Introduction
What is project
Logical Frmwrk
Schedule
Budget
Stakeholders
Partnership
Procurement
Services
M&E
Reporting
Visibility
Seminar on Project Preparation
Link between LFA approach and Application Form
CHECKING THE PROJECT DESIGN
Natasa Gospodjinacki
Kiev, 3-4 September 2015
Funded by European Union
Introduction
What is project
Logical Frmwrk
Schedule
Budget
Stakeholders
Partnership
Procurement
Services
M&E
Reporting
Visibility
2
Once you have a robust logframe, supported by various data that you have collected
and analysed, the process of completing the full grant application form should be quite
straight forward.
It is of paramount importance to follow every detail of the Call for Proposals documents.
This means that you MUST:
• ƒread ALL the details in the Guidelines and accompanying documents;
• ƒcomplete EVERY SECTION of the Application Form, following the guidelines
carefully. For example, if the guidelines suggest that one particular section should
only be a maximum of 3 pages, do not exceed 3 pages!;
• ƒcarefully follow the instructions regarding deadlines and how to make the
application. If the deadline is missed or if your application documents are not
complete, your application will not be considered.
Connecting the LFA with FA
Reporting
Funded by European Union
Introduction
What is project
Logical Frmwrk
Schedule
Budget
Stakeholders
Partnership
Procurement
Services
M&E
Reporting
Visibility
Look at the various headings of the application form.
1. Discuss what you have to do in order to live up to
the application requirements?
2. What would you include in the various chapters for
your own project?
Introduction
Exercise application form
Funded by European Union
Introduction
What is project
Logical Frmwrk
Schedule
Budget
Stakeholders
Partnership
Procurement
Services
M&E
Reporting
Visibility
Grant Application Form (Part B) describes the Action in the following parts:
1. General information
• It mainly includes reference to the CfPs, title of the Action, location, and other
call-specific information.
It is suggested to fill in this part at the end, after having completed the other sections.
Include the country of operation in the title.
Introduction
Full Application Form
Funded by European Union
Introduction
What is project
Logical Frmwrk
Schedule
Budget
Stakeholders
Partnership
Procurement
Services
M&E
Reporting
Visibility
2. The Action (from 2.1. to 2.4)
Description of the Action and its effectiveness (2.1.1)
• Elaborate of the expected results of the Action and the indicators used to
monitor achievement, making reference to the overall objective(s) and specific
objective of your Action;
• Elaborate on the activities to be undertaken to reach the expected results,
specifying the implementing body responsible for each activity or work
programme;
• Indicate how the action will improve the situation of the beneficiaries.
Introduction
Full Application Form (1)
Funded by European Union
Introduction
What is project
Logical Frmwrk
Schedule
Budget
Stakeholders
Partnership
Procurement
Services
M&E
Reporting
Visibility
Methodology (2.1.2) - includes coordination, monitoring and role of partners;
Complete this section once the problem analysis has been carried out and the logframe matrix has been
taken shape.
• Elaborate on the most salient methodological aspects one by one and explain why you chose a
certain methodology among others;
• It is always good to show how the action proposed is linked to the work done previously by the
applicant organisation or implementing partners;
• Show how your project proposal fits with the development strategy of the region/country of
implementation;
• State and show how your organisation will participate to in country coordination of development
aid intervention and how your action will eventually integrate and support (and not duplicate!) other
organisations' efforts;
• Include general information about the monitoring and evaluation system you will put in place;
• Be sure to highlight the main elements and draw on the findings and conclusion of the stakeholder
analysis you conducted;
• Provide a short description of the management team in charge for the project, by providing details
on the resources that will be used;
• Include the communication and visibility plan you have budgeted.
Introduction
Full Application Form (2)
Funded by European Union
Introduction
What is project
Logical Frmwrk
Schedule
Budget
Stakeholders
Partnership
Procurement
Services
M&E
Reporting
Visibility
Duration and indicative plan (2.1.3)
• Always insert the project duration in months and not years (e.g. 36 months,
instead of 3 years).
• Use the action plan format as you find it, caring not to modify it too much
while adapting it to your necessities;
• It is suggested to clearly identify milestones and show the points of your
project action plan where the end of a specific activity may have an impact
(dependency) on the start/completion of another one.
Activities on this critical path shall be monitored carefully and cannot be delayed or
the whole project will be delayed, unless the loss of time can be offset somewhere
else later on the action plan.
Introduction
Full Application Form (3)
Funded by European Union
Introduction
What is project
Logical Frmwrk
Schedule
Budget
Stakeholders
Partnership
Procurement
Services
M&E
Reporting
Visibility
Sustainability (2.1.4)
• Link pre-conditions and assumptions to your project objectives and envisaged
results;
• Provide elements (quantified data) for the impact that your Action will have at
technical, economic, social and policy levels;
• Include a sound risk analysis with foreseen mitigation measures;
• Describe potential multiplier effects and any dissemination plan foreseen to
ensure the project's flow of benefits;
• Explain how sustainability will secured after completion of the action: financing
follow-up activities, sources of revenue for covering all future maintenance costs,
general services realised/reinforced, creation of community networks.
Introduction
Full Application Form (4)
Funded by European Union
Introduction
What is project
Logical Frmwrk
Schedule
Budget
Stakeholders
Partnership
Procurement
Services
M&E
Reporting
Visibility
Link the narrative description of the Application Form with the information in
the logframe and budget, caring of using the same terminology and cross-
checking the totals wherever resources and costs are quantified.
The rest of the Full Application Form (Part B) concerns the description and
experience of the applicant, co-applicant, affiliated entity(ies) if any.
As a major requirement, the applicant should demonstrate its capacity to
manage and implement actions.
Please note that where registration in PADOR is mandatory the applicant will not
have to fill in section 3.2 (Profile) and 3.3 (Capacity to manager and implement
actions) as this information is already contained in PADOR.
Introduction
Full Application Form (5)
Funded by European Union
Introduction
What is project
Logical Frmwrk
Schedule
Budget
Stakeholders
Partnership
Procurement
Services
M&E
Reporting
Visibility
• Logical Framework
• Budget, amount requested from the Contracting Authority and other expected
sources of funding.
If the action is implemented in partnership with other organisations, the following
information should be provided for co-applicant(s), affiliated entity(ies) together
with its main legal credentials:
• experience of similar actions, in relation to the role in the implementation of
the proposed action;
• history of cooperation with the applicant;
• role and involvement in preparing the proposed action;
• role and involvement in implementing the proposed action;
• partnership statement must be undersigned with each implementing partner.
Introduction
Full Application (6)
Funded by European Union
Introduction
What is project
Logical Frmwrk
Schedule
Budget
Stakeholders
Partnership
Procurement
Services
M&E
Reporting
Visibility
• Check list and statements (Signed Mandate by Co-Applicant(s), Signed
Declaration by the Applicant)
• PADOR registration of applicant, co-applicant and for affiliated entities (if
any) – (offline form, if applicable)
Introduction
Full Application (7)
Funded by European Union
Introduction
What is project
Logical Frmwrk
Schedule
Budget
Stakeholders
Partnership
Procurement
Services
M&E
Reporting
Visibility
12
Reporting
BEFORE SENDING YOUR PROPOSAL, PLEASE CHECK THAT EACH OF THE FOLLOWING CRITERIA HAVE BEEN MET IN FULL AND TICK THEM OFF
Tick the items off below
Title of the Proposal: <indicate the title> Yes No
PART 1 (ADMINISTRATIVE) 1. The correct grant application form has been used.
2. The Declaration by the Applicant has been filled in and signed.
3. The proposal is typed and is in English.
4. One original and 2 copy(ies) are included
5. An electronic version of the proposal (CD-Rom) is enclosed
6. Each co-applicant has completed and signed the mandate and the mandate is included.
7. Each affiliated entity(ies) has completed and signed an affiliated entity(ies)'s statement and the statements are included.
8. The budget is enclosed, in balance, presented in the format requested, and stated in EUR.
9. The logical framework has been completed and is enclosed.
PART 2 (ELIGIBILITY) 10. The duration of the action is between 24 and 48 months (the minimum and maximum
allowed).
11. The requested contribution is between 500.000 EURO and 1.000.000 EURO (the minimum and maximum allowed).
12. The requested contribution is between 50 % and 90% of the estimated total eligible costs (minimum and maximum percentage allowed).
13. The total amount of financing requested on the basis of simplified cost options does not exceed EUR <60 000 /threshold in 2.1.4 of Guidelines> per each applicant.
14. The requested contribution has not been changed by more than 20 % compared to the amount requested at the concept note stage.
Funded by European Union
Introduction
What is project
Logical Frmwrk
Schedule
Budget
Stakeholders
Partnership
Procurement
Services
M&E
Reporting
Visibility
13
• Strictly follow provided format;
• Hand written AFs will be rejected;
• No supplementary annexes are to be sent;
• Mark envelopes properly as per GfA.
• Only hand delivered or posted AFs accepted;
…and also
Reporting
Funded by European Union
Introduction
What is project
Logical Frmwrk
Schedule
Budget
Stakeholders
Partnership
Procurement
Services
M&E
Reporting
Visibility
14
SOME SUGGESTIONS AND TIPS
Reporting
Funded by European Union
Introduction
What is project
Logical Frmwrk
Schedule
Budget
Stakeholders
Partnership
Procurement
Services
M&E
Reporting
Visibility
Major reasons for rejection of Application
The application arrived after the deadline
• Respect the deadline. Rejection of late proposals is automatic and there will be
no exceptions!
• Once the launching date of Call for Proposal is known, prepare a work plan for
the completion of your proposal, where you list the essential activities to be
undertaken and the milestones to be achieved against a time schedule.
• Do not forget that printing and compiling stacks (and double checking printed
copies) of paper take at least a day or two, or that it takes some time to deliver
these. If you are even a minute past the deadline, your proposal will be
automatically rejected with 100% certainty.
60-90 days seems a lot of time, but be sure this feeling will change once you will be
preparing your proposal.
Introduction
What is project
Funded by European Union
Introduction
What is project
Logical Frmwrk
Schedule
Budget
Stakeholders
Partnership
Procurement
Services
M&E
Reporting
Visibility
Major reasons for rejection of Application (2)
The application failed to pass the administrative check
• The compulsory format of the Application Form was not
respected;
• Essential documents were missing (budget, logical
framework, etc.);
• Missing signatures and stamps on the assigned parts of
the documents;
• Project duration is longer than indicated in GfA;
Introduction
What is project
Funded by European Union
Introduction
What is project
Logical Frmwrk
Schedule
Budget
Stakeholders
Partnership
Procurement
Services
M&E
Reporting
Visibility
Major reasons for rejection of Application (3)
Partnership
Declaration not signed by all partners and/or main applicant;
Declaration is submitted in a different format from the one foreseen by the procedure;
One or more partners are not eligible!
Funded by European Union
Introduction
What is project
Logical Frmwrk
Schedule
Budget
Stakeholders
Partnership
Procurement
Services
M&E
Reporting
Visibility
Major reasons for rejection of Application (4) Budget
Requested amount exceeds maximum or minimum value defined in the Guidelines;
Wrongly calculated budget lines what leads to incorrect amounts of expenses and consequently to incorrect total budget amount;
justification of the budget not filled in;
Parts of budget are missing in the electronic form;
Funded by European Union
Introduction
What is project
Logical Frmwrk
Schedule
Budget
Stakeholders
Partnership
Procurement
Services
M&E
Reporting
Visibility
Common Application Errors Quality of the content
• The relevance of the project (to needs and constraints of the country/region and to those of the target
groups and final beneficiaries) is not convincing;
• Proposal shows no clear relation to the objectives of the Programme;
• Objectives, methodology and results are insufficiently elaborated and explained;
• The Description of the Action from Concept Notes is copy pasted and no additional information is
provided;
• Goals too ambitious and not reasonably substantiated by the proposed activities;
• Poor logic verification (internal logic, indicators, sources of verification);
• Not well elaborated core Activities and not properly correlated;
• Indicators are not quantifiable and measurable;
• Project tasks not properly defined;
• Distribution of tasks and responsibilities among project team and partners is not adequate;
Introduction
What is project
Funded by European Union
Introduction
What is project
Logical Frmwrk
Schedule
Budget
Stakeholders
Partnership
Procurement
Services
M&E
Reporting
Visibility
…and also
• Timeframe for the implementation is not realistic;
• Target groups and Final beneficiaries are not well defined (too wide);
• Sustainability and multiplier effect are not properly described;
• Added value inexistent or poorly described;
• The involvement of co-applicants and affiliated entities not well elaborated;
• Ownership not ensured– you may be awarded a grant, but then lose it through
poor implementation.
• Capacities for project implementations - own organistation was not presented
properly, as well as the resources.
Introduction
What is project
Funded by European Union
Introduction
What is project
Logical Frmwrk
Schedule
Budget
Stakeholders
Partnership
Procurement
Services
M&E
Reporting
Visibility
Quality elements of a proposal (1)
Relevance: proposals meets priorities and needs
• Good problems analysis, possible solutions and high level of consistency with
the needs;
• Key stakeholders, target groups, beneficiaries clearly identified;
• Problem needs and priorities of target groups properly addressed;
What is project
Funded by European Union
Introduction
What is project
Logical Frmwrk
Schedule
Budget
Stakeholders
Partnership
Procurement
Services
M&E
Reporting
Visibility
Quality elements of a proposal (2)
Feasibility of the project design:
• Project intervention logic (e.g. overall objective, specific objective, results);
• Costs/benefits of the project resources assessed and clearly incorporated in the
project;
• Work plan (activities) clear and logical - address clearly identified needs;
• Monitoring and evaluations assessed and incorporated in the project design;
• Assumptions & risks assessed and appropriate risk management strategy
incorporated in the project design.
What is project
Funded by European Union
Introduction
What is project
Logical Frmwrk
Schedule
Budget
Stakeholders
Partnership
Procurement
Services
M&E
Reporting
Visibility
Quality elements of a proposal (3)
Efficiency: how resources are converted into results;
Effectiveness: activity results compared to the energy spent to develop it;
Sustainability: continuity of the benefits produced by the intervention.
What is project
Funded by European Union
Introduction
What is project
Logical Frmwrk
Schedule
Budget
Stakeholders
Partnership
Procurement
Services
M&E
Reporting
Visibility
Quality elements of a proposal (4)
• Collect as much information as you can about the problem your organisation
is intending to address.
The information must be valid and credible. You can use official reports and publications,
academic research papers, newspaper articles, and collect your own data through interviews
and surveys and other research techniques;
• Use tools such as ‘the problem tree’ and ‘objective tree’ to analyse the
problem and identify what is actually feasible given the size and nature of the
problem, the capacity of your organisation, and the context of the problem.
• You also need to ensure that both your organisation and the community which
it serves agree that the problem is a priority to be addressed. If no-one else
agrees it is a priority, you will find it difficult to implement a project;
• Actions should be designed to produce specific, measurable results in
response to identified problems;
What is project
Funded by European Union
Introduction
What is project
Logical Frmwrk
Schedule
Budget
Stakeholders
Partnership
Procurement
Services
M&E
Reporting
Visibility
Quality elements of a proposal (5)
• Conduct a stakeholder analysis and gather the opinions and advice of as
many stakeholders and potential partners as you can.
The more allies you have for the design and implementation of your project, the
stronger your proposal will be.
• Ensure that your project preparation takes into consideration any special needs
and responds appropriately to challenges related to any forms of
discrimination or environmental impact issues.
• Remember that in many Calls for Proposals, there are specific criteria related to
actions involving gender, environmental, and ethnic minority issues.
What is project
Funded by European Union
Introduction
What is project
Logical Frmwrk
Schedule
Budget
Stakeholders
Partnership
Procurement
Services
M&E
Reporting
Visibility
Quality elements of a proposal (6)
Keep it brief, simple and clear;
Explain how your project complements or builds on other ongoing initiatives;
Be realistic! Especially regarding:
• Commitment of key stakeholders;
• Expected results within timeframe;
• Ability to influence problem dynamics;
• The influence and capacity of the applicant, co-applicant(s) and target group(s).
Focus on impact :
• Explain concrete benefits and expected impact of the project, not just activities;
What is project
Funded by European Union
Introduction
What is project
Logical Frmwrk
Schedule
Budget
Stakeholders
Partnership
Procurement
Services
M&E
Reporting
Visibility
27
Emphasize your experience. Mention your previous experience with the
proposed activities.
If this is the first time you’ll be undertaking such an activity, explain with concrete
steps how you’ll manage the activity in order to show the Evaluator/Assessor how
you’ll overcome your lack of experience and whether you can establish a balance
between your institutional strengths and weaknesses.
ƒƒInvolve your partners. Partners are not just for meeting the pre-conditions of a
CfP.
They’re a part of this process to bring different experiences and knowledge to the
table and they should add a substantial value to the proposed project. Explain how
they will reinforce your proposed action and how they have already contributed.
More tips from the experts:
Reporting
Funded by European Union
Introduction
What is project
Logical Frmwrk
Schedule
Budget
Stakeholders
Partnership
Procurement
Services
M&E
Reporting
Visibility
28
Identify your activities carefully. An experienced Evaluator/Assessor can tell
whether the project is proposed so as to obtain finance for a certain activity, like
financing a festival or study tour, rather than achieving the proposed objective.
Correlate your activities with each need and explain how you will meet the needs
and thus reach your project objectives clearly. The activities must serve as a way of
achieving the project’s goals, not the other way around.
Pay more attention to monitoring and evaluation.
Show the Evaluator/Assessor that you have already thought about and planned the
monitoring and evaluation tools that you’ll use during project implementation;
ƒƒ
Give a strong argument on sustainability. Show the Evaluator/Assessor that
you have already given considerable thought about how you will ensure the
sustainability of your action. Make your argument realistic and do make it dependent
on external factors, but within your responsibility and capacity.
More tips from the experts (2):
Reporting
Funded by European Union
Introduction
What is project
Logical Frmwrk
Schedule
Budget
Stakeholders
Partnership
Procurement
Services
M&E
Reporting
Visibility
29
GOOD LUCK!
Reporting
Funded by European Union
Introduction
What is project
Logical Frmwrk
Schedule
Budget
Stakeholders
Partnership
Procurement
Services
M&E
Reporting
Visibility