of the contractor approached you to ask for changes to the payment schedule. They found that their initial work and costs were much higher than originally expected and they now wish to increase the second payment to 30% and reduce the final payment to 10%.

During the discussion you got the impression that the company is in serious financial trouble.

Which of the following should be the most appropriate initial step? 

Offer to pay 25% now and to reduce the final payment down to 15%. Make sure that the contractor agrees in writing that the open work for your project will be done by their company with the highest priority.

Point out that the contractor is not in a position to demand a change to the contract. Ensure that sufficient pressure is applied to ensure that the delay doesn't get to big and no additional costs occur.

Offer the subcontractor to the pay the unearned incentive as an unbureaucratic measure to help the company and to make sure that they will be able to finish the work for your project.

Revisit the processes of project risk management, re-assess your risks related to scope, time, costs, and so on and check your time and budget contingencies, then urgently meet the contractor.

Page 39: 70 Free Questions & Websites

Marked for review

 56. A review of management processes and the associated documentation is commonly called 

Audit

Inspection

Testing and measuring

Screening

Marked for review

 57. Which of the following is true in regard to the Code of Accounts? 

It allows one to easily identify the breakdown level of the item in the resource structure.

It describes the coding structure used by the performing organization to report financial information in its general ledger.

Page 40: 70 Free Questions & Websites

It is the collection of unique identifiers generally assigned to WBS items.

It defines ethical behavior in the project and the responsibilities to the customer and the profession.

Marked for review

 58. You are the manager of your company's project management office. The company is running many concurrent projects; most of them share a resource pool of technical staff. Understanding how resources are utilized across projects has been found essential to overall project performance, including cost effectiveness and profitability.

This morning you received a message that the resource pool members will be unable to perform as planned for the next months because the overall work load has grown too high and while delays are adding up, the morale of the staff is going down.

What should you do next? 

Ensure that quantitative information for all projects is being made available in a uniform fashion and that this information is reliable. Then consolidate this information to get an understanding of the status of the portfolio. Then propose the appropriate decisions.

Implement an enterprise project management software solution which is able to  level the human resources across the various projects and which has the capability to model resource assignment on a percentage level thus optimizing resource utilization for the overall organization.

Do nothing related to the described problem unless you are explicitly requested by the organizations upper management. Supporting decision making on the level on which project portfolio management is done, is not the project management office's business.

Evaluating project management software which supports planning and scheduling across enterprise-wide project portfolios and helps managing the overall availability of enterprise resources is not the business of the project management office.

Page 41: 70 Free Questions & Websites

Marked for review

 59. You have been criticized that certain specifications in your Scope Statement do not meet the test for SMART objectives. But what are SMART objectives? 

Objectives specified in far more detail than necessary for a execution of a successful project.

Easily achievable objectives which help you reducing the pressure on yourself and the team.

Objectives that should be achieved in order to attain formal recognition by both the customer and the project sponsor.

Objectives that are described using specific, measurable, assignable, realistic and time-related specifications.

Marked for review

 60. You have been assigned as a project manager to a software project. While you and your team are working on a WBS (Work breakdown structure), you notice that you are spending a lot of time discussing the level of granularity needed to create a sufficiently decomposed document.

Which of the following criteria should probably not support your discussion at this moment?  

Status/completion of WBS items is measurable.

Time/cost of WBS items and activities is easily estimated.

Start/end events of work packages are clearly defined.

Page 42: 70 Free Questions & Websites

Resource availability can be reliably foreseen.

Marked for review

 61. You are performing Earned value technique on your project.

After budget approval, an additional and unexpected cost item has been identified, which made the project more expensive some weeks ago. The item has meanwhile been paid by the project team, and it is expected that for the remaining duration of the project, costs will be as budgeted.

In this case, which is the best formula to calculate EaC (Estimate at Completion)? 

EaC = BaC - CV

EaC = BaC / CPI

EaC = AC + BtC / CV

You can not compute the EaC.

Marked for review

 62. During a company event, you had the opportunity to talk to a colleague project manager. He told you that in his current project actual costs are 15% under cumulated costs budgeted for today.

What do you think?   

The information given to you by the colleague is not sufficient to assess project

Page 43: 70 Free Questions & Websites

performance.

The project will probably be completed with total costs remaining under budget until the end.

A significant cost increase during the further course of the project will probably bring the costs back to baseline level.

Original cost forecasting and budgeting for the project must have been poor to allow this variance.

Marked for review

 63. What is the meaning of a concept called the "Journey to Abilene"? 

Project managers should visit their customers far more often than what is usual in order to avoid misunderstandings and bad emotions.

International projects may have an increased need for traveling which can lead to additional costs and troubles with time zones.

Committee decisions can have the paradox outcome, that a jointly made or approved decision is not desired by any individual group member.

A project is a temporary endeavor undertaken to create a unique product, service or result. Repeating it would be similar to making the same journey twice.

Page 44: 70 Free Questions & Websites

Marked for review

 64. Which of the following statements describes best the relationship between project phases and the Project life cycle? 

The Project life cycle includes the time when the project is performed and the expected product lifespan after that.

In project management, the sequence of project phases and phase gates is often referred to as Project life cycle.

The Project life cycle is regarded as a sequence of project activities while phases are defined to control overlapping activities.

The Project life cycle describes how iterations of project management processes are used when a project schedule is developed. 

Marked for review

Page 45: 70 Free Questions & Websites

 65. Which is for most project situations an appropriate order for the development of scope related documents? 

1. Project SOW (Statement of work), 2. Project charter, 3. Preliminary project scope statement,4. Project scope management plan, 5. Project scope statement, 6. WBS (Work breakdown structure) and WBS dictionary.

1. Work breakdown structure, 2. Scope statement, 3. Project charter, 4. CSOW (Contractual statement of work), 5. Contractual Work breakdown structure,6. WBS dictionary.

1. Feasibility study, 2. Business case, 3. Contract, 4. CWBS (Contractual work breakdown structure), 5. Scope of work descriptions, 6. PID (Project initiation document).

1. BOM (Bill of materials), 2. CAP (Control account plan), 3. Project charter, 4. Project scope statement, 5. Change management plan,6. Scope baseline.

Marked for review

 66. What is the S-curve in project management?

 

A graph that is generated if a normal curve is integrated.

A graph that is to be integrated to generate a normal curve.

Page 46: 70 Free Questions & Websites

A metaphoric description of the short term uncertainties that are present in every project.

The graph that describes the typical growth of earned value during the course of the project.

Marked for review

 67. The output of the resource planning process is a document "resource requirements". This a description of what types of resources are required in what quantities...  

...where the term resources is limited to equipment and materials.

...for each element at the lowest level of the work breakdown structure.

...where the term resources is limited to human resources.

...to be obtained solely from the performing organization.

Marked for review

 68. What is not the purpose of Configuration control when Configuration management is applied in a project? 

Verification that the configuration identification for a configured item is accurate, complete, and will meet specified program needs.

Ensuring that proposed and approved engineering changes to configuration items are fully coordinated and documented.

Ensuring timely revisions to the established functional baseline documentation in

Page 47: 70 Free Questions & Websites

order to avoid problems from excessive description deltas.

Ensuring timely revisions to the established technical baseline documentation in order to avoid problems from excessive description deltas.

Marked for review

 69. Which statement describes best the meaning of the term Cost baseline?

A cost baseline is always created by translating time-phased cost information into cost data on activity or work-package level.

A cost baseline is an approved time-phased budget that will be used to measure and monitor cost performance on the project.

Data to draw a cost baseline can be easily generated and updated as necessary from information related to actual project cost.

A cost baseline is usually displayed in the form of an inverse S-curve drawn from the beginning of the project until data date.

Marked for review

 70. Which is not true in regard of RoI (Return on Investment) for a project? 

It defines the cumulated net income from an investment at a given point in time or during a defined period.

Page 48: 70 Free Questions & Websites

It includes investment, direct and indirect costs and may include allowances for capital cost, depreciation, risk of loss, and/or inflation.

It is most commonly stated as a percentage of the investment or as a dimensionless index figure.

It is the time when cumulated net income is equal to the investment.

Marked for review

 71. A project sponsor requested Earned Value Data on two concurrent projects from the project managers. Both projects are regarded as equally important and strategically beneficial and have been finished by over 80%. He received the following information:Project A:    PV: $1,800,000   EV: $2,300,000   AC: $2,100,000Project B:   PV: $2,000,000   EV: $1,500,000   AC: $1,600,000The sponsor considers to shift some resources from Project A to Project B to speed up the second project which is currently behind schedule. What is the most likely outcome of such a measure? 

Changing team assignments during late course of a project typically increases cost efficiency.

Changing team assignments during late course of a project typically increases time efficiency.

According to the Law of diminishing returns, the consolidated Cost variance of the two projects will decrease.

According to the Law of diminishing returns, the consolidated Cost variance of the two projects will increase.

Page 49: 70 Free Questions & Websites

Marked for review

 72. Which of the following statements describes best the relationship of quality and grade? 

Low grade is always a problem; low quality may be overcome by a good rework and repair process.

Grade is a category or rank given to entities having different functional requirements but the same need for quality.

Both quality and grade can often be improved through intelligent measuring, testing and examining.

Low quality is always a problem as it bears on an item's ability to meet requirements; low grade may sometimes be acceptable.

Marked for review

Page 50: 70 Free Questions & Websites

 73. Network templates which contain only portions of a network are often referred to as  

Subnets or fragnets

Subprojects

Programs

WBS items

Marked for review

 74. In making an investment in a project, investors require compensation for which of the following? 

The risk-free rate of return plus a risk exposure premium plus a premium for expected inflation

Sacrifice of immediate use of cash for consumption or other investments, possibility of inflation and risk

Payback period in years x investment x (1 + discount rate)periods

Page 51: 70 Free Questions & Websites

Inflation and depreciation

Marked for review

 75.

You just created the following network logic diagram to describe the planned flow of activities for your project which will start tomorrow:

Which potential inconsistency in the diagram should you solve right now? 

Activity E is a logical dangle in relation to the sink before the finish milestone.

Activity F is a logical dangle in relation to the burst point after the start milestone.

You can not calculate a critical path when lags and/or leads are calculated in percent.

Activities E to F need another task drawn as a hammock to calculate Level Of Effort.

Result: of 75, %    

I am...

Page 52: 70 Free Questions & Websites

...generally interested in the PMP certification.

...on my way to pass the PMP exam.

...already certified as a PMP.

Finished? We love to see results and are interested in any comments. Click here, if you want to send us yours. And don't forget to ask for the free "Guided Risk Register" Access database application to help you better understand the Project Risk Management knowledge area processes.

Please note: The Solve Sample Test function and some other functions in this page use Javascript and Dynamic HTML which are not supported by all browsers.

 

Did you stumble over the questions 2, 13, 27, 37, 63, 70, 74? Then check this link for free Decision Tree Software. You will find a lot of helpful articles and a software tool Occam's Tree which can aid you understanding better—even as a free trial .

More providers of free PMP prep questions

Christelle P. from Canada mailed Oct 11 2003:

"I passed the test! Thanks for the 75 prep questions. The only way to succeed is to write tons of practice exams!"

So true! Here are more free sample tests with many more than 1,500 prep items (questions and answering options). Of course, I can not guarantee for their quality, but practicing is always helpful.

Provider URL Free Test Questions Comment

9:pm GmbH de.9pm.biz 20 Prep questions in German language from the translators of the PMBOK Guide

Ajith Namboothiri ajith.free-site-host.com 136 Requires registration. Number of questions may grow, as visitors are invited to add further questions. Many questions of CAPM exam style.

CertGear www.certgear.com 6 Free trial of CertGear's exam simulator.

Certification.about.com certification.about.com 20  

GetPMP getpmp.com 20 Excerpt from an offering GetPMP exam simulator. The provider is unidentified.

Head First Labs www.headfirstlabs.com 200 PDF file with 2MB for download. It serves as an appetizer for the Head First PMP prep book published in 3/07.

Page 53: 70 Free Questions & Websites

MeasureUp www.measureup.com 7 Simulates online a test environment similar to the original environment.

Oliver F. Lehmann www.oliverlehmann.com 175 PDF file (app. 1MB) for download. Just like the real thing: Questions are written against the PMP Examination Specification and reference to a current project management source.

New: German language aid for the 175 questions at Deutsche Sprachhilfe

PMConnection www.pmconnection.com 10  

PMExam.com www.pmexam.com ? Order their free Daily Digest as an e-mail service. A great resource with intelligent questions.

PM Study www.pmstudy.com 50 200 free questions after optional registration.

PMTI www.4pmti.com 15 Registration required.

Pmzilla www.pmzilla.com 155 Registration required.

PreparePM www.preparepm.com 165 Visitors are invited to contribute with further questions. Number of questions may grow.

ProXalt www.proxalt.com 20 Registration required.

Tutorials Point www.tutorialspoint.com 200  

Voight Project Solutions www.voightps.com 200 My friend and colleague Dr. Roger Voight has a large body of free questions. Many of them are also helpful for CAPM candidates.